Control de Buffer
Control de Buffer
Control de Buffer
SETUP:
Fecha de Inicio de Obra 3-Aug
Fecha Fin Meta (Sin Buffers) 10-Dec
Fecha Fin Compromiso 31-Dec
BUFFER (DÍAS) 17
PLAZO PROYECTO (DÍAS) 126
FECHA PREVISTA DE ENTREGA 12-Dec
DATOS:
FECHA DE ÚLTIMO REPORTE: 26-Oct-2015
BUFFER CONSUMIDO (DÍAS) 9 / 17
DÍAS TRANSCURRIDOS DE PROYECTO 71 / 126
% VALORIZADO DE PROYECTO (ACUMULADO) 35.1%
% TIEMPO TRANSCURRIDO A LA ÚLTIMA VALORIZACIÓN 38.9%
% TIEMPO TRANSCURRIDO A LA FECHA DE REPORTE 56.3%
90%
80%
PORCENTAJE DE EJECUCIÓN DE CRONOGRAMA
70%
60%
PORCENTAJE DE AVANCE /
50%
40%
30%
20%
10%
0%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
PORCENTAJ
PORCENTAJ
30%
20%
10%
0%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
0 100
90% Zona Verde: 0 40
90%
Zona Amarilla: 5 40
Zona Roja: 95 20
80% 80% 100 100
70% 70%
52.9%
56.3%
60% 60%
Buffer Consumido
50% 50%
ma
40% 40%
30% 30%
20%
20%
10%
10%
0%
0% 0
0% 10% 20% 30% 4
0% 90% 100%
0% 90% 100%
Consumo de Buffer
AÑO 1
0 0 0
October-15 November-15 December-15
2,307,188 2,072,116 813,388
4,967,474 7,039,590 7,852,978
60% 80% 100%
#NAME? #NAME? #NAME?
#NAME? #NAME? #NAME?
as cada 7 días
estas fechas
e tener un
ue se considere