MR/QA&I/04/2014: Power Grid Corporation of India Limited Material Inspection Clearance Certificate
MR/QA&I/04/2014: Power Grid Corporation of India Limited Material Inspection Clearance Certificate
MR/QA&I/04/2014: Power Grid Corporation of India Limited Material Inspection Clearance Certificate
55886
06-Jul-2011 13:02:00
T =
POWER GRID CORPORATION OF
INDIA LIMITED
MATERIAL INSPECTION
CLEARANCE CERTIFICATE
- :
LOA No:
CC-CS/96-WR1/TW-681/3/G6/NOA-I/3549
.... :
MFG. MICC No:
AEPL/EMC/RR03/MICC-01
:
Contract
Name:
TOWER PACKAGE TW03 FOR 765 KV D/C
RAIGARH POOLING STATION (NEAR KOTRA)
RAIPUR POOLING STATION TRANSMISSION
LINES (PART III) ASSOCIATED WITH IPP
GENERATION PROJECTS IN CHATTISGARH,
PHASE I, STAGE I, PART A.
:
Contractor:
ELECTRICAL
MANUFACTURING CO LTD
(EMC), KOLKATA
Part I : |H 1 (Details of Items Inspected)
LOA Sl No Item as Inspected UM LOA Qty Qty Accepted Cumm. Qty
A1,1.3(ii) MICC CLAIM NO.-01 FOR STUB & CLEAT - BNA MT 3 0.371 0.371
A1,1.2(ii) MICC CLAIM NO.-01 FOR STUB & CLEAT - HT MT 101 17.747 17.747
A1,1.2(i) MICC CLAIM NO.-01 FOR STUB & CLEAT - MS MT 17 2.317 2.317
Part II : .. (CIP Details)
ID CIP Date Call ID Manufacturer Issued By
170040
06-Jul-2011
12:59:00
2011061790
M/S AMITASHA ENTERPRISES PVT. LTD., 36, VILLAGE
NILDOH, MIDC AREA, HINGNA ROAD, NAGPUR.
SUBHASH
CHANDRA
VERMA
Part III : .... (MICC Details)
MICC Remarks Recovery Details, if Any
MICC CLAIM NO.-01 DTD.-06.07.2011 FOR DA (STUB)-25SETS,
DC(STUB)-02SETS AND DD(STUB)-10SETS SUBMITTED BY M/S AEPL NAS
BEEN CHECKED WITH RESPECT TO APPROVED BOM, LOA, L2 NETWORK AND
RELATED CIPS. THE MINUMAM WEIGHT OF BNA IS CONSIDERED.
AS PER LOA QTY.
(CERTIFICATE) :
Certified that the Material offered is Inspected / test certificates reviewed and authorised for despatch as per CIPs
given above in PartII. All the deviations observed during manufacturing and/or inspection/review have been properly
disposed off by the competent authority. This certificate is issued for on account payment purpose only for billable
items as above and as per LOA / approved BOM. This however does not absolve the contractor of his contractual
responsibilities.
On Behalf of POWERGRID:
Signature:
Name:
Designation:
Stamp:
Date:
SUBHASH CHANDRA
VERMA
DY.MANAGER.
06-Jul-2011 13:02:00