Canada Line Agreement Overview
Canada Line Agreement Overview
Canada Line Agreement Overview
Mayors Council
From:
Cathy McLay, Acting Chief Executive Officer and Chief F inancial Officer
Date:
Subject:
PURPOSE
The
purpose
of
this
report
is
to
provide
the
Mayors
Council
with
a
high
level
overview
of
the
Canada
Line
Concessionaire
Agreement.
BACKGROUND
Canada
Line
is
a
19km
rail
rapid
transit
system
connecting
downtown
Vancouver,
the
Vancouver
International
Airport
and
Central
R ichmond.
It
has
16
stations,
two
bridges
and
nine
kilometres
of
tunnel.
The
development
and
construction
of
the
project
w as
jointly
funded
by:
the
G overnment
of
Canada
( Canada),
the
Province
of
B ritish
Columbia
( the
Province),
the
S outh
Coast
B ritish
Columbia
Transportation
Authority
( TransLink),
Vancouver
International
Airport
Authority
(VIAA),
the
City
of
Vancouver
and
InTransitBC.
The
procurement
stage
began
in
the
summer
of
2003
w ith
the
approval
by
the
Province,
TransLink
and
VIAA
to
begin
a
competitive
process
to
select
a
contractor
to
design,
build,
partially
finance,
operate
and
m aintain
the
line.
The
procurement
concluded
w ith
execution
of
a
contract
( Concession
Agreement),
between
Canada
Line
R apid
Transit
Inc.
( CLCO),
a
w holly
owned
subsidiary
of
TransLink,
and
the
selected
contractor,
InTransitBC.
The
finalization
of
project
documentation
occurred
on
July
29,
2005
(Financial
Close)
and
InTransitBC
began
construction
of
the
system
shortly
thereafter.
The
commercial
relationship
between
InTransitBC
and
TransLink
is
governed
by
the
Concession
Agreement
w hich
sets
out
the
rights
and
obligations
of
each
party
in
the
delivery
of
the
project
over
35-years,
of
w hich
four
years
involved
the
construction
phase
of
the
project
and
then
followed
by
31-years
of
operating
and
m aintaining
the
Canada
Line.
Substantial
completion
of
the
construction
phase
of
the
project
w as
achieved
in
August
2009
with
line
opening
up
to
the
public
on
August
17,
2009.
During
the
operating
period,
payments
will
be
m ade
to
InTransitBC
for
the
achievement
of
performance
targets
that
m easure,
for
example,
train
frequency,
safety
and
ridership.
DISCUSSION
The
Concession
Payments
m ade
to
InTransitBC
during
the
operating
period
comprises
a
blended
payment
m ade
up
of
the
following
three
m ain
cost
elements:
1) Payment
to
the
concessionaire
for
the
costs
to
operate
the
Canada
Line
for
the
next
31-years
( starting
in
August
2009)
and
ending
on
July
31,
2040
( the
Operating
&
Maintenance
Costs
Element);
2) Repayment
of
the
$721
m illion
in
private
capital
that
the
concessionaire
contributed
to
the
project
( the
Capital
Element):
3) Payment
of
the
interest
on
the
loan
of
the
$721
m illion
w hich
gets
repaid
over
the
31-years
of
the
operating
concession
( the
Interest
Expense
Element).
The
Concession
Agreement
m akes
no
attempt
to
breakout
these
three
cost
elements.
It
is
just
one
blended
payment
m ade
to
the
concessionaire
m ade
every
four
w eeks
(28-days)
over
31-
years.
It
w as
structured
this
w ay
to
provide
TransLink
w ith
m ore
security
as
the
agreement
allows
TransLink
to
reduce
or
w ithhold
these
periodic
payments
if
InTransitBC
doesnt
perform
according
to
various
performance
requirements.
The
calculation
of
the
Concession
Payments
m ade
to
InTransitBC
during
the
operating
period
is
based
on
a
complicated
formula.
However
the
following
are
the
m ain
driving
factors:
Base
Payment
multiplied
by
a
Compound
Inflation
F actor
multiplied
by
a
Ramp-Up
F actor
multiplied
by
an
Adverse
Performance
F actor
( e.g.
95%
if
performance
is
5%
below
expected)
Above
plus
or
m inus
a
Base
Volume
Adjustment.
Above
plus
a
Special
Event
Adjustment
The
Base
Payments
for
each
28-day
period
during
the
operating
period
w ere
fixed
at
the
signing
of
the
Concession
Agreement
and
are
all
expressed
in
April
1,
2003
dollars.
The
Concession
Agreement
includes
a
S chedule
that
clearly
sets
out
the
amount
of
these
B ase
Payments
for
each
of
the
404
28-day
operating
periods.
They
are
as
follows:
Period
1
Period
2
to
332
Period
333
Period
334
to
404
$6,947,290.00
$6,408,830.00
$5,236,370.00
$4,063,910.00
26.00%
30.00%
100.00%
35.750%
22.500%
100.000%
The
Ramp-Up
F actor
w as
only
relevant
in
the
first
two
years
of
operation.
It
w as
80%
in
the
first
year
and
92%
in
the
second
year
and
then
100%
thereafter.
The
Adverse
Performance
F actor
takes
into
account
any
adverse
performance
by
the
concessionaire
below
w hat
is
required
in
the
contract.
As
long
as
the
Concessionaire
performs
according
to
plan
these
adjustments
are
usually
very
small
and
cover
essentially
two
items:
1) Availability
(i.e.
vehicle
availability,
station
availability
and
system
availability),
so
e.g.
any
problems
that
result
in
a
train
not
running
to
a
prearranged
schedule
or
any
m ajor
system
shutdowns
w ould
result
in
a
certain
percent
reduction
from
100%
based
on
another
complicated
formula
as
set
out
in
the
Concession
Agreement;
and
2) Quality,
so
e.g.
any
graffiti
or
garbage
on
the
platforms
or
on
or
in
the
trains
not
being
removed
w ithin
a
reasonable
timeframe
w ould
also
result
in
a
certain
percent
reduction
from
100%
based
on
a
formula
as
set
out
in
the
Concession
Agreement.
Mystery
S hoppers
help
police
this.
The
adjustment
up
or
down
for
a
Base
Volume
Adjustment
takes
into
account
any
actual
ridership
over
the
base
volume
ridership.
The
further
adjustment
for
a
Special
Event
Adjustment
takes
into
account
the
cost
the
Concessionaire
incurs
for
providing
extra
service
for
special
events
such
as
Celebration
of
Light,
Hockey
G ames,
S anta
Clause
Parade,
etc.
Summary
TransLink
is
following
the
payment
terms
and
schedule
as
set
out
in
the
concession
agreement
signed
on
July
29,
2005.