17 Insumos Const. Pista Atletismo PDF
17 Insumos Const. Pista Atletismo PDF
17 Insumos Const. Pista Atletismo PDF
MANO DE OBRA
0101010003 OPERARIO hh 1,288.9965 5.00 6,444.98
0101010004 OFICIAL hh 262.1073 4.38 1,148.03
0101010005 PEON hh 5,049.8187 3.75 18,936.82
0101030000 TOPOGRAFO hh 176.7851 10.00 1,767.85
28,297.68
MATERIALES
0201010022 ACEITE PARA MOTOR MULTIGRADO 20W-50 gal 0.4994 80.00 39.95
0201010024 GRASA lbs 0.7135 9.00 6.42
0201030002 GASOLINA 84 OCTANOS gal 9.2755 11.00 102.03
0201040003 KEROSENE gal 251.9344 18.00 4,534.82
02010500010001 ASFALTO RC-250 gal 1,007.7376 20.00 20,154.75
02010500010004 EMULSION ASFALTICA CSE (CATIONICA SUPER gal 4,698.4291 28.00 131,556.01
ESTABILIZANTE)
02040100020002 ALAMBRE NEGRO N° 8 kg 64.6906 5.00 323.45
0204030009 ESTACAS DE FIERRO CORRUGADO und 37.6370 2.00 75.27
0204120001 CLAVOS PARA MADERA C/C 3" kg 50.7571 5.00 253.79
02070100010002 PIEDRA CHANCADA 1/2" m3 79.3611 50.00 3,968.06
02070100050001 PIEDRA MEDIANA DE 4" m3 27.3988 42.00 1,150.75
02070200010001 ARENA FINA m3 9.7103 60.00 582.62
02070200010002 ARENA GRUESA m3 116.5211 38.00 4,427.80
0207020011 MATERIAL CLASIF. DE CANTERA P/SUB RASANTE m3 214.9350 1.43 307.36
0207020012 MATERIAL CLASIF. DE CANTERA P/BASE m3 644.7945 30.00 19,343.84
0207020014 MATERIAL CLASIF. DE CANTERA P/SUB BASE m3 644.7945 30.00 19,343.84
0207030007 HORMIGON (PUESTO EN OBRA) m3 67.4088 45.00 3,033.40
0207070002 AGUA m3 183.1361 0.50 91.57
0210050008 POLIESTIRENO EXPANDIDO (TECKNOPOR DE 1" X 4' X 8') pln 5.9422 13.00 77.25
0213010002 CEMENTO PORTLAND TIPO IP (42.5 kg) bol 570.0431 22.00 12,540.95
02130300010001 YESO BOLSA 25 KG bol 16.4986 6.00 98.99
0222100004 XILOL gal 7.2211 33.00 238.30
0231010001 MADERA TORNILLO CEPILLADA p2 20.3366 6.00 122.02
02310100010004 MADERA TORNILLO p2 703.2788 5.50 3,868.03
02310500010010 TRIPLAY LUPUNA DE 4' X 8' X 19 mm pln 27.3691 110.00 3,010.60
0238010002 LIJA PARA FIERRO plg 18.0950 2.50 45.24
0238010005 CORDEL m 157.4590 0.08 12.60
0240020017 PINTURA DE TRAFICO gal 24.0702 55.00 1,323.86
0240020018 PINTURA ESMALTE SINTETICO gal 10.8570 42.00 455.99
02400800120002 THINNER STANDARD gal 18.0950 16.00 289.52
231,379.08
EQUIPOS
03010000020001 NIVEL TOPOGRAFICO he 172.4573 12.00 2,069.49
0301000009 ESTACION TOTAL día 21.8761 100.00 2,187.61
0301000024 MIRAS Y JALONES hm 168.1662 2.50 420.42
0301000025 MIRA TOPOGRAFICA he 4.2906 2.50 10.73
0301060006 ESCOBA und 31.4918 18.00 566.85
0301100009 RODILLO LISO VIBRATORIO AUTOPROPULSADO 70-100HP 7-9 hm 71.5242 180.00 12,874.36
ton
03011600010008 CARGADOR SOBRE LLANTAS 125-155 HP 3 yd3 hm 3.8893 200.00 777.86
0301180003 TRACTOR DE ORUGAS DE 140-160 HP hm 16.1917 230.00 3,724.09
03012200040003 CAMION VOLQUETE DE 14 m3 hm 23.3972 130.00 3,041.64
03012200040004 CAMION CISTERNA 4 X 2 (AGUA) 122 HP 1,500 gl hm 100.7264 100.00 10,072.64
0301220010 MOTONIVELADORA DE 125 HP hm 96.6325 200.00 19,326.50
0301220011 CAMION IMPRIMADOR DE 1800 gl hm 15.7459 180.00 2,834.26
0301260002 COMPRESORA NEUMATICA 225-350 PCM hm 5.3536 80.00 428.29
03012900010005 VIBRADOR DE CONCRETO 4 HP 1.50" hm 7.9622 10.00 79.62
0301290004 MEZCLADORA DE CONCRETO DE 9 - 11P3 hm 139.0172 20.00 2,780.34
61,194.70
Total S/. 320,871.46