Project Controls Procedure
Project Controls Procedure
Project Controls Procedure
1. Introduction
This procedure describes the project controls necessary for the successful execution of a
project.
2. Responsibilities
Developing cost, schedule and progress reporting and control procedures, and the Work
Breakdown Structure (WBS).
Implementing a reporting system for the above that enables effective management of the
project at all levels of responsibility.
Continuous tracking and monitoring deviations from the Budget, Schedule, Project Scope,
Commitments, Expenditures and Cash Flows
Developing Schedules.
Establishing the systems, procedures and reports to enable the Construction Manager
and staff to effectively manage their work including progress reports, staffing plans,
schedules and cost reports.
3. Procedure
3.1. Project Control Procedures
The project controls program for each project site must include:
1. Field Budget Development
2. Development of a change management system
3. Site Cost Control
4. Site Planning and Scheduling
5. Site Schedule Control
6. Reporting
7. Close-out procedures
3.2 Procedures Outlined
3.2.1
Site Budget
A Control Budget must be input into a cost system to establish the cost baseline
and will only be changed to reflect approved changes in scope. The primary
purpose of a budget estimate is to establish a baseline for cost control of the
project. All future cost deviations will be reported against the original budget.
Some examples of this type of reporting are outlined below:
3.2.2
3.2.3
Change Reporting
The Project Manager will be responsible for ensuring that monthly deviation status
is reported on as part of the monthly project report. This status will include a copy
of the change requests and the assessment of deviation impact to the Forecast.
The Change requests and records will be updated and presented. Disapproved
and cancelled deviations remain on the permanent Change register with no cost
impact.
3.2.4
Approval of Documentation
Change registers, with comments will be used to document agreements and to
formally distribute the results of changes to the project management team.
Appropriate signatures on the original changes will be required to authorise
changes.
The Project Manager will also be responsible for maintaining the record file for
each change and for transmitting this file to the project members as required.
4
Cost Control:
4.1 The project will be budgeted and controlled in accordance with a Project Code of Accounts
and Project Work Breakdown Structure. The project budget will establish the control budget
for all project analysis and reporting functions. Cost control consists of the following major
elements:
Establishing the control structure and philosophy
Establishing a control budget
Preparing forecasts
Preparing cash flow and commitment plans
Producing cost reports
Project Controls will produce and update the Forecast Cost every month.
4.2
4.3
5
Planning
5.1
Preparing the project plan consists of developing the Work Breakdown Structure (WBS);
understanding all of the project objectives, requirements and restraints which have a
bearing on the timing and sequencing of the work; and developing this information into the
project logic plan. Once the project logic plan is completed, the planner/scheduler begins
the process of scheduling.
Four base levels of schedule are used:
Incorporation of new information, which may require adjusting the schedule logic
and durations
The Contractors schedule will be produced within 14 days of contract award and will
conform to an agreed upon milestone schedule contained in the signed contract. These
activities shall be of sufficient detail to ensure an appropriate basis for monitoring and
evaluating the sequence of the Work and shall include major constraints and interface
points.
Narrative schedule analysis reports will be completed from each contractor and presented
in each monthly progress report.
The Contractor will provide look-ahead schedules every 2 weeks in accordance with the
Contract Project Level Schedule.
Project schedules are to be monitored weekly and updated bi-weekly to determine that
critical milestones are being met and those activities are progressing as required.
The Critical will be determined by those activities with the least amount of total float.
Critical path activities control the overall duration of the project. An activity with less than
10 days total float is critical and will require thorough monitoring on a regular basis to
ensure timeous completion of the project..
Schedule Alerts will be issued to advise project management of factors that might cause a
change in the established schedule for the project. Early detection of these factors is the
key to taking remedial action to mitigate the impact to the completion of the project and it
will be the responsibility of the Project Manager to ensure that the factors that may delay
the project are resolved.
5.2 Reporting
Monthly Progress Reports will serve as the base document from which the Project
Management Team will utilize for overall reporting of the project to the client. The site
Monthly Progress Report will be incorporated into the Project Management Team report
and will provide a comprehensive picture of where the project has been, current status, or
forecast relative to Control Budget and schedules. The report will empower management
to take corrective actions that favourably impact the project if required.
6
Closeout
It is important that each project provides actual cost data to the Clients Project Controls
system. Copies of each of the capital cost estimates prepared for this project must be
archived at the conclusion of each project.
A project completion report must be the accumulation of data from each of the major
disciplines involved in the execution of the project. This document is a critique of how
effective the project management effort was applied. Key focus areas should be:
This document should contain the in-depth analysis of the various elements of cost on the
job. The primary purpose of the analysis is to provide historical data to be used in making
better estimates for the future planning of projects.
Final Cost Reports must be retained in the client databases and the Project Controls library.
The data contained in these reports should be the primary source of information to be used in
analyzing future estimates.
Attachments
The following attachments and flow processes provide the mechanism to implement Quality
Control and assurance programme:
1.
2.
3.
4.
1.
PM
Project Manager
AO
Assignment Owner
Date :
Project No
Date Issued
Approved
Not
Approved
Comments
Sheet No
Contract No
2) BCP Title:
4) Project Title:
Subproject Title
5) Date Received by the secretariat: Level 2 . Level1. Level0.
6) Change Designation:
Routine
Priority
Emergency
[
[
[
]
]
]
7) BCP Level:
Level 0 [
Level 1 [
Level 2 [
8) Directed Change:
]
]
]
Yes
No
11) Phone:
[
[
9) AO
]
]
12)Fax:
13) e-mail
14) Change Description to Scope, Schedule, Cost, Quality, Risk, HR, Comm., Procurement
(ref Change Request form from appropriate Plan attached)
15) Change Justification and Impact (If directed change, specify authority and attach
change control request
Approved Baseline
Change
Proposed
18) Current
Project Budget
Change
Contingency R
R
19) Impact on funding (TEC+OPC=TPC):
Project year
Approved Budget
Capita Operatin
l
g
Previous
Years
Current Year
Year 2
Year 3
Year 4
Year 5
Beyond 5
Years
Proposed Change
Capita Operatin
l
g
Proposed
R
Annual changes
Capita Operatin
l
g
Proposed Profile
Capita Operating
l
Sub Total
Total Budget
*Include only the sum of those changes approved since the last budget update to show the
total impact (shown in the last 2 columns) on the current budget
20) Funding source for TEC increases:
Change
Baseline
Revised
PROJECT TITLE:
BASELEINE DOCUMENT
DATE
SUBPROJECT NO:
TPC
TEC
LOG DATE:
BCP
No
description of change
1.1.1
Disposition
Date/Result
Level Level
2
1
Baseline Changes
Level
0
DISPOSITION CODES
AP APPROVED
CA CONDITIONALLY APPROVED
DF DEFERRED
EN - ENDORSED
RJ REJECTED
AK ACKNOWLEDGED
NOTES :
TP
C
TE
C
SCH
Con
SCP
Reference: CPDS or
ADS
TP
TE
CO
FY
C
C
N
FN
INPUT
12
PROCEDURE
Leve
Leve
Lev
l1
l2
el3
Decision Recorded by
Secretariat of the Committee
OUTPUT
Yes
1.Change Approved
2.Change Acknowledged to
implement in system
Answer - No
1.Conditional approval
2.Deferrment
3.Rejection
Endorsed