Prerequisites: PLM220 SAP Project System - Logistics

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

PLM220

SAP Project System - Logistics


Product Group
Solution
Sub-solution
Component
Delivery Methods
Level
Exam
Sample Questions
Cut Score
Duration
Languages

:
: SAP ERP
:
:
: Certification
: Details, Configuration & Transaction
:
: PDF Link
:
: 5 days
: English

Prerequisites
Essential

PLM200 or PLM210

Recommended

None

SAP ERP 6.0 with Enhancement Package 7; MRS 9.0

Project Structures
o Creating Project Structures
Functions and Types of Scheduling
o Scheduling Dates for WBS Elements
o Performing Scheduling of Network and Activities
o Customizing in Time Scheduling
o Scheduling Activities
o Scheduling Constraints and Dependencies in Networks
o Setting Actual Dates for WBS Elements and Activities
Project Capacities
o Processing Internal Activities
o Analyzing Internal Activities and Capacity Requirements
o Generating Capacity Requirements
o Executing Capacity Analyses for Projects and Work Centers
o Performing Capacity Leveling
o Performing Capacity Leveling with MRS
o Processing Confirmations and Triggering a Workflow for Variances
o Confirming Network Activities using the Cross Application Time Sheet (CATS)
External Activities
o Executing Services for Externally-Processed Activities
o Using Workflows in the Project System
o Integrating Service Activities
Project Materials
o Assigning Material Components to Network Manually

Course based on software release


Content

Assigning Material Components to Activities Automatically


Maintaining the Field Selection for Material Components
o Searching for Materials using Enhanced Features and Functions
o Processing Material Procurement
o Creating a Third-Party Requisition for Non-Stock Items
o Executing an In-House Production Process
o Processing Preliminary Requirements in Projects
o Grouping Material Requirements
o Using Material Assemblies
o Performing a Material Availability Check
o Generating Deliveries for the Shipping of Assemblies
Progress Tracking
o Monitoring Deadlines using Progress Tracking
Project Analysis and Procurement Processes with ProMan
o Monitoring Logistical Data and Procurement Processes using ProMan
o
o