CRONOGRAMA
CRONOGRAMA
CRONOGRAMA
LUGAR: LIMA-LIMA-ANCON
FECHA: NOVIEMBRE 2021
CRONOGRAMA VALORIZADO DE AVANCE DE OBRA
01.01.04 ALQUILER DE SERVICIOS HIGIENICOS (CONTENEDORES) mes 2.00 S/. 500.00 S/. 1,000.00 S/. 500.00 S/. 500.00
01.02.02 CAPACITACION DE SEGURIDAD Y SALUD glb 1.00 S/. 499.20 S/. 499.20 S/. 499.20
01.02.03 EQUIPOS DE PROTECCION INDIVIDUAL gbl 1.00 S/. 3,524.44 S/. 3,524.44 S/. 3,524.44
01.02.04 EQUIPOS DE PROTECION COLECTIVA glb 1.00 S/. 1,556.93 S/. 1,556.93 S/. 1,556.93
01.02.05 RECURSOS PARA REPUESTAS ANTE EMERGENCIA glb 1.00 S/. 1,500.00 S/. 1,500.00 S/. 1,500.00
01.03 TRABAJOS PRELIMINARES S/. 2,919.22 S/. 2,919.22 100.00%
01.03.01 DEMOLICION DE SARDINEL DE CONCRETO m 13.90 S/. 17.36 S/. 241.30 S/. 241.30
01.03.02 DEMOLICION DE MARTILLOS DE CONCRETO EXISTENTE D m2 69.79 S/. 14.37 S/. 1,002.88 S/. 1,002.88
01.03.03 TRAZO Y REPLANTEO INICIAL m2 3101.92 S/. 0.54 S/. 1,675.04 S/. 1,675.04
02 CIRCULACION PEATONAL(PERIMETRICAS E INTERIORES) . S/. 175,064.80 S/. 131,618.65 75.18% S/. 43,446.15 24.82%
LUGAR: LIMA-LIMA-ANCON
FECHA: NOVIEMBRE 2021
CRONOGRAMA VALORIZADO DE AVANCE DE OBRA
LUGAR: LIMA-LIMA-ANCON
FECHA: NOVIEMBRE 2021
CRONOGRAMA VALORIZADO DE AVANCE DE OBRA
Costo Directo S/. S/. 216,622.09 S/. 145,668.44 S/. 3.62 S/. 70,953.65
Gastos Generales 8.00% S/. S/. 17,329.77 S/. 11,653.48 S/. 5,676.29
Utilidades 7.00% S/. 15,163.55 S/. 10,196.79 S/. 4,966.76
Sub Total S/. S/. 249,115.40 S/. 167,518.71 67.25% S/. 81,596.70 32.75%
IGV 18.00% S/. S/. 44,840.77 S/. 30,153.37 S/. 14,687.41
PRESUPUESTO TOTAL S/. 293,956.18 S/. 197,672.07 S/. 96,284.10
a SEMANA ! SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7
188,623.20 112,595.17 449,140.21 282,888.94 554,186.16 684,525.15 176,986.59
01 11,591.01
01.01 10,500.00
01.02 1,091.01
02 128,260.42 66,344.64 287,413.93 228,105.51 213,141.95 583,538.79 98,027.38
02.01 42,682.45
02.01.01 33,609.49
02.01.02 9,072.96
02.02 15,629.22
02.02.01 6,271.22
02.02.02 9,358.00
02.03 69,948.75 66,344.64 287,413.93 50,515.89
02.03.01 69,948.75 14,007.24 0.00
02.03.02 1,184.70
02.03.03 52,337.40 8,733.50
02.03.04 277,495.73 50,515.89
02.04 177,589.62 213,141.95 583,538.79 98,027.38
02.04.01 177,589.62 31,002.61 31,002.61 13,296.06
02.04.02 182,139.34 31,143.56 31,143.56
02.04.03 47,309.01 16,016.18
02.04.04 474,083.61 37,571.58
02.05
02.05.01
02.05.02
02.05.03
02.06
02.06.01
02.06.02
02.06.03
02.06.04
03 11,170.04 21,736.31 6,507.62 17,407.46 32,367.34 11,971.02 9,832.07
03.01 966.98
03.01.01 232.26
03.01.02 734.72
03.02 10,203.06 21,736.31 6,507.62 930.63
03.02.01 5,659.92 4,045.69
03.02.02 4,543.14 3,247.42
03.02.03 1,690.17
03.02.04 5,407.61
03.02.05 949.96 6,507.62 930.63
03.02.06 6,395.46
03.03 16,476.83 32,367.34 11,971.02 9,832.07
03.03.01 16,476.83 2.67
03.03.02 6,411.10 2,139.59 0.64
03.03.03 25,953.57 9,831.43 9,831.43
03.03.04
03.03.05
03.03.06
03.03.07
03.03.08
04 11,095.90 16,279.74 146,984.18 33,258.73 306,610.05 86,949.13 67,060.93
04.01 11,095.90 16,279.74 17,151.30
04.01.01 11,095.90 4,191.62
04.01.02 12,088.12 15,117.23
04.01.03 2,034.07
04.02 129,832.88 33,258.73 6,212.54 6,212.54 6,212.54
04.02.01 85,700.57
04.02.02 27,494.27
04.02.03 13,501.97 27,046.19
04.02.04 3,136.07 6,212.54 6,212.54 6,212.54 6,212.54
04.03 300,397.51 80,736.59 60,848.39
04.03.01 59,136.02 11,128.12 11,128.12
04.03.02 39,860.47 27,855.08 7,966.88
04.03.03 201,401.02 41,753.39 41,753.39
04.03.04
04.03.05
04.03.06
05
05.01
05.01.01
05.02
05.02.01
05.02.02
05.03
05.03.01
05.03.02
05.03.03
05.03.04
05.03.05
05.03.06
05.03.07
06 26,505.83 8,234.48 8,234.48 4,117.24 2,066.82 2,066.21 2,066.21
06.01 13,067.96 4,102.06 4,102.06 2,051.03 0.61
06.02 13,437.87 4,132.42 4,132.42 2,066.21 2,066.21 2,066.21 2,066.21
07
07.01
07.02
07.03
08
08.01
09
09.01
09.02
09.03
SEMANA 8 SEMANA 9 SEMANA 10SEMANA 1SEMANA 1SEMANA 1SEMANA 1SEMANA 15SEMANA 1
254,380.61 116,518.89 101,357.74 41,698.55 44,041.52 46,008.54 49,095.75 158,244.98 58,685.22
64,275.33 26,848.03
26,703.75
37,571.58 26,848.03
11,110.26 17,917.75 10,653.52 6,133.97 5,524.74 790.89
11,110.26 17,917.75 7,684.37
2,969.15 1,160.05
4,973.92 5,524.74 790.89
34,896.48 12,758.07 0.76
2,181.17 2,545.58 0.76
18,334.43 9,176.77
8,403.28 1,035.72
5,977.60
4,332.74 4,611.30 2,200.40 1,159.79
1,407.42
2,600.89 800.03
198.57
324.43
3,612.70 2,200.40 629.34
530.45
59,094.05 66,802.10 74,092.39 20,197.21 20,032.99 4,056.88 3,167.53 1,810.96
5,347.44
8,010.50
295.79
295.79
126,382.70 7,147.20 7,147.20 7,147.20 14,110.35 3,021.76
16,374.89
110,007.81 7,147.20 7,147.20 7,147.20 3,065.21
11,045.14 3,021.76
3,049.95
3,049.95
26,591.00
5,500.00
3,500.00
17,591.00
SEMANA 1SEMANA SEMANA SEMANA 20
16,785.83 8,502.86 1,707.62 0.51
16,785.83 8,502.86 1,707.62 0.51
14,651.89 4,190.61
2,133.94
4,312.25 1,707.62 0.51
CALENDARIO DE UTILIZACION DE EQUIPO
MANO DE OBRA
1.1 CAPATAZ 1 1 1 1
1.2 OPERARIO 1 1 1 1
1.3 OFICIAL 1 1 1 1
1.4 PEON 1 1 1 1
1.5 TOPOGRAFO 1 1 1 1 1
1.6 MANO DE OBRA - T 2 2 2 2 2
1.7 MANO DE OBRA - LT 1 1 1 1 1
1.8 MANO DE OBRA-A 1 1 1 1 1
1.9 MANO DE OBRA - SEÑALIZACION 2 2 2
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y
1.10 1 1 1 1 1
SALUD EN EL TRABAJO
1.11 MANO DE OBRA - PROTECCION COLECTIVA 1 1 1
1.12 CHARLAS DE CAPACITACION EN SEGURIDAD AL PERSONAL 1 1 1 1 1
1.13 MANO DE OBRA - CAPACITACION EN SEGURIDAD 1 1 1 1 1
MATERIALES
2.1 ALAMBRE NEGRO Nro. 8 1 1 1 1 1
2.2 ALAMBRE NEGRO Nro.16 1 1 1 1
2.3 CLAVOS CON CABEZA DE 2 1/2", 3", 4" 1 1 1 1 1
2.4 CLAVOS CON CABEZA DE 3" 1 1 1 1 1
2.5 CLAVOS CON CABEZA DE 4" 1 1 1
2.6 ACERO 1 1 1
2.7 ARENA GRUESA 1 1 1
2.8 ARENA FINA 1 1 1 1
2.9 PIEDRA CHANCADA DE 1/2” Y 3/4" 1 1 1
2.10 AGUA 1 1 1 1 1
2.11 AGUA 1 1 1 1
2.12 ASFALTO LIQUIDO RC-250 1 1 1 1
2.13 MEZCLA ASFALTICA EN CALIENTE 1 1 1
2.14 TRANSPORTE DE MEZCLA ASFALTICA C/VOLQUETE 10M3 1 1 1 1
2.15 LADRILLO KK TIPO IV 24X13X09 CM 1 1 1 1
2.16 CEMENTO PORTLAND TIPO I (42.5kg) 1 1 1 1
2.17 PEGAMENTO PARA TUBERIA PVC 1 1 1 1
2.18 CAL (BOLSA X 20 kg) 1 1 1 1
2.19 CORDEL 1 1 1 1
2.20 IMPERMEABILIZANTE LIQUIDO PARA CONCRETO 1 1 1 1
2.21 EXTINTOR DE POLVO SECO 1 1 1 1
2.22 DISCO DE CORTE DE 16" 1 1
2.23 CASCO DE PROTECCION 1 1
2.24 BOTINES DE CUERO 1 1
2.25 TAPONES AUDITIVOS 1 1
2.26 GUANTES DE CUERO 1 1
2.27 RESPIRADOR CONTRA POLVO 1 1
2.28 CHALECOS REFLECTIVOS 1 1
2.29 LENTES DE PROTECCION 1 1
2.30 MATERIALES - PROTECCION COLECTIVA 1 1
2.31 MATERIALES - SEÑALIZACION SEGURIDAD 1 1
2.32 CAMILLA 1 1
2.33 BOTIQUIN CON MEDICINA 1
2.34 CILINDRO VACIO 1
2.35 TAPA DE CONCRETO C/MARCO F°F PARA BUZON ø 0.60m 1
2.36 GASOLINA 95 OCTANOS 1
2.37 HORMIGON 1
2.38 AFIRMADO 1
2.39 MADERA TORNILLO 1
2.40 MADERA TORNILLO-A 1
2.41 KEROSENE INDUSTRIAL 1
2.42 TUBO PVC-SAP - 8" (5M) 1
2.43 TUBO PVC-SAP-4" (3M) 1
2.44 TUBO PVC-SAP - 6" (5M) 1
2.45 TAPON PVC SAL P/DESAGUE 08” 1
EQUIPOS 1
3.1 HERRAMIENTA 1
3.2 HERRAMIENTA-T 1
3.3 HERRAMIENTA - LT 1
3.4 COMP. NEUMATICA - 93 HP - 335/375 PCM 1
3.5 MARTILLO NEUMATICO - 25/29 KG 1
3.6 RETROEXCAVADORA S/LLANT. 62 HP -1 YD3 1
3.7 TRACTOR DE TIRO DE 60HP 1
3.8 PLANCHA COMPACTADORA VIBRAT. 4.0 HP 1
3.9 RODILLO NEUMATICO AUTOP. 81-100HP 5.5-20T 1
3.10 RODILLO TANDEM ESTATIC AUT 58-70HP 8-10T 1
3.11 MEZCLADORA DE CONC.(TAMBOR) 11 P3,18 HP 1
3.12 VIBRADOR A GASOLINA Y 1 3/4", 4 HP 1
3.13 CORTADORA DE CONCRETO 13 HP 1
3.14 CAMION VOLQUETE 4x2, 210/280 HP, 8 M3 1
3.15 TEODOLITO Y MIRA 1
3.16 BARREDORA MECANICA 10-20HP
3.17 PAVIMENTADORA SOBRE ORUGAS 105HP 10-16'
3.18 CAMION IMPRIMADOR 6x2 178-210HP 2000 GLN
CRONOGRAMA DE ADQUISICION DE MATERIALES
MANO DE OBRA
30369.23
MATERIALES
2.3 CLAVOS CON CABEZA DE 2 1/2", 3", 4" kg 2.32 2.80 6.49
2.35 TAPA DE CONCRETO C/MARCO F°F PARA BUZON ø 0.60m und 5.00 300.00 1500.00
2.45 TAPON PVC SAL P/DESAGUE 08” und 4.42 36.76 162.54
29628.27
EQUIPOS
3.9 RODILLO NEUMATICO AUTOP. 81-100HP 5.5-20T h-m 1.21 127.67 154.29
3.10 RODILLO TANDEM ESTATIC AUT 58-70HP 8-10T h-m 1.21 93.28 112.73
3.14 CAMION VOLQUETE 4x2, 210/280 HP, 8 M3 h-m 3.87 196.77 760.75
3.17 PAVIMENTADORA SOBRE ORUGAS 105HP 10-16' h-m 1.21 133.17 160.94
CRONOGRAMA DE ADQUISICION DE MATERIALES
3.18 CAMION IMPRIMADOR 6x2 178-210HP 2000 GLN h-m 0.25 122.29 30.16
6411.24