KNOWLEDGE-BASED ENGINEERING IN CONSTRUCTION: THE
PREFABRICATED TIMBER HOUSING CASE
SUBMITTED:
REVISED:
PUBLISHED:
EDITOR:
November 2007
August 2008
September 2008
B-C Björk
Marcus Sandberg, PhD,
Division of Functional Product Development,
Department of Applied Physics and Mechanical Engineering, Luleå University of Technology,
marcus.sandberg@ltu.se
Helena Johnsson, PhD,
Division of Structural Engineering – Timber Structures,
Department of Civil, Mining and Environmental Engineering, Luleå University of Technology,
helena.johnsson@ltu.se
Tobias Larsson, Professor,
Division of Functional Product Development,
Department of Applied Physics and Mechanical Engineering, Luleå University of Technology,
tobias.c.larsson@ltu.se
SUMMARY: Swedish prefabricators of domestic buildings need to become more effective and efficient; the aim
of this paper is to investigate the usefulness of rule-based IT support tools for this purpose. The current sales
and design process at a timber volume element prefabricator is presented and evaluated regarding information
management and standardisation. It was found that information management during early design is often ad hoc
and person dependent; therefore searching for information that could lead to reuse of past solutions is rather
time demanding. There is a need for standardisation due to a mentality of designing one-of-a-kind buildings.
Knowledge-based engineering is seen as an enabler to enhance the current situation and an IT support
procedure is suggested. A demonstrator stair tool was tested, which lets the seller discuss needs with the
customer and then use the tool to assess cost and manufacturability. It is argued that the IT support procedure
can enable; automation of activities and availability of down stream knowledge in virtual format and a
connection between instances of the same geometry. If design flaws can be found early on, downstream waste
activities can be reduced. Standardisation could be realised through modularisation, which the implementation
of the IT support tool procedure could gain from.
KEYWORDS: Timber prefabrication, information management, knowledge-based engineering, early phase
design, manufacturing evaluation
1. INTRODUCTION
The Swedish house building industry needs to increase its effectiveness (doing the right things) and efficiency
(doing things right). Timber volume element (TVE) prefabricators have focused on how to minimize time spent
at the construction site and prefabricate as much as possible in the factory, but production is still handicraftbased and the organisation is more function-oriented than process-oriented (Höök 2005). Design is usually
project-based, where building systems are developed in a way that makes reuse of earlier solutions difficult.
Hence, construction researchers have begun to look at methods developed within the manufacturing industry
(Gann 1996). IT support is seen as an enabler of effectiveness and efficiency, even though the company
organisation has to be robust to gain positive results (Wheelwright and Clark 1992). Johnsson (2006) described
IT support used at TVE fabricators in Sweden, and found issues are among others, a low level of use of virtual
models. The use of enterprise-resource planning software to integrate company functions in a business system,
e.g. to enable better sales support, is common in the manufacturing industry, though it is not extensively used by
Swedish TVE prefabricators (Bergström and Stehn 2005). Knowledge-based engineering (KBE), where the
geometry engine of computer aided design (CAD) software is coupled to a rule base for automatic product
configuration and evaluation, has become more and more popular in recent decades (Chapman and Pinfold 1999;
Rosenfeld 1995). KBE has, however, not been extensively tested within the TVE prefabrication industry or even
ITcon Vol. 13 (2008), Sandberg et al, pg. 408
the construction industry. The aim of this paper is to investigate the usefulness of rule-based IT tools for
information management and standardisation by surveying the early design process at a TVE prefabricator.
2. LITERATURE REVIEW
2.1 Knowledge-based engineering
There is a trend that construction research is looking to adopt methods from the engineering industry (Gann
1996). One method originating from the manufacturing industry is knowledge-based engineering (KBE), which
according to Rosenfeld, (1995), was first coined at the launch of the CAD-software ICAD in 1984. KBE is a
method to enhance engineering design by creating design support tools based on a CAD-environment. By
capturing and formalising knowledge into rules, routine and time demanding work can be automated and
engineering knowledge can be made available in the CAD-environment. KBE enables parameterisation of
topologies; a simple example is a cylinder that can swiftly be transformed into a rectangular prism governed by
sets of rules. Engineering knowledge can be made available to evaluate the impact of design on, for example,
manufacturing operations, assembly and maintenance. By doing so, cost estimations and warning messages can
be generated as a result of design changes. Because design activities are automated, KBE represents a way of
capturing design processes. KBE software often have an object oriented structure, where geometry is created and
evaluated in terms of classes containing stored rules, and a geometry engine that manages and visualises the
geometry. Chapman and Pinfold (1999) claim that KBE can promote organisation of the information flow and
create rapid design solutions where more ideas and scenarios can be evaluated than without KBE. Examples of
KBE applications are within aerospace (Isaksson 2003) and automotive (Chapman and Pinfold 2001). Isaksson
(2003) claims that KBE can enable the use of information from later processes in early design, though the KBE
application may be quite intricate to organise within the virtual modelling environment, i.e. CAD, product-data
and product life-cycle management systems. Chapman and Pinfold (2001) argue that KBE can be used to
automate the pre-processing stages of structure analysis. KBE is often used to support engineering design
decisions, by enabling synthesis and analysis faster than done manually, rather than excelling the knowledge of
the engineering designers. KBE can however reduce the loss of experience during staff turnover as information
and knowledge can be stored in the product model.
2.2 Industrialised house-building
Lessing (2006) p.179, assumes industrialisation as a key issue for the house-building industry and further defines
industrialised house-building as:
“Industrialised house-building is a thoroughly developed building process with a well-suited organization for
efficient management, preparation and control of the included activities, flows, resources and results for which
highly developed components are used in order to create maximum customer value.”
For several decades, detached houses for one to two families have been built more or less industrially, where
volume elements of completely prefabricated rooms occur. Elements for multi-storey buildings have also been
prefabricated industrially, e.g. concrete walls. Fig. 1 shows a view of industrialised house-building that means
reducing on-site construction and increasing factory prefabrication.
2.3 IT support for industrialised house-building
Together with organizational changes computers can enable enhancements of the industrialised house-building
industry (Olofsson et al. 2004). In their investigation, Olofsson et al. state that the greatest potential for
integration of computer product models is for specialised companies, such as timber volume element (TVE)
prefabricators. To become a successful TVE prefabricator, customisation and flexibility issues have to be
overcome (Höök 2005) and addressed in the product models. Johnsson (2006) has documented information
technology currently used at some TVE prefabricators in Sweden. Examples of found issues are lack of
information management strategy, low level of use of virtual models for documentation, and lack of integration
between virtual construction tools and Enterprise Resource Planning (ERP) systems. According to Bergström
and Stehn (2005), there is a low use of ERP systems in the industrialised timber industry. This low use is argued
to depend on the complexity of the business process. Crowley (1998) states that computers cannot solve every
problem, rather the market is the driving force.
ITcon Vol. 13 (2008), Sandberg et al, pg. 409
Figure 1. One view of industrialised building, from (Höök and Stehn 2005) .
2.4 KBE in construction
Work for rule-based construction can be found. Gross (1996) describes a rule-based program for building
construction kits where the program controls the placement of house object according to a number of grids.
Gross argues that creativity is still possible although rules constrain the positioning as compared to kids playing
with Lego™ and having seemingly unlimited possibilities to create new innovative constructions. Ganeshan et
al. (1996) present an object-oriented CAD system that is integrated with a rule-base to allow for cost and time
evaluation of construction design alternatives. It is argued that using the tool designers can get feedback earlier
on than usually. Xuejun et al. (1990) presents a system that automatically plans house layouts. It is a
combinatorial problem that is handled with artificial intelligence and provides full automation i.e. lesser
interaction than the other work presented above. This may cause black-boxes if the automation is not understood.
As seen above there are work that focus on automated design in different ways but the issue of building a rulebase that supports the design process need to be explored further.
3. CASE STUDY
3.1 Research approach
A case study at a Swedish TVE prefabricating company, a small and medium sized enterprise (SME), was
performed. The company’s process from customer and supplier negotiations and early design to on-site
assembly, where used software was included, were mapped before this study and further refined during an open
focused group discussion. Company representatives from management, market, design and production functions
participated in the discussion, which was recorded and analysed as a qualitative interview. The reason for
discussing, e.g. preparation and production, is because it is extremely important to evaluate manufacturability
during design. After the mapping discussion, a group discussion on the topic of information management and
standardisation during design was conducted. The group discussion followed the future workshop model
(Kensing and Madsen 1991), which is intended for participative software development and has the phases
ITcon Vol. 13 (2008), Sandberg et al, pg. 410
critique, fantasy and realisation. The critique phase focuses on experienced issues and problems, the fantasy
phase on ideas if resources are unlimited and the realisation phase on realistic ideas. Four people from the
company holding the positions local manager, production manager, seller and design manager participated in the
mapping discussion and the workshop. Separate semi-structured interviews were conducted after the workshop
to gain further information on the topic from the workshop with two other building designers and two layout
architects, e.g. kitchen furnishing. Most interviews were recorded, while some informal interview were
summarised afterwards in text.
Stair and joist frames are used as limited examples, yet having sales, design and production connection, to show
the research ideas in a demonstrator. This demonstrator can be used to discuss overarching implications such as
when using IT support of the kind being exemplified. Conclusions can be drawn by discussing issues of
supporting whole house design.
3.2 Company introduction
The company develops and produces houses, e.g. multi-storey buildings and detached houses for dwellings and
schools, and sheds for construction workers using industrialised timber volume element prefabrication. Turnover
is approximately €40M with around 300 employees. The company has four production units in Sweden, one of
which this study was conducted at. Fig. 2 shows an overview of a timber volume prefabrication process.
Figure 2. Timber volume prefabrication.
3.3 Findings
3.3.1 Process
The company does not have an explicit process map of their workflow. Some engineering designers say they
work “from the beginning to the end”, indicating that they think the process is obvious and thus not necessary to
describe.
Fig. 3 shows the process phases on a time axis to give an understanding of the time proportions, while Fig. 4
presents the first phase, customer and supplier negotiations and early design. The dark shaded activities are of
interest for the suggested IT support tool. Each output document from an activity is connected to the software it
was created in. Involved in this phase are customers, sellers, designers and sometimes production and purchase
staff.
9 – 14 months
5 – 6 weeks
5 – 6 weeks
4 weeks
3 weeks
time
customer and supplier negotiations and early design
building design detailed design production
on-site
assembly
Figure 3. Process phases on a time axis.
Manufacturability evaluation during design, done during check off meetings, is mainly based on experience. No
tool or documented method for manufacturability evaluation was presented. Design flaws found and corrected
ITcon Vol. 13 (2008), Sandberg et al, pg. 411
during production are not always updated in the latest drawing because, according to the production manager,
they make one-of-a-kind houses and a certain house will probably not be produced again. “Once, we made the
same house again, but then the first house took fire and was destroyed.” So a one-of-a-kind mentality exists
among the employees even though the houses have similarities, e.g. geometrical.
Figure 4. The customer and supplier negotiations and early design phase.
3.3.2 Information management
The company lacks an overall information strategy and much information is only available on printouts or
through personal memory or in a non-accessible format that is only understood by the one who wrote it, i.e. the
rationale or context is missing. Some software is claimed to be time demanding to use because of a lack of
integration with other software. One example is a custom made program for economic calculations, where
manual work becomes time demanding due to the lack of integration with an in-house component database. The
level of integration between the CAD-software (AutoCad ADT™) and the ERP system (VISMA™) is also low.
CAD-models are not parametric and design work has characteristics of time demanding routine work, e.g.
sometimes the same feature is drawn multiple times in the same model without connection to the other features.
This implies that each part has to be redesigned separately at a design change. One designer has stated the
difficulty in reusing CAD-objects, as the outer dimensions always change from project to project. However, inhouse architects reuse kitchen objects during kitchen design. Knowledge and information transfer usually takes
place by working together in the same room. It is possible to find printouts from earlier projects and finding
documents if a project is remembered, e.g. knowing the project number and the house details considered
interesting for the new project. No database exists with the possibility to automatically search for documents of
earlier project. Salespersons quite often have to search for information, usually in document folders containing
printouts from earlier projects. Therefore, finding information that can be reused becomes time demanding and
there is a risk for efforts being made on solving an already resolved design task.
ITcon Vol. 13 (2008), Sandberg et al, pg. 412
3.3.3 Standardisation
Standardisation during design is not evident. Finding a standard for the building system is difficult because the
interviewees claim that every order is a one-of-a-kind and will not be used again. When discussing product
platforms, one interviewee regarding every joist frame as one platform. It is, however, expressed that having a
low number of building elements that can be used by the customer to define the framework design for the house
would be beneficial. A team, with staff from sales, design and production, has however been formed recently to
work with standardisation. The objective for this team is to focus on standardising solutions for corners and
walls and other parts that not are supposed to be affected be the opinion of the customer. Standardised parts are
then stored in a database which everyone has access to. There also exist certain platform houses, but there are
different opinions of what a platform house is. Some see platform houses as houses where change what-so-ever
is prohibited while others accept variation to some degree.
4. SUGGESTION OF IT SUPPORT TOOL PROCEDURE
4.1 Chosen scenario
Stairs are a crucial component in buildings and a possible module to standardise. Therefore, stairs were chosen
as an example to demonstrate a sell and design support tool (SDST) in a virtual construction environment. The
company uses a stair design program, but the program does not enable automatic updating of geometry affected
by new stair configurations. The following current process was detailed during the workshop and chosen to be
supported by the SDST:
1. The customer creates an idea together with an external architect, and based on this idea the seller and
the customer have agreed upon a house layout.
2. The seller suggests a U-stair, which is the standard stair that can save space, but the customer wants
to know what the house will cost if a straight or a turning stair is chosen.
3. The seller goes back to the company and investigates how the house layout and choice of stairs affect
the cost by consulting earlier project documents and company staff, if possible, and calculates the
cost for each stair choice.
4. When the cost is calculated the customer and seller meet again and the customer can decide which
stair to choose.
4.2 IT support tool functionality
The idea is to automate and support parts of activities 2 and 3; see section 4.1. Fig. 5 shows an outline of a GUI
for the demonstrator IT support tool. During activity 2, the type of stair can be varied (U, round and straight) and
how the joist frame of the house is affected can be assessed. With the IT support it is possible to conduct activity
2 with the customer, since the assessment is partly automated. Stair placement in the layout plan can be varied to
change the entrance to the upper floor. It is also possible to change the joist configuration in terms of extra
stiffening beams, and automate this activity by implementing equations for mechanics of the materials. If the
placement of the stair or the joist configuration is not feasible, i.e. not possible in terms of stiffness or to
manufacture, a warning message is generated and suggestions for changes are given. Views can be changed to
show the layout more about aesthetics than engineering contents. This is exemplified in Fig. 5 top-right, as the
joist frame is hidden and the floor layout is presented. The layout can be mirrored to facilitate design of terrace
houses, where flats are mirrored to enable, for example, the sharing of pipes and ventilation facilities. The design
activity described here can be found in Fig. 4 Evaluation of dimensions, choice of installation, though the choice
of installation is beyond the scope here.
The production cost is continuously calculated at every change and totalled in the interface. A cost report shows
the cost components for material and work. The material cost is based on the bill of materials generated from the
software where the configurator is implemented; see section 4.5. The work cost is calculated based on rules for
standard production activities, e.g. the average time of producing a joist frame of this dimension. If the joist
frame is configured for stiffness, then time and cost are changed for the fastening of more beams. This cost
estimation activity can be found in Fig.4 Seller makes an overarching project calculation.
ITcon Vol. 13 (2008), Sandberg et al, pg. 413
4.3 Knowledge acquisition
There are approaches to acquire knowledge as described by the MOKA consortium, where specially designed
ICARE forms are used to obtain control of how knowledge is acquired and interconnected (Stokes 2001). The
knowledge already acquired in this study was found by using the approach described in section 3.1. The
collected knowledge can be divided into different categories, e.g. heuristics (rule-of-thumb), empirical
knowledge, tacit knowledge, common sense, logic and geometrical knowledge.
Figure 5. Outline of the stair and joist frame configurator.
4.4 Formalisation
The acquired knowledge can be formalised into a rule base that guides the automation. This means that
knowledge that can be explicitly expressed as production rules, i.e. if condition then action, is most suitable for
formalisation. Categories containing explicit knowledge can be, for example, geometrical, rule-of-thumb and
common sense. If an object-oriented approach is used, a class division could be made where classes for synthesis
and analysis are separated, since synthesis knowledge, such as design intent, tends to change more often than
analysis knowledge, such as manufacturability evaluation. However, it is occasionally practical to integrate
synthesis and analysis knowledge into the same class if a continuous evaluation with many detailed parameters is
strived for. If an evaluation is done on a less detailed level, a class separation is more suitable. A combination
could also be useful. An example of synthesis rules:
if stair-type = U-stair then stair-opening-overlap = 20
else stair-opening-overlap = 10;
trimmed-joist-length = stair-width + stair-opening-overlap;
ITcon Vol. 13 (2008), Sandberg et al, pg. 414
Example of analysis rules:
if joist-frame-length > joist-frame-max-length
then print “It is not possible to produce lengths longer than ” +
joist-frame-max-length “ as the production line is not wide enough.”
if stair-type = round-stair
then production-time-stair-opening = production-time-stair-opening-standard +
production-time-stair-opening-round-stair-additional
else production-time-stair-opening = production-time-stair-opening-standard
A class hierarchy for the SDST look as shown in Fig. 6. The class House volume instantiates the sub-classes
Joist frame, Stair and Cost and theses classes in turn instantiate sub-classes.
House volume
Joist frame
Bottom floor
First floor
Stair
Stair hole
Cost
Work
Material
Figure 6. Class hierarchy for the SDST.
Explanation of the rules needs to be done in the code syntax to enable transparent updating.
4.5 Implementation
Implementation is done in a virtual construction software package that has possibilities for parameterisation and
object oriented programming. KBE (Rosenfeld 1995) enables parameterisation of topologies along with the
implementation of engineering rules for evaluation of manufacturability during design, for instance. If possible,
AutoCad ADT™ should be used as software to start the implementation at the company of the SDST, making
the process of starting to test the SDST easier rather than climbing the threshold implied of new software. The
initial demonstrator outlined in Fig. 5 has been done in Microsoft PowerPoint™ to show the idea of automating
engineering design and evaluation.
5. CHALLENGES AND OPPORTUNITIES
5.1 Process issues
A new process map, see Fig. 4, emerged from the study that differed from the original map. The process map
would perhaps change again if a new group was inquired. A clear process description that the company decides
to follow is needed to work effective and efficiently.
Because an IT support tool like the suggested SDST automates downstream activities, e.g. Evaluation of
dimensions, choice of installation and Seller makes an overarching project calculation, it is possible to conduct
these activities upstream during, for example Offer is given if the customer has not already decided the details
activity, Fig. 4. This implies that the process is changed, as some activities can be conducted earlier. This can
possibly save time as the process is automated. It however sets demands on the downstream activities to start
earlier. When automated the activity is standardised and the variation of the activity output will probably be less
compared to the manual activity. Therefore the people of the downstream activities will have knowledge of what
input their activity will have. This can be a quality securer as standardisation decreases variation. Upstream the
automation implies that more information is made available and more what-if scenarios can be conducted and
this can probably help in making decisions.
5.2 Information management
Managing the information flow in a company is a vast task. This paper concentrates on how information can be
readily available to sellers and designers, how routine time demanding work can be reduced by automation, and
how such a system for design automation is chosen and maintained to enable successful communication. The
ITcon Vol. 13 (2008), Sandberg et al, pg. 415
creation of an information strategy would facilitate the work, e.g. use of virtual models and information transfer
could be consequent.
5.2.1 Accessible information
It was found from the study that experience is seldom documented, but rather sustained in the memories of
people and transferred to co-workers in close proximity. It is likely that the transferred knowledge is mostly
explicit i.e. directly expressible instead of implicit knowledge that require more reflection to explain.
Information of earlier houses can be found on printouts, but needs to also be accessible digitally. All revisions
need to be stored in a digital model to avoid repeating the errors in the future. There seems to be a need for a
database such as the product data management (PDM) systems found in the engineering industry to make
information accessible for everyone (Johnsson 2006). Some information can only be retrieved through older
software, which only a few people can handle. If the information from the older software can be obtained from a
system that more people can handle, time and expense could be saved. The proposed IT support tool in section 4
could store product information about geometry configuration and engineering knowledge, e.g.
manufacturability evaluation. However, the objective of the suggested IT support procedure is to help the staff
make better design decisions, by delivering information in a timely manner, rather than excel the amount of
knowledge that is held by the staff. This information or knowledge may not be available as the staff is busy or as
it is not evident who to contact to get the information.
5.2.2 Automation
Some design work is time demanding due to unstructured work methods and an absence of functionality in the
virtual construction environment. Parameterisation is a common way of automating design activities, and an
extension of parameterisation is found in KBE. Through KBE, resources can be used for value-adding activities
instead of time demanding routine work. Automation may also create “black-boxes”, where the user does not
understand what happens during the automation and therefore not trust the application. Including explanation
texts in the user interface and limiting the amount of automation to mostly routine and time demanding activities
in a balance of manual and automatic work might avoid the understanding problem. Simply automating more
early design activities will not solve the issue of updating the virtual models when late design changes are done
due to problems found during production. Since there are problems during production due to design there is
currently a lack of production knowledge among the designers. A KBE tool may exceed individual designers in
knowledge about production but not in the overarching knowledge of the house. However, production problems
can be reduced if rules controlling the manufacturability of the geometry are implemented.
The issue of the same geometry objects not being connected might be overcome by using regular CAD tools,
with assembly instance functions. Creating and following the information strategy can resolve such problems.
The issue of not being able to reuse geometry due to all volumes having different outer dimensions, as one of the
interviewed designers noted, could be overcome through parameterisation. KBE could also ensure quality for
parts of the process being automated, as these parts will be constantly performed the same way.
5.2.3 Choice of software
The virtual construction environment is always under discussion, often regarding the drawbacks. The choice of
software is not an easy matter, since there are always many needs to satisfy. The problem is often that all needs
are not known when a decision is taken, but rather appear when the software is in use. Sometimes, people will
ask for newer programs believing that the problems with the older software will be solved, not considering the
risk that newer programs introduce new problems. Therefore, it is important to base the choice of software on
needs and not technology. In this study, the issue of purchasing new and functional software versus keeping the
older software that people are used to was discussed. To enable automation, AutoCad ADT™ could be
exchanged for AutoCad Revit™. An alternative to using AutoCad ADT™ is to connect external software
through the API (Application Programming Interface) and thus control the geometry definition process. The
neutral format IFC (Industry Foundation Classes) could be used to represent the building system and gain even
more flexibility in choice of software. KBE software, such as UGS NX™1 (http://
www.plm.automation.siemens.com/en_us/), is mostly found in the manufacturing industry. KBE may be less
expensive for smaller companies instead of purchasing an expensive ERP package, and methods exist for KBE
in SMEs (Lovett et al. 2000). However, there is also a question of integrating KBE systems with other product
data management systems to avoid isolated KBE applications (Catic and Malmqvist 2007). Also, software for
ITcon Vol. 13 (2008), Sandberg et al, pg. 416
design of stairs, e.g. Staircon™ (http://www.staircon.com), could be used as an evaluator of stairs that are
implemented in the SDST.
To provide a useful environment for product configuration, as through the SDST, there is a need for trouble free
integration with other systems for geometric data and costing. As the configurator should contain rules that
ensure that the building system standard is followed there is a possibility to create new articles to store in an
article data base. Ultimately there would be no redundant information e.g. avoid that same information is stored
both in the ERP-system as in the CAD-system. One idea is to use a database (e.g. PDM) with house articles
where all other systems (CAD, VISMA, Excel etc) could extract and add information from and to the database.
The connection between the systems could be automatic, semi-automatic or manual. For example, a bill of
materials, from the CAD-system could automatically be sent to the cost-system (through the database) and act as
a base for cost activities of the purchase department.
The PowerPoint demonstrator is currently being transferred into AutoCad ADT and the automation capabilities
described in section 4 is being implemented by means of Visual Basic™.
5.2.4 Maintaining the system
Creating a successful software system specially customised for the company can be challenging, though even
more challenging is keeping the system up to date with the latest knowledge and information. One way is to
teach the user to program the system live, when working and new information is available. The idea of Wikis,
where everyone at the company can change information on documents, is also argued to be an enabler for
keeping information updated during engineering activities (Weerasinghe and Salustri 2007). A regular updating
policy, e.g. once a month, could be part of the information strategy. Another approach is to create a new position,
sometimes called knowledge engineer or a project information officer, as suggested by Froese (2004).
5.2.5 Whole house
The proposed IT procedure is exemplified with a stair and joist frame application which is a limited application.
New challenges will be faced when extending the discussion to whole house standardisation. One challenge is to
create an information structure that is transparent and maintainable as the information content is larger. There are
also more people within and outside the company (e.g. architects, lead and end customers) involved in the
information handling process which increase the demand of the information back bone system – the system that
all digital information handling is based on. In the case of the case study company there is a need to decide upon
what information back bone system to use, e.g. ERP or PDM, if aiming towards whole house models. Currently
when dealing with the limit case of stairs and joist frames it is possible to have a working automation without
focusing too much on the back bone system. More people also increase the demand of following the information
strategy. Using a system engineering perspective may be useful where the whole house is the total system that
contains subsystems in a hierarchical order.
5.3 Standardisation
A standardisation effort could provide a number of benefits. The seller could sell the “right” product from the
start, i.e. a product that does not need to be changed due to problems found during e.g. production or purchase. It
would be fewer question marks during design, it would probably be easier to predict purchase actions and
develop collaboration with suppliers. Standardised CAD-files could be used to automatically generate lists of
material to be purchased. Production could work more on routine and spend less time on reviewing drawings.
Two ways to conduct standardisation is by modularisation and product platforms.
5.3.1 Modularisation
To create an IT support tool that automatically generates geometry, it is useful to conduct a modularisation to
facilitate rules coding, since class division and class coding can be guided by the module network. Modular
function deployment (MFD) is an approach to divide the product into modules with interfaces that allow the
modules to change and still fit together (Erixon et al. 1994). MFD is suitable for products with large series, and
thus motivates the cost for development of interfaces that connect the modules to each other. The interviewees
perceived their products as one-of-a-kind objects, though they did not seem to share the same view of similarity
between the products as the author, and conducting a modularisation effort may help the company staff to see the
similarities. Because stairs are manufactured by a subcontractor, considering inter firm modularity might also be
ITcon Vol. 13 (2008), Sandberg et al, pg. 417
important (Staudenmayer et al. 2005). Bertelsen (2005) argues that modularisation already exists somewhat in
construction and that there is a balance between efficiency and monotony if striving for further modularisation.
5.3.2 Product platforms
Another approach to standardisation is that of creating product platforms, as the company in the study also have
looked at. Modularisation is one key to promote the creation of product platforms. According to Simpson (2004),
there is a proactive and a reactive approach to the creation of platforms. The reactive approach seems to be for
the company in the study, since its need for standardisation was identified. Most work for platforms is done for
large companies but there are also tools suitable for SMEs, such as variant mode and effect analysis (Schuh and
Tanner 1998). When a platform has been developed it is often more straightforward to create a rule base for
automation, as the platform is defined and “only” needs to be programmed for automation.
5.4 Organisational issues
New work processes need to be defined and followed. New software needs to be learnt for proper use, e.g.
ensuring a continuous updating of information. New roles may be needed, such as a project information officer.
In other words, there is a need for change in company culture to trust and be able to use a support tool. Having a
positive attitude to change is one enabler for success. A lack of knowledge often creates scepticism. Therefore, it
is important to have a learning organisation approach (Love et al. 2000).
Value creation is one of the most important issues for companies because it is connected to the satisfaction of
their customers and the success of the companies. Company core knowledge or intellectual property therefore
comes into focus, which companies like to hold secret. Sometimes employees also experience an automation
effort as leading to unemployment instead of minimising time demanding work. The issue of collaborating,
instead of working function-oriented, could be helped by letting staff from different company divisions
collaborate during regular updating of the IT support.
6. CONCLUSION
This paper presents a study at a Swedish timber volume element prefabricator, where process, information
management and standardisation of the building system were evaluated. An IT support tool procedure has been
suggested and discussed to overcome the found issues. It is argued that the IT support tool procedure can enable:
x
Automation of activities and availability of knowledge of later activities (e.g. production and
stiffness evaluation) during early activities (e.g. seller and customer negotiations), thereby
changing the company process. Automation may free up time for value creating activities and
reduce manufacturability problems, since design flaws can be found early on. Automation may
also create an overview of parts of the company process, as activities are modelled and described
for the user.
x
Availability of the modelled product knowledge in virtual format instead of searching in document
folders. This may decrease the time for information search. Information is, however, limited to the
model.
x
A connection between instances of the same geometry objects is created, such as parameterisation
and a class structure for the geometry. This may free up time to attempt more solutions or conduct
more evaluations.
The software needed for the implementation of the IT support procedure should have parametric possibilities and
preferable object oriented capabilities. The IT support tool needs to be updated on a regular basis to have the
latest information available. This updating can be part of an IT strategy. Standardisation is needed because the
amount of knowledge has to be limited and well described to create the tool. To draw more exact conclusions, a
complete implementation and evaluation of the suggested IT support procedure is needed. An implementation is
currently being conducted.
7. ACKNOWLEDGEMENT
Funding has been provided by VINNOVA through the Centre for Lean Wood Engineering and is greatly
acknowledged.
ITcon Vol. 13 (2008), Sandberg et al, pg. 418
8. REFERENCES
Bergström M., and Stehn L. (2005). Benefits and disadvantages of ERP in industrialised timber frame housing in
Sweden. Construction Management and Economics, Vol. 23, No. 8, 831-838.
Bertelsen S. (2005). Modularization - a third approach to making construction lean? IGLC-13, Sydney,
Australia, 81-88.
Catic A., and Malmqvist J. (2007). Towards integration of KBE and PLM. International conference on
engineering design, Paris, France,
Chapman C. B., and Pinfold M. (1999). Design engineering - a need to rethink the solution using knowledge
based engineering. Knowledge-Based Systems, Vol. 12, No. 257-267.
Chapman C. B., and Pinfold M. (2001). The application of a knowledge based engineering approach to the rapid
design and analysis of an automotive structure. Advances in Engineering Software, Vol. 32, No. 12,
903-912.
Crowley A. (1998). Construction as a manufacturing process: Lessons from the automotive industry. Computers
& Structures, Vol. 67, No. 5, 389.
Erixon G., Erlandson A., von Yxkull A., and Mo Östergren B. (1994). Modulindela produkten (in Swedish),
Kristianstads Boktryckeri AB, Kristianstad.
Froese T. M. (2004). Help wanted: project information officer. ECPPM 2004 - eWork and eBusiness in
Architecture, Engineering and Construction, A. Dikbas and Scherer, R., eds., Istanbul, Turkey, 19-24.
Ganeshan R., Stumpf A., Chin S., Liu L., and Harrison B. (1996). Integrating Object-Oriented CAD and RuleBased Technologies for Construction Planning. US Army Corps of Engineerg - Construction
Engineering Research Laboratories.
Gann D. G. (1996). Construction as a manufacturing process? Similarities and differences between industrialized
housing and car production in Japan. Construction Management & Economics, Vol. 14, No. 5, 437-450.
Gross M. D. (1996). Why can't CAD be more like Lego? CKB, a program for building construction kits.
Automation in construction, Vol. 5, No. 285-300.
http:// www.plm.automation.siemens.com/en_us/), Last accessed: April 25 2008
http://www.staircon.com, Last accessed: April 25 2008
Höök M. (2005). Timber volume element prefabrication - Production and market aspects. Licentiate thesis,
Luleå University of Technology
Höök M., and Stehn L. (2005). Connecting lean construction to prefabrication complexity in Swedish volume
element housing. Proceedings of the 13th IGLC conference, Sydney, Australia,
Isaksson O. (2003). A generative modeling approach to engineering design. International Conference on
Engineering Design, Stockholm, Sweden,
Johnsson H. (2006). IT-stöd för industriellt byggande i trä (in Swedish). Luleå University of Technology, Luleå.
Kensing F., and Madsen K. H. (1991). Generating Visions: Future Workshops and Metaphorical Design. Design
at work: Cooperative design of computer systems, Greenbaum, J. and Kyng, M., eds., Lawrence
Earlbaum, Hillsdale.
Lessing J. (2006). Industrialised House-Building: Concept and Processes. Licentiate thesis, Lund Institute of
Technology
Love P. E. D., Li H., Irani Z., and Faniran O. (2000). Total quality management and the learning organization: a
dialogue for change in construction. Construction Management and Economics, Vol. 18, No. 321-331.
Lovett P. J., Ingram A., and Bancroft C. N. (2000). Knowledge-based engineering for SMEs - a methodology.
Journal of Material Processing Technology, Vol. 107, No. 384-389.
Olofsson T., Cassel E., Stehn L., Ruuth S., Edgar J.-O., and Lindbäck S. (2004). PROFLEX - Produktmodeller i
ett flexibelt industriellt byggande (in Swedish). 2004:06, Luleå University of Technology, Luleå.
ITcon Vol. 13 (2008), Sandberg et al, pg. 419
Rosenfeld L. W. (1995). Solid Modeling and Knowledge-Based Engineering. Handbook of Solid Modeling,
LaCourse, D. E., ed., McGraw-Hill, Inc., New York.
Schuh G., and Tanner H. R. (1998). Mastering variant variety using the variant mode and effects analysis. Proc.
ASME Design Engineering Technology Conf., Paper No. DETC980DFM-5736,
Simpson T. W. (2004). Product platform design and customization: Status and promise. Artificial Intelligence for
Engineering Design, Analysis and Manufacturing, Vol. 18, No. 1, 3-20.
Staudenmayer N., Tripsas M., and Tucci C. L. (2005). Interfirm Modularity and Its Implications for Product
Development. Journal of Product Innovation Management, Vol. 22, No. 4, 303-321.
Stokes M. (2001). "Managing Engineering Knowledge - MOKA: Methodology for Knowledge Based
Engineering", ASME Press.
Weerasinghe J. S., and Salustri F. A. (2007). Use of wikis as an engineering collaborative tool. Interational
Conference on Engineering Design, Paris, France,
Wheelwright S. C., and Clark K. B. (1992). Revolutionizing Product Development: Quantum Leaps in Speed,
Efficiency and Quality, The Free Press, New York.
Xuejun C., and Yunhe P. (1990). Automated design of house-floor layout with distributed planning. Computer
Aided Design, Vol. 22, No. 4, 213-22.
ITcon Vol. 13 (2008), Sandberg et al, pg. 420