CALENDARIO DE INSUMOS
CALENDARIO DE INSUMOS
CALENDARIO DE INSUMOS
: MEJORAMIENTO DEL CERCO PERIMETRICO DE LA I.E. Nro 40213 DE TUCTUMPAYA, DEL DISTRITO DE POCSI, PROVINCIA DE
Obra
AREQUIPA, DEPARTAMENTO DE AREQUIPA
Ubicacion : POCSI - AREQUIPA - AREQUIPA
Costo A : Dic - 2024 Cliente : MUNICIPALIDAD DISTRITAL DE POCSI
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 15 Días 15 Días 15 Días
45 Dias
MANO DE OBRA
47 00006 CAPATAZ HH 86.79 28.38 2,463.10 618.49 546.77 1,297.84 2,463.10
47 00086 TOPOGRAFO HH 20.29 28.38 575.83 575.83 - - 575.83
47 00007 OPERARIO HH 890.33 28.38 25,267.57 4,016.22 5,391.83 15,859.52 25,267.57
47 00008 OFICIAL HH 227.24 22.32 5,072.00 1,499.84 1,765.89 1,806.27 5,072.00
47 00009 PEON HH 1,103.37 20.21 22,299.11 7,329.35 4,138.53 10,831.23 22,299.11
47 07421 CHOFER MES 1.50 2,000.00 3,000.00 1,000.00 1,000.00 1,000.00 3,000.00
47 00112 OPERADOR DE EQUIPO LIVIANO HH 6.94 28.38 196.96 196.96 - - 196.96
MATERIALES
00 07106 EXTINTOR DE POLVO QUIMICO SECO (PQS) und 2.00 127.12 254.24 84.75 84.75 84.74 254.24
02 00093 ALAMBRE NEGRO N°16 KG 25.50 3.09 78.80 7.70 71.10 - 78.80
02 00018 ALAMBRE NEGRO N°8 KG 331.95 3.09 1,025.73 228.03 392.45 405.25 1,025.73
02 06824 BISAGRA DE FIERRO 3" PAR 0.94 3.31 3.11 3.11 - - 3.11
02 06825 CHAPA YALE 02 GOLPES UND 0.12 61.36 7.36 7.36 - - 7.36
02 00022 CLAVOS CON CABEZA DE 2 1/2", 3", 4" KG 74.19 5.51 408.79 195.91 211.78 1.10 408.79
02 06203 CLAVOS PARA MADERA CON CABEZA DE 3" kg 2.65 5.50 14.58 - - 14.58 14.58
02 07477 PERNOS HEXAGONALES DE 3/4" x 3 1/2" UND 9.00 4.80 43.20 43.20 - - 43.20
03 06206 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 1,183.86 6.19 7,328.09 - 7,328.09 - 7,328.09
04 00033 ARENA FINA M3 13.25 95.00 1,258.75 583.64 - 675.11 1,258.75
04 00029 ARENA GRUESA M3 22.22 85.00 1,888.70 520.50 597.22 770.98 1,888.70
05 00002 AGUA M3 4.06 6.00 24.36 2.55 15.22 6.59 24.36
05 00099 PIEDRA CHANCADA DE 1/2" M3 6.82 90.00 613.80 613.80 - - 613.80
05 07423 PIEDRA GRANDE DE 6"- 8" M3 10.42 62.00 646.04 646.04 - - 646.04
05 00030 PIEDRA ZARANDEADA DE 1/2'' Y 3/4'' M3 15.00 63.03 945.45 - 659.75 285.70 945.45
17 01402 LADRILLO K.K. DE ARCILLA 9X14X24 CM UND 3,955.77 1.32 5,221.62 - - 5,221.62 5,221.62
21 07480 AGUA PARA LA OBRA MES 1.50 150.00 225.00 75.00 75.00 75.00 225.00
21 00003 CEMENTO PORTLAND TIPO IP (42.5KG) BOL 325.24 26.00 8,456.24 2,071.91 3,101.62 3,282.71 8,456.24
29 07476 BANNER DE 3.60X2.40 m UND 1.00 350.00 350.00 350.00 - - 350.00
29 07050 CONO DE SEGURIDAD UND 4.00 33.90 135.60 117.52 18.08 - 135.60
29 07056 GUANTES DE CUERO PAR 20.00 8.05 161.00 161.00 - - 161.00
29 07470 PLANCHA CORRUGADA SUPERTECHALIT PLN 9.60 24.00 230.40 230.40 - - 230.40
29 07465 SEÑALIZACION EVACUACION UND 25.00 15.90 397.50 132.50 132.50 132.50 397.50
29 07478 TEROKAL 1/8 GLN UND 1.05 6.00 6.30 6.30 - - 6.30
30 04939 ADITIVO IMPERMEABILIZANTE KG 19.73 31.50 621.50 - - 621.50 621.50
30 03988 EXTINTOR DE 4 KILOS UND 1.00 200.00 200.00 173.33 26.67 - 200.00
30 02895 WINCHA UND 0.28 15.00 4.20 4.20 - - 4.20
30 03568 YESO (BOLSA DE 28 Kg) BOL 3.26 15.00 48.90 48.90 - - 48.90
34 02519 GASOLINA 84 OCTANOS GLN 5.21 12.30 64.08 64.08 - - 64.08
37 07456 ARNES DE SEGURIDAD CON LINEA DE VIDA UND 2.00 135.00 270.00 270.00 - - 270.00
37 06946 CHALECO REFLECTIVO UND 10.00 30.30 303.00 303.00 - - 303.00
37 06999 ZAPATOS DE SEGURIDAD PAR 10.00 63.56 635.60 635.60 - - 635.60
38 00005 HORMIGON M3 4.77 45.00 214.65 214.65 - - 214.65
39 07087 AGUA PARA LA CONSTRUCCION M3 0.66 19.22 12.69 - - 12.69 12.69
39 07053 BLOQUEADOR SOLAR FPS (FRASCO) UND 2.00 129.90 259.80 225.16 34.64 - 259.80
Página 1 de 3
Calendario de Utilizacion de Recursos
: MEJORAMIENTO DEL CERCO PERIMETRICO DE LA I.E. Nro 40213 DE TUCTUMPAYA, DEL DISTRITO DE POCSI, PROVINCIA DE
Obra
AREQUIPA, DEPARTAMENTO DE AREQUIPA
Ubicacion : POCSI - AREQUIPA - AREQUIPA
Costo A : Dic - 2024 Cliente : MUNICIPALIDAD DISTRITAL DE POCSI
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 15 Días 15 Días 15 Días
45 Dias
39 07464 BOTIQUIN EQUIPADO UND 2.00 250.00 500.00 166.67 166.67 166.66 500.00
39 07453 CAMISA MANGA LARGA DENIM und 10.00 44.41 444.10 444.10 - - 444.10
39 07458 CASCO DE SEGURIDAD INCL. PORTAVIENTO UND 10.00 19.18 191.80 191.80 - - 191.80
39 07051 CINTA DE SEGURIDAD DE COLOR ROJO RLL 2.00 42.37 84.74 73.44 11.30 - 84.74
39 07463 CINTA PLASTICA DE SEÑAL DE PELIGRO RLL 20.00 35.00 700.00 233.33 233.33 233.34 700.00
39 07052 CINTA SEÑALIZADORA AMARILLA RLL 2.00 42.37 84.74 73.44 11.30 - 84.74
39 07077 ENERGIA ELECTRICA MES 1.50 200.00 300.00 100.00 100.00 100.00 300.00
39 07455 GUANTES DE JEBE PAR 10.00 8.62 86.20 86.20 - - 86.20
39 07454 LENTES DE SEGURIDAD OSCUROS UND 20.00 6.91 138.20 138.20 - - 138.20
39 07431 LIJA PARA METAL N°80 PGO 65.83 1.20 79.00 - - 79.00 79.00
39 07475 MALLA ARPILLERA DOBLE H=2.0 m. M 81.92 6.40 524.29 524.29 - - 524.29
39 07049 MALLA DE SEGURIDAD RLL 1.00 38.50 38.50 33.37 5.13 - 38.50
39 07462 MALLA FAENA rll 10.00 38.15 381.50 127.17 127.17 127.16 381.50
39 07459 MASCARILLA ANTIPOLVO UND 10.00 10.55 105.50 105.50 - - 105.50
39 07460 PANTALON DRILL UND 10.00 38.15 381.50 381.50 - - 381.50
39 07461 POLO MANGA LARGA UND 10.00 15.00 150.00 150.00 - - 150.00
39 07457 TAPONES DE OIDO UND 20.00 3.85 77.00 77.00 - - 77.00
39 07054 TRANQUERA Y DISPOSITIVOS DE SEGURIDAD UND 2.00 258.47 516.94 448.01 68.93 - 516.94
43 00025 LIJA PARA MADERA UND 6.48 1.40 9.07 - - 9.07 9.07
43 00020 MADERA TORNILLO P2 1,142.08 9.26 10,575.66 3,967.07 5,489.11 1,119.48 10,575.66
43 07479 PUNTAL DE EUCALIPTO ROLLIZO 4" x 5.0 M UND 2.00 16.00 32.00 32.00 - - 32.00
43 03911 ROLLIZO DE EUCALIPTO DE 3" X 3.00 M PZA 39.01 14.20 553.94 553.94 - - 553.94
44 07481 ESTACAS DE MADERA UND 1.85 2.00 3.70 3.70 - - 3.70
44 05123 TRIPLAY DE 4'x8'x 12 mm PLN 20.44 97.00 1,982.68 660.89 1,321.79 - 1,982.68
44 07471 TRIPLAY LUPUNA DE 4'x8'x 6 mm PLN 6.00 60.00 360.00 360.00 - - 360.00
49 07078 FLETE TERRESTRE GLB 1.00 1,000.00 1,000.00 1,000.00 - - 1,000.00
54 00731 BASE IMPRIMANTE KG 26.32 6.48 170.55 - - 170.55 170.55
54 00027 PINTURA ESMALTE GLN 5.66 65.00 367.90 147.77 8.67 211.46 367.90
54 00624 PINTURA IMPRIMANTE GLN 10.53 45.00 473.85 - - 473.85 473.85
54 07432 PINTURA LATEX VINIL ACRILICA GLN 10.52 57.00 599.64 - - 599.64 599.64
54 00064 SELLADOR BLANCO PARA MUROS GLN 3.25 65.34 212.36 - - 212.36 212.36
65 07426 REGLA DE METAL DE 2"x1"x2m UND 3.19 2.30 7.34 - - 7.34 7.34
EQUIPO
32 07482 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y EQUIP GLB 1.00 1,800.00 1,800.00 1,800.00 - - 1,800.00
37 00004 HERRAMIENTAS MANUALES %MO 2,199.55 423.96 452.70 1,322.89 2,199.55
48 07430 ANDAMIO DE METAL CON TABLAS HE 390.96 1.50 586.44 - - 586.44 586.44
48 03174 CAMION VOLQUETE 15 M3 HM 1.88 140.00 263.20 263.20 - - 263.20
48 01579 CIZALLA P/CORTE DE FIERRO HM 3.70 2.80 10.36 - 10.36 - 10.36
48 07024 ESTACION TOTAL, INCL TRIPODE, PRISMAS Y ACCESORIOS HM 100.29 26.18 2,625.59 2,625.59 - - 2,625.59
48 07422 MEZCLADORA DE CONCRETO 9 - 11 P3 (23 HP) HM 6.94 13.00 90.22 90.22 - - 90.22
49 02334 CAMIONETA PICK-UP 4x2 C. SIMPLE 1 TON MES 1.50 6,500.00 9,750.00 3,250.00 3,250.00 3,250.00 9,750.00
49 00385 CARGADOR S/LLANTAS 110 - 125 HP HM 1.88 200.00 376.00 376.00 - - 376.00
49 07125 COMPRESORA NEUMATICA 87 HP 250-330 PCM/MAQ. SERVIDA HM 2.79 94.40 263.38 263.38 - - 263.38
49 01649 MARTILLO NEUMATICO DE 29 Kg. HM 5.57 8.09 45.06 45.06 - - 45.06
Página 2 de 3
Calendario de Utilizacion de Recursos
: MEJORAMIENTO DEL CERCO PERIMETRICO DE LA I.E. Nro 40213 DE TUCTUMPAYA, DEL DISTRITO DE POCSI, PROVINCIA DE
Obra
AREQUIPA, DEPARTAMENTO DE AREQUIPA
Ubicacion : POCSI - AREQUIPA - AREQUIPA
Costo A : Dic - 2024 Cliente : MUNICIPALIDAD DISTRITAL DE POCSI
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 15 Días 15 Días 15 Días
45 Dias
49 06835 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 18.69 19.07 356.42 110.30 168.88 77.24 356.42
49 07353 NIVEL TOPOGRAFICO CON TRIPODE HM 20.29 10.00 202.90 202.90 - - 202.90
49 00032 VIBRADOR A GASOLINA 1 3/4", 4HP HM 12.91 6.31 81.46 - 55.89 25.57 81.46
49 00927 WINCHE - 2 BALDES, 3.6 HP HM 3.30 21.25 70.13 - 35.07 35.06 70.13
COSTO DIRECTO 131,087.06 42,786.83 37,108.19 51,192.04 131,087.06
GASTOS GENERALES 23,387.50 7,633.68 6,620.55 9,133.27 23,387.50
SUBTOTAL 154,474.56 50,420.51 43,728.74 60,325.31 154,474.56
GASTOS DE SUPERVISION 6.86567 % 9,000.00 2,937.60 2,547.72 3,514.68 9,000.00
GASTOS DE LIQUIDACION 2.66998 % 3,500.00 1,142.40 990.78 1,366.82 3,500.00
COSTOS OPERATIVOS 3.05141 % 4,000.00 1,305.60 1,132.32 1,562.08 4,000.00
PRESUPUESTO DE EJECUCION 170,974.56 55,806.11 48,399.56 66,768.89 170,974.56
TOTAL ACUMULADO 55,806.11 104,205.67 170,974.56
PORCENTAJE DE AVANCE 32.64% 28.31% 39.05%
PORCENTAJE ACUMULADO 32.64% 60.95% 100.00%
Página 3 de 3