The Beauharnois Bridge, Montreal, Canada
Alejandro Acerete, Civil Eng. MSc, Acciona Infraestructuras—Civil-Works and Structures, Madrid, Spain; Javier Ayala,
Director, Acciona—Engineering Area-Civil-Works and Structures, Madrid, Spain; Gabriel Menendez Pidal, Civil Eng. MSc,
Dragados, Madrid, Spain and Luis Peset, Civil Eng. MSc, Dragados, Madrid, Spain.
Contact: aacerete@acciona.es
DOI: 10.2749/101686614X13854694314685
Abstract
The bridge over the Beauharnois Canal
(BHC) is the main structure of the
Nouvelle Autoroute 30 project, with a
total length of 2551 m. It crosses the
BHC and the Saint Laurent Seaway
(SLS).
This paper describes the development
of the design and construction process
of the Beauharnois Bridge carried out
by a leading construction company in
Montreal. It describes the construction
procedures carried out to achieve the
works in a schedule severely limited
by the technical clauses of the contract
and winter conditions.
This paper emphasizes the different
prefabrication systems employed in
the construction of the bridge and the
incremental launching technique used
to erect the steel box-girders of the east
part over the BHC and the SLS.
The bridge superstructure is divided
into two parts: the east part, formed by
a closed composite structure with a steel
box-girder spanning over 82 m, and the
west part, designed with a concrete deck
composed of five concrete prefabricated
beams spanning a typical length of 45 m.
The east part, with a length of 1456 m,
was designed with no expansion joints.
This side of the deck includes the main
span of 150 m and was entirely assembled at the east abutment and erected
in place using the incremental launching technique.
Keywords: Incremental launching; precast piers; hybrid joints; deck without
joints.
Structure Description
The bridge, with a total length of
2551 m, crosses from east to west of
the Beauharnois Canal (BHC) and
the Saint Laurent Seaway (SLS) canal
with a twin deck.
The SLS is an international navigational infrastructure connecting
the Great Lakes of North America
with the Atlantic Ocean through the
402 Technical Report
Québec region in Canada. This strategic point governs the conditions under
which the Beauharnois Bridge has
been designed and built (Fig. 1).
The bridge length is divided into three
parts:
• West approach, over land, from the
west abutment (axis 1) to the transition pier 26
• Area of the main span over the SLS
between piers 26 and 31
• East approach, over the BHC
waters, between pier 31 and the east
abutment (axis 44).
The design of the bridge, carried out
by a multinational professional services firm in London, was divided into
two parts: the east part that includes
the area of the 150 m main span and
the east approach with typical spans of
82 m. The 14 m wide twin composite
decks are formed by a steel box-girder.
The west approach has 1094 m divided
into 25 typical spans of approximately
44,5 m. It is composed of continuous
decks with five precast concrete beams.
Foundations
Design
The pier’s foundation design on the
water side presented an important
challenge. The rock was located 14 m
under water level and it was composed
of quartzitic sandstone with siliceous
cement of high compressive strength
(average values of 150–200 MPa up to
350 MPa); besides, it was very abrasive.
(Fig. 2).
The design took advantage of the highstrength rock, transmitting important
forces through the rock socket; and to
confirm these assumptions, two load
tests using a high-capacity sacrificial
loading device were carried out.
over the water when compared with
other underwater solutions using
cofferdams.
– The environment permit required
minimum surface distortion at the
canal bottom.
– The hydroelectric power plant
located downstream required minimum head losses as a result of the
bridge construction, so minimum
interferance in the canal waters flow
was sought.
Each pile cap consisted of two groups of
three piles placed in an equilateral triangle and interconnected by a tie beam.
Foundations of the west approach were
designed with 96 steel-driven piles and
a double T-shaped pile cap with a configuration similar to that described.
Construction
Piles were cast with steel casing embedded on the rock. The piles were drilled
from barges and their position was
controlled and located using the GPS
system. The construction rate achieved
was one pile/week and machine.
The pile caps were cast in two phases
in order to minimize the formwork
structure. The soffit was supported on
piles with sand jacks to ease formwork
removal. The first pour of the pile
caps were 1 m high. Once the strength
was reached, the soffit formwork was
removed using the sand jacks. The
formwork was moved to the next pier
so that the second phase of casting
could take place.
Besides reducing the concrete weight
supported by the formwork, this system also allowed work on two piers
in parallel. Also, the reduced concrete
volume had, as a consequence, less
hydration heat produced in the concrete mass.
The design was based on piles and
pile caps over the water for different
reasons:
Piers
– Because piles were drilled from a
barge, they were easier to construct
Typical void piers of the bridge are
3,6 m in diameter and 400 mm in
Typical piers
Structural Engineering International 3/2014
67700
44
thickness and their height varies along
the longitudinal profile of the bridge
between 4 and 38 m.
40
81900
41
81900
42
81900
43
The design of the piers was originally
based on in situ construction, but a
precast alternative was developed in
2009 as a means to speed up construction and improve quality in view of the
site conditions.
39
81900
Each precast column had two parts:
5m
81900
38
81900
81900
35
81900
34
1456700
36
81900
t-109
t par
Wes
37
1050500
81900
• The base, with an in situ part divided
into two lifts: the first lift of the pier
is where plastic hinges could be
formed during an earthquake; the
second is where the anchorages of
the post-tension system are located.
• The precast segments, designed
with post-tension tendons and using
the match cast technique, to attach
together all elements of the top part.
64500
31
81900
32
81900
33
Once the in situ part was built, the
assembling of all the precast elements
reached a production rate of one pier
per day and crane crew.
The transition between the two different decks is done at pier 26 with a
singular pier head that combines the
support for both decks at two different
levels (Fig. 3).
63700
28
406200
150000
29
63000
Main span
30
Transition Pier 26
m
457
art-1
p
East
33250
37850
1
Structural Engineering International 3/2014
Fig. 1: Beauharnois Bridge general view
2498
2
33250
45000
45000
45000 44200 44500 44500 44500 44500 44500 44500 44500 44200 44200 44500 44500 44500 44500 44500 44500 44500 44500 44500 44500 44500
65000
27
26
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
4 4A 5
Main Piers
10696
3
13180
1094700
This pier has been designed as a
mobile point on the west approach
and as a fixed point on the east part.
This double function is achieved with
a seismic retainer that links the boxgirder with the pier head. The volume
of this pier head made it impossible to
prefabricate, but the rest of the column
shaft was prefabricated.
The main piers are the fixed points of
the east part; as there are no expansion
joints, they attract most of the seismic
forces of the 1457 m deck. The combination of ductility and resistance required
for these piers has been balanced by providing a strong connection with the deck
and the foundation and slender double
columns (diapason columns) (Fig. 4).
The connection between the main
piers and the deck combines different elements: (a) a massive pier head
20 m long and 8,5 m wide, (b) a concrete block cast inside the box-girder
to connect the pier head with the deck,
and (c) steel haunches bolted to the
bottom of the box-girder.
Several construction stages were
needed to cast the pier head. The last
Technical Report
403
23 220
2830 1500
Ø2400
Bridge
Pont
2500 1500
3000
1500 2500
4000
B
Point D’implantation
SOP
Fall Fall
pente pente
4000
Voir note 3
See note 3
ÉL. A
+ 45 mm
3000
4500
ÉL. A
PLAN
Pile
Pier
Pile
Pier
B
Fig. 2: Construction of foundations on the water (Units: mm)
ch
West approa
East part
Main span
Fig. 3: Transition Pier 26
two stages of the connection with
the deck were (a) the erection of the
haunches (a reinforcement of the steel
section with a nose shape) and connection to the pier head and (b) the cast
of the concrete block inside the boxgirder. These operations were carried
404 Technical Report
out once the incremental launching
was finished.
West Deck
The west deck was designed with precast concrete beams using a standard
bulb-T-shaped girder section with
2000 mm depth beams.
The total length of 1094 m has 25 typical spans of 44,5 m and it is divided
into three segments by the expansion
joints located at axis 1, 8, 17, and 26.
Structural Engineering International 3/2014
28
259,0 m3
20,2 m3
1,90 nom.
16 m3
0,7 m
89,7 m3
4,5 m3
2,00 m
169,0 m3
2,00 m
107,4 m3
Top of column
Fig. 4: Main Piers
13 770
3275
7220
3275
5060
Demi-dalle
préfabriquée
precast semi-slab
1000
(typ.)
(+0,000)
(–0,075)
250 dalle
250 slab
Conduit
ducts
CJP
2%
(–0,628)
2%
Contreventment horizontal
(W310×97 profilé)
Horizontal bracing
(W310×97 section)
CJP
Trou pour its
conduit hole
for its duct
3675
Profondeur de poutre
girder depth
(–0,686)
2160
Passerelle
D’accés
access
walkway
R200
CJP
CJP
190
CJP
5400
(–4,303)
190
Fig. 5: East deck construction (Units: mm)
The deck is 14,2 m wide and is continuous over the piers.
East Deck
The east deck is 13,7 m wide and has
a composite section with a steel boxgirder 8,2 m wide and 3,7 m height.
The entire length of 1457 m is divided
into 18 spans with typical spans of
82 m and the main span of 150 m; it
is continuous, with no intermediate
expansion joints. The box-girder was
assembled at the east abutment and
erected with the launching technique
described subsequently (Fig. 5).
The concrete deck was designed with
full-width precast prestressed slabs. All
the elements required for the drainage
support were also included in the precast slab.
The purpose of the design was to
maximize the deck elements included
in the precast section of the deck. The
objective was to improve productivity
on-site. With this system, once the slabs
were installed, the rest of the deck was
cast at the rate of 82 m every 3 days
and concreting crew.
• The 150 m main span over the SLS
channel was erected without affecting ship traffic, using the launching
technique.
• Hybrid steel mechanical joints
were used, combining welding and
bolting.
Construction Singularities
The construction of the Beauharnois
Bridge was a challenge from different
points of view. The various constraints
introduced the following singularities
in the bridge design and construction:
• Partial precast piers with the anchorage zone in the in situ base of the
column instead of in the foundation
(Fig. 6).
• The east part, constructed with
no expansion joints and using the
launching procedure. The assembly
and launch operations were singular
because of the variable curvature of
the longitudinal elevation profile.
Structural Engineering International 3/2014
Partial Precast Piers
The typical piers were prefabricated
with two peculiarities:
1. The post-tension system that joins
all the precast elements has the
anchor block at the base of the pier.
Usually the anchors are located
at the foundation, where there is
enough concrete volume to be able
to spread the concentrated loads of
the post-tension system. This design
was chosen so that the precast solution could be introduced without
affecting the foundation’s design
(prepared for in situ piers).
Technical Report
405
H4
Top segment
H1
4000 length
precast segment
Second last
top segment
H5
C.J.
H2
in-stiu
bottom lift
C.J.
1800
1800
ÉL. B
Fig. 6: Partial precast piers critical areas
Fig. 7: Launch over the Beauharnois canal
these pier heads were reduced to 100
t over water, and to 150 t and 250 t
(expansion joint pier heads) on land.
At the base of the pier, the first in situ
lift was designed to be able to develop
plastic hinges in case of an earthquake.
The partial precast piers solution
proved efficient to advance works in
winter conditions. It allows working
in parallel with the in situ part and the
fabrication at the shop.
Incremental Launching
Fig. 8: Launching over the main span
2. The transition between the in situ
and the precast part was solved with
a “wet joint.” This joint was cast in
place with high-strength and nonshrinkage grout. The leveling operations of the first precast segments
406 Technical Report
were critical in achieving the proper
alignment of the pier.
3. The pier heads were designed prefabricated with the requirement of
being able to lift them with standard
cranes. As a result, the weight of
Initially, the constraints of the contract
only left a 3 month winter construction
season per year over the navigational
channel. For this reason, incremental
launching was selected as the most
adequate construction method to erect
the steel structure over the water.
Nonstandard launching design and
equipment were required to achieve
what has been a launching record in
Canada and North America, including a
Structural Engineering International 3/2014
Fig. 9: Launching over the Beauharnois canal
hybrid joint with two technological
obstacles:
1. If welding was done first with no
constraints from the bolting, the
geometry of the joint could not have
been controlled, as the weld deformation introduced important variations in the joint angle.
2. If bolting was fixed at the beginning of the operations, the welding
introduced important tensions in
the nearer bolts that were not considered in the joint design.
The final method statement was sought
through a process to fix the geometry
with some bolts and pins introduced at
the holes surrounding the weld. These
pins were removed when the first
passes of the weld were completed.
Fig. 10: Hybrid mechanical joints
Conclusion
temporary stayed tower and special temporary supports combined with jacks.
The operations were carried in 20 different launching stages (10 per deck).
At each stage, 160 m were put in place
with an average speed of 7 m/h. This
method allowed erecting a total of
2900 m of steel box-girders in less than
a year, with production peaks of 270 m
per month.
In order to cross the main span (150 m)
with the launching, it was decided to
install four temporary bearings with
850 t jacks in the main piers. Each pair
of bearing on each side of the pier was
20 m apart and connected hydraulically. The result was a “swing bearing
system” that reduced the effective
span to launch to 130 m.
The steel box-girder cross section was
selected for the typical span. This section was designed to resist the launching forces of the typical span of 82 m,
but it was not enough to launch the
box-girder over the main span. For
this reason, a temporary stayed tower
had to be used to provide enough
resistance to the box-girder. This tower
also allowed controlling the deflection at the tip of the launching nose
(Figs 7–9).
The different construction singularities
used to design and construct the bridge
allowed the owner to open the bridge to
traffic on schedule in December 2012.
Assembling with Hybrid Mechanical
Joints
When winter and technical requirements introduced important constraints to the schedule, precast and
industrialized solutions for construction proved to be the key to the success.
The longitudinal profile of the boxgirder is divided into 40 segments, with
lengths that range from 18 m to 41,7 m.
Each pair of segments was joined using
a hybrid mechanical joint that combines welding and bolted techniques
in the same joint: top flanges and webs
were bolted and the bottom flange was
partially welded and bolted.
The reason for using this system was to
be able to slide the box-girder supported
on the bottom flange. This 300 mm wide
sliding area was required to be continuous all along the entire length of the
bridge with no bolts. For this reason, the
sliding area had to be welded at each
mechanical joint. On the other hand, to
optimize assembling works, especially
during winter, all other parts of the section had to be bolted (Fig. 10).
This double constraint introduced
in the project a new concept of
Structural Engineering International 3/2014
SEI Data Block
Owner:
Ministère de Transport du Québec &
Nouvell Autorute 30 S.E.N.C (Acciona-Iridium)
Contractor:
Nouvell Autorute 30 CJV
(Dragados-Acciona-Aecon-Verrault)
Steel (t):
15 500
3
Concrete (m ):
70 000
Precast concrete (m3):
25 000
Rebar steel (t):
21 000
Estimated cost
(USD million):
275 USD (300 CAD)
Service date:
December 2012
Technical Report
407