MT PDZ Maju - DOCKING & REPAIR WORK PLANNING SCHEDULES
Revision No:
Last Update:
3.0
28.02.2015
Updated by:
KYUZRI
Target Milestones:
ETA Yard (Day 1)
10.03.2015
ETD Yard (Day 15)
25.03.2015
As per meeting resolutions dated 22.01.2015 at Huangpu Shipyard:
Target Docking Period
4 to 5 days
Target berthing upon arrival
3 to 4 days
Target for Hatch Cover Steel Repairs
3 days upon vessel's arrival yard
Special Focus Areas of Works (Major) :
1. Hull blasting and painting
2. Tailshaft sleeve renewal
3. Bow Thruster overhauls
4. Cargo Hold Hatch cover steel repair works, blasting and painting
5. Damaged stern plating plate renewal works
6. Cargo hold inner bottom plating and cell guides
7. Main engine major overhauls
8. Generator major overhauls (3nos.)
9. Safety and Alarm Function Functional Testing and Troubleshooting
Note :
1. This includes estimation of total abt. 95tons steel renewal if needed
Harbor/Quay Trial Date
Seatrials Date
Khairul, Sariza, Khairudin
Yong
Zailan
Owner's PMT
Mobilzation Plan
No. Milestones/Scope of Works
ETA
Wharf
Floating Dcok
Wharf
-2 -1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Sa Su Mo Tu Wd Th Fr Sa Su Mo Tu Wd Th Fr Sa Su Mo
Accumalate Days
Date
Job Ref. No
Day
Kamarul
ETD
15 16 17
24 25 26
Tu Wd Th
1.0 Milestones:
1
2
3
4
5
6
7
8
9
10
11
12
Owner's Project Management Team(PMT) arrives HuangPu
Owner's PMT meeting with Class NK
Owner's PMT Drydocking Kick-Off Meeting with Yard PMT
Vessel's arrives Yard and berthing (Yard and Owner finalzing few repair items onboard)
Docking
Undocking and berthing
Harbor/Quay Trials ( includes Bow Thruster Performance Trials)
M/E Endurance Trials/Sea-Trilas
Works Completion/Delivery
Vessel ETD Yard
Cost querry for final billing
Owner's PMT leaves Yard
2.0 Scope of Works:
2.1 HULL (H)
1
2
3
4
5
6
7
8
2.2
1
2
3
4
5
6
7
8
Hull blasting and painting , seachest, rudder clearances
Hatch cover blasting, steel renewal and painting
Hull and Ballast Tanks Zinc Anodes + Tanks Cleaning (if necessary)
Propeller /Stern Tube/Tailshaft withdraw & repairs /Intermediate Shaft/Rudder Clearances
Bow Thruster
Anchor& Anchor Chains & Chain Locker
Deck and Catwalk
Stern Plating and Aft Mooring Repairs + Hull/Cargo Hold/Cell Guides/Ballast tanks Plating renew upon inspection
(see note 1)
DECK (D)
Windlass and winches
Bunkering lines testing
MAGNETIC COMPASS ADJUSTMENT
CO2 FIXED EXTINGUISHER BOTTLESS PRESSURE TESTING
Deck Crane
ACCOMODATION LADDER
LIFEBOAT + DAVIT
Radio & Nav. (Radar,Dopper Log,VHF, MF/HF, Auto Pilot,RPM Tacho,Speed Log, Window Viper & Steering)
Yard's Total
MAN
1
2
3
4
5
6 7
8
9 10 11 12 13 14 15 16
1
2
3
4
5
6 7
8
9 10 11 12 13 14 15 16
H001, 002, 009
H001A
H003, 010A&B
H003A&B,004&A,005
H006
H007, 008
H011
H015, H015A&B
D001,002,002A,003
D004
D005
D006
D007-009
D010
D011
D012-017, D019-021
9 Container System( Lashing gear eqpt., Reefer Terminals, Twist locks)
10 Air Vent Pipes, Sounding Pipes and Deck Terminal Pipes for Cable Reefer and Hydrant Pipes
11 Deck Outfitting ( WT Door, Small Hatches, Manholes and Railings)
2.3 MECHANICAL(M)
D023-026
D022, 027-028,032, 034-039,042
D029-031,033, 040-041&A
1 Sea Valves ( suction, overboard and sanitary)
2 M/E Major Overhauls and Parts Replacement (LO Cooler, Governor, Air Cooler, Liner, Bearing, T/C & LO Pump)
3 Engine room pump
4 A/E#1,2 and 3 Major Overhaul and Parts Replacement ( Governors, Fuel Pump, Main bearing, Crankshaft#3)
5 Boiler works
6 Ventilation Fans/Blowers Overhauls(E/R, Purifier, AC, Galley, Cargo Hold, CO2, Thruster, Egen)
7 ER Seawater Piping Works
2.4 ELECTRICAL(E)
Fire/Safety and Engine Device Testing (+ Trouble shooting and repairs if any)
Alternator works+Motor Megger Testing(+ Repairs if any)
Mainswitchboard servicing + ECR Consul (+ Trouble shooting and repairs if any)
Prepared by:
Engr. Khairulmuzammil Yuzri (KYUZRI)
PDZ MAJU Drydocking Project Director
05th February 2014
1
2
3
4
5
6 7
8
9 10 11 12 13 14 15 16
1
2
3
4
5
6 7
8
9 10 11 12 13 14 15 16
M001
M002-006
M007
M008-011
M012
M013-20
M021-042
E001-002
E003,E005&A
E004,E006
Reviewed and Approved by:
Mr. Bruce Lee
Ship Repair Division, CSSC Huangpu Wenchong Shipbuilding Co. Ltd.
Email dated 25th February 2015