Inspection and Testing Plan

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3
At a glance
Powered by AI
The document outlines inspection and testing plans for mechanical, electrical and architectural works on a construction project.

Inspection and testing plans are provided for material approval, storage, installation, pre-handover activities etc. Responsible parties include resident engineer, clerk of works and mechanical engineer.

Inspection and testing plans include material approval, storage, surface preparation, bricklaying, plastering, rendering, railing and painting works. Responsible parties include resident engineer and other CESB staff.

Inspection and Testing Plan

Customer: Cakna Enterprise Sdn.


Bhd INSPECTION AND TEST PLAN FOR :
Contract No: MECHANICAL & ELECTRICAL
Project name: HUSM (Pakej 1)
Responsibility Records Inspectio
Inspections/ Sampling Requirement
Acceptance n/test
No Work/Activity testing /Frequen /standard/sp
Check Verify Approval criteria procedur
required cy ecification
e
1 Each
Mock-up Mock-up Specificatio
Material Approval material RE RE P Refer B.Q Check DO
form file n & codes
used
2 Confirm to Each Delivery Orders as Specificatio
Material inspection RE/CoW RE - Visual
order delivery dockets placed ns & codes
3 Safe,
Each Specification, secure/
Storage and protection As specified CS ME - Checklist Visual
week as attached adequate
protection
4 Specification
Task Each s/ OHS All tasks
Preliminary activities CS ME - Checklist Visual
completion work area practice & completed
regulations
5 Checklist
Check Each Shopdrawing
Material installation ME ME - Checklist and test Checked
shopdrawings work area s
panel
6 All matters All items
Each Shopdrawin Specification, Final
Pre-handover activities finalized, CS ME ME completed
work area gs as attached inspection
clean and tidy to specified
* RE = Resident Engineer, CoW = Clerk of Work, P = Principle, ME, Mechanical & Electrical Engineer, CS = Other CESB staff
Customer: Cakna Enterprise Sdn.
Bhd INSPECTION AND TEST PLAN FOR
Contract No: ARCHITECH
Project name: HUSM (Pakej 1)
Responsibility Records Inspectio
Inspections/ Sampling Requirement
Acceptance n/test
No Work/Activity testing /Frequen /standard/sp
Check Verify Approval criteria procedur
required cy ecification
e
1 Material Approval Each Refer B.Q Check DO
Mock-up Mock-up Specificatio
material
form file n & codes
used
2
Confirm to Each Delivery Orders as Specificatio
Material inspection Visual
order delivery dockets placed ns & codes
3 Each Specification, Safe,
week as attached secure/
Storage and protection As specified Checklist Visual
adequate
protection
4 Task Each Specification All tasks
completion work area s/ OHS completed
Preliminary activities Checklist Visual
practice &
regulations
5 Surface preparation Ready to Checklist Visual
Each Specification, Smooth and
paint, clean
work area as standard clean
and smooth
6
Confirm to Each Specification, Specificatio
Brick layer Checklist Visual
specified work area as standard ns & codes
7 Plastering All maters Checklist Visual
Each Specification, Smooth and
finalized,
work area as standard clean
clean and tidy
8 Rendering All maters Checklist Visual
Each Specification, Smooth and
finalized,
work area as standard clean
clean and tidy
9
Location and Each Specification, All tasks
Railing Checklist Visual
level work area as standard completed
10 Full&
Checklist
uniform Each Specification,
Painting Checklist and test Visual
cover, work area as standard
panel
smooth, color
* RE = Resident Engineer, CoW = Clerk of Work, P = Principle, ME, Mechanical & Electrical Engineer, CS = Other CESB staff