PRESUPUESTO DEL PROYECTO ACTUALIZADO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMUALDO SALDO
ITEM DESCRIPCION
UND METRADO P. UNITARIO TOTAL METRADO MONTO S/ % METRADO MONTO S/ % METRADO MONTO S/ % METRADO MONTO S/ %
01 TRABAJOS PRELIMINARES
01.01 CARTEL DE OBRA 4.8 M X 3.6 M und 2.00 1,555.10 S/ 3,110.20 2.00 S/ 3,110.20 100.00% 0.00 S/ - 0.00% 2.00 S/ 3,110.20 100.00% - S/ - 0.00%
01.02 CAMPAMENTO glb 1.00 101,800.00 S/ 101,800.00 0.90 S/ 91,518.20 90.00% 0.10 S/ 10,180.00 10.00% 1.00 S/ 101,698.20 100.00% - S/ 101.80 0.00%
01.03 MOVILIZACIÒN Y DESMOVILIZACIÒN DE EQUIPO glb 1.00 122,358.72 S/ 122,358.72 0.95 S/ 116,118.43 95.00% 0.05 S/ 6,117.94 5.00% 1.00 S/ 122,236.37 100.00% - S/ 122.35 0.00%
01.04 TOPOGRAFIA Y GEOREFERENCIACION km 13.39 1,293.75 S/ 17,323.31 13.39 S/ 17,325.91 100.00% 0.00 S/ - 0.00% 13.39 S/ 17,325.91 100.00% - S/ (2.60) 0.00%
01.05 MANTENIMIENTO DEL TRANSITO Y SEGURIDAD VIAL
mes 10.00 9,567.74 S/ 95,677.40 10.00 S/ 95,677.41 100.00% 0.00 S/ 0.01 0.00% 10.00 S/ 95,677.42 100.00% - S/ (0.02) 0.00%
DURANTE LA EJECUCION DE TRABAJOS
01.06 MEJORAMIENTO ACCESOS A LA CANTERA km 1.00 34,318.31 S/ 34,318.31 1.00 S/ 34,318.32 100.00% 0.00 S/ - 0.00% 1.00 S/ 34,318.32 100.00% - S/ (0.01) 0.00%
01.07 MEJORAMIENTO ACCESOS A D.M.E. Y CAMPAMENTO km 0.40 34,318.31 S/ 13,727.32 0.40 S/ 13,658.69 100.00% 0.00 S/ - 0.00% 0.40 S/ 13,658.69 100.00% - S/ 68.63 0.00%
01.08 REMOCION Y REPOSICION DE CERCAS DE ALAMBRE m 3,124.74 22.08 S/ 68,994.26 3,124.74 S/ 68,994.26 100.00% 0.00 S/ - 0.00% 3,124.74 S/ 68,994.26 100.00% - S/ - 0.00%
01.09 APERTURA DE DME Y CAMPAMENTO glb 1.00 125,271.22 S/ 125,271.22 1.00 S/ 125,020.68 100.00% 0.00 S/ - 0.00% 1.00 S/ 125,020.68 100.00% - S/ 250.54 0.00%
01.10 FLETE DE MATERIALES A OBRA glb 1.00 400,069.14 S/ 400,069.14 1.00 S/ 397,186.69 100.00% 0.00 S/ - 0.00% 1.00 S/ 397,186.69 100.00% - S/ 2,882.45 0.00%
02 SEGURIDAD Y SALUD S/ -
02.01 EQUIPOS DE PROTECCION INDIVUAL glb 1.00 48,450.00 S/ 48,450.00 1.00 S/ 48,450.00 100.00% 0.00 S/ - 0.00% 1.00 S/ 48,450.00 100.00% - S/ - 0.00%
02.02 EQUIPOS DE PROTECCION COLECTIVA glb 1.00 11,835.00 S/ 11,835.00 1.00 S/ 11,835.01 100.00% 0.00 S/ - 0.00% 1.00 S/ 11,835.01 100.00% - S/ (0.01) 0.00%
02.03 SEÑALIZACION TRANSITORIA DE SEGURIDAD EN OBRA glb 1.00 17,882.36 S/ 17,882.36 1.00 S/ 17,936.00 100.00% 0.00 S/ - 0.00% 1.00 S/ 17,936.00 100.00% - S/ (53.64) 0.00%
02.04 RECURSOS PARA RESPUESTA ANTE EMERGENCIAS EN
glb 1.00 32,628.96 S/ 32,628.96 1.00 S/ 32,726.85 100.00% 0.00 S/ - 0.00% 1.00 S/ 32,726.85 100.00% - S/ (97.89) 0.00%
SEGURIDAD Y SALUD EN EL TRABAJO
03 MOVIMIENTO DE TIERRAS S/ -
03.01 DESBROCE Y LIMPIEZA ha 0.27 6,757.82 S/ 1,824.61 0.27 S/ 1,824.60 100.00% 0.00 S/ - 0.00% 0.27 S/ 1,824.60 100.00% - S/ 0.01 0.00%
03.02 EXCAVACION EN EXPLACIONES EN MATERIAL COMUN m³ 86,481.23 11.26 S/ 973,778.65 86,481.23 S/ 973,778.64 100.00% 0.00 S/ - 0.00% 86,481.23 S/ 973,778.64 100.00% - S/ 0.01 0.00%
03.03 PERFILADO Y COMPACTADO DE SUB-RASANTE EN
m² 119,702.13 2.39 S/ 286,088.09 119,702.13 S/ 286,088.09 100.00% 0.00 S/ - 0.00% 119,702.13 S/ 286,088.09 100.00% - S/ - 0.00%
ZONAS DE CORTE
03.04 CONFORMACION DE TERRAPLENES m³ 34,964.73 32.15 S/ 1,124,116.07 34,964.73 S/ 1,124,116.07 100.00% 0.00 S/ - 0.00% 34,964.73 S/ 1,124,116.07 100.00% - S/ - 0.00%
03.05 MEJORAMIENTO DE SUB RASANTE C/MAT. PRESTAMO m³ 13,097.70 31.39 S/ 411,136.80 13,097.70 S/ 411,136.81 100.00% 0.00 S/ - 0.00% 13,097.70 S/ 411,136.81 100.00% - S/ (0.01) 0.00%
04 SUB BASES Y BASES S/ -
04.01 SUB BASE GRANULAR DE 0.20 M m² 111,826.62 27.88 S/ 3,117,726.17 111,826.62 S/ 3,117,726.17 100.00% 0.00 S/ - 0.00% 111,826.62 S/ 3,117,726.17 100.00% - S/ - 0.00%
04.02 BASE GRANULAR DE 0.15 M m² 100,987.63 21.57 S/ 2,178,303.24 100,987.63 S/ 2,178,303.32 100.00% 0.00 S/ - 0.00% 100,987.63 S/ 2,178,303.32 100.00% - S/ (0.08) 0.00%
05 PAVIMENTO ASFALTICO S/ -
05.01 IMPRIMACION ASFALTICA m² 96,773.24 10.03 S/ 970,635.60 96,773.24 S/ 970,635.60 100.00% 0.00 S/ - 0.00% 96,773.24 S/ 970,635.60 100.00% - S/ - 0.00%
05.02
TRATAMIENTO SUPERFICIAL BICAPA (TSB) m² - 19.57 S/ - S/ -
05.03 RIEGO DE LIGA m² 95,719.64 5.69 S/ 544,644.75 95,719.64 S/ 544,644.75 100.00% 0.00 S/ - 0.00% 95,719.64 S/ 544,644.75 100.00% - S/ - 0.00%
06 DRENAJE S/ -
06.01 ALCANTARILLAS MCA S/ -
06.01.01 DESBROCE Y LIMPIEZA MANUAL m² 1,160.64 2.90 S/ 3,365.86 1,160.64 S/ 3,365.86 100.00% 0.00 S/ - 0.00% 1,160.64 S/ 3,365.86 100.00% - S/ - 0.00%
06.01.02 TRAZO/NIVELES Y REPLANTEO m² 1,018.57 6.00 S/ 6,111.42 1,018.57 S/ 6,111.41 100.00% 0.00 S/ - 0.00% 1,018.57 S/ 6,111.41 100.00% - S/ 0.01 0.00%
06.01.03 DESVIO PROVISIONAL DE CURSOS DE AGUA m 1,003.58 26.38 S/ 26,474.44 1,003.58 S/ 26,474.43 100.00% 0.00 S/ - 0.00% 1,003.58 S/ 26,474.43 100.00% - S/ 0.01 0.00%
06.01.04 DEMOLICION DE ALCANTARILLAS Y CABEZALES
m³ 21.31 131.81 S/ 2,808.87 21.31 S/ 2,808.88 100.00% 0.00 S/ - 0.00% 21.31 S/ 2,808.88 100.00% - S/ (0.01) 0.00%
EXISTENTES DE MCA
06.01.05 EXCAVACION PARA ESTRUCTURAS C/MAQUINARIA m³ 2,019.72 9.41 S/ 19,005.59 2,019.72 S/ 19,005.59 100.00% 0.00 S/ - 0.00% 2,019.72 S/ 19,005.59 100.00% - S/ - 0.00%
06.01.06 ENCOFRADO Y DESENCOFRADO CUERPO m² 1,807.43 52.64 S/ 95,143.12 1,807.43 S/ 95,143.12 100.00% 0.00 S/ - 0.00% 1,807.43 S/ 95,143.12 100.00% - S/ - 0.00%
06.01.07 ENCOFRADO Y DESENCOFRADO CABEZALES m² 675.76 51.52 S/ 34,815.16 675.76 S/ 34,815.16 100.00% 0.00 S/ - 0.00% 675.76 S/ 34,815.16 100.00% - S/ - 0.00%
06.01.08 ACERO DE REFUERZO F'Y = 4200 KG/CM2 kg 56,563.77 7.76 S/ 438,934.86 56,563.77 S/ 438,934.85 100.00% 0.00 S/ - 0.00% 56,563.77 S/ 438,934.85 100.00% - S/ 0.01 0.00%
06.01.09 CONCRETO F'C = 1000 KG/CM2 PARA SOLADOS m² 439.58 38.78 S/ 17,046.91 439.58 S/ 17,046.92 100.00% 0.00 S/ - 0.00% 439.58 S/ 17,046.92 100.00% - S/ (0.01) 0.00%
06.01.10 CONCRETO F'C = 210 KG/CM2 m³ 513.42 574.51 S/ 294,965.10 513.42 S/ 294,965.09 100.00% 0.00 S/ - 0.00% 513.42 S/ 294,965.09 100.00% - S/ 0.01 0.00%
06.01.11 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS m³ 1,260.72 38.09 S/ 48,020.80 1,260.72 S/ 48,020.80 100.00% 0.00 S/ - 0.00% 1,260.72 S/ 48,020.80 100.00% - S/ - 0.00%
06.01.12 RELLENO CON MATERIAL GRANULAR ESTRUCTURAS m³ 16.00 80.26 S/ 1,284.16 16.00 S/ 1,284.16 100.00% 0.00 S/ - 0.00% 16.00 S/ 1,284.16 100.00% - S/ - 0.00%
06.01.13 MAMPOSTERIA CON PIEDRA EMBOQUILLADA F'C = 175
m³ 125.51 289.48 S/ 36,332.63 125.51 S/ 36,332.63 100.00% 0.00 S/ - 0.00% 125.51 S/ 36,332.63 100.00% - S/ - 0.00%
KG/CM2 + 60%PM
06.01.14 LIMPIEZA Y CONFORMACION DE CAUCE m 287.50 50.11 S/ 14,406.63 287.50 S/ 14,406.63 100.00% 0.00 S/ - 0.00% 287.50 S/ 14,406.63 100.00% - S/ - 0.00%
06.02 ALCANTARILLAS TMC S/ -
06.02.01 DESBROCE Y LIMPIEZA MANUAL m² 2,479.60 2.90 S/ 7,190.84 2,479.60 S/ 7,190.84 100.00% 0.00 S/ - 0.00% 2,479.60 S/ 7,190.84 100.00% - S/ - 0.00%
06.02.02 TRAZO NIVELES Y REPLANTEO m² 2,479.60 6.00 S/ 14,877.60 2,479.60 S/ 14,877.60 100.00% 0.00 S/ - 0.00% 2,479.60 S/ 14,877.60 100.00% - S/ - 0.00%
06.02.03 DESVIO PROVISIONAL DE CURSOS DE AGUA m 364.15 26.38 S/ 9,606.28 364.15 S/ 9,606.27 100.00% 0.00 S/ - 0.00% 364.15 S/ 9,606.27 100.00% - S/ 0.01 0.00%
06.02.04 DEMOLICION DE ALCANTARILLAS DE TMC L=9.00 m und 23.00 824.79 S/ 18,970.17 23.00 S/ 18,970.17 100.00% 0.00 S/ - 0.00% 23.00 S/ 18,970.17 100.00% - S/ - 0.00%
VALORIZACION DE FINAL DE OBRA
CONSORCIO SUPERVISOR II
OBRA : "CREACION DE LA CARRETERA A NIVEL DE BICAPA DESDE EL CRUCE CARRETERA TARAPOTO-SISA EN EL KM 36-SANTA MARTHA HASTA LA LOCALIDAD DE NUEVO SANTA ROSA, DISTRITO DE SANTA ROSA - PROVINCIA DE EL DORADO - DEPARTAMENTO DE SAN MARTIN"
PRESUPUESTO DEL PROYECTO ACTUALIZADO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMUALDO SALDO
ITEM DESCRIPCION
UND METRADO P. UNITARIO TOTAL METRADO MONTO S/ % METRADO MONTO S/ % METRADO MONTO S/ % METRADO MONTO S/ %
PRESUPUESTO DEL PROYECTO ACTUALIZADO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMUALDO SALDO
ITEM DESCRIPCION
UND METRADO P. UNITARIO TOTAL METRADO MONTO S/ % METRADO MONTO S/ % METRADO MONTO S/ % METRADO MONTO S/ %
PRESUPUESTO DEL PROYECTO ACTUALIZADO AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMUALDO SALDO
ITEM DESCRIPCION
UND METRADO P. UNITARIO TOTAL METRADO MONTO S/ % METRADO MONTO S/ % METRADO MONTO S/ % METRADO MONTO S/ %
11.03 SEÑALES INFORMATIVAS m² 25.70 579.72 S/ 14,898.80 - S/ - 0.00% 25.70 S/ 14,898.80 100.00% 25.70 S/ 14,898.80 100.00% - S/ - 0.00%
11.04 POSTES DE SOPORTE DE CONCRETO und 224.00 290.96 S/ 65,175.04 - S/ - 0.00% 224.00 S/ 65,175.04 100.00% 224.00 S/ 65,175.04 100.00% - S/ - 0.00%
11.05 ESTRUCTURA DE SOPORTES DE SEÑALES TIPO E-1 und 11.00 1,880.83 S/ 20,689.13 - S/ - 0.00% 11.00 S/ 20,689.13 100.00% 11.00 S/ 20,689.13 100.00% - S/ - 0.00%
11.06 CIMENTACION Y MONTAJE DE SEÑAL INFORMATIVA und 22.00 712.39 S/ 15,672.58 - S/ - 0.00% 22.00 S/ 15,672.58 100.00% 22.00 S/ 15,672.58 100.00% - S/ - 0.00%
11.07 POSTE DELINEADOR und 399.00 171.80 S/ 68,548.20 - S/ - 0.00% 399.00 S/ 68,548.20 100.00% 399.00 S/ 68,548.20 100.00% - S/ - 0.00%
11.08 TACHA RETROREFLECTIVA und 52.00 23.08 S/ 1,200.16 - S/ - 0.00% 52.00 S/ 1,200.16 100.00% 52.00 S/ 1,200.16 100.00% - S/ - 0.00%
11.09 MARCAS EN EL PAVIMENTO m² 3,235.54 14.50 S/ 46,915.33 - S/ - 0.00% 3235.54 S/ 46,915.33 100.00% 3,235.54 S/ 46,915.33 100.00% - S/ - 0.00%
11.10 GUARDAVIA METALICA m 242.00 260.88 S/ 63,132.96 - S/ - 0.00% 242.00 S/ 63,132.96 100.00% 242.00 S/ 63,132.96 100.00% - S/ - 0.00%
11.11 SECCION FINAL und 5.00 206.28 S/ 1,031.40 - S/ - 0.00% 5.00 S/ 1,031.40 100.00% 5.00 S/ 1,031.40 100.00% - S/ - 0.00%
11.12 SECCION DE AMORTIGUACION und 5.00 315.81 S/ 1,579.05 - S/ - 0.00% 5.00 S/ 1,579.05 100.00% 5.00 S/ 1,579.05 100.00% - S/ - 0.00%
11.13 CAPTAFAROS und 62.00 36.91 S/ 2,288.42 - S/ - 0.00% 62.00 S/ 2,288.42 100.00% 62.00 S/ 2,288.42 100.00% - S/ - 0.00%
11.14 POSTE DE KILOMETRAJE und 14.00 263.55 S/ 3,689.70 - S/ - 0.00% 14.00 S/ 3,689.70 100.00% 14.00 S/ 3,689.70 100.00% - S/ - 0.00%
11.15 GIBAS O RESALTO m 14.00 634.53 S/ 8,883.42 - S/ - 0.00% 14.00 S/ 8,883.42 100.00% 14.00 S/ 8,883.42 100.00% - S/ - 0.00%
12 PLAN DE MANEJO AMBIENTAL S/ -
12.01 PROGRAMA DE MITIGACION AMBIENTAL S/ -
12.01.01 DEPOSITOS DE MATERIAL EXCEDENTE m³ 6,783.58 1.37 S/ 9,293.50 6,783.58 S/ 9,293.49 100.00% 0.00 S/ - 0.00% 6,783.58 S/ 9,293.49 100.00% - S/ 0.01 0.00%
12.02 PROGRAMA DE MONITOREO AMBIENTAL S/ -
12.02.01 2,000.00 S/ 36,000.00 6.00 S/ 12,000.00 33.33% 12.00 S/ 24,000.00 66.67% 18.00 S/ 36,000.00 100.00% - S/ - 0.00%
MONITOREO DE LA CALIDAD DEL AGUA und 18.00
12.02.02
MONITOREO DE LA CALIDAD DEL AIRE und 3.00 1,500.00 S/ 4,500.00 1.00 S/ 1,500.00 33.33% 2.00 S/ 3,000.00 66.67% 3.00 S/ 4,500.00 100.00% - S/ - 0.00%
12.02.03 MONITOREO DE LA CALIDAD DE RUIDO und 3.00 527.53 S/ 1,582.59 1.00 S/ 527.53 33.33% 2.00 S/ 1,055.06 66.67% 3.00 S/ 1,582.59 100.00% - S/ - 0.00%
12.03
PROGRAMA DE MANEJO DE REISDUOS S/ -
12.03.01 ADQUISICION DE CONTENEDORES und 10.00 732.00 S/ 7,320.00 10.00 S/ 7,320.00 100.00% 0.00 S/ - 0.00% 10.00 S/ 7,320.00 100.00% - S/ - 0.00%
12.03.02 BAÑO QUIMICO PORTATIL mes 2.80 4,560.00 S/ 12,768.00 2.80 S/ 12,768.00 100.00% 0.00 S/ - 0.00% 2.80 S/ 12,768.00 100.00% - S/ - 0.00%
12.04 PROGRAMA DE CIERRE Y ABANDONO S/ -
12.04.01 READECUACION AMBIENTAL DE CAMPAMENTOS ha 1.00 14,955.90 S/ 14,955.90 - S/ - 0.00% 1.00 S/ 14,955.90 100.00% 1.00 S/ 14,955.90 100.00% - S/ - 0.00%
12.04.02 READECUACION AMBIENTAL DE DME ha 1.50 13,124.85 S/ 19,687.28 1.50 S/ 19,687.28 100.00% 0.00 S/ - 0.00% 1.50 S/ 19,687.28 100.00% - S/ - 0.00%