Dailyreportfrom Site: Date 20.02.2013
Dailyreportfrom Site: Date 20.02.2013
Dailyreportfrom Site: Date 20.02.2013
S.No:41
1.
Date 20.02.2013
Details of
communications
received on (E-mail,
Fax, Courier, Post, by
hand etc.,)
Nil.
2.
3.
Nil.
4.
Nil.
5.
MR.M.E.MANIKANDAN(2141)
5.1
Staff (VEESONS)
5.2
6.
Utkal Engineers:
Boiler: Supervisor:01 IB
05; Riger-03;grinder-0 Helper-07(Total=20)
7.
8.
Site status:
VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM
1) CB line modification work completed.
2) CBD sample cooler line modification work completed
3) FD header Branch Damper & PA line Poking Nozzle attending
platform erection work Completed.
4) Drum level transmitter impulse piping modification work
completed.
5) Furnace seal plate welding work u/p.
6) Dividing chute to mixing nozzle chute flange welding U/P.
7) ID fan outlet Bend erection work completed.
8) Oil firing system piping welding work Completed.
ESP;
1) Rain Support beam erection work completed.
2) Discharge electrode alignment third field completed.
Prepared by (Name):
M.E.MANIKANDAN
M.E.MANIKANDAN
Signature:
Signature:
Staff No : 2141