Atp 11a

Download as pdf or txt
Download as pdf or txt
You are on page 1of 39

ATP11A Siteforge Process 850 MHz

Document History
Version

Author

Date

Remarks

Version 1.0

Ashish Shukla

3-Sep-2015

New ATP 11B procedure for 850 Mhz

Version 1.1

Ashish Shukla

11-SEP-2015

Modification in Slide 36 Remark about Existing Antenna Swap


and Transfer to ware house

Agenda
Work Order Assignment Management Flow chart
Example on WO Assignment Management Flow
Procedure to use SITEFORGE using tab in field
WO Assignment Management Flow(ATP-11A)
Install and usage of various Login
Procedure to use SITEFORGE using tab in field

Introduction to Work Order Assignment Management


Work Order Assignment Management is also known as WAS.
WAS is going to help users in automating the Work Order(WO) flow in a
systematic manner using a portal called SITEFORGE.
Using this portal each level of Management employees will receive and
execute their WO or Task assigned to them.
Helps to trace the network status through online mode.
Provides Visual steps to guide users on progress and upcoming steps.
Improves productivity & complete visibility.
Helps users to monitor Parameter Compliance Index(Planned Vs. Actual).
Helps users to Search/Filter Sites & WO based on various parameters.

Network Lifecycle Management Flow


(Work Allocation System)

WO assignment management flow


Responsibility:
GIS/SIITE
FORGE;
Notification:
Samsung CH

Responsibility:Sam
sung CH;
Notification:Samsun
g AM, RJIL CTO
Responsibility:
Samsung Am
Notification:
Samsung CM

On Hold with
justification

WO is created & issued to respective


SAMSUNG CH by RJIL

Samsung QE
Accept
On hold with
issue list to eNB
Eng

CH assigns the WO to
respective Samsung AM
Accept
1. AM assign Samsung eNB
engineer & QE for that Site
2. Assign various tasks of that WO
to single or multiple SOLPAR

SAMSUNG AM will Accept

Reject
Responsibility:
SOLPAR PM
Notification :Samsung
AM & Samsung eNB
er.

SOLPAR PM assigns task to


SOLPAR field engineer

RJIL Circle
CTO
Accept/
Reject
Accept

Task is auto-closed in SITEFORGE


Responsibility:
SOLPAR field
engineer
Notification: Samsung
eNB er. & SOLPAR PM
Responsibility:
SOLPAR FE &
SAMSUNG eNB er.
Notification: Samsung
AM & SOLPAR PM

SOLPAR field er. Executes task(Pre


ATP 11A) & saves it in tab & uploads
to server once in coverage & notify
to eNB Eng.
Pre-ATP11A is acknowledged by eNB Eng
joint ATP11A is performed (FE + eNB Eng)
Report is modified on Tab ,if required (FE)
Joint-ATP11A is completed & report is
uploaded on server. Samsung eNB er. to
certify

End

Response:Sam
sung QE
Notification:
Samsung-Reg
QM,AM,CM;
SOLPAR-PM,FE

Responsibility:
Samsung AM
Notification:
Regional
QM,SAMS
CM,Circle RJIL
CTO
Responsibility:
Circle RJIL CTO
Notfication:
Samsung
CH,AM;System(
GIS,REIMS)

Responsibility:
SAMSUNG AM
Notification:
SOLPAR PM,
SAMSUNG CH

Login Creation & Siteforge Installation

Login creation - introduction


Objective
Procedure to install and use (Work Allocation System
WAS [Siteforge]) in Samsung Galaxy Tab 3 8 by Solpar
field engineers
Steps
User (Solpar field engr.) creation by : Solpar
Project manager
Intimation mail to field engineer : From
Siteforge team (system.siteforge@gmail.com)

Click activation link

Login to Siteforge and change password


(default password is with project manager)
Download and install .apk (installation file).
Start using the siteforge by clicking the icon.

Login creation - Intimation mail

Receive mail from siteforge team


Click on Activation Link

Login creation accessing the site first time


If the mail is accessible in the TAB

Click on Activation Link

If the mail is not accessible in the TAB (eg. Official


mail not configured in the the TAB)
Open explorer, type below link in the address bar
https://siteforge.ril.com/siteforge/jsp/index.jsp

Login creation password change


Change the password

Default password would be available with your


project manager

Login
Login with the new password

Changing security setting


Before downloading the installation file, change
the security setting
Go to TAB setting
Turn on Blocking mode
Tick Unknown sources check box

Download and install installation file (.apk) file

Click Download Apk,


Once downloaded, go to notifications and click .apk file
Select install

ATP 11A Procedure

How to Login?-FE
Login with your user name from Samsung TAB

ATP 11A Process

Click on Task

ATP 11A Process

Click drop down Menu to Select Specific band

ATP 11A Process

Select 850 Band

ATP 11A Process

Select the Site and Click on Perform ATP 11A

Site Information

EDIT

Click On Next

Installation Scenario

Field Engineer need to answer the above question that


they have installed Multiband or Penta Band during 850 Mhz Installation

Antenna Make & Model

EDIT
Enter the Information based on ACE/ROSENBERGER Model Type Used

EDIT

Antenna Height incuding building height and


tower foundation height in Case of RTP/RTT/RTD

Antenna & Cable Information

Tilt Information

Azimuth Information

inch RF jumper Information

CPRI Cable & RRH Type

CPRI Length

RRH type V1/V2

Installation Check List

EDIT
CDU Installation Check List

Press yes or no to depict the status

Installation Check List

RRH Installation Check

Installation Check List

Antenna Installation Check

Installation Check List

Cabling Check for 850 Mhz

Grounding Check

Site Inventory List

Field Engineer need to capture the Serial number


of all the site inventory for 850 Mhz

Capture the 850 Mhz L9CA serial Number

Capture 850 Mhz RRH Serial Number for all Three sectors

Capture 850 Mhz Antenna Serial Number for all Three sectors

Site Inventory List

Capture 850 Mhz Antenna Serial Number for all Three sectors

Incase of Pentaband / Muntiband Antenna capture the serial number


of all the three RET in all the 3 Sectors

Site Photograph

Collect the mentioned photographs

Site Photograph

Site Photograph

Site Photograph

Site Photograph

Remarks

Incase of existing antenna are swapped with new antenna then SOLPAR
need to mention the YES/NO , and also confirm that they are sent back to
warehouse .

Add remarks about the work done if any

Click Next

Acceptance Sheet

Thank You!!!