Activity Description Predecessors Duration: ST4004 Management Science Methods CPM Example Carols by Candlelight

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 1

ST4004 Management Science Methods CPM Example Carols by Candlelight An enthusiastic local musician decides that he is going to organize

a special Christmas eve carol choir service in a local hall. The tasks involved are as follows: Activity A B C D E F G H I J K L M N O P Q R S Description Select music Learn Music Order copies from publishers Auditions Rehearsals Solo rehearsals Rent Candelabra Buy Candles Set up & decorate candelabra Buy decorations Set up decorations Order choir robes Press robes Check out PA system Modify hall acoustics Final acoustics check Final rehearsal Arrange choir party Hold the service. Predecessors A A B, C D D D G H D J D L D N O E, F, P Q, I, K M, R Duration 7 14 14 3 70 70 14 1 1 1 1 7 7 7 14 1 1 1 1

Assuming that seven days a week are available, when must he start in order to be ready in time?