Project Management Assignment
Project Management Assignment
ASSIGNMENT
Project Time Management:
A project has 11 activities. The precedence relationships and the three
point estimates are provided in the following table:
Activity
Immediate
Predecessor
A
B
C
D
E
F
G
H
I
J
K
A
A
A
B, C
B, C
E, F
E, F
D, H
G, I
Optimistic
Time
(Hours)
4
1
3
4
0.5
3
1
5
2
2.5
3
Most Likely
Time
(Hours)
6
4.5
3
5
1
4
1.5
6
5
2.75
5
Pessimistic
Time
(Hours)
8
5
3
6
1.5
5
5
7
8
4.5
7