Cronograma Desembolso
Cronograma Desembolso
Cronograma Desembolso
PROYECT : "CONSTRUCCION DE PUENTE; EN EL (LA) VIA VECINAL QUE CONECTA EL ANEXO DE NUEVA ESPERANZA CON LA COMUNIDAD LA VICTORIA
EN LA LOCALIDAD DE NUEVA ESPERANZA, DISTRITO DE TAYABAMBA, PROVINCIA DE PATAZ - LA LIBERTAD
MES - 01 MES - 02
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
SEM - 01 SEM - 02 SEM - 03 SEM - 04 SEM - 01 SEM - 02 SEM - 03 SEM - 04
01 OBRAS PROVISIONALES 7,472.91
01.01 CAMPAMENTO PROVICIONAL DE OBRA m2 40.00 56.28 2,251.20 2,251.20
01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 1,000.00 1,000.00 300.00 300.00 400.00
01.03 DESBROCE Y LIMPIEZA DE TERRENO m2 104.00 9.32 969.28 969.28
01.04 CARTEL DE OBRA 3.60x2.40 und 1.00 970.43 970.43 970.43
01.05 MANTENIENTO DE TRANSITO Y SEGURIDAD VIAL glb 1.00 382.00 382.00 133.70 114.60 76.40 57.30
01.06 MEDIDAS DE SEGURIDAD PARA PERSONAL glb 1.00 750.00 750.00 93.75 93.75 93.75 93.75 93.75 93.75 93.75 93.75
01.07 PLAN PARA LA VIGILANCIA, PREVENCION Y CONTROL DEL COVID -19 glb 1.00 1,150.00 1,150.00 143.75 143.75 143.75 143.75 143.75 143.75 143.75 143.75
02 TRABAJOS PRELIMINARES 1,253.00
02.01 TRAZO Y REPLANTEO INICAL m2 140.00 5.04 705.60 493.92 211.68
02.02 LIMPIEZA DEL TERRENO MANUAL m2 140.00 3.91 547.40 547.40
03 MOVIMIENTO DE TIERRAS 22,936.92
03.01 EXCAVACION DE ZANJAS PARA ZAPATAS m3 113.00 95.00 10,735.00 5,367.50 5,367.50
03.02 CORTE DE TERRENO ROCOSO C/N EQUIPO (COMPRENSORA Y MARTILLO m3 20.46 16.59 339.43 339.43
03.03 CORTE DE MATERIAL SUELTO CON EQUIPO m3 54.45 2.89 157.36 78.68 78.68
03.04 APISONADO DE TERRENO m2 18.75 113.26 2,123.63 2,123.63
03.05 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 108.98 57.73 6,291.42 3,145.71 3,145.71
03.06 RELLENO DE PIEDRA DE 4" m3 21.48 110.61 2,375.90 2,375.90
03.07 ELIMINACION DE MATERIAL EXCEDENTE m3 89.89 10.17 914.18 457.09 457.09
04 SUB ESTRUCTURAS 28,399.64
04.01 CONCRETO ZAPATAS f'c=210 kg/cm2 m3 32.58 446.50 14,546.97 7,273.49 7,273.49
04.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 2,019.34 6.86 13,852.67 6,926.34 6,926.34
04.03 MUROS REFORZADOS 19,281.41
04.03.01 CONCRETO 210 KG/CM2 m3 25.04 457.18 11,447.79 5,723.90 3,434.34 2,289.56
04.03.02 ENCOFRADO Y DESENCOFRADO DE MURETES m2 38.20 52.13 1,991.37 995.69 597.41 398.27
04.03.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 851.64 6.86 5,842.25 2,921.13 2,921.13
04.04 PARAPETOS 2,324.04
04.04.01 CONCRETO f'c=175 kg/cm2 m3 2.20 430.89 947.96 473.98 473.98
04.04.02 ENCOFRADO Y DESENCOFRADO PARA MURO PARAPETO m2 12.00 78.79 945.48 472.74 472.74
04.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 62.77 6.86 430.60 430.60
04.05 ALETAS DE MUROS 24,019.69
04.05.01 CONCRETO 210 KG/CM2 m3 31.83 457.18 14,552.04 7,276.02 7,276.02
04.05.02 ENCOFRADO Y DESENCOFRADO DE MURETES m2 67.49 52.13 3,518.25 1,759.13 1,759.13
04.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 867.26 6.86 5,949.40 5,949.40
05 SUPER ESTRUCTURAS 26,459.43
05.01 CONCRETO f'c=245 kg/cm2 EN VIGAS m3 12.68 468.73 5,943.50 5,943.50
05.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 92.94 51.87 4,820.80 2,410.40 2,410.40
05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 2,287.92 6.86 15,695.13 15,695.13
05.04 LOSAS MECIZAS 21,843.55
05.04.01 CONCRETO MACIZA f'c=245 kg/cm2 m3 17.92 461.72 8,274.02 8,274.02
05.04.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 57.00 51.87 2,956.59 1,478.30 1,478.30
05.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 1,522.18 6.86 10,442.15 10,442.15
05.04.04 TUBERIA PVC SAL 3"(EMPOTRE BARANDAS) m 2.80 36.32 101.70 101.70
CRONOGRAMA VALORIZADO DE OBRA
PROYECT : "CONSTRUCCION DE PUENTE; EN EL (LA) VIA VECINAL QUE CONECTA EL ANEXO DE NUEVA ESPERANZA CON LA COMUNIDAD LA VICTORIA
EN LA LOCALIDAD DE NUEVA ESPERANZA, DISTRITO DE TAYABAMBA, PROVINCIA DE PATAZ - LA LIBERTAD
MES - 01 MES - 02
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
SEM - 01 SEM - 02 SEM - 03 SEM - 04 SEM - 01 SEM - 02 SEM - 03 SEM - 04
05.04.05 TUBERIA PVC SAL DE 6" m 4.20 16.45 69.09 69.09
05.05 VEREDA 3,030.07
05.05.01 CONCRETO f'c=175 kg/cm2 m3 1.87 430.89 805.76 805.76
05.05.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 23.40 51.87 1,213.76 1,213.76
05.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 147.31 6.86 1,010.55 1,010.55
06 REVOQUES Y ENLUCIDOS 11,782.20
06.01 TARRAJEO (MURO Y ALETAS) ACABADO PULIDO C:A 1:5 e=2 cm m2 105.69 55.57 5,873.19 5,873.19
06.02 TARRAJEO DE VIGAS m2 92.94 57.93 5,384.01 5,384.01
06.03 TARRAJEO PULIDO EN AREAS PEQUEÑAS m2 12.00 43.75 525.00 525.00
07 PINTURAS 384.70
07.01 PINTADO DE MUROS (contraimpacto-parapetos) m2 10.00 38.47 384.70 384.70
08 SEÑALIZACION 765.32
08.01 SEÑAL IMFORMATIVA (1.80xmx1.00m)incl.PORTICO und 2.00 382.66 765.32 765.32
08.02 OTROS 2,412.33
08.02.01 PASAMANO METALICO m 22.40 97.22 2,177.73 2,177.73
08.02.02 LIMPIEZA GENERAL DE LA OBRA m2 60.00 3.91 234.60 234.60
09 FLETE 18,360.00
09.01 FLETE TERRESTRE glb 1.00 18,360.00 18,360.00 9,180.00 7,344.00 1,836.00
COSTO DIRECTO 190,725.21 20,529.61 6,323.11 39,961.15 64,093.35 33,925.06 2,461.81 4,954.29 18,476.83
GASTOS GENERALES (7%) 13,350.76 1,437.07 442.62 2,797.28 4,486.53 2,374.75 172.33 346.80 1,293.38
UTILIDADES (7%) 13,350.76 1,437.07 442.62 2,797.28 4,486.53 2,374.75 172.33 346.80 1,293.38
"""""""""""""""" """""""""""" """""""""""" """""""""""" """""""""""" """""""""""" """""""""""" """""""""""" """"""""""""""""
SUB TOTAL 217,426.74 23,403.76 7,208.35 45,555.71 73,066.42 38,674.56 2,806.46 5,647.89 21,063.59
IGV (18%) 39,136.81 4,212.68 1,297.50 8,200.03 13,151.96 6,961.42 505.16 1,016.62 3,791.45
"""""""""""""""" """""""""""" """""""""""" """""""""""" """""""""""" """""""""""" """""""""""" """""""""""" """"""""""""""""
TOTAL VALOR REFERENCIAL 256,563.55 27,616.43 8,505.85 53,755.74 86,218.38 45,635.99 3,311.63 6,664.51 24,855.03
SUPERVISION 6% 15,393.81
ELABORACION DE EXPEDIENTE TECNICO 12% 30,787.63
---------------- ---------------- ---------------- ---------------- ---------------- ---------------- ---------------- ---------------- ----------------
COSTO TOTAL 302,744.99 27,616.43 8,505.85 53,755.74 86,218.38 45,635.99 3,311.63 6,664.51 24,855.03
% 10.76% 3.32% 20.95% 33.61% 17.79% 1.29% 2.60% 9.69%
% ACUMULADO 10.76% 14.08% 35.03% 68.64% 86.42% 87.71% 90.31% 100.00%
69% 31%
OBRAS PROVISIONALES 7,472.91 4,862.11 537.50 637.50 352.10 313.90 237.50 237.50 294.80
OBRAS PRELIMINARES 1,253.00 1,041.32 211.68
MOVIMIENTO DE TIERRAS 22,936.92 5,446.18 5,785.61 0.00 2,580.72 2,375.90 0.00 3,145.71 3,602.80
SUB ESTRUCTURAS 28,399.64 0.00 0.00 14,199.82 14,199.82 0.00 0.00 0.00 0.00
MUROS REFORZADOS 19,281.41 0.00 0.00 9,640.71 6,952.87 2,687.83 0.00 0.00 0.00
PARAPETOS 2,324.04 0.00 0.00 430.60 946.72 946.72 0.00 0.00 0.00
ALETAS DE MUROS 24,019.69 0.00 0.00 7,708.53 9,035.15 7,276.02 0.00 0.00 0.00
SUPER ESTRUCTURAS 26,459.43 0.00 0.00 0.00 18,105.53 8,353.90 0.00 0.00 0.00
LOSAS MECIZAS 21,843.55 0.00 0.00 0.00 11,920.45 9,923.11 0.00 0.00 0.00
VEREDA 3,030.07 0.00 0.00 0.00 0.00 0.00 2,224.31 805.76 0.00
REVOQUES Y ENLUCIDOS 11,782.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,782.20
PINTURAS 384.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 384.70
SEÑALIZACION 765.32 0.00 0.00 0.00 0.00 0.00 0.00 765.32 0.00
OTROS 2,412.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,412.33
FLETE 18,360.00 9,180.00 0.00 7,344.00 0.00 1,836.00 0.00 0.00 0.00
COSTO DIRECTO S/. 190,725.21 S/. 20,529.61 S/. 6,323.11 S/. 39,961.15 S/. 64,093.35 S/. 33,925.06 S/. 2,461.81 S/. 4,954.29 S/. 18,476.83
GASTOS GENERALES (7%) 13,350.76 1,437.07 442.62 2,797.28 4,486.53 2,374.75 172.33 346.80 1,293.38
UTILIDADES (7%) 13,350.76 1,437.07 442.62 2,797.28 4,486.53 2,374.75 172.33 346.80 1,293.38
""""""""""""""""
SUB TOTAL 217,426.74 23,403.76 7,208.35 45,555.71 73,066.42 38,674.56 2,806.46 5,647.89 21,063.59
IGV (18%) 39,136.81 4,212.68 1,297.50 8,200.03 13,151.96 6,961.42 505.16 1,016.62 3,791.45
""""""""""""""""
TOTAL VALOR REFERENCIAL 256,563.55 27,616.43 8,505.85 53,755.74 86,218.38 45,635.99 3,311.63 6,664.51 24,855.03
ELABORACION DE EXPEDIENTE TECNICO 12% 30,787.63
SUPERVISION 6% 15,393.81 1,656.99 510.35 3,225.34 5,173.10 2,738.16 198.70 399.87 1,491.30
------------
COSTO TOTAL S/. 302,744.99 S/. 29,273.42 S/. 9,016.20 S/. 56,981.08 S/. 91,391.48 S/. 48,374.15 S/. 3,510.32 S/. 7,064.38 S/. 26,346.33