General Specification Revised February 2005: The Following Section Has Been Added
General Specification Revised February 2005: The Following Section Has Been Added
General Specification Revised February 2005: The Following Section Has Been Added
Section 6
Protection of Substructure
Section 3
Section 4
Concrete Work
Section 5
Blockwork
Woodwork
Section 9
Section 13
The old Electrical Section 19 has now been broken down into nine Sections covering the
specializations within Electrical Works. Most of the content is unchanged however,
Section 22 has been substantially revised, particularly the Dimming clauses.
There is now a detailed index at the end of the specification
The following Particular Specifications have been revised:
Air Handling Units
Building Management Systems
Catering Equipment
Lifts
Sketch AIRCOND/011 has been revised.
Sketches AIRCOND/042 and 043 covering Gantries and Ceiling Access Doors have been
added.
Sketches INTDES/001 Manufactured Boards and INTDES/002 Ceiling Carcassing have
also been added and these are referred to in the Section 7.
Finally, in Section 16.2 covering Ductwork, it is now a requirement for A.C. ducting to be
pressure tested after installation and before the joints are insulated.
End