Some remarks on the expected delay of project duration in a PERT network

  • Published:
Zeitschrift für Operations Research Aims and scope Submit manuscript

Summary

In this note a problem of estimating the expected project delay of a given completion time in a PERT network is reconsidered. Some remarks on application of the approach, proposed recently by Hartmann, are given.

Zusammenfassung

In diesem Bericht wird nochmals das Problem der Abschätzung des Erwartungswerts der Überschreitung eines Projektendtermins in Erwägung gezogen, wobei das Projekt mit dem PERT-Netzplan beschrieben ist. Einige Bemerkungen bezüglich der Verwendung des neuerdings vonHartmann vorgeschlagenen Ansatzes zu diesem Problem werden angegeben.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Subscribe and save

Springer+ Basic
$34.99 /Month
  • Get 10 units per month
  • Download Article/Chapter or eBook
  • 1 Unit = 1 Article or 1 Chapter
  • Cancel anytime
Subscribe now

Buy Now

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

References

  • Hartmann, J.: Stochastisches PERT — Eine vergleichende Untersuchung über die Effizienz eines Verfahrens zur stochastischen Projektplanung. Zeitschrift für Operations Research28, 1984, B59-B69.

    Google Scholar 

  • Martin, J.J.: Distribution of the Time through a Directed Acyclic Network. Operations Research13, 1965, 46–66.

    Google Scholar 

  • Meilijson, I., andA. Nádas: Convex Majorization with an Application to the Lengths of Critical Paths. Journal of Applied Probability16, 1979, 671–677.

    Google Scholar 

  • Nádas, A.: Probabilistic PERT. IBM Journal of Research and Development23, 1979, 339–347.

    Google Scholar 

  • Shogan, A. W.: Bounding Distributions for a Stochastic PERT Network. Networks7, 1977, 359–381.

    Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Rights and permissions

Reprints and permissions

About this article

Cite this article

Kamburowski, J. Some remarks on the expected delay of project duration in a PERT network. Zeitschrift für Operations Research 28, B221–B225 (1984). https://doi.org/10.1007/BF01920514

Download citation

  • Received:

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF01920514

Keywords