DIMENSIONES
ITEM DESCRIPCION UND CANT. N° VECES SUB TOTAL TOTAL
LARGO ANCHO ALTO
04 PLANTA DE TRATAMIENTO DE AGUA RESIDUALES
04.01. CAMARA DE REJAS Y DESARENADOR
04.01.04.02 ACERO DE REFUERZO F'Y = 4200 KG/CM2 KG Ver detalle de Acero 155.41
155.41
04.01.04.03 ENCOFRADO Y DESENCOFRADO NORMAL M2 20.41
Muros
- Transicion Entrada 4.00 0.50 0.60 1.20
2.00 0.25 0.60 0.30
- Camara de Rejas 6.00 1.70 0.60 6.12
4.00 0.30 0.60 0.72
- Desarenador 6.00 1.50 0.82 7.38
4.00 0.30 0.82 0.98
4.00 0.30 0.82 0.98
4.00 0.15 0.82 0.49
- Transicion Salida 4.00 0.65 0.72 1.87
2.00 0.25 0.72 0.36
DIMENSIONES
ITEM DESCRIPCION UND CANT. N° VECES SUB TOTAL TOTAL
LARGO ANCHO ALTO
04.01.05. TARRAJEOS Y ENLUCIDOS
04.01.05.01 TARRAJEO C/IMPERMEABILIZANTE, MEZCLA 1:2 E=1.5CM EN INTERIORES M2 12.46
Muros
- Transicion Entrada 2.00 0.50 0.60 0.60
1.00 0.25 0.60 0.15
- Camara de Rejas 4.00 1.70 0.60 4.08
2.00 0.30 0.60 0.36
- Desarenador 4.00 1.50 0.82 4.92
2.00 0.30 0.82 0.49
2.00 0.30 0.82 0.49
2.00 0.15 0.82 0.25
- Transicion Salida 2.00 0.65 0.72 0.94
1.00 0.25 0.72 0.18
04.01.05.02 TARRAJEO EN EXTERIORES MORTERO 1:5 E=1.5 CM M2 7.96
- Transicion Entrada 2.00 0.50 0.60 0.60
1.00 0.25 0.60 0.15
- Camara de Rejas 2.00 1.70 0.60 2.04
2.00 0.30 0.60 0.36
- Desarenador 2.00 1.50 0.82 2.46
2.00 0.30 0.82 0.49
2.00 0.30 0.82 0.49
2.00 0.15 0.82 0.25
- Transicion Salida 2.00 0.65 0.72 0.94
1.00 0.25 0.72 0.18
04.01.06. CARPINTERIA METALICA
04.01.06.01 REJILLA EN CAMARA UND 1.00
1.00 1.00
04.01.06.02 REJILLA EN LA VENTANA DE CAMARA UND 2.00
2.00 2.00
04.01.07. PINTURA
04.01.07.01 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS M2 7.96
- Transicion Entrada 2.00 0.50 0.60 0.60
1.00 0.25 0.60 0.15
- Camara de Rejas 2.00 1.70 0.60 2.04
2.00 0.30 0.60 0.36
- Desarenador 2.00 1.50 0.82 2.46
2.00 0.30 0.82 0.49
2.00 0.30 0.82 0.49
2.00 0.15 0.82 0.25
- Transicion Salida 2.00 0.65 0.72 0.94
1.00 0.25 0.72 0.18
04.01.08. INSTALACIONES HIDRAULICAS
04.01.08.01 VALVULA DE COMPUERTA FIERRO FUNDIDO TIPO MAZZA DE 6" UND 1.00
1.00 1.00
04.01.08.02 COMPUERTAS DE PVC INCLUY. MARCO - SEGUN DETALLE UND 4.00
4.00 4.00
04.01.08.03 VERTEDERO SUTRO INCLUY. MARCO - SEGUN DETALLE UND 1.00
1.00 1.00
DIMENSIONES
ITEM DESCRIPCION UND CANT. N° VECES SUB TOTAL TOTAL
LARGO ANCHO ALTO
04.02. MEDIDOR PARSHAL
04.02.04.02 ACERO DE REFUERZO F'Y = 4200 KG/CM2 KG Ver detalle de Acero 53.36
53.36
04.02.04.03 ENCOFRADO Y DESENCOFRADO NORMAL M2 9.87
Muros
- Parshall 1.00 7.12 0.76 5.41
1.00 5.87 0.76 4.46
04.02.05. TARRAJEOS Y ENLUCIDOS
04.02.05.01 TARRAJEO C/IMPERMEABILIANTE, MEZCLA 1:2 E=1.5CM, EN INTERIORES M2 5.53
Muros
- Parshall 1.00 7.27 0.76 5.53
04.02.06. PINTURA
04.02.06.01 PINTURA ESMALTE EN MUROS EXTERIORES 2 MANOS M2 4.58
- Parshall 1.00 6.02 0.76 4.58
04.02.07. OTROS
04.02.07.01 ACCESORIOS MEDIDOR PARSHALL UND 1.00
- Canaletas Parshall Según diseño 1.00 1.00 1.00
04.03.04.02 ACERO DE REFUERZO F'Y = 4200 KG/CM2 KG Ver detalle de Acero 8,601.16
8,601.16
04.03.04.03 ENCOFRADO Y DESENCOFRADO NORMAL M2 450.12
Losa de Fondo
- Tanque Imhoff 2.00 area= 2.55 5.10
2.00 area= 2.15 4.31
- Camara Compuerta 2.70 0.10 0.27
- Vertedero Ingreso 1.00 1.70 0.45 0.77
2.00 0.45 0.15 0.14
1.00 1.70 0.15 0.26
- Vertedero Salida 1.00 1.70 0.45 0.77
2.00 0.45 0.15 0.14
1.00 0.45 0.15 0.07
Muros
- Tanque Imhoff 4.00 7.40 6.31 186.78
4.00 5.50 6.31 138.82
- Camara Compuerta 1.00 2.30 0.85 1.96
1.00 1.90 0.85 1.62
- Vertedero Ingreso 2.00 1.70 0.25 0.85
- Vertedero Salida 2.00 1.70 0.25 0.85
- Muro Intermedio 2.00 6.80 2.00 27.20
2.00 6.80 2.00 27.20
2.00 6.80 1.34 18.20
2.00 6.80 2.08 28.22
- Pantalla Difusora 2.00 1.70 1.58 5.36
- Pantalla Deflectora 2.00 1.70 0.38 1.28
DIMENSIONES
ITEM DESCRIPCION UND CANT. N° VECES SUB TOTAL TOTAL
LARGO ANCHO ALTO
04.03.05. TARRAJEOS Y ENLUCIDOS
04.03.05.01 TARRAJEO C/IMPERMEABILIZANTE, MEZCLA 1:2 E=1.5CM, EN INTERIORES M2 1.00 307.96
Losa de Fondo
- Tanque Imhoff 1.00 6.91 5.50 38.00
- Camara Compuerta 1.00 0.65 0.60 0.39
- Vertedero Ingreso 1.00 1.70 0.30 0.51
1.00 1.70 0.45 0.77
- Vertedero Salida 1.00 1.70 0.30 0.51
1.00 1.70 0.45 0.77
Muros
- Tanque Imhoff 2.00 6.80 6.31 85.82
2.00 5.50 6.31 69.41
- Camara Compuerta 1.00 1.90 0.85 1.62
- Vertedero Ingreso 1.00 1.70 0.40 0.68
1.00 1.70 0.40 0.68
- Vertedero Salida 1.00 1.70 0.40 0.68
1.00 1.70 0.40 0.68
- Muro Intermedio 2.00 6.80 2.00 27.20
2.00 6.80 2.00 27.20
2.00 6.80 1.34 18.20
2.00 6.80 2.08 28.22
- Pantalla Difusora 2.00 1.70 1.58 5.36
- Pantalla Deflectora 2.00 1.70 0.38 1.28
04.04.04.02 ACERO CORRUGADO F'Y = 4200 KG/CM2, ZAPATAS KG Ver detalle de Acero 905.32
905.32
04.04.04.03 ENCOFRADO Y DESENCOFRADO NORMAL M2 142.84
Columnas
6.00 1.00 3.00 18.00
Muros
Posterio y frontal 4.00 4.72 2.00 37.76
laterales 8.00 4.65 1.55 57.66
Canaleta
2.00 10.00 0.70 14.00
4.00 10.00 0.30 12.00
Salpicadores
4.00 1.20 0.60 2.88
Dados de Apoyo
4.00 0.30 0.45 0.54
Muros
Posterio y frontal 2.00 4.72 2.00 18.88
laterales 4.00 4.65 1.55 28.83
Canaleta
1.00 10.40 0.50 5.20
2.00 10.40 0.30 6.24
04.04.05.02 TARRAJEO /MORTERO MEZCLA 1:3 E=1.5CM, EN EXTERIORES M2 58.63
Columnas
1.00 2.50 3.00 7.50
Muros
Posterio y frontal 2.00 4.72 2.00 18.88
laterales 4.00 4.65 1.55 28.83
Salpicadores
4.00 1.20 0.60 2.88
Dados de Apoyo
4.00 0.30 0.45 0.54
04.04.06. FILTROS
04.04.06.01 FILTRO DE GRAVA GRUESA Dprom = 1" a 1 1/2" M3 4.81
AREA= 0.48 10.00 4.81
04.04.06.02 FILTRO DE ARENA DE 2 a 3 mm M3 5.00
5.00 10.00 0.10 5.00
04.04.06.03 LADRILLO KK 18 HUECOS M2 50.00
5.00 10.00 50.00
DIMENSIONES
ITEM DESCRIPCION UND CANT. N° VECES SUB TOTAL TOTAL
LARGO ANCHO ALTO
04.04.07. ESTRUCTURA DE MADERA
04.05.04.02 ACERO DE REFUERZO F'Y = 4200 KG/CM2 KG Ver detalle de Acero 87.66
87.66
DIMENSIONES
ITEM DESCRIPCION UND CANT. N° VECES SUB TOTAL TOTAL
LARGO ANCHO ALTO
04.05.04.03 ENCOFRADO Y DESENCOFRADO DE LOSA Y TAPA M2 1.01
Losa 1.00 perimetro 4.83 0.10 0.48
1.00 4.05 0.10 0.41
Tapa 1.00 perimetro 2.50 0.05 0.13
04.05.05. MUROS
04.05.05.01 MURO DE CABEZA LADRILLO CORRIENTE M2 8.85
Muro circular 1.00 perimetro 3.90 2.27 8.85
04.05.06. OTROS
04.05.06.01 ACCESORIOS PARA POZO DE PERCOLACION GLB 1.00
1.00 1.00 1.00
04.06.04.02 ACERO DE REFUERZO F'Y = 4200 KG/CM2 KG Ver detalle de Acero 6,112.72 6,112.72 ##
04.06.05.02 TARRAJEO EN EXTERIORES, MORTERO C:A 1:5, E=1.5CM M2 2.00 100.58 201.15 ##
Muros
- Filtro Biologico 2.00 8.00 3.20 51.20
2.00 6.90 3.20 44.16
- Camara Ingreso 2.00 0.60 0.65 0.78
1.00 0.80 0.65 0.52
- Camara Salida 2.00 0.95 1.45 2.76
1.00 0.80 1.45 1.16
04.06.06. FILTRO
04.06.06.01 GRAVA ZARANDEADA 1" a 1 1/2 " M3 2.00 39.52 79.04 ##
1.00 7.60 6.50 0.80 39.52
04.06.10. VARIOS
04.06.10.01 VIGUETA PREFABRICADA EN DRENAJE DE FILTRO UND. 2.00 19.00 38.00 38.00 ##
04.06.10.02 CANALETA DE REPARTICION UND. 2.00 14.00 28.00 28.00 ##
DIMENSIONES
ITEM DESCRIPCION UND CANT. N° VECES SUB TOTAL TOTAL
LARGO ANCHO ALTO
04.07.00. CAMARA DE CONTACTO DE CLORO (01 UND) 1.00
Buzoneta
-Muros exteriores 2.00 0.80 0.10 0.60 0.10
-Muros Interiores 2.00 0.60 1.00 0.60 0.72
-Losa 1.00 0.80 0.80 0.13 0.08
04.07.04.02 ACERO DE REFUERZO F'Y = 4200 KG/CM2 KG Ver detalle de Acero 89.45 89.45
Muros
- Tanque de contacto de cloro 2.00 2.30 1.40 6.44
-Muros interiores 2.00 1.00 1.40 2.80
DIMENSIONES
ITEM DESCRIPCION UND CANT. N° VECES SUB TOTAL TOTAL
LARGO ANCHO ALTO
Buzoneta
-Muros exteriores 2.00 0.80 0.60 0.96
-Muros Interiores 2.00 0.60 0.60 0.72
-Losa 3.00 0.80 0.13 0.31
Muros
-Muros interiores 2.00 1.10 1.40 3.08
Buzoneta
-Muros Interiores 2.00 0.70 0.60 0.84
Muros
- Tanque de contacto de cloro 2.00 2.40 1.40 6.72
Buzoneta
-Muros exteriores 2.00 0.90 0.60 1.08
-Losa 3.00 0.80 0.13 0.31
Muros
- Tanque de contacto de cloro 2.00 2.40 1.40 6.72
Buzoneta
-Muros exteriores 2.00 0.90 0.60 1.08
-Losa 3.00 0.80 0.13 0.31
04.07.08. ACCESORIOS
04.07.08.01 SUMINISTRO E INSTAL. DE ACCESORIOS P/ CAMARA DE CONTACTO DE CLORO UND 1.00
-Codo de PVC 90 x1/2" und 4.00 4.00
-Llave de paso PVC 1/2" und 3.00 3.00
-Tuberia PVC C-10 de 1/2" ml 2.85 2.85
-Union universal PVC 1/2" und 6.00 6.00
-Tanque politileno de 500 L und 1.00 1.00
-Adaptador PVC UPR 1/2'' und 6.00 6.00
-Niple PVC SAP C/R 1/2'' und 6.00 6.00
-Valvula Flotadora de 1/2'' und 1.00 1.00
-Tapon PVC 1/2'' und 1.00 1.00
-Planchas de PVC e=3 cm S.D. (1.00x0.75m) und 7.00 7.00
04.10.05.01.01 EXCAVACION DE BUZON TIPO I D=1.6M (A MANO) - H=1.20M, (T.N.) UND 3.00 3.00 3.00
04.10.05.01.01 ELIMINACION DE MATERIAL EXCEDENTE (D. PROM. 1KM) M3 ESP. 1.25 7.24 9.05
04.11.05. OTROS
04.11.05.01 SUMINISTRO E INSTALACION DE VALVULAS UND. 1.00 2.00 2.00