Question Bank - OPM
Question Bank - OPM
Question Bank - OPM
Q 3. What are the various approaches in CVP analysis and what all are the assumption in which the
CVP analysis is based.
Q4.Two alternative set ups, A and B are available for the manufacture of a component on a particular
machine, where the operating cost per hour is Rs 20/-
Which of these set ups should be used for long range and economic production?
Q 5. Machine A and B are both capable of manufacturing a product. They compare as follows:
Which machine will have the lower cost per unit of output, If run for the whole year.
If only 4000 pieces are to be produced in a year, which machine would have the lower cost / piece.
Will you answer to first question above will change if you are informed that 12.5% of the output of
machine B, get rejected at the inspection date. If so, what would be the new solution.
Q 6. Methods P and Q are both capable of manufacturing a product. They compare as follows
The annual requirement is 1500 nos. Operating cost per hour of the process is Rs 128 for both
processes. Material cost is the same in each case.
Production Manager of a unit wants to know from what quantity he can use automatic machine as
against semi automatic machine.
Q. 8.Two alternative set ups, A and B are available for the manufacture of a component on a
particular machine, where the operating cost per hour is Rs 20/-
Which of these set ups should be used for long range and economic production?
Module 2. Forecasting
Q 1. What are the various factors that are common to al forecasting methods.
Q 6. The table below contains the weighted moving average forecasts for Spencer. If we use
the sum of digits weighting scheme with N=4, we shall calculate the WMA (weighted Mean
Average) for the period 10 and 11.
Q 7. Table below gives the forecast that would be generated for a Mall, by an exponential
smoothing model using α= 0.2 and an initial forecast for week upto 9. Work out the forecast
for week 10,11 .
Wee Actual sales
k
1 110
2 102
3 108
4 121
5 112
6 105
7 114
8 106
9 115
10
11
Q 8. Given the following data: Calculate the forecast of the number of complaints for week 6 with a
smoothing constant of 0.40.
Q 9. Using the trend line method, calculate the forecast for the period 10 and 11.
Perio Demand
d
1 44
2 52
3 50
4 54
5 55
6 55
7 60
8 56
9 62
Q 10. Compute MAD, MSE and MAPE for the following data:
Q 6. Describe the various ways of improving the behavioral aspects of employee to achieve higher
productivity.
Q 8. List and compare the various step in Method study and Work Measurement.
Q 12. Calculate the standard production per shift of 8 hours duration with the following data:
Observed Time per unit= 5 mins, Rating factor = 120%, Total allowance= 33.33% of normal
time.
Q 13. Calculate the ST per article produced from the following data obtained by work
sampling study.
Q 14. Compute the production cost per piece from the following data:
Wage rate Rs 2000 per month consisting of 25 working days and 8 hours per shift.
The time for manufacture of 4 pieces of the item was observed during time study. The
manufacture of 4 elements a, b, c and d. The data collected during the time study are as
under. Time observed( in mins) during the various cycles are as below.
Allowance: the personal fatigue and delay allowance can be taken as 25%.
Q 15. A work sampling study is to be made of a typist pool. It is felt that typist are idle 30% of
the time. How many observations should be made in order to have 95.5% confidence so that
the accuracy is within ± 4%.
Q 16. In a work sampling study , a mechanic was found to be idle for 20% of time. Find out
the number of observation needed to conform to the above figures with a confidence level of
95% and a relative error level by ±5%.
Q 17. An industrial engineer, deputed to conduct a time study for a job, has, after
observation, divided the job into 5 elements. He had noted the timings for four cycles of the
job as below:
Compute the basic time for the job and the standard time if the relaxation allowance of 12%,
a contingency allowance of 3 % and incentive of 20% are applicable for the job.
Q 2. What are the various models available to identify a near ideal location.
Q 3. XYZ company is evaluating four locations for a new plant and has weighted the relevant
scores as given below. Scores have been assigned with higher values indicative of preferred
conditions. Using these, develop a qualitative factor comparison for the four locations.
Q 4. A company is to decide on the location of a new plant. It has narrowed down the choice
to 3 locations A, B and C: Data in respect of which is furnished below:
Q 5. A company has to select one location out of the five alternatives considered for a new
plant . The annual operating costs and other intangible factors are given below for these five
locations.
Q 10. Compare the merits and demerits between Product and process layout.
Q 12. Using the information contained in the table shown, do each of the following:
0.3 min 0.4 min 0.2 min 0.1 min 0.5min 0.3min
a c e g h i
b d f
0.6 min 1.2 min 0.6 min
Q 14. As part of a major renovation plant, the industrial engineering department has been
asked to balance a revised assembly line of operation to achieve an output of 240 units per
eight hour day. Task times and precedence relationship are as follows:
Q 15. Two layout alternatives are shown below. The facility’s product, their travel between
departments and the distance between departments for each layout alternative are also
shown below: The layout alternative that minimizes the monthly product travel through the
facility be determined.
Layout A
8 4 10 2 5
3 7 1 9 6
Layout B
7 1 9 6 3
4 10 2 5 8
Dept Dist between Dist between Dept Dist between Dist between
movement dept dept movement dept dept
combination Layout A Layout B combination Layout A Layout B
1-5 30 30 3-9 30 20
1-7 10 10 4-5 30 30
1-9 10 10 4-7 10 10
1-10 10 10 4-10 10 10
2-5 10 10 5-6 10 10
2-6 20 20 6-9 10 10
2-10 10 10 7-8 20 50
3-6 40 10 8-10 20 30
Q 1. What is aggregate capacity planning and list the various steps in ACP.
Q 2. Write short notes on Top Down ,Bottom Up , Time fence and Rough cut capacity
planning.
Q 3. What are the various factor that decide the plant capacity.
Q 4. Explain with the help of a flow chart the working of CRP ( capacity requirement
planning).
Q 5. What are the objectives and function of MPS ( Master production Schedules).
Q 7. A company that makes industrial pumps wants to make a make MPS for June and July.
Marketing has forecasted demand of 120 pumps for Jun and 160 pumps for Jul. These have
been evenly distributed over the four weeks in each month: 30 per week in Jun and 40 per
week in Jul. The stock in hand at the beginning is 64 pumps. Find the MPS and uncommitted
ATP inventory.
Q 8. A firm produces two products P and Q on produce to order basis. The demand for the
products come from several sources. The estimate demand for the two products over the
next 5 weeks are given below:
The beginning inventory for P is 50 and Q is 60. Prepare a MPS for these two products.
Q 4. Calculate the vendor rating for the following. The item under consideration is the same
from all suppliers.
Supplier’s data A B C
Quantity supplied 90 80 75
Quantity accepted 78 80 70
Price of each item Rs 4 Rs 4.2 Rs 3.9
Delivery Promised 6 weeks 6 weeks 6 weeks
Actual deliveries made 8 weeks 6.2 weeks 7 weeks
in
Weightage for quality = 70%, price= 20% and Delivery = 10%
Q 8. Calculate the carrying cost and inventory cost on the data provided below:
The company has an average inventory of Rs 60 lacks and has placed order of 3400 orders in
the year of review. Calculate the cost per order and inventory carrying cost as percentage
based on the above costs. What would be the EOQ, if the annual demand of an item is 12000
numbers and unit price is Rs 60 per unit.
Q 14. An auto industry purchases spark plugs at the rate of Rs 25 per piece. The annual
consumption is 18,000 nos. If the ordering cost is Rs 250 per order and carrying cost is 25%pa.
What would be the EOQ. If the supplier of spark offers a discount of 5 % for order quantity of
3000 Nos per order, do u accept the discount offer.
Q 15. For a given item of constant demand rate of 60000 units per annum, the unit price is Rs
60. Ordering cost per order is Rs 600/ and the carrying cost is 30%pa on average inventory
value. What would be the total cost at optimal order quantity?
The vendor is offering a quantity discount of 5 % if 20000 units are purchased at a time. Do u
accept the offer.
Q 16. A company uses 1200 units per month of an electronic component each costing Rs 2.
Placing each order cost Rs 50/- and carrying cost is 6% pa of the average inventory.
Find EOQ,
If the company gets 5% discount if it places the single order at the first instant , should the
accept the order.
Q 1. List the difference in the understanding of small “q” and big “ Q”.
o MBQNA Awards.
o Deming prize.
o Balbridge Awards