Installation and Operating Instructions R.O.C.O.F Protection Relay
Installation and Operating Instructions R.O.C.O.F Protection Relay
Installation and Operating Instructions R.O.C.O.F Protection Relay
http://energy.tycoelectronics.com
Tyco Electronics UK Limited Crompton Instruments Freebournes Road, Witham, Essex, CM8 3AH, UK Tel: +44 1376 509 509 Fax: +44 1376 509 511
Crompton Instruments Freebournes Road Witham Essex CM8 3AH England Tel: +44 (0) 1376 509 509 Fax: +44 (0) 1376 509 511 E-Mail: crompton.info@tycoelectronics.com
Issue 1 11/2002
Page
1 4 5 6 6/7 7
Section 2 Technical
Theoretical considerations Product internal function Vector Shift and R.O.C.O.F Limits of operation Full specification Product construction 8 9 14 15 16 17
Section 3 Interfacing
Installation instructions EMC instructions Low Voltage Directives Interface diagram 119 Fusing recommendation Output protocol 19 19/20 18 18 18
Section 1
Introduction
This product is designed for applications where a generator is running parallel with a mains supply either from a utility or other generators. This protection relay is specifically designed to protect the mains from the potential damaging effects of asynchronous generator output. It is designed to detect disconnection of a generator from the network and trip the generators circuit breaker. For optimum safety each generator should have its own protection relay. This relay senses a Vector shift and a Rate Of Change Of Frequency (R.O.C.O.F) as measurement parameters as part of UK Utilities recommendations G.59/1 and ETR 13.
1.
This product is intended to be used with gensets. The applications for gensets can be grouped as follows:Single stand alone use: Standby Emergency replacement for (part) load supply (UPS) Mobile Independent Temporary local islanded load supply Full time local islanded load supply with optional CHP
Networked use: Co-generation Multiple gensets connected together, or Single or multiple gensets connected to a Utility grid. Full or part time running, connected to or switching over from the Utility supply. Full time base load supply, via Utility connection Part time peak load supply, via Utility connection Full time load supply, normally via Utility connection with waste heat recovery.
Uninterruptible Power Supplies (UPS) Base Load Peak lopping Combined Heat and Power (CHP)
2.
This protection relay is intended to be used with networked gensets as listed above. In this application, the gensets used are connected to the Utility grid at least part time, and therefore require the specific protection provided by this relay as explained below. Due to a lightening strike or other fault on the network the automatic reclosers on the network line will disconnect momentarily to clear this fault. During this fault clearing period the islanded generator will drift slightly out of synchronism with the grid. Having cleared the fault, which may take less than a second, the auto reclosers would then attempt to reconnect the grid to an unsynchronised genset. Other faults may occur on the network, but however long the fault clearing process takes, it is clearly important to have high speed detection of the genset having become islanded.
3.
The genset attempts to keep the remains of the network and the attached load live. The remaining load may be too large for the genset to handle and instability may occur, which may damage certain loads. Personnel working on the lines would be subject to the hazards from a live genset in the area. When faults have been cleared, the network would be connected to an out of synchronism genset, with damaging results.
4.
Utilities require that their approval be given before the gensets are connected to the grid, and that protection devices with known performance are installed. Requirements vary with countries and with application.
5.
When a genset becomes islanded, the output voltage and frequency do not necessarily change a large amount: this will depend on the remaining load size relative to the generator capability. Therefore voltage and frequency relays cannot be relied upon.
6.
The loss of mains relay should detect a shift in phase between generator and the supply. This phase angle should be less than the angle used when synchronising the generator. Additionally, allowance must be made for time taken for the circuit breaker to have moved into the open position, and consideration should be given to the time it takes for the auto recloser to have completed its reclosing process.
7.
Preferred methods of detection of loss of mains are Rate Of Change Of Frequency and Vector Shift.
8.
The Vector shift relay measures the length of each cycle of the voltage wave. At the moment a genset becomes disconnected, the sudden change in load causes a sudden change in cycle length. The single cycle becomes shifted with time: it takes longer or shorter. The speed of sensing is fast enough to complete the opening of the genset main circuit breaker before the auto recloser completes reclosing. Hence the Vector shift relay is an excellent method of detecting disconnection from the gird.
9.
The R.O.C.O.F. relay senses stability of the frequency. A genset in routine operation will have a normal frequency excursion due to changing loads and the compensated fuel inlet. These frequency excursions are small. The rate at which the frequency changes inside these excursions is relatively high compared with those of a large network. The speed of sensing is fast enough to complete the opening of the genset main circuit breaker before the auto reclosers complete reclosing. Hence a R.O.C.O.F. relay adjacent to the genset is also an excellent method of detecting disconnection from the grid.
Benefits
G
For G59 duty. Professional, small, economical, versatile. Simple to install and operate Permits fast, reliable and accurate mains failure detection to protect grid, load, and the generator. Provides continuous supervision; simultaneously using both vector shift and rate of change of frequency functions in one unit, which monitor power quality and disconnections. Improved discrimination between operational switching effects and true grid disconnections. Fault values, which caused a trip, may be accurately read using the data output. Special advanced algorithm, design to avoid nuisance trips.
Features
Specifically designed to comply with Utility requirements, G.59/1, ETR 113, and other recommendations and approvals.
G
Unique new algorithm. Continuous self supervision. Controlled power up/down. Status and fault indication. Digital data and status output. Status LEDs show: Mains on, Vector trip, R.O.C.O.F trip, near trip. Input live and being monitored. 2 to 24 phase shift. 0.1 to 1Hz R.O.C.O.F Remote health check indication and reset feature. Continuous monitoring for phase steps and rate of change of frequency. Separate LEDs to indicate type of trip: Vector (=phase step) or rate of change of frequency. Internal self check functions control the LED marked Self Test OK and the health status output relay. On detection of any of the following, this LED will go out and this relay will move to the not ready state: input signal level too low to support valid measurements auxiliary supply too low to support operation of the unit either of the two watchdog circuits timing is out detection of an internal maths error condition, possibly as a result of the input frequency being too high. External input to inhibit (holding off) the operation of the unit until other external monitoring or control functions have stabilised e.g. generator has synchronised and been connected to the grid. Changeover relay contacts to indicate that the unit is monitoring the input signal. Changeover relay contacts to indicate that the unit has detected signal conditions causing a trip.
User selectable delay of 2-12 seconds starts after; a) unit completion of self test and initialisation routine and/or b) release of the hold off function provided by the inhibit terminals. (whichever is the latest). User selectable setting of phase step (vector shift) from 2 to 24 with a resolution of better than 2 using the data output. User selectable setting of rate of change of frequency from 0.1 to 1.0 Hz/second in 0.05 Hz/second steps (visible using the data output). Fibre optic output for software display of:Waveform Frequency Vector shift set point Vector shift value when trip occurred R.O.C.O.F. set point Present R.O.C.O.F. value (i.e. this acts as a R.O.C.O.F. meter) R.O.C.O.F. value when trip occurred
Models Available
Model No. 256-ROCL or 246-ROCL may be ordered having one of the following standard voltages: 110, 120, 220, 230, 240, 380, 400, 415. Exceptionally, any voltage in the range 63 to 480V will be considered. This model covered the frequency range of 40 to 70Hz.
Order Code:
256 ROCL 246 ROCL Please also supply the Voltage requirement, bearing in mind this relay can be connected Line to Neutral, but preferably should be connected Line to Line.
Dimensions
Section 2
Technical Theoretical Considerations The Vector Shift Concept
Any generator may be represented by an Ideal Generator i.e. a generator with a source impedance of zero, and an equivalent series impedance (See Figure 1). When operating at no load the signal at the output terminals of the generator will be identical to that of the ideal Generator. However, when a load is applied there will be a voltage drop and attendant phase shift across the series impedance.
When paralleling a generator to the mains supply it is necessary to ensure that the Output voltage of the generator (by definition at no load) and the voltage of the mains are equal to within close limits, and that the phase of the two waveforms (which includes frequency) is similarly equal to close limits, at the instant of connection very little current flows. In order for the generator to deliver power to the mains, current must flow in the series impedance resulting in a phase shift (Vector Shift) of the signals between the mains and the Ideal Generator. It may now be seen that if the mains is removed and the generator experiences a relatively large change in load (in either direction) then there will be a near
instantaneous change in the phase shift across the series impedance of the generator. See fig 3. The equivalent series impedance and resultant phase step magnitude versus load changes may be calculated if the generator characteristics are known but this is beyond the scope of this document. This protection relay continually monitors the phase of the signal waveform compared with that of preceding samples and looks for the instantaneous change in phase. The unit can produce a signal to disconnect the generator from the mains within two cycles of the signal waveform. On start up, the unit trip circuit may be inhibited for a period to allow for synchronising and stabilising of the system after initial paralleling using either the inhibit connections or simply setting the delay timer.
The microprocessor holds 32 consecutive periods in a cyclic butter from which it determines the present average period of the incoming waveform called the current average. Each cycle of the square wave signal is compared with the current average and any deviations from the average which exceed the limits determined by the vector shift setting read from the front panel potentiometer will initiate a potential vector shift trip. The unit will wait for the next period of the input waveform to qualify the vector shift trip. There are a number of possible conditions, which determine the qualification of a vector shift, but basically these may be summarised as:A vector shift will be confirmed if a change in input waveform period is present for not more than one cycle and that the period of the waveform after the disturbance has returned to the average period as calculated before the disturbance.
10
After checking for vector shifts the unit will use the cyclic buffer contents to calculate the rate of change of frequency of the input waveform. The calculated rate of change of frequency is compared with the set point as determined by the front panel potentiometer. The front panel contains a further potentiometer marked delay. The position of the potentiometer determines the period from the end of the initialisation sequence or release of the inhibit function (whichever is the latter) before which the vector shift and R.O.C.O.F. detection is enabled. It must be emphasised that this is not a delay from the detection of phase step to relay operation the unit is designed to have a fast response hence there would be little point in introducing a variable delay into the process. The delay is intended to permit the use of the unit in situations where a delay is required from an external event, e.g. generator synchronised to the mains, before monitoring is enabled.
11
Initialisation
The initialisation period for the unit will require a minimum of 64 cycles of the input waveform to flush the cyclic buffer and averaging routines. The unit will not detect a trip condition during this initialisation period.
R.O.C.O.F. Trip
This LED will illuminate whenever the unit detects a rate of change of frequency trip. The LED will remain illuminated and the trip relay will remain energised until one of the following conditions is met. 1. 2. 3. Auxiliary supply removed (and returned). Signal removed (and returned). External reset terminals shorted together. Reset button held down until self test OK LED extinguishes.
12
Reset Switch
The reset button, when held depressed will cause the unit to restart. The switch operates by forcing the watchdog to time out and thus provides a natural defence against inadvertent operation, the switch must be held depressed for the full term of the watchdog timer. A momentary operation of the switch will be ignored. Successful operation is identified by the SELF TEST OK will extinguish when the unit restarts. If the reset switch is held depressed the front panel LEDs will illuminate periodically as the unit attempts to restart.
Inhibit Contacts
Inhibit input is marked CONTROL on unit. The inhibit contacts provide a mechanism for preventing the unit from detecting vector shift or rate of change of frequency trips. It must be emphasised that these contacts are not isolated from the units terminal power supply and thus only Basic Insulation is provided from both auxiliary and signal connections. Connecting these terminals together through an impedance of less than 1k ohm prior to resetting the unit will disable the detection of signal trip conditions until the contacts are released (greater than 10k ohm). NOTE: If the contacts are connected together after the self test OK LED has illuminated will have no effect. The unit only uses this signal at power up. The self test OK LED will not illuminate until the inhibit terminals are released (impedance of greater than 10k ohm) and the delay period has expired.
13
R.O.C.O.F (Hz/Second)
0.05 0.1 0.15 0.25 0.30 0.35 0.40 0.45 0.50 0.55 0.60 0.65
What this means is that for each of the R.O.C.O.F trip level settings in column one, the corresponding Phase Step values in column two should not be exceeded. This general rule need not be adhered to. If it is not adhered to, then a trip, which shows up as R.O.C.O.F. may in fact have been Vector Shift.
14
Limits of Operation
As previously mentioned there is a low pass filter in the input stages to the product to reduce the susceptibility to interference. One effect of this filter is that it slows down the fast edges associated with any vector shift. For very large vector shifts this filter may cause the vector shift to spread across two cycles of the waveform, and, as described above, the vector shift qualifying algorithm will reject the vector shift if two consecutive cycles exhibit period which exceed the vector shift limit determined by the front panel potentiometer. In the majority of applications this effect is unlikely to cause any problems, however, the maximum vector shift which can be reliably detected when the unit is set to its maximum sensitivity of 2 is 50. Note: This characteristic is valid for 50Hz operation, for other frequencies please contact Crompton Instruments.
15
RESOLUTION:
Delay Range: 0.1s Phase angle shift: 0.5 at 50/60Hz Frequency rate change: 0.1Hz/s PHYSICAL: Vibration: Housing:
Burden: Overload:
BSEN60068-2-6 256 DIN rail or surface mount; 70mm (h), 150mm (w) 112.5mm (d) Weight: 0.8kg
OUTPUT:
Relays: Contacts: Rating: Operations:
USER ADJUSTMETNS: Initial auxiliary supply switch-on delay (supervision delay): 1 to 10s Phase angle shift: 2 to 24. Frequency rate change: 0.1 to 1Hz/s REMOTE CONTROL: Reset:
PERFORMANCE:
Setting Accuracy: Vector Shift better than 1 R.O.C.O.F 0.05 Hz/s Temperature Range: 0 to 50C normal -10 to 50C extended Performance may not meet published specification but the unit will not sustain permanent damage in this range Storage Temperature: -10 to +70C Response time: Phase angle shift: up to 2 cycles +5ms relay time Frequency rate change: 3 to 32 cycles +5ms relay time Isolation: BS 142, Section 1.3 Safety: BSEN61010 1993 AMD 8961 1996 EMC: BSEN 50081-2 emission BSEN 50082-2 immunity
Interrupt auxiliary supply, press reset button or c onnect remote reset contacts For switch-on delay >10s close inhibit contacts
Inhibit:
INDICATORS: Green:
Yellow: Red:
1. Auxiliary on 2. Unit active, switch on delay expired on self test OK Near trip 1. Vector trip and relay energised 2. R.O.C.O.F. trip and relay energised.
16
Model 256
The protection relay is housed in an industry standard DIN and surface mount ABS case. Only one PCB is used, which holds all the electronic components as well as the transformers and relays. To enable this efficient use of space, a double sided PCB is used, which contains the EMC screening. The microprocessor is fitted in a plug-in socket which makes for convenient updating of the software to later issues if the system expansion makes this desirable. The contraction is strong and rigid, in line with other Crompton Instruments protection relays, and is ideal for mounting in a floor standing or wall hanging panel rather than fitting onto the generator itself.
17
Section 3
Interfacing
Installation
For reliable operation the units signal connections should be connected as close to the generator as is practical. The unit uses the vector shift produced by the generators characteristic impedance when the generator load changes. Any additional impedance introduced by bus bars etc., which could introduce vector shifts during normal operation (not mains failure) should be avoided in the connection to the unit as it may be necessary to de-sensitise the vector shift trip point to avoids nuisance trips.
EMC Instructions
While all practical measures have been taken to avoid the susceptibility to Radio Frequency Interference (R.F.I) when used in particularly noisy environments, consideration must be given to providing a screened environment for the product. The unit has been designed to comply with Industrial Immunity Specification EN 50082-2, to withstand voltage surges of 4kV peak and to comply with the limits of emissions detail din EN50081-2. It is recommended that external Surge Suppression Barriers are introduced into the Auxiliary and Signal connections in situations where 4kV surges are anticipated, as a guide the surge protection barrier should limit the output voltage to 2kV. The Inhibit and Reset connections are not electrically isolated from one another and should be connected using cable incorporating a common screen to prevent differential signals entering the unit along these lines. The screened cable used for the Inhibit and Reset connections should be segregated from sources of electrical noise.
18
Interface Diagram
Fusing Recommendation
The unit does not have internal fuses therefore external fuses must be used in the auxiliary and signal connections for safety protection under fault conditions. The peak input current for the auxiliary may be calculated using the expression: Peak Current (Amps) = 33 / Nominal Voltage. This peak current will decay exponentially over approximately 10 cycles of the auxiliary supply. The peak input current for the signal is not affected by a start-up period it is determined from the signal burden.
19
Where each of the characters A to F indicated above may be any of the hexadecimal characters 0 through to F.
1.
The first line represents the present period between consecutive rising edges, to change this to the value of the frequency of the Signal input, convert the number to hexadecimal, multiply by 0.5E-06 and reciprocate: Frequency (Hz) = 1/Hex (AAAA) * 0.5E-6)
2.
The second line represents the setting of the Vector Shift potentiometer, to change this number to degrees, divide it by the present period and multiply by 360: Vector Shift Setting (Degrees) = (Hex(BBBB)/Hex(AAAA)) * 360
3.
The third line will remain at zero until the unit trips on a phase step, at this point it will contain the period of the cycle which caused the trip. To change this number to the phase step in degrees, subtract the present period, divide the result by the present period and multiply by 360. Phase Step Trip value (Degrees) = ( (Hex (CCCC) Hex (AAAA)) / Hex (AAAA) * 360
4.
The fourth line represents the current Rate of Change of Frequency in 0.05 Hz/Second increments. To change the number to the rate of change of frequency in Hz/second multiply by 0.05. R.O.C.O.F (Hz/Second) = Hex (DDDD) * 0.05
5 .
The fifth line represents the setting of the R.O.C.O.F. potentiometer in 0.05 Hz/second increments. To change the number to rate of change of frequency in Hz/second multiply by 0.05. R.O.C.O.F. Limit Setting (Hz/Second) = Hex(EEEE) * 0.05
6.
The sixth line will be zero until the unit trips on the rate of change of frequency at this point it will contain the rate of change of frequency at which the unit tripped in 0.05 Hz/second increments. To change the number to the rate of change of frequency in Hz/second multiply by 0.05. R.O.C.O.F. Trip Value (Hx/second) = Hex(FFFF) * 0.05
20
The Information contained in these installation instructions is for use only by installers trained to make electrical power installations and is intended to describe the correct method of installation for this product. However, Tyco Electronics has no control over the field conditions which influence product installation. It is the user's responsibility to determine the suitability of the installation method in the user's field conditions. Tyco Electronics' only obligations are those in Tyco Electronics' standard Conditions of Sale for this product and in no case will Tyco Electronics be liable for any other incidental, indirect or consequential damages arising from the use or misuse of the products. Crompton is a trade mark.
Tyco Electronics UK Limited Crompton Instruments Freebournes Road, Witham, Essex, CM8 3AH, UK Tel: +44 1376 509 509 Fax: +44 1376 509 511
http://energy.tycoelectronics.com