D7.5
Final survey design and
methodology
https://xrotor-project.eu
@XROTORProject
December 2021
This project has received funding from the European Union's
Horizon 2020 research and innovation programme under grant
agreement No 101007135
Ref. Ares(2021)7946002 - 22/12/2021
X-SHAPED RADICAL OFFSHORE WIND TURBINE FOR
OVERALL COST OF ENERGY REDUCTION
Project acronym: XROTOR
Grant agreement number: 101007135
WP7 Environmental and Socio-Economic Impact
D7.5 Final Survey Design and Methodology
Lead Beneficiary: University College Cork
Delivery date: 31st December 2021
Author(s) information (alphabetical):
Name
Organisation
Email
Peter Deeney
UCC
peter.deeney@ucc.ie
Niall Dunphy
UCC
n.dunphy@ucc.ie
Document Information
Version
Date
1
21/12/2021
Description
Final version
Prepared by
Reviewed by
Deeney &
Dunphy
W. Leithead
Approved by
W. Leithead
(Project
Coordinator)
The XROTOR Project has received funding from the European Union’s Horizon 2020
research and innovation programme under grant agreement no. 101007135.
Executive Summary
Deliverable Description:
To identify the factors on which potential buyers base their purchasing decisions. The survey will include
details of at least 12 potential attributes that influence purchasing decisions influencing attributes of
offshore wind turbines. In particular, the market potential of the technology will be assessed using
primary data from original surveys of potential buyers and users of innovations (Stakeholder Group 2).
Responsible:
University College Cork
Outcome Summary:
A plan is proposed to continue with the online engagement with Group 2 as well as person to person if
that is possible. The first stage is to use a SWOT analysis to encourage critical thinking regarding wind
turbine design. The second stage is to enter a modified Delphi study which consists of two elements
based on the criteria used to judge the suitability of turbines. The first element is a sequencing exercise,
the second is a pairwise comparison feeding into an AHP. This Delphi study will provide feedback to
participants and be repeated to allow for recollection and reflection on the part of the participants so
as to produce a considered priority list of criteria.
List of acronyms and abbreviations
AHP
Analytic Hierarchy Process
ASD
Asynchronous Structured Dialogue
O&M
Operations and Maintenance
OEM
Original Equipment Manufacturers
PCM
Pairwise Comparison Matrix
Contents
1
Introduction ...................................................................................................................................... 4
2
Survey Structure .............................................................................................................................. 6
3
4
2.1
SWOT...................................................................................................................................... 7
2.2
Delphi Cycle ............................................................................................................................ 7
2.2.1
Sequencing Exercise .......................................................................................................... 7
2.2.2
Analytic Hierarchy Process (AHP) ...................................................................................... 7
List of Criteria and Hierarchical Arrangement .................................................................................. 9
3.1
Hierarchical Tree for the Criteria ............................................................................................. 9
3.2
An Indicative List of Criteria from D7.2 ................................................................................. 10
Conclusion ..................................................................................................................................... 10
References ............................................................................................................................................ 11
1 Introduction
This report is a preparatory document which describes the methodology adopted and survey design choices
applied for exploring the potential purchasing decision influencing attributes of offshore wind turbines with
stakeholder group 2 (the Wider Wind Energy Community1). The report presents the survey methodology
along with the analytical tools proposed for its interpretation. In order to combine both qualitative and
quantitative data, SWOT Analysis, a sequencing exercise and an analytic hierarchy process (AHP) will be used
within a modified Delphi study. The survey will take place during the second-year workshop for Group 2.
The first part of the final survey, the SWOT analysis, will build on the cumulative explorations of the annual
asynchronous structured dialogues (ASDs) which will introduce the community members to each other’s
ideas and provide an initial set of criteria which can be used as a first step towards the final list. The SWOT
analysis is an examination of a business idea or concept looking at positive and negative aspects of the idea
both now and in the future, under the headings of strengths, weaknesses, opportunities, and threats. It is
described in more detail below in Section 2.1.
The sequencing exercise will ask participants to arrange various criteria used to select wind turbines, in order
of importance, see Section 2.2.1. The current indicative list of criteria given in Error! Reference source not
found. is based on the work presented in D7.2 and will be amended as required as the engagement
continues. These will be formed into a hierarchical tree of criteria used by those in Group 2 to determine
their preferred choice of turbine designs. This is expected to produce a result similar to Error! Reference
source not found. on page 9. Such a hierarchical system will be used as the framework for the analytic
hierarchy process (AHP) which takes the pairwise relative strengths within and between the levels to produce
a weighting for each criterion (Saaty, 2008; Lin, Kou and Ergu, 2014; Sobczyk et al., 2017; Deeney et al., 2021).
The use of AHP here assigns individual weights to the criteria used by members of Group 2 to make decisions
regarding their wind turbine preferences. The method for the arrangement of the hierarchical tree is
described in Section 3.1, and the methods for AHP described in Section 2.2.2. The AHP methods allow for a
detailed comparison between the criteria which goes beyond simple sequencing, which is why the AHP is
carried out after the sequencing exercise.
The sequencing and AHP are arranged in a modified Delphi study which will provide feedback to participants
regarding the rationales used by the other participants in making their judgements. These two methods,
sequencing and AHP will be repeated so that participants will have the opportunity to re-evaluate their
positions, taking into account input from others who also have expertise, and possibly a different perspective.
1 Group 2 are members of the wider wind energy community as defined in the Description of Action WP7 Description of work and
role of partners. Group 2 consists of developers, academics, consultancies, standards bodies, operators, vessel companies,
installation companies, O&M providers, OEMs etc.
LC-SC3-RES-1-2019
Deliverable D7.5
X-ROTOR
The decision to conclude the Delphi study will follow the methodology of our previous work (Deeney et al.,
2021).
SWOT to help the participants compare the criteria and to offer opinions on the design presented
to them.
Modified Delphi Study
o
A sequencing exercise to explore the relative importance of the criteria
o
AHP to assign weights to each criterion
The final survey will determine the attributes which decision makers take into account when choosing an
offshore wind turbine. These attributes may include capital expenditure, operational expenditure,
manufacturing quality, and met-ocean conditions & water depths at the installation site.
While the methods laid out below are based on the current state of the art, it is to be borne in mind that the
asynchronous structured dialogues (ASDs) with both the Group 1 and Group 2 will bring new information to
the project. The surveys, questionnaires, and discussions from these ASDs will widen the approach of the
researchers and provide the research project with insights from industry and the communities. It is therefore
quite likely that the methods proposed here will be developed in the light of the new information and new
insights.
December 2021
Page 5 of 11
LC-SC3-RES-1-2019
Deliverable D7.5
X-ROTOR
2 Survey Structure
It is proposed to arrange three methods to obtain the opinions of Group 2 regarding the importance of the
criteria they use to judge wind turbines. Firstly, the SWOT analysis explained in Section 2.1 will be used to
encourage thinking about the qualities of the X-Rotor design. Then the following Delphi Cycle (Figure 1) will
be used to quantify the relative importance of these criteria. The Delphi Cycle will begin with a simple
sequencing exercise, where participants arrange the criteria in order of importance. Then they will carry
out pairwise comparisons of the four level 1 criteria of Figure 2, the economic, environmental, social and
technical considerations of the X-Rotor design, followed by four sets of similar comparisons at level 2. The
results of these comparisons, both the sequencing and AHP, will be given to the participants along with the
rationale for the decisions. This will constitute one Delphi Cycle. Delphi Cycles will be repeated. The SWOT
analysis and the Delphi Cycle will be discussed in the next two sections.
Figure 1: The Structure of the Survey
December 2021
Page 6 of 11
LC-SC3-RES-1-2019
Deliverable D7.5
X-ROTOR
2.1 SWOT
A standard method to consider the future of a business idea is to perform a Strengths, Weaknesses,
Opportunities, Threats Analysis (SWOT). This has been established in the literature as a method of analysing
business models and ideas (Helms and Nixon, 2010; Tugrul and Cimen, 2016; Coelho Junior et al., 2020). In
the survey plan, the SWOT analysis performs two functions, firstly it introduces the current design ideas for
the X-ROTOR to Group 2 participants so that they may focus their thinking, and second it acts as a reward for
the participants giving them early information on the newly developed turbine design.
2.2 Delphi Cycle
After the SWOT analysis the participants will enter the Delphi Cycle. This follows a standard Delphi pattern
of sharing the anonymised opinions and the rationales of the participants, so that the arguments behind
decisions may be presented in a fair manner disconnected from personalities. The two exercises in the Delphi
cycle are direct criteria comparison and pairwise hierarchical comparisons.
2.2.1 Sequencing Exercise
A direct method is to present a list of criteria to participants and ask them to arrange the list into their
sequence of importance. This has the advantage of being simple and of encouraging the participants to
consider the relative importance of the criteria, which will be relevant for AHP.
2.2.2 Analytic Hierarchy Process (AHP)
The analytic hierarchy process (AHP) to be used is a detailed method to build a pairwise comparison matrix
(PCM) using the methods of Saaty (2008). The disadvantage of this method is that it requires a reasonable
amount of time as there are many pairwise comparisons to be made. For example, to compare four items in
pairs requires six pairs2. The methods used here follow the approach taken by Deeney et al. (2021).
While there is debate about the degree to which a Delphi study tries to impose consensus where it may not
exist, the purpose of the survey is to explore opinions and probe the criteria used by Group 2 members when
selecting and using offshore wind turbines. The purpose is not to develop consensus among that community.
An important concern when using a Delphi study is to decide when to stop. There is of course the practical
limit of the patience and commitment of the participants. From a theoretical standpoint it would be ideal to
call a halt to the cycle when there is sufficient agreement on the outcome. With a mixed group of participants,
it may not be realistic to assume that there will be a consensus or that the group’s opinions will converge.
There are statistical tests to assess the building of consensus, and it will be interesting to discover if the Delphi
process has that effect with Group 2. A standard method to measure consensus is Kendall’s W statistic
(Kendall and Smith, 1939; Yusof, Ishak and Doheim, 2018) which ranges from zero for no consensus to one
2
There are n(n-1)/2 ways to choose a pair from a selection of n objects.
December 2021
Page 7 of 11
LC-SC3-RES-1-2019
Deliverable D7.5
X-ROTOR
for complete agreement. The method uses the ranking order and hence is scale invariant. Following from our
earlier work, (Deeney et al., 2021), a practical stopping condition may be that, (Wi+1 – Wi) / (1 – Wi) > 0.05,
where Wi is Kendall’s W for the ith iteration of the Delphi study. A further stopping condition may be that the
weights produced for the criteria, converge as the iterations increase. Consider the weights produced by the
ith iteration of the Delphi study using the AHP method describing n criteria, to be a vector, vi = (vi,1, vi,2, vi,3,..
,vi,n), where vi,1 + vi,2 + vi,3 +,.. vi,n = 1. Then define the distance di between the ith iteration and the next iteration,
as
and, insist that as well as the consensus condition of Kendal, a convergence condition of di < 0.05 may be
included.
It would also be interesting to compare the results of the direct comparison and the more sophisticated AHP
results. This comparison will form part of the analysis of the survey. On a practical level it would not be useful
to go beyond three Delphi cycles as there is a limit to the time and patience of the participants.
December 2021
Page 8 of 11
LC-SC3-RES-1-2019
Deliverable D7.5
X-ROTOR
3 List of Criteria and Hierarchical Arrangement
The members of Group 2 were approached as part of D7.2 to find out what criteria professionals apply to the
choice of wind turbine technology. Based on the feedback of this workshop in the first year of the research
project, the following criteria have been suggested. These criteria have been categorised as economic,
environmental, social or technical, see Figure 2.
3.1 Hierarchical Tree for the Criteria
Figure 2: Hierarchical Structure of Criteria Based on First Workshop
December 2021
Page 9 of 11
LC-SC3-RES-1-2019
Deliverable D7.5
X-ROTOR
3.2 An Indicative List of Criteria from D7.2
D7.2, produced an initial list of criteria which was presented to Group 1 for its consideration. Analysis of the
Group 2 responses produced the following sequence of criteria, starting with the most important, LCOE and
ending with Impact on scenery. This list is presented as an indication of a possible list to be used in the survey
of Group 2.
-
Levelised Cost of Energy,
-
Choice of height,
-
Ability to survive extreme conditions,
-
Likelihood of collision with birds,
-
Installation cost,
-
Impact on fishing industry,
-
Maintenance costs,
-
Choice of fixed or floating,
-
Purchase cost,
-
Effect on radio and radar signals,
-
O&M cost,
-
Visibility,
-
Choice of power capacity,
-
Impact on shipping,
-
Impact on local people,
-
Noise output,
-
Impact on wildlife,
-
Impact on scenery.
-
Onshore requirements,
4 Conclusion
There needs to be flexibility as new information comes from the Group 1 and Group 2 during the course of
the project. It is however possible to plan for the survey. The survey will take place during the second
workshop for Group 2. This may be done online or in person depending on the circumstances. The initial part
of the survey is to examine the available information on the X-Rotor design and perform a SWOT analysis as
described above.
A list of criteria building on the intervening engagements with the stakeholder groups, will be sequenced and
will have weights assigned following the method above utilising an AHP approach applied in a modified Delphi
study. The Delphi study will be drawn to a conclusion when it is clear that a consensus has emerged or after
three cycles are completed. This is to take into account the ability of Group 2 to commit time and personal
attention to the exercise.
The survey will give an evidence-based priority list for the criteria used by wind energy professionals when
deciding which type of wind turbine to use.
December 2021
Page 10 of 11
LC-SC3-RES-1-2019
Deliverable D7.5
X-ROTOR
References
Coelho Junior, M. G., Biju, B. P., Silva Neto, E. C. da, Oliveira, A. L. de, Tavares, A. A. de O., Basso, V. M.,
Turetta, A. P. D., Carvalho, A. G. de, & Sansevero, J. B. B. (2020). Improving the management
effectiveness and decision-making by stakeholders’ perspectives: A case study in a protected area
from the Brazilian Atlantic Forest. Journal of Environmental Management, 272, 111083.
https://doi.org/10.1016/j.jenvman.2020.111083
Deeney, P., Nagle, A. J., Gough, F., Lemmertz, H., Delaney, E. L., McKinley, J. M., Graham, C., Leahy, P. G.,
Dunphy, N. P., & Mullally, G. (2021). End-of-Life alternatives for wind turbine blades: Sustainability
Indices based on the UN sustainable development goals. Resources, Conservation and Recycling, 171,
105642. https://doi.org/10.1016/j.resconrec.2021.105642
Helms, M. M. and Nixon, J. (2010) ‘Exploring SWOT analysis – where are we now?: A review of academic
research from the last decade’, Journal of Strategy and Management, 3(3), pp. 215–251. doi:
10.1108/17554251011064837.
Kendall, M. G. and Smith, B. B. (1939) ‘The Problem of m Rankings’, The Annals of Mathematical Statistics,
10(3), pp. 275–287. doi: 10.1214/aoms/1177732186.
Lin, C., Kou, G. and Ergu, D. (2014) ‘A statistical approach to measure the consistency level of the pairwise
comparison matrix’, Journal of the Operational Research Society, 65(9), pp. 1380–1386. doi:
10.1057/jors.2013.92.
Saaty, T. L. (2008) ‘Decision Making with the Analytic Hierarchy Process’, International Journal of Services
Sciences, 1(1), pp. 83–98.
Sobczyk, E. J., Kicki, J., Sobczyk, W., & Szuwarzyński, M. (2017). Support of mining investment choice
decisions with the use of multi-criteria method. Resources Policy, 51, 94–99.
https://doi.org/10.1016/j.resourpol.2016.11.012
Tugrul, B. and Cimen, S. (2016) ‘Importance of corporate governance for energy in sustainable
development and evaluation with quantitative SWOT analysis’, Acta Physica Polonica A, 130(1), pp.
87–89. doi: 10.12693/APhysPolA.130.87.
Yusof, N., Ishak, S. S. M. and Doheim, R. (2018) ‘Identifying factors for incorporating spatial data into BIM
using the delphi method’, Construction Economics and Building, 18(3), pp. 1–17. doi:
10.5130/AJCEB.v18i3.6031.
December 2021