LPG Panjang Project Information LPG Presentation Share1
LPG Panjang Project Information LPG Presentation Share1
LPG Panjang Project Information LPG Presentation Share1
09-1707
PROJECT INFORMATION
BRIEF INFO PROJECT
JAKARTA, 19 OCTOBER 2009 1
OUTLINE
1. Project Information 2. Plant Location & Plot Plan 3. Project Description 4. Scope of Work 5. Project Procedure 6. Project Organization 7. Project Schedule 8. Engineering Plan 9. Procurement Plan 10. Construction Plan 11. Pre-commissioning & Commissioning Plan 12. QA/QC Plan 13. HSE Plan
2
PROJECT INFORMATION
: LPG Panjang Project : 09-1707 : Depot Pertamina Panjang, Lampung : PT. Pertamina Pemasaran dan Niaga (Pertamina) Contractor : PT. Rekayasa Industri (Rekind) Project Scheme : EPCC Contract Value : US$ 8,381,929 and IDR 46,180,699,000 GPM : 6,5% (Include ppH Final) Contract Scheme : Lump Sum (L/S Items) and Unit Price (BQ Items) Project Duration : 24 Months Effective Date : 25 August 2009 (as of SPMB)
3
PLANT LOCATION
DEPOT PERTAMINA PANJANG, LAMPUNG. ~15 KM FROM BANDAR LAMPUNG ~80 KM FROM BAKAUHENI PORT 2+2,5+2 HOURS BY CAR&SHIP FROM JAKARTA
LANDSCAPE LOCATION
DEPOT AREA-I
PERTAMINA JETTY
PLOT PLAN
TEMPORARY SITE OFFICE
TANK#1
TANK#2
PLOT PLAN
PROJECT DESCRIPTION
Product : Terminal LPG Pressurized Tank Capacity : 2 x 2500 MT Main Processing Plants :
Marine Loading Arm / MLA (Liquid Size 12, Vapor Size 6, Op. Press 12 Bar & Temp 30C) LPG Spherical Tanks, (2 @2500 MT Cap.,Op Press 12kg/cm2G & Temp 38C) LPG Pump (2 ea, Cap. 167m3/hr) Filling System (TLA 3ea w/ Shelter & Metering) Terminal Software Management (TSM) Metering
8
PROJECT DESCRIPTION
(Continued)
Utility Facilities:
IA/PA System 20 SCFM Capacity Water System Substation (MCC 380 Volt, SWGR 20KV) Emergency Diesel Generator (EDG), 500 KVA Capacity Weighing Bridge, 60 MT Capacity Telecommunication System Fire Fighting System CCTV
9
10
SCOPE OF WORK
(Continued)
B. New Facilities :
1. 2. 3. 4. Marine Loading Arm (MLA) Piping System LPG Spherical Tank complete w/ Foundation LPG Loading System complete w/ Pump, Metering, Truck Loading Arm, Shelter, Odorizing, weigh Bridge. 5. Terminal Software Management (TSM) 6. Instrumentation System (CCTV, Control) 7. Electrical System (Power, Lighting, Telecommunication) 8. Utility System (IA/PA, Water, EDG) 9. Fire Fighting System 10. Building (Control Room & Office, Sub Station) 11. Fence, Pavement & Drainage
11
PC Pile Concrete Steel Structure Tank Erection Mech. Erection Piping Electrical
: 96 piles : 1,600 m3 : 32 Ton : 1,600 Ton : 90 Ton : 13,000 Dia-in : Swithgear/MCC, Busduct, UPS & Transformer (1Unit), Cable (8000 m), Lighting (130 ea) Control System : 100 I/O Field Instrument : ATG (2 sets), MOV (23 ea), ESDV (7ea), Metering (5 sets)
12
PROJECT PROCEDURE
(CORRESPONDENCE SCHEME BETWEEN CLIENT AND CONTRACTOR)
13
PROJECT ORGANIZATION
(CLIENT Side)
DEPUTI DIREKTUR DISTRIBUSI
GUSRIZAL
VP JASA TEKNIK
HERU PURNOMO
KOORDINATOR PELAKSANA
BOY KARTAATMADJA
KONSULTAN PENGAWAS**
KONSULTAN PENGAWAS**
KONSULTAN PENGAWAS**
14
PROJECT ORGANIZATION
(Contractor Side)
EVP Industrial Plant M. Ali Suharsono Project Director Eddy Herman Harun Project Manager Eko Tjipto
Schedule Control Engineer Jabidi Cost Control Engineer Novie Dianing H Project Administration Iin PY
SITE OFFICE
Superintendent Civil Asep Permana Superintendent Mech. Ali RIdo Superintendent Piping Arief Hari S Superintendent Elec& Inst Asep Saepudin
Chief Logistic & Warehouse TBN Field Purchaser/ Sub. Contract Eng. TBN Warehouse Supervisor & Material Control TBN
HSE S/I
Surveyor TBN
HSE S/V
Security TBN
15
A PROJECT TEAM
1 2 3 4 5 6 7 Eddy Herman Harun Eko Tjipto Hedijanto Utomo Teguh Puji Subagya Yoni Cahyono Welly Fitriadi Rahman 1310 0811141047 1510 08111667038 1567 08161327814 1450 0811136682
2113 081399056000 yoni@rekayasa.co.id 1513 081383429383 welly@rekayasa.co.id 1475 081322330442 fitriadi_rahman@rekayasa.co.id 1475 081373776084 beny_lesmana@rekayasa.co.id 2260 08159909681 ito_mulyanto@rekayasa.co.id 2222 085697015723 ali_rido@rekayasa.co.id 1187 08121052660 2112 08157189003 2244 08159408192 2229 08567700973
asper@rekayasa.co.id arif_hari@rekayasa.co.id dikky@rekayasa.co.id asep_saepudin@rekayasa.co.id
8 Benny Lesmana 9 Ito Mulyanto 10 Ali Rido 11 Asep Permana 12 Arif Hary Saputro 13 Dikky Hafianto 14 Asep Saepudin
16
SCHEDULE
(MASTER SCHEDULE)
17
SCHEDULE
(OVERALL S-CURVE)
NO LPG PROJECT ENGINEERING PROCESS AND COMMISIONING CIVIL, BUILDING AND STRUCTURE MECHANICAL PIPING ELECTRICAL INSTRUMENT PROCUREMENT CIVIL MECHANICAL PIPING HSE ELECTRICAL, INSTRUMENT & CONTROL SYSTEM TELECOMMUNICATION INSPECTION, TEST, COMMISIONING, CERTIFICATION, SPA CONSTRUCTION CIVIL MECHANICAL PIPING HEALTH SAFETY AND ENVIRONMENT ELECTRICAL, INSTRUMENT & CONTROL SYSTEM TELECOMMUNICATION INSPECTION, TEST, COMMISIONING, CERTIFICATION, SPA
0.1958 0.1025 0.0065 0.1062 0.0033 0.0026
30 40 50 60
DESCRIPTION
BOBOT (%) #REF! 0.0900 0.1674 0.3103 0.0498 0.2494 0.1329 0.0902
70 80 90 100
OCT'09
NOV'09
DEC'09
JAN'10
FEB'10
MAR'10
APR'10
MAY'10
JUN'10
JUL'10
AUG'10
SEPT'10
OCT'10
NOV'10
DEC'10
JAN'11
FEB'11
MAR'11
APR'11
MAY'11
JUN'11
JUL'11
0.67071 0.35201
0.60616 0.30286 0.58370 0.86997 0.39759 0.34494 0.40074 0.95863 0.44861 0.30447
0.5641
0.00877
0.00877
2.10151 1.47470
2.10151
2.10151
0.00877
0.00877
0.00877
0.3460 0.1198
20
0.04654
0.04654
0.04654
0.04654
0.25997
0.21342
0.21342 0.7123
0.03540 0.7123
0.21027 0.7347
0.04666 0.7592
0.00942
0.01751
0.0632 0.0030
0.0632 0.0054
0.0478
0.0478
0.0377
0.0089
0.0089
0.0089
0 .1 2
0 .4 7
0 .5 8
0 .3 3
2 .4 6
3 .2 3
3 .4 8
2 .5 4
1 .7 9
0 .5 9
0 .6 1
0 .6 7
0 .6 5
0 .7 7
0 .7 6
0 .6 2
0 .5 3
0 .0 7
0 .0 2
0 .0 1
1.00
1 0 0 .0 0
1 6 .1 7
3 3 .4 2
4 7 .8 0
6 2 .9 9
7 2 .6 9
7 6 .9 1
7 9 .8 8
8 2 .5 4
8 5 .8 4
8 8 .9 6
9 2 .7 8
9 5 .9 7
9 8 .0 7
9 9 .7 5
9 9 .8 9
9 9 .9 4
9 9 .9 8
18
0 .3 6
1 .5 5
4 .2 6
6 .6 6
0 .0 1
1.
PROCUREMENT PLAN
OBJECTIVE: To Procure Materials & Equipment complying with Specification and to Deliver them to the project site on the right time. STRATEGY: Early PO issuance for Long Lead Items (LPG Tank, MLA, LPG Pump) Open Tender Scheme E-pro implementation for bulk materials
20
COMMISIONING PLAN
1. 2. 3. 4.
The activities for this plan will run on from precommissioning phase Prepare start up procedure & performance test procedure Manpower Supply Execution
Utility Commissioning (IA/PA, EDG, etc) Fire Fighting System Commissioning Receive LPG from ship tanker (flow rate 250 MT/hr) Store LPG in spherical tanks (net capacity 2500 MT each) Distribute LPG to tank trucks (30 MT/hr parallel filling)
5.
QA/QC OBJECTIVE
TO ENSURE THAT THE WORK, PRODUCTS, OR SERVICES COMPLY TO PROJECT SPECIFICATION (PRINCIPLES REQUIREMENTS)
23
HSEOBJECTIVE
CORPORATE PROJECT:
Zero Accident with LTIFR < 1 and LTISR < 1 HSE Performance = 70
PROJECT OBJECTIVE:
Zero Accident with: - FATALITY = 0 - PERMANENT DISABLILITY = 0 - FIRST AID < 20 Cases HSE Performance = 75
24
25
26
27
29
3M WITDH
30
31
32
33
34
35