Professional Documents
Culture Documents
Time Impact Analysis
Time Impact Analysis
More Useable:
Frozen work plan. If the Contractor has not been given remediation
direction and is not able to redeploy his work force in order to keep it in
readiness for resumption of work, then the work plan is said to be frozen
and the assumptions inherent in a TIA remain valid.
Forward looking. Delays planned to occur or occurring at the present time
are better subjects for a TIA then those that have already finished.
Short duration of delay. In general, TIAs are intended to model delays of
less than one month. If longer periods are considered, then Optional Step
3b must be considered.
Less Useable:
The less linear (or serial in nature) the work plan. Work plans based upon
resource considerations are more easily adjusted without detriment to the
project completion or planned expenses than those based upon physical
constraints.
The more mitigation was accomplished during the delay. This can be the
opposite of a frozen work plan. The more work that was performed outof-sequence, the more construction restrictions waved, the more effort
that is performed by either the Owner or contractor on behalf of reducing
the effects of a delay upon project completion, the less effective a TIA is in
modeling the effects of a delay.
The longer the time period between the schedule update and the start of
the delay, the more conditions will have changed between the planned
work schedule and the actual work schedule before the time of the delay.
Specification
A Time Impact Analysis is performed by following the following steps,
STEP 1: Model the Impact with a Fragnet. The fragnet should consist of a
subset of the activities in the project schedule that were involved directly with the
delay. The delay should be described as simply as possible with the fewest
number of activities and relationships added in order to substantially reflect the
impact of the delay to the schedule.
Existing relationships and activities should be left intact wherever passable. It is
expected that the added relationships will cause some of the existing
relationships to become redundant to the CPM calculation but relationships
should only be deleted where the retention of that relationship would negate the
actual work restraints on the project.
It is acceptable to add a delay as a successor to an activity when in fact, that
delay occurred during the activity and delayed its completion. It is also
acceptable to break the existing delayed activity into two activities, with one
representing the planned work before the delay and the other the planned work
after the delay as long as the combined durations of the split activities equals the
original duration of that activity.
The Owner should review, negotiate (if necessary,) and approve the fragnet
before proceeding with the further steps. It is acceptable to combine all of the
following steps into one, buy the Owner still needs to approve the step
considerations in order in order to approve the TIA.
STEP 2: Select the appropriate accepted schedule to impact. The appropriate
schedule should be the last accepted schedule update prior to the date of the
delay. The baseline schedule should be used if the delay began prior to the first
schedule update.
If the date between the start of the delay and the last accepted schedule update
is too large (or if significant deviation to the schedule were experienced between
the last data date and the start of the delay,) the contractor may elect to first
provide a new schedule update with a data date immediately prior to the start of
the delay. If this new update schedule is to be used, it must first be submitted to
the Owner for review and acceptance just like any other schedule update for that
project.
The schedule to be impacted will be called, the original schedule update. The
data date may not be altered from that used by the original schedule update and
the impacted schedule.
Constraints not required by contract must not be included in the analysis. Any
constraint that is required by contract must be the least restrictive one that still
describes the contractual requirement. The list of constraints from least
restrictive to most restrictive is as follows,
STEP 3a: Insert the fragnet into a copy of the appropriate schedule. Using the
approved fragnet as a template, add the impact activities and make the existing
activity adjustments as necessary to mirror the fragnet. With the duration of the
delay activities set to zero, all computed and actual dates in the original schedule
update must match that from the schedule which it was derived from.
OPTIONAL STEP 3b: If the delay time period involved is long or if substantial
mitigation of the delay has occurred, then an option step may be made to
consider the effects of mitigation.
Typical construction law requires that the contractor mitigate the effects of any
delay, if that mitigation can be made without additional cost or disruption to the
project. If Step 2b is not implemented, a statement must be provided with the
TIA to explain why this step was unnecessary. Reasons for not implementing
Optional Step 3b include frozen work plan, forward-looking impact analysis, and
shortness of duration of the delay.
In lieu of actually redesigning the logic that was in effect when the delay occurred
to that which was actually used after the delay occurred, the contractor my elect
to revise the remaining duration status of every activity in the schedule to the
remaining duration status evidenced at the time of the actual end of the delay.
This revision of the status to the impacted schedule will reflect the resultant
effects of mitigation of the project. Activities performed out-of-sequence will still
exist as successors to the impacted activity, but their remaining durations will be
reduced to reflect the work performed during the delay period.
STEP 4: Recompute the CPM and note a change in the project completion date.
This analysis is primarily interested in the estimated early completion of the last
milestone prior to demobilization (usually substantial completion.) This is due to
the consideration of Extended Field Overhead. The delay or acceleration effect
to all contractual milestones still outstanding should be noted and documented.
STEP 5: Determine the amount of project delay. If the contract specifies work
days, then this measurement is made in work days. If the contract specifies
calendar days or lists an absolute date for completion, then the award is made in
calendar days.
STEP 6: Determine the actual dates of the delay. Using the original schedule
update, determine when the successor activity to the delay impact actually
became a project critical activity. On schedules without negative float, the
activity will be predicted to become project critical on the computed late start
date. The first date of delay due to this impact will be the next day after the
activity late start date. Every day after this start of delay will be labeled a delay
day (counting work days or calendar days as appropriate) until the number of
delay days is exhausted.