Cronograma Valorizado de Agua Potablel

Descargar como xls, pdf o txt
Descargar como xls, pdf o txt
Está en la página 1de 2

DIAGRAMA DE BARRAS GANTT

OBRA : AMPLIACION DE LA RED MATRIZ DE AGUA POTABLE Y ALCANTARILLADO EN EL SECTOR DE CABALLO PAMPA
PROVINCIA : HUANCAVELICA
DPTO. : HUANCAVELICA
LUGAR : MALECON CABALLO PAMPA
Tiempo de ejecución del proyecto = 15 días.
DIAS
Item Descripción Partida UND METRADO P. UNIT. TOTAL
10 11 12 13 14 15

68.40 0.00
CINTA PLASTICA P/SEÑAL DE PELIGRO, LIMITE DE
01.00.00 GLB 1.00 68.40 68.40
OBRA

25.65
02.00.00 LIMPIEZA DE TERRENO MANUAL. GLB 1.00 25.65 25.65

80.43 80.43 80.43 0.00


TRAZO, NIVELACION Y REPLANTEO INICIAL Y FINAL
03.00.00 GLB 1.00 241.30 241.30
DE LA OBRA

110.00 110.00 110.00


EXCAVACION DE ZANJA MANUAL EN TERR-NORMAL
04.00.00 GLB 1.00 330.00 330.00
DE 1,00 M. A 1.20 M. DE PROF.

0.00 256.13 256.13 0.00


EXCAVACION DE ZANJA CON MAQUINARIAEN TERR-
05.00.00 GLB 1.00 512.25 512.25
NORMAL DE 1,00 M. A 1.20 M. DE PROF.

0.00 51.93 51.93 51.93 0.00


REFINE Y NIVELACION DE ZANJA TERR-NORMAL
06.00.00 GLB 1.00 155.80 155.80
PARA TUB. DE 1.00A 1.20 M. DE PROF.

0.00 123.18 123.18 123.18 0.00 0.00


PREPARACION Y COLOCACION DE CAMA DE APOYO
07.00.00 GLB 1.00 369.55 369.55
PARA TUB. E=0.10M

0.00 0.00 219.45 219.45 219.45 0.00


RELLENO Y COMPACTACION DE ZANJA TERR-
08.00.00 GLB 1.00 658.35 658.35
NORMAL PARA TUB. DE 1.00M. A 1.20M. PROF.

0.00 0.00 205.68 205.68


09.00.00 ELIMINACION DE MATERIAL EXCEDENTE GLB 1.00 411.35 411.35

347.23 347.23 347.23 347.23


10.00.00 TUBERIA PVC UF DN= 90MM C-7.5 GLB 1.00 1388.90 1388.90

86.45
11.00.00 PRUEBA HIDRAULICA+DESINFECCION TUB. PVC GLB 1.00 86.45 86.45

932.72 932.72 932.72


12.00.00 SUMINISTRO E INSTALACION DE ACCESORIOS GLB 1.00 2798.16 2798.16

A TOTAL COSTO DIRECTO 7046.16 284.48 968.90 2121.07 1674.51 1705.07 292.13
B GASTOS GENERALES (15.00% de A) 1056.92 42.67 145.34 318.16 251.18 255.76 43.82
C SUBTOTAL A+ B 8103.08 327.16 1114.24 2439.23 1925.69 1960.83 335.94
D TOTAL GENERAL C 8103.08 327.16 1114.24 2439.23 1925.69 1960.83 335.94
PORCENTAJE 100.00% 4.04 13.75 30.10 23.76 24.20 4.15
DIAGRAMA DE BARRAS GANTT
OBRA : CONSTRUCCION DEL SISTEMA DE ALCANTARILLADO DE LA LOCALIDAD YAURECCAN
PROVINCIA : CHURCAMPA
DPTO. : HUANCAVELICA

Tiempo de ejecución del proyecto = 180 días.


DIAS
Item Descripción Partida UND METRADO P. UNIT. TOTAL
30 60 90 120 150 180 210 240

75,917.57 0.00 0.00 0.00 0.00 0.00 0.00 50,611.71


01.01.00 OBRAS PRELIMINARES GLB 1.00 126,529.28 126,529.28
60.00% 40.00%
354,900.61 354,900.61 354,900.61 354,900.61 354,900.61 0.00 0.00 0.00
103.00 MOVIMIENTO DE TIERRAS GLB 1.00 1,774,503.05 1,774,503.05
20.00% 20.00% 20.00% 20.00% 20.00%
0.00 10,500.73 10,500.73 10,500.73 10,500.73 10,500.73 0.00 0.00
612.01 MEJORAMIENTO DE SUBRASANTE GLB 1.00 52,503.65 52,503.65
20.00% 20.00% 20.00% 20.00% 20.00%
0.00 915,910.31 1,221,213.75 1,221,213.75 915,910.31 915,910.31 610,606.87 305,303.43
615.00 PAVIMENTOS GLB 1.00 6,106,068.73 6,106,068.73
15.00% 20.00% 20.00% 15.00% 15.00% 10.00% 5.00%
0.00 0.00 0.00 197,978.82 395,957.63 593,936.45 593,936.45 197,978.81
622.01 OBRAS DE ARTE Y DRENAJE GLB 1.00 1,979,788.16 1,979,788.16
10.00% 20.00% 30.00% 30.00% 10.00%
0.00 0.00 0.00 0.00 0.00 69,746.07 92,994.76 69,746.07
635.06 SEÑALIZACION Y SEGURIDAD VIAL GLB 1.00 232,486.90 232,486.90
30.00% 40.00% 30.00%
0.00 11,914.89 11,914.89 11,914.89 11,914.89 11,914.89 11,914.89 7,943.28
642.00 IMPACTO AMBIENTAL GLB 1.00 79,432.62 79,432.62
15.00% 15.00% 15.00% 15.00% 15.00% 15.00% 10.00%
19,985.24 29,977.86 29,977.86 29,977.86 29,977.86 29,977.86 19,985.24 9,992.62
643.00 MANTENIMIENTO VIAL GLB 1.00 199,852.40 199,852.40
10.00% 15.00% 15.00% 15.00% 15.00% 15.00% 10.00% 5.00%
0.00 209,079.69 209,079.69 278,772.92 278,772.92 209,079.69 139,386.46 69,693.24
645.00 TRANSPORTE GLB 1.00 1,393,864.61 1,393,864.61
15.00% 15.00% 20.00% 20.00% 15.00% 10.00% 5.00%
0.00 0.00 16,772.47 33,544.94 33,544.94 33,544.94 33,544.94 16,772.46
906.09 VARIOS GLB 1.00 167,724.69 167,724.69
10.00% 20.00% 20.00% 20.00% 20.00% 10.00%
A TOTAL COSTO DIRECTO 12,112,754.09 450,803.42 1,532,284.09 1,854,360.00 2,138,804.52 2,031,479.89 1,874,610.94 1,502,369.61 728,041.62
B GASTOS GENERALES (10.00% de A) 1,210,670.00 45,057.81 153,151.82 185,343.32 213,773.55 203,046.45 187,367.40 150,161.87 72,767.78
C UTILIDAD (8.00% de A) 969,020.33 36,064.27 122,582.73 148,348.80 171,104.36 162,518.39 149,968.88 120,189.57 58,243.33
D SUBTOTAL A+ B + C 14,292,444.42 531,925.50 1,808,018.64 2,188,052.12 2,523,682.43 2,397,044.73 2,211,947.22 1,772,721.05 859,052.73
E I.G.V. (19%) 2,715,564.44 101,065.85 343,523.54 415,729.90 479,499.66 455,438.50 420,269.97 336,817.00 163,220.02
F TOTAL GENERAL D+E 17,008,008.86 632,991.35 2,151,542.18 2,603,782.02 3,003,182.09 2,852,483.23 2,632,217.19 2,109,538.05 1,022,272.75
PORCENTAJE 100.00% 3.72% 12.65% 15.31% 17.66% 16.77% 15.48% 12.40% 6.01%