Planning Package For Project
Planning Package For Project
Planning Package For Project
SHEET [ CRS ]
CONTRACT NUMBER
GC11106200
CONTRACT TITLE
EDL/GC11106200/EXT/TN/0107
DATE
19/7/2012
DOCUMENT NUMBER
DOCUMENT TITLE
3392-00-69-00-0003
DOCUMENT REVISION
QP PROJECT NUMBER
3392
Engineering
No.
QP COMMENTS
CONTRACTOR RESPONSE
Page 1 of 6
COMMENTS RESOLUTION
SHEET [ CRS ]
CONTRACT NUMBER
GC11106200
CONTRACT TITLE
EDL/GC11106200/EXT/TN/0047
DATE
19/7/2012
DOCUMENT NUMBER
DOCUMENT TITLE
3392-00-69-00-0003
DOCUMENT REVISION
QP PROJECT NUMBER
3392
Schedule
No.
QP COMMENTS
CONTRACTOR RESPONSE
Done
Please clarify the duration allowed and basis of assumption for the
pipeline precomm activities for 60 days??
Page 2 of 6
COMMENTS RESOLUTION
SHEET [ CRS ]
CONTRACT NUMBER
GC11106200
CONTRACT TITLE
EDL/GC11106200/EXT/TN/0047
DATE
19/7/2012
DOCUMENT NUMBER
DOCUMENT TITLE
3392-00-69-00-0003
DOCUMENT REVISION
QP PROJECT NUMBER
3392
Schedule
No.
4
QP COMMENTS
CONTRACTOR RESPONSE
Page 3 of 6
COMMENTS RESOLUTION
SHEET [ CRS ]
CONTRACT NUMBER
GC11106200
CONTRACT TITLE
EDL/GC11106200/EXT/TN/0047
DATE
19/7/2012
DOCUMENT NUMBER
DOCUMENT TITLE
3392-00-69-00-0003
DOCUMENT REVISION
QP PROJECT NUMBER
3392
Progress measurements
No.
1
QP COMMENTS
CONTRACTOR RESPONSE
No.
1
QP COMMENTS
CONTRACTOR RESPONSE
Contractor has not provided the Late curves as per the item #2 under the
section Progress Curves and histogram (Previous QP comments)
Page 4 of 6
Done
COMMENTS RESOLUTION
SHEET [ CRS ]
CONTRACT NUMBER
GC11106200
CONTRACT TITLE
EDL/GC11106200/EXT/TN/0047
DATE
19/7/2012
DOCUMENT NUMBER
DOCUMENT TITLE
3392-00-69-00-0003
DOCUMENT REVISION
No.
QP PROJECT NUMBER
3392
QP COMMENTS
CONTRACTOR RESPONSE
Procurement
It is advised adopt the wt factor allowed for individual line item under
the procurement based on the overall value of procurement rather
than based upon long lead and other item individually ( however long
lead /Bulk item category shall be retained as it is ) .
Done
Done
Page 5 of 6
COMMENTS RESOLUTION
SHEET [ CRS ]
CONTRACT NUMBER
GC11106200
CONTRACT TITLE
EDL/GC11106200/EXT/TN/0047
DATE
19/7/2012
DOCUMENT NUMBER
DOCUMENT TITLE
3392-00-69-00-0003
DOCUMENT REVISION
QP PROJECT NUMBER
3392
Construction
No.
QP COMMENTS
CONTRACTOR RESPONSE
Done
Some point was taken into consideration:
Page 6 of 6
Page 1 of 266
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
METHOD STATEMENT FOR PROJECT
CONTROL
______________________________________
Page 2 of 266
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
July 19,2012
PLANNING PACKAGE
CONTENTS
Page 3 of 266
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
PLANNING PACKAGE
Page 4 of 266
DATE
July 19,2012
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
July 19,2012
PLANNING PACKAGE
1. Introduction
This method statement outline the procedure and requirements of the progress measurement
methodology and control for the project EPIC of 16" - 36 km Jet A1 Fuel Pipeline from the QP
refinery to BSV-3 .
2. Purpose
The purpose of this method statement is to ensure that the project schedule will be monitored and
implemented on time without any delay according to appendix-H as the following dates : Contract Effective Date : Feb 26,2012
Achieve Mechanical Completion of Pipeline and all Facilities : Nov 25,2013.
Milestone (1) : Achieve Commissioning of Pipeline and All Facilities : May 25,2014 .
Complete Baseline Survey (Optional) : July 25,2014
Scheduled Project Completion :Aug 25,2014 (30-Months from the Effective Date)
3. Project Control
3.1 General
Petrojet will develop comprehensive project control procedures and detailed plans based upon
the Appendix-H of the contract and Appendix-D (Attachment D-3) of the contract .
It is the responsibility of the project control to identify the scope of the work in complete details
and project control will support the project in order to ensure its completion on time by the
following functions :
Highlight the Milestones for the project , highlight the interfaces of the project with
others.
Close coordination and monitoring of sub-contractors and suppliers progress of works for
their scope through an agreed progress reporting mechanism .
Detecting any obstacle which may affect the planned dates/cost, studying the situation,
and determining both the best solution and any corrective action which will ensure that the
baseline end date of the project is met without any deviation .
Analysis Assuring that the project progress is occurring in accordance with the approved
time schedule .
Page 5 of 266
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
July 19,2012
PLANNING PACKAGE
Using a specialized software Primavera Version 6.7 to provide electronic schedules that
can be used in either electronic or printout forms to illustrate planning information, look
ahead/behind schedules, etc.
Petrojet project control, as deliverables will issue ninety days lookahead schedule and within the
time specified in the contract , will develop Comprehensive Project Planning Package which
will form the basis for the monitoring of the works .
The Planning Package will be submitted to QP for approval and once approved will be used as
the basis of progress monitoring .
To retain the consistency on progress reporting , the weight factors shall not be modified during
the course of the contract .
3.2 Integrated Planning Network
Petrojet project control will establish a comprehensive time schedule using primavera P6 . the
schedule will be resource loaded . The total project schedule will be fully integrated showing
all activities more than 1000 activities - related to engineering, procurement, construction,
pre-commissioning, commissioning in addition to the optional items .
The CPM network will include all aspects of the work and will be sufficiently detailed to the
satisfaction of the QP representative . Detailed activities of the work/service will include all
parties, vendors and sub-contractors necessary to complete the works .
3.3 Progress Measurement
Petrojet project control will develop, maintain and update a computerized progress
measurement system . the progress measurement system will enable monitoring and follow-up
of progress (actual versus planned) for all activities performed by Petrojet.
The progress will be calculated from the lowest control level and electronically rolled up to the
upper levels .
The progress basis shall be as the following : The engineering progress will be Milestone progress and based on the estimated manhours that will be related to the engineering document register (EDR).
The procurement progress will be Milestone progress and based on the cost that will be
related to the procurement status register (PSR) .
Page 6 of 266
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
July 19,2012
PLANNING PACKAGE
The construction progress will be based on the estimated man-hours/efforts that will be
exported from Primavera time schedule to the progress control Excel sheets.
The pre-commissioning and commissioning progress will be based on the manhours/efforts that will be exported from Primavera time schedule to the progress control
Excel sheets .
The progress of optional items (Laying new FOC, Kahrama option (1) and the Baseline
survey) will be based on the man-hours/efforts that will be exported from Primavera
time schedule to the progress control Excel sheets .
5%
Procurement
40 %
Construction
48 %
5%
Optional Items
2%
-----------------------------------------------------------------------------------------------------------------------------The Engineering progress chain milestones will be according to the contract as the following : Started
5%
Cumulative
5%
35 %
Cumulative
40 %
25 %
Cumulative
65 %
20 %
Cumulative
85 %
10 %
Cumulative
95 %
Issue As Built
5%
Cumulative
100 %
Equipment
5%
Cumulative
5%
5%
Cumulative
10 %
5%
Cumulative
15 %
15 %
Cumulative
30 %
10%
Cumulative
40%
Page 7 of 266
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
July 19,2012
PLANNING PACKAGE
20%
Cumulative
60 %
Ex-Works Delivery
10 %
Cumulative
70 %
15 %
Cumulative
85 %
5%
Cumulative
90 %
10%
Cumulative
100 %
5%
Cumulative
5%
10 %
Cumulative
15 %
15 %
Cumulative
30 %
10 %
Cumulative
40 %
10 %
Cumulative
50 %
30 %
Cumulative
80 %
20 %
Cumulative
100 %
B)
Bulk Material
Page 8 of 266
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
July 19,2012
PLANNING PACKAGE
The reports will be generated from the day of commencement of ROW activity. This report
will be indicating quantitative scope and the progress achieved daily and the cumulative
progress in terms of quantity and percentage in addition to the planned quantity for each
activity.
The report will include the progress achieved in all disciplines in both pipeline and QP
refinery. This report will indicate the weather conditions.
4.3 Weekly Reports
The Weekly Progress Report (WPR) will be submitted covering all activities under each
phase during the entire duration of the contract.
The report will be generated on weekly basis with progress cut-off every Thursday. Hard and
soft copy of this report will be officially submitted to QP.
The contents of the WPR will be as per the Appendix D (Attachment 3 Clause 4.3).
4.4 Monthly Reports
The Monthly Progress Report (MPR) will be submitted during the entire duration of the
contract within 3 working days from the cut off date, Last weekly cut off-date in a calendar
month will be treated as monthly as agreed with QP.
The contents of the MPR will be as per the Appendix D (Attachment 3 Clause 4.6) .
4.5 Engineering Document Register
The Engineering Document Register (EDR) will be submitted as part of the planning
package.
Once approved it will be used as the main tool for monitoring the progress of the engineering
deliverables .
Updated engineering document register (EDR) will be submitted along with the weekly
progress report. The register will be updated on weekly basis with progress cut-off every
Thursday.
All deliverables will be listed and will be monitored as per agreed percentage weightings .
The register will serve as a tool in registering, planning, tracking, monitoring, expediting and
reporting the status of all engineering deliverables .
Page 9 of 266
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
July 19,2012
PLANNING PACKAGE
Invoicing
The monthly invoice will be prepared and issued based on the following : Invoice will be submitted on monthly basis .
All the standard invoicing formats will be used .
Page 10 of 266
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
July 19,2012
PLANNING PACKAGE
The cut-off date of the monthly progress report will be used as the same cut-off date
for the invoicing .
Advanced copy of draft invoice will be submitted to QP by email prior to official
issuance .
The supported document for the monthly invoice will be the engineering document
register, Procurement different Documents and the approved construction verification
sheet .
The monthly progress payment will be submitted to QP thru an official letter .
6. Cost Control
The purpose of the Project Cost Control System is to provide the Project Manager with a
status of the Project with respect to the financial budget .
For this reason the cost control engineer will perform the following:
Coordinate change control program, as required and initiate change identification and
develop approximate cost impact to serve as decision making tool. Follow up with
more detailed estimate to meet Project and contractual requirements.
Maintain cost and commitment data to assist in forecasting.
Monitor Sub-contractors costs. Update forecast for each subcontract as variances are
identified through the change control program.
Prepare monthly cost control report.
7. Project Calendar
The Progress Review Meeting will be held on weekly basis on Monday .
The Weekly Progress Report will be submitted every Sunday .
The Monthly Progress Report will be submitted on the first Sunday of the month.
The Monthly Invoice for the achieved works will be submitted during the first week
of the month.
Achieve Mechanical Completion of Pipeline and all Facilities : (21) Months.
Milestone (1) : Achieve Commissioning of Pipeline and All Facilities : (27) Months .
Scheduled Project Completion : (30) Months from the Effective Date
Page 11 of 266
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
PLANNING PACKAGE
8. References
Appendix A:
Scope of Work.
Appendix B:
Schedule of Prices
Appendix D:
Administration Instruction
Appendix F:
Appendix H:
Page 12 of 266
DATE
July 19,2012
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
WORK BREAK DOWN STRUCTURE
______________________________________
Page 13 of 266
Document Description
Date
Issued For
GC 11106200
July 19,2012
ETROJET
100.00%
ENGINEERING
PROCUREMENT
CONSTRUCTION
PRECOMMISSIONING &
COMMISSIONING
OPTIONAL
5.00%
40.00%
48.00%
5.00%
2.00%
GENERAL
=4.65%
PROCESS
=6.42%
LOSS PREVENTION
=1.44%
FIRE & GAS
=6.77%
PIPELINES
=8.55%
MECH/PIPING
=10.76%
INSTRUMENTATION
=10.36%
TELECOMMUNICATION =1.00%
ELECTRICAL
=16.88%
CIVIL & STRUCTURAL
=28.21%
BUILDING & SERVICES =2.26%
CATHODIC PROTECTION =2.70%
____________________________
TOTAL
=100%
BULK MATERIALS
PIPELINE FROM QP
REFINERY TO BSV-3
QP REFINERY
BSV-3
77.25%
22.75%
47.75%
46.88%
5.37%
PIG LAUNCHER
=1.44%
EOT CRANE
=2.27%
JIB CRANE
=0.62%
MAINLINE PUMPS
=28.33%
BOOSTER PUMPS
=15.75%
SWITCHGEAR PANELS =12.11%
DISTRIBUTIONBOARDS =0.31%
UPS SYSTEM
=1.18%
CONTROL VALVE
=2.73%
ESD VALVE
=0.57%
ISOLATION VALVES
=0.47%
MOV
=5.49%
ALL OTHER VALVES
=2.85%
CORIOLLIS FLOWMETER =3.22%
JUNCTION BOXES
=1.29%
FIRE DETECTORS
=0.93%
SCADA
=16.79%
TELECOM EQUIPMENS =0.33%
LEAK DETECTION SYSTEM=3.31%
___________________________
TOTAL
=100%
STRAIGHT RUN
=63.85%
OPEN CUT CROSSING =8.43%
HDD CROSSING
=13.29%
CATHODIC PRPTECT. =4.22%
ANCHOR BLOCK
= 1.90%
HYDRAULIC TEST
=4.75%
COMMON ACTIVITIES=3.56%
________________________
TOTAL
= 100%
Page 14 of 266
CIVIL WORKS
=49.64%
MECH. WORKS
=34.38%
E&I WORKS
= 15.98%
________________________
TOTAL
= 100%
CIVIL WORKS
=25.71%
MECH. WORKS
=18.57%
E&I WORKS
= 55.72%
________________________
TOTAL
= 100%
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
INTEGRATED PLANNING NETWORK
______________________________________
Page 15 of 266
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
781
26-Feb-12
25-Aug-14
18-Jan-12
25-Aug-14
651
26-Feb-12
25-Aug-14
18-Jan-12
25-Aug-14
911
26-Feb-12
25-Aug-14
26-Feb-12
25-Aug-14
26-Feb-12
GCM1100
GCM1110
25-May-14
25-May-14
25-Aug-14
25-Aug-14
GCM1120
GED1100
GED1110
GED1120
26-Feb-12
Total
Float 2012
28-Mar-12
26-Aug-12
16-Apr-12
15-Sep-12
17
Project Management
Documents (PL. PKG.,HSE
Plan,PQP,Etc.)
Cost Break Down
90
28-Mar-12
14-Jul-12
16-Apr-12
01-Aug-12
17
20
20-May-12
13-Jun-12
09-Jun-12
02-Jul-12
17
75
29-May-12 26-Aug-12
17-Jun-12
15-Sep-12
17
110
04-Mar-12
05-Aug-12
18-Jan-12
09-Sep-12
26
04-Mar-12
07-Mar-12
18-Jan-12
24-Jan-12
-31
26-Apr-12
14-May-12
03-Jul-12
49
GMOB1100
GMOB1110
TCF To Be Established
36
07-Mar-12
GMOB1120
48
29-May-12 05-Aug-12
03-Jul-12
09-Sep-12
26
193
27-Mar-12
24-Jan-12
25-Aug-14
563
Engineering Phase
Actual Work
Critical Re...
Remaining Work
Milestone
06-Nov-12
PETROJET CO
Page 16 of 266
2014
127
Mobilization
2013
J
Date
19-Jul-12
Revision
Rev(5)
Checked
Y.Abdalshaf...
Approved
21-Jul-12 22:12
Activity Name
General
EGN-1000
Original
Duration
Early Start
114
27-Mar-12
Early Finish
03-Sep-12
Late Start
24-Jan-12
Late Finish
02-Aug-12
27-Mar-12
EGN-1010
18
27-Mar-12
EGN-1080
22-Apr-12
19-Feb-12
-45
EGN-1130
03-Sep-12
02-Aug-12
-22
192
28-Mar-12
06-Nov-12
21-Feb-12
25-Aug-14
563
106
08-Apr-12
02-Sep-12
21-Feb-12
20-Nov-12
57
24-Apr-12
26-Apr-12
21-Feb-12
23-Feb-12
-45
Common
19-Apr-12
24-Jan-12
16-Feb-12
-45
EGN-1030
46
29-Apr-12
01-Jul-12
26-Feb-12
29-Apr-12
-45
EGN-1040
73
16-Apr-12
25-Jul-12
15-Mar-12
25-Jun-12
-22
EGN-1050
76
08-Apr-12
22-Jul-12
07-Mar-12
20-Jun-12
-22
EGN-1110
42
05-Jul-12
02-Sep-12
23-Sep-12
20-Nov-12
57
86
29-May-12 25-Sep-12
29-May-12
25-Aug-14
499
67
29-May-12 29-Aug-12
29-May-12
25-Aug-14
518
54
29-May-12 12-Aug-12
29-May-12
12-Aug-12
Reports
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 17 of 266
2014
-45
EGN-1020
Process
2013
J
-22
Detail Engineering
24-Jan-12
Total
Float 2012
Date
19-Jul-12
Revision
Rev(5)
Checked
Y.Abdalshaf...
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
50
10-Jun-12
16-Aug-12
15-Jul-12
20-Sep-12
25
47
21-Jun-12
26-Aug-12
21-Aug-12
25-Oct-12
44
45
25-Jun-12
26-Aug-12
23-Jun-14
25-Aug-14
521
46
27-Jun-12
29-Aug-12
13-Sep-12
18-Nov-12
57
83
03-Jun-12
25-Sep-12
03-Jun-12
25-Aug-14
499
44
04-Jun-12
02-Aug-12
03-Jun-12
02-Aug-12
EPR-1110 PFDs
45
03-Jun-12
02-Aug-12
03-Jun-12
02-Aug-12
EPR-1120 P&IDs
13
04-Jun-12
20-Jun-12
03-Jun-12
20-Jun-12
12
21-Jun-12
08-Jul-12
20-May-14
05-Jun-14
499
15-Aug-12
21-Aug-12
14-Jul-14
21-Jul-14
499
10
22-Aug-12
04-Sep-12
21-Jul-14
04-Aug-14
499
15
05-Sep-12
25-Sep-12
04-Aug-14
25-Aug-14
499
83
17-Jun-12
09-Oct-12
16-Aug-12
22-Nov-12
32
65
04-Jul-12
02-Oct-12
11-Sep-12
15-Nov-12
32
45
01-Aug-12
02-Oct-12
13-Sep-12
15-Nov-12
32
Process - Drawings
Lists/Schedules/Reports
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 18 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
45
25-Jul-12
25-Sep-12
11-Sep-12
13-Nov-12
35
47
04-Jul-12
06-Sep-12
11-Sep-12
15-Nov-12
50
68
17-Jun-12
18-Sep-12
16-Aug-12
20-Nov-12
45
51
17-Jun-12
26-Aug-12
16-Aug-12
28-Oct-12
45
51
17-Jun-12
26-Aug-12
16-Aug-12
28-Oct-12
45
51
17-Jun-12
26-Aug-12
16-Aug-12
28-Oct-12
45
51
17-Jun-12
26-Aug-12
16-Aug-12
28-Oct-12
45
51
10-Jul-12
18-Sep-12
10-Sep-12
20-Nov-12
45
48
05-Aug-12
09-Oct-12
17-Sep-12
22-Nov-12
32
48
05-Aug-12
09-Oct-12
17-Sep-12
22-Nov-12
32
48
05-Aug-12
09-Oct-12
17-Sep-12
22-Nov-12
32
44
05-Aug-12
03-Oct-12
17-Sep-12
18-Nov-12
32
46
05-Aug-12
07-Oct-12
17-Sep-12
20-Nov-12
32
105
12-Jun-12
05-Nov-12
24-Jul-12
25-Aug-14
470
79
12-Jun-12
30-Sep-12
24-Jul-12
26-Dec-12
63
Specifications
Specifications
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 19 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
47
12-Jun-12
15-Aug-12
24-Jul-12
27-Sep-12
31
48
03-Jul-12
06-Sep-12
27-Sep-12
04-Dec-12
63
41
05-Aug-12
30-Sep-12
30-Oct-12
26-Dec-12
63
41
05-Aug-12
30-Sep-12
30-Oct-12
26-Dec-12
63
70
14-Jun-12
19-Sep-12
26-Jul-12
17-Dec-12
63
49
14-Jun-12
21-Aug-12
26-Jul-12
03-Oct-12
31
49
14-Jun-12
21-Aug-12
26-Jul-12
03-Oct-12
31
49
14-Jun-12
21-Aug-12
26-Jul-12
03-Oct-12
31
49
14-Jun-12
21-Aug-12
26-Jul-12
03-Oct-12
31
44
22-Jul-12
19-Sep-12
16-Oct-12
17-Dec-12
63
49
14-Jun-12
21-Aug-12
26-Jul-12
03-Oct-12
31
49
14-Jun-12
21-Aug-12
12-Sep-12
20-Nov-12
65
EFG-1120 Horns
49
14-Jun-12
21-Aug-12
12-Sep-12
20-Nov-12
65
52
13-Jun-12
23-Aug-12
25-Jul-12
25-Aug-14
522
42
13-Jun-12
09-Aug-12
25-Jul-12
23-Sep-12
31
Material Requisitions
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 20 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
42
27-Jun-12
23-Aug-12
23-Sep-12
20-Nov-12
63
42
27-Jun-12
23-Aug-12
26-Jun-14
25-Aug-14
522
42
27-Jun-12
23-Aug-12
23-Sep-12
20-Nov-12
63
77
22-Jul-12
05-Nov-12
05-Aug-12
25-Aug-14
470
59
15-Aug-12
05-Nov-12
12-Sep-12
20-Nov-12
11
42
09-Sep-12
05-Nov-12
23-Sep-12
20-Nov-12
11
45
15-Aug-12
16-Oct-12
12-Sep-12
14-Nov-12
21
EFG-1210F&G JB schedule
45
21-Aug-12
22-Oct-12
18-Sep-12
20-Nov-12
21
62
22-Jul-12
15-Oct-12
05-Aug-12
25-Aug-14
485
54
01-Aug-12
15-Oct-12
15-Aug-12
30-Oct-12
11
46
22-Jul-12
23-Sep-12
05-Aug-12
08-Oct-12
11
46
22-Jul-12
23-Sep-12
19-Aug-12
22-Oct-12
21
45
24-Jul-12
24-Sep-12
10-Jun-14
12-Aug-14
491
44
07-Aug-12
07-Oct-12
24-Jun-14
25-Aug-14
491
43
30-Jul-12
26-Sep-12
22-Jun-14
20-Aug-14
495
Common
QP Refinery
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 21 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Reports
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
43
02-Aug-12
01-Oct-12
25-Jun-14
25-Aug-14
495
160
28-Mar-12
06-Nov-12
14-Mar-12
20-Nov-12
10
160
28-Mar-12
06-Nov-12
14-Mar-12
20-Nov-12
10
03-Jun-12
10-May-12
-15
06-Nov-12
20-Nov-12
10
19-Aug-12
09-Oct-12
37
50
21-Jun-12
29-Aug-12
11-Sep-12
20-Nov-12
59
42
28-Mar-12
24-May-12
14-Mar-12
10-May-12
-10
56
09-May-12
25-Jul-12
30-Aug-12
18-Nov-12
82
36
09-May-12
27-Jun-12
30-Aug-12
21-Oct-12
82
51
16-May-12
25-Jul-12
06-Sep-12
18-Nov-12
82
50
17-May-12
25-Jul-12
09-Sep-12
18-Nov-12
82
33
14-May-12
27-Jun-12
04-Sep-12
21-Oct-12
82
50
17-May-12
25-Jul-12
09-Sep-12
18-Nov-12
82
58
29-Apr-12
17-Jul-12
28-May-12
20-Nov-12
90
Calculation
Specifications
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 22 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
55
30-Apr-12
15-Jul-12
29-May-12
14-Aug-12
22
55
30-Apr-12
15-Jul-12
03-Jun-12
19-Aug-12
25
56
29-Apr-12
15-Jul-12
28-May-12
14-Aug-12
22
56
29-Apr-12
15-Jul-12
28-May-12
14-Aug-12
22
53
06-May-12
17-Jul-12
04-Jun-12
16-Aug-12
22
41
07-May-12
02-Jul-12
24-Sep-12
20-Nov-12
101
39
09-May-12
02-Jul-12
07-Jun-12
16-Aug-12
33
39
09-May-12
02-Jul-12
07-Jun-12
01-Aug-12
22
27
09-May-12
14-Jun-12
07-Jun-12
16-Jul-12
22
27
09-May-12
14-Jun-12
12-Jun-12
19-Jul-12
25
27
09-May-12
14-Jun-12
11-Jul-12
16-Aug-12
45
35
05-Jun-12
23-Jul-12
04-Jul-12
24-Sep-12
45
35
05-Jun-12
23-Jul-12
05-Aug-12
20-Sep-12
43
35
05-Jun-12
23-Jul-12
09-Jul-12
27-Aug-12
25
35
05-Jun-12
23-Jul-12
04-Jul-12
22-Aug-12
22
Material Requisitions
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 23 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
35
05-Jun-12
23-Jul-12
04-Jul-12
22-Aug-12
22
35
05-Jun-12
23-Jul-12
04-Jul-12
22-Aug-12
22
35
05-Jun-12
23-Jul-12
04-Jul-12
22-Aug-12
22
05-Jun-12
23-Jul-12
07-Aug-12
24-Sep-12
45
10-Jun-12
23-Sep-12
09-May-12
23-Oct-12
22
46
12-Jun-12
15-Aug-12
13-May-12
15-Jul-12
-22
50
18-Jun-12
26-Aug-12
17-May-12
25-Jul-12
-22
50
18-Jun-12
26-Aug-12
17-May-12
25-Jul-12
-22
44
03-Jul-12
02-Sep-12
03-Jun-12
01-Aug-12
-22
42
05-Jul-12
02-Sep-12
05-Jun-12
01-Aug-12
-22
45
23-Jul-12
23-Sep-12
21-Aug-12
23-Oct-12
22
44
10-Jul-12
09-Sep-12
22-Aug-12
23-Oct-12
32
52
10-Jun-12
20-Aug-12
09-May-12
19-Jul-12
-22
43
05-Jul-12
03-Sep-12
22-Jul-12
19-Sep-12
12
10
10-Jul-12
23-Jul-12
08-Aug-12
22-Aug-12
22
MTO
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 24 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
10
10-Jul-12
23-Jul-12
08-Aug-12
22-Aug-12
22
Mechanical / Piping
115
09-May-12
16-Oct-12
21-May-12
20-Nov-12
25
Specifications
58
24-May-12 13-Aug-12
24-May-12
19-Nov-12
70
50
24-May-12 01-Aug-12
24-May-12
01-Aug-12
44
05-Jun-12
05-Aug-12
02-Jul-12
02-Sep-12
20
44
07-Jun-12
07-Aug-12
18-Sep-12
19-Nov-12
74
52
03-Jun-12
13-Aug-12
03-Jun-12
13-Aug-12
46
29-May-12
31-Jul-12
15-Jul-12
17-Sep-12
34
46
29-May-12
31-Jul-12
15-Jul-12
17-Sep-12
34
46
29-May-12
31-Jul-12
16-Jul-12
18-Sep-12
35
EME-1150 Specs-Gaskets
46
29-May-12
31-Jul-12
16-Jul-12
18-Sep-12
35
46
29-May-12
31-Jul-12
14-Jun-12
19-Aug-12
13
46
29-May-12
31-Jul-12
14-Jun-12
19-Aug-12
13
46
29-May-12
31-Jul-12
14-Jun-12
19-Aug-12
13
46
29-May-12
31-Jul-12
01-Jul-12
03-Sep-12
24
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 25 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
93
03-Jun-12
09-Oct-12
10-Jun-12
20-Nov-12
30
49
17-Jun-12
22-Aug-12
09-Aug-12
17-Oct-12
40
43
11-Jun-12
08-Aug-12
20-Sep-12
20-Nov-12
74
40
10-Jun-12
02-Aug-12
10-Jun-12
02-Aug-12
40
11-Jun-12
05-Aug-12
11-Jun-12
05-Aug-12
47
05-Jun-12
08-Aug-12
02-Jul-12
05-Sep-12
20
42
07-Jun-12
05-Aug-12
10-Jul-12
06-Sep-12
24
42
03-Jun-12
30-Jul-12
15-Jul-12
11-Sep-12
31
42
07-Jun-12
05-Aug-12
25-Jun-12
22-Aug-12
13
42
07-Jun-12
05-Aug-12
10-Jul-12
06-Sep-12
24
42
07-Jun-12
05-Aug-12
16-Jul-12
12-Sep-12
28
44
09-Aug-12
09-Oct-12
17-Sep-12
18-Nov-12
28
109
14-May-12
11-Oct-12
21-May-12
20-Nov-12
28
45
21-May-12
22-Jul-12
15-Jul-12
16-Sep-12
40
41
13-Jun-12
08-Aug-12
24-Sep-12
20-Nov-12
74
Data sheets
Technical Requisitions
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 26 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
44
21-May-12
19-Jul-12
21-May-12
19-Jul-12
44
21-May-12
19-Jul-12
21-May-12
19-Jul-12
45
21-May-12
22-Jul-12
18-Jun-12
19-Aug-12
20
45
20-May-12
19-Jul-12
20-Jun-12
22-Aug-12
24
45
14-May-12
15-Jul-12
18-Sep-12
20-Nov-12
92
45
20-May-12
19-Jul-12
18-Sep-12
20-Nov-12
88
45
20-May-12
19-Jul-12
20-Jun-12
22-Aug-12
24
45
20-May-12
19-Jul-12
18-Sep-12
20-Nov-12
88
44
13-Aug-12
11-Oct-12
19-Sep-12
20-Nov-12
28
41
15-May-12
10-Jul-12
01-Jul-12
27-Aug-12
34
41
15-May-12
10-Jul-12
04-Jul-12
30-Aug-12
37
94
30-May-12
08-Oct-12
12-Jun-12
20-Nov-12
31
44
10-Jul-12
09-Sep-12
06-Aug-12
07-Oct-12
20
52
13-Jun-12
23-Aug-12
10-Jul-12
20-Sep-12
20
44
12-Jul-12
11-Sep-12
08-Aug-12
09-Oct-12
20
Piping Calculations/Schedules/Reports
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 27 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
45
07-Jun-12
08-Aug-12
18-Sep-12
20-Nov-12
74
48
14-Jun-12
20-Aug-12
13-Sep-12
20-Nov-12
66
44
08-Aug-12
08-Oct-12
04-Sep-12
05-Nov-12
20
44
08-Aug-12
08-Oct-12
04-Sep-12
05-Nov-12
20
44
08-Aug-12
08-Oct-12
04-Sep-12
05-Nov-12
20
54
30-May-12 13-Aug-12
12-Jun-12
27-Aug-12
10
51
28-Jun-12
06-Sep-12
10-Sep-12
20-Nov-12
53
115
09-May-12
16-Oct-12
23-May-12
20-Nov-12
25
49
09-May-12
16-Jul-12
23-May-12
31-Jul-12
11
49
09-May-12
16-Jul-12
23-May-12
31-Jul-12
11
49
09-May-12
16-Jul-12
09-Jul-12
16-Sep-12
44
49
09-May-12
16-Jul-12
23-May-12
31-Jul-12
11
51
14-Jun-12
23-Aug-12
28-Jun-12
09-Sep-12
11
51
14-Jun-12
23-Aug-12
28-Jun-12
09-Sep-12
11
50
10-Jul-12
17-Sep-12
24-Jul-12
02-Oct-12
11
Drawings
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 28 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
50
10-Jul-12
17-Sep-12
13-Aug-12
22-Oct-12
25
52
05-Jul-12
16-Sep-12
05-Aug-12
16-Oct-12
22
49
10-Jul-12
16-Sep-12
06-Aug-12
14-Oct-12
20
49
10-Jul-12
16-Sep-12
06-Aug-12
14-Oct-12
20
48
29-Jul-12
02-Oct-12
23-Aug-12
30-Oct-12
20
60
19-Jul-12
10-Oct-12
22-Aug-12
14-Nov-12
25
44
16-Aug-12
16-Oct-12
19-Sep-12
20-Nov-12
25
49
14-May-12
19-Jul-12
12-Sep-12
20-Nov-12
88
19-Jul-12
25-Jul-12
19-Aug-12
03-Sep-12
28
19-Jul-12
25-Jul-12
27-Aug-12
03-Sep-12
28
23-Jul-12
25-Jul-12
19-Aug-12
22-Aug-12
20
109
20-May-12
17-Oct-12
04-Jun-12
25-Aug-14
483
68
24-May-12 27-Aug-12
19-Jun-12
20-Dec-12
83
47
20-Jun-12
23-Aug-12
16-Jul-12
19-Sep-12
19
51
14-Jun-12
23-Aug-12
30-Jul-12
09-Oct-12
33
MTO
Specifications
EIN-1130
EIN-1140
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 29 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
47
20-Jun-12
23-Aug-12
01-Jul-12
04-Sep-12
47
20-Jun-12
23-Aug-12
01-Jul-12
04-Sep-12
47
20-Jun-12
23-Aug-12
01-Jul-12
04-Sep-12
47
20-Jun-12
23-Aug-12
01-Jul-12
04-Sep-12
47
20-Jun-12
23-Aug-12
01-Jul-12
04-Sep-12
47
20-Jun-12
23-Aug-12
01-Jul-12
04-Sep-12
47
20-Jun-12
23-Aug-12
01-Jul-12
04-Sep-12
47
20-Jun-12
23-Aug-12
01-Jul-12
04-Sep-12
EIN-1230
47
20-Jun-12
23-Aug-12
01-Jul-12
04-Sep-12
EIN-1240
47
20-Jun-12
23-Aug-12
15-Jul-12
18-Sep-12
18
EIN-1250
47
20-Jun-12
23-Aug-12
12-Aug-12
16-Oct-12
38
48
24-May-12
30-Jul-12
19-Jun-12
26-Aug-12
19
48
24-May-12
30-Jul-12
19-Jun-12
26-Aug-12
19
EIN-1290
Specification for
Instrument,F&G,Control &
Telecommunication
Cables
Specifications for conditioning
monitoring system ( new UCP)
interface
( as per
Specifications
for design)
Leak
Detection System
Specification for DCS
47
06-Jun-12
09-Aug-12
05-Jul-12
10-Sep-12
22
EIN-1292
48
05-Jun-12
09-Aug-12
04-Jul-12
10-Sep-12
22
EIN-1150
EIN-1160
EIN-1170
EIN-1180
EIN-1190
EIN-1200
EIN-1210
EIN-1220
EIN-1270
EIN-1280
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 30 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
EIN-1295
51
12-Jun-12
21-Aug-12
11-Jul-12
20-Sep-12
22
EIN-1300
52
17-Jun-12
27-Aug-12
04-Oct-12
17-Dec-12
80
52
17-Jun-12
27-Aug-12
09-Oct-12
20-Dec-12
83
59
28-May-12 16-Aug-12
19-Jun-12
21-Oct-12
46
47
28-May-12
31-Jul-12
12-Aug-12
16-Oct-12
55
47
28-May-12
31-Jul-12
15-Aug-12
21-Oct-12
58
47
28-May-12
31-Jul-12
12-Aug-12
16-Oct-12
55
47
28-May-12
31-Jul-12
12-Aug-12
16-Oct-12
55
38
10-Jun-12
31-Jul-12
05-Jul-12
28-Aug-12
20
50
10-Jun-12
16-Aug-12
25-Jun-12
03-Sep-12
12
50
10-Jun-12
16-Aug-12
01-Aug-12
10-Oct-12
39
50
10-Jun-12
16-Aug-12
19-Jun-12
28-Aug-12
EIN-1390
50
10-Jun-12
16-Aug-12
04-Jul-12
11-Sep-12
18
EIN-1400
50
10-Jun-12
16-Aug-12
19-Jun-12
28-Aug-12
100
20-May-12
04-Oct-12
04-Jun-12
20-Nov-12
33
EIN-1305
Data Sheets
EIN-1310
EIN-1320
EIN-1330
EIN-1340
EIN-1350
EIN-1360
EIN-1370
EIN-1380
Material Requisitions
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 31 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
EIN-1680
42
24-May-12
22-Jul-12
08-Aug-12
07-Oct-12
55
EIN-1690
42
20-May-12
16-Jul-12
07-Aug-12
04-Oct-12
58
42
24-May-12
22-Jul-12
08-Aug-12
07-Oct-12
55
EIN-1710
42
24-May-12
22-Jul-12
08-Aug-12
07-Oct-12
55
EIN-1720
42
24-May-12
22-Jul-12
04-Jun-12
01-Aug-12
EIN-1730
46
24-May-12
26-Jul-12
04-Jun-12
07-Aug-12
46
24-May-12
26-Jul-12
17-Jul-12
19-Sep-12
39
EIN-1750
46
24-May-12
26-Jul-12
24-Jun-12
27-Aug-12
22
EIN-1760
46
22-May-12
24-Jul-12
17-Jun-12
19-Aug-12
18
EIN-1770
46
24-May-12
26-Jul-12
24-Jun-12
27-Aug-12
22
EIN-1780
39
24-May-12
17-Jul-12
16-Jul-12
09-Sep-12
38
46
02-Aug-12
04-Oct-12
17-Sep-12
20-Nov-12
33
46
24-May-12
26-Jul-12
17-Sep-12
20-Nov-12
83
EIN-1800
MR for Instrument,F&G,Control
& Telecommunication Cables
MR for Instrument / Mech /
Pneumatic hook ups and
Mech/Pneumatic
Bulk up
material
MR for Electrical hook
and
electrical bulk Material (Junction
boxes
glandsSystem
MR forand
Leakcable
Detection
46
24-May-12
26-Jul-12
19-Jun-12
22-Aug-12
19
EIN-1810
MR for DCS
46
24-May-12
26-Jul-12
24-Jun-12
27-Aug-12
22
EIN-1700
EIN-1740
EIN-1790
EIN-1795
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 32 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
EIN-1820
MR for ESD
46
24-May-12
26-Jul-12
24-Jun-12
27-Aug-12
22
EIN-1825
MR for SCADA-RTU
46
24-May-12
26-Jul-12
24-Jun-12
27-Aug-12
22
46
24-May-12
26-Jul-12
09-Jul-12
11-Sep-12
33
46
24-May-12
26-Jul-12
09-Jul-12
11-Sep-12
33
91
13-Jun-12
17-Oct-12
02-Aug-12
25-Aug-14
483
71
01-Jul-12
07-Oct-12
02-Aug-12
22-Nov-12
34
43
18-Jul-12
16-Sep-12
17-Sep-12
15-Nov-12
44
43
23-Jul-12
19-Sep-12
20-Sep-12
20-Nov-12
44
42
09-Aug-12
07-Oct-12
24-Sep-12
21-Nov-12
33
44
24-Jul-12
23-Sep-12
10-Sep-12
11-Nov-12
35
45
30-Jul-12
30-Sep-12
16-Sep-12
18-Nov-12
35
45
05-Aug-12
04-Oct-12
20-Sep-12
22-Nov-12
35
43
05-Aug-12
02-Oct-12
20-Sep-12
20-Nov-12
35
30-Jul-12
01-Aug-12
12-Sep-12
17-Sep-12
33
46
01-Jul-12
02-Sep-12
02-Aug-12
07-Oct-12
25
EIN-1830
MR for Modification to
PMS/UPS for Data Transfer to
DCS/SCADA
EIN-1840 MR for PLC/RTU System at
BSV-3 for 16" Jet A1 Fuel
Pipeline
Documents / Drawings
Common
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 33 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
91
13-Jun-12
17-Oct-12
13-Aug-12
17-Aug-14
477
52
13-Jun-12
23-Aug-12
13-Aug-12
24-Oct-12
44
48
18-Jul-12
23-Sep-12
02-Oct-12
09-Dec-12
55
49
26-Jun-12
02-Sep-12
22-Aug-12
30-Oct-12
42
52
01-Jul-12
10-Sep-12
27-Aug-12
07-Nov-12
42
48
18-Jul-12
23-Sep-12
13-Sep-12
20-Nov-12
42
44
23-Jul-12
20-Sep-12
07-Oct-12
06-Dec-12
55
44
23-Jul-12
20-Sep-12
05-Sep-12
06-Nov-12
33
42
16-Aug-12
14-Oct-12
01-Oct-12
28-Nov-12
33
43
15-Aug-12
14-Oct-12
30-Sep-12
28-Nov-12
33
43
24-Jul-12
20-Sep-12
17-Jun-14
17-Aug-14
496
43
20-Aug-12
17-Oct-12
03-Oct-12
03-Dec-12
33
43
20-Aug-12
17-Oct-12
23-Sep-12
21-Nov-12
25
90
13-Jun-12
16-Oct-12
23-Aug-12
25-Aug-14
484
44
13-Jun-12
13-Aug-12
23-Aug-12
24-Oct-12
52
QP Refinery
BSV-3
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 34 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
47
18-Jul-12
20-Sep-12
02-Oct-12
06-Dec-12
55
49
24-Jun-12
29-Aug-12
19-Sep-12
27-Nov-12
64
44
24-Jun-12
22-Aug-12
19-Sep-12
20-Nov-12
64
44
24-Jun-12
22-Aug-12
19-Sep-12
20-Nov-12
64
43
23-Jul-12
19-Sep-12
11-Oct-12
11-Dec-12
59
43
23-Jul-12
19-Sep-12
10-Sep-12
08-Nov-12
36
43
30-Jul-12
26-Sep-12
01-Oct-12
29-Nov-12
46
43
01-Aug-12
30-Sep-12
25-Oct-12
25-Dec-12
62
43
09-Aug-12
08-Oct-12
25-Jun-14
25-Aug-14
490
42
20-Aug-12
16-Oct-12
04-Oct-12
03-Dec-12
34
42
20-Aug-12
16-Oct-12
23-Sep-12
20-Nov-12
25
86
03-Jun-12
30-Sep-12
04-Jul-12
25-Aug-14
496
45
15-Jul-12
13-Sep-12
14-Aug-12
25-Aug-14
507
45
15-Jul-12
13-Sep-12
14-Aug-12
16-Oct-12
23
45
15-Jul-12
13-Sep-12
14-Aug-12
16-Oct-12
23
Telecom
Specification
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 35 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
45
15-Jul-12
13-Sep-12
23-Jun-14
25-Aug-14
507
42
03-Jun-12
30-Jul-12
04-Jul-12
30-Aug-12
23
42
03-Jun-12
30-Jul-12
04-Jul-12
30-Aug-12
23
42
03-Jun-12
30-Jul-12
04-Jul-12
30-Aug-12
23
46
29-Jul-12
30-Sep-12
17-Sep-12
20-Nov-12
37
43
29-Jul-12
25-Sep-12
17-Sep-12
15-Nov-12
37
43
01-Aug-12
30-Sep-12
20-Sep-12
20-Nov-12
37
127
08-May-12
02-Oct-12
23-May-12
25-Aug-14
593
Specifications
73
10-May-12 20-Aug-12
23-May-12
24-Sep-12
25
Common
44
15-May-12
15-Jul-12
28-May-12
09-Sep-12
40
44
15-May-12
15-Jul-12
28-May-12
26-Jul-12
44
15-May-12
15-Jul-12
01-Jul-12
29-Aug-12
33
44
15-May-12
15-Jul-12
09-Jul-12
09-Sep-12
40
67
10-May-12 12-Aug-12
23-May-12
23-Aug-12
50
15-May-12
28-May-12
05-Aug-12
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
23-Jul-12
PETROJET CO
Page 36 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
42
14-Jun-12
12-Aug-12
26-Jun-12
23-Aug-12
42
14-Jun-12
12-Aug-12
26-Jun-12
23-Aug-12
41
10-May-12
05-Jul-12
23-May-12
18-Jul-12
41
13-May-12
08-Jul-12
24-May-12
19-Jul-12
43
21-Jun-12
20-Aug-12
25-Jul-12
24-Sep-12
25
43
21-Jun-12
20-Aug-12
25-Jul-12
24-Sep-12
25
43
21-Jun-12
20-Aug-12
25-Jul-12
24-Sep-12
25
84
08-May-12 13-Aug-12
10-Jun-12
20-Nov-12
85
42
21-May-12
17-Jul-12
05-Jul-12
20-Nov-12
90
42
21-May-12
17-Jul-12
23-Sep-12
20-Nov-12
90
42
21-May-12
17-Jul-12
05-Jul-12
02-Sep-12
33
70
08-May-12 13-Aug-12
10-Jun-12
19-Sep-12
27
45
15-May-12
16-Jul-12
08-Jul-12
06-Sep-12
38
43
14-Jun-12
13-Aug-12
23-Jul-12
19-Sep-12
27
43
13-May-12
10-Jul-12
10-Jun-12
08-Aug-12
21
BSV-3
Option-1
EEL-1600
Specification for 415V
Switchboard modificaion
(Option-1
Kahrama connection)
Data Sheets
Common
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 37 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
43
08-May-12
05-Jul-12
23-Jul-12
19-Sep-12
54
43
08-May-12
05-Jul-12
10-Jul-12
06-Sep-12
45
BSV-3
Early Finish
Late Start
Late Finish
Material Requisitions
Common
Option-1
EEL-1730
MR for 415V Switchboard
modificaion (Option-1 Kahrama
connection)
EEL-1920
MR for 415V Switchboard
modificaion (Substation 6003)
Calculations/Reports
QP Refinery
Actual Work
Critical Re...
Remaining Work
Milestone
Total
Float 2012
2013
J
2014
71
16-May-12 22-Aug-12
13-Jun-12
25-Aug-14
523
44
23-May-12
23-Jul-12
09-Jul-12
06-Sep-12
33
44
23-May-12
23-Jul-12
09-Jul-12
06-Sep-12
33
48
16-May-12
22-Jul-12
13-Jun-12
28-Aug-12
27
44
22-May-12
22-Jul-12
28-Jun-12
28-Aug-12
27
44
16-May-12
16-Jul-12
13-Jun-12
14-Aug-12
21
42
26-Jun-12
22-Aug-12
23-Sep-12
25-Aug-14
523
42
26-Jun-12
22-Aug-12
23-Sep-12
25-Aug-14
523
42
26-Jun-12
22-Aug-12
23-Sep-12
20-Nov-12
64
42
26-Jun-12
22-Aug-12
26-Jun-14
25-Aug-14
523
97
15-May-12 26-Sep-12
15-Jul-12
22-Jan-13
84
97
15-May-12 26-Sep-12
23-Aug-12
22-Jan-13
84
PETROJET CO
Page 38 of 266
Date
19-Jul-12
Revision
Rev(5)
Checked
Y.Abdalshaf...
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
EEL-1010Cable Sizing
43
26-Jun-12
23-Aug-12
23-Aug-12
22-Oct-12
42
EEL-1030Lighting Calculations
43
22-Jul-12
18-Sep-12
16-Sep-12
14-Nov-12
41
43
15-May-12
12-Jul-12
09-Sep-12
07-Nov-12
84
43
30-Jul-12
26-Sep-12
22-Nov-12
22-Jan-13
84
49
20-May-12
25-Jul-12
12-Sep-12
20-Nov-12
84
58
12-Jun-12
30-Aug-12
15-Jul-12
16-Oct-12
33
45
12-Jun-12
13-Aug-12
15-Jul-12
13-Sep-12
23
EEL-1770Lighting Calculation
44
02-Jul-12
30-Aug-12
15-Aug-12
16-Oct-12
33
04-Jul-12
20-Nov-12
47
BSV-3
Early Finish
Late Start
Late Finish
Total
Float 2012
Lists/Schedules
82
24-May-12 16-Sep-12
QP Refinery
52
27-Jun-12
06-Sep-12
12-Aug-12
20-Nov-12
53
43
27-Jun-12
26-Aug-12
12-Aug-12
10-Oct-12
33
44
02-Jul-12
30-Aug-12
15-Aug-12
16-Oct-12
33
45
08-Jul-12
06-Sep-12
29-Aug-12
30-Oct-12
38
25-Jul-12
31-Jul-12
29-Aug-12
04-Sep-12
25
44
02-Jul-12
30-Aug-12
23-Aug-12
23-Oct-12
38
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 39 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
EEL-1190DB Schedules
Original
Duration
Early Start
45
08-Jul-12
Early Finish
Late Start
Late Finish
Total
Float 2012
06-Sep-12
18-Sep-12
20-Nov-12
53
82
24-May-12 16-Sep-12
04-Jul-12
20-Nov-12
47
44
24-May-12
24-Jul-12
04-Jul-12
03-Sep-12
29
45
19-Jun-12
20-Aug-12
18-Sep-12
20-Nov-12
66
45
16-Jul-12
16-Sep-12
26-Aug-12
25-Oct-12
29
23-Jul-12
29-Jul-12
02-Sep-12
06-Sep-12
29
45
17-Jun-12
16-Aug-12
26-Jul-12
26-Sep-12
29
EEL-1830DB Schedules
45
24-Jun-12
23-Aug-12
18-Sep-12
20-Nov-12
63
101
15-May-12
02-Oct-12
18-Jul-12
03-Dec-12
44
46
21-Jun-12
23-Aug-12
19-Jul-12
20-Sep-12
20
SLD
98
15-May-12 27-Sep-12
18-Jul-12
03-Dec-12
47
98
15-May-12 27-Sep-12
18-Jul-12
03-Dec-12
47
BSV-3
Drawings/Layouts
QP Refinery
EEL-1200
11KV SLD
43
23-Jul-12
19-Sep-12
25-Sep-12
25-Nov-12
47
EEL-1210
3.3KV SLD
43
26-Jul-12
24-Sep-12
30-Sep-12
28-Nov-12
47
EEL-1220
415V SLD
43
31-Jul-12
27-Sep-12
03-Oct-12
03-Dec-12
47
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 40 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
EEL-1230
110V AC UPS SLD
49
15-May-12
22-Jul-12
18-Jul-12
25-Sep-12
47
EEL-1240
MOV DB SLD-Pump House
45
28-May-12
29-Jul-12
31-Jul-12
02-Oct-12
47
EEL-1250
LPN SLD modification- SER 12
Extension
EEL-1260
MOV DB-Pig Launcher area
43
10-Jul-12
06-Sep-12
12-Sep-12
12-Nov-12
47
45
03-Jun-12
02-Aug-12
06-Aug-12
08-Oct-12
47
EEL-1270
LPN - Pig Launcher area
43
15-Jul-12
11-Sep-12
17-Sep-12
15-Nov-12
47
EEL-1280
LPN SLD - Pump house
43
18-Jul-12
16-Sep-12
20-Sep-12
20-Nov-12
47
46
05-Jul-12
06-Sep-12
11-Sep-12
20-Nov-12
53
EEL-1840
415V SLD
46
05-Jul-12
06-Sep-12
11-Sep-12
14-Nov-12
49
EEL-1850
LPN SLD - Plant area
46
05-Jul-12
06-Sep-12
17-Sep-12
20-Nov-12
53
44
15-Jul-12
12-Sep-12
19-Sep-12
20-Nov-12
49
44
15-Jul-12
12-Sep-12
19-Sep-12
20-Nov-12
49
73
21-Jun-12
01-Oct-12
24-Jul-12
20-Nov-12
36
71
25-Jun-12
01-Oct-12
09-Aug-12
20-Nov-12
36
46
24-Jul-12
25-Sep-12
28-Aug-12
30-Oct-12
25
44
24-Jul-12
23-Sep-12
30-Aug-12
30-Oct-12
27
BSV-3
Station-T1
EEL-1870
DB SLD modification
Layouts
QP Refinery
EEL-1300
Cable Routing Layout - Pump
House/SS/SER-12
EEL-1310
Cable Routing Layout - Pig
Launcher area
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 41 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
EEL-1320
Earthing Layout - Plump
House/SS/SER-12
EEL-1330
Earthing Layout - Pig Launcher
area
EEL-1340
Lighting Layout - Pump House
44
01-Aug-12
01-Oct-12
19-Sep-12
20-Nov-12
36
44
30-Jul-12
27-Sep-12
19-Sep-12
20-Nov-12
38
44
25-Jul-12
24-Sep-12
19-Sep-12
20-Nov-12
41
EEL-1350
Lighting Layout - Pig Launcher
area
EEL-1360
Lighting Layout-SER 12
Extension
EEL-1370
Lightning Protection
Layout-SER 12 Extension
EEL-1380
Equipment Layout
modification-S/S 6003
EEL-1390
Equipment Layout-SER 12
Extension
44
25-Jul-12
24-Sep-12
19-Sep-12
20-Nov-12
41
44
25-Jul-12
24-Sep-12
19-Sep-12
20-Nov-12
41
44
08-Jul-12
05-Sep-12
19-Sep-12
20-Nov-12
54
45
15-Jul-12
13-Sep-12
12-Sep-12
14-Nov-12
44
45
25-Jun-12
26-Aug-12
09-Aug-12
11-Oct-12
34
52
04-Jul-12
13-Sep-12
15-Aug-12
31-Oct-12
34
EEL-1400
Cable Routing Layout
44
15-Jul-12
12-Sep-12
15-Aug-12
15-Oct-12
23
EEL-1410
Earthing Layout
45
15-Jul-12
13-Sep-12
29-Aug-12
31-Oct-12
34
EEL-1420
Lighting Layout
42
04-Jul-12
30-Aug-12
20-Aug-12
17-Oct-12
34
43
21-Jun-12
20-Aug-12
24-Jul-12
20-Sep-12
23
43
21-Jun-12
20-Aug-12
24-Jul-12
20-Sep-12
23
45
01-Aug-12
02-Oct-12
18-Sep-12
20-Nov-12
35
BSV-3
Station-T1
EEL-1445
Cable Routing Layout (Station
T1)
Area classification drawings
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 42 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
45
01-Aug-12
02-Oct-12
18-Sep-12
20-Nov-12
35
44
01-Aug-12
01-Oct-12
19-Sep-12
20-Nov-12
36
44
22-Jul-12
19-Sep-12
19-Sep-12
20-Nov-12
44
44
22-Jul-12
19-Sep-12
19-Sep-12
20-Nov-12
44
192
28-Mar-12
06-Nov-12
17-May-12
27-Dec-12
44
Specifications
52
06-May-12
16-Jul-12
03-Jun-12
14-Aug-12
21
42
06-May-12
02-Jul-12
03-Jun-12
31-Jul-12
21
44
08-May-12
08-Jul-12
05-Jun-12
06-Aug-12
21
44
08-May-12
08-Jul-12
05-Jun-12
06-Aug-12
21
44
08-May-12
08-Jul-12
05-Jun-12
06-Aug-12
21
44
16-May-12
16-Jul-12
13-Jun-12
14-Aug-12
21
44
16-May-12
16-Jul-12
13-Jun-12
14-Aug-12
21
43
28-Mar-12
27-May-12
17-May-12
17-Jul-12
37
43
28-Mar-12
27-May-12
17-May-12
17-Jul-12
37
102
27-May-12
15-Oct-12
11-Jun-12
20-Nov-12
26
ECI-1000
ECI-1010
ECI-1020
ECI-1030
ECI-1040
ECI-1050
Scope of Work
ECI-1140
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 43 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
43
27-May-12
24-Jul-12
11-Jun-12
09-Aug-12
12
86
05-Jun-12
02-Oct-12
20-Jun-12
18-Oct-12
12
43
17-Jul-12
13-Sep-12
01-Aug-12
01-Oct-12
12
46
13-Aug-12
15-Oct-12
17-Sep-12
20-Nov-12
26
44
19-Jun-12
19-Aug-12
27-Aug-12
25-Oct-12
49
46
02-Jul-12
03-Sep-12
09-Sep-12
11-Nov-12
49
44
31-May-12
31-Jul-12
30-Jul-12
30-Sep-12
43
45
02-Jul-12
02-Sep-12
29-Aug-12
31-Oct-12
43
46
01-Jul-12
02-Sep-12
17-Sep-12
20-Nov-12
57
104
09-Jul-12
06-Nov-12
02-Aug-12
27-Dec-12
44
87
09-Jul-12
06-Nov-12
02-Aug-12
27-Dec-12
37
47
21-Aug-12
24-Oct-12
05-Sep-12
11-Nov-12
12
47
20-Aug-12
23-Oct-12
24-Oct-12
27-Dec-12
47
47
21-Aug-12
24-Oct-12
17-Sep-12
21-Nov-12
20
47
09-Jul-12
11-Sep-12
05-Sep-12
11-Nov-12
43
ECI-1080
ECI-1090
ECI-1095
ECI-1096
ECI-1110
ECI-1120
ECI-1130
ECI-1150
ECI-1160
QP Refinery
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 44 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
47
09-Jul-12
11-Sep-12
10-Sep-12
14-Nov-12
46
45
14-Aug-12
15-Oct-12
10-Sep-12
12-Nov-12
20
45
22-Aug-12
23-Oct-12
18-Sep-12
20-Nov-12
20
45
22-Aug-12
23-Oct-12
18-Sep-12
20-Nov-12
20
44
13-Aug-12
11-Oct-12
13-Sep-12
14-Nov-12
24
44
13-Aug-12
11-Oct-12
13-Sep-12
14-Nov-12
24
44
19-Aug-12
17-Oct-12
19-Sep-12
20-Nov-12
24
72
22-Jul-12
29-Oct-12
02-Aug-12
12-Nov-12
10
78
22-Jul-12
06-Nov-12
02-Aug-12
20-Nov-12
10
44
14-Aug-12
14-Oct-12
10-Sep-12
11-Nov-12
20
46
31-Jul-12
02-Oct-12
17-Sep-12
20-Nov-12
35
48
10-Jul-12
13-Sep-12
26-Aug-12
31-Oct-12
34
48
10-Jul-12
13-Sep-12
26-Aug-12
31-Oct-12
34
44
22-Jul-12
19-Sep-12
03-Oct-12
04-Dec-12
54
44
22-Jul-12
19-Sep-12
03-Oct-12
04-Dec-12
54
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 45 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
54
17-Jul-12
30-Sep-12
13-Sep-12
20-Dec-12
59
44
23-Jul-12
20-Sep-12
19-Sep-12
20-Nov-12
43
44
17-Jul-12
16-Sep-12
13-Sep-12
14-Nov-12
43
44
23-Jul-12
20-Sep-12
19-Sep-12
20-Nov-12
43
47
26-Jul-12
30-Sep-12
17-Oct-12
20-Dec-12
59
50
08-Aug-12
16-Oct-12
11-Sep-12
20-Nov-12
25
45
08-Aug-12
09-Oct-12
11-Sep-12
13-Nov-12
25
45
15-Aug-12
16-Oct-12
18-Sep-12
20-Nov-12
25
BSV-3
Early Finish
Late Start
Late Finish
Total
Float 2012
78
12-Jun-12
27-Sep-12
25-Jul-12
20-Nov-12
38
Specification
42
18-Jun-12
14-Aug-12
25-Jul-12
23-Sep-12
28
42
18-Jun-12
14-Aug-12
25-Jul-12
23-Sep-12
28
40
20-Jun-12
14-Aug-12
29-Jul-12
23-Sep-12
28
40
20-Jun-12
14-Aug-12
29-Jul-12
23-Sep-12
28
44
12-Jun-12
12-Aug-12
02-Aug-12
03-Oct-12
38
Material Requisition
Actual Work
Critical Re...
Remaining Work
Milestone
2014
Building Services
2013
J
PETROJET CO
Page 46 of 266
Date
19-Jul-12
Revision
Rev(5)
Checked
Y.Abdalshaf...
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
44
12-Jun-12
12-Aug-12
02-Aug-12
03-Oct-12
38
74
18-Jun-12
27-Sep-12
08-Aug-12
20-Nov-12
38
44
18-Jun-12
16-Aug-12
08-Aug-12
09-Oct-12
38
44
18-Jun-12
16-Aug-12
08-Aug-12
09-Oct-12
38
44
18-Jun-12
16-Aug-12
08-Aug-12
09-Oct-12
38
42
24-Jun-12
20-Aug-12
14-Aug-12
11-Oct-12
38
41
30-Jul-12
24-Sep-12
19-Sep-12
15-Nov-12
38
41
02-Aug-12
27-Sep-12
24-Sep-12
20-Nov-12
38
43
24-Jun-12
21-Aug-12
20-Sep-12
20-Nov-12
65
19-Aug-12
21-Aug-12
15-Nov-12
20-Nov-12
65
43
24-Jun-12
21-Aug-12
20-Sep-12
20-Nov-12
65
149
01-Apr-12
24-Oct-12
26-Jun-12
20-Nov-12
19
134
01-Apr-12
03-Oct-12
26-Jun-12
30-Oct-12
19
60
01-Apr-12
21-Jun-12
26-Jun-12
18-Sep-12
63
50
26-Jul-12
03-Oct-12
21-Aug-12
30-Oct-12
19
Schedules / Lists
Reports/Calculations/Schedule
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 47 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
70
10-Jul-12
15-Oct-12
08-Aug-12
13-Nov-12
21
43
09-Aug-12
08-Oct-12
04-Sep-12
04-Nov-12
19
43
16-Aug-12
15-Oct-12
16-Sep-12
13-Nov-12
21
39
10-Jul-12
02-Sep-12
08-Aug-12
01-Oct-12
21
43
14-Aug-12
11-Oct-12
09-Sep-12
07-Nov-12
19
43
14-Aug-12
11-Oct-12
09-Sep-12
07-Nov-12
19
49
19-Aug-12
24-Oct-12
12-Sep-12
20-Nov-12
19
44
19-Aug-12
17-Oct-12
12-Sep-12
13-Nov-12
19
45
23-Aug-12
24-Oct-12
18-Sep-12
20-Nov-12
19
387
25-Apr-12
17-Oct-13
03-Apr-12
25-Nov-13
26
382
02-May-12
17-Oct-13
05-Jun-12
17-Nov-13
21
29
02-May-12
12-Jun-12
05-Jun-12
16-Jul-12
25
21
02-May-12 31-May-12
05-Jun-12
04-Jul-12
25
03-Jun-12
12-Jun-12
05-Jul-12
16-Jul-12
25
402
23-Jul-12
29-Aug-13
19-Aug-12
17-Nov-13
80
Specifications/SOW
Data Sheets
Procurement Phase
Long Lead Items (Equipment)
QP Supplied Free Issue Material
PP1100
PP1110
Mechanical Items
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 48 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
401
24-Jul-12
29-Aug-13
19-Aug-12
17-Nov-13
80
24-Jul-12
26-Jul-12
19-Aug-12
21-Aug-12
26
26-Jul-12
02-Aug-12
21-Aug-12
28-Aug-12
26
16-Aug-12
23-Aug-12
11-Sep-12
18-Sep-12
26
30
06-Sep-12
06-Oct-12
02-Oct-12
01-Nov-12
26
60
06-Oct-12
05-Dec-12
01-Nov-12
31-Dec-12
26
200
21-Oct-12
09-May-13
16-Nov-12
04-Jun-13
26
15
09-May-13 24-May-13
04-Jun-13
19-Jun-13
26
45
24-May-13
08-Jul-13
19-Jun-13
03-Aug-13
26
08-Jul-13
15-Jul-13
03-Aug-13
10-Aug-13
26
45
15-Jul-13
29-Aug-13
03-Oct-13
17-Nov-13
80
367
01-Aug-12
03-Aug-13
26-Sep-12
13-Oct-13
71
01-Aug-12
03-Aug-12
26-Sep-12
28-Sep-12
56
03-Aug-12
10-Aug-12
28-Sep-12
05-Oct-12
56
24-Aug-12
31-Aug-12
19-Oct-12
26-Oct-12
56
Pig Launcher
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 49 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
30
31-Aug-12
30-Sep-12
26-Oct-12
25-Nov-12
56
60
30-Sep-12
29-Nov-12
25-Nov-12
24-Jan-13
56
180
15-Oct-12
13-Apr-13
10-Dec-12
08-Jun-13
56
15
13-Apr-13
28-Apr-13
08-Jun-13
23-Jun-13
56
45
28-Apr-13
12-Jun-13
23-Jun-13
07-Aug-13
56
12-Jun-13
19-Jun-13
07-Aug-13
14-Aug-13
56
45
19-Jun-13
03-Aug-13
29-Aug-13
13-Oct-13
71
367
23-Jul-12
25-Jul-13
07-Sep-12
13-Oct-13
80
PLJI1100
23-Jul-12
25-Jul-12
07-Sep-12
09-Sep-12
46
PLJI1110
25-Jul-12
01-Aug-12
09-Sep-12
16-Sep-12
46
15-Aug-12
22-Aug-12
30-Sep-12
07-Oct-12
46
30
22-Aug-12
21-Sep-12
07-Oct-12
06-Nov-12
46
60
21-Sep-12
20-Nov-12
06-Nov-12
05-Jan-13
46
180
06-Oct-12
04-Apr-13
21-Nov-12
20-May-13
46
15
04-Apr-13
19-Apr-13
20-May-13
04-Jun-13
46
PLJI1120
PLJI1130
PLJI1140
PLJI1150
PLJI1160
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 50 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
PLJI1170
PLJI1180
PLJI1190
Pumps
Actual Work
Critical Re...
Remaining Work
Milestone
Original
Duration
Early Start
Early Finish
45
19-Apr-13
03-Jun-13
04-Jun-13
19-Jul-13
46
03-Jun-13
10-Jun-13
19-Jul-13
26-Jul-13
46
45
10-Jun-13
25-Jul-13
29-Aug-13
13-Oct-13
80
455
19-Jul-12
17-Oct-13
21-Jul-12
23-Oct-13
455
19-Jul-12
17-Oct-13
21-Jul-12
23-Oct-13
19-Jul-12
21-Jul-12
21-Jul-12
23-Jul-12
21-Jul-12
28-Jul-12
23-Jul-12
30-Jul-12
11-Aug-12
18-Aug-12
13-Aug-12
20-Aug-12
30
18-Aug-12
17-Sep-12
20-Aug-12
19-Sep-12
60
17-Sep-12
16-Nov-12
19-Sep-12
18-Nov-12
268
02-Oct-12
27-Jun-13
04-Oct-12
29-Jun-13
15
27-Jun-13
12-Jul-13
29-Jun-13
14-Jul-13
45
12-Jul-13
26-Aug-13
14-Jul-13
28-Aug-13
26-Aug-13
02-Sep-13
28-Aug-13
04-Sep-13
45
02-Sep-13
17-Oct-13
08-Sep-13
23-Oct-13
PETROJET CO
Page 51 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
455
19-Jul-12
17-Oct-13
21-Jul-12
23-Oct-13
19-Jul-12
21-Jul-12
21-Jul-12
23-Jul-12
21-Jul-12
28-Jul-12
23-Jul-12
30-Jul-12
11-Aug-12
18-Aug-12
13-Aug-12
20-Aug-12
30
18-Aug-12
17-Sep-12
20-Aug-12
19-Sep-12
60
17-Sep-12
16-Nov-12
19-Sep-12
18-Nov-12
268
02-Oct-12
27-Jun-13
04-Oct-12
29-Jun-13
15
27-Jun-13
12-Jul-13
29-Jun-13
14-Jul-13
45
12-Jul-13
26-Aug-13
14-Jul-13
28-Aug-13
26-Aug-13
02-Sep-13
28-Aug-13
04-Sep-13
45
02-Sep-13
17-Oct-13
08-Sep-13
23-Oct-13
393
31-Jul-12
28-Aug-13
04-Sep-12
13-Oct-13
46
357
31-Jul-12
23-Jul-13
07-Sep-12
13-Oct-13
82
31-Jul-12
02-Aug-12
07-Sep-12
09-Sep-12
38
02-Aug-12
09-Aug-12
09-Sep-12
16-Sep-12
38
Booster Pumps
Switchgear Panels
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 52 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Actual Work
Critical Re...
Remaining Work
Milestone
Original
Duration
Early Start
Early Finish
23-Aug-12
30-Aug-12
30-Sep-12
07-Oct-12
38
30
30-Aug-12
29-Sep-12
07-Oct-12
06-Nov-12
38
60
29-Sep-12
28-Nov-12
06-Nov-12
05-Jan-13
38
170
14-Oct-12
02-Apr-13
21-Nov-12
10-May-13
38
15
02-Apr-13
17-Apr-13
10-May-13
25-May-13
38
45
17-Apr-13
01-Jun-13
25-May-13
09-Jul-13
38
01-Jun-13
08-Jun-13
09-Jul-13
16-Jul-13
38
45
08-Jun-13
23-Jul-13
29-Aug-13
13-Oct-13
82
357
02-Aug-12
25-Jul-13
07-Sep-12
13-Oct-13
80
02-Aug-12
04-Aug-12
07-Sep-12
09-Sep-12
36
04-Aug-12
11-Aug-12
09-Sep-12
16-Sep-12
36
25-Aug-12
01-Sep-12
30-Sep-12
07-Oct-12
36
30
01-Sep-12
01-Oct-12
07-Oct-12
06-Nov-12
36
60
01-Oct-12
30-Nov-12
06-Nov-12
05-Jan-13
36
170
16-Oct-12
04-Apr-13
21-Nov-12
10-May-13
36
PETROJET CO
Page 53 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
15
04-Apr-13
19-Apr-13
10-May-13
25-May-13
36
45
19-Apr-13
03-Jun-13
25-May-13
09-Jul-13
36
03-Jun-13
10-Jun-13
09-Jul-13
16-Jul-13
36
45
10-Jun-13
25-Jul-13
29-Aug-13
13-Oct-13
80
387
06-Aug-12
28-Aug-13
04-Sep-12
13-Oct-13
46
06-Aug-12
08-Aug-12
04-Sep-12
06-Sep-12
29
08-Aug-12
15-Aug-12
06-Sep-12
13-Sep-12
29
29-Aug-12
05-Sep-12
27-Sep-12
04-Oct-12
29
30
05-Sep-12
05-Oct-12
04-Oct-12
03-Nov-12
29
60
05-Oct-12
04-Dec-12
03-Nov-12
02-Jan-13
29
200
20-Oct-12
08-May-13
18-Nov-12
06-Jun-13
29
15
08-May-13 23-May-13
06-Jun-13
21-Jun-13
29
45
23-May-13
07-Jul-13
21-Jun-13
05-Aug-13
29
07-Jul-13
14-Jul-13
05-Aug-13
12-Aug-13
29
45
14-Jul-13
28-Aug-13
29-Aug-13
13-Oct-13
46
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 54 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
416
22-Jul-12
11-Sep-13
12-Aug-12
13-Oct-13
32
412
26-Jul-12
11-Sep-13
27-Aug-12
13-Oct-13
32
26-Jul-12
28-Jul-12
27-Aug-12
29-Aug-12
32
28-Jul-12
04-Aug-12
29-Aug-12
05-Sep-12
32
18-Aug-12
25-Aug-12
19-Sep-12
26-Sep-12
32
30
25-Aug-12
24-Sep-12
26-Sep-12
26-Oct-12
32
60
24-Sep-12
23-Nov-12
26-Oct-12
25-Dec-12
32
225
09-Oct-12
22-May-13
10-Nov-12
23-Jun-13
32
15
22-May-13
06-Jun-13
23-Jun-13
08-Jul-13
32
45
06-Jun-13
21-Jul-13
08-Jul-13
22-Aug-13
32
21-Jul-13
28-Jul-13
22-Aug-13
29-Aug-13
32
45
28-Jul-13
11-Sep-13
29-Aug-13
13-Oct-13
32
412
22-Jul-12
07-Sep-13
27-Aug-12
13-Oct-13
36
22-Jul-12
24-Jul-12
27-Aug-12
29-Aug-12
36
24-Jul-12
31-Jul-12
29-Aug-12
05-Sep-12
36
Valves
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 55 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
14-Aug-12
21-Aug-12
19-Sep-12
26-Sep-12
36
30
21-Aug-12
20-Sep-12
26-Sep-12
26-Oct-12
36
60
20-Sep-12
19-Nov-12
26-Oct-12
25-Dec-12
36
225
05-Oct-12
18-May-13
10-Nov-12
23-Jun-13
36
15
18-May-13
02-Jun-13
23-Jun-13
08-Jul-13
36
45
02-Jun-13
17-Jul-13
08-Jul-13
22-Aug-13
36
17-Jul-13
24-Jul-13
22-Aug-13
29-Aug-13
36
45
24-Jul-13
07-Sep-13
29-Aug-13
13-Oct-13
36
397
30-Jul-12
31-Aug-13
11-Sep-12
13-Oct-13
43
30-Jul-12
01-Aug-12
11-Sep-12
13-Sep-12
43
PLVI1110
01-Aug-12
08-Aug-12
13-Sep-12
20-Sep-12
43
22-Aug-12
29-Aug-12
04-Oct-12
11-Oct-12
43
30
29-Aug-12
28-Sep-12
11-Oct-12
10-Nov-12
43
60
28-Sep-12
27-Nov-12
10-Nov-12
09-Jan-13
43
210
13-Oct-12
11-May-13
25-Nov-12
23-Jun-13
43
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 56 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
15
11-May-13 26-May-13
23-Jun-13
08-Jul-13
43
45
26-May-13
10-Jul-13
08-Jul-13
22-Aug-13
43
10-Jul-13
17-Jul-13
22-Aug-13
29-Aug-13
43
45
17-Jul-13
31-Aug-13
29-Aug-13
13-Oct-13
43
397
31-Jul-12
01-Sep-13
12-Aug-12
13-Oct-13
42
31-Jul-12
02-Aug-12
12-Aug-12
14-Aug-12
12
02-Aug-12
09-Aug-12
14-Aug-12
21-Aug-12
12
23-Aug-12
30-Aug-12
04-Sep-12
11-Sep-12
12
30
30-Aug-12
29-Sep-12
11-Sep-12
11-Oct-12
12
60
29-Sep-12
28-Nov-12
11-Oct-12
10-Dec-12
12
210
14-Oct-12
12-May-13
26-Oct-12
24-May-13
12
15
12-May-13 27-May-13
24-May-13
08-Jun-13
12
45
27-May-13
11-Jul-13
08-Jun-13
23-Jul-13
12
11-Jul-13
18-Jul-13
23-Jul-13
30-Jul-13
12
45
18-Jul-13
01-Sep-13
29-Aug-13
13-Oct-13
42
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 57 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Coriollis Flowmeter
Actual Work
Critical Re...
Remaining Work
Milestone
Original
Duration
Early Start
Early Finish
387
09-Aug-12
31-Aug-13
22-Aug-12
13-Oct-13
43
09-Aug-12
11-Aug-12
22-Aug-12
24-Aug-12
13
11-Aug-12
18-Aug-12
24-Aug-12
31-Aug-12
13
01-Sep-12
08-Sep-12
14-Sep-12
21-Sep-12
13
30
08-Sep-12
08-Oct-12
21-Sep-12
21-Oct-12
13
60
08-Oct-12
07-Dec-12
21-Oct-12
20-Dec-12
13
200
23-Oct-12
11-May-13
05-Nov-12
24-May-13
13
15
11-May-13 26-May-13
24-May-13
08-Jun-13
13
45
26-May-13
10-Jul-13
08-Jun-13
23-Jul-13
13
10-Jul-13
17-Jul-13
23-Jul-13
30-Jul-13
13
45
17-Jul-13
31-Aug-13
29-Aug-13
13-Oct-13
43
423
17-Jul-12
13-Sep-13
09-Sep-12
13-Oct-13
30
382
08-Aug-12
25-Aug-13
19-Sep-12
13-Oct-13
49
08-Aug-12
10-Aug-12
19-Sep-12
21-Sep-12
42
10-Aug-12
17-Aug-12
21-Sep-12
28-Sep-12
42
PETROJET CO
Page 58 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
31-Aug-12
07-Sep-12
12-Oct-12
19-Oct-12
42
30
07-Sep-12
07-Oct-12
19-Oct-12
18-Nov-12
42
60
07-Oct-12
06-Dec-12
18-Nov-12
17-Jan-13
42
210
07-Oct-12
05-May-13
18-Nov-12
16-Jun-13
42
15
05-May-13 20-May-13
16-Jun-13
01-Jul-13
42
45
20-May-13
04-Jul-13
01-Jul-13
15-Aug-13
42
04-Jul-13
11-Jul-13
15-Aug-13
22-Aug-13
42
45
11-Jul-13
25-Aug-13
29-Aug-13
13-Oct-13
49
367
31-Jul-12
02-Aug-13
09-Sep-12
13-Oct-13
72
PLIJ1100
31-Jul-12
02-Aug-12
09-Sep-12
11-Sep-12
40
PLIJ1110
02-Aug-12
09-Aug-12
11-Sep-12
18-Sep-12
40
23-Aug-12
30-Aug-12
02-Oct-12
09-Oct-12
40
30
30-Aug-12
29-Sep-12
09-Oct-12
08-Nov-12
40
60
29-Sep-12
28-Nov-12
08-Nov-12
07-Jan-13
40
180
14-Oct-12
12-Apr-13
23-Nov-12
22-May-13
40
PLIJ1120
PLIJ1130
PLIJ1140
PLIJ1150
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 59 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
PLIJ1160
PLIJ1170
PLIJ1180
PLIJ1190
Original
Duration
Early Start
15
12-Apr-13
27-Apr-13
22-May-13
06-Jun-13
40
45
27-Apr-13
11-Jun-13
06-Jun-13
21-Jul-13
40
11-Jun-13
18-Jun-13
21-Jul-13
28-Jul-13
40
45
18-Jun-13
02-Aug-13
29-Aug-13
13-Oct-13
72
357
09-Aug-12
01-Aug-13
03-Oct-12
13-Oct-13
73
09-Aug-12
11-Aug-12
03-Oct-12
05-Oct-12
55
11-Aug-12
18-Aug-12
05-Oct-12
12-Oct-12
55
01-Sep-12
08-Sep-12
26-Oct-12
02-Nov-12
55
30
08-Sep-12
08-Oct-12
02-Nov-12
02-Dec-12
55
60
08-Oct-12
07-Dec-12
02-Dec-12
31-Jan-13
55
170
23-Oct-12
11-Apr-13
17-Dec-12
05-Jun-13
55
15
11-Apr-13
26-Apr-13
05-Jun-13
20-Jun-13
55
45
26-Apr-13
10-Jun-13
20-Jun-13
04-Aug-13
55
10-Jun-13
17-Jun-13
04-Aug-13
11-Aug-13
55
45
17-Jun-13
01-Aug-13
29-Aug-13
13-Oct-13
73
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 60 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
397
12-Aug-12
13-Sep-13
11-Sep-12
13-Oct-13
30
12-Aug-12
14-Aug-12
11-Sep-12
13-Sep-12
30
14-Aug-12
21-Aug-12
13-Sep-12
20-Sep-12
30
04-Sep-12
11-Sep-12
04-Oct-12
11-Oct-12
30
30
11-Sep-12
11-Oct-12
11-Oct-12
10-Nov-12
30
60
11-Oct-12
10-Dec-12
10-Nov-12
09-Jan-13
30
210
26-Oct-12
24-May-13
25-Nov-12
23-Jun-13
30
15
24-May-13
08-Jun-13
23-Jun-13
08-Jul-13
30
45
08-Jun-13
23-Jul-13
08-Jul-13
22-Aug-13
30
23-Jul-13
30-Jul-13
22-Aug-13
29-Aug-13
30
45
30-Jul-13
13-Sep-13
29-Aug-13
13-Oct-13
30
318
17-Jul-12
31-May-13
11-Sep-12
26-Jul-13
56
17-Jul-12
19-Jul-12
11-Sep-12
13-Sep-12
56
19-Jul-12
26-Jul-12
13-Sep-12
20-Sep-12
56
09-Aug-12
16-Aug-12
04-Oct-12
11-Oct-12
56
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 61 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
30
16-Aug-12
15-Sep-12
11-Oct-12
10-Nov-12
56
60
15-Sep-12
14-Nov-12
10-Nov-12
09-Jan-13
56
136
25-Sep-12
08-Feb-13
20-Nov-12
05-Apr-13
56
15
08-Feb-13
23-Feb-13
05-Apr-13
20-Apr-13
56
45
23-Feb-13
09-Apr-13
20-Apr-13
04-Jun-13
56
09-Apr-13
16-Apr-13
04-Jun-13
11-Jun-13
56
45
16-Apr-13
31-May-13
11-Jun-13
26-Jul-13
56
324
23-Jul-12
12-Jun-13
20-Sep-12
10-Aug-13
59
PLM1200
23-Jul-12
25-Jul-12
20-Sep-12
22-Sep-12
59
PLM1210
25-Jul-12
01-Aug-12
22-Sep-12
29-Sep-12
59
15-Aug-12
22-Aug-12
13-Oct-12
20-Oct-12
59
30
22-Aug-12
21-Sep-12
20-Oct-12
19-Nov-12
59
60
21-Sep-12
20-Nov-12
19-Nov-12
18-Jan-13
59
148
25-Sep-12
20-Feb-13
23-Nov-12
20-Apr-13
59
15
20-Feb-13
07-Mar-13
20-Apr-13
05-May-13
59
PLM1220
PLM1230
PLM1240
PLM1250
PLM1260
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 62 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
45
07-Mar-13
21-Apr-13
05-May-13
19-Jun-13
59
21-Apr-13
28-Apr-13
19-Jun-13
26-Jun-13
59
45
28-Apr-13
12-Jun-13
26-Jun-13
10-Aug-13
59
397
31-Jul-12
01-Sep-13
11-Sep-12
13-Oct-13
42
31-Jul-12
02-Aug-12
11-Sep-12
13-Sep-12
42
02-Aug-12
09-Aug-12
13-Sep-12
20-Sep-12
42
23-Aug-12
30-Aug-12
04-Oct-12
11-Oct-12
42
30
30-Aug-12
29-Sep-12
11-Oct-12
10-Nov-12
42
60
29-Sep-12
28-Nov-12
10-Nov-12
09-Jan-13
42
210
14-Oct-12
12-May-13
25-Nov-12
23-Jun-13
42
15
12-May-13 27-May-13
23-Jun-13
08-Jul-13
42
45
27-May-13
11-Jul-13
08-Jul-13
22-Aug-13
42
11-Jul-13
18-Jul-13
22-Aug-13
29-Aug-13
42
45
18-Jul-13
01-Sep-13
29-Aug-13
13-Oct-13
42
387
08-Aug-12
30-Aug-13
04-Sep-12
13-Oct-13
44
PLM1270
PLM1280
PLM1290
PLTE1100
PLTE1110
PLTE1120
PLTE1130
PLTE1140
PLTE1150
PLTE1160
PLTE1170
PLTE1180
PLTE1190
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 63 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
08-Aug-12
10-Aug-12
04-Sep-12
06-Sep-12
27
10-Aug-12
17-Aug-12
06-Sep-12
13-Sep-12
27
31-Aug-12
07-Sep-12
27-Sep-12
04-Oct-12
27
30
07-Sep-12
07-Oct-12
04-Oct-12
03-Nov-12
27
60
07-Oct-12
06-Dec-12
03-Nov-12
02-Jan-13
27
200
22-Oct-12
10-May-13
18-Nov-12
06-Jun-13
27
15
10-May-13 25-May-13
06-Jun-13
21-Jun-13
27
45
25-May-13
09-Jul-13
21-Jun-13
05-Aug-13
27
09-Jul-13
16-Jul-13
05-Aug-13
12-Aug-13
27
45
16-Jul-13
30-Aug-13
29-Aug-13
13-Oct-13
44
353
12-Jul-12
30-Jun-13
01-Sep-12
24-Aug-13
55
351
12-Jul-12
28-Jun-13
03-Sep-12
30-Jul-13
32
330
02-Aug-12
28-Jun-13
03-Sep-12
30-Jul-13
32
02-Aug-12
04-Aug-12
03-Sep-12
05-Sep-12
32
04-Aug-12
11-Aug-12
05-Sep-12
12-Sep-12
32
PLLD1100
PLLD1110
PLLD1120
PLLD1130
PLLD1140
PLLD1150
PLLD1160
PLLD1170
PLLD1180
PLLD1190
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 64 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
25-Aug-12
01-Sep-12
26-Sep-12
03-Oct-12
32
10
31-Oct-12
10-Nov-12
02-Dec-12
12-Dec-12
32
10
10-Dec-12
20-Dec-12
11-Jan-13
21-Jan-13
32
50
20-Dec-12
08-Feb-13
21-Jan-13
12-Mar-13
32
50
10-Mar-13
29-Apr-13
11-Apr-13
31-May-13
32
30
29-May-13
28-Jun-13
30-Jun-13
30-Jul-13
32
330
12-Jul-12
07-Jun-13
03-Sep-12
30-Jul-13
53
12-Jul-12
14-Jul-12
03-Sep-12
05-Sep-12
53
14-Jul-12
21-Jul-12
05-Sep-12
12-Sep-12
53
04-Aug-12
11-Aug-12
26-Sep-12
03-Oct-12
53
10
10-Oct-12
20-Oct-12
02-Dec-12
12-Dec-12
53
10
19-Nov-12
29-Nov-12
11-Jan-13
21-Jan-13
53
50
29-Nov-12
18-Jan-13
21-Jan-13
12-Mar-13
53
50
17-Feb-13
08-Apr-13
11-Apr-13
31-May-13
53
30
08-May-13
07-Jun-13
30-Jun-13
30-Jul-13
53
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 65 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Electrical
Actual Work
Critical Re...
Remaining Work
Milestone
Original
Duration
Early Start
Early Finish
320
14-Aug-12
30-Jun-13
23-Sep-12
09-Aug-13
40
290
14-Aug-12 31-May-13
16-Oct-12
02-Aug-13
63
14-Aug-12
16-Aug-12
16-Oct-12
18-Oct-12
63
16-Aug-12
23-Aug-12
18-Oct-12
25-Oct-12
63
06-Sep-12
13-Sep-12
08-Nov-12
15-Nov-12
63
10
12-Nov-12
22-Nov-12
14-Jan-13
24-Jan-13
63
10
22-Dec-12
01-Jan-13
23-Feb-13
05-Mar-13
63
30
01-Jan-13
31-Jan-13
05-Mar-13
04-Apr-13
63
30
02-Mar-13
01-Apr-13
04-May-13
03-Jun-13
63
30
01-May-13 31-May-13
03-Jul-13
02-Aug-13
63
290
31-Aug-12
17-Jun-13
16-Oct-12
02-Aug-13
46
31-Aug-12
02-Sep-12
16-Oct-12
18-Oct-12
46
02-Sep-12
09-Sep-12
18-Oct-12
25-Oct-12
46
23-Sep-12
30-Sep-12
08-Nov-12
15-Nov-12
46
10
29-Nov-12
09-Dec-12
14-Jan-13
24-Jan-13
46
PETROJET CO
Page 66 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
10
08-Jan-13
18-Jan-13
23-Feb-13
05-Mar-13
46
30
18-Jan-13
17-Feb-13
05-Mar-13
04-Apr-13
46
30
19-Mar-13
18-Apr-13
04-May-13
03-Jun-13
46
30
18-May-13
17-Jun-13
03-Jul-13
02-Aug-13
46
320
14-Aug-12
30-Jun-13
23-Sep-12
09-Aug-13
40
14-Aug-12
16-Aug-12
23-Sep-12
25-Sep-12
40
16-Aug-12
23-Aug-12
25-Sep-12
02-Oct-12
40
06-Sep-12
13-Sep-12
16-Oct-12
23-Oct-12
40
10
12-Nov-12
22-Nov-12
22-Dec-12
01-Jan-13
40
10
22-Dec-12
01-Jan-13
31-Jan-13
10-Feb-13
40
45
01-Jan-13
15-Feb-13
10-Feb-13
27-Mar-13
40
45
17-Mar-13
01-May-13
26-Apr-13
10-Jun-13
40
30
31-May-13
30-Jun-13
10-Jul-13
09-Aug-13
40
326
17-Jul-12
08-Jun-13
09-Sep-12
24-Aug-13
77
23-Jul-12
08-Jun-13
08-Oct-12
24-Aug-13
77
Instrumentation
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 67 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Actual Work
Critical Re...
Remaining Work
Milestone
Original
Duration
Early Start
Early Finish
23-Jul-12
25-Jul-12
08-Oct-12
10-Oct-12
77
25-Jul-12
01-Aug-12
10-Oct-12
17-Oct-12
77
15-Aug-12
22-Aug-12
31-Oct-12
07-Nov-12
77
10
21-Oct-12
31-Oct-12
06-Jan-13
16-Jan-13
77
10
30-Nov-12
10-Dec-12
15-Feb-13
25-Feb-13
77
45
10-Dec-12
24-Jan-13
25-Feb-13
11-Apr-13
77
45
23-Feb-13
09-Apr-13
11-May-13
25-Jun-13
77
30
09-May-13
08-Jun-13
25-Jul-13
24-Aug-13
77
320
23-Jul-12
08-Jun-13
08-Oct-12
24-Aug-13
77
23-Jul-12
25-Jul-12
08-Oct-12
10-Oct-12
77
25-Jul-12
01-Aug-12
10-Oct-12
17-Oct-12
77
15-Aug-12
22-Aug-12
31-Oct-12
07-Nov-12
77
10
21-Oct-12
31-Oct-12
06-Jan-13
16-Jan-13
77
10
30-Nov-12
10-Dec-12
15-Feb-13
25-Feb-13
77
45
10-Dec-12
24-Jan-13
25-Feb-13
11-Apr-13
77
PETROJET CO
Page 68 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
45
23-Feb-13
09-Apr-13
11-May-13
25-Jun-13
77
30
09-May-13
08-Jun-13
25-Jul-13
24-Aug-13
77
17-Jul-12
02-Jun-13
09-Sep-12
26-Jul-13
54
17-Jul-12
19-Jul-12
09-Sep-12
11-Sep-12
54
19-Jul-12
26-Jul-12
11-Sep-12
18-Sep-12
54
09-Aug-12
16-Aug-12
02-Oct-12
09-Oct-12
54
10
15-Oct-12
25-Oct-12
08-Dec-12
18-Dec-12
54
10
24-Nov-12
04-Dec-12
17-Jan-13
27-Jan-13
54
45
04-Dec-12
18-Jan-13
27-Jan-13
13-Mar-13
54
45
17-Feb-13
03-Apr-13
12-Apr-13
27-May-13
54
30
03-May-13
02-Jun-13
26-Jun-13
26-Jul-13
54
320
09-Aug-12
25-Jun-13
06-Oct-12
22-Aug-13
58
09-Aug-12
11-Aug-12
06-Oct-12
08-Oct-12
58
11-Aug-12
18-Aug-12
08-Oct-12
15-Oct-12
58
01-Sep-12
08-Sep-12
29-Oct-12
05-Nov-12
58
POCM1100
POCM1110
POCM1120
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 69 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
POCM1130
Actual Work
Critical Re...
Remaining Work
Milestone
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
07-Nov-12
17-Nov-12
04-Jan-13
14-Jan-13
58
17-Dec-12
27-Dec-12
13-Feb-13
23-Feb-13
58
27-Dec-12
10-Feb-13
23-Feb-13
09-Apr-13
58
12-Mar-13
26-Apr-13
09-May-13
23-Jun-13
58
26-May-13
25-Jun-13
23-Jul-13
22-Aug-13
58
30-Jul-12
27-Jun-13
01-Sep-12
26-Jul-13
29
120
30-Jul-12
27-Nov-12
01-Sep-12
30-Dec-12
33
30-Jul-12
01-Aug-12
01-Sep-12
03-Sep-12
33
01-Aug-12
08-Aug-12
03-Sep-12
10-Sep-12
33
22-Aug-12
29-Aug-12
24-Sep-12
01-Oct-12
33
10
08-Sep-12
18-Sep-12
11-Oct-12
21-Oct-12
33
10
28-Sep-12
08-Oct-12
31-Oct-12
10-Nov-12
33
10
18-Oct-12
28-Oct-12
20-Nov-12
30-Nov-12
33
10
07-Nov-12
17-Nov-12
10-Dec-12
20-Dec-12
33
10
17-Nov-12
27-Nov-12
20-Dec-12
30-Dec-12
33
PETROJET CO
Page 70 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
PSUB1100
PSUB1110
PSUB1120
PSUB1130
PSUB1140
Actual Work
Critical Re...
Remaining Work
Milestone
Original
Duration
Early Start
290
10-Sep-12
27-Jun-13
09-Oct-12
26-Jul-13
29
10-Sep-12
12-Sep-12
09-Oct-12
11-Oct-12
29
12-Sep-12
19-Sep-12
11-Oct-12
18-Oct-12
29
03-Oct-12
10-Oct-12
01-Nov-12
08-Nov-12
29
10
09-Dec-12
19-Dec-12
07-Jan-13
17-Jan-13
29
10
18-Jan-13
28-Jan-13
16-Feb-13
26-Feb-13
29
45
28-Jan-13
14-Mar-13
26-Feb-13
12-Apr-13
29
45
29-Mar-13
13-May-13
27-Apr-13
11-Jun-13
29
30
28-May-13
27-Jun-13
26-Jun-13
26-Jul-13
29
355
25-Apr-12
04-Sep-13
03-Apr-12
25-Nov-13
58
25-Apr-12
09-May-12
11
25-Apr-12
03-Apr-12
-15
27-May-12
17-Jul-12
37
0
0
Early Finish
Late Start
21-May-12
27-Jun-12
PETROJET CO
Page 71 of 266
Late Finish
03-Jul-12
11-Jul-12
Total
Float 2012
2013
J
2014
32
11
Date
19-Jul-12
Revision
Rev(5)
Checked
Y.Abdalshaf...
Approved
21-Jul-12 22:12
Activity Name
PSUB1150
Original
Duration
Early Start
18-Jul-12
01-Aug-12
11
08-Aug-12
30-Aug-12
17
08-Aug-12
22-Aug-12
11
22-Aug-12
13-Sep-12
17
03-Oct-12
13-Nov-12
30
26-Dec-12
05-Feb-13
30
Early Finish
Late Start
20-Mar-13
Late Finish
30-Apr-13
23-Jul-13
Total
Float 2012
12-Jun-13
30
04-Sep-13
04-Sep-13
25-Nov-13
25-Nov-13
58
378
02-Sep-12
25-Nov-13
19-Sep-12
27-Nov-13
378
02-Sep-12
25-Nov-13
22-Sep-12
27-Nov-13
237
02-Sep-12
11-Jun-13
22-Sep-12
25-Jul-13
37
72
02-Sep-12
27-Nov-12
22-Sep-12
12-Jan-13
37
10
02-Sep-12
15-Sep-12
22-Sep-12
03-Oct-12
16
CPA1110
Right Of Way
15
05-Sep-12
23-Sep-12
24-Sep-12
11-Oct-12
16
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 72 of 266
2014
30
CPA1100
Actual Work
2013
J
Date
19-Jul-12
Revision
Rev(5)
Checked
Y.Abdalshaf...
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
CPA1120
Trench Excavation
15
11-Sep-12
29-Sep-12
30-Sep-12
17-Oct-12
16
CPA1130
13
19-Sep-12
04-Oct-12
08-Oct-12
23-Oct-12
16
13
25-Sep-12
10-Oct-12
14-Oct-12
29-Oct-12
16
CPA1150
15
29-Sep-12
16-Oct-12
17-Oct-12
04-Nov-12
16
CPA1160
15
04-Oct-12
22-Oct-12
17-Nov-12
05-Dec-12
37
CPA1170
15
10-Oct-12
28-Oct-12
24-Nov-12
11-Dec-12
37
CPA1180
Pre-Padding
15
16-Oct-12
03-Nov-12
29-Nov-12
17-Dec-12
37
CPA1190
Lowering Of Pipeline
15
22-Oct-12
08-Nov-12
05-Dec-12
23-Dec-12
37
CPA1200
Tie-Ins Of Strings
15
28-Oct-12
14-Nov-12
11-Dec-12
30-Dec-12
37
CPA1210
Post Padding
15
03-Nov-12
20-Nov-12
17-Dec-12
06-Jan-13
37
CPA1220
Final Backfilling
15
08-Nov-12
27-Nov-12
23-Dec-12
12-Jan-13
37
76
16-Sep-12
15-Dec-12
11-Oct-12
29-Jan-13
37
CPA1140
CPB1100
10
16-Sep-12
27-Sep-12
11-Oct-12
23-Oct-12
22
CPB1110
Right Of Way
15
23-Sep-12
10-Oct-12
11-Oct-12
29-Oct-12
16
CPB1120
Trench Excavation
15
29-Sep-12
16-Oct-12
17-Oct-12
04-Nov-12
16
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 73 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
13
07-Oct-12
22-Oct-12
25-Oct-12
10-Nov-12
16
13
13-Oct-12
28-Oct-12
31-Oct-12
15-Nov-12
16
CPB1150
15
16-Oct-12
03-Nov-12
04-Nov-12
21-Nov-12
16
CPB1160
15
22-Oct-12
08-Nov-12
05-Dec-12
23-Dec-12
37
CPB1170
15
28-Oct-12
14-Nov-12
11-Dec-12
30-Dec-12
37
CPB1180
Pre-Padding
15
03-Nov-12
20-Nov-12
17-Dec-12
06-Jan-13
37
CPB1190
Lowering Of Pipeline
15
08-Nov-12
27-Nov-12
23-Dec-12
12-Jan-13
37
15
14-Nov-12
03-Dec-12
30-Dec-12
17-Jan-13
37
15
20-Nov-12
09-Dec-12
06-Jan-13
23-Jan-13
37
15
27-Nov-12
15-Dec-12
12-Jan-13
29-Jan-13
37
80
29-Sep-12
03-Jan-13
29-Oct-12
16-Feb-13
37
CPB1130
CPB1140
Early Finish
Late Start
Late Finish
Total
Float 2012
CPC1100
10
29-Sep-12
10-Oct-12
29-Oct-12
10-Nov-12
26
CPC1110
Right Of Way
15
10-Oct-12
28-Oct-12
29-Oct-12
15-Nov-12
16
CPC1120
Trench Excavation
15
16-Oct-12
03-Nov-12
04-Nov-12
21-Nov-12
16
CPC1130
13
24-Oct-12
08-Nov-12
12-Nov-12
28-Nov-12
16
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 74 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
13
30-Oct-12
14-Nov-12
18-Nov-12
04-Dec-12
16
CPC1150
15
03-Nov-12
20-Nov-12
21-Nov-12
10-Dec-12
16
CPC1160
15
08-Nov-12
27-Nov-12
23-Dec-12
12-Jan-13
37
CPC1170
15
14-Nov-12
03-Dec-12
30-Dec-12
17-Jan-13
37
CPC1180
Pre-Padding
15
20-Nov-12
09-Dec-12
06-Jan-13
23-Jan-13
37
CPC1190
Lowering Of Pipeline
15
27-Nov-12
15-Dec-12
12-Jan-13
29-Jan-13
37
15
03-Dec-12
20-Dec-12
17-Jan-13
04-Feb-13
37
15
09-Dec-12
27-Dec-12
23-Jan-13
10-Feb-13
37
15
15-Dec-12
03-Jan-13
29-Jan-13
16-Feb-13
37
84
11-Oct-12
21-Jan-13
15-Nov-12
05-Mar-13
37
CPC1140
Early Finish
Late Start
Late Finish
Total
Float 2012
CPD1100
10
11-Oct-12
23-Oct-12
15-Nov-12
28-Nov-12
30
CPD1110
Right Of Way
15
28-Oct-12
14-Nov-12
15-Nov-12
04-Dec-12
16
CPD1120
Trench Excavation
15
03-Nov-12
20-Nov-12
21-Nov-12
10-Dec-12
16
CPD1130
13
11-Nov-12
27-Nov-12
01-Dec-12
16-Dec-12
16
13
17-Nov-12
03-Dec-12
06-Dec-12
22-Dec-12
16
CPD1140
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 75 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
CPD1150
Welding Of Pipes
15
20-Nov-12
09-Dec-12
10-Dec-12
29-Dec-12
16
CPD1160
15
27-Nov-12
15-Dec-12
12-Jan-13
29-Jan-13
37
CPD1170
15
03-Dec-12
20-Dec-12
17-Jan-13
04-Feb-13
37
CPD1180
Pre-Padding
15
09-Dec-12
27-Dec-12
23-Jan-13
10-Feb-13
37
CPD1190
Lowering Of Pipeline
15
15-Dec-12
03-Jan-13
29-Jan-13
16-Feb-13
37
15
20-Dec-12
09-Jan-13
04-Feb-13
21-Feb-13
37
15
27-Dec-12
15-Jan-13
10-Feb-13
27-Feb-13
37
15
03-Jan-13
21-Jan-13
16-Feb-13
05-Mar-13
37
88
24-Oct-12
07-Feb-13
04-Dec-12
23-Mar-13
37
CPE1100
10
24-Oct-12
05-Nov-12
04-Dec-12
16-Dec-12
34
CPE1110
Right Of Way
15
14-Nov-12
03-Dec-12
04-Dec-12
22-Dec-12
16
CPE1120
Trench Excavation
15
20-Nov-12
09-Dec-12
10-Dec-12
29-Dec-12
16
CPE1130
13
29-Nov-12
15-Dec-12
18-Dec-12
05-Jan-13
16
13
05-Dec-12
20-Dec-12
24-Dec-12
10-Jan-13
16
15
09-Dec-12
27-Dec-12
29-Dec-12
16-Jan-13
16
CPE1140
CPE1150
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 76 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
CPE1160
15
15-Dec-12
03-Jan-13
29-Jan-13
16-Feb-13
37
CPE1170
15
20-Dec-12
09-Jan-13
04-Feb-13
21-Feb-13
37
CPE1180
Pre-Padding
15
27-Dec-12
15-Jan-13
10-Feb-13
27-Feb-13
37
CPE1190
Lowering Of Pipeline
15
03-Jan-13
21-Jan-13
16-Feb-13
05-Mar-13
37
15
09-Jan-13
27-Jan-13
21-Feb-13
11-Mar-13
37
15
15-Jan-13
02-Feb-13
27-Feb-13
17-Mar-13
37
15
21-Jan-13
07-Feb-13
05-Mar-13
23-Mar-13
37
92
06-Nov-12
25-Feb-13
22-Dec-12
09-Apr-13
37
CPF1100
10
06-Nov-12
18-Nov-12
22-Dec-12
05-Jan-13
38
CPF1110
Right Of Way
15
03-Dec-12
20-Dec-12
22-Dec-12
10-Jan-13
16
CPF1120
Trench Excavation
15
09-Dec-12
27-Dec-12
29-Dec-12
16-Jan-13
16
CPF1130
13
17-Dec-12
03-Jan-13
07-Jan-13
22-Jan-13
16
13
23-Dec-12
09-Jan-13
13-Jan-13
28-Jan-13
16
CPF1150
15
27-Dec-12
15-Jan-13
16-Jan-13
03-Feb-13
16
CPF1160
15
03-Jan-13
21-Jan-13
16-Feb-13
05-Mar-13
37
CPF1140
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 77 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
CPF1170
15
09-Jan-13
27-Jan-13
21-Feb-13
11-Mar-13
37
CPF1180
Pre-Padding
15
15-Jan-13
02-Feb-13
27-Feb-13
17-Mar-13
37
CPF1190
Lowering Of Pipeline
15
21-Jan-13
07-Feb-13
05-Mar-13
23-Mar-13
37
CPF1200
Tie-Ins Of Strings
15
27-Jan-13
13-Feb-13
11-Mar-13
28-Mar-13
37
CPF1210
Post Padding
15
02-Feb-13
19-Feb-13
17-Mar-13
03-Apr-13
37
CPF1220
Final Backfilling
15
07-Feb-13
25-Feb-13
23-Mar-13
09-Apr-13
37
96
19-Nov-12
14-Mar-13
10-Jan-13
27-Apr-13
37
10
19-Nov-12
02-Dec-12
10-Jan-13
22-Jan-13
42
CPG1110
15
20-Dec-12
09-Jan-13
10-Jan-13
28-Jan-13
16
15
27-Dec-12
15-Jan-13
16-Jan-13
03-Feb-13
16
13
06-Jan-13
21-Jan-13
24-Jan-13
09-Feb-13
16
13
12-Jan-13
27-Jan-13
30-Jan-13
14-Feb-13
16
15
15-Jan-13
02-Feb-13
03-Feb-13
20-Feb-13
16
15
21-Jan-13
07-Feb-13
05-Mar-13
23-Mar-13
37
15
27-Jan-13
13-Feb-13
11-Mar-13
28-Mar-13
37
Right Of Way
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 78 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
CPG1180 Pre-Padding
15
02-Feb-13
19-Feb-13
17-Mar-13
03-Apr-13
37
15
07-Feb-13
25-Feb-13
23-Mar-13
09-Apr-13
37
15
13-Feb-13
03-Mar-13
28-Mar-13
15-Apr-13
37
15
19-Feb-13
09-Mar-13
03-Apr-13
21-Apr-13
37
15
25-Feb-13
14-Mar-13
09-Apr-13
27-Apr-13
37
100
03-Dec-12
01-Apr-13
28-Jan-13
14-May-13
37
Early Finish
Late Start
Late Finish
Total
Float 2012
CPH1100
10
03-Dec-12
15-Dec-12
28-Jan-13
09-Feb-13
46
CPH1110
Right Of Way
15
09-Jan-13
27-Jan-13
28-Jan-13
14-Feb-13
16
CPH1120
Trench Excavation
15
15-Jan-13
02-Feb-13
03-Feb-13
20-Feb-13
16
CPH1130
13
23-Jan-13
07-Feb-13
11-Feb-13
26-Feb-13
16
13
29-Jan-13
13-Feb-13
17-Feb-13
04-Mar-13
16
CPH1150
15
02-Feb-13
19-Feb-13
20-Feb-13
10-Mar-13
16
CPH1160
15
07-Feb-13
25-Feb-13
23-Mar-13
09-Apr-13
37
CPH1170
15
13-Feb-13
03-Mar-13
28-Mar-13
15-Apr-13
37
CPH1180
Pre-Padding
15
19-Feb-13
09-Mar-13
03-Apr-13
21-Apr-13
37
CPH1140
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 79 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
15
25-Feb-13
14-Mar-13
09-Apr-13
27-Apr-13
37
15
03-Mar-13
20-Mar-13
15-Apr-13
02-May-13
37
15
09-Mar-13
26-Mar-13
21-Apr-13
08-May-13
37
15
14-Mar-13
01-Apr-13
27-Apr-13
14-May-13
37
104
16-Dec-12
18-Apr-13
14-Feb-13
02-Jun-13
37
CPH1190
Lowering Of Pipeline
Early Finish
Late Start
Late Finish
Total
Float 2012
CPI1100
10
16-Dec-12
29-Dec-12
14-Feb-13
26-Feb-13
50
CPI1110
Right Of Way
15
27-Jan-13
13-Feb-13
14-Feb-13
04-Mar-13
16
CPI1120
Trench Excavation
15
02-Feb-13
19-Feb-13
20-Feb-13
10-Mar-13
16
CPI1130
13
10-Feb-13
25-Feb-13
28-Feb-13
16-Mar-13
16
13
16-Feb-13
03-Mar-13
06-Mar-13
21-Mar-13
16
CPI1150
15
19-Feb-13
09-Mar-13
10-Mar-13
27-Mar-13
16
CPI1160
15
25-Feb-13
14-Mar-13
09-Apr-13
27-Apr-13
37
CPI1170
15
03-Mar-13
20-Mar-13
15-Apr-13
02-May-13
37
CPI1180
Pre-Padding
15
09-Mar-13
26-Mar-13
21-Apr-13
08-May-13
37
CPI1190
Lowering Of Pipeline
15
14-Mar-13
01-Apr-13
27-Apr-13
14-May-13
37
CPI1140
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 80 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
CPI1200
Tie-Ins Of Strings
15
20-Mar-13
07-Apr-13
02-May-13
20-May-13
37
CPI1210
Post Padding
15
26-Mar-13
13-Apr-13
08-May-13
26-May-13
37
CPI1220
Final Backfilling
15
01-Apr-13
18-Apr-13
14-May-13
02-Jun-13
37
108
30-Dec-12 06-May-13
04-Mar-13
19-Jun-13
37
CPJ1100
10
30-Dec-12
12-Jan-13
04-Mar-13
16-Mar-13
54
CPJ1110
Right Of Way
15
13-Feb-13
03-Mar-13
04-Mar-13
21-Mar-13
16
CPJ1120
Trench Excavation
15
19-Feb-13
09-Mar-13
10-Mar-13
27-Mar-13
16
CPJ1130
13
27-Feb-13
14-Mar-13
18-Mar-13
02-Apr-13
16
13
05-Mar-13
20-Mar-13
24-Mar-13
08-Apr-13
16
CPJ1150
15
09-Mar-13
26-Mar-13
27-Mar-13
14-Apr-13
16
CPJ1160
15
14-Mar-13
01-Apr-13
27-Apr-13
14-May-13
37
CPJ1170
15
20-Mar-13
07-Apr-13
02-May-13
20-May-13
37
CPJ1180
Pre-Padding
15
26-Mar-13
13-Apr-13
08-May-13
26-May-13
37
CPJ1190
Lowering Of Pipeline
15
01-Apr-13
18-Apr-13
14-May-13
02-Jun-13
37
CPJ1200
Tie-Ins Of Strings
15
07-Apr-13
24-Apr-13
20-May-13
08-Jun-13
37
CPJ1140
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 81 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
CPJ1210
Post Padding
15
13-Apr-13
30-Apr-13
26-May-13
13-Jun-13
37
CPJ1220
Final Backfilling
15
18-Apr-13
06-May-13
02-Jun-13
19-Jun-13
37
112
13-Jan-13
23-May-13
25-Mar-13
08-Jul-13
37
CPK1100
10
13-Jan-13
24-Jan-13
25-Mar-13
06-Apr-13
61
CPK1110
Right Of Way
15
03-Mar-13
20-Mar-13
25-Mar-13
11-Apr-13
19
CPK1120
Trench Excavation
15
09-Mar-13
26-Mar-13
31-Mar-13
17-Apr-13
19
CPK1130
13
14-Mar-13
30-Mar-13
04-Apr-13
20-Apr-13
18
13
20-Mar-13
04-Apr-13
10-Apr-13
25-Apr-13
18
CPK1150
15
26-Mar-13
13-Apr-13
14-Apr-13
01-May-13
16
CPK1160
15
01-Apr-13
18-Apr-13
14-May-13
02-Jun-13
37
CPK1170
15
07-Apr-13
24-Apr-13
20-May-13
08-Jun-13
37
CPK1180
Pre-Padding
15
13-Apr-13
30-Apr-13
26-May-13
13-Jun-13
37
CPK1190
Lowering Of Pipeline
15
18-Apr-13
06-May-13
02-Jun-13
19-Jun-13
37
15
24-Apr-13
12-May-13
08-Jun-13
25-Jun-13
37
15
30-Apr-13
18-May-13
13-Jun-13
01-Jul-13
37
CPK1140
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 82 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
15
06-May-13 23-May-13
19-Jun-13
08-Jul-13
37
116
26-Jan-13
11-Jun-13
11-Apr-13
25-Jul-13
37
CPL1100
10
26-Jan-13
06-Feb-13
11-Apr-13
23-Apr-13
65
CPL1110
Right Of Way
15
20-Mar-13
07-Apr-13
11-Apr-13
29-Apr-13
19
CPL1120
Trench Excavation
15
26-Mar-13
13-Apr-13
17-Apr-13
05-May-13
19
CPL1130
13
31-Mar-13
15-Apr-13
22-Apr-13
07-May-13
19
13
06-Apr-13
21-Apr-13
28-Apr-13
13-May-13
19
CPL1150
15
13-Apr-13
30-Apr-13
01-May-13
19-May-13
16
CPL1160
15
18-Apr-13
06-May-13
02-Jun-13
19-Jun-13
37
CPL1170
15
24-Apr-13
12-May-13
08-Jun-13
25-Jun-13
37
CPL1180
Pre-Padding
15
30-Apr-13
18-May-13
13-Jun-13
01-Jul-13
37
CPL1190
Lowering Of Pipeline
15
06-May-13 23-May-13
19-Jun-13
08-Jul-13
37
CPL1200
Tie-Ins Of Strings
15
12-May-13 30-May-13
25-Jun-13
14-Jul-13
37
CPL1210
Post Padding
15
18-May-13
05-Jun-13
01-Jul-13
20-Jul-13
37
CPL1220
Final Backfilling
15
23-May-13
11-Jun-13
08-Jul-13
25-Jul-13
37
CPL1140
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 83 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
CPCR100
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
164
15-Nov-12 30-May-13
20-Jan-13
01-Aug-13
53
164
15-Nov-12 30-May-13
20-Jan-13
01-Aug-13
53
144
20-Dec-12
10-Jun-13
24-Feb-13
13-Aug-13
54
CPCR1110
46
20-Dec-12
14-Feb-13
24-Feb-13
18-Apr-13
54
CPCR1120
46
18-Feb-13
13-Apr-13
22-Apr-13
16-Jun-13
54
CPCR1130
46
16-Apr-13
10-Jun-13
19-Jun-13
13-Aug-13
54
287
29-Oct-12
06-Oct-13
17-Dec-12
03-Nov-13
24
204
29-Oct-12
29-Jun-13
17-Dec-12
31-Jul-13
27
180
29-Oct-12
01-Jun-13
17-Dec-12
20-Jul-13
41
180
27-Nov-12
29-Jun-13
30-Dec-12
31-Jul-13
27
80
02-Jul-13
06-Oct-13
31-Jul-13
03-Nov-13
24
20
02-Jul-13
27-Jul-13
31-Jul-13
24-Aug-13
24
20
09-Jul-13
01-Aug-13
06-Aug-13
29-Aug-13
24
20
15-Jul-13
07-Aug-13
12-Aug-13
05-Sep-13
24
10
07-Aug-13
19-Aug-13
05-Sep-13
17-Sep-13
24
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 84 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
20
19-Aug-13
12-Sep-13
17-Sep-13
10-Oct-13
24
20
12-Sep-13
06-Oct-13
10-Oct-13
03-Nov-13
24
34
23-May-13
03-Jul-13
21-Jul-13
29-Aug-13
48
22
23-May-13
19-Jun-13
21-Jul-13
27-Aug-13
58
23-May-13 26-May-13
21-Jul-13
23-Jul-13
48
28-May-13
03-Jun-13
24-Jul-13
30-Jul-13
48
03-Jun-13
08-Jun-13
30-Jul-13
04-Aug-13
48
08-Jun-13
17-Jun-13
08-Aug-13
18-Aug-13
52
17-Jun-13
19-Jun-13
25-Aug-13
27-Aug-13
58
22
08-Jun-13
03-Jul-13
04-Aug-13
29-Aug-13
48
08-Jun-13
10-Jun-13
04-Aug-13
06-Aug-13
48
11-Jun-13
17-Jun-13
07-Aug-13
13-Aug-13
48
17-Jun-13
22-Jun-13
13-Aug-13
18-Aug-13
48
22-Jun-13
01-Jul-13
18-Aug-13
27-Aug-13
48
01-Jul-13
03-Jul-13
27-Aug-13
29-Aug-13
48
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 85 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Hydraulic Test
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
113
17-Jun-13
29-Oct-13
13-Aug-13
21-Nov-13
20
CPHT1100
14
17-Jun-13
03-Jul-13
13-Aug-13
29-Aug-13
48
CPHT1110
45
06-Aug-13
29-Sep-13
29-Aug-13
22-Oct-13
20
CPHT1120
Pipeline Pressurizing
10
29-Sep-13
10-Oct-13
22-Oct-13
03-Nov-13
20
CPHT1130
15
12-Oct-13
29-Oct-13
04-Nov-13
21-Nov-13
20
141
11-Jun-13
25-Nov-13
25-Jul-13
27-Nov-13
Common Activities
CPCA1100
30
11-Jun-13
17-Jul-13
25-Jul-13
29-Aug-13
37
CPCA1110
ROW Re-Instatement
60
04-Aug-13
14-Oct-13
17-Sep-13
26-Nov-13
37
CPCA1120
30
21-Oct-13
25-Nov-13
23-Oct-13
27-Nov-13
360
05-Sep-12
05-Nov-13
19-Sep-12
27-Nov-13
19
354
05-Sep-12
29-Oct-13
19-Sep-12
27-Nov-13
25
183
05-Sep-12
10-Apr-13
19-Sep-12
19-May-13
34
39
05-Sep-12
21-Oct-12
19-Sep-12
12-Jan-13
69
CRCU1100
Excavation For Culvert No. (1)
05-Sep-12
11-Sep-12
19-Sep-12
25-Sep-12
13
11-Sep-12
20-Sep-12
25-Sep-12
04-Oct-12
13
QP Refinery
Civil Work
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 86 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
CRCU1120
RC For Culvert No. (1)
16
20-Sep-12
09-Oct-12
04-Oct-12
23-Oct-12
13
CRCU1130
Backfilling For Culvert No. (1)
10
09-Oct-12
21-Oct-12
30-Dec-12
12-Jan-13
69
39
03-Oct-12
18-Nov-12
17-Oct-12
23-Jan-13
55
CRCU1200
Excavation For Culvert No. (2)
03-Oct-12
09-Oct-12
17-Oct-12
23-Oct-12
13
CRCU1210
PC For Culvert No. (2)
09-Oct-12
18-Oct-12
23-Oct-12
01-Nov-12
13
CRCU1220
RC For Culvert No. (2)
16
18-Oct-12
06-Nov-12
01-Nov-12
20-Nov-12
13
CRCU1230
Backfilling For Culvert No. (2)
10
06-Nov-12
18-Nov-12
12-Jan-13
23-Jan-13
55
39
31-Oct-12
17-Dec-12
14-Nov-12
04-Feb-13
41
CRCU1300
Excavation For Culvert No. (3)
31-Oct-12
06-Nov-12
14-Nov-12
20-Nov-12
13
CRCU1310
PC For Culvert No. (3)
06-Nov-12
15-Nov-12
20-Nov-12
01-Dec-12
13
CRCU1320
RC For Culvert No. (3)
16
15-Nov-12
05-Dec-12
01-Dec-12
19-Dec-12
13
CRCU1330
Backfilling For Culvert No. (3)
10
05-Dec-12
17-Dec-12
23-Jan-13
04-Feb-13
41
39
29-Nov-12
16-Jan-13
13-Dec-12
16-Feb-13
27
CRCU1400
Excavation For Culvert No. (4)
29-Nov-12
05-Dec-12
13-Dec-12
19-Dec-12
13
CRCU1410
PC For Culvert No. (4)
05-Dec-12
15-Dec-12
19-Dec-12
30-Dec-12
13
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 87 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
CRCU1420
RC For Culvert No. (4)
16
15-Dec-12
05-Jan-13
30-Dec-12
19-Jan-13
13
CRCU1430
Backfilling For Culvert No. (4)
10
05-Jan-13
16-Jan-13
04-Feb-13
16-Feb-13
27
39
29-Dec-12
13-Feb-13
13-Jan-13
27-Feb-13
13
CRCU1500
Excavation For Culvert No. (5)
29-Dec-12
05-Jan-13
13-Jan-13
19-Jan-13
13
CRCU1510
PC For Culvert No. (5)
05-Jan-13
14-Jan-13
19-Jan-13
28-Jan-13
13
CRCU1520
RC For Culvert No. (5)
16
14-Jan-13
02-Feb-13
28-Jan-13
16-Feb-13
13
CRCU1530
Backfilling For Culvert No. (5)
10
02-Feb-13
13-Feb-13
16-Feb-13
27-Feb-13
13
39
27-Jan-13
13-Mar-13
06-Mar-13
07-May-13
48
CRCU1600
Excavation For Culvert No. (6)
27-Jan-13
02-Feb-13
06-Mar-13
12-Mar-13
34
CRCU1610
PC For Culvert No. (6)
02-Feb-13
11-Feb-13
12-Mar-13
21-Mar-13
34
CRCU1620
RC For Culvert No. (6)
16
11-Feb-13
02-Mar-13
21-Mar-13
09-Apr-13
34
CRCU1630
Backfilling For Culvert No. (6)
10
02-Mar-13
13-Mar-13
25-Apr-13
07-May-13
48
39
24-Feb-13
10-Apr-13
03-Apr-13
19-May-13
34
CRCU1700
Excavation For Culvert No. (7)
24-Feb-13
02-Mar-13
03-Apr-13
09-Apr-13
34
CRCU1710
PC For Culvert No. (7)
02-Mar-13
11-Mar-13
09-Apr-13
18-Apr-13
34
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 88 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
CRCU1720
RC For Culvert No. (7)
16
11-Mar-13
30-Mar-13
18-Apr-13
07-May-13
34
CRCU1730
Backfilling For Culvert No. (7)
10
30-Mar-13
10-Apr-13
07-May-13
19-May-13
34
120
06-Nov-12
30-Mar-13
16-Dec-12
07-May-13
34
75
06-Nov-12
05-Feb-13
16-Dec-12
16-Mar-13
34
75
31-Dec-12
30-Mar-13
09-Feb-13
07-May-13
34
157
13-Feb-13
18-Aug-13
27-Feb-13
01-Sep-13
12
14
13-Feb-13
02-Mar-13
27-Feb-13
16-Mar-13
12
02-Mar-13
07-Mar-13
16-Mar-13
21-Mar-13
12
16
07-Mar-13
26-Mar-13
21-Mar-13
09-Apr-13
12
26-Mar-13
01-Apr-13
09-Apr-13
15-Apr-13
12
01-Apr-13
04-Apr-13
15-Apr-13
18-Apr-13
12
04-Apr-13
14-Apr-13
18-Apr-13
28-Apr-13
12
28
14-Apr-13
16-May-13
28-Apr-13
01-Jun-13
12
60
25-May-13 05-Aug-13
18-Jun-13
28-Aug-13
20
60
08-Jun-13
22-Jun-13
01-Sep-13
12
SER12 Extension
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
18-Aug-13
PETROJET CO
Page 89 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Pump House
Original
Duration
Early Start
Early Finish
Late Start
Late Finish
Total
Float 2012
204
02-Mar-13
29-Oct-13
17-Mar-13
27-Nov-13
25
22
22-May-13
18-Jun-13
08-Jun-13
28-Jul-13
33
CRCP1700
Excavation For E&I Duct Bank
22-May-13 29-May-13
08-Jun-13
13-Jun-13
13
CRCP1710
PC For E&I Duct Bank
29-May-13
04-Jun-13
13-Jun-13
19-Jun-13
13
CRCP1720
RC For E&I Duct Bank
10
04-Jun-13
16-Jun-13
19-Jun-13
01-Jul-13
13
16-Jun-13
18-Jun-13
25-Jul-13
28-Jul-13
33
72
02-Mar-13
25-May-13
17-Mar-13
13-Jul-13
40
22
02-Mar-13
27-Mar-13
17-Mar-13
30-Jun-13
80
02-Mar-13
07-Mar-13
17-Mar-13
23-Mar-13
13
07-Mar-13
13-Mar-13
23-Mar-13
28-Mar-13
13
10
13-Mar-13
25-Mar-13
28-Mar-13
09-Apr-13
13
25-Mar-13
27-Mar-13
27-Jun-13
30-Jun-13
80
22
13-Mar-13
08-Apr-13
28-Mar-13
02-Jul-13
72
13-Mar-13
19-Mar-13
28-Mar-13
03-Apr-13
13
19-Mar-13
25-Mar-13
03-Apr-13
09-Apr-13
13
CRCP1730
Backfilling For E&I Duct Bank
Pump Foundations
CRCP1100
Excavation For Main Pump No.
(1)
CRCP1110
PC For Main Pump No. (1)
CRCP1120
RC For Main Pump No. (1)
CRCP1130
Backfilling For Main Pump No.
(1)
Main Pump No. (2)
CRCP1200
Excavation For Main Pump No.
(2)
CRCP1210
PC For Main Pump No. (2)
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 90 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
10
25-Mar-13
06-Apr-13
09-Apr-13
21-Apr-13
13
06-Apr-13
08-Apr-13
30-Jun-13
02-Jul-13
72
22
25-Mar-13
20-Apr-13
09-Apr-13
06-Jul-13
64
25-Mar-13
31-Mar-13
09-Apr-13
15-Apr-13
13
31-Mar-13
06-Apr-13
15-Apr-13
21-Apr-13
13
10
06-Apr-13
17-Apr-13
21-Apr-13
02-May-13
13
17-Apr-13
20-Apr-13
02-Jul-13
06-Jul-13
64
22
06-Apr-13
01-May-13
21-Apr-13
08-Jul-13
56
CRCP1400
Excavation For Booster Pump
No. (1)
CRCP1410
PC For Booster Pump No. (1)
06-Apr-13
11-Apr-13
21-Apr-13
27-Apr-13
13
11-Apr-13
17-Apr-13
27-Apr-13
02-May-13
13
CRCP1420
RC For Booster Pump No. (1)
10
17-Apr-13
29-Apr-13
02-May-13
14-May-13
13
CRCP1430
Backfilling For Booster Pump
No. (1)
29-Apr-13
01-May-13
06-Jul-13
08-Jul-13
56
22
17-Apr-13
13-May-13
02-May-13
10-Jul-13
48
17-Apr-13
23-Apr-13
02-May-13
08-May-13
13
23-Apr-13
29-Apr-13
08-May-13
14-May-13
13
CRCP1220
RC For Main Pump No. (2)
CRCP1230
Backfilling For Main Pump No.
(2)
Main Pump No. (3)
CRCP1300
Excavation For Main Pump No.
(3)
CRCP1310
PC For Main Pump No. (3)
CRCP1320
RC For Main Pump No. (3)
CRCP1330
Backfilling For Main Pump No.
(3)
Booster Pump No. (1)
CRCP1500
Excavation For Booster Pump
No. (2)
CRCP1510
PC For Booster Pump No. (2)
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 91 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
CRCP1520
RC For Booster Pump No. (2)
10
29-Apr-13
CRCP1530
Backfilling For Booster Pump
No. (2)
Early Finish
11-May-13
11-May-13 13-May-13
Late Start
Late Finish
Total
Float 2012
14-May-13
26-May-13
13
08-Jul-13
10-Jul-13
48
22
29-Apr-13
25-May-13
14-May-13
13-Jul-13
40
CRCP1600
Excavation For Booster Pump
No. (3)
CRCP1610
PC For Booster Pump No. (3)
29-Apr-13
05-May-13
14-May-13
20-May-13
13
05-May-13 11-May-13
20-May-13
26-May-13
13
CRCP1620
RC For Booster Pump No. (3)
10
11-May-13 22-May-13
26-May-13
08-Jun-13
13
CRCP1630
Backfilling For Booster Pump
No. (3)
22-May-13 25-May-13
10-Jul-13
13-Jul-13
40
169
11-Apr-13
29-Oct-13
03-Jun-13
27-Nov-13
25
CRCD1100
Steel Structure Fabrication For
The Pump Shed
CRCD1110Excavation For For The Pump
Shed
CRCD1120
PC For For The Pump Shed
60
11-Apr-13
22-Jun-13
03-Jun-13
13-Aug-13
44
10
22-May-13
04-Jun-13
08-Jun-13
19-Jun-13
13
10
04-Jun-13
16-Jun-13
19-Jun-13
01-Jul-13
13
CRCD1130
RC For For The Pump Shed
20
16-Jun-13
10-Jul-13
01-Jul-13
25-Jul-13
13
CRCD1140
Backfilling For The Pump Shed
10-Jul-13
15-Jul-13
28-Jul-13
01-Aug-13
15
CRCD1150
Steel Structure Erection For The
Pump Shed
CRCD1160
Corrugated Sheets Cladding For
The Pump Shed
30
15-Jul-13
19-Aug-13
13-Aug-13
18-Sep-13
25
15
19-Aug-13
07-Sep-13
18-Sep-13
06-Oct-13
25
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 92 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
CRCD1170
Paving For The Pump Shed
15
07-Sep-13
24-Sep-13
06-Oct-13
23-Oct-13
25
CRCD1180
Insulation & Fireproofing
30
24-Sep-13
29-Oct-13
23-Oct-13
27-Nov-13
25
81
22-May-13 27-Aug-13
15-Jun-13
12-Sep-13
13
22-May-13 30-May-13
15-Jun-13
22-Jun-13
19
Launcher Station
Early Finish
Late Start
Late Finish
Total
Float 2012
10
30-May-13
11-Jun-13
22-Jun-13
03-Jul-13
19
18
18-Jun-13
10-Jul-13
03-Jul-13
25-Jul-13
13
10-Jul-13
17-Jul-13
25-Jul-13
01-Aug-13
13
20
17-Jul-13
10-Aug-13
01-Aug-13
25-Aug-13
13
15
10-Aug-13
27-Aug-13
25-Aug-13
12-Sep-13
13
45
15-Aug-13
08-Oct-13
31-Aug-13
23-Oct-13
13
25
15-Aug-13
15-Sep-13
31-Aug-13
30-Sep-13
13
10
15-Sep-13
26-Sep-13
30-Sep-13
12-Oct-13
13
10
26-Sep-13
08-Oct-13
12-Oct-13
23-Oct-13
13
159
30-Apr-13
05-Nov-13
19-May-13
07-Nov-13
40
30-Apr-13
17-Jun-13
19-May-13
13-Aug-13
48
Roads
Mechanical Work
General
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 93 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
30
30-Apr-13
05-Jun-13
19-May-13
24-Jun-13
16
06-Jun-13
17-Jun-13
03-Aug-13
13-Aug-13
48
159
30-Apr-13
05-Nov-13
19-May-13
07-Nov-13
60
30-Apr-13
11-Jul-13
19-May-13
30-Jul-13
16
48
22-May-13
20-Jul-13
02-Jul-13
28-Aug-13
34
60
28-Jul-13
07-Oct-13
30-Jul-13
09-Oct-13
15
07-Oct-13
24-Oct-13
09-Oct-13
27-Oct-13
15
13-Oct-13
30-Oct-13
15-Oct-13
02-Nov-13
15
19-Oct-13
05-Nov-13
21-Oct-13
07-Nov-13
12
23-Sep-13
07-Oct-13
25-Sep-13
09-Oct-13
32
17-Jul-13
24-Aug-13
10-Aug-13
17-Sep-13
20
15
17-Jul-13
04-Aug-13
10-Aug-13
27-Aug-13
20
15
25-Jul-13
12-Aug-13
18-Aug-13
05-Sep-13
20
15
06-Aug-13
24-Aug-13
29-Aug-13
17-Sep-13
20
119
10-Jun-13
29-Oct-13
16-Jul-13
16-Nov-13
15
Launcher Station
E&I Work
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 94 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
119
10-Jun-13
29-Oct-13
16-Jul-13
16-Nov-13
15
59
10-Jun-13
19-Aug-13
16-Jul-13
24-Sep-13
30
30
10-Jun-13
16-Jul-13
16-Jul-13
20-Aug-13
30
30
22-Jun-13
28-Jul-13
28-Jul-13
01-Sep-13
30
30
15-Jul-13
19-Aug-13
19-Aug-13
24-Sep-13
30
20
18-Aug-13
11-Sep-13
01-Sep-13
25-Sep-13
12
CREE1100
Lighting Fixtures, Sockets For
Rooms
CREE1110Low Voltage Cables
18-Aug-13
25-Aug-13
01-Sep-13
09-Sep-13
12
24-Aug-13
31-Aug-13
08-Sep-13
15-Sep-13
12
CREE1120
Termination
04-Sep-13
11-Sep-13
18-Sep-13
25-Sep-13
12
CREE1130
UPS System 110 V, 1 ph, 7 KVA
27-Aug-13
04-Sep-13
11-Sep-13
18-Sep-13
12
34
19-Sep-13
29-Oct-13
07-Oct-13
16-Nov-13
15
CREP1100
Lighting System For Pump Area
19-Sep-13
29-Sep-13
07-Oct-13
16-Oct-13
15
25-Sep-13
05-Oct-13
13-Oct-13
22-Oct-13
15
CREP1120
Low Voltage Cable Laying For
Pump Area
CREP1130
High Voltage Cable Laying For
Pump Area
29-Sep-13
08-Oct-13
16-Oct-13
26-Oct-13
15
02-Oct-13
12-Oct-13
20-Oct-13
29-Oct-13
15
Electrical
Substation 6003
CRES1100
Modification Of Existing 11 KV
Switchgear
CRES1110Modification Of Existing 3.3 KV
Switchgear
CRES1120
Modification Of Existing 415 V
Switchgear
Extension Of SER 12
Pump Area
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 95 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
06-Oct-13
15-Oct-13
23-Oct-13
02-Nov-13
15
12
15-Oct-13
29-Oct-13
02-Nov-13
16-Nov-13
15
31
22-Sep-13
28-Oct-13
09-Oct-13
16-Nov-13
16
22-Sep-13
29-Sep-13
09-Oct-13
16-Oct-13
15
28-Sep-13
05-Oct-13
15-Oct-13
22-Oct-13
15
03-Oct-13
10-Oct-13
22-Oct-13
29-Oct-13
16
09-Oct-13
16-Oct-13
28-Oct-13
04-Nov-13
16
15-Oct-13
22-Oct-13
03-Nov-13
10-Nov-13
16
10
16-Oct-13
28-Oct-13
04-Nov-13
16-Nov-13
16
60
19-Aug-13
29-Oct-13
24-Sep-13
16-Nov-13
15
24
11-Sep-13
09-Oct-13
25-Sep-13
23-Oct-13
12
CRIE1100Laying of Cables
11-Sep-13
18-Sep-13
25-Sep-13
02-Oct-13
12
18-Sep-13
25-Sep-13
02-Oct-13
09-Oct-13
12
21-Sep-13
28-Sep-13
05-Oct-13
12-Oct-13
12
23-Sep-13
30-Sep-13
07-Oct-13
14-Oct-13
12
CREP1140
Installation Of Distribution
Boards For Pump Area
CREP1150
Termination For Pump Area
Launcher Area
Extension Of SER 12
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 96 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
25-Sep-13
02-Oct-13
09-Oct-13
16-Oct-13
12
02-Oct-13
09-Oct-13
16-Oct-13
23-Oct-13
12
29
25-Sep-13
29-Oct-13
13-Oct-13
16-Nov-13
15
CRIP1100Laying Of Cables
25-Sep-13
05-Oct-13
13-Oct-13
22-Oct-13
15
29-Sep-13
08-Oct-13
16-Oct-13
26-Oct-13
15
02-Oct-13
12-Oct-13
20-Oct-13
29-Oct-13
15
06-Oct-13
15-Oct-13
23-Oct-13
02-Nov-13
15
09-Oct-13
19-Oct-13
27-Oct-13
05-Nov-13
15
13-Oct-13
22-Oct-13
30-Oct-13
09-Nov-13
15
16-Oct-13
26-Oct-13
03-Nov-13
12-Nov-13
15
20-Oct-13
29-Oct-13
06-Nov-13
16-Nov-13
15
27
28-Sep-13
29-Oct-13
15-Oct-13
16-Nov-13
15
28-Sep-13
05-Oct-13
15-Oct-13
22-Oct-13
15
01-Oct-13
08-Oct-13
19-Oct-13
26-Oct-13
15
05-Oct-13
12-Oct-13
22-Oct-13
29-Oct-13
15
Launcher Area
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 97 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
08-Oct-13
15-Oct-13
26-Oct-13
02-Nov-13
15
12-Oct-13
19-Oct-13
29-Oct-13
05-Nov-13
15
15-Oct-13
22-Oct-13
02-Nov-13
09-Nov-13
15
19-Oct-13
26-Oct-13
05-Nov-13
12-Nov-13
15
22-Oct-13
29-Oct-13
09-Nov-13
16-Nov-13
15
25
19-Aug-13
18-Sep-13
24-Sep-13
23-Oct-13
30
CRIS1100Laying of Cables
10
19-Aug-13
31-Aug-13
24-Sep-13
06-Oct-13
30
10
31-Aug-13
12-Sep-13
06-Oct-13
17-Oct-13
30
10
07-Sep-13
18-Sep-13
12-Oct-13
23-Oct-13
30
92
18-Jul-13
04-Nov-13
01-Aug-13
27-Nov-13
20
25
08-Aug-13
08-Sep-13
12-Oct-13
10-Nov-13
54
CRIL1140Installation Of Pressure
Transmitters With Tubes &
Fittings
CRIL1150Installation Of Junction Boxes
For Launcher
CRIL1160Installation Of Gas Detectors For
Launcher
CRIL1170Installation Of Manual Call Point
For Launcher
CRIL1180Termination For Launcher
Substation 6003
BSV (3)
Civil Works
Early Finish
Late Start
Late Finish
Total
Float 2012
CBSC1100
Excavation In BSV-3
10
08-Aug-13
20-Aug-13
12-Oct-13
23-Oct-13
54
CBSC1110
10
14-Aug-13
26-Aug-13
17-Oct-13
29-Oct-13
54
CBSC1120
10
20-Aug-13
01-Sep-13
23-Oct-13
04-Nov-13
54
CBSC1130
Fence In BSV-3
10
26-Aug-13
08-Sep-13
29-Oct-13
10-Nov-13
54
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Page 98 of 266
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
Original
Duration
Early Start
64
20-Aug-13
04-Nov-13
23-Oct-13
27-Nov-13
20
15
20-Aug-13
08-Sep-13
23-Oct-13
10-Nov-13
54
29-Oct-13
04-Nov-13
21-Nov-13
27-Nov-13
20
90
18-Jul-13
02-Nov-13
01-Aug-13
27-Nov-13
22
90
18-Jul-13
02-Nov-13
01-Aug-13
27-Nov-13
22
10
18-Jul-13
30-Jul-13
01-Aug-13
13-Aug-13
12
10
04-Sep-13
16-Sep-13
18-Sep-13
30-Sep-13
12
10
21-Oct-13
02-Nov-13
16-Nov-13
27-Nov-13
22
30
04-Sep-13
09-Oct-13
18-Sep-13
23-Oct-13
12
10
04-Sep-13
16-Sep-13
18-Sep-13
30-Sep-13
12
10
16-Sep-13
28-Sep-13
30-Sep-13
12-Oct-13
12
10
28-Sep-13
09-Oct-13
12-Oct-13
23-Oct-13
12
151
24-Nov-13 21-May-14
26-Nov-13
24-May-14
60
24-Nov-13
04-Feb-14
26-Nov-13
06-Feb-14
60
07-Dec-13
16-Feb-14
09-Dec-13
18-Feb-14
Mechanical Works
CBSM1100
CBSM1120
E&I Works
Electrical
Instrumentation
Pre-Commissioning/Commissioning
FCOM1100
FCOM1110
Actual Work
Critical Re...
Remaining Work
Milestone
Early Finish
PETROJET CO
Page 99 of 266
Late Start
Late Finish
Date
19-Jul-12
Total
Float 2012
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
FCOM1120
FCOM1130
FCOM1140
FCOM1150
FCOM1160
FCOM1170
FCOM1180
FCOM1190
Original
Duration
Early Start
60
18-Dec-13
27-Feb-14
21-Dec-13
02-Mar-14
60
31-Dec-13
11-Mar-14
02-Jan-14
13-Mar-14
60
12-Jan-14
23-Mar-14
14-Jan-14
25-Mar-14
60
23-Jan-14
03-Apr-14
26-Jan-14
06-Apr-14
60
04-Feb-14
15-Apr-14
06-Feb-14
17-Apr-14
15-Apr-14
19-Apr-14
17-Apr-14
21-Apr-14
System Readiness To Be
Operated
Jet A1 Fuel Ready To Be Taken
- In
16
19-Apr-14
07-May-14
21-Apr-14
10-May-14
10
10-May-14 21-May-14
12-May-14
24-May-14
447
05-Nov-12
24-Dec-12
28-Jul-14
150
05-Nov-12 31-May-13
24-Dec-12
19-Jul-13
35
10
20-May-13 31-May-13
01-Aug-13
15-Aug-13
54
36
11-Jun-14
16-Jun-14
28-Jul-14
74
31-May-14 25-Aug-14
18-Jun-14
25-Aug-14
Optional Items
OPT1100
OPT1110
OPT1120
Early Finish
23-Jul-14
23-Jul-14
Late Start
Late Finish
Total
Float 2012
FPCO1100
As-Built Drawings
50
31-May-14
28-Jul-14
18-Jun-14
16-Aug-14
16
FPCO1110
40
01-Jun-14
17-Jul-14
30-Jun-14
16-Aug-14
25
Actual Work
Critical Re...
Remaining Work
Milestone
PETROJET CO
Date
19-Jul-12
Revision
Rev(5)
2013
J
Checked
Y.Abdalshaf...
2014
Approved
21-Jul-12 22:12
Activity Name
FPCO1120
Project Handover
Actual Work
Critical Re...
Remaining Work
Milestone
Original
Duration
Early Start
50
28-Jun-14
Early Finish
25-Aug-14
PETROJET CO
Late Start
28-Jun-14
Late Finish
25-Aug-14
Date
19-Jul-12
Total
Float 2012
2013
J
2014
Revision
Rev(5)
Checked
Y.Abdalshaf...
Approved
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
MANPOWER SCHEDULE AND HISTOGRAM
______________________________________
July-12
August-12
September-12
October-12
November-12
December-12
January-13
February-13
March-13
April-13
May-13
June-13
July-13
August-13
September-13
October-13
November-13
December-13
January-14
February-14
March-14
April-14
12
12
16
16
16
16
16
16
16
16
16
16
16
Pipe Fitter
12
12
12
16
16
16
16
16
16
16
16
16
16
16
15
15
15
20
20
20
20
20
20
20
20
20
20
20
10
Blasting Technician
Coating Technician
August-14
June-12
July-14
May-12
June-14
April-12
May-14
March-12
Rigger
Direct Labour
Mechanical Labour
Welder
Grinder
N.D.T Technician
Hydro-test Technician
Civil Labour
Carpenter
12
12
12
12
12
12
12
12
12
Carpenter Assistant
Steel Fixer
March-13
April-13
May-13
June-13
July-13
August-13
September-13
October-13
November-13
December-13
January-14
February-14
Scafolder
Insulation Technician
Steel Welder
Erection Fitter
Electrician Technician
Instrument Technician
termination Technician
Pump Technician
August-14
February-13
July-14
January-13
June-14
December-12
May-14
November-12
April-14
October-12
March-14
September-12
August-12
July-12
June-12
May-12
April-12
March-12
Direct Labour
E&I Labour
Cathodic Protection
Technican
General Labour
Survyor
June-12
July-12
August-12
September-12
October-12
November-12
December-12
January-13
February-13
March-13
April-13
May-13
June-13
July-13
August-13
September-13
October-13
November-13
December-13
January-14
February-14
March-14
April-14
May-14
June-14
July-14
August-14
Surveyor Assistant
May-12
April-12
March-12
Direct Labour
Skilled Labor
10
10
10
10
10
10
10
10
10
10
10
10
10
Un Skilled Labor
10
10
10
15
15
15
15
15
15
15
15
15
15
15
15
10
Maintenance Labor
Safety Officers
Dozer Operator
Grader Operator
Loader Operator
June-13
July-13
August-13
September-13
October-13
November-13
December-13
August-14
May-13
July-14
April-13
June-14
March-13
May-14
February-13
April-14
January-13
March-14
December-12
February-14
November-12
January-14
October-12
Trailer Driver
September-12
August-12
July-12
June-12
May-12
April-12
Tractor Driver
March-12
Direct Labour
10
11
43
113
136
171
189
188
189
190
195
195
201
199
192
187
175
124
60
43
34
28
25
25
14
12
August-13
September-13
October-13
November-13
December-13
January-14
February-14
March-14
April-14
May-14
June-14
July-14
August-14
November-12
July-13
October-12
June-13
September-12
May-13
August-12
April-13
July-12
March-13
June-12
February-13
May-12
January-13
April-12
December-12
March-12
In-Direct Labour
Engineeres Staff
Mechanical Engineer
Civil Engineer
E&I Engineer
Planning Engineer
Inspection Engineer
H.S.E Engineer
Purchasing Engineer
November-12
December-12
January-13
February-13
March-13
April-13
May-13
June-13
July-13
August-13
September-13
October-13
November-13
December-13
January-14
February-14
March-14
April-14
May-14
Welder Supervisor
Civil Supervisor
Fitting-Up Supervisor
E&I Supervisor
Coating Supervisor
Rigger Supervisor
H.S.E Supervisor
Equipment Supervisor
Maintenance Supervisor
Fitting-Up Supervisor
E&I Supervisor
Coating Supervisor
Rigger Supervisor
Welder Supervisor
Civil Supervisor
August-14
September-12
July-14
August-12
June-14
July-12
June-12
May-12
April-12
Maintenance Engineer
March-12
In-Direct Labour
December-12
January-13
February-13
March-13
April-13
May-13
June-13
July-13
August-13
September-13
October-13
November-13
December-13
January-14
February-14
March-14
April-14
May-14
Equipment Supervisor
Maintenance Supervisor
Accountant
Purchasing Executive
Security Executive
Guardman
Doctor
35
53
62
63
65
65
65
67
68
79
83
83
83
80
77
76
74
46
46
45
45
44
44
13
11
11
July-12
June-12
May-12
April-12
Administrator
March-12
August-14
October-12
July-14
September-12
June-14
August-12
H.S.E Supervisor
In-Direct Labour
Others
Total
16
19
19
200
Number
150
100
50
0
Series1
1
0
2
0
3
4
4
10
5
11
6
43
7
113
8
136
9
171
10
189
11
188
12
189
13
190
14
195
15
195
16
201
17
199
18
192
19
187
20
175
21
124
22
60
23
43
24
34
25
28
26
25
27
25
28
14
29
12
30
8
90
80
70
Number
60
50
40
30
20
10
0
In-Direct Labour
1
7
2
16
3
19
4
19
5
35
6
53
7
62
8
63
9
65
10
65
11
65
12
67
13
68
14
79
15
83
16
83
17
83
18
80
19
77
20
76
21
74
22
46
23
46
24
45
25
45
26
44
27
44
28
13
29
11
30
11
200
Number
150
100
50
0
Series1
1
0
2
0
3
4
4
10
5
11
6
43
7
113
8
136
9
171
10
189
11
188
12
189
13
190
14
195
15
195
16
201
17
199
18
192
19
187
20
175
21
124
22
60
23
43
24
34
25
28
26
25
27
25
28
14
29
12
30
8
250
Number
200
150
100
50
0
Total Labour
1
7
2
16
3
23
4
29
5
46
6
7
8
9
10 11 12 13 14 15 16 17 18 19 20 21 22 23
96 175 199 236 254 253 256 258 274 278 284 282 272 264 251 198 106 89
24
79
25
73
26
69
27
69
28
27
29
23
30
19
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
EQUIPMENT DEPLOYMENT
______________________________________
March-13
April-13
May-13
June-13
July-13
August-13
September-13
October-13
November-13
December-13
January-14
Grader
Loader
Truck
Trailer
July-12
June-12
May-12
April-12
March-12
Tractor
Concrete Pump
Aspalt Finisher
Fork Lift
Side Boom
Water Tank
12
16
20
20
20
20
20
20
20
20
12
12
12
16
Crane up to 60 ton
Welding Machine
Flat bed
August-14
February-13
July-14
January-13
June-14
December-12
May-14
November-12
April-14
October-12
March-14
September-12
February-14
August-12
Dozer
Equipment
August-13
September-13
October-13
November-13
Filling Pump
Handling Pump
Pressurizing Pump
Generator
August-14
July-13
July-14
June-13
June-14
May-13
Blasting Compressor
May-14
April-13
April-14
March-13
March-14
February-13
February-14
January-13
January-14
December-12
December-13
November-12
October-12
September-12
August-12
July-12
June-12
May-12
April-12
March-12
Equipment
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
PROGRESS MEASUREMENT SYSTEM (PMS)
INCLUDING EDR & PSR
______________________________________
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
ENGINEERING DOCUMENT REGISTER
(EDR)
______________________________________
DESCRIPTION
THIS WEEK
UP TO DATE
REL. WT. %
PLANNED %
ACTUAL %
DEV. %
PLANNED %
ACTUAL %
DEV. %
PLANNED %
ACTUAL %
DEV. %
GENERAL
4.59
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PROCESS
6.34
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
LOSS PREVENTION
2.37
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
4.26
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PIPELINE
8.85
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
MECHANICAL/PIPING
10.51
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
INSTRUMENTATION
9.96
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
TELECOMMUNICATION
1.05
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
ELECTRICAL
15.73
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
10
27.38
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
11
BUILDING SERVICES
2.08
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
12
CATHODIC PROTECTION
1.88
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
95.00
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
5.0%
5.0%
40.0%
29Apr12
1May12
1May12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
WTD
WTG
85.0%
95.0%
1Jul12
1Jul12
PRG
Remarks
Planned
Actual
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00000
0.00%
0.00
0.00%
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.000
0.00%
0.000
0.00%
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
10May12
11Jun12
24Jun12
0.00%
1.149
8Apr12
10Apr12
10Apr12
8May12
14May12
15Jul12
22Jul12
0.00%
0.00%
22Jul12
2.455
16Apr12
18Apr12
18Apr12
3May12
27Jun12
18Jul12
25Jul12
0.00%
0.00%
25Jul12
0.833
5Jul12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.158
0.00%
4.595
PROCESS
REPORTS/CALCULATIONS
3392-32-00-36-0001 Steady State Hydraulic Analysis/Report
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
29May12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
4Jun12
31May12
31May12
20Jun12
15Jul12
5Aug12
12Aug12
12Aug12
0.00%
0.526
10Jun12
18Jun12
21Jun12
12Jul12
19Jul12
9Aug12
16Aug12
0.00%
0.00%
16Aug12
0.789
21Jun12
28Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.395
25Jun12
1Jul12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.316
27Jun12
1Jul12
4Jul12
25Jul12
1Aug12
22Aug12
29Aug12
0.00%
0.00%
29Aug12
0.105
0.00%
DRAWINGS
3392-32-00-41-0001 Schematic Flow Diagrams
3392-32-00-31-0001 PFDs
3392-32-00-30-0009
6Jun12
7Jun12
28Jun12
5Jul12
26Jul12
2Aug12
2Aug12
0.00%
0.158
3Jun12
6Jun12
7Jun12
28Jun12
5Jul12
26Jul12
2Aug12
0.00%
0.00%
2Aug12
0.210
4Jun12
6Jun12
7Jun12
28Jun12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.552
3Jun12
4Jun12
7Jun12
28Jun12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.263
6/32012
4Jun12
7Jun12
28Jun12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.263
3Jun12
4Jun12
7Jun12
28Jun12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.263
4Jun12
6Jun12
7Jun12
24Jun12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.263
12Jun12
14Jun12
19Jun12
9Jul12
30Jul12
20Aug12
27Aug12
0.00%
0.00%
27Aug12
0.263
3Jun12
4Jun12
7Jun12
28Jun12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.263
4Jun12
6Jun12
7Jun12
28Jun12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.263
4Jun12
6Jun12
7Jun12
28Jun12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.263
28Jun12
4Jul12
8Jul12
29Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.263
28Jun12
4Jul12
8Jul12
15Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.263
14Jun12
18Jun12
20Jun12
8Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.658
0.00%
6.340
LOSS PREVENTION
PHILOSOPHIES / SCHEDULES
3392-32-19-53-0001 Fire Protection and Safety Philosophy
P
F
F
A
P
F
F
A
P
F
F
A
1Aug12
5Aug12
7Aug12
28Aug12
4Sep12
25Sep12
2Oct12
2Oct12
0.00%
0.158
25Jul12
29Jul12
31Jul12
21Aug12
28Aug12
18Sep12
25Sep12
0.00%
0.00%
25Sep12
0.079
4Jul12
5Jul12
12Jul12
2Aug12
9Aug12
30Aug12
6Sep12
0.00%
0.00%
6Sep12
0.079
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
5.0%
5.0%
40.0%
P
F
F
A
P
F
F
A
P
F
F
A
17Jun12
19Jun12
1Jul12
P
F
F
A
P
F
F
A
1Aug12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
5Aug12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
WTD
WTG
85.0%
95.0%
26Aug12
26Aug12
PRG
Remarks
Planned
Actual
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.000
0.00%
0.000
0.00%
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
SPECIFICATIONS
3392-32-19-17-0001
22Jul12
29Jul12
19Aug12
0.00%
0.237
17Jun12
19Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.079
10Jul12
11Jul12
12Jul12
2Aug12
9Aug12
30Aug12
6Sep12
0.00%
0.00%
6Sep12
0.158
0.00%
5Aug12
7Aug12
28Aug12
4Sep12
25Sep12
2Oct12
2Oct12
0.00%
0.474
1Aug12
6Aug12
6Aug12
27Aug12
3Sep12
24Sep12
1Oct12
0.00%
0.00%
1Oct12
0.395
0.00%
DRAWINGS
3392-32-19-21-0001
3392-32-19-21-0002
12Aug12
14Aug12
4Sep12
11Sep12
2Oct12
9Oct12
9Oct12
0.00%
0.158
5Aug12
12Aug12
14Aug12
4Sep12
11Sep12
2Oct12
9Oct12
0.00%
0.00%
9Oct12
0.158
19Jul12
29Jul12
30Jul12
20Aug12
27Aug12
17Sep12
24Sep12
0.00%
0.00%
24Sep12
0.079
5Aug12
7Aug12
8Aug12
29Aug12
5Sep12
26Sep12
3Oct12
0.00%
0.00%
3Oct12
0.158
5Aug12
12Aug12
12Aug12
2Sep12
9Sep12
30Sep12
7Oct12
0.00%
0.00%
7Oct12
0.158
0.00%
2.368
3392-32-15-17-0021
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
12Jun12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
14Jun12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
13Jun12
P
F
F
A
9Sep12
13Jun12
20Jun12
11Jul12
18Jul12
8Aug12
15Aug12
15Aug12
0.00%
0.088
3Jul12
10Jul12
12Jul12
2Aug12
9Aug12
30Aug12
6Sep12
0.00%
0.00%
6Sep12
0.039
5Aug12
5Aug12
5Aug12
26Aug12
2Sep12
23Sep12
30Sep12
0.00%
0.00%
30Sep12
0.039
5Aug12
5Aug12
5Aug12
26Aug12
2Sep12
23Sep12
30Sep12
0.00%
0.00%
30Sep12
0.079
0.00%
DATA SHEETS
3392-32-15-12-0027 Data Sheet for Flame Detectors
24Jun12
26Jun12
17Jul12
24Jul12
14Aug12
21Aug12
21Aug12
0.00%
0.053
14Jun12
24Jun12
26Jun12
17Jul12
24Jul12
14Aug12
21Aug12
0.00%
0.00%
21Aug12
0.035
14Jun12
24Jun12
26Jun12
17Jul12
24Jul12
14Aug12
21Aug12
0.00%
0.00%
21Aug12
0.044
14Jun12
24Jun12
26Jun12
17Jul12
24Jul12
14Aug12
21Aug12
0.00%
0.00%
21Aug12
0.053
22Jul12
24Jul12
25Jul12
15Aug12
22Aug12
12Sep12
19Sep12
0.00%
0.00%
19Sep12
0.061
14Jun12
24Jun12
26Jun12
17Jul12
24Jul12
14Aug12
21Aug12
0.00%
0.00%
21Aug12
0.053
14Jun12
24Jun12
26Jun12
17Jul12
24Jul12
14Aug12
21Aug12
0.00%
0.00%
21Aug12
0.044
14Jun12
24Jun12
26Jun12
17Jul12
24Jul12
14Aug12
21Aug12
0.00%
0.00%
21Aug12
0.035
0.00%
MATERIAL REQUISITIONS
3392-RQ-32-15-0020 MRs for F&G Devices (Detectors & Alarm Devices)
13Jun12
14Jun12
5Jul12
12Jul12
2Aug12
9Aug12
9Aug12
0.00%
0.035
27Jun12
27Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
0.00%
0.00%
23Aug12
0.022
27Jun12
27Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
0.00%
0.00%
23Aug12
0.044
27Jun12
27Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
0.00%
0.00%
23Aug12
0.022
0.00%
DOCUMENTS / DRAWINGS
Common
3392-32-15-39-0001 F&G devices typical installation details
10Sep12
10Sep12
1Oct12
8Oct12
29Oct12
5Nov12
5Nov12
0.00%
0.281
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
5.0%
5.0%
40.0%
P
F
F
A
P
F
F
A
15Aug12
21Aug12
21Aug12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
1Aug12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
11Sep12
18Sep12
9Oct12
WTD
WTG
85.0%
95.0%
16Oct12
16Oct12
PRG
27Aug12
27Aug12
17Sep12
24Sep12
15Oct12
22Oct12
Remarks
Planned
Actual
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.000
0.00%
0.000
0.00%
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00%
0.403
21Aug12
0.00%
0.00%
22Oct12
0.403
0.00%
QP Refinery
3392-32-15-39-0004 F&G Cause and Effect
2Jul12
20Aug12
10Sep12
17Sep12
8Oct12
15Oct12
15Oct12
0.00%
0.237
22Jul12
29Jul12
29Jul12
19Aug12
26Aug12
16Sep12
23Sep12
0.00%
0.00%
23Sep12
0.386
22Jul12
29Jul12
29Jul12
19Aug12
26Aug12
16Sep12
23Sep12
0.00%
0.00%
23Sep12
0.351
24Jul12
30Jul12
30Jul12
20Aug12
27Aug12
17Sep12
24Sep12
0.00%
0.00%
24Sep12
0.368
7Aug12
12Aug12
12Aug12
2Sep12
9Sep12
30Sep12
7Oct12
0.00%
0.00%
7Oct12
0.447
30Jul12
31Jul12
1Aug12
22Aug12
29Aug12
19Sep12
26Sep12
0.00%
0.00%
26Sep12
0.316
2Aug12
5Aug12
6Aug12
27Aug12
3Sep12
24Sep12
1Oct12
0.00%
0.00%
1Oct12
0.324
0.00%
4.262
PIPELINE
SPECIFICATIONS
3392-33-13-17-3001 Specifications for Hot Induction Bends
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
29Apr12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
9May12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
5Jun12
P
F
F
A
10Jul12
30Apr12
1May12
20May12
23May12
8Jul12
15Jul12
15Jul12
0.00%
0.070
29Apr12
30Apr12
1May12
20May12
23May12
8Jul12
15Jul12
0.00%
0.00%
15Jul12
0.070
30Apr12
2May12
2May12
20May12
23May12
8Jul12
15Jul12
0.00%
0.00%
15Jul12
0.070
30Apr12
2May12
2May12
20May12
23May12
8Jul12
15Jul12
0.00%
0.00%
15Jul12
0.070
6May12
7May12
7May12
27May12
19Jun12
10Jul12
17Jul12
0.00%
0.00%
17Jul12
0.070
7May12
13May12
14May12
28May12
4Jun12
25Jun12
2Jul12
0.00%
0.00%
2Jul12
0.070
0.00%
DATA SHEETS
3392-33-13-12-3001 Data Sheet for Hot Induction Bends
9May12
9May12
30May12
5Jun12
26Jun12
2Jul12
2Jul12
0.00%
0.053
9May12
9May12
9May12
21May12
0.00%
0.00%
14Jun12
0.053
9May12
10May12
13May12
28May12
0.00%
0.00%
14Jun12
0.053
9May12
10May12
13May12
28May12
0.00%
0.00%
14Jun12
0.053
0.00%
MATERIAL REQUISITIONS
3392-RQ-33-13-3001 MR for Isolation Joints
5Jun12
10Jun12
17Jun12
25Jun12
16Jul12
23Jul12
23Jul12
0.00%
0.044
5Jun12
3Jun12
10Jun12
17Jun12
25Jun12
16Jul12
23Jul12
0.00%
0.00%
23Jul12
0.044
5Jun12
3Jun12
10Jun12
17Jun12
25Jun12
16Jul12
23Jul12
0.00%
0.00%
23Jul12
0.044
5Jun12
3Jun12
10Jun12
17Jun12
25Jun12
16Jul12
23Jul12
0.00%
0.00%
23Jul12
0.044
5Jun12
3Jun12
10Jun12
17Jun12
25Jun12
16Jul12
23Jul12
0.00%
0.00%
23Jul12
0.044
5Jun12
3Jun12
10Jun12
17Jun12
25Jun12
16Jul12
23Jul12
0.00%
0.00%
23Jul12
0.044
5Jun12
3Jun12
10Jun12
17Jun12
25Jun12
16Jul12
23Jul12
0.00%
0.00%
23Jul12
0.044
0.00%
MTOs
3392-33-13-91-3001 Pipeline Material Take-Off
22Jul12
23Jul12
23Jul12
23Jul12
23Jul12
23Jul12
23Jul12
0.00%
0.263
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
5.0%
5.0%
40.0%
9May12
28May12
5Jun12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
WTD
WTG
85.0%
95.0%
27Jun12
PRG
Remarks
Planned
Actual
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
CALCULATIONS
3392-33-13-20-3050 Pipeline Wall Thickness Calculation
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
24Jun12
0.00%
0.079
14May12
28May12
5Jun12
24Jun12
0.00%
0.00%
27Jun12
0.079
16May12
28May12
5Jun12
24Jun12
27Jun12
18Jul12
25Jul12
0.00%
0.00%
25Jul12
0.132
17May12
28May12
5Jun12
24Jun12
27Jun12
18Jul12
25Jul12
0.00%
0.00%
25Jul12
0.105
17May12
28May12
5Jun12
24Jun12
27Jun12
18Jul12
25Jul12
0.00%
0.00%
25Jul12
0.105
0.00%
REPORTS
3392-33-13-17-3007 Pipeline Pigging Philosophy
P
F
F
A
25Jun12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
12Jun12
27Jun12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
0.00%
0.158
0.00%
17Jun12
19Jun12
10Jul12
18Jul12
8Aug12
15Aug12
15Aug12
0.00%
0.175
18Jun12
1Jul12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.088
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.114
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.114
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.114
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.114
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.114
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.114
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.114
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.114
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.114
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.114
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.114
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.053
18Jun12
21Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.00%
0.00%
26Aug12
0.061
3Jul12
5Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.088
5Jul12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.105
5Jul12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.105
5Jul12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.105
5Jul12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.105
5Jul12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.105
5Jul12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.105
5Jul12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.105
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
5.0%
5.0%
40.0%
5Jul12
8Jul12
8Jul12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
29Jul12
5Aug12
26Aug12
WTD
WTG
85.0%
95.0%
2Sep12
2Sep12
PRG
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Sep12
29Jul12
29Jul12
19Aug12
26Aug12
16Sep12
23Sep12
2Sep12
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00%
0.00%
23Sep12
0.184
0.00%
0.0000
0.00%
0.00%
0.105
23Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
0.0000
0.00%
0.00%
0.105
5Jul12
Actual
0.00%
0.00%
0.105
5Jul12
Planned
0.00%
0.00%
0.105
5Jul12
Remarks
0.00%
0.105
5Jul12
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
3392-33-13-20-3039
3392-33-13-50-3008
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
5.0%
5.0%
40.0%
10Jul12
15Jul12
15Jul12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
5Aug12
12Aug12
2Sep12
WTD
WTG
85.0%
95.0%
9Sep12
9Sep12
PRG
11Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
11Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
20Aug12
11Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
20Aug12
19Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
20Aug12
11Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
20Aug12
11Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
20Aug12
11Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
20Aug12
11Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
20Aug12
19Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
20Aug12
8Jul12
9Jul12
30Jul12
6Aug12
27Aug12
3Sep12
20Aug12
8Jul12
9Jul12
30Jul12
6Aug12
27Aug12
3Sep12
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.000
0.00%
0.000
0.00%
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00%
0.00%
3Sep12
0.193
5Jul12
0.0000
0.00%
0.00%
0.044
5Jul12
0.0000
0.00%
0.00%
0.044
19Jun12
0.0000
0.00%
0.00%
0.044
10Jun12
0.0000
0.00%
0.00%
0.044
10Jun12
0.0000
0.00%
0.00%
0.044
10Jun12
0.0000
0.00%
0.00%
0.044
10Jun12
0.0000
0.00%
0.00%
0.044
19Jun12
Actual
0.00%
0.00%
0.044
10Jun12
Planned
0.00%
0.00%
0.044
10Jun12
Remarks
0.00%
0.184
10Jun12
0.00%
0.00%
3Sep12
0.526
0.00%
8.848
MECHANICAL/PIPING
MECHANICAL
SCHEDULES / LISTS
3392-32-13-10-0002 Equipment Schedule
P
F
F
A
13Jun12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
24May12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
10Jun12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
21May12
P
F
F
A
10Jul12
25Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
23Aug12
0.00%
0.105
0.00%
SPECIFICATIONS
3392-32-13-17-0010 Specs - Pumps
3392-32-13-17-0014
4Jun12
6Jun12
27Jun12
4Jul12
25Jul12
1Aug12
1Aug12
0.00%
0.079
5Jun12
10Jun12
10Jun12
1Jul12
8Jul12
29Jul12
5Aug12
0.00%
0.00%
5Aug12
0.053
17Jun12
19Jun12
20Jun12
8Jul12
16Jul12
6Aug12
13Aug12
0.00%
0.00%
13Aug12
0.000
17Jun12
19Jun12
20Jun12
9Jul12
16Jul12
6Aug12
13Aug12
0.00%
0.00%
13Aug12
0.000
0.00%
DATA SHEETS
3392-32-00-12-0007 Datasheet for Main Transfer Pumps
7Jun12
11Jun12
1Jul12
5Jul12
26Jul12
2Aug12
2Aug12
0.00%
0.079
11Jun12
7Jun12
14Jun12
4Jul12
8Jul12
29Jul12
5Aug12
0.00%
0.00%
5Aug12
0.079
5Jun12
13Jun12
13Jun12
4Jul12
11Jul12
1Aug12
8Aug12
0.00%
0.00%
8Aug12
0.079
17Jun12
27Jun12
27Jun12
18Jul12
25Jul12
15Aug12
22Aug12
0.00%
0.00%
22Aug12
0.079
18Jun12
19Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
0.00%
0.00%
23Aug12
0.079
0.00%
TECHNICAL REQUISITIONS
3392-RQ-32-13-0009 MR for Main Transfer Pumps
24May12
24May12
14Jun12
21Jun12
12Jul12
19Jul12
19Jul12
0.00%
0.079
21May12
24May12
24May12
14Jun12
21Jun12
12Jul12
19Jul12
0.00%
0.00%
19Jul12
0.079
21May12
27May12
27May12
17Jun12
24Jun12
15Jul12
22Jul12
0.00%
0.00%
22Jul12
0.053
21May12
27May12
27May12
17Jun12
24Jun12
15Jul12
22Jul12
0.00%
0.00%
22Jul12
0.053
0.00%
PIPING
SCHEDULES / LISTS
3392-32-13-10-0001 Line Schedule
15Jul12
15Jul12
5Aug12
12Aug12
2Sep12
9Sep12
9Sep12
0.00%
0.114
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
5.0%
5.0%
40.0%
12Jul12
15Jul12
17Jul12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
7Aug12
14Aug12
4Sep12
WTD
WTG
85.0%
95.0%
11Sep12
11Sep12
PRG
7Jun12
13Jun12
4Jul12
11Jul12
1Aug12
8Aug12
25Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
8Aug12
24Jul12
24Jul12
24Jul12
24Jul12
24Jul12
24Jul12
20Aug12
25Jul12
25Jul12
25Jul12
25Jul12
25Jul12
25Jul12
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00%
0.00%
24Jul12
0.368
23Jul12
Actual
0.00%
0.00%
0.237
19Jul12
Planned
0.00%
0.00%
0.105
14Jun12
Remarks
0.00%
0.132
7Jun12
0.00%
0.00%
25Jul12
0.132
0.00%
CALCULATIIONS / REPORTS
3392-32-13-20-0001 Pipe Wall thickness Calculation
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
30May12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
3Jun12
30May12
13Jun12
8Jul12
16Jul12
6Aug12
13Aug12
13Aug12
0.00%
0.079
8Aug12
12Aug12
13Aug12
3Sep12
10Sep12
1Oct12
8Oct12
0.00%
0.00%
8Oct12
0.316
8Aug12
12Aug12
13Aug12
3Sep12
10Sep12
1Oct12
8Oct12
0.00%
0.00%
8Oct12
0.316
8Aug12
12Aug12
13Aug12
3Sep12
10Sep12
1Oct12
8Oct12
0.00%
0.00%
8Oct12
0.316
28Jun12
10Jul12
12Jul12
2Aug12
9Aug12
30Aug12
6Sep12
0.00%
0.00%
6Sep12
0.079
0.00%
SPECIFICATIONS
3392-32-13-17-0001 Piping Material Specifications
3392-32-13-17-0009 Specs-Gaskets
3Jun12
13Jun12
8Jul12
16Jul12
6Aug12
13Aug12
13Aug12
0.00%
0.158
29May12
29May12
5Jun12
26Jun12
3Jul12
24Jul12
31Jul12
0.00%
0.00%
31Jul12
0.070
29May12
29May12
5Jun12
26Jun12
3Jul12
24Jul12
31Jul12
0.00%
0.00%
31Jul12
0.070
29May12
29May12
5Jun12
26Jun12
3Jul12
24Jul12
31Jul12
0.00%
0.00%
31Jul12
0.070
29May12
29May12
5Jun12
26Jun12
3Jul12
24Jul12
31Jul12
0.00%
0.00%
31Jul12
0.070
29May12
29May12
5Jun12
26Jun12
3Jul12
24Jul12
31Jul12
0.00%
0.00%
31Jul12
0.053
29May12
29May12
5Jun12
26Jun12
3Jul12
24Jul12
31Jul12
0.00%
0.00%
31Jul12
0.053
29May12
29May12
5Jun12
26Jun12
3Jul12
24Jul12
31Jul12
0.00%
0.00%
31Jul12
0.035
29May12
29May12
5Jun12
26Jun12
3Jul12
24Jul12
31Jul12
0.00%
0.00%
31Jul12
0.035
0.00%
DATA SHEETS
3392-32-00-12-0001 Data Sheet for Gate valves
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
7Jun12
10Jun12
12Jun12
1Jul12
8Jul12
29Jul12
5Aug12
5Aug12
0.00%
0.079
3Jun12
3Jun12
4Jun12
25Jun12
2Jul12
23Jul12
30Jul12
0.00%
0.00%
30Jul12
0.079
7Jun12
10Jun12
12Jun12
1Jul12
8Jul12
29Jul12
5Aug12
0.00%
0.00%
5Aug12
0.079
7Jun12
10Jun12
12Jun12
1Jul12
8Jul12
29Jul12
5Aug12
0.00%
0.00%
5Aug12
0.079
7Jun12
10Jun12
12Jun12
1Jul12
8Jul12
29Jul12
5Aug12
0.00%
0.00%
5Aug12
0.079
9Aug12
12Aug12
14Aug12
4Sep12
11Sep12
2Oct12
9Oct12
0.00%
0.00%
9Oct12
0.079
0.00%
TECHNICAL REQUISITIONS
3392-RQ-32-13-0001 MR for Gate valves
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
20May12
30May12
24May12
14Jun12
21Jun12
12Jul12
19Jul12
19Jul12
0.00%
0.035
20May12
30May12
24May12
14Jun12
21Jun12
12Jul12
19Jul12
0.00%
0.00%
19Jul12
0.035
20May12
30May12
24May12
14Jun12
21Jun12
12Jul12
19Jul12
0.00%
0.00%
19Jul12
0.035
20May12
30May12
24May12
14Jun12
21Jun12
12Jul12
19Jul12
0.00%
0.00%
19Jul12
0.035
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
5.0%
5.0%
40.0%
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
20May12
30May12
24May12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
9May12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
14Jun12
21Jun12
12Jul12
WTD
WTG
85.0%
95.0%
19Jul12
19Jul12
PRG
15Aug12
16Aug12
6Sep12
13Sep12
4Oct12
11Oct12
30May12
15May12
5Jun12
12Jun12
3Jul12
10Jul12
11Oct12
30May12
15May12
5Jun12
12Jun12
3Jul12
10Jul12
Actual
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.000
0.00%
0.000
0.00%
0.0000
0.0000
0.00%
0.00%
10Jul12
0.035
15May12
Planned
0.00%
0.00%
0.035
15May12
Remarks
0.00%
0.035
13Aug12
0.00%
0.00%
10Jul12
0.035
0.00%
DRAWINGS
3392-32-13-22-0001 Overall Plot plan - QP Refinery
10May12
17May12
4Jun12
20Jun12
8Jul12
16Jul12
16Jul12
0.00%
0.132
9May12
10May12
17May12
4Jun12
20Jun12
8Jul12
16Jul12
0.00%
0.00%
16Jul12
0.132
9May12
10May12
17May12
4Jun12
20Jun12
8Jul12
16Jul12
0.00%
0.00%
16Jul12
0.210
9May12
10May12
17May12
4Jun12
20Jun12
8Jul12
16Jul12
0.00%
0.00%
16Jul12
0.210
21Jun12
26Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
0.00%
0.00%
23Aug12
0.210
14Jun12
26Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
0.00%
0.00%
23Aug12
0.114
10Jul12
22Jul12
23Jul12
13Aug12
20Aug12
10Sep12
17Sep12
0.00%
0.00%
17Sep12
0.158
10Jul12
22Jul12
23Jul12
13Aug12
20Aug12
10Sep12
17Sep12
0.00%
0.00%
17Sep12
0.158
5Jul12
8Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
0.00%
0.00%
16Sep12
0.158
10Jul12
22Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
0.00%
0.00%
16Sep12
0.158
10Jul12
22Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
0.00%
0.00%
16Sep12
0.158
10Jul12
22Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
0.00%
0.00%
16Sep12
0.158
10Jul12
22Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
0.00%
0.00%
16Sep12
0.158
10Jul12
22Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
0.00%
0.00%
16Sep12
0.158
10Jul12
22Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
0.00%
0.00%
16Sep12
0.158
10Jul12
22Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
0.00%
0.00%
16Sep12
0.158
10Jul12
22Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
0.00%
0.00%
16Sep12
0.158
29Jul12
6Aug12
7Aug12
28Aug12
4Sep12
25Sep12
2Oct12
0.00%
0.00%
2Oct12
0.158
29Jul12
6Aug12
7Aug12
28Aug12
4Sep12
25Sep12
2Oct12
0.00%
0.00%
2Oct12
0.158
29Jul12
5Aug12
7Aug12
28Aug12
4Sep12
25Sep12
2Oct12
0.00%
0.00%
2Oct12
0.158
29Jul12
5Aug12
7Aug12
28Aug12
4Sep12
25Sep12
2Oct12
0.00%
0.00%
2Oct12
0.158
19Jul12
13Aug12
15Aug12
5Sep12
12Sep12
3Oct12
10Oct12
0.00%
0.00%
10Oct12
1.508
16Aug12
19Aug12
21Aug12
11Sep12
18Sep12
9Oct12
16Oct12
0.00%
0.00%
16Oct12
1.008
14May12
14May12
24May12
14Jun12
21Jun12
12Jul12
19Jul12
0.00%
0.00%
19Jul12
0.158
0.00%
10.505
INSTRUMENTATION
SPECIFICATIONS
3392-32-15-17-0001
P
F
F
A
20Jun12
26Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
23Aug12
0.00%
0.088
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
3392-33-15-17-0002
3392-32-15-17-0013
3392-32-15-17-0014
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
5.0%
5.0%
40.0%
14Jun12
28Jun12
28Jun12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
19Jul12
26Jul12
16Aug12
WTD
WTG
85.0%
95.0%
23Aug12
23Aug12
PRG
26Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
26Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
23Aug12
26Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
23Aug12
26Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
23Aug12
26Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
23Aug12
26Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
23Aug12
26Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
23Aug12
26Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
23Aug12
26Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
23Aug12
3Jun12
4Jun12
25Jun12
2Jul12
23Jul12
30Jul12
23Aug12
3Jun12
4Jun12
25Jun12
2Jul12
23Jul12
30Jul12
30Jul12
6Jun12
14Jun12
5Jul12
12Jul12
2Aug12
9Aug12
30Jul12
5Jun12
14Jun12
5Jul12
12Jul12
2Aug12
9Aug12
9Aug12
12Jun12
26Jun12
17Jul12
24Jul12
14Aug12
21Aug12
9Aug12
4Jul12
2Jul12
23Jul12
30Jul12
20Aug12
27Aug12
21Aug12
4Jul12
2Jul12
23Jul12
30Jul12
20Aug12
27Aug12
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00%
0.00%
27Aug12
0.044
17Jun12
0.0000
0.00%
0.00%
0.053
17Jun12
0.0000
0.00%
0.00%
0.061
12Jun12
0.0000
0.00%
0.00%
0.061
5Jun12
0.0000
0.00%
0.00%
0.088
6Jun12
0.0000
0.00%
0.00%
0.123
24May12
0.0000
0.00%
0.00%
0.053
24May12
0.0000
0.00%
0.00%
0.070
20Jun12
0.0000
0.00%
0.00%
0.061
20Jun12
0.0000
0.00%
0.00%
0.079
20Jun12
0.0000
0.00%
0.00%
0.079
20Jun12
0.0000
0.00%
0.00%
0.079
20Jun12
0.0000
0.00%
0.00%
0.053
20Jun12
Actual
0.00%
0.00%
0.053
20Jun12
Planned
0.00%
0.00%
0.053
20Jun12
Remarks
0.00%
0.088
20Jun12
0.00%
0.00%
27Aug12
0.044
0.00%
DATA SHEETS
3392-32-15-12-0001 Data Sheet for Pressure & DP Gauges
3392-32-15-12-0007 Data Sheet for Mass Flow meter & Flow Computer
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
28May12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
24May12
28May12
5Jun12
26Jun12
3Jul12
24Jul12
31Jul12
31Jul12
0.00%
0.053
28May12
28May12
5Jun12
26Jun12
3Jul12
24Jul12
31Jul12
0.00%
0.00%
31Jul12
0.053
28May12
28May12
5Jun12
26Jun12
3Jul12
24Jul12
31Jul12
0.00%
0.00%
31Jul12
0.053
10Jun12
11Jun12
11Jun12
1Jul12
5Jul12
26Jul12
31Jul12
0.00%
0.00%
31Jul12
0.070
10Jun12
10Jun12
21Jun12
12Jul12
19Jul12
9Aug12
16Aug12
0.00%
0.00%
16Aug12
0.061
10Jun12
10Jun12
21Jun12
12Jul12
19Jul12
9Aug12
16Aug12
0.00%
0.00%
16Aug12
0.061
10Jun12
10Jun12
21Jun12
12Jul12
19Jul12
9Aug12
16Aug12
0.00%
0.00%
16Aug12
0.044
10Jun12
10Jun12
21Jun12
12Jul12
19Jul12
9Aug12
16Aug12
0.00%
0.00%
16Aug12
0.070
0.00%
TECHNICAL REQUISITIONS
3392-RQ-32-15-0001 MR for Pressure Gauges
24May12
27May12
17Jun12
24Jun12
15Jul12
22Jul12
22Jul12
0.00%
0.026
20May12
24May12
22May12
12Jun12
18Jun12
9Jul12
16Jul12
0.00%
0.00%
16Jul12
0.026
24May12
24May12
27May12
17Jun12
24Jun12
15Jul12
22Jul12
0.00%
0.00%
22Jul12
0.026
24May12
24May12
27May12
17Jun12
24Jun12
15Jul12
22Jul12
0.00%
0.00%
22Jul12
0.044
24May12
24May12
31May12
21Jun12
28Jun12
19Jul12
26Jul12
0.00%
0.00%
26Jul12
0.044
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
3392-RQ-32-15-0011
3392-RQ-32-15-0012
3392-RQ-32-15-0013
3392-RQ-32-15-0018
3392-RQ-32-15-0019
5.0%
5.0%
40.0%
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
24May12
24May12
31May12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
18Jul12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
13Jun12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
21Jun12
28Jun12
19Jul12
WTD
WTG
85.0%
95.0%
26Jul12
26Jul12
PRG
24May12
31May12
21Jun12
28Jun12
19Jul12
26Jul12
24May12
31May12
21Jun12
28Jun12
19Jul12
26Jul12
26Jul12
24May12
29May12
19Jun12
26Jun12
17Jul12
24Jul12
26Jul12
24May12
24May12
12Jun12
19Jun12
10Jul12
17Jul12
24Jul12
24May12
9Aug12
30Aug12
6Sep12
27Sep12
4Oct12
17Jul12
24May12
31May12
21Jun12
28Jun12
19Jul12
26Jul12
4Oct12
24May12
31May12
21Jun12
28Jun12
19Jul12
26Jul12
26Jul12
24May12
31May12
21Jun12
28Jun12
19Jul12
26Jul12
26Jul12
24May12
31May12
21Jun12
28Jun12
19Jul12
26Jul12
26Jul12
24May12
31May12
21Jun12
28Jun12
19Jul12
26Jul12
26Jul12
24May12
31May12
21Jun12
28Jun12
19Jul12
26Jul12
26Jul12
24May12
31May12
21Jun12
28Jun12
19Jul12
26Jul12
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00%
0.00%
26Jul12
0.044
24May12
0.0000
0.00%
0.00%
0.026
24May12
0.0000
0.00%
0.00%
0.026
24May12
0.0000
0.00%
0.00%
0.026
24May12
0.0000
0.00%
0.00%
0.035
24May12
0.0000
0.00%
0.00%
0.018
24May12
0.0000
0.00%
0.00%
0.018
24May12
0.0000
0.00%
0.00%
0.035
2Aug12
0.0000
0.00%
0.00%
0.044
24May12
Actual
0.00%
0.00%
0.035
24May12
Planned
0.00%
0.00%
0.035
24May12
Remarks
0.00%
0.044
24May12
0.00%
0.00%
26Jul12
0.044
0.00%
DOCUMENTS/DRAWINGS
COMMON
3392-32-15-31-0001 Instrument process hook-up Diagrams
3392-32-15-53-0001
3392-32-15-53-0002
3392-32-15-53-0003
JB Connection Diagram
22Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
16Sep12
0.00%
0.096
23Jul12
24Jul12
25Jul12
15Aug12
22Aug12
12Sep12
19Sep12
0.00%
0.00%
19Sep12
0.096
9Aug12
12Aug12
12Aug12
2Sep12
9Sep12
30Sep12
7Oct12
0.00%
0.00%
7Oct12
0.096
24Jul12
29Jul12
29Jul12
19Aug12
26Aug12
16Sep12
23Sep12
0.00%
0.00%
23Sep12
0.342
30Jul12
5Aug12
5Aug12
26Aug12
2Sep12
23Sep12
30Sep12
0.00%
0.00%
30Sep12
0.175
5Aug12
6Aug12
7Aug12
28Aug12
4Sep12
25Sep12
2Oct12
0.00%
0.00%
2Oct12
0.070
30Jul12
1Aug12
2Aug12
2Aug12
2Aug12
2Aug12
2Aug12
0.00%
0.00%
2Aug12
0.307
1Jul12
3Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.105
5Aug12
8Aug12
9Aug12
30Aug12
6Sep12
27Sep12
4Oct12
0.00%
0.00%
4Oct12
0.167
0.00%
QP Refinery
3392-32-15-54-0001 Cause and Effect Diagrams (As per SOW)
20Jun12
27Jun12
18Jul12
25Jul12
15Aug12
22Aug12
22Aug12
0.00%
0.281
18Jul12
29Jul12
29Jul12
19Aug12
26Aug12
16Sep12
23Sep12
0.00%
0.00%
23Sep12
0.237
26Jun12
26Jun12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.368
1Jul12
15Jul12
16Jul12
6Aug12
13Aug12
3Sep12
10Sep12
0.00%
0.00%
10Sep12
0.079
18Jul12
29Jul12
29Jul12
19Aug12
26Aug12
16Sep12
23Sep12
0.00%
0.00%
23Sep12
0.079
23Jul12
26Jul12
26Jul12
16Aug12
23Aug12
13Sep12
20Sep12
0.00%
0.00%
20Sep12
0.079
23Jul12
25Jul12
26Jul12
16Aug12
23Aug12
13Sep12
20Sep12
0.00%
0.00%
20Sep12
0.368
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
3392-32-15-66-0002
5.0%
5.0%
40.0%
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
16Aug12
19Aug12
19Aug12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
13Jun12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
9Sep12
16Sep12
7Oct12
WTD
WTG
85.0%
95.0%
14Oct12
14Oct12
PRG
19Aug12
19Aug12
9Sep12
16Sep12
7Oct12
14Oct12
25Jul12
26Jul12
16Aug12
23Aug12
13Sep12
20Sep12
14Oct12
21Aug12
22Aug12
12Sep12
19Sep12
10Oct12
17Oct12
20Sep12
21Aug12
22Aug12
12Sep12
19Sep12
10Oct12
17Oct12
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.000
0.00%
0.000
0.00%
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.000
0.00%
0.000
0.00%
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00%
0.00%
17Oct12
0.316
20Aug12
Actual
0.00%
0.00%
0.289
20Aug12
Planned
0.00%
0.00%
0.447
24Jul12
Remarks
0.00%
0.368
15Aug12
0.00%
0.00%
17Oct12
0.298
0.00%
BSV-3
3392-33-15-61-0001 Cause and Effect Diagrams (As per SOW)
3392-33-15-66-0004
18Jun12
18Jun12
9Jul12
16Jul12
6Aug12
13Aug12
13Aug12
0.00%
0.219
18Jul12
24Jul12
26Jul12
16Aug12
23Aug12
13Sep12
20Sep12
0.00%
0.00%
20Sep12
0.237
24Jun12
26Jun12
4Jul12
25Jul12
1Aug12
22Aug12
29Aug12
0.00%
0.00%
29Aug12
0.368
23Jul12
3Jul12
26Jul12
16Aug12
23Aug12
13Sep12
20Sep12
0.00%
0.00%
20Sep12
0.173
23Jul12
24Jul12
25Jul12
15Aug12
22Aug12
12Sep12
19Sep12
0.00%
0.00%
19Sep12
0.342
30Jul12
31Jul12
1Aug12
22Aug12
29Aug12
19Sep12
26Sep12
0.00%
0.00%
26Sep12
0.342
1Aug12
5Aug12
5Aug12
26Aug12
2Sep12
23Sep12
30Sep12
0.00%
0.00%
30Sep12
0.447
9Aug12
13Aug12
13Aug12
3Sep12
10Sep12
1Oct12
8Oct12
0.00%
0.00%
8Oct12
0.289
20Aug12
20Aug12
21Aug12
11Sep12
18Sep12
9Oct12
16Oct12
0.00%
0.00%
16Oct12
0.289
20Aug12
20Aug12
21Aug12
11Sep12
18Sep12
9Oct12
16Oct12
0.00%
0.00%
16Oct12
0.298
0.00%
9.959
TELECOMMUNICATION
SPECIFICATIONS
3392-32-16-51-0001
3392-32-16-51-0002
3392-32-16-51-0004
P
F
F
A
P
F
F
A
P
F
F
A
15Jul12
P
F
F
A
P
F
F
A
3Jun12
P
F
F
A
P
F
F
A
29Jul12
18Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
13Sep12
0.00%
0.123
15Jul12
18Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
0.00%
0.00%
13Sep12
0.123
15Jul12
18Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
0.00%
0.00%
13Sep12
0.158
0.00%
MATERIAL REQUISITIONS
3392-RQ-32-16-0001
3Jun12
4Jun12
25Jun12
2Jul12
23Jul12
30Jul12
30Jul12
0.00%
0.053
3Jun12
3Jun12
4Jun12
25Jun12
2Jul12
23Jul12
30Jul12
0.00%
0.00%
30Jul12
0.053
0.00%
DRAWINGS
3392-32-16-53-0001 Overall TELECOM system cable block diagram
30Jul12
31Jul12
21Aug12
28Aug12
18Sep12
25Sep12
25Sep12
0.00%
0.289
1Aug12
5Aug12
5Aug12
26Aug12
2Sep12
23Sep12
30Sep12
0.00%
0.00%
30Sep12
0.254
0.00%
1.052
ELECTRICAL
SPECIFICATIONS
COMMON
3392-32-16-17-0001 Specification for Electrical Bulk Materials
3392-32-16-17-0003
P
F
F
A
P
F
F
A
P
F
F
A
15May12
P
F
F
A
15May12
15May12
20May12
10Jun12
17Jun12
8Jul12
15Jul12
15Jul12
0.00%
0.053
15May12
15May12
20May12
10Jun12
17Jun12
8Jul12
15Jul12
0.00%
0.00%
15Jul12
0.053
15May12
15May12
20May12
10Jun12
17Jun12
8Jul12
15Jul12
0.00%
0.00%
15Jul12
0.053
0.00%
QP Refinery
3392-32-16-17-0004
15May12
28May12
18Jun12
25Jun12
16Jul12
23Jul12
23Jul12
0.00%
0.079
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
5.0%
5.0%
40.0%
14Jun12
18Jun12
20Jun12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
8Jul12
15Jul12
5Aug12
WTD
WTG
85.0%
95.0%
12Aug12
12Aug12
PRG
18Jun12
20Jun12
8Jul12
15Jul12
5Aug12
12Aug12
22May12
22May12
5Jun12
7Jun12
28Jun12
5Jul12
12Aug12
13May12
13May12
3Jun12
10Jun12
1Jul12
8Jul12
Actual
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00%
0.00%
5Jul12
0.053
13May12
Planned
0.00%
0.00%
0.053
10May12
Remarks
0.00%
0.079
14Jun12
0.00%
0.00%
8Jul12
0.079
0.00%
BSV-3
3392-33-16-17-0010 Specification for 415V Switchboard modificaion
P
F
F
A
21Jun12
P
F
F
A
P
F
F
A
21May12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
15May12
P
F
F
A
23May12
P
F
F
A
P
F
F
A
22May12
P
F
F
A
P
F
F
A
26Jun12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
26Jun12
24Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
20Aug12
0.00%
0.079
0.00%
DATA SHEETS
COMMON
3392-32-16-12-0001 Data Sheet for Distribution Boards
21May12
22May12
12Jun12
19Jun12
10Jul12
17Jul12
17Jul12
0.00%
0.079
21May12
21May12
22May12
12Jun12
19Jun12
10Jul12
17Jul12
0.00%
0.00%
17Jul12
0.053
0.00%
QP Refinery
3392-32-16-12-0003 Data Sheet for 11 & 3.3 KV Switchgear Modification
5Jun12
21May12
11Jun12
18Jun12
9Jul12
16Jul12
16Jul12
0.00%
0.079
14Jun12
18Jun12
20Jun12
8Jul12
16Jul12
6Aug12
13Aug12
0.00%
0.00%
13Aug12
0.079
13May12
14May12
15May12
5Jun12
12Jun12
3Jul12
10Jul12
0.00%
0.00%
10Jul12
0.079
8May12
9May12
10May12
31May12
7Jun12
28Jun12
5Jul12
0.00%
0.00%
5Jul12
0.079
8May12
9May12
10May12
31May12
7Jun12
28Jun12
5Jul12
0.00%
0.00%
5Jul12
0.079
0.00%
MATERIAL REQUISITIONS
COMMON
3392-RQ-32-16-0011 MR for Distribution Boards
29May12
28May12
18Jun12
25Jun12
16Jul12
23Jul12
23Jul12
0.00%
0.079
0.00%
QP Refinery
3392-RQ-32-16-0012 MR for 11KV, 3.3KV & 415V Switchboard Modifications
29May12
27May12
17Jun12
24Jun12
15Jul12
22Jul12
22Jul12
0.00%
0.079
16May12
31May12
21May12
11Jun12
18Jun12
9Jul12
16Jul12
0.00%
0.00%
16Jul12
0.053
0.00%
BSV-3
3392-RQ-33-16-0014 MR for 415V Switchboard modificaion
3392-RQ-32-16-0015
28Jun12
27Jun12
18Jul12
25Jul12
15Aug12
22Aug12
22Aug12
0.00%
0.079
26Jun12
28Jun12
27Jun12
18Jul12
25Jul12
15Aug12
22Aug12
0.00%
0.00%
22Aug12
0.000
0.00%
REPORTS / CALCULATIONS
QP Refinery
3392-32-16-30-0001 Cable Sizing Calculation
1Jul12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
23Aug12
0.00%
0.237
22Jul12
24Jul12
24Jul12
14Aug12
21Aug12
11Sep12
18Sep12
0.00%
0.00%
18Sep12
0.395
15May12
16May12
17May12
7Jun12
14Jun12
5Jul12
12Jul12
0.00%
0.00%
12Jul12
0.158
30Jul12
31Jul12
1Aug12
22Aug12
29Aug12
19Sep12
26Sep12
0.00%
0.00%
26Sep12
0.789
20May12
16May12
30May12
20Jun12
27Jun12
18Jul12
25Jul12
0.00%
0.00%
25Jul12
0.789
0.00%
BSV-3
3392-33-16-30-0006 Cable Sizing Calculation
P
F
F
A
P
F
F
A
12Jun12
P
F
F
A
P
F
F
A
27Jun12
14Jun12
18Jun12
9Jul12
16Jul12
6Aug12
13Aug12
13Aug12
0.00%
0.158
2Jul12
11Jun12
4Jul12
25Jul12
2Aug12
23Aug12
30Aug12
0.00%
0.00%
30Aug12
0.316
0.00%
LISTS / SCHEDULES
QP Refinery
3392-32-16-31-0001 Electrical load list
3392-32-16-41-0011 DB Schedules
27Jun12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
26Aug12
0.00%
0.079
8Jul12
11Jul12
12Jul12
2Aug12
9Aug12
30Aug12
6Sep12
0.00%
0.00%
6Sep12
0.263
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
5.0%
5.0%
40.0%
2Jul12
4Jul12
5Jul12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
26Jul12
2Aug12
23Aug12
WTD
WTG
85.0%
95.0%
30Aug12
30Aug12
PRG
11Jul12
12Jul12
2Aug12
9Aug12
30Aug12
6Sep12
30Jul12
30Jul12
30Jul12
30Jul12
30Jul12
30Jul12
6Sep12
1Jul12
5Jul12
26Jul12
2Aug12
23Aug12
30Aug12
Actual
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00%
0.00%
30Jul12
0.474
2Jul12
Planned
0.00%
0.00%
0.395
25Jul12
Remarks
0.00%
0.079
8Jul12
0.00%
0.00%
30Aug12
0.079
0.00%
BSV-3
3392-33-16-30-0031 Electrical load list
3392-33-16-41-0021 DB Schedules
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
24May12
P
F
F
A
P
F
F
A
P
F
F
A
21Jun12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
23Jul12
31May12
29May12
19Jun12
26Jun12
17Jul12
24Jul12
24Jul12
0.00%
0.079
24Jun12
19Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
0.00%
0.00%
23Aug12
0.105
17Jun12
19Jun12
21Jun12
12Jul12
19Jul12
9Aug12
16Aug12
0.00%
0.00%
16Aug12
0.079
16Jul12
22Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
0.00%
0.00%
16Sep12
0.210
23Jul12
29Jul12
29Jul12
29Jul12
29Jul12
29Jul12
29Jul12
0.00%
0.00%
29Jul12
0.210
19Jun12
19Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
0.00%
0.00%
20Aug12
0.079
0.00%
DRAWINGS
3392-32-16-21-0001 Typical EARTHING INSTALLATION DETAILS
25Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
23Aug12
0.00%
0.105
21Jun12
25Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
0.00%
0.00%
23Aug12
0.105
21Jun12
25Jun12
28Jun12
19Jul12
26Jul12
16Aug12
23Aug12
0.00%
0.00%
23Aug12
0.105
0.00%
24Jul12
25Jul12
15Aug12
22Aug12
12Sep12
19Sep12
19Sep12
0.00%
0.316
26Jul12
29Jul12
30Jul12
20Aug12
27Aug12
17Sep12
24Sep12
0.00%
0.00%
24Sep12
0.316
31Jul12
8Jul12
2Aug12
23Aug12
30Aug12
20Sep12
27Sep12
0.00%
0.00%
27Sep12
0.316
15May12
27May12
27May12
17Jun12
24Jun12
15Jul12
22Jul12
0.00%
0.00%
22Jul12
0.237
28May12
5Jun12
3Jun12
24Jun12
1Jul12
22Jul12
29Jul12
0.00%
0.00%
29Jul12
0.210
10Jul12
11Jul12
12Jul12
2Aug12
9Aug12
30Aug12
6Sep12
0.00%
0.00%
6Sep12
0.237
3Jun12
4Jun12
7Jun12
28Jun12
5Jul12
26Jul12
2Aug12
0.00%
0.00%
2Aug12
0.210
15Jul12
16Jul12
17Jul12
7Aug12
14Aug12
4Sep12
11Sep12
0.00%
0.00%
11Sep12
0.237
18Jul12
22Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
0.00%
0.00%
16Sep12
0.237
0.00%
BSV-3
3392-33-16-32-0010 415V SLD
P
F
F
A
P
F
F
A
5Jul12
P
F
F
A
15Jul12
P
F
F
A
P
F
F
A
P
F
F
A
24Jul12
8Jul12
12Jul12
2Aug12
9Aug12
30Aug12
6Sep12
6Sep12
0.00%
0.395
5Jul12
8Jul12
12Jul12
2Aug12
9Aug12
30Aug12
6Sep12
0.00%
0.00%
6Sep12
0.210
0.00%
STATION - T1
3392-33-16-32-0013 DB SLD modification
17Jul12
18Jul12
8Aug12
15Aug12
5Sep12
12Sep12
12Sep12
0.00%
0.210
0.00%
LAYOUTS
QP Refinery
3392-32-16-11-0001 Cable Routing Layout - Pump House/SS/SER-12
29Jul12
31Jul12
21Aug12
28Aug12
18Sep12
25Sep12
25Sep12
0.00%
0.552
24Jul12
29Jul12
31Jul12
21Aug12
28Aug12
18Sep12
25Sep12
0.00%
0.00%
25Sep12
0.395
1Aug12
6Aug12
6Aug12
27Aug12
3Sep12
24Sep12
1Oct12
0.00%
0.00%
1Oct12
0.500
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
5.0%
5.0%
40.0%
30Jul12
1Aug12
2Aug12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
23Aug12
30Aug12
20Sep12
WTD
WTG
85.0%
95.0%
27Sep12
27Sep12
PRG
30Jul12
30Jul12
20Aug12
27Aug12
17Sep12
24Sep12
30Jul12
30Jul12
20Aug12
27Aug12
17Sep12
24Sep12
24Sep12
30Jul12
30Jul12
20Aug12
27Aug12
17Sep12
24Sep12
24Sep12
30Jul12
30Jul12
20Aug12
27Aug12
17Sep12
24Sep12
24Sep12
18Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
24Sep12
1Jul12
1Jul12
22Jul12
29Jul12
19Aug12
26Aug12
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.000
0.00%
0.000
0.00%
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00%
0.00%
13Sep12
0.395
25Jun12
0.0000
0.00%
0.00%
0.237
15Jul12
0.0000
0.00%
0.00%
0.474
25Jul12
Actual
0.00%
0.00%
0.289
25Jul12
Planned
0.00%
0.00%
0.421
25Jul12
Remarks
0.00%
0.368
25Jul12
0.00%
0.00%
26Aug12
0.316
0.00%
BSV-3
3392-33-16-11-0011 Cable Routing Layout
P
F
F
A
P
F
F
A
P
F
F
A
15Jul12
P
F
F
A
21Jun12
P
F
F
A
22Jul12
18Jul12
18Jul12
8Aug12
15Aug12
5Sep12
12Sep12
12Sep12
0.00%
0.395
15Jul12
19Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
0.00%
0.00%
13Sep12
0.447
4Jul12
5Jul12
5Jul12
26Jul12
2Aug12
23Aug12
30Aug12
0.00%
0.00%
30Aug12
0.368
0.00%
STATION - T1
3392-33-16-11-0014 Cable Routing Layout (Station T1)
24Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
20Aug12
0.00%
0.289
0.00%
24Jul12
25Jul12
15Aug12
22Aug12
12Sep12
19Sep12
19Sep12
0.00%
0.474
0.00%
15.731
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
6May12
8May12
7May12
28May12
4Jun12
25Jun12
2Jul12
2Jul12
0.00%
0.061
8May12
8May12
13May12
3Jun12
10Jun12
1Jul12
8Jul12
0.00%
0.00%
8Jul12
0.061
8May12
8May12
13May12
3Jun12
10Jun12
1Jul12
8Jul12
0.00%
0.00%
8Jul12
0.061
8May12
8May12
13May12
3Jun12
10Jun12
1Jul12
8Jul12
0.00%
0.00%
8Jul12
0.061
16May12
20May12
21May12
11Jun12
18Jun12
9Jul12
16Jul12
0.00%
0.00%
16Jul12
0.158
16May12
20May12
21May12
11Jun12
18Jun12
9Jul12
16Jul12
0.00%
0.00%
16Jul12
0.061
0.00%
P
F
F
A
P
F
F
A
28Mar12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
27May12
28Mar12
1Apr12
22Apr12
29Apr12
20May12
27May12
27May12
0.00%
0.210
25Mar12
28Mar12
28Mar12
29Apr12
2May12
0.00%
0.00%
2May12
0.132
0.00%
29May12
29May12
19Jun12
26Jun12
17Jul12
24Jul12
24Jul12
0.00%
0.096
5Jun12
7Jun12
11Jun12
2Jul12
9Jul12
30Jul12
6Aug12
0.00%
0.00%
6Aug12
0.167
5Jun12
7Jun12
11Jun12
27Jun12
4Jul12
25Jul12
1Aug12
0.00%
0.00%
1Aug12
0.096
18Jun12
20Jun12
27Jun12
18Jul12
25Jul12
15Aug12
22Aug12
0.00%
0.00%
22Aug12
0.105
5Jun12
7Jun12
11Jun12
27Jun12
4Jul12
25Jul12
1Aug12
0.00%
0.00%
1Aug12
0.114
10Jun12
10Jun12
13Jun12
8Jul12
16Jul12
6Aug12
13Aug12
0.00%
0.00%
13Aug12
0.114
6Jun12
7Jun12
11Jun12
27Jun12
5Jul12
26Jul12
2Aug12
0.00%
0.00%
2Aug12
0.140
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
5.0%
5.0%
40.0%
6Jun12
7Jun12
11Jun12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
27Jun12
5Jul12
26Jul12
WTD
WTG
85.0%
95.0%
2Aug12
2Aug12
PRG
10Jun12
11Jun12
8Jul12
16Jul12
6Aug12
13Aug12
7Jun12
11Jun12
27Jun12
5Jul12
26Jul12
2Aug12
13Aug12
7Jun12
11Jun12
27Jun12
5Jul12
26Jul12
2Aug12
2Aug12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
2Aug12
21Jun12
3Jul12
24Jul12
31Jul12
21Aug12
28Aug12
2Sep12
5Aug12
5Aug12
26Aug12
2Sep12
23Sep12
30Sep12
28Aug12
5Aug12
7Aug12
28Aug12
4Sep12
25Sep12
2Oct12
30Sep12
7Jun12
13Jun12
27Jun12
4Jul12
25Jul12
1Aug12
2Oct12
10Jun12
13Jun12
8Jul12
16Jul12
6Aug12
13Aug12
1Aug12
10Jun12
13Jun12
8Jul12
16Jul12
6Aug12
13Aug12
13Aug12
10Jun12
13Jun12
8Jul12
16Jul12
6Aug12
13Aug12
13Aug12
10Jun12
13Jun12
8Jul12
16Jul12
6Aug12
13Aug12
13Aug12
18Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00%
0.00%
13Aug12
0.298
17Jul12
0.0000
0.00%
0.00%
0.123
10Jun12
0.0000
0.00%
0.00%
0.123
10Jun12
0.0000
0.00%
0.00%
0.123
10Jun12
0.0000
0.00%
0.00%
0.123
10Jun12
0.0000
0.00%
0.00%
0.386
6Jun12
0.0000
0.00%
0.00%
0.193
2Aug12
0.0000
0.00%
0.00%
0.193
1Aug12
0.0000
0.00%
0.00%
0.552
21Jun12
0.0000
0.00%
0.00%
0.193
1Jul12
Actual
0.00%
0.00%
0.193
6Jun12
Planned
0.00%
0.00%
0.140
6Jun12
Remarks
0.00%
0.114
10Jun12
0.00%
0.00%
13Sep12
1.079
0.00%
TYPICAL CALCULATIONS
3392-32-17-22-0001
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
31May12
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
21Aug12
31May12
5Jun12
26Jun12
3Jul12
24Jul12
31Jul12
31Jul12
0.00%
0.316
19Jun12
21Jun12
24Jun12
15Jul12
22Jul12
12Aug12
19Aug12
0.00%
0.00%
19Aug12
0.210
2Jul12
9Jul12
9Jul12
30Jul12
6Aug12
27Aug12
3Sep12
0.00%
0.00%
3Sep12
0.342
2Jul12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.237
2Jul12
8Jul12
8Jul12
29Jul12
5Aug12
26Aug12
2Sep12
0.00%
0.00%
2Sep12
0.474
13Aug12
20Aug12
20Aug12
10Sep12
17Sep12
8Oct12
15Oct12
0.00%
0.00%
15Oct12
0.395
0.00%
27Aug12
29Aug12
19Sep12
26Sep12
17Oct12
24Oct12
24Oct12
0.00%
0.649
20Aug12
26Aug12
28Aug12
18Sep12
25Sep12
16Oct12
23Oct12
0.00%
0.00%
23Oct12
0.649
21Aug12
27Aug12
29Aug12
19Sep12
26Sep12
17Oct12
24Oct12
0.00%
0.00%
24Oct12
0.649
9Jul12
15Jul12
17Jul12
7Aug12
14Aug12
4Sep12
11Sep12
0.00%
0.00%
11Sep12
0.535
9Jul12
15Jul12
17Jul12
7Aug12
14Aug12
4Sep12
11Sep12
0.00%
0.00%
11Sep12
0.535
14Aug12
20Aug12
20Aug12
10Sep12
17Sep12
8Oct12
15Oct12
0.00%
0.00%
15Oct12
0.535
22Aug12
28Aug12
28Aug12
18Sep12
25Sep12
16Oct12
23Oct12
0.00%
0.00%
23Oct12
0.535
22Aug12
26Aug12
28Aug12
18Sep12
25Sep12
16Oct12
23Oct12
0.00%
0.00%
23Oct12
0.403
13Aug12
15Aug12
16Aug12
6Sep12
13Sep12
4Oct12
11Oct12
0.00%
0.00%
11Oct12
0.403
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
3392-32-14-40-0031
3392-32-14-40-0033
3392-32-14-40-0035
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
5.0%
5.0%
40.0%
13Aug12
15Aug12
16Aug12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
6Sep12
13Sep12
4Oct12
WTD
WTG
85.0%
95.0%
11Oct12
11Oct12
PRG
21Aug12
22Aug12
12Sep12
19Sep12
10Oct12
17Oct12
2Sep12
2Sep12
23Sep12
30Sep12
21Oct12
28Oct12
17Oct12
2Sep12
2Sep12
23Sep12
30Sep12
21Oct12
28Oct12
28Oct12
2Sep12
2Sep12
23Sep12
30Sep12
21Oct12
28Oct12
28Oct12
2Sep12
2Sep12
23Sep12
30Sep12
21Oct12
28Oct12
28Oct12
2Sep12
2Sep12
23Sep12
30Sep12
21Oct12
28Oct12
28Oct12
2Sep12
2Sep12
23Sep12
30Sep12
21Oct12
28Oct12
28Oct12
3Sep12
3Sep12
24Sep12
1Oct12
22Oct12
29Oct12
28Oct12
3Sep12
3Sep12
24Sep12
1Oct12
22Oct12
29Oct12
29Oct12
3Sep12
3Sep12
24Sep12
1Oct12
22Oct12
29Oct12
29Oct12
3Sep12
3Sep12
24Sep12
1Oct12
22Oct12
29Oct12
29Oct12
3Sep12
3Sep12
24Sep12
1Oct12
22Oct12
29Oct12
29Oct12
3Sep12
3Sep12
24Sep12
1Oct12
22Oct12
29Oct12
29Oct12
3Sep12
3Sep12
24Sep12
1Oct12
22Oct12
29Oct12
29Oct12
19Aug12
19Aug12
9Sep12
16Sep12
7Oct12
14Oct12
29Oct12
17Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
14Oct12
17Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
13Sep12
17Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
13Sep12
17Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
13Sep12
17Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
13Sep12
17Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
13Sep12
17Jul12
19Jul12
9Aug12
16Aug12
6Sep12
13Sep12
13Sep12
24Jul12
25Jul12
15Aug12
22Aug12
12Sep12
19Sep12
13Sep12
24Jul12
25Jul12
15Aug12
22Aug12
12Sep12
19Sep12
19Sep12
24Jul12
25Jul12
15Aug12
22Aug12
12Sep12
19Sep12
19Sep12
24Jul12
25Jul12
15Aug12
22Aug12
12Sep12
19Sep12
19Sep12
24Jul12
25Jul12
15Aug12
22Aug12
12Sep12
19Sep12
19Sep12
24Jul12
25Jul12
15Aug12
22Aug12
12Sep12
19Sep12
19Sep12
9Sep12
11Sep12
2Oct12
9Oct12
30Oct12
6Nov12
19Sep12
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.00%
0.00%
6Nov12
0.258
0.00%
0.0000
0.00%
0.00%
0.204
5Sep12
0.0000
0.00%
0.00%
0.205
22Jul12
0.0000
0.00%
0.00%
0.205
22Jul12
0.0000
0.00%
0.00%
0.205
22Jul12
0.0000
0.00%
0.00%
0.205
22Jul12
0.0000
0.00%
0.00%
0.205
22Jul12
0.0000
0.00%
0.00%
0.205
22Jul12
0.0000
0.00%
0.00%
0.487
10Jul12
0.0000
0.00%
0.00%
0.487
10Jul12
0.0000
0.00%
0.00%
0.492
10Jul12
0.0000
0.00%
0.00%
0.342
10Jul12
0.0000
0.00%
0.00%
0.342
10Jul12
0.0000
0.00%
0.00%
0.316
10Jul12
0.0000
0.00%
0.00%
0.921
10Jul12
0.0000
0.00%
0.00%
0.456
14Aug12
0.0000
0.00%
0.00%
0.456
25Jul12
0.0000
0.00%
0.00%
0.456
25Jul12
0.0000
0.00%
0.00%
0.456
25Jul12
0.0000
0.00%
0.00%
0.535
25Jul12
0.0000
0.00%
0.00%
0.456
25Jul12
0.0000
0.00%
0.00%
0.456
25Jul12
0.0000
0.00%
0.00%
0.482
25Jul12
0.0000
0.00%
0.00%
0.482
22Jul12
0.0000
0.00%
0.00%
0.482
22Jul12
0.0000
0.00%
0.00%
0.456
22Jul12
0.0000
0.00%
0.00%
0.456
22Jul12
Actual
0.00%
0.00%
0.535
22Jul12
Planned
0.00%
0.00%
0.403
22Jul12
Remarks
0.00%
0.403
19Aug12
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
5.0%
5.0%
40.0%
22Jul12
5Aug12
5Aug12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
26Aug12
2Sep12
23Sep12
WTD
WTG
85.0%
95.0%
30Sep12
30Sep12
PRG
9Sep12
11Sep12
2Oct12
9Oct12
30Oct12
6Nov12
4Aug12
5Aug12
26Aug12
2Sep12
23Sep12
30Sep12
6Nov12
19Aug12
20Aug12
10Sep12
17Sep12
8Oct12
15Oct12
30Sep12
8Aug12
9Aug12
30Aug12
6Sep12
27Sep12
4Oct12
15Oct12
13Aug12
14Aug12
4Sep12
11Sep12
2Oct12
9Oct12
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.000
0.00%
0.000
0.00%
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.000
0.00%
0.000
0.00%
0.0000
0.0000
0.0000
0.0000
0.00%
0.00%
4Oct12
0.158
13Aug12
0.0000
0.00%
0.00%
0.158
8Aug12
Actual
0.00%
0.00%
0.241
19Aug12
Planned
0.00%
0.00%
0.241
22Jul12
Remarks
0.00%
0.444
5Sep12
0.00%
0.00%
9Oct12
0.158
0.00%
BSV-3
3392-33-14-20-0004 Civil GA (BSV-3)
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
23Jul12
P
F
F
A
P
F
F
A
8Aug12
26Jul12
26Jul12
16Aug12
23Aug12
13Sep12
20Sep12
20Sep12
0.00%
0.241
17Jul12
22Jul12
22Jul12
12Aug12
19Aug12
9Sep12
16Sep12
0.00%
0.00%
16Sep12
0.241
23Jul12
26Jul12
26Jul12
16Aug12
23Aug12
13Sep12
20Sep12
0.00%
0.00%
20Sep12
0.241
26Jul12
5Aug12
5Aug12
26Aug12
2Sep12
23Sep12
30Sep12
0.00%
0.00%
30Sep12
0.296
0.00%
12Aug12
14Aug12
4Sep12
11Sep12
2Oct12
9Oct12
9Oct12
0.00%
0.235
15Aug12
19Aug12
21Aug12
11Sep12
18Sep12
9Oct12
16Oct12
0.00%
0.00%
16Oct12
0.342
0.00%
27.382
BUILDING SERVICES
CALCULATION / SCHEDULES / MTO
3392-32-34-17-0001 HVAC Load Calculation
P
F
F
A
P
F
F
A
P
F
F
A
12Jun12
P
F
F
A
20May12
P
F
F
A
P
F
F
A
20Jun12
17Jun12
17Jun12
8Jul12
15Jul12
5Aug12
12Aug12
12Aug12
0.00%
0.158
18Jun12
21Jun12
21Jun12
12Jul12
19Jul12
9Aug12
16Aug12
0.00%
0.00%
16Aug12
0.070
18Jun12
21Jun12
21Jun12
12Jul12
19Jul12
9Aug12
16Aug12
0.00%
0.00%
16Aug12
0.175
0.00%
SPECIFICATIONS
3392-32-34-17-0004 HVAC Specification
20May12
19Jun12
8Jul12
15Jul12
5Aug12
12Aug12
12Aug12
0.00%
0.105
0.00%
TECHNICAL REQUISITIONS
3392-RQ-32-34-0001
7Jun12
27Jun12
18Jul12
25Jul12
15Aug12
22Aug12
22Aug12
0.00%
0.053
21May12
7Jun12
7Jun12
28Jun12
5Jul12
26Jul12
2Aug12
0.00%
0.00%
2Aug12
0.053
0.00%
DRAWINGS
3392-32-34-20-0001 SER-12 Building Extension HVAC Layout
3392-32-34-20-0002
3392-32-34-20-0003
3392-32-34-20-0004
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
P
F
F
A
18Jun12
21Jun12
21Jun12
12Jul12
19Jul12
9Aug12
16Aug12
16Aug12
0.00%
0.333
18Jun12
21Jun12
21Jun12
12Jul12
19Jul12
9Aug12
16Aug12
0.00%
0.00%
16Aug12
0.333
18Jun12
21Jun12
21Jun12
12Jul12
19Jul12
9Aug12
16Aug12
0.00%
0.00%
16Aug12
0.333
24Jun12
24Jun12
25Jun12
16Jul12
23Jul12
13Aug12
20Aug12
0.00%
0.00%
20Aug12
0.289
30Jul12
30Jul12
30Jul12
20Aug12
27Aug12
17Sep12
24Sep12
0.00%
0.00%
24Sep12
0.088
2Aug12
2Aug12
2Aug12
23Aug12
30Aug12
20Sep12
27Sep12
0.00%
0.00%
27Sep12
0.088
0.00%
2.078
CATHODIC PROTECTION
REPORTS
3392-32-64-81-0005 CP Design Report (including Calculations)
P
F
F
A
26Jul12
P
F
F
A
9Aug12
6Aug12
8Aug12
29Aug12
5Sep12
26Sep12
3Oct12
3Oct12
0.00%
0.474
0.00%
SPECIFICATIONS / SOW
3392-32-64-81-0001 CP Material Specification
12Aug12
13Aug12
3Sep12
10Sep12
1Oct12
8Oct12
8Oct12
0.00%
0.158
0.00%
DETAILED DESIGN FOR EPIC OF 16" JET FUEL PIPELINE FROM QP REFINERY TO BSV-3
CONTRACT NO.: GC11106200
CLIENT: Petrojet
CLIENT
Start
Draft
Issued
Date
Completion
for QP
Receiving
Review
Comments
5.0%
5.0%
40.0%
P
F
F
A
P
F
F
A
16Aug12
19Aug12
20Aug12
P
F
F
A
14Aug12
P
F
F
A
P
F
F
A
19Aug12
Issued for
QP Approval
Issue as
Final
Receiving
AFC with
AFC Issue
Comments
Hold
65.0%
10Sep12
17Sep12
8Oct12
WTD
WTG
85.0%
95.0%
15Oct12
15Oct12
PRG
10Jul12
10Jul12
31Jul12
7Aug12
28Aug12
2Sep12
Remarks
Planned
Actual
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.000
0.00%
0.000
0.00%
0.00%
0.158
10Jul12
0.00%
0.00%
2Sep12
0.237
0.00%
DATA SHEETS
3392-32-64-81-0004 CP Material Data Sheet
16Aug12
16Aug12
6Sep12
13Sep12
4Oct12
11Oct12
11Oct12
0.00%
0.158
0.00%
DRAWINGS
3392-32-64-81-0008 CP Detail Drawings
21Aug12
22Aug12
12Sep12
19Sep12
10Oct12
17Oct12
17Oct12
0.00%
0.298
23Aug12
27Aug12
29Aug12
19Sep12
26Sep12
17Oct12
24Oct12
0.00%
0.00%
24Oct12
0.395
0.00%
1.877
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
PROCUREMENT STATUS REGISTER (PSR)
______________________________________
26-Feb-12
Description
% Weight
Q.ty
SNO
Val ue
WT% Overall
Value of
Procurement
37535313.00
80.92%
Progress Scale
Sec.
(As 100%
Phase)
8,850,035.00
19.08%
% WT respect
to Overall
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%
0.00%
A
% Variance
Respect to
Overall
0.00%
100%
A
P
46,385,348.00
% Phy
100%
A
P
% PROGRESS
0.00%
ETROJE
As Of : 26-Feb-12
T
SNO
Val ue
WT% Overall
Value of
Procurement
Progress Scale
WT%Long
Lead
Phase
Sec.
MR
RFQ to
Vendors
Purchase
Order
Issued
5%
Issued
10%
Order
15%
Vendor
Filled SPIR
Document
Approved
30%
Receipt
40%
FAT
Ex-works
Compl'n
60%
Delivery
70%
Material at site
Received
85%
QP
Inspected
90%
Spare
Parts
At Site
SPIR's
517,498
1.12%
1.38%
26-Jul-12
08-Jul-13
15-Jul-13
15-Jul-13
29-Aug-13
1.76%
2.17%
EOT Crane
28-Apr-13
100,000
0.22%
0.27%
Isolation Joints
25-Jul-12
21-Apr-13
28-Apr-13
28-Apr-13
12-Jun-13
221,785
0.48%
0.59%
Jib Cranes
25-Jul-12
19-Apr-13
25-Jul-13
P
F
A
B PUMPS
10,150,000
21.88%
27.04%
Mainline Pumps
28-Jul-12
12-Jul-13
5,645,000
12.17%
15.04%
Booster Pumps
21-Jul-12
28-Jul-12
12-Jul-13
A
P
F
A
4,340,841
C1
9.36%
11.56%
Switchgear Panels
17-Apr-13
23-Jul-13
C2
0.24%
0.30%
19-Apr-13
25-Jul-13
C3
0.91%
1.13%
UPS System
07-Jul-13
14-Jul-13
14-Jul-13
28-Aug-13
D1
P
F
A
977,651
2.11%
2.60%
28-Jul-12
21-Jul-13
28-Jul-13
28-Jul-13
11-Sep-13
D2
0.55%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0.00%
0.00%
24-Jul-12
31-Jul-12
17-Jul-13
24-Jul-13
24-Jul-13
07-Sep-13
0.00%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0.00%
0.00%
0.00%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0.00%
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
0.00%
0.00%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0.00%
0.55%
Shipment
Type
0.00%
2.60%
0.44%
0%
11.56%
205,000
0.00%
1.13%
D VALVES
0%
0.30%
422,708
0.00%
11.56%
111,086
0%
12.99%
0.00%
15.04%
C ELECTRICAL
0.00%
27.04%
Vendor
Name
0.00%
42.08%
21-Jul-12
PO #
0.00%
0.59%
F
A
B2
0.00%
0.00%
0.27%
F
A
B1
0.00%
0.00%
2.17%
F
A
A4
0.00%
1.38%
815,000
A3
0.00%
4.41%
A2
% Phy
% Equiv
% Variance
to Phase
100.00%
A
P
F
A
A MECHANICAL ITEMS
A1
% PROGRESS
% Weight
0.00%
0.00%
By Sea
0.00%
By Sea
Remarks
ETROJE
As Of : 26-Feb-12
T
SNO
Val ue
WT% Overall
Value of
Procurement
Progress Scale
170,000
D3
0.37%
WT%Long
Lead
Phase
0.45%
Sec.
MR
RFQ to
Vendors
Purchase
Order
Issued
5%
Issued
10%
Order
15%
Vendor
Filled SPIR
Document
Approved
30%
Receipt
40%
FAT
Ex-works
Compl'n
60%
Delivery
70%
Material at site
Received
85%
QP
Inspected
90%
10-Jul-13
17-Jul-13
Spare
Parts
At Site
17-Jul-13
SPIR's
0%
D4
4.24%
5.24%
11-Jul-13
18-Jul-13
18-Jul-13
01-Sep-13
D5
2.20%
2.72%
10-Jul-13
17-Jul-13
17-Jul-13
31-Aug-13
A
P
F
A
E INSTRUMENTATION WORKS,DCS,ESD
AND F&G SYSTEMS
E1
1,155,406
2.49%
3.08%
04-Jul-13
11-Jul-13
11-Jul-13
25-Aug-13
E2
1.23%
Junction Boxes
27-Apr-13
E3
0.72%
0.88%
01-Jul-13
01-Jul-13
15-Aug-13
E4
3.46%
4.27%
21-Jul-12
28-Jul-12
18-Apr-13
18-Apr-13
02-Jun-13
E5
6,014,629
12.97%
16.02%
23-Jul-13
30-Jul-13
30-Jul-13
13-Sep-13
A
P
F
A
118,503
F1
0.26%
0.32%
11-Jul-13
18-Jul-13
18-Jul-13
01-Sep-13
P
F
A
I1
2.55%
3.16%
0%
0.00%
0.00%
0.00%
0.00%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0.00%
0.00%
09-Jul-13
16-Jul-13
16-Jul-13
30-Aug-13
0.00%
0.00%
0%
0.00%
0%
0.00%
0.00%
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
0.00%
By Sea
By Sea
0.00%
0.00%
0.00%
0%
0.00%
0.00%
0%
0.00%
0.00%
3.16%
Shipment
Type
0.00%
3.16%
10-Aug-12 17-Aug-12 07-Sep-12 07-Oct-12 06-Dec-12 10-May-13 25-May-13
Vendor
Name
0.00%
0.32%
1,185,032
0.00%
0.32%
0%
16.02%
0.00%
4.27%
F
A
0%
0.88%
1,603,703
0.00%
1.23%
331,809
0%
3.08%
1.00%
0.00%
25.49%
462,162
0%
2.72%
PO #
0.00%
5.24%
1,020,000
% Phy
% Equiv
% Variance
to Phase
0.45%
1,967,500
% PROGRESS
% Weight
0.00%
By Sea
Remarks
ETROJET
As Of : 26-Feb-12
Description
Q.ty
Sl NO
Value
WT% Overall
Value of
Procurement
Progress Scale
WT% for
Other
Items
Sec.
RFQ to
Vendors
Purchase
Order
Issued
5%
Order
15%
Ex-works
50% OF Est
Qty
30%
90% OF Est
Qty
40%
Material at site
50% OF Est
Qty
50%
90% OF Est
Qty
80%
All Material
received and
PO Closed
100%
% Weight
% PROGRESS
(As 100%
Phase)
% Phy
% Equiv to
Phase
0.0%
0.00%
100.00%
2.1 MECHANICAL
0.0%
0.00%
0%
0.00%
56.36%
A
1 Lot
4,950,000.00
10.67%
55.93%
11-Aug-12
01-Sep-12
10-Nov-12
20-Dec-12
08-Feb-13
29-Apr-13
28-Jun-13
A
1 Lot
2.1.2
38,000.00
0.08%
0.43%
Bulk Items
Stud bolts, Nuts, Gaskets etc.,
21-Jul-12
11-Aug-12
20-Oct-12
29-Nov-12
18-Jan-13
08-Apr-13
07-Jun-13
2.2 ELECTRICAL
0.22%
1.13%
0.44%
2.30%
1.10%
5.78%
23-Aug-12
13-Sep-12
22-Nov-12
01-Jan-13
31-Jan-13
01-Apr-13
31-May-13
09-Sep-12
30-Sep-12
09-Dec-12
18-Jan-13
17-Feb-13
18-Apr-13
17-Jun-13
13-Sep-12
22-Nov-12
01-Jan-13
15-Feb-13
01-May-13
30-Jun-13
Temperature Elements,
2.3.2 Temperature Transmitters,
Thermowell
275,520.00
0.59%
3.11%
0.08%
0.40%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
24.50%
01-Aug-12
22-Aug-12
31-Oct-12
10-Dec-12
24-Jan-13
09-Apr-13
08-Jun-13
01-Aug-12
22-Aug-12
31-Oct-12
10-Dec-12
24-Jan-13
-
09-Apr-13
08-Jun-13
0.00%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
0.40%
0%
By Sea
0.00%
By Sea
0.00%
Local
0.00%
Terrestrial
0.00%
Terrestrial
0.00%
3.11%
34,958.00
0%
Item
0.00%
5.78%
Item
0.00%
2.30%
23-Aug-12
0.00%
0.00%
1.13%
Pressure Transmitters,
2.3.1 Differential Pressure
Transmitters, Pressure Gauges
0.00%
9.21%
2.3 INSTRUMENTATION
0%
0.00%
511,515.00
0.00%
0%
Item
0%
203,462.00
0.00%
0.00%
Item
0%
0%
100,379.00
0.00%
Item
0%
0.43%
Shipment
Type
0.00%
55.93%
10-Jun-10
Vendor
Name
0.00%
% Variance
PO #
0.00%
0.00%
Air Freight
0.00%
Air Freight
Remarks
ETROJET
As Of : 26-Feb-12
Description
Sl NO
Q.ty
Value
Lot
1,858,213.00
WT% Overall
Value of
Procurement
WT% for
Other
Items
Sec.
4.01%
21.00%
Progress Scale
RFQ to
Vendors
Purchase
Order
Issued
5%
Order
15%
50% OF Est
Qty
30%
90% OF Est
Qty
40%
50% OF Est
Qty
50%
90% OF Est
Qty
80%
26-Jul-12
16-Aug-12
25-Oct-12
04-Dec-12
18-Jan-13
03-Apr-13
Ex-works
Material at site
All Material
received and
PO Closed
100%
% PROGRESS
(As 100%
Phase)
% Phy
% Equiv to
Phase
0%
0.00%
02-Jun-13
21.00%
% Weight
0%
0.00%
0%
0.00%
0.86%
A
Item
76,000.00
0.16%
0.86%
18-Aug-12
08-Sep-12
17-Nov-12
27-Dec-12
10-Feb-13
26-Apr-13
25-Jun-13
H.1
200,497.00
0.43%
2.27%
H.2
1.30%
6.80%
0.00%
0.00%
0%
0.00%
9.06%
10-Aug-12
31-Aug-12
20-Sep-12
10-Oct-12
30-Oct-12
19-Nov-12
29-Nov-12
19-Sep-12
10-Oct-12
19-Dec-12
28-Jan-13
14-Mar-13
-
13-May-13
27-Jun-13
0.00%
0.00%
0%
0.00%
0%
0.00%
0%
0.00%
6.80%
0%
Shipment
Type
By Sea
By Sea
0.00%
2.27%
601,491.00
0%
0.00%
Item
0.00%
0%
A
Item
0.00%
Vendor
Name
0.00%
0.86%
0.00%
% Variance
PO #
0.00%
0.00%
Terrestrial
0.00%
By Sea
Remarks
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
CONSTRUCTION PROGRESS
MEASUREMENT
______________________________________
PREVIOUS WEEK
SER.
DESCRIPTION
THIS WEEK
UP TO DATE
MAN HOURS
REL. WT. %
PLANNED
ACTUAL
DEV.
PLANNED
ACTUAL
DEV.
PLANNED
ACTUAL
DEV.
498424
47.36%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
489518
46.51%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
56000
5.32%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
8460
0.80%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
1052402
100.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
TOTAL OF CONSTRUCTION
PHASE
26-Feb-12
ID
DESCRIPTION
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
2-Sep-12
15-Sep-12
10
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
5-Sep-12
23-Sep-12
15
3000
M/L
600
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
11-Sep-12
29-Sep-12
15
3000
M/L
3240
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
19-Sep-12
4-Oct-12
13
3000
M/L
1920
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
25-Sep-12
10-Oct-12
13
3000
M/L
840
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
29-Sep-12
16-Oct-12
15
250
Each
7800
29.4%
0.00%
0.00%
0.00%
0.00%
0.00%
4-Oct-12
22-Oct-12
15
250
Each
2040
7.7%
0.00%
0.00%
0.00%
0.00%
0.00%
10-Oct-12
28-Oct-12
15
250
Each
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CPA1180 Pre-Padding
16-Oct-12
3-Nov-12
15
3000
M/L
1680
6.3%
0.00%
0.00%
0.00%
0.00%
0.00%
22-Oct-12
8-Nov-12
15
3000
M/L
2520
9.5%
0.00%
0.00%
0.00%
0.00%
0.00%
28-Oct-12
14-Nov-12
15
100
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Nov-12
20-Nov-12
15
3000
M/L
1320
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
8-Nov-12
27-Nov-12
15
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
100.0%
0.00%
0.00%
0.00%
26-Feb-12
ID
DESCRIPTION
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
16-Sep-12
27-Sep-12
10
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
23-Sep-12
10-Oct-12
15
3000
M/L
600
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
29-Sep-12
16-Oct-12
15
3000
M/L
3240
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
7-Oct-12
22-Oct-12
13
3000
M/L
1920
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
13-Oct-12
28-Oct-12
13
3000
M/L
840
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
16-Oct-12
3-Nov-12
15
250
Each
7800
29.4%
0.00%
0.00%
0.00%
0.00%
0.00%
22-Oct-12
8-Nov-12
15
250
Each
2040
7.7%
0.00%
0.00%
0.00%
0.00%
0.00%
28-Oct-12
14-Nov-12
15
250
Each
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CPB1180 Pre-Padding
3-Nov-12
20-Nov-12
15
3000
M/L
1680
6.3%
0.00%
0.00%
0.00%
0.00%
0.00%
8-Nov-12
27-Nov-12
15
3000
M/L
2520
9.5%
0.00%
0.00%
0.00%
0.00%
0.00%
14-Nov-12
3-Dec-12
15
100
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
20-Nov-12
9-Dec-12
15
3000
M/L
1320
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
27-Nov-12
15-Dec-12
15
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
100.0%
0.00%
0.00%
0.00%
29-Sep-12
10-Oct-12
10
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
10-Oct-12
28-Oct-12
15
3000
M/L
600
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
16-Oct-12
3-Nov-12
15
3000
M/L
3240
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
24-Oct-12
8-Nov-12
13
3000
M/L
1920
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
CPC1130
26-Feb-12
ID
DESCRIPTION
CPC1140
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
30-Oct-12
14-Nov-12
13
3000
M/L
840
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Nov-12
20-Nov-12
15
250
Each
7800
29.4%
0.00%
0.00%
0.00%
0.00%
0.00%
8-Nov-12
27-Nov-12
15
250
Each
2040
7.7%
0.00%
0.00%
0.00%
0.00%
0.00%
14-Nov-12
3-Dec-12
15
250
Each
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CPC1180 Pre-Padding
20-Nov-12
9-Dec-12
15
3000
M/L
1680
6.3%
0.00%
0.00%
0.00%
0.00%
0.00%
27-Nov-12
15-Dec-12
15
3000
M/L
2520
9.5%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Dec-12
20-Dec-12
15
100
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
9-Dec-12
27-Dec-12
15
3000
M/L
1320
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Dec-12
3-Jan-13
15
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
100.0%
0.00%
0.00%
0.00%
11-Oct-12
23-Oct-12
10
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
28-Oct-12
14-Nov-12
15
3000
M/L
600
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Nov-12
20-Nov-12
15
3000
M/L
3240
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
11-Nov-12
27-Nov-12
13
3000
M/L
1920
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
17-Nov-12
3-Dec-12
13
3000
M/L
840
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
20-Nov-12
9-Dec-12
15
250
Each
7800
29.4%
0.00%
0.00%
0.00%
0.00%
0.00%
27-Nov-12
15-Dec-12
15
250
Each
2040
7.7%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Dec-12
20-Dec-12
15
250
Each
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
ID
DESCRIPTION
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
CPD1180 Pre-Padding
9-Dec-12
27-Dec-12
15
3000
M/L
1680
6.3%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Dec-12
3-Jan-13
15
3000
M/L
2520
9.5%
0.00%
0.00%
0.00%
0.00%
0.00%
20-Dec-12
9-Jan-13
15
100
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
27-Dec-12
15-Jan-13
15
3000
M/L
1320
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Jan-13
21-Jan-13
15
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
100.0%
0.00%
0.00%
0.00%
24-Oct-12
5-Nov-12
10
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
14-Nov-12
3-Dec-12
15
3000
M/L
600
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
20-Nov-12
9-Dec-12
15
3000
M/L
3240
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
29-Nov-12
15-Dec-12
13
3000
M/L
1920
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
5-Dec-12
20-Dec-12
13
3000
M/L
840
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
9-Dec-12
27-Dec-12
15
250
Each
7800
29.4%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Dec-12
3-Jan-13
15
250
Each
2040
7.7%
0.00%
0.00%
0.00%
0.00%
0.00%
20-Dec-12
9-Jan-13
15
250
Each
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CPE1180 Pre-Padding
27-Dec-12
15-Jan-13
15
3000
M/L
1680
6.3%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Jan-13
21-Jan-13
15
3000
M/L
2520
9.5%
0.00%
0.00%
0.00%
0.00%
0.00%
9-Jan-13
27-Jan-13
15
100
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Jan-13
2-Feb-13
15
3000
M/L
1320
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
ID
DESCRIPTION
21-Jan-13
7-Feb-13
DUR.
QUAN.
UNIT
15
3000
M/L
Q.DONE
M/H
480
1.8%
26520
100.0%
0.00%
0.00%
DEV %
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
6-Nov-12
18-Nov-12
10
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Dec-12
20-Dec-12
15
3000
M/L
600
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
9-Dec-12
27-Dec-12
15
3000
M/L
3240
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
17-Dec-12
3-Jan-13
13
3000
M/L
1920
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
23-Dec-12
9-Jan-13
13
3000
M/L
840
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
27-Dec-12
15-Jan-13
15
250
Each
7800
29.4%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Jan-13
21-Jan-13
15
250
Each
2040
7.7%
0.00%
0.00%
0.00%
0.00%
0.00%
9-Jan-13
27-Jan-13
15
250
Each
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CPF1180 Pre-Padding
15-Jan-13
2-Feb-13
15
3000
M/L
1680
6.3%
0.00%
0.00%
0.00%
0.00%
0.00%
21-Jan-13
7-Feb-13
15
3000
M/L
2520
9.5%
0.00%
0.00%
0.00%
0.00%
0.00%
27-Jan-13
13-Feb-13
15
100
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
2-Feb-13
19-Feb-13
15
3000
M/L
1320
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
7-Feb-13
25-Feb-13
15
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
100.0%
0.00%
0.00%
0.00%
480
1.8%
0.00%
0.00%
0.00%
19-Nov-12
2-Dec-12
10
3000
M/L
Page 150 of 266
0.00%
0.00%
26-Feb-12
ID
DESCRIPTION
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
20-Dec-12
9-Jan-13
15
3000
M/L
600
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
27-Dec-12
15-Jan-13
15
3000
M/L
3240
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
6-Jan-13
21-Jan-13
13
3000
M/L
1920
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
12-Jan-13
27-Jan-13
13
3000
M/L
840
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Jan-13
2-Feb-13
15
250
Each
7800
29.4%
0.00%
0.00%
0.00%
0.00%
0.00%
21-Jan-13
7-Feb-13
15
250
Each
2040
7.7%
0.00%
0.00%
0.00%
0.00%
0.00%
27-Jan-13
13-Feb-13
15
250
Each
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CPG1180 Pre-Padding
2-Feb-13
19-Feb-13
15
3000
M/L
1680
6.3%
0.00%
0.00%
0.00%
0.00%
0.00%
7-Feb-13
25-Feb-13
15
3000
M/L
2520
9.5%
0.00%
0.00%
0.00%
0.00%
0.00%
13-Feb-13
3-Mar-13
15
100
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
19-Feb-13
9-Mar-13
15
3000
M/L
1320
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
25-Feb-13
14-Mar-13
15
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
100.0%
0.00%
0.00%
0.00%
3-Dec-12
15-Dec-12
10
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
9-Jan-13
27-Jan-13
15
3000
M/L
600
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Jan-13
2-Feb-13
15
3000
M/L
3240
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
23-Jan-13
7-Feb-13
13
3000
M/L
1920
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
29-Jan-13
13-Feb-13
13
3000
M/L
840
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
ID
DESCRIPTION
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
2-Feb-13
19-Feb-13
15
250
Each
7800
29.4%
0.00%
0.00%
0.00%
0.00%
0.00%
7-Feb-13
25-Feb-13
15
250
Each
2040
7.7%
0.00%
0.00%
0.00%
0.00%
0.00%
13-Feb-13
3-Mar-13
15
250
Each
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CPH1180 Pre-Padding
19-Feb-13
9-Mar-13
15
3000
M/L
1680
6.3%
0.00%
0.00%
0.00%
0.00%
0.00%
25-Feb-13
14-Mar-13
15
3000
M/L
2520
9.5%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Mar-13
20-Mar-13
15
100
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
9-Mar-13
26-Mar-13
15
3000
M/L
1320
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
14-Mar-13
1-Apr-13
15
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
100.0%
0.00%
0.00%
0.00%
16-Dec-12
29-Dec-12
10
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
27-Jan-13
13-Feb-13
15
3000
M/L
600
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
2-Feb-13
19-Feb-13
15
3000
M/L
3240
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
10-Feb-13
25-Feb-13
13
3000
M/L
1920
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
16-Feb-13
3-Mar-13
13
3000
M/L
840
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
19-Feb-13
9-Mar-13
15
250
Each
7800
29.4%
0.00%
0.00%
0.00%
0.00%
0.00%
25-Feb-13
14-Mar-13
15
250
Each
2040
7.7%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Mar-13
20-Mar-13
15
250
Each
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CPI1180 Pre-Padding
9-Mar-13
26-Mar-13
15
3000
M/L
1680
6.3%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
ID
DESCRIPTION
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
14-Mar-13
1-Apr-13
15
3000
M/L
2520
9.5%
0.00%
0.00%
0.00%
0.00%
0.00%
20-Mar-13
7-Apr-13
15
100
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Mar-13
13-Apr-13
15
3000
M/L
1320
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
1-Apr-13
18-Apr-13
15
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
100.0%
0.00%
0.00%
0.00%
30-Dec-12
12-Jan-13
10
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
13-Feb-13
3-Mar-13
15
3000
M/L
600
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
19-Feb-13
9-Mar-13
15
3000
M/L
3240
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
27-Feb-13
14-Mar-13
13
3000
M/L
1920
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
5-Mar-13
20-Mar-13
13
3000
M/L
840
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
9-Mar-13
26-Mar-13
15
250
Each
7800
29.4%
0.00%
0.00%
0.00%
0.00%
0.00%
14-Mar-13
1-Apr-13
15
250
Each
2040
7.7%
0.00%
0.00%
0.00%
0.00%
0.00%
20-Mar-13
7-Apr-13
15
250
Each
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CPJ1180 Pre-Padding
26-Mar-13
13-Apr-13
15
3000
M/L
1680
6.3%
0.00%
0.00%
0.00%
0.00%
0.00%
1-Apr-13
18-Apr-13
15
3000
M/L
2520
9.5%
0.00%
0.00%
0.00%
0.00%
0.00%
7-Apr-13
24-Apr-13
15
100
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
13-Apr-13
30-Apr-13
15
3000
M/L
1320
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
18-Apr-13
6-May-13
15
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
ID
DESCRIPTION
DUR.
QUAN.
UNIT
Q.DONE
M/H
26520
100.0%
DEV %
0.00%
0.00%
0.00%
13-Jan-13
24-Jan-13
10
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Mar-13
20-Mar-13
15
3000
M/L
600
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
9-Mar-13
26-Mar-13
15
3000
M/L
3240
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
14-Mar-13
30-Mar-13
13
3000
M/L
1920
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
20-Mar-13
4-Apr-13
13
3000
M/L
840
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Mar-13
13-Apr-13
15
250
Each
7800
29.4%
0.00%
0.00%
0.00%
0.00%
0.00%
1-Apr-13
18-Apr-13
15
250
Each
2040
7.7%
0.00%
0.00%
0.00%
0.00%
0.00%
7-Apr-13
24-Apr-13
15
250
Each
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CPK1180 Pre-Padding
13-Apr-13
30-Apr-13
15
3000
M/L
1680
6.3%
0.00%
0.00%
0.00%
0.00%
0.00%
18-Apr-13
6-May-13
15
3000
M/L
2520
9.5%
0.00%
0.00%
0.00%
0.00%
0.00%
24-Apr-13
12-May-13
15
100
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
30-Apr-13
18-May-13
15
3000
M/L
1320
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
6-May-13
23-May-13
15
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
100.0%
0.00%
0.00%
0.00%
26-Jan-13
6-Feb-13
10
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
20-Mar-13
7-Apr-13
15
3000
M/L
600
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
ID
DESCRIPTION
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
26-Mar-13
13-Apr-13
15
3000
M/L
3240
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
31-Mar-13
15-Apr-13
13
3000
M/L
1920
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
6-Apr-13
21-Apr-13
13
3000
M/L
840
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
13-Apr-13
30-Apr-13
15
250
Each
7800
29.4%
0.00%
0.00%
0.00%
0.00%
0.00%
18-Apr-13
6-May-13
15
250
Each
2040
7.7%
0.00%
0.00%
0.00%
0.00%
0.00%
24-Apr-13
12-May-13
15
250
Each
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CPL1180 Pre-Padding
30-Apr-13
18-May-13
15
3000
M/L
1680
6.3%
0.00%
0.00%
0.00%
0.00%
0.00%
6-May-13
23-May-13
15
3000
M/L
2520
9.5%
0.00%
0.00%
0.00%
0.00%
0.00%
12-May-13
30-May-13
15
100
1800
6.8%
0.00%
0.00%
0.00%
0.00%
0.00%
18-May-13
5-Jun-13
15
3000
M/L
1320
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
23-May-13
11-Jun-13
15
3000
M/L
480
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
100.0%
0.00%
0.00%
0.00%
ITEM
M/H
WEIGHT%
PLAN
DEV
26520
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
ID
DESCRIPTION
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
26520
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
26520
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
10
26520
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
11
26520
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
12
26520
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
318240
100%
0.00%
0.00%
0.00%
42000
100.0%
0.00%
0.00%
0.00%
42000
100.0%
0.00%
0.00%
0.00%
15-Nov-12
30-May-13
164
84
Each
0.00%
0.00%
20-Dec-12
14-Feb-13
46
Each
22080
33.3%
0.00%
0.00%
0.00%
0.00%
0.00%
18-Feb-13
13-Apr-13
46
Each
22080
33.3%
0.00%
0.00%
0.00%
0.00%
0.00%
16-Apr-13
10-Jun-13
46
Each
22080
33.3%
0.00%
0.00%
0.00%
0.00%
0.00%
66240
100.0%
0.00%
0.00%
0.00%
26-Feb-12
ID
DESCRIPTION
CPCT1100
Cables To Be Welded By
Thermite
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
29-Oct-12
1-Jun-13
180
100
7200
50.0%
0.00%
0.00%
0.00%
0.00%
0.00%
29-Nov-12
1-Jul-13
180
100
7200
50.0%
0.00%
0.00%
0.00%
0.00%
0.00%
14400
100.0%
0.00%
0.00%
0.00%
2-Jul-13
27-Jul-13
20
100
800
12.0%
0.00%
0.00%
0.00%
0.00%
0.00%
9-Jul-13
1-Aug-13
20
100
2240
33.7%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Jul-13
7-Aug-13
20
100
800
12.0%
0.00%
0.00%
0.00%
0.00%
0.00%
7-Aug-13
19-Aug-13
10
100
560
8.4%
0.00%
0.00%
0.00%
0.00%
0.00%
19-Aug-13
12-Sep-13
20
100
1120
16.9%
0.00%
0.00%
0.00%
0.00%
0.00%
12-Sep-13
6-Oct-13
20
100
1120
16.9%
0.00%
0.00%
0.00%
0.00%
0.00%
6640
100.0%
0.00%
0.00%
0.00%
23-May-13
26-May-13
100
288
6.1%
0.00%
0.00%
0.00%
0.00%
0.00%
28-May-13
3-Jun-13
100
650
13.7%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Jun-13
8-Jun-13
100
800
16.8%
0.00%
0.00%
0.00%
0.00%
0.00%
8-Jun-13
17-Jun-13
100
2960
62.3%
0.00%
0.00%
0.00%
0.00%
0.00%
17-Jun-13
19-Jun-13
100
54
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
4752
100.0%
0.00%
0.00%
0.00%
26-Feb-12
ID
DESCRIPTION
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
8-Jun-13
10-Jun-13
100
288
6.1%
0.00%
0.00%
0.00%
0.00%
0.00%
11-Jun-13
17-Jun-13
100
650
13.7%
0.00%
0.00%
0.00%
0.00%
0.00%
17-Jun-13
22-Jun-13
100
800
16.8%
0.00%
0.00%
0.00%
0.00%
0.00%
22-Jun-13
1-Jul-13
100
2960
62.3%
0.00%
0.00%
0.00%
0.00%
0.00%
1-Jul-13
3-Jul-13
100
54
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
4752
100.0%
0.00%
0.00%
0.00%
CPAB2110
CPAB2140
18-Jun-13
6-Jul-13
14
36000
M/L
3360
14.2%
0.00%
0.00%
0.00%
0.00%
0.00%
6-Aug-13
29-Sep-13
45
36000
M/L
12960
54.8%
0.00%
0.00%
0.00%
0.00%
0.00%
29-Sep-13
10-Oct-13
10
36000
M/L
4080
17.3%
0.00%
0.00%
0.00%
0.00%
0.00%
12-Oct-13
29-Oct-13
15
36000
M/L
3240
13.7%
0.00%
0.00%
0.00%
0.00%
0.00%
23640
100.0%
0.00%
0.00%
0.00%
11-Jun-13
17-Jul-13
30
100
1920
10.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CPCA1110
ROW Re-Instatement
4-Aug-13
14-Oct-13
60
36000
M/L
7200
40.5%
0.00%
0.00%
0.00%
0.00%
0.00%
30
100
8640
48.6%
0.00%
0.00%
0.00%
0.00%
0.00%
17760
100.0%
0.00%
0.00%
0.00%
26-Feb-12
ID
DESCRIPTION
SER.
ITEM
DUR.
QUAN.
UNIT
Q.DONE
M/H
M/H
WEIGHT%
PLAN
DEV %
DEV
318240
63.85%
0.00%
0.00%
0.00%
0.00%
0.00%
42000
8.43%
0.00%
0.00%
0.00%
0.00%
0.00%
66240
13.29%
0.00%
0.00%
0.00%
0.00%
0.00%
14400
2.89%
0.00%
0.00%
0.00%
0.00%
0.00%
6640
1.33%
0.00%
0.00%
0.00%
0.00%
0.00%
4752
0.95%
0.00%
0.00%
0.00%
0.00%
0.00%
4752
0.95%
0.00%
0.00%
0.00%
0.00%
0.00%
23640
4.74%
0.00%
0.00%
0.00%
0.00%
0.00%
17760
3.56%
0.00%
0.00%
0.00%
0.00%
0.00%
498424
100.00%
0.00%
0.00%
0.00%
26-Feb-12
DATE:
ID
DESCRIPTION
EARLY START
EARLY FINISH
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
QP REFINERY
CIVIL WORKS
NO. OFF (7) CULVERTS
CULVERT NO. (1)
CRCU1100
5-Sep-12
11-Sep-12
100
650
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1110
11-Sep-12
20-Sep-12
100
1600
2.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1120
20-Sep-12
9-Oct-12
16
100
5920
9.9%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1130
9-Oct-12
21-Oct-12
10
100
400
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Oct-12
9-Oct-12
100
650
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1210
9-Oct-12
18-Oct-12
100
1600
2.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1220
18-Oct-12
6-Nov-12
16
100
5920
9.9%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1230
6-Nov-12
18-Nov-12
10
100
400
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
31-Oct-12
6-Nov-12
100
650
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1310
6-Nov-12
15-Nov-12
100
1600
2.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1320
15-Nov-12
5-Dec-12
16
100
5920
9.9%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1330
5-Dec-12
17-Dec-12
10
100
400
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
DATE:
ID
DESCRIPTION
EARLY START
EARLY FINISH
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
CRCU1400
29-Nov-12
5-Dec-12
100
650
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1410
5-Dec-12
15-Dec-12
100
1600
2.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1420
15-Dec-12
5-Jan-13
16
100
5920
9.9%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1430
5-Jan-13
16-Jan-13
10
100
400
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
29-Dec-12
5-Jan-13
100
650
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1510
5-Jan-13
14-Jan-13
100
1600
2.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1520
14-Jan-13
2-Feb-13
16
100
5920
9.9%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1530
2-Feb-13
13-Feb-13
10
100
400
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
27-Jan-13
2-Feb-13
100
650
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1610
2-Feb-13
11-Feb-13
100
1600
2.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1620
11-Feb-13
2-Mar-13
16
100
5920
9.9%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1630
2-Mar-13
13-Mar-13
10
100
400
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
24-Feb-13
2-Mar-13
100
650
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1710
2-Mar-13
11-Mar-13
100
1600
2.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1720
11-Mar-13
30-Mar-13
16
100
5920
9.9%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCU1730
30-Mar-13
10-Apr-13
10
100
400
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
DATE:
ID
DESCRIPTION
EARLY START
EARLY FINISH
DUR.
QUAN.
UNIT
Q.DONE
M/H
59990
100.0%
DEV %
0.00%
0.00%
0.00%
6-Nov-12
5-Feb-13
75
100
15750
65.6%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCS1110
31-Dec-12
30-Mar-13
75
100
8250
34.4%
0.00%
0.00%
0.00%
0.00%
0.00%
24000
100.0%
0.00%
0.00%
0.00%
13-Feb-13
2-Mar-13
14
100
1120
3.0%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCE1110
P.C (Foundation)
2-Mar-13
7-Mar-13
100
1200
3.3%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCE1120
R.C (Foundation)
7-Mar-13
26-Mar-13
16
100
2800
7.6%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCE1130
Insulation (Foundation)
26-Mar-13
31-Mar-13
100
720
2.0%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCE1140
BackFilling (Foundation)
1-Apr-13
4-Apr-13
100
280
0.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCE1150
R.C (Columns)
4-Apr-13
14-Apr-13
100
2160
5.9%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCE1160
14-Apr-13
16-May-13
28
100
4480
12.2%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCE1170
External Finishing
25-May-13
5-Aug-13
60
100
12000
32.6%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCE1180
Internal Finishing
8-Jun-13
18-Aug-13
60
100
12000
32.6%
0.00%
0.00%
0.00%
0.00%
0.00%
36760
100.0%
0.00%
0.00%
0.00%
26-Feb-12
DATE:
ID
DESCRIPTION
EARLY START
EARLY FINISH
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
CRCP1100
2-Mar-13
7-Mar-13
100
650
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1110
7-Mar-13
13-Mar-13
100
1130
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1120
13-Mar-13
25-Mar-13
10
100
3600
3.6%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1130
25-Mar-13
27-Mar-13
100
200
0.2%
0.00%
0.00%
0.00%
0.00%
0.00%
13-Mar-13
19-Mar-13
100
650
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1210
19-Mar-13
25-Mar-13
100
1130
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1220
25-Mar-13
6-Apr-13
10
100
3600
3.6%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1230
6-Apr-13
8-Apr-13
100
200
0.2%
0.00%
0.00%
0.00%
0.00%
0.00%
25-Mar-13
31-Mar-13
100
650
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1310
31-Mar-13
6-Apr-13
100
1130
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1320
6-Apr-13
17-Apr-13
10
100
3600
3.6%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1330
17-Apr-13
20-Apr-13
100
200
0.2%
0.00%
0.00%
0.00%
0.00%
0.00%
6-Apr-13
11-Apr-13
100
650
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1410
11-Apr-13
17-Apr-13
100
1130
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1420
17-Apr-13
29-Apr-13
10
100
3600
3.6%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1430
29-Apr-13
1-May-13
100
200
0.2%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
DATE:
ID
DESCRIPTION
EARLY START
EARLY FINISH
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
17-Apr-13
23-Apr-13
100
650
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1510
23-Apr-13
29-Apr-13
100
1130
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1520
29-Apr-13
11-May-13
10
100
3600
3.6%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1530
11-May-13
13-May-13
100
200
0.2%
0.00%
0.00%
0.00%
0.00%
0.00%
29-Apr-13
5-May-13
100
650
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1610
5-May-13
11-May-13
100
1130
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1620
11-May-13
22-May-13
10
100
3600
3.6%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1630
22-May-13
25-May-13
100
200
0.2%
0.00%
0.00%
0.00%
0.00%
0.00%
22-May-13
29-May-13
100
650
0.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1710
29-May-13
4-Jun-13
100
1130
1.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1720
4-Jun-13
16-Jun-13
10
100
3600
3.6%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCP1730
16-Jun-13
18-Jun-13
100
200
0.2%
0.00%
0.00%
0.00%
0.00%
0.00%
11-Apr-13
22-Jun-13
60
100
19680
19.8%
0.00%
0.00%
0.00%
0.00%
0.00%
22-May-13
4-Jun-13
10
100
1300
1.3%
0.00%
0.00%
0.00%
0.00%
0.00%
4-Jun-13
16-Jun-13
10
100
2260
2.3%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
DATE:
ID
DESCRIPTION
EARLY START
EARLY FINISH
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
CRCD1130
16-Jun-13
10-Jul-13
20
100
7200
7.2%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCD1140
10-Jul-13
15-Jul-13
100
400
0.4%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Jul-13
19-Aug-13
30
100
9840
9.9%
0.00%
0.00%
0.00%
0.00%
0.00%
19-Aug-13
7-Sep-13
15
100
4920
4.9%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCD1150
CRCD1160
CRCD1170
7-Sep-13
24-Sep-13
15
100
4950
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCD1180
24-Sep-13
29-Oct-13
30
100
9900
9.9%
0.00%
0.00%
0.00%
0.00%
0.00%
99510
100.0%
0.00%
0.00%
0.00%
22-May-13
30-May-13
100
780
5.2%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCL1110
30-May-13
11-Jun-13
10
100
2000
13.5%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCL1120
18-Jun-13
10-Jul-13
18
100
6660
44.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCL1130
10-Jul-13
17-Jul-13
100
270
1.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCL1140
17-Jul-13
10-Aug-13
20
100
4000
26.9%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCL1150
10-Aug-13
27-Aug-13
15
100
1152
7.8%
0.00%
0.00%
0.00%
0.00%
0.00%
14862
100.0%
0.00%
0.00%
0.00%
15-Aug-13
15-Sep-13
25
100
4320
55.6%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCR1110
15-Sep-13
26-Sep-13
10
100
1728
22.2%
0.00%
0.00%
0.00%
0.00%
0.00%
CRCR1120
26-Sep-13
8-Oct-13
10
100
1728
22.2%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
DATE:
ID
DESCRIPTION
EARLY START
EARLY FINISH
DUR.
QUAN.
UNIT
Q.DONE
M/H
7776
207.8%
0.00%
0.00%
DEV %
0.00%
ITEM
M/H
WEIGHT%
PLAN
DEV
59990
24.7%
0.00%
0.00%
0.00%
0.00%
0.00%
24000
9.9%
0.00%
0.00%
0.00%
0.00%
0.00%
SER12 EXTENSION
36760
15.1%
0.00%
0.00%
0.00%
0.00%
0.00%
PUMP HOUSE
99510
41.0%
0.00%
0.00%
0.00%
0.00%
0.00%
LAUNCHER STATION
14862
6.1%
0.00%
0.00%
0.00%
0.00%
0.00%
THE ROADS
7776
3.2%
0.00%
0.00%
0.00%
0.00%
0.00%
242898
100%
0.00%
0.00%
0.00%
30-Apr-13
5-Jun-13
30
100
17700
76.1%
0.00%
0.00%
0.00%
0.00%
0.00%
6-Jun-13
18-Jun-13
10
100
5545
23.9%
0.00%
0.00%
0.00%
0.00%
0.00%
23245
100.0%
0.00%
0.00%
0.00%
Piping Fabrication
30-Apr-13
11-Jul-13
60
100
49224
40.5%
0.00%
0.00%
0.00%
0.00%
0.00%
CRMP1110
22-May-13
20-Jul-13
48
100
11040
9.1%
0.00%
0.00%
0.00%
0.00%
0.00%
CRMP1120
28-Jul-13
7-Oct-13
60
100
47327
39.0%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
DATE:
ID
DESCRIPTION
EARLY START
EARLY FINISH
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
CRMP1130
7-Oct-13
24-Oct-13
15
100
4320
3.6%
0.00%
0.00%
0.00%
0.00%
0.00%
CRMP1140
Loops to be Pressurized
13-Oct-13
30-Oct-13
15
100
6120
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
CRMP1150
19-Oct-13
5-Nov-13
15
100
3240
2.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRMP1160
Tie in at Refinary
23-Sep-13
7-Oct-13
12
100
180
0.1%
0.00%
0.00%
0.00%
0.00%
0.00%
121451
100.0%
0.00%
0.00%
0.00%
Piping Fabrication
17-Jul-13
4-Aug-13
15
100
8739
36.9%
0.00%
0.00%
0.00%
0.00%
0.00%
CRM1170
25-Jul-13
12-Aug-13
15
100
3545
15.0%
0.00%
0.00%
0.00%
0.00%
0.00%
CRM1180
6-Aug-13
24-Aug-13
15
100
11400
48.1%
0.00%
0.00%
0.00%
0.00%
0.00%
23684
100.0%
0.00%
0.00%
0.00%
ITEM
M/H
WEIGHT%
PLAN
DEV
GENERAL
23245
13.8%
0.00%
0.00%
0.00%
0.00%
0.00%
PUMP HOUSE
121451
72.1%
0.00%
0.00%
0.00%
0.00%
0.00%
LAUNCHER STATION
23684
14.1%
0.00%
0.00%
0.00%
0.00%
0.00%
168380
100%
0.00%
0.00%
0.00%
26-Feb-12
DATE:
ID
CRES1100
CRES1110
CRES1120
DESCRIPTION
Modification Of Existing 11
KV Switchgear
Modification Of Existing 3.3
KV Switchgear
Modification Of Existing 415 V
Switchgear
EARLY START
EARLY FINISH
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
10-Jun-13
16-Jul-13
30
100
6300
14.9%
0.00%
0.00%
0.00%
0.00%
0.00%
22-Jun-13
28-Jul-13
30
100
6300
14.9%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Jul-13
19-Aug-13
30
100
6300
14.9%
0.00%
0.00%
0.00%
0.00%
0.00%
EXTENSION OF SER-12
CREE1100
18-Aug-13
25-Aug-13
100
1020
2.4%
0.00%
0.00%
0.00%
0.00%
0.00%
CREE1110
24-Aug-13
31-Aug-13
100
1020
2.4%
0.00%
0.00%
0.00%
0.00%
0.00%
CREE1130
27-Aug-13
4-Sep-13
100
1020
2.4%
0.00%
0.00%
0.00%
0.00%
0.00%
CREE1120
Termination
4-Sep-13
11-Sep-13
100
1020
2.4%
0.00%
0.00%
0.00%
0.00%
0.00%
CREP1100
19-Sep-13
29-Sep-13
100
1680
4.0%
0.00%
0.00%
0.00%
0.00%
0.00%
CREP1110
25-Sep-13
5-Oct-13
100
1680
4.0%
0.00%
0.00%
0.00%
0.00%
0.00%
29-Sep-13
8-Oct-13
100
1680
4.0%
0.00%
0.00%
0.00%
0.00%
0.00%
2-Oct-13
12-Oct-13
100
1680
4.0%
0.00%
0.00%
0.00%
0.00%
0.00%
6-Oct-13
15-Oct-13
100
1680
4.0%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Oct-13
29-Oct-13
12
100
2520
6.0%
0.00%
0.00%
0.00%
0.00%
0.00%
22-Sep-13
29-Sep-13
100
1260
3.0%
0.00%
0.00%
0.00%
0.00%
0.00%
28-Sep-13
5-Oct-13
100
1260
3.0%
0.00%
0.00%
0.00%
0.00%
0.00%
3-Oct-13
10-Oct-13
100
1260
3.0%
0.00%
0.00%
0.00%
0.00%
0.00%
PUMP AREA
CREP1120
CREP1130
CREP1140
CREP1150
LAUNCHER AREA
CREL1100
CREL1110
CREL1120
26-Feb-12
DATE:
ID
CREL1130
CREL1140
CREL1150
DESCRIPTION
EARLY START
EARLY FINISH
DUR.
QUAN.
UNIT
9-Oct-13
16-Oct-13
100
1260
3.0%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Oct-13
22-Oct-13
100
1260
3.0%
0.00%
0.00%
0.00%
0.00%
0.00%
16-Oct-13
28-Oct-13
10
100
2100
5.0%
0.00%
0.00%
0.00%
0.00%
0.00%
42300
100.0%
0.00%
0.00%
0.00%
Q.DONE
M/H
DEV %
INSTRUMENTATION WORKS
SUB-STATION 6003
CRIS1100
Laying of Cables
19-Aug-13
31-Aug-13
10
100
2100
5.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CRIS1110
31-Aug-13
12-Sep-13
10
100
2100
5.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CRIS1120
7-Sep-13
18-Sep-13
10
100
2100
5.8%
0.00%
0.00%
0.00%
0.00%
0.00%
11-Sep-13
18-Sep-13
100
1020
2.8%
0.00%
0.00%
0.00%
0.00%
0.00%
18-Sep-13
25-Sep-13
100
1020
2.8%
0.00%
0.00%
0.00%
0.00%
0.00%
21-Sep-13
28-Sep-13
100
1020
2.8%
0.00%
0.00%
0.00%
0.00%
0.00%
23-Sep-13
30-Sep-13
100
1020
2.8%
0.00%
0.00%
0.00%
0.00%
0.00%
25-Sep-13
2-Oct-13
100
1020
2.8%
0.00%
0.00%
0.00%
0.00%
0.00%
2-Oct-13
9-Oct-13
100
1020
2.8%
0.00%
0.00%
0.00%
0.00%
0.00%
CRIP1100
Laying Of Cables
25-Sep-13
5-Oct-13
100
1680
4.7%
0.00%
0.00%
0.00%
0.00%
0.00%
CRIP1110
Installation Of Flow
Transmitter
29-Sep-13
8-Oct-13
100
1680
4.7%
0.00%
0.00%
0.00%
0.00%
0.00%
EXTENSION OF SER-12
CRIE1100
CRIE1120
CRIE1130
CRIE1140
CRIE1150
CRIE1160
Laying of Cables
DCS System Cabinet to be
Modified
DCS Marchaling Cabinet to be
Modified
ESD System Cabinet to be
Modified
F&G System Cabinet to be
Modified
PUMP AREA
26-Feb-12
DATE:
ID
CRIP1120
CRIP1130
CRIP1140
CRIP1150
CRIP1160
CRIP1170
DESCRIPTION
Installation Of Pressure
Gauges With Fittings
Installation Of Pressure
Transmitters With Tubes &
Fittings
Installation
Of Junction Boxes
For Pump Area
Installation Of Gas Detectors
For Pump Area
Installation Of Manual Call
Point For Pump Area
Termination For Pump Area
EARLY START
EARLY FINISH
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
2-Oct-13
12-Oct-13
100
1680
4.7%
0.00%
0.00%
0.00%
0.00%
0.00%
6-Oct-13
15-Oct-13
100
1680
4.7%
0.00%
0.00%
0.00%
0.00%
0.00%
9-Oct-13
19-Oct-13
100
1680
4.7%
0.00%
0.00%
0.00%
0.00%
0.00%
13-Oct-13
22-Oct-13
100
1680
4.7%
0.00%
0.00%
0.00%
0.00%
0.00%
16-Oct-13
26-Oct-13
100
1680
4.7%
0.00%
0.00%
0.00%
0.00%
0.00%
20-Oct-13
29-Oct-13
100
1680
4.7%
0.00%
0.00%
0.00%
0.00%
0.00%
LAUNCHER AREA
CRIL1110
Laying Of Cables
28-Sep-13
5-Oct-13
100
1260
3.5%
0.00%
0.00%
0.00%
0.00%
0.00%
CRIL1120
1-Oct-13
8-Oct-13
100
1260
3.5%
0.00%
0.00%
0.00%
0.00%
0.00%
5-Oct-13
12-Oct-13
100
1260
3.5%
0.00%
0.00%
0.00%
0.00%
0.00%
CRIL1130
CRIL1140
CRIL1150
CRIL1160
CRIL1170
CRIL1180
Installation Of Pressure
Gauges With Fittings
Installation Of Pressure
Transmitters With Tubes &
Fittings
Installation
Of Distribution
Boards For Launcher
Installation Of Gas Detectors
For Launcher
Installation Of Manual Call
Point For Launcher
8-Oct-13
15-Oct-13
100
1260
3.5%
0.00%
0.00%
0.00%
0.00%
0.00%
12-Oct-13
19-Oct-13
100
1260
3.5%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Oct-13
22-Oct-13
100
1260
3.5%
0.00%
0.00%
0.00%
0.00%
0.00%
19-Oct-13
26-Oct-13
100
1260
3.5%
0.00%
0.00%
0.00%
0.00%
0.00%
22-Oct-13
29-Oct-13
100
1260
3.5%
0.00%
0.00%
0.00%
0.00%
0.00%
35940
100.0%
0.00%
0.00%
0.00%
ITEM
M/H
Page 170 of 266
WEIGHT%
PLAN
DEV
26-Feb-12
DATE:
ID
DESCRIPTION
EARLY START
EARLY FINISH
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
CIVIL WORKS
242898
49.62%
0.00%
0.00%
0.00%
0.00%
0.00%
MECHANICAL WORKS
168380
34.40%
0.00%
0.00%
0.00%
0.00%
0.00%
ELECTRICAL WORKS
42300
8.64%
0.00%
0.00%
0.00%
0.00%
0.00%
INSTRUMENTATION WORKS
35940
7.34%
0.00%
0.00%
0.00%
0.00%
0.00%
489518
100.00%
0.00%
0.00%
0.00%
26-Feb-12
DATE:
ID
DESCRIPTION
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
BSV-3
CIVIL WORKS
CBSC1100 Excavation In BSV-3
Plain Concrete In
BSV-3
Re-Inforced Concrete
CBSC1120
In BSV-3
CBSC1110
8-Aug-13
20-Aug-13
10
100
1200
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
14-Aug-13
26-Aug-13
10
100
1200
8.3%
0.00%
0.00%
0.00%
0.00%
0.00%
20-Aug-13
1-Sep-13
10
100
6000
41.7%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Aug-13
8-Sep-13
10
100
6000
41.7%
0.00%
0.00%
0.00%
0.00%
0.00%
14400
100.0%
0.00%
0.00%
0.00%
20-Aug-13
8-Sep-13
15
100
7800
75.0%
0.00%
0.00%
0.00%
0.00%
0.00%
6-Nov-13
12-Nov-13
100
2600
25.0%
0.00%
0.00%
0.00%
0.00%
0.00%
10400
100.0%
0.00%
0.00%
0.00%
18-Jul-13
30-Jul-13
10
100
5100
32.7%
0.00%
0.00%
0.00%
0.00%
0.00%
4-Sep-13
16-Sep-13
10
100
2550
16.3%
0.00%
0.00%
0.00%
0.00%
0.00%
21-Oct-13
2-Nov-13
10
100
7950
51.0%
0.00%
0.00%
0.00%
0.00%
0.00%
15600
100.0%
0.00%
0.00%
0.00%
26-Feb-12
DESCRIPTION
Installation Of
Pressure Transmitters
CBSI1120 Termination
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
4-Sep-13
16-Sep-13
10
100
5100
32.7%
0.00%
0.00%
0.00%
0.00%
0.00%
16-Sep-13
28-Sep-13
10
100
2550
16.3%
0.00%
0.00%
0.00%
0.00%
0.00%
28-Sep-13
9-Oct-13
10
100
7950
51.0%
0.00%
0.00%
0.00%
0.00%
0.00%
15600
100.0%
0.00%
0.00%
0.00%
ITEM
M/H
WEIGHT%
PLAN
CIVIL WORKS
14400
25.71%
0.00%
0.00%
0.00%
0.00%
0.00%
MECHANICAL WORKS
10400
18.57%
0.00%
0.00%
0.00%
0.00%
0.00%
ELECTRICAL WORKS
15600
27.86%
0.00%
0.00%
0.00%
0.00%
0.00%
INSTRUMENTATION WORKS
15600
27.86%
0.00%
0.00%
0.00%
0.00%
0.00%
56000
100.00%
0.00%
0.00%
0.00%
DEV
26-Feb-12
DATE:
ID
DESCRIPTION
DUR.
QUAN.
UNIT
Q.DONE
M/H
DEV %
Close Out
Project Close Out
FPCO1100 As-Built Drawings
FPCO1110
Asset Capitalization
Schedule (ACS)
31-May-14
28-Jul-14
50
100
2700
31.9%
0.00%
0.00%
0.00%
0.00%
0.00%
1-Jun-14
17-Jul-14
40
100
3200
37.8%
0.00%
0.00%
0.00%
0.00%
0.00%
28-Jun-14
25-Aug-14
50
100
2560
30.3%
0.00%
0.00%
0.00%
0.00%
0.00%
8460
100.0%
0.00%
0.00%
0.00%
ITEM
Close out
TOTAL OF ALL WORKS INSIDE BSV-3
M/H
WEIGHT%
PLAN
ACTUAL
8460
100.00%
0.00%
0.00%
8460
100.00%
DEV
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
26-Feb-12
DESCRIPTION
E START
M/H
WEIGHT%
PLANNED
%
ACTUAL
%
WT. PL %
WT. ACT%
DEV %
4,500
6.56%
0.00%
0.00%
0.00%
0.00%
0.00%
E FINISH
DUR.
T. Q.TY
UNIT
24-Nov-13
4-Feb-14
60
100
Q.DONE
FCOM1110
7-Dec-13
16-Feb-14
60
100
9,000
13.12%
0.00%
0.00%
0.00%
0.00%
0.00%
FCOM1120
18-Dec-13
27-Feb-14
60
100
9,000
13.12%
0.00%
0.00%
0.00%
0.00%
0.00%
FCOM1130
31-Dec-13
11-Mar-14
60
100
9,000
13.12%
0.00%
0.00%
0.00%
0.00%
0.00%
FCOM1140
12-Jan-14
23-Mar-14
60
100
9,000
13.12%
0.00%
0.00%
0.00%
0.00%
0.00%
FCOM1150
23-Jan-14
3-Apr-14
60
100
9,000
13.12%
0.00%
0.00%
0.00%
0.00%
0.00%
FCOM1160
4-Feb-14
15-Apr-14
60
100
9,000
13.12%
0.00%
0.00%
0.00%
0.00%
0.00%
15-Apr-14
19-Apr-14
100
2,240
3.27%
0.00%
0.00%
0.00%
0.00%
0.00%
19-Apr-14
7-May-14
16
100
5,600
8.17%
0.00%
0.00%
0.00%
0.00%
0.00%
FCOM1190
10-May-14
21-May-14
10
100
2,240
3.27%
0.00%
0.00%
0.00%
0.00%
0.00%
68580
100.0%
0.00%
0.00%
0.00%
Date :
26-Feb-12
Act. ID
DESCRIPTION
E START
E FINISH
DUR.
T. Q.TY
UNIT
Q.DONE
M/H
5-Nov-12
31-May-13
150
100
12,000
71.22%
0.00%
WT. PL %
WT. ACT%
DEV %
0.00%
0.00%
0.00%
0.00%
OPT1100
OPT1110
20-May-13
31-May-13
10
100
800
4.75%
0.00%
0.00%
0.00%
0.00%
0.00%
OPT1120
Baseline Survey
11-Jun-14
23-Jul-14
36
100
4,050
24.04%
0.00%
0.00%
0.00%
0.00%
0.00%
16850
100.0%
0.00%
0.00%
0.00%
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
PROGRESS S-CURVES, LATE CURVES AND
TABLES ON WEEKLY AND MONTHLY BASIS
______________________________________
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
PROGRESS S-CURVES
_____________________________________
100.00
PROG. %
90.00
80.00
70.00
60.00
50.00
40.00
30.00
Planned
Actual
Dev.
20.00
10.00
:
:
:
%
%
%
0.00
DATE
Page 179 of 266
100.00
PROG. %
90.00
80.00
70.00
60.00
50.00
40.00
30.00
Planned
Actual
Dev.
20.00
10.00
:
:
:
%
%
%
0.00
DATE
Page 180 of 266
100.00
PROG. %
90.00
80.00
70.00
60.00
50.00
40.00
30.00
Planned
Actual
Dev.
20.00
10.00
:
:
:
%
%
%
0.00
DATE
Page 181 of 266
100.00
PROG. %
90.00
80.00
70.00
60.00
50.00
40.00
30.00
Planned
Actual
Dev.
20.00
10.00
:
:
:
%
%
%
0.00
DATE
Page 182 of 266
100.00
PROG. %
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
Planned
Actual
Dev.
10.00
:
:
:
%
%
%
0.00
DATE
Page 183 of 266
100.00
PROG. %
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
Planned
Actual
Dev.
10.00
:
:
:
%
%
%
0.00
DATE
Page 184 of 266
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
PROGRESS LATE CURVE
______________________________________
21-Jul-12 22:34
12500d
187500d
10000d
150000d
7500d
112500d
5000d
75000d
2500d
37500d
Mar
Apr
May
Jun
Jul
2012
Budgeted Units
Remaining Late Units
Limit
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
2013
PETROJET CO
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Date
19-Jul-12
Mar
Apr
May
2014
Revision
Rev(5)
Jun
Checked
Y.Abdalshaf...
Jul
Aug
Approved
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
PROGRESS TABLES ON WEEKLY AND
MONTHLY BASIS
______________________________________
PLANNED
PLANNED
PLANNED
29-02-2012
31-03-2012
30-04-2012
31-05-2012
30-06-2012
31-07-2012
31-08-2012
30-09-2012
31-10-2012
30-11-2012
31-12-2012
Engineering
0.00
0.07
1.66
5.54
15.30
40.64
65.86
85.47
94.75
95.00
95.00
Procurement
0.00
0.00
0.00
0.00
0.00
4.20
12.38
23.53
27.26
34.92
39.50
Construction
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.22
5.44
11.30
18.17
Precomm&Comm
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Optional
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
8.60
19.27
Overall
0.00
0.00
0.08
0.28
0.77
3.71
8.25
14.27
18.25
24.31
29.66
31-01-2013
28-02-2013
31-03-2013
30-04-2013
31-05-2013
30-06-2013
31-07-2013
31-08-2013
30-09-2013
31-10-2013
30-11-2013
Engineering
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
Procurement
40.27
42.42
42.42
52.59
61.06
76.09
86.47
92.89
96.59
100.00
100.00
Construction
26.15
33.04
42.00
49.91
59.07
67.44
73.79
82.03
89.64
98.15
99.20
Precomm&Comm
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.55
Optional
29.93
39.56
50.23
60.55
75.96
75.96
75.96
75.96
75.96
75.96
75.96
Overall
34.01
38.37
42.88
50.95
59.05
69.08
76.28
82.80
87.93
93.38
93.91
31-12-2013
31-01-2014
28-02-2014
31-03-2014
30-04-2014
31-05-2014
30-06-2014
31-07-2014
25-08-2014
Engineering
95.00
95.00
95.00
95.00
95.00
95.00
97.33
100.00
100.00
Procurement
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
Construction
99.20
99.20
99.20
99.20
99.20
99.20
99.53
99.90
100.00
Precomm&Comm
10.20
35.37
63.93
81.93
93.56
100.00
100.00
100.00
100.00
Optional
75.96
75.96
75.96
75.96
75.96
75.96
86.84
100.00
100.00
Overall
94.40
95.65
97.08
97.98
98.56
98.89
99.38
99.95
100.00
26-02-2012 01-03-2012 08-03-2012 15-03-2012 22-03-2012 29-03-2012 05-04-2012 12-04-2012 19-04-2012 26-04-2012 03-05-2012
PLANNED
Engineering
0.00
0.00
0.00
0.00
0.00
0.07
0.14
1.18
1.53
1.53
2.26
Procurement
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Construction
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Precomm&Comm
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Optional
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Overall
0.00
0.00
0.00
0.00
0.00
0.00
0.01
0.06
0.08
0.08
0.11
10
10-05-2012 17-05-2012 24-05-2012 31-05-2012 07-06-2012 14-06-2012 21-06-2012 28-06-2012 05-07-2012 12-07-2012 19-07-2012
PLANNED
Engineering
2.49
3.80
4.43
5.54
7.84
9.99
12.44
15.30
18.76
23.13
28.26
Procurement
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Construction
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Precomm&Comm
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Optional
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Overall
0.12
0.19
0.22
0.28
0.39
0.50
0.62
0.77
0.94
1.16
1.41
11
12
13
14
15
16
17
18
19
20
21
26-07-2012 02-08-2012 09-08-2012 16-08-2012 23-08-2012 30-08-2012 06-09-2012 13-09-2012 20-09-2012 27-09-2012 04-10-2012
PLANNED
Engineering
35.57
42.82
47.93
53.80
59.93
65.86
72.62
76.68
80.72
84.02
87.46
Procurement
2.19
4.90
5.08
8.21
11.35
12.25
13.55
14.73
20.48
20.94
23.57
Construction
0.00
0.00
0.00
0.00
0.00
0.00
0.02
0.19
0.49
0.96
1.69
Precomm&Comm
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Optional
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Overall
2.65
4.10
4.43
5.97
7.54
8.19
9.06
9.82
12.46
13.04
14.61
22
23
24
25
26
27
28
29
30
31
32
11-10-2012 18-10-2012 25-10-2012 01-11-2012 08-11-2012 15-11-2012 22-11-2012 29-11-2012 06-12-2012 13-12-2012 20-12-2012
PLANNED
Engineering
89.47
91.64
94.75
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
Procurement
27.14
27.14
27.26
27.26
27.26
28.86
32.90
34.90
36.63
38.32
39.38
Construction
2.58
3.46
4.48
5.62
6.93
8.20
9.67
11.08
12.59
14.03
15.48
Precomm&Comm
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Optional
0.00
0.00
0.00
0.00
1.03
3.44
5.85
8.26
10.67
13.07
15.48
Overall
16.57
17.10
17.79
18.35
19.00
20.30
22.67
24.19
25.66
27.07
28.24
33
34
35
36
37
38
39
40
41
42
43
27-12-2012 03-01-2013 10-01-2013 17-01-2013 24-01-2013 31-01-2013 07-02-2013 14-02-2013 21-02-2013 28-02-2013 07-03-2013
PLANNED
Engineering
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
Procurement
39.50
39.83
39.83
39.83
39.94
40.27
40.27
42.03
42.07
42.42
42.44
Construction
17.19
18.95
20.67
22.45
24.27
26.15
27.98
29.65
31.26
33.04
34.92
Precomm&Comm
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Optional
17.89
20.30
22.71
25.12
27.52
29.93
32.34
34.75
37.16
39.56
41.97
Overall
29.16
30.18
31.06
31.96
32.93
34.01
34.94
36.49
37.33
38.37
39.33
44
45
46
47
48
49
50
51
52
53
54
14-03-2013 21-03-2013 28-03-2013 04-04-2013 11-04-2013 18-04-2013 25-04-2013 02-05-2013 09-05-2013 16-05-2013 23-05-2013
PLANNED
Engineering
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
Procurement
42.44
42.44
42.44
46.14
46.95
48.79
49.03
53.03
53.93
56.45
57.30
Construction
36.88
39.01
41.16
43.06
44.98
46.83
48.03
50.55
52.77
54.87
56.77
Precomm&Comm
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Optional
44.38
46.79
49.20
51.61
54.01
56.42
58.83
61.24
63.65
66.06
69.76
Overall
40.32
41.39
42.47
44.91
46.20
47.87
48.59
51.45
52.92
54.99
56.31
55
56
57
58
59
60
61
62
63
64
65
30-05-2013 06-06-2013 13-06-2013 20-06-2013 27-06-2013 04-07-2013 11-07-2013 18-07-2013 25-07-2013 01-08-2013 08-08-2013
PLANNED
Engineering
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
Procurement
60.96
63.92
66.30
66.53
73.74
76.50
78.37
82.43
85.72
86.47
86.47
Construction
58.79
60.72
62.87
64.83
66.65
68.40
69.90
70.82
72.33
74.02
75.56
Precomm&Comm
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Optional
75.19
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
Overall
58.86
60.98
62.97
64.00
67.76
69.70
71.17
73.23
75.28
76.39
77.13
66
67
68
69
70
71
72
73
74
75
76
15-08-2013 22-08-2013 29-08-2013 05-09-2013 12-09-2013 19-09-2013 26-09-2013 03-10-2013 10-10-2013 17-10-2013 24-10-2013
PLANNED
Engineering
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
Procurement
86.82
86.82
92.38
95.04
95.30
96.59
96.59
96.59
96.59
100.00
100.00
Construction
77.31
79.26
81.41
83.39
85.35
86.85
88.41
90.72
93.16
94.65
96.59
Precomm&Comm
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Optional
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
Overall
78.11
79.04
82.30
84.31
85.36
86.59
87.34
88.45
89.62
91.70
92.63
77
78
79
80
81
82
83
84
85
86
87
31-10-2013 07-11-2013 14-11-2013 21-11-2013 28-11-2013 05-12-2013 12-12-2013 19-12-2013 26-12-2013 02-01-2014 09-01-2014
PLANNED
Engineering
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
Procurement
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
Construction
98.15
98.57
98.94
99.10
99.20
99.20
99.20
99.20
99.20
99.20
99.20
Precomm&Comm
0.00
0.00
0.00
0.00
0.36
1.00
2.56
4.56
7.91
11.51
16.05
Optional
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
Overall
93.38
93.58
93.76
93.84
93.90
93.94
94.01
94.11
94.28
94.46
94.69
88
89
90
91
92
93
94
95
96
97
98
16-01-2014 23-01-2014 30-01-2014 06-02-2014 13-02-2014 20-02-2014 27-02-2014 06-03-2014 13-03-2014 20-03-2014 27-03-2014
PLANNED
Engineering
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
Procurement
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
Construction
99.20
99.20
99.20
99.20
99.20
99.20
99.20
99.20
99.20
99.20
99.20
Precomm&Comm
21.33
27.18
34.35
41.70
49.54
56.64
63.18
68.43
73.30
77.24
80.43
Optional
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
Overall
94.95
95.24
95.60
95.97
96.36
96.72
97.04
97.31
97.55
97.75
97.91
99
100
101
102
103
104
105
106
107
108
109
03-04-2014 10-04-2014 17-04-2014 24-04-2014 01-05-2014 08-05-2014 15-05-2014 22-05-2014 29-05-2014 05-06-2014 12-06-2014
PLANNED
Engineering
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.00
95.63
Procurement
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
Construction
99.20
99.20
99.20
99.20
99.20
99.20
99.20
99.20
99.20
99.24
99.32
Precomm&Comm
83.05
84.36
86.93
90.84
94.01
96.73
98.22
100.00
100.00
100.00
100.00
Optional
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
75.96
Overall
98.04
98.10
98.23
98.43
98.59
98.72
98.80
98.89
98.89
98.90
98.97
110
111
112
113
114
115
116
117
118
119
120
19-06-2014 26-06-2014 03-07-2014 10-07-2014 17-07-2014 24-07-2014 31-07-2014 07-08-2014 14-08-2014 21-08-2014 25-08-2014
PLANNED
Engineering
96.25
96.88
97.50
98.13
98.75
99.38
100.00
100.00
100.00
100.00
100.00
Procurement
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
Construction
99.40
99.48
99.57
99.68
99.79
99.85
99.90
99.92
99.95
99.98
100.00
Precomm&Comm
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
Optional
80.54
84.55
88.55
92.56
96.57
100.00
100.00
100.00
100.00
100.00
100.00
Overall
99.14
99.29
99.44
99.60
99.77
99.90
99.95
99.96
99.98
99.99
100.00
121
122
123
124
125
126
127
128
129
130
131
Month No.
Date
Cumulative Planned
29-Feb-12
0.00
0.00
31-Mar-12
0.00
0.00
30-Apr-12
0.08
0.08
31-May-12
0.28
0.19
30-Jun-12
0.77
0.49
31-Jul-12
3.71
2.95
31-Aug-12
8.25
4.53
30-Sep-12
14.27
6.03
31-Oct-12
18.25
3.98
30-Nov-12
24.31
6.06
10
31-Dec-12
29.66
5.34
11
31-Jan-13
34.01
4.35
12
28-Feb-13
38.37
4.36
13
31-Mar-13
42.88
4.51
14
30-Apr-13
50.95
8.07
15
31-May-13
59.05
8.09
16
30-Jun-13
69.08
10.03
17
31-Jul-13
76.28
7.20
18
31-Aug-13
82.80
6.52
19
30-Sep-13
87.93
5.13
20
31-Oct-13
93.38
5.45
21
30-Nov-13
93.91
0.53
22
31-Dec-13
94.40
0.48
23
31-Jan-14
95.65
1.26
24
28-Feb-14
97.08
1.43
25
31-Mar-14
97.98
0.90
26
30-Apr-14
98.56
0.58
27
31-May-14
98.89
0.32
28
30-Jun-14
99.38
0.49
29
31-Jul-14
99.95
0.57
30
25-Aug-14
100.00
0.05
Month No.
Date
Cumulative Planned
26-Feb-12
0.00
0.00
1-Mar-12
0.00
0.00
8-Mar-12
0.00
0.00
15-Mar-12
0.00
0.00
22-Mar-12
0.00
0.00
29-Mar-12
0.00
0.00
5-Apr-12
0.01
0.00
12-Apr-12
0.06
0.05
19-Apr-12
0.08
0.02
26-Apr-12
0.08
0.00
10
3-May-12
0.11
0.04
11
10-May-12
0.12
0.01
12
17-May-12
0.19
0.07
13
24-May-12
0.22
0.03
14
31-May-12
0.28
0.06
15
7-Jun-12
0.39
0.12
16
14-Jun-12
0.50
0.11
17
21-Jun-12
0.62
0.12
18
28-Jun-12
0.77
0.14
19
5-Jul-12
0.94
0.17
20
12-Jul-12
1.16
0.22
21
19-Jul-12
1.41
0.26
22
26-Jul-12
2.65
1.24
23
2-Aug-12
4.10
1.45
24
9-Aug-12
4.43
0.33
25
16-Aug-12
5.97
1.55
26
23-Aug-12
7.54
1.56
27
30-Aug-12
8.19
0.66
28
6-Sep-12
9.06
0.87
29
13-Sep-12
9.82
0.76
30
20-Sep-12
12.46
2.65
31
27-Sep-12
13.04
0.57
32
4-Oct-12
14.61
1.57
33
11-Oct-12
16.57
1.96
34
18-Oct-12
17.10
0.53
Month No.
Date
Cumulative Planned
35
25-Oct-12
17.79
0.69
36
1-Nov-12
18.35
0.56
37
8-Nov-12
19.00
0.65
38
15-Nov-12
20.30
1.30
39
22-Nov-12
22.67
2.37
40
29-Nov-12
24.19
1.53
41
6-Dec-12
25.66
1.47
42
13-Dec-12
27.07
1.42
43
20-Dec-12
28.24
1.17
44
27-Dec-12
29.16
0.92
45
3-Jan-13
30.18
1.03
46
10-Jan-13
31.06
0.87
47
17-Jan-13
31.96
0.90
48
24-Jan-13
32.93
0.97
49
31-Jan-13
34.01
1.08
50
7-Feb-13
34.94
0.93
51
14-Feb-13
36.49
1.55
52
21-Feb-13
37.33
0.84
53
28-Feb-13
38.37
1.04
54
7-Mar-13
39.33
0.96
55
14-Mar-13
40.32
0.99
56
21-Mar-13
41.39
1.07
57
28-Mar-13
42.47
1.08
58
4-Apr-13
44.91
2.44
59
11-Apr-13
46.20
1.29
60
18-Apr-13
47.87
1.67
61
25-Apr-13
48.59
0.72
62
2-May-13
51.45
2.86
63
9-May-13
52.92
1.47
64
16-May-13
54.99
2.06
65
23-May-13
56.31
1.33
66
30-May-13
58.86
2.54
67
6-Jun-13
60.98
2.13
68
13-Jun-13
62.97
1.98
69
20-Jun-13
64.00
1.03
Month No.
Date
Cumulative Planned
70
27-Jun-13
67.76
3.76
71
4-Jul-13
69.70
1.94
72
11-Jul-13
71.17
1.47
73
18-Jul-13
73.23
2.07
74
25-Jul-13
75.28
2.04
75
1-Aug-13
76.39
1.11
76
8-Aug-13
77.13
0.74
77
15-Aug-13
78.11
0.98
78
22-Aug-13
79.04
0.94
79
29-Aug-13
82.30
3.26
80
5-Sep-13
84.31
2.01
81
12-Sep-13
85.36
1.04
82
19-Sep-13
86.59
1.24
83
26-Sep-13
87.34
0.75
84
3-Oct-13
88.45
1.11
85
10-Oct-13
89.62
1.17
86
17-Oct-13
91.70
2.08
87
24-Oct-13
92.63
0.93
88
31-Oct-13
93.38
0.75
89
7-Nov-13
93.58
0.20
90
14-Nov-13
93.76
0.18
91
21-Nov-13
93.84
0.08
92
28-Nov-13
93.90
0.07
93
5-Dec-13
93.94
0.03
94
12-Dec-13
94.01
0.08
95
19-Dec-13
94.11
0.10
96
26-Dec-13
94.28
0.17
97
2-Jan-14
94.46
0.18
98
9-Jan-14
94.69
0.23
99
16-Jan-14
94.95
0.26
100
23-Jan-14
95.24
0.29
101
30-Jan-14
95.60
0.36
102
6-Feb-14
95.97
0.37
103
13-Feb-14
96.36
0.39
104
20-Feb-14
96.72
0.35
Month No.
Date
Cumulative Planned
105
27-Feb-14
97.04
0.33
106
6-Mar-14
97.31
0.26
107
13-Mar-14
97.55
0.24
108
20-Mar-14
97.75
0.20
109
27-Mar-14
97.91
0.16
110
3-Apr-14
98.04
0.13
111
10-Apr-14
98.10
0.07
112
17-Apr-14
98.23
0.13
113
24-Apr-14
98.43
0.20
114
1-May-14
98.59
0.16
115
8-May-14
98.72
0.14
116
15-May-14
98.80
0.07
117
22-May-14
98.89
0.09
118
29-May-14
98.89
0.00
119
5-Jun-14
98.90
0.02
120
12-Jun-14
98.97
0.07
121
19-Jun-14
99.14
0.16
122
26-Jun-14
99.29
0.15
123
3-Jul-14
99.44
0.15
124
10-Jul-14
99.60
0.16
125
17-Jul-14
99.77
0.16
126
24-Jul-14
99.90
0.13
127
31-Jul-14
99.95
0.06
128
7-Aug-14
99.96
0.01
129
14-Aug-14
99.98
0.01
130
21-Aug-14
99.99
0.01
131
25-Aug-14
100.00
0.01
Month No.
Date
Cumulative Planned
30-Aug-12
0.00
0.00
6-Sep-12
0.02
0.02
13-Sep-12
0.19
0.17
20-Sep-12
0.49
0.30
27-Sep-12
0.96
0.47
4-Oct-12
1.69
0.73
11-Oct-12
2.58
0.89
18-Oct-12
3.46
0.88
25-Oct-12
4.48
1.02
10
1-Nov-12
5.62
1.14
11
8-Nov-12
6.93
1.31
12
15-Nov-12
8.20
1.27
13
22-Nov-12
9.67
1.47
14
29-Nov-12
11.08
1.41
15
6-Dec-12
12.59
1.51
16
13-Dec-12
14.03
1.44
17
20-Dec-12
15.48
1.45
18
27-Dec-12
17.19
1.71
19
3-Jan-13
18.95
1.76
20
10-Jan-13
20.67
1.72
21
17-Jan-13
22.45
1.78
22
24-Jan-13
24.27
1.82
23
31-Jan-13
26.15
1.88
24
7-Feb-13
27.98
1.83
25
14-Feb-13
29.65
1.67
26
21-Feb-13
31.26
1.61
27
28-Feb-13
33.04
1.78
28
7-Mar-13
34.92
1.88
29
14-Mar-13
36.88
1.96
30
21-Mar-13
39.01
2.13
31
28-Mar-13
41.16
2.15
32
4-Apr-13
43.06
1.90
33
11-Apr-13
44.98
1.92
34
18-Apr-13
46.83
1.85
35
25-Apr-13
48.03
1.20
36
2-May-13
50.55
2.52
37
9-May-13
52.77
2.22
Month No.
Date
Cumulative Planned
38
16-May-13
54.87
2.10
39
23-May-13
56.77
1.90
40
30-May-13
58.79
2.02
41
6-Jun-13
60.72
1.93
42
13-Jun-13
62.87
2.15
43
20-Jun-13
64.83
1.96
44
27-Jun-13
66.65
1.82
45
4-Jul-13
68.40
1.75
46
11-Jul-13
69.90
1.50
47
18-Jul-13
70.82
0.92
48
25-Jul-13
72.33
1.51
49
1-Aug-13
74.02
1.69
50
8-Aug-13
75.56
1.54
51
15-Aug-13
77.31
1.75
52
22-Aug-13
79.26
1.95
53
29-Aug-13
81.41
2.15
54
5-Sep-13
83.39
1.98
55
12-Sep-13
85.35
1.96
56
19-Sep-13
86.85
1.50
57
26-Sep-13
88.41
1.56
58
3-Oct-13
90.72
2.31
59
10-Oct-13
93.16
2.44
60
17-Oct-13
94.65
1.49
61
24-Oct-13
96.59
1.94
62
31-Oct-13
98.15
1.56
63
7-Nov-13
98.57
0.42
64
14-Nov-13
98.94
0.37
65
21-Nov-13
99.10
0.16
66
28-Nov-13
99.20
0.10
67
5-Dec-13
99.20
0.00
68
12-Dec-13
99.20
0.00
69
19-Dec-13
99.20
0.00
70
26-Dec-13
99.20
0.00
71
2-Jan-14
99.20
0.00
72
9-Jan-14
99.20
0.00
73
16-Jan-14
99.20
0.00
74
23-Jan-14
99.20
0.00
Month No.
Date
Cumulative Planned
75
30-Jan-14
99.20
0.00
76
6-Feb-14
99.20
0.00
77
13-Feb-14
99.20
0.00
78
20-Feb-14
99.20
0.00
79
27-Feb-14
99.20
0.00
80
6-Mar-14
99.20
0.00
81
13-Mar-14
99.20
0.00
82
20-Mar-14
99.20
0.00
83
27-Mar-14
99.20
0.00
84
3-Apr-14
99.20
0.00
85
10-Apr-14
99.20
0.00
86
17-Apr-14
99.20
0.00
87
24-Apr-14
99.20
0.00
88
1-May-14
99.20
0.00
89
8-May-14
99.20
0.00
90
15-May-14
99.20
0.00
91
22-May-14
99.20
0.00
92
29-May-14
99.20
0.00
93
5-Jun-14
99.24
0.04
94
12-Jun-14
99.32
0.08
95
19-Jun-14
99.40
0.08
96
26-Jun-14
99.48
0.08
97
3-Jul-14
99.57
0.09
98
10-Jul-14
99.68
0.11
99
17-Jul-14
99.79
0.11
100
24-Jul-14
99.85
0.06
101
31-Jul-14
99.90
0.05
102
7-Aug-14
99.92
0.02
103
14-Aug-14
99.95
0.03
104
21-Aug-14
99.98
0.03
105
25-Aug-14
100.00
0.02
31-Mar-12
30-Apr-12
31-May-12
30-Jun-12
31-Jul-12
31-Aug-12
30-Sep-12
31-Oct-12
30-Nov-12
31-Dec-12
0
1
2
3
4
5
6
7
8
9
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Series1
Series2
25-Aug-14
31-Jul-14
30-Jun-14
31-May-14
30-Apr-14
31-Mar-14
28-Feb-14
31-Jan-14
31-Dec-13
30-Nov-13
31-Oct-13
30-Sep-13
31-Aug-13
31-Jul-13
30-Jun-13
31-May-13
30-Apr-13
31-Mar-13
28-Feb-13
31-Jan-13
29-Feb-12
100.00
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
26-Feb-12
15-Mar-12
5-Apr-12
26-Apr-12
17-May-12
7-Jun-12
28-Jun-12
19-Jul-12
9-Aug-12
30-Aug-12
20-Sep-12
11-Oct-12
1-Nov-12
22-Nov-12
13-Dec-12
3-Jan-13
24-Jan-13
14-Feb-13
7-Mar-13
28-Mar-13
18-Apr-13
9-May-13
30-May-13
20-Jun-13
11-Jul-13
1-Aug-13
22-Aug-13
12-Sep-13
3-Oct-13
24-Oct-13
14-Nov-13
5-Dec-13
26-Dec-13
16-Jan-14
6-Feb-14
27-Feb-14
20-Mar-14
10-Apr-14
1-May-14
22-May-14
12-Jun-14
3-Jul-14
24-Jul-14
14-Aug-14
100.00
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0 2 4 6 8 101214161820222426283032343638404244464850525456586062646668707274767880828486889092949698100
102
104
106
108
110
112
114
116
118
120
122
124
126
128
130
Series1
Series2
Series1
Series2
14-Aug-14
24-Jul-14
3-Jul-14
12-Jun-14
22-May-14
1-May-14
10-Apr-14
20-Mar-14
27-Feb-14
6-Feb-14
16-Jan-14
26-Dec-13
5-Dec-13
14-Nov-13
24-Oct-13
3-Oct-13
12-Sep-13
22-Aug-13
1-Aug-13
11-Jul-13
20-Jun-13
30-May-13
9-May-13
18-Apr-13
28-Mar-13
7-Mar-13
14-Feb-13
24-Jan-13
3-Jan-13
13-Dec-12
22-Nov-12
1-Nov-12
11-Oct-12
20-Sep-12
30-Aug-12
100.00
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75 77 79 81 83 85 87 89 91 93 95 97 99101103105
100.00%
90.00%
7.00%
80.00%
6.00%
70.00%
5.00%
60.00%
4.00%
50.00%
40.00%
3.00%
30.00%
2.00%
20.00%
1.00%
19-Apr12
21-Jun12
Plan Wk %
Plan Cumm. %
21-Oct12
34
33
32
31
30
29
28
27
26
25
24
23
22
21
20
19
18
28-Jun- 5-Jul-12 12-Jul-12 19-Jul-12 26-Jul-12 2-Aug-12 9-Aug-12 16-Aug- 23-Aug- 30-Aug- 6-Sep-12 13-Sep- 20-Sep- 27-Sep- 5-Oct-12 13-Oct12
12
12
12
12
12
12
12
Actual Wk %
Week start
Week End
Week No.
17
16
15
14
13
12
11
10
0.00%
10.00%
0.00%
Actual Cumm %
23-Mar-12
29-Mar-12
30-Mar-12
5-Apr-12
6-Apr-12
12-Apr-12
13-Apr-12
19-Apr-12
20-Apr-12
26-Apr-12
27-Apr-12
3-May-12
4-May-12
10-May-12
11-May-12
17-May-12
18-May-12
24-May-12
25-May-12
31-May-12
1-Jun-12
7-Jun-12
8-Jun-12
14-Jun-12
15-Jun-12
21-Jun-12
22-Jun-12
28-Jun-12
29-Jun-12
5-Jul-12
6-Jul-12
12-Jul-12
13-Jul-12
19-Jul-12
20-Jul-12
26-Jul-12
27-Jul-12
2-Aug-12
3-Aug-12
9-Aug-12
10-Aug-12
16-Aug-12
17-Aug-12
23-Aug-12
24-Aug-12
30-Aug-12
31-Aug-12
6-Sep-12
7-Sep-12
13-Sep-12
14-Sep-12
20-Sep-12
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
0.07%
1.04%
0.35%
0.73%
0.23%
1.31%
0.63%
1.11%
2.30%
2.15%
2.45%
2.86%
3.46%
4.37%
5.13%
7.31%
7.25%
5.11%
5.87%
6.13%
5.93%
6.76%
4.06%
4.04%
3.30%
0.07%
0.14%
1.18%
1.53%
1.53%
2.26%
2.49%
3.80%
4.43%
5.54%
7.84%
9.99%
12.44%
15.30%
18.76%
23.13%
28.26%
35.57%
42.82%
47.93%
53.80%
59.93%
65.86%
72.62%
76.68%
80.72%
84.02%
Week start
Week End
Week No.
28-Sep-12
5-Oct-12
6-Oct-12
13-Oct-12
14-Oct-12
21-Oct-12
22-Oct-12
29-Oct-12
30-Oct-12
6-Nov-12
7-Nov-12
14-Nov-12
15-Nov-12
22-Nov-12
23-Nov-12
30-Nov-12
1-Dec-12
8-Dec-12
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
Plan Wk %
3.44%
2.01%
2.17%
3.11%
0.25%
87.46%
89.47%
91.64%
94.75%
95.00%
95.00%
95.00%
Plan Wk %
21-Sep-12
27-Sep-12
Actual Wk %
Plan Cumm. %
Actual Cumm %
Actual Wk %
Plan Cumm. %
Actual Cumm %
100.00%
90.00%
8.00%
80.00%
7.00%
70.00%
6.00%
60.00%
5.00%
50.00%
4.00%
40.00%
3.00%
30.00%
2.00%
20.00%
1.00%
Actual Bi-Wk %
Bi-Week start
Bi-Week End
Bi-Week No.
20-Jul-12
26-Jul-12
1
Plan Bi-Wk %
Plan Wk %
Plan Cumm. %
3-Aug-12
9-Aug-12
2
17-Aug-12
23-Aug-12
3
31-Aug-12
6-Sep-12
4
14-Sep-12
20-Sep-12
5
28-Sep-12
4-Oct-12
6
12-Oct-12
18-Oct-12
7
26-Oct-12
1-Nov-12
8
9-Nov-12
15-Nov-12
9
23-Nov-12
29-Nov-12
10
7-Dec-12
13-Dec-12
11
21-Dec-12
27-Dec-12
12
4-Jan-13
10-Jan-13
13
18-Jan-13
24-Jan-13
14
1-Feb-13
7-Feb-13
15
15-Feb-13
21-Feb-13
16
1-Mar-13
7-Mar-13
17
2.89%
6.27%
2.20%
6.93%
3.09%
3.57%
0.12%
1.60%
6.04%
3.42%
1.18%
0.33%
0.11%
0.33%
1.80%
0.37%
5.08%
11.35%
13.55%
20.48%
23.57%
27.14%
27.26%
28.86%
34.90%
38.32%
39.50%
39.83%
39.94%
40.27%
42.07%
42.44%
15-Mar-13
21-Mar-13
18
32
33
31
2-May-13
30
18-Apr-13
29
4-Apr-13
28
21-Mar-13
27
7-Mar-13
26
21
21-Feb-13
25
20
7-Feb-13
24
19
24-Jan-13
23
18
22
17
1-Nov-12
16
18-Oct-12
15
4-Oct-12
14
20-Sep-12
13
6-Sep-12
12
23-Aug-12
11
9-Aug-12
10
26-Jul-12
0.00%
10.00%
27-Jun-13
11-Jul-13
25-Jul-13
8-Aug-13
22-Aug-13
5-Sep-13
19-Sep-13
3-Oct-13
17-Oct-13
0.00%
Actual Cumm %
29-Mar-13
4-Apr-13
19
12-Apr-13
18-Apr-13
20
26-Apr-13
2-May-13
21
10-May-13
16-May-13
22
24-May-13
30-May-13
23
7-Jun-13
13-Jun-13
24
21-Jun-13
27-Jun-13
25
5-Jul-13
11-Jul-13
26
19-Jul-13
25-Jul-13
27
2-Aug-13
8-Aug-13
28
16-Aug-13
22-Aug-13
29
30-Aug-13
5-Sep-13
30
13-Sep-13
19-Sep-13
31
3.70%
2.65%
4.24%
3.42%
4.51%
5.34%
7.44%
4.63%
7.35%
0.75%
0.35%
8.22%
1.55%
46.14%
48.79%
53.03%
56.45%
60.96%
66.30%
73.74%
78.37%
85.72%
86.47%
86.82%
95.04%
96.59%
27-Sep-13
3-Oct-13
32
11-Oct-13
17-Oct-13
33
3.41%
Actual Bi-Wk %
Plan Cumm. %
2.19%
Actual Cumm %
42.44%
96.6%
100%
100.00%
90.00%
5.00%
80.00%
70.00%
4.00%
60.00%
3.00%
50.00%
40.00%
2.00%
30.00%
20.00%
1.00%
0.00%
33
32
31
30
29
28
27
26
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
0.00%
10.00%
27-Sep-12 11-Oct-12 25-Oct-12 8-Nov-12 22-Nov-12 6-Dec-12 20-Dec-12 3-Jan-13 17-Jan-13 31-Jan-13 14-Feb-13 28-Feb-13 14-Mar-13 28-Mar-13 11-Apr-13 25-Apr-13 9-May-13 23-May-13 6-Jun-13 20-Jun-13 4-Jul-13 18-Jul-13 1-Aug-13 15-Aug-13 29-Aug-13 12-Sep-13 26-Sep-13 10-Oct-13 24-Oct-13 7-Nov-13 21-Nov-13 5-Dec-13 2-Jan-14 13-Feb-14 20-Mar-14 24-Apr-14 29-May-14 3-Jul-14
Actual Bi-Wk %
Bi-Week start
Bi-Week End
Bi-Week No.
Plan Wk %
Plan Cumm. %
Actual Cumm %
22-Sep-12
27-Sep-12
6-Oct-12
11-Oct-12
20-Oct-12
25-Oct-12
3-Nov-12
8-Nov-12
17-Nov-12
22-Nov-12
1-Dec-12
6-Dec-12
15-Dec-12
20-Dec-12
29-Dec-12
3-Jan-13
12-Jan-13
17-Jan-13
26-Jan-13
31-Jan-13
9-Feb-13
14-Feb-13
23-Feb-13
28-Feb-13
9-Mar-13
14-Mar-13
23-Mar-13
28-Mar-13
6-Apr-13
11-Apr-13
20-Apr-13
25-Apr-13
4-May-13
9-May-13
18-May-13
23-May-13
1-Jun-13
6-Jun-13
15-Jun-13
20-Jun-13
29-Jun-13
4-Jul-13
13-Jul-13
18-Jul-13
27-Jul-13
1-Aug-13
10-Aug-13
15-Aug-13
24-Aug-13
29-Aug-13
7-Sep-13
12-Sep-13
21-Sep-13
26-Sep-13
5-Oct-13
10-Oct-13
19-Oct-13
24-Oct-13
2-Nov-13
7-Nov-13
16-Nov-13
21-Nov-13
30-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
1.62%
1.90%
2.45%
2.74%
2.92%
2.89%
3.47%
3.50%
3.70%
3.50%
3.39%
3.84%
4.28%
3.82%
3.05%
4.74%
4.00%
3.95%
4.11%
3.57%
1.50%
4.12%
3.29%
4.10%
3.94%
3.06%
5.19%
1.05%
3.92%
0.53%
0.10%
0.96%
2.58%
4.48%
6.93%
9.67%
12.59%
15.48%
18.95%
22.45%
26.15%
29.65%
33.04%
36.88%
41.16%
44.98%
48.03%
52.77%
56.77%
60.72%
64.83%
68.40%
69.90%
74.02%
77.31%
81.41%
85.35%
88.41%
93.60%
94.65%
98.57%
99.1%
99.2%
8-Feb-14
13-Feb-14
15-Mar-14
20-Mar-14
19-Apr-14
24-Apr-14
24-May-14
29-May-14
28-Jun-14
3-Jul-14
2-Aug-14
7-Aug-14
19-Aug-14
25-Aug-14
0.37%
0.24%
0.19%
99.6%
99.8%
100.0%
Plan Bi-Wk %
Actual Bi-Wk %
Plan Cumm. %
Actual Cumm %
Week start
Week End
Week No.
Plan Wk %
Actual Wk %
Plan Cumm. %
99.2%
99.2%
99.2%
99.2%
Actual Cumm %
99.2%
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
CONSTRUCTION VERIFICATION SHEET
______________________________________
Document Description
GC 11106200
ITEM
4.0
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
PREVIOUS
MONTH
4.A
Pipeline
4.A1
4.A1.1
Transportation of Pipes
23040.0
0.0221
36000
MT
4.A1.2
Pipe Stringing
10080.0
0.0097
36000
MT
4.A1.3
Welding
93600.0
0.0897
3000
J.No
4.A1.4
NDT
24480.0
0.0235
3000
J.No
4.A1.5
21600.0
0.0207
3000
J.No
4.A1.6
Lowering of pipe
30240.0
0.0290
36000
MT
4.A1.7
576.0
0.0006
No.
4.A1.8
3360.0
0.0032
36000
MT
4.A1.9
12960.0
0.0124
36000
MT
4.A1.10
Pipeline Pressurizing
4080.0
0.0039
36000
MT
4.A1.11
3240.0
0.0031
36000
MT
0.2177
4.A2
4.A2.1
ROW
4.A2.1a
5760.0
0.0055
36000
MT
4.A2.1b
Right Of Way
7200.0
0.0069
36000
MT
4.A2.1c
ROW Re-Instatement
7200.0
0.0069
36000
MT
0.0193
4.A2.2
Trenching
4.A2.2a
Trench Excavation
38880.0
0.0372
36000
MT
4.A2.2b
42000.0
0.0402
84
No.
4.A2.2c
66240.0
0.0635
No.
0.1410
4.A2.3
4.A2.3a
Pre-Padding
20160.0
0.0193
36000
MT
4.A2.3b
Post Padding
15840.0
0.0152
36000
MT
4.A2.3c
Final Backfilling
5760.0
0.0055
36000
MT
WEIGHTAGE ACTUAL
UNIT
Construction and
Installation
ETROJET
PREVIOUS
MONTH
Document Description
GC 11106200
ITEM
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
PREVIOUS
MONTH
1300.0
0.0012
Each
4.A2.3e
1600.0
0.0015
Each
4.A2.3f
5920.0
0.0057
Each
4.A2.3g
108.0
0.0001
Each
4.A2.3h
1920.0
0.0018
36000
MT
4.A2.3i
Punch List
8640.0
0.0083
Lot
Lot
4.A3
Tie-ins
4.A3.1
Tie-Ins Of Strings
0.0587
21600.0
4.A4
0.0207
0.0207
7200.0
0.0069
18
Connections
4.A4.1b
7200.0
0.0069
18
No.
800.0
0.0008
25
No.
4.A4.2b
2240.0
0.0021
No.
4.A4.2c
800.0
0.0008
No.
4.A4.2d
Rectifier To Be Installed
560.0
0.0005
No.
4.A4.2e
Cables To Be Connected
1120.0
0.0011
1500
MT
4.A4.2f
1120.0
0.0011
Lot
4.B
4.B1
WEIGHTAGE ACTUAL
UNIT
4.A2.3d
ETROJET
0.0202
4.B1.1 General
4.B1.1a
17700.0
0.0170
530
M/L
4.B1.1b
5545.0
0.0053
170
M/L
Piping Fabrication
49224.0
0.0472
10800
D.I
4.B1.2b
11040.0
0.0106
4000
M2
4.B1.2c
47327.0
0.0453
7200
D.I
PREVIOUS
MONTH
Document Description
GC 11106200
ITEM
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
PREVIOUS
MONTH
4320.0
0.0041
Lot
4.B1.2e
Loops to be Pressurized
6120.0
0.0059
Lot
4.B1.2f
3240.0
0.0031
Lot
Piping Fabrication
8739.0
0.0084
900
D.I
4.B1.3b
3545.0
0.0034
625
M2
4.B1.3c
11400.0
0.0109
600
D.I
4.B1.4 BSV-3
4.B1.4a
7800.0
0.0075
No.
4.B1.4b
2600.0
0.0025
Lot
4.B2
0.1711
Laying of Cables
2100.0
0.0020
2100
4.B2.1b
2100.0
0.0020
200
4.B2.1c
2100.0
0.0020
150
Laying Of Cables
1680.0
0.0016
5555
M/L
4.B2.2b
1680.0
0.0016
No.
4.B2.2c
1680.0
0.0016
12
No.
4.B2.2d
1680.0
0.0016
10
No.
4.B2.2e
1680.0
0.0016
No.
4.B2.2f
1680.0
0.0016
No.
4.B2.2g
1680.0
0.0016
No.
4.B2.2h
1680.0
0.0016
Lot
Laying Of Cables
1260.0
0.0012
13775
4.B2.3b
1260.0
0.0012
No.
4.B2.3c
1260.0
0.0012
No.
4.B2.3d
1260.0
0.0012
No.
4.B2.3e
1260.0
0.0012
No.
WEIGHTAGE ACTUAL
UNIT
4.B1.2d
ETROJET
PREVIOUS
MONTH
Document Description
GC 11106200
ITEM
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
PREVIOUS
MONTH
1260.0
0.0012
No.
4.B2.3g
1260.0
0.0012
No.
4.B2.3h
1260.0
0.0012
Lot
4.B2.4 BSV-3
4.B2.4a
Laying Of Cables
5100.0
0.0049
Lot
4.B2.4b
2550.0
0.0024
Lot
4.B2.4c
Termination
7950.0
0.0076
Lot
4.B3
0.0435
Electrical
6300.0
0.0060
No.
4.B3.1b
6300.0
0.0060
No.
4.B3.1c
6300.0
0.0060
No.
1680.0
0.0016
Lot
4.B3.2b
1680.0
0.0016
Lot
4.B3.2c
1680.0
0.0016
524
M/L
4.B3.2d
1680.0
0.0016
205
M/L
4.B3.2e
1680.0
0.0016
Lot
4.B3.2f
2520.0
0.0024
Lot
1260.0
0.0012
Lot
4.B3.3b
1260.0
0.0012
Lot
4.B3.3c
1260.0
0.0012
120
M/L
4.B3.3d
1260.0
0.0012
260
M/L
4.B3.3e
1260.0
0.0012
Lot
4.B3.3f
2100.0
0.0020
Lot
4.B3.4 BSV-3
4.B3.4a
5100.0
0.0049
Lot
4.B3.4b
2550.0
0.0024
125
4.B3.4c
7950.0
0.0076
No.
WEIGHTAGE ACTUAL
UNIT
4.B2.3f
ETROJET
PREVIOUS
MONTH
Document Description
GC 11106200
ITEM
DESCRIPTION
MANHOURS
4.B5
RELATIVE
WEIGHT
QUANTITY
PREVIOUS
MONTH
0.0516
4.B5.1a
4550.0
0.0044
515
Cu.M
4.B5.1b
11200.0
0.0107
298
Cu.M
4.B5.1c
41440.0
0.0397
210
Cu.M
4.B5.1d
2800.0
0.0027
No.
15750.0
0.0151
220
No.
4.B5.2b
8250.0
0.0079
220
No.
3900.0
0.0037
No.
6780.0
0.0065
No.
21600.0
0.0207
No.
1200.0
0.0011
No.
650.0
0.0006
141
Cu.M
1130.0
0.0011
114
Cu.M
3600.0
0.0034
62
Cu.M
200.0
0.0002
Lot
19680.0
0.0189
165
Ton
1300.0
0.0012
95
Cu.M
2260.0
0.0022
95
Cu.M
7200.0
0.0069
73
Cu.M
400.0
0.0004
Lot
9840.0
0.0094
165
Ton
4920.0
0.0047
2850
Sq.M
4950.0
0.0047
188
Cu.M
WEIGHTAGE ACTUAL
UNIT
4.B5.3.3g
ETROJET
PREVIOUS
MONTH
Document Description
GC 11106200
ITEM
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
PREVIOUS
MONTH
780.0
0.0007
27
Cu.M
4.B5.4b
2000.0
0.0019
27
Cu.M
4.B5.4c
6660.0
0.0064
25
Cu.M
4.B5.4d
270.0
0.0003
Lot
4.B5.4e
4000.0
0.0038
Lot
4.B5.4f
1152.0
0.0011
50
Cu.M
4.B5.5 Roads
4.B5.5a
4320.0
0.0041
677
Sq.M
4.B5.5b
1728.0
0.0017
19
Sq.M
4.B5.5b
1728.0
0.0017
67
Sq.M
4.B5.6 BSV-3
4.B5.6a
Excavation In BSV-3
1200.0
0.0011
21
Cu.M
4.B5.6b
1200.0
0.0011
21
Cu.M
4.B5.6c
6000.0
0.0057
37
Cu.M
4.B5.6d
Fence In BSV-3
6000.0
0.0057
60
M/L
4.B9
4.B9
4.B11
Extension of SER-12
0.2018
9900.0
0.0095
Lot
1120.0
0.0011
28
Cu.M
1200.0
0.0011
Sq.M
2800.0
0.0027
40
Sq.M
720.0
0.0007
Lot
280.0
0.0003
Lot
2160.0
0.0021
Cu.M
4480.0
0.0043
40
Cu.M
12000.0
0.0115
Lot
12000.0
0.0115
Lot
1020.0
0.0010
Lot
WEIGHTAGE ACTUAL
UNIT
4.B5.4a
ETROJET
PREVIOUS
MONTH
Document Description
GC 11106200
ITEM
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
PREVIOUS
MONTH
1020.0
0.0010
Lot
1020.0
0.0010
Set
4.B11.2d Termination
1020.0
0.0010
Lot
1020.0
0.0010
250
M/L
1020.0
0.0010
Lot
1020.0
0.0010
Lot
1020.0
0.0010
Lot
1020.0
0.0010
Lot
1020.0
0.0010
Lot
0.0450
1043762.0
1.0000
WEIGHTAGE ACTUAL
UNIT
ETROJET
PREVIOUS
MONTH
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
MARCHING CHART
______________________________________
Final Backfilling
A
Page 216 of 266
30.7
31.8
32.9
34.1
35.2
36.0
28.9
30.1
31.2
32.3
33.4
34.6
A
36.0
36.0
34.0
32.9
31.8
30.7
36.0
34.6
33.5
32.4
31.3
30.2
29.1
28.1
27.0
25.9
24.8
23.7
22.6
21.5
20.4
19.3
18.2
17.1
16.1
15.0
13.9
12.8
11.7
10.6
9.5
8.4
7.3
36.0
34.4
33.4
32.3
31.2
30.1
29.0
27.9
26.8
25.7
24.6
23.5
22.4
21.4
20.3
19.2
18.1
17.0
15.9
14.8
13.7
12.6
11.5
10.4
9.4
8.3
7.2
4-Apr-13
11-Apr-13
18-Apr-13
25-Apr-13
32.3 28/Mar/13
33.4 4/Apr/13
34.4 11/Apr/13
36.0 18/Apr/13
27/Jun/13
20/Jun/13
13/Jun/13
6/Jun/13
30/May/13
23/May/13
16/May/13
9/May/13
2/May/13
31-Oct-13
3/Oct/13
10/Oct/13
17/Oct/13
24/Oct/13
31/Oct/13
7/Nov/13
23.4
26.6
18.9
36.0
28/Nov/13
28-Nov-13
21-Nov-13
21/Nov/13
19-Jul-12
14-Nov-13
Marching Chart
7-Nov-13
GC 11106200
14/Nov/13
24-Oct-13
26/Sep/13
20.1
19-Sep-13
Issued For
36.0
17-Oct-13
19/Sep/13
16.8
12-Sep-13
Date
6.9
10-Oct-13
12/Sep/13
13.6
5-Sep-13
Document Description
29.9
3-Oct-13
5/Sep/13
10.3
29-Aug-13
Contract Number
0.0
26-Sep-13
29/Aug/13
7.0
22-Aug-13
15-Aug-13
22/Aug/13
8-Aug-13
1-Aug-13
3.7
A
15/Aug/13
0.5
1/Aug/13
25-Jul-13
18-Jul-13
11-Jul-13
4-Jul-13
27-Jun-13
20-Jun-13
13-Jun-13
6-Jun-13
30-May-13
23-May-13
16-May-13
9-May-13
2-May-13
28-Mar-13
31.2 21/Mar/13
25/Apr/13
21-Mar-13
14-Mar-13
7-Mar-13
28-Feb-13
21-Feb-13
14-Feb-13
7-Feb-13
31-Jan-13
24-Jan-13
17-Jan-13
10-Jan-13
3-Jan-13
27-Dec-12
20-Dec-12
13-Dec-12
6-Dec-12
29-Nov-12
22-Nov-12
15-Nov-12
8-Nov-12
1-Nov-12
25-Oct-12
30.1 14/Mar/13
29.0 7/Mar/13
27.9 28/Feb/13
26.8 21/Feb/13
25.7 14/Feb/13
24.6 7/Feb/13
23.5 31/Jan/13
22.4 24/Jan/13
21.4 17/Jan/13
20.3 10/Jan/13
19.2 3/Jan/13
18.1 27/Dec/12
17.0 20/Dec/12
15.9 13/Dec/12
14.8 6/Dec/12
13.7 29/Nov/12
12.6 22/Nov/12
11.5 15/Nov/12
10.4 8/Nov/12
9.4 1/Nov/12
8.3 25/Oct/12
7.2 18/Oct/12
6.1 11/Oct/12
25/Jul/13
36.0
A
18/Jul/13
36.0
34.1
20.6
36.0
34.3
33.2
A
11/Jul/13
36.0
34.3
33.2
32.1
34.0
32.9
31.8
30.7
29.6
11.6
36.0
34.6
33.5
32.4
31.3
33.0
31.9
30.9
29.8
28.7
29.6
28.5
27.4
26.3
25.2
24.2
23.1
22.0
20.9
19.8
18.7
17.6
16.5
15.4
14.3
13.2
12.2
11.1
10.0
8.9
7.8
6.7
A
4/Jul/13
36.0
36.0
34.9
33.8
32.6
31.5
32.1
31.0
29.9
28.8
27.7
28.5
27.4
26.3
25.2
24.2
23.1
22.0
20.9
19.8
18.7
17.6
16.5
15.4
14.3
13.2
12.2
11.1
10.0
8.9
7.8
6.7
5.6
6.2
6.1
2.6
36.0
34.0
32.9
31.8
30.7
29.6
31.0
29.9
28.8
27.7
26.6
27.6
26.5
25.4
24.3
23.2
22.1
21.0
19.9
18.9
17.8
16.7
15.6
14.5
13.4
12.3
11.2
10.1
9.0
7.9
6.9
5.8
4.7
5.6
5.1
5.0
18-Oct-12
5.0 4/Oct/12
30.2
29.1
28.1
27.0
25.9
26.6
25.6
24.5
23.4
22.3
21.2
20.1
19.0
17.9
16.8
15.7
14.6
13.6
12.5
11.4
10.3
9.2
8.1
7.0
5.9
4.8
3.7
4.5
4.5
4.1
3.9
11-Oct-12
3.9 27/Sep/12
30.4
29.3
28.1
27.0
25.9
25.6
24.5
23.4
22.3
21.2
20.1
19.0
17.9
16.8
15.7
14.6
13.6
12.5
11.4
10.3
9.2
8.1
7.0
5.9
4.8
3.7
2.6
3.6
3.4
3.4
3.0
2.8
4-Oct-12
2.8 20/Sep/12
12
28.5
27.4
26.3
25.2
24.2
24.8
23.7
22.6
21.5
20.4
19.3
18.2
17.1
16.1
15.0
13.9
12.8
11.7
10.6
9.5
8.4
7.3
6.2
5.1
4.1
3.0
1.9
2.6
2.5
2.3
2.3
1.9
1.7
27-Sep-12
1.7 13/Sep/12
16
8/Aug/13
P
24.8
23.6
22.5
21.4
20.3
19.1
18.0
16.9
15.8
14.6
13.5
12.4
11.3
10.1
9.0
7.9
6.8
5.6
4.5
3.4
2.3
1.1
1.6
1.6
1.4
1.2
1.2
0.8
20-Sep-12
0.6 6/Sep/12
20
0.0
P
23.1
22.0
20.9
19.8
18.7
17.6
16.5
15.4
14.3
13.2
12.2
11.1
10.0
8.9
7.8
6.7
5.6
4.5
3.4
2.3
1.2
0.2
0.8
0.5
0.5
0.3
0.2
0.2
0.6
13-Sep-12
6-Sep-12
24
36.0
29.6
27.8
19.4
17.7
28.4
18.3
16.6
26.7
17.2
15.4
27.3
16.1
14.3
25.6
14.9
13.2
26.2
13.8
12.1
24.4
12.7
10.9
25.1
11.6
9.8
23.3
10.4
8.7
23.9
9.3
7.6
22.2
8.2
6.4
22.8
7.1
5.3
21.1
5.9
4.2
21.7
4.8
3.1
19.9
3.7
1.9
20.6
2.6
0.8
18.8
1.4
0.5
A
0.3
0.0
Post Padding
P
0.0
Tie-Ins of Strings
P
0.0
Lowering
P
0.0
Pre-Padding
P
0.0
0.0
NDT
P
0.0
Welding of Pipes
P
0.0
Pipe Stringing
P
0.0
Pipe Transportation
P
0.0
Trench Excavation
P
0.0
Right Of Way
P
0.0
DESCRIPTION/
DATE
0.0
0
30-Aug-12
EPIC For New 16" - 36 Km Jet A1 Fuel Pipeline From QP Refinery To BSV-3
ETROJET
36
32
28
Right Of Way
Trench Excavation
Pipe Transportation
Pipe Stringing
Welding of Pipes
NDT
Pre-Padding
Lowering
Tie-Ins of Strings
Post Padding
Final Backfilling
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
CASH FLOW CURVE AND TABLE
______________________________________
25-Aug-14
31-Jul-14
30-Jun-14
31-May-14
30-Apr-14
31-Mar-14
28-Feb-14
31-Jan-14
31-Dec-13
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
30-Nov-13
31-Dec-12
31-Oct-13
30-Nov-12
30-Sep-13
31-Oct-12
31-Aug-13
30-Sep-12
31-Jul-13
31-Aug-12
30-Jun-13
31-Jul-12
31-May-13
30-Jun-12
30-Apr-13
31-May-12
31-Mar-13
30-Apr-12
28-Feb-13
31-Mar-12
31-Jan-13
29-Feb-12
120000000
115000000
110000000
105000000
100000000
95000000
90000000
85000000
80000000
75000000
70000000
65000000
60000000
55000000
50000000
45000000
40000000
35000000
30000000
25000000
20000000
15000000
10000000
5000000
0
Month No.
Date
Cumulative Cash
Flow (QR)
Percentage Per
Month
29-Feb-12
0.00%
31-Mar-12
2630
2630
0.00%
30-Apr-12
62375
59745
0.05%
31-May-12
208167
145792
0.12%
30-Jun-12
574901
366734
0.31%
31-Jul-12
3503361
2928460
2.50%
31-Aug-12
8300094
4796733
4.10%
30-Sep-12
15012456
6712362
5.74%
31-Oct-12
19637567
4625111
3.95%
30-Nov-12
27040797
7403230
6.33%
10
31-Dec-12
33658179
6617381
5.66%
11
31-Jan-13
39145613
5487434
4.69%
12
28-Feb-13
44596642
5451029
4.66%
13
31-Mar-13
50307596
5710954
4.88%
14
30-Apr-13
60164963
9857367
8.43%
15
31-May-13
70139876
9974913
8.53%
16
30-Jun-13
82212930
12073055
10.32%
17
31-Jul-13
90891072
8678142
7.42%
18
31-Aug-13
98835036
7943964
6.79%
19
30-Sep-13
105122710
6287674
5.37%
20
31-Oct-13
111811637
6688926
5.72%
21
30-Nov-13
112455893
644256
0.55%
22
31-Dec-13
112752876
296983
0.25%
23
31-Jan-14
113527493
774617
0.66%
24
28-Feb-14
114406438
878946
0.75%
25
31-Mar-14
114960396
553957
0.47%
26
30-Apr-14
115318314
357918
0.31%
27
31-May-14
115516507
198194
0.17%
28
30-Jun-14
116166002
649494
0.56%
29
31-Jul-14
116928613
762612
0.65%
30
25-Aug-14
116988359
59746
0.05%
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
INVOICING SYSTEM
______________________________________
PETROJET
The Petroleum Projects and
Technical Consultations Co.
One of the Egyptian General Petroleum
Corporation Companies
abcdef
INTERIM INVOICE
Part 1
1.1) Invoice Number :
1.3)
1.4)
1.5)
Title :
To : May 31,2012
_________________________________________________________________________________
Part 2
2.1) Original Contract Value
2.2)
Variations,
2.3)
QR
116,988,359,00
0,00
116,988,359,00
_________________________________________________________________________________
Part 3
3.1) Cumulative value of work done
QR
00,00
3.2)
0,00
3.3)
00,00
_________________________________________________________________________________
Part 4
4.1) Gross Value of work done as per this invoice
QR
00,00
4.2)
Less : Advance
0,00
4.3)
00,00
4.4)
00,00
4.5)
00,00
4.6)
Amount in Words :
_________________________________________________________________________________
Part 5
5.1) Authorized Signature
5.2)
5.3)
5.4)
Company Seal
This invoice should be supported by a statement showing progress in work as per schedule of
prices certified by QP representative for the job. Invoice without this certification is liable to be
rejected by Qatar Petroleum.
Page 221 of 266
REPORT NO. :
PERIOD :
CURRENCY : QR
ITEM NO.
LUMP SUM
VALUE
INVOICE AMOUNTS
PERCENTAGE
This Period
Previous
To Date
This Period
Previous
To Date
6912860.00
5.91%
0.000000%
0.000000%
0.000000%
0.00
0.00
0.00
3757524.00
3.21%
0.000000%
0.000000%
0.000000%
0.00
0.00
0.00
PROCUREMENT (SCHEDULE 3)
46385347.66
39.65%
0.000000%
0.000000%
0.000000%
0.00
0.00
0.00
CONSTRUCTION (SCHEDULE 4)
52832810.46
45.16%
0.000000%
0.000000%
0.000000%
0.00
0.00
0.00
PRE-COMMISSIONING &
COMMISSIONING (SCHEDULE 5)
3077540.58
2.63%
0.000000%
0.000000%
0.000000%
0.00
0.00
0.00
SPARES (SCHEDULE 6)
669488.81
0.57%
0.000000%
0.000000%
0.000000%
0.00
0.00
0.00
3202787.00
2.74%
0.000000%
0.000000%
0.000000%
0.00
0.00
0.00
PROVISIONAL (SCHEDULE 8)
150000.00
0.13%
0.000000%
0.000000%
0.000000%
0.00
0.00
0.00
116988359
100.00%
0.000000%
0.000000%
0.000000%
0.00
0.00
0.00
PETROJET COMPANY
QATAR PETROLEUM
REVIEWED BY
APPROVED BY :
APPROVED BY
NAME
HANY BADIE
NAME
JOB TITLE
JOB TITLE :
DATE
DATE
COMPANY REVIEW AND APPROVAL OF THE PRODUCT OF AGREED PROGRESS AND LUMPSUM VALUES IN
THIS SUPPORTING DOCUMENTATION DOES NOT SIGNIFY APPROVAL OF THIS INVOICE .
Item
Description
Unit
Amount Q.R
Up to Last
Month Invoice
For This
Invoice
% of
Invoice
Total Invoice
PRELIMINARIES
CONTRACT Particulars
For convenience, only those provisions considered to have
an obvious financial effect are set out below and against
each provision, the price is inserted for compliance:
Item
150,011.00
Item
341,322.00
Item
162,060.00
QR.
653,393.00
Item
Description
Unit
Amount Q.R
Up to Last
Month Invoice
For This
Invoice
% of
Invoice
Total Invoice
GENERAL MATTERS
Item
1,637,958
Item
691,403
Item
286,250
Item
1,002,484
Item
806,180
Item
398,340
Item
317,115
Item
33,116
Item
20,000
Item
7,200
Item
24,126
Item
30,000
Item
50,000
Item
179,045
Item
776,250
QR.
6,259,467.00
Item
APPENDIX B PART II
Description
Unit
Amount Q.R
Up to Last
Month Invoice
For This
Invoice
% of
Invoice
Total Invoice
Collection
Item
653,393.00
Item
6,259,467.00
QR.
6,912,860
Item
APPENDIX B PART II
Description
Unit
Amount Q.R
Item
103,245
Item
107,938
Item
18,771
Item
84,473
Item
39,890
Carry out Project Risk Assessment as per cl. 3.1.16 of SOW App.A.
Item
9,386
Topographic Survey
Item
9,386
Item
37,544
Geotechnical Investigations
Item
18,771
Up to Last
Month Invoice
For This
Invoice
% of
Invoice
Total Invoice
Process
Item
337,893
Item
478,682
Pipelines
Item
450,524
Item
455,217
Electrical
Item
375,437
Loss Prevention
Item
103,245
Item
305,042
Building Services
Item
225,262
Telecommunication
Item
25,077
Item
46,199
Environmental Control
Item
60,000
Item
23,465
Item
277,824
Item
164,253
QR.
3,757,524
Item
APPENDIX B PART II
Description
Unit
Amount Q.R
Up to Last
Month Invoice
For This
Invoice
% of
Invoice
Total Invoice
Mechanical Items
A1
Item
517,498
A2
EOT Crane
Item
815,000
A3
Jib Cranes
Item
221,785
Pumps
B1
Mainline Pumps
Item
10,150,000
B2
Booster Pumps
Item
5,645,000
Electrical
C1
Switchgear Panels
Item
4,340,841
C2
Item
111,086
C3
UPS System
Item
422,708
C4
Item
100,379
C5
Item
203,462
C6
Cables
Item
511,515
Valves
D1
Item
977,651
D2
Item
205,000
D3
Item
170,000
D4
Item
1,967,500
D5
Item
1,020,000
E1
Instruments
E1.1
Item
1,155,406
E1.2
Item
275,520
Item
34,958
E2
Item
462,162
E3
Item
1,603,703
E4
Item
331,809
E5
Item
6,014,629
E6
Item
1,858,213
Item
118,503
Item
76,000
Item
801,988
Item
1,185,032
5,088,000
E1.3
QR.
46,385,348
Item
4.0
APPENDIX B PART II
Description
Unit
Amount Q.R
Up to Last
Month Invoice
For This
Invoice
% of
Invoice
Total Invoice
4.A
Pipeline
Pipelines including but not limited to installation, welding,
testing, coating etc.
Item
9,088,007.00
4.A.2.1 ROW
Item
1,009,779.00
4.A.2.2 Trenching
Item
5,048,893.00
4.A.1
4.2.3
Item
4,260,490.00
4.A.3
Tie-Ins
Item
1,075,779.00
4.A.4
Item
1,748,742.00
4.A.5
Item
540,580.00
4.B
4.B.1
Item
4,695,500.00
4.B.2
Item
1,572,285.00
4.B.3
Electrical
Item
1,457,285.00
4.B.4
Loss Prevention
Item
100,000.00
4.B.5
Item
11,423,351.00
4.B.6
Building Services
Item
114,430.00
4.B.7
Telecommunication
Item
1,165,828.00
4.B.8
Coating
Item
850,000.00
4.B.9
Item
4,613,488.00
4.B.10
Item
203,825.00
Item
318,500.00
Item
3,546,048.00
QR.
52,832,810.00
Item
APPENDIX B PART II
Description
Unit
Amount Q.R
Up to Last
Month Invoice
For This
Invoice
% of
Invoice
Total Invoice
A1
Pipeline
Item
1,259,981
A2
Pumps
Item
200,000
A3
Item
797,000
A4
Item
155,500
A5
Security System
Item
108,000
A6
Item
170,220
A7
Item
321,840
Item
65,000
QR.
3,077,540.58
Item
APPENDIX B PART II
Description
Unit
Amount Q.R
Item
182,429
Item
457,286
Item
29,774
QR.
669,489
Up to Last
Month Invoice
For This
Invoice
Total Invoice
% of
Invoice
Item
APPENDIX B PART II
Description
Unit
Amount Q.R
Up to Last
Month Invoice
For This
Invoice
% of
Invoice
Total Invoice
Item
648,696
Item
375,177
Item
256,550
Item
905,924
Item
75,910
Item
227,730
Item
712,800
QR.
3,202,787.00
Item
APPENDIX B PART II
Description
Unit
Amount Q.R
Item
100,000.00
Item
50,000.00
QR.
150,000
Up to Last
Month Invoice
For This
Invoice
% of
Invoice
Total Invoice
ITEM NO
2.0
TOTAL
WEIGHTAGE
DESCRIPTION
Engineering
Engineering for the complete Scope of Work including but not
limited to:
0.027
0.029
0.005
0.022
0.011
Carry out Project Risk Assessment as per cl. 3.1.16 of SOW - App.A.
0.002
Topographic Survey
0.002
0.010
Geotechnical Investigations
0.005
Process
0.090
0.127
Pipelines
0.120
0.121
Electrical
0.100
Loss Prevention
0.027
0.081
Building Services
0.060
Telecommunication
0.007
0.012
Environmental Control
0.016
0.006
0.074
0.044
Total
1.000
CUMMULATIVE
WTG PROGRESS
CUMMLATIVE
PROGRESS %
REMARKS
Document Description
GC 11106200
ITEM
DESCRIPTION
WEIGHTAGE
QUANTITY
Engineering
Engineering for the complete Scope of Work including but
not limited to:
0.0275
Lot
0.0287
Lot
0.0050
Lot
HAZOP
per cclause
O Study as pe
ause 4.2.3
3 of
o SOW
SO - App.A.
pp
0.0225
Lot
0.0106
Lot
Carry out Project Risk Assessment as per cl. 3.1.16 of SOW - App.A.
0.0025
Lot
Topographic Survey
0.0025
Lot
0.0100
Lot
Geotechnical Investigations
0.0050
Lot
Process
0.0899
Lot
0.1274
Lot
Pipelines
0.1199
0 1199
Lot
0.1211
Lot
Electrical
0.0999
Lot
Loss Prevention
0.0275
Lot
0.0812
Lot
Building Services
0.0599
Lot
Telecommunication
0.0067
Lot
0.0123
Lot
Environmental Control
0.0160
Lot
0.0062
Lot
0.0739
Lot
0.0437
Lot
Total Weightage
WEIGHTAGE ACTUAL
UNIT
PREVIOUS
THIS MONTH
MONTH
2.0
ETROJET
1.0000
AS ON
DATE
PREVIOUS
MONTH
THIS
MONTH
AS ON
DATE
ITEM NO
TOTAL
WEIGHTAGE
DESCRIPTION
Procurement for the complete Scope of Work including but not
limited to:
Mechanical Items
A1
0.011
A2
EOT Crane
0.018
A3
Jib Cranes
0.005
Pumps
B1
Mainline Pumps
0.219
B2
Booster Pumps
0.122
Electrical
C1
Switchgear Panels
0.094
C2
0.002
C3
UPS System
0.009
C4
0.002
C5
0.004
C6
Cables
0.011
Valves
D1
0.021
D2
0.004
D3
0.004
D4
0.042
D5
0.022
E
E1
E1.1
0.025
E1.2
0.006
E1.3
0.001
E2
Junction Boxes
0.010
E3
0.035
E4
0.007
E5
0.130
E6
0.040
0.003
0.002
0.017
0.026
Total
0.110
1.000
CUMMULATIVE
WTG PROGRESS
CUMMLATIVE
PROGRESS %
REMARKS
Document Description
GC 11106200
ITEM
3.0
DESCRIPTION
QR
WEIGHTAGE
QUANTITY
UNIT
Procurement
Procurement for the complete Scope of Work including but
not limited to:
Mechanical Items
3.A1
517497.7
0.0112
Lot
3.A2
EOT Crane
815000.0
0.0176
Lot
3.A3
Jib Cranes
221784.7
0.0048
Lot
3.B
Pumps
3.B1
Mainline Pumps
10150000.0
0.2188
Lot
3
3.B2
p
Booster Pumps
5645000.0
0.1217
Lot
4340841.0
0.0936
Lot
3.C
Electrical
3.C1
Switchgear Panels
3.C2
111086.3
0.0024
Lot
3.C3
UPS System
422707.8
0.0091
Lot
3.C4
100379.2
0.0022
Lot
3.C5
203461.6
0.0044
Lot
3.C6
Cables
511515.5
0.0110
Lot
3.D
Valves
3.D1
977651.2
0.0211
Lot
3.D2
205000.0
0.0044
Lot
3.D3
170000.0
0.0037
Lot
3.D4
1967500.0
0.0424
Lot
3.D5
3 D5
All other
th misc.
i
ttypes off valves
l
1020000.0
1020000 0
0.0220
0 0220
Lot
L t
3.E
3.E1
Instruments
3.E1.1
1155405.9
0.0249
Lot
3.E1.2
275519.9
0.0059
Lot
3.E1.3
34958.4
0.0008
Lot
3.E2
Junction Boxes
462162.4
0.0100
Lot
3.E3
1603703.5
0.0346
Lot
3.E4
331808.9
0.0072
Lot
3.E5
6014628.6
0.1297
Lot
3.E6
1858212.7
0.0401
Lot
118503.2
0.0026
Lot
76000.0
0.0016
Lot
F
G
H
801987.7
0.0173
Lot
1185031.7
0.0255
Lot
Lot
K.i
5088000.0
0.1097
Total Weightage
46385348
1.0000
PREVIOUS
THIS MONTH
MONTH
ETROJET
WEIGHTAGE ACTUAL
AS ON
DATE
PREVIOUS
MONTH
THIS
MONTH
AS ON
DATE
Price (QR)
RELATIVE
WEIGHT
9088007.360
0.172
4.A.2.1
ROW
1009778.596
0.019
4.A.2.2
Trenching
5048892.978
0.096
4.A2.3
4260490.382
0.081
4.A.3
Tie-Ins
1075778.596
0.020
4.A.4
1748742.205
0.033
4.A.5
540579.600
0.010
ITEM NO
4.0
DESCRIPTION
4.A
4.A.1
4.B
Pipeline
4.B.1
4695500.000
0.089
4.B.2
1572285.171
0.030
4.B.3
Electrical
1457285.171
0.028
4.B.4
Loss Prevention
100000.000
0.002
4.B.5
11423351.000
0.216
4.B.6
Building Services
114430.000
0.002
4.B.7
Telecommunication
1165828.137
0.022
4.B.8
Coating
850000.000
0.016
4.B.9
4613488.000
0.087
4.B.10
203825.459
0.004
4.B.11
Extension of SER-12 including installation of Aircoditioning unit, F&G systems and all other woks in line
with existing SER-12.
318500.000
0.006
3546047.808
0.067
52832810.46
1.000
4.C
Total
CUMMULATIVE
WTG PROGRESS
CUMMLATIVE
PROGRESS %
REMARKS
Document Description
GC 11106200
ITEM
4.0
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
UNIT
4.A
Pipeline
4.A1
to
4.A1.1
Transportation of Pipes
23040.0
0.0221
36000
MT
4.A1.2
Pipe Stringing
10080.0
0.0097
36000
MT
4.A1.3
Welding
93600.0
0.0897
3000
J.No
4.A1.4
NDT
24480.0
0.0235
3000
J.No
4.A1.5
21600.0
0.0207
3000
J.No
4.A1.6
Lowering of pipe
30240.0
0.0290
36000
MT
4.A1.7
576.0
0.0006
No.
4 A1 8
4.A1.8
3360 0
3360.0
0 0032
0.0032
36000
MT
4.A1.9
12960.0
0.0124
36000
MT
4.A1.10
Pipeline Pressurizing
4080.0
0.0039
36000
MT
4.A1.11
3240.0
0.0031
36000
MT
4.A2
4.A2.1
0.2177
4.A2.1a
5760.0
0.0055
36000
MT
4.A2.1b
Right Of Way
7200.0
0.0069
36000
MT
4.A2.1c
ROW Re-Instatement
7200.0
0.0069
36000
MT
4.A2.2
0.0193
Trenching
4.A2.2a
Trench Excavation
38880.0
0.0372
36000
MT
4 A2 2b
4.A2.2b
42000 0
42000.0
0 0402
0.0402
84
No
No.
4.A2.2c
66240.0
0.0635
No.
4.A2.3
0.1410
4.A2.3a
Pre-Padding
20160.0
0.0193
36000
MT
4.A2.3b
Post Padding
15840.0
0.0152
36000
MT
PREVIOUS
MONTH
THIS MONTH
ETROJET
WEIGHTAGE ACTUAL
AS ON
DATE
PREVIOUS
MONTH
THIS
MONTH
AS ON
DATE
Document Description
GC 11106200
ITEM
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
UNIT
4.A2.3c
Final Backfilling
5760.0
0.0055
36000
MT
4.A2.3d
1300.0
0.0012
Each
4.A2.3e
1600.0
0.0015
Each
4.A2.3f
5920.0
0.0057
Each
4.A2.3g
108.0
0.0001
Each
4.A2.3h
1920.0
0.0018
36000
MT
4.A2.3i
Punch List
8640.0
0.0083
Lot
Lot
4.A3
4.A3.1
0.0587
Tie-ins
Tie-Ins Of Strings
21600.0
4 A4
4.A4
0.0207
0.0207
7200.0
0.0069
18
Connections
4.A4.1b
7200.0
0.0069
18
No.
800.0
0.0008
25
No.
4.A4.2b
2240.0
0.0021
No.
4.A4.2c
800.0
0.0008
No.
4.A4.2d
Rectifier To Be Installed
560.0
0.0005
No.
4.A4.2e
Cables To Be Connected
1120.0
0.0011
1500
MT
1120.0
0.0011
Lot
4.A4.2f
4.B
4 B1
4.B1
0.0202
4.B1.1 General
4.B1.1a
17700.0
0.0170
530
M/L
4.B1.1b
5545.0
0.0053
170
M/L
49224.0
0.0472
10800
D.I
Piping Fabrication
PREVIOUS
MONTH
THIS MONTH
ETROJET
WEIGHTAGE ACTUAL
AS ON
DATE
PREVIOUS
MONTH
THIS
MONTH
AS ON
DATE
Document Description
GC 11106200
ITEM
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
UNIT
4.B1.2b
11040.0
0.0106
4000
M2
4.B1.2c
47327.0
0.0453
7200
D.I
4.B1.2d
4320.0
0.0041
Lot
4.B1.2e
Loops to be Pressurized
6120.0
0.0059
Lot
4.B1.2f
3240.0
0.0031
Lot
Piping Fabrication
8739.0
0.0084
900
D.I
4.B1.3b
3545.0
0.0034
625
M2
4.B1.3c
11400.0
0.0109
600
D.I
4.B1.4 BSV-3
4.B1.4a
7800.0
0.0075
No.
4 B1 4b
4.B1.4b
Tie-In
Tie
In To The Existing Inside BSV-3
BSV 3
2600 0
2600.0
0 0025
0.0025
Lot
4.B2
0.1711
Laying of Cables
2100.0
0.0020
2100
4.B2.1b
2100.0
0.0020
200
4.B2.1c
2100.0
0.0020
150
Laying Of Cables
1680.0
0.0016
5555
M/L
4.B2.2b
1680.0
0.0016
No.
4.B2.2c
1680.0
0.0016
12
No.
4.B2.2d
1680.0
0.0016
10
No.
4.B2.2e
1680.0
0.0016
No.
4 B2 2f
4.B2.2f
1680 0
1680.0
0 0016
0.0016
No
No.
4.B2.2g
1680.0
0.0016
No.
4.B2.2h
1680.0
0.0016
Lot
Laying Of Cables
1260.0
0.0012
13775
4.B2.3b
1260.0
0.0012
No.
PREVIOUS
MONTH
THIS MONTH
ETROJET
WEIGHTAGE ACTUAL
AS ON
DATE
PREVIOUS
MONTH
THIS
MONTH
AS ON
DATE
Document Description
GC 11106200
ITEM
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
UNIT
4.B2.3c
1260.0
0.0012
No.
4.B2.3d
1260.0
0.0012
No.
4.B2.3e
1260.0
0.0012
No.
4.B2.3f
1260.0
0.0012
No.
4.B2.3g
1260.0
0.0012
No.
4.B2.3h
1260.0
0.0012
Lot
4.B2.4 BSV-3
4.B2.4a
Laying Of Cables
5100.0
0.0049
Lot
4.B2.4b
2550.0
0.0024
Lot
4.B2.4c
Termination
7950.0
0.0076
Lot
4 B3
4.B3
0.0435
Electrical
6300.0
0.0060
No.
4.B3.1b
6300.0
0.0060
No.
4.B3.1c
6300.0
0.0060
No.
1680.0
0.0016
Lot
4.B3.2b
1680.0
0.0016
Lot
4.B3.2c
1680.0
0.0016
524
M/L
4.B3.2d
1680.0
0.0016
205
M/L
4.B3.2e
1680.0
0.0016
Lot
4.B3.2f
2520.0
0.0024
Lot
1260 0
1260.0
0 0012
0.0012
Lot
4.B3.3b
1260.0
0.0012
Lot
4.B3.3c
1260.0
0.0012
120
M/L
4.B3.3d
1260.0
0.0012
260
M/L
4.B3.3e
1260.0
0.0012
Lot
4.B3.3f
2100.0
0.0020
Lot
PREVIOUS
MONTH
THIS MONTH
ETROJET
WEIGHTAGE ACTUAL
AS ON
DATE
PREVIOUS
MONTH
THIS
MONTH
AS ON
DATE
Document Description
GC 11106200
ITEM
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
UNIT
4.B3.4 BSV-3
4.B3.4a
5100.0
0.0049
Lot
4.B3.4b
2550.0
0.0024
125
4.B3.4c
7950.0
0.0076
No.
4.B5
0.0516
4550.0
0.0044
515
Cu.M
4.B5.1b
11200.0
0.0107
298
Cu.M
4.B5.1c
41440.0
0.0397
210
Cu.M
4.B5.1d
2800.0
0.0027
No.
15750.0
0.0151
220
No.
4.B5.2b
8250.0
0.0079
220
No.
3900.0
0.0037
No.
4.B5.3.1b
6780.0
0.0065
No.
4.B5.3.1c
21600.0
0.0207
No.
4.B5.3.1d
1200.0
0.0011
No.
650.0
0.0006
141
Cu.M
4.B5.3.2b
1130.0
0.0011
114
Cu.M
4.B5.3.2c
3600.0
0.0034
62
Cu.M
4 B5 3 2d
4.B5.3.2d
200 0
200.0
0 0002
0.0002
Lot
19680.0
0.0189
165
Ton
4.B5.3.3b
1300.0
0.0012
95
Cu.M
4.B5.3.3c
2260.0
0.0022
95
Cu.M
4.B5.3.3d
7200.0
0.0069
73
Cu.M
PREVIOUS
MONTH
THIS MONTH
ETROJET
WEIGHTAGE ACTUAL
AS ON
DATE
PREVIOUS
MONTH
THIS
MONTH
AS ON
DATE
Document Description
GC 11106200
ITEM
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
UNIT
4.B5.3.3e
400.0
0.0004
Lot
4.B5.3.3f
9840.0
0.0094
165
Ton
4.B5.3.3g
4920.0
0.0047
2850
Sq.M
4.B5.3.3h
4950.0
0.0047
188
Cu.M
780.0
0.0007
27
Cu.M
4.B5.4b
2000.0
0.0019
27
Cu.M
4.B5.4c
6660.0
0.0064
25
Cu.M
4.B5.4d
270.0
0.0003
Lot
4.B5.4e
4000.0
0.0038
Lot
4.B5.4f
1152.0
0.0011
50
Cu.M
4 B5 5 Roads
4.B5.5
4.B5.5a
4320.0
0.0041
677
Sq.M
4.B5.5b
1728.0
0.0017
19
Sq.M
4.B5.5b
1728.0
0.0017
67
Sq.M
4.B5.6 BSV-3
4.B5.6a
Excavation In BSV-3
1200.0
0.0011
21
Cu.M
4.B5.6b
1200.0
0.0011
21
Cu.M
4.B5.6c
6000.0
0.0057
37
Cu.M
4.B5.6d
Fence In BSV-3
6000.0
0.0057
60
M/L
4.B9
4.B9
4.B11
Extension of SER-12
0.2018
9900.0
0.0095
Lot
1120.0
0.0011
28
Cu.M
4.B11.1b
P.C (Foundation)
1200.0
0.0011
Sq.M
4.B11.1c
R.C (Foundation)
2800.0
0.0027
40
Sq.M
4.B11.1d
Insulation (Foundation)
720.0
0.0007
Lot
4.B11.1e
BackFilling (Foundation)
280.0
0.0003
Lot
PREVIOUS
MONTH
THIS MONTH
ETROJET
WEIGHTAGE ACTUAL
AS ON
DATE
PREVIOUS
MONTH
THIS
MONTH
AS ON
DATE
Document Description
GC 11106200
ITEM
DESCRIPTION
MANHOURS
RELATIVE
WEIGHT
QUANTITY
UNIT
4.B11.1f
R.C (Columns)
2160.0
0.0021
Cu.M
4.B11.1g
4480.0
0.0043
40
Cu.M
4.B11.1h
External Finishing
12000.0
0.0115
Lot
4.B11.1i
Internal Finishing
12000.0
0.0115
Lot
Lighting Fixtures
Fixtures, Sockets For Rooms
1020 0
1020.0
0 0010
0.0010
Lot
4.B11.2b
1020.0
0.0010
Lot
4.B11.2c
1020.0
0.0010
Set
4.B11.2d
Termination
1020.0
0.0010
Lot
Laying of Cables
1020.0
0.0010
250
M/L
4.B11.3b
1020.0
0.0010
Lot
4.B11.3c
1020.0
0.0010
Lot
4.B11.3d
1020.0
0.0010
Lot
4.B11.3e
1020.0
0.0010
Lot
4.B11.3f
1020.0
0.0010
Lot
0.0450
1043762.0
1.0000
PREVIOUS
MONTH
THIS MONTH
ETROJET
WEIGHTAGE ACTUAL
AS ON
DATE
PREVIOUS
MONTH
THIS
MONTH
AS ON
DATE
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
DAILY PROGRESS REPORT
(DPR) FORMAT
______________________________________
Ser.
Activity
Unit
Total
Q.ty
Target
P 1/1
Q.ty
Previous
Today
Cumu.
Q.ty
Cumu.
%
Variance
%
M/L
36000
0.00%
0.00%
0.00%
M/L
36000
0.00%
0.00%
0.00%
Trench Excavation
M/L
36000
0.00%
0.00%
0.00%
Pipe Transportation
M/L
36000
0.00%
0.00%
0.00%
Pipe Stringing
M/L
36000
0.00%
0.00%
0.00%
Joint
3000
0.00%
0.00%
0.00%
N.D.T
Joint
3000
0.00%
0.00%
0.00%
Joint
3000
0.00%
0.00%
0.00%
Pre-Padding
M/L
36000
0.00%
0.00%
0.00%
10
Lowering
M/L
36000
0.00%
0.00%
0.00%
11
Post Padding
M/L
36000
0.00%
0.00%
0.00%
12
Each
226
0.00%
0.00%
0.00%
13
Final Back-Filling
M/L
36000
0.00%
0.00%
0.00%
14
Cleaning By Pigs
M/L
36000
0.00%
0.00%
0.00%
Planning Engineer
Project Manager
M. Salah
M. Mamdouh
Page 246 of 266
Remarks
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
WEEKLY PROGRESS REPORT
(WPR) FORMAT
______________________________________
DOC
NO
3392-WPR-0010
DOUMENT TITLE
DATE
July 19,2012
Eng. M. Salah
Eng. M. Mamdouh
Planning Engineer
Project Manager
DOC
NO
3392-WPR-0010
DOUMENT TITLE
DATE
TABLE OF CONTENTS
1. PROJECT KEY EVENTS
2. PHYSICAL PROGRESS
3. QUANTITATIVE PROGRESS
4. WEEKLY HIGHLIGHT
5. SAFETY STATISTICS
6. MOBILIZATION AND DE-MOBILIZATION
7. INTERFACE STATUS
8. SUB-CONTRACTORS LIST / STATUS
9. ACTIVITES PLANNED FOR NEXT WEEK
10. AREA OF CONCERNS
11. ATTACHMENTS
10.1
Manpower Status
10.2
Equipment Status
10.3
10.4
Marching Chart
10.5
10.6
10.7
10.8
10.9
July 19,2012
DOC
NO
3392-WPR-0010
DOUMENT TITLE
DATE
July 19,2012
S/NO.
Description
Original plan
Forecast*
Actual
Contract Award
Feb 26,2012
Feb 26,2012
Mar 7,2012
Mar 17,2012
Construction Start
June 3,2012
June 3,2012
Jul 15,2012
Jul 16,2012
Jul 30,2012
Sep 1,2012
10
Feb 25,2013
11
Nov 21,2013
12
May 23,2014
13
Jul 23,2014
14
Aug 25,2014
* Forecasted dates reflect current work plan & will not impact the date of the Commissioning
achieving of PL and all facilities. (May 25,2014)
DOC
NO
3392-WPR-0010
DOUMENT TITLE
DATE
July 19,2012
2. PHYSICAL PROGRESS
Progress figures based on the approved project baseline schedule
This Week
Description
WT %
Cumulative
Planned
%
Actual
%
Planned
%
Actual
%
Variance
%
Engineering
5.0 %
0.00 %
0.00 %
0.00 %
0.00 %
0.00 %
Procurement
40.0 %
00.00 %
00.00 %
00.00 %
00.00 %
00.00 %
Construction
48.0 %
00.00 %
00.00 %
00.00 %
00.00 %
00.00 %
Pre-commissioning &
Commissioning
5.0 %
00.00 %
00.00 %
00.00 %
00.00 %
00.00 %
Optional
2.0 %
00.00 %
00.00 %
00.00 %
00.00 %
00.00 %
100.0 %
0.00 %
0.00 %
0.00 %
0.00 %
0.00 %
Total Project
3. QUANTITATIVE PROGRESS
This Week
Activity
Unit
Cumulative
Quantity
Planned
Actual
Planned
Actual
Survey Work
M/L
36000
0.0
0.0
0.0
0.0
M/L
36000
0.0
0.0
0.0
0.0
Trench Excavation
M/L
36000
0.0
0.0
0.0
0.0
M/L
36000
0.0
0.0
0.0
0.0
M/L
36000
0.0
0.0
0.0
0.0
Welding Of Pipes
Joint
3000
0.0
0.0
0.0
0.0
Joint
3000
0.0
0.0
0.0
0.0
Joint
3000
0.0
0.0
0.0
0.0
Sand Pre-Padding
M/L
36000
0.0
0.0
0.0
0.0
Lowering Of Pipeline
M/L
36000
0.0
0.0
0.0
0.0
Sand Padding
M/L
36000
0.0
0.0
0.0
0.0
100
0.0
0.0
0.0
0.0
Each
84
0.0
0.0
0.0
0.0
HDD Crossings
Each
0.0
0.0
0.0
0.0
Final Backfilling
M/L
36000
0.0
0.0
0.0
0.0
Tie-in Of Sections
DOC
NO
3392-WPR-0010
DOUMENT TITLE
DATE
July 19,2012
4. WEEKLY HIGHLIGHT
4-1 Engineering
4-2 Procurement
Construction
1.
Completion of the grading for the route of 16" Jet A1 Fuel P/L with total length of 0.0 km.
2.
3.
106.48 Km of 16" coated pipes had been transported from coating plant to the field site,
LSTK Contractor is requested to expedite the delivery of the remaining 16" pipes with
productivity not less than 1.5 km / day to overcome the delay in the pipe transportation
activity.
4.
0.00 Km of 16" coated pipes had been stringed along the route.
5.
Finalized the welding activity for 0.00 Km of 16" pipes out of 36 km.
6.
7.
Finalized the field joint coating (FBE) with total quantity 0.00 km out of 36 km.
8.
Finalized the lowering activity with total quantity 0.00 km out of 36 km.
9.
10.
Finalized the sand padding activity with total quantity 0.0 km out of 36 km.
11.
Finalized the final backfilling activity with total quantity 0.0 km out of 36 km
12.
Finalized the rock cap cover activity with total quantity 0.0 km out of 36 km
DOC
NO
3392-WPR-0010
DOUMENT TITLE
DATE
July 19,2012
5. SAFETY STATISTICS
Near
Miss
FAI
MTC
FAT
LTI
RDI
MVA's
Fires
Others
*
Manpower
204
Manhours
(This Week)
12240
Year to date
(MH)
12240
Project to date
(MH)
12240
FAI : First Aid Incident / MTC : Medical Treatment Case / FAT : Fatality / LTI : Lost Time Injury-Illness /
RDI : Restricted Duty Incident
* Other Incident (Spill, damage to property, environment, etc)
7. INTERFACE STATUS
Petrojet already attended the meeting with Kahramaa to finalize the necessary permit and
requirements by Kahramaa approved consultant as a first stage to get QP approval to execute the
option # (1) at BSV-3 (Pole mounted Transformer ) .
DOC
NO
3392-WPR-0010
DOUMENT TITLE
DATE
July 19,2012
No.
Sub-Contracting Description
Status
Engineering Consultant
TCF construction
Security sub-contractor
N.D.T
10
Cathodic Protection
11
12
Commissioning
Remarks
Already
Awarded
DOC
NO
3392-WPR-0010
DOUMENT TITLE
DATE
July 19,2012
Unit
Quantity
Q.ty
Survey Work
M/L
36000
M/L
36000
Trench Excavation
M/L
36000
Transportation Of Coated
Pipes
M/L
36000
M/L
36000
Welding Of Pipes
Joint
3000
Joint
3000
Joint
3000
Sand Pre-Padding
M/L
36000
Lowering Of Pipeline
M/L
36000
Sand Padding
M/L
36000
100
Each
84
HDD Crossings
Each
Final Backfilling
M/L
36000
Tie-in Of Sections
Cumulative Planned Up
To End Of Next Week
Q.ty
DOC
NO
3392-WPR-0010
DOUMENT TITLE
DATE
July 19,2012
EPIC Contractor is requested to take the corrective action and maximize the
resources to mitigate the severe delay of the engineering phase .
EPIC Contractor is requested to expedite the finalizing of the (WPS) which will
be followed with the PQR and welders qualifications .
11. ATTACHMENTS
DOC NO
3392-00-69-00-0003
DOUMENT TITLE
REV 5
DATE
JULY 19,2012
PLANNING PACKAGE
______________________________________
MONTHLY PROGRESS REPORT
(MPR) FORMAT
______________________________________
DOC
NO
3392-MPR-0003
DOUMENT TITLE
DATE
June 28,2012
Eng. M. Salah
Eng. M. Mamdouh
Planning Engineer
Project Manager
DOC
NO
3392-MPR-0003
DOUMENT TITLE
DATE
TABLE OF CONTENTS
1. PROJECT KEY EVENTS
2. PHYSICAL PROGRESS
3. QUANTITATIVE PROGRESS
4. EXECUTIVE SUMMARY
5. SAFETY STATISTICS
6. MOBILIZATION AND DE-MOBILIZATION
7. INTERFACE STATUS
8. SUB-CONTRACTORS LIST / STATUS
9. ACTIVITES PLANNED FOR NEXT MONTH
10. AREA OF CONCERNS
11. VARIANCE ANALYSIS AND MITIGATION PLAN
12. ATTACHMENTS
10.1
Manpower Status
10.2
Equipment Status
10.3
10.4
Marching Chart
10.5
10.6
10.7
10.8
10.9
June 28,2012
DOC
NO
3392-MPR-0003
DOUMENT TITLE
DATE
June 28,2012
S/NO.
Description
Original plan
Forecast*
Actual
Contract Award
Feb 26,2012
Feb 26,2012
Mar 7,2012
Mar 17,2012
Construction Start
June 3,2012
June 3,2012
Jul 15,2012
Jul 16,2012
Jul 30,2012
Sep 1,2012
10
Feb 25,2013
11
Nov 21,2013
12
May 23,2014
13
Jul 23,2014
14
Aug 25,2014
* Forecasted dates reflect current work plan & will not impact the date of the Commissioning
achieving of PL and all facilities. (May 25,2014)
DOC
NO
3392-MPR-0003
DOUMENT TITLE
DATE
June 28,2012
2. PHYSICAL PROGRESS
Progress figures based on the approved project baseline schedule
This Month
Description
WT %
Cumulative
Planned
%
Actual
%
Planned
%
Actual
%
Variance
%
Engineering
5.0 %
0.00 %
0.00 %
0.00 %
0.00 %
0.00 %
Procurement
40.0 %
00.00 %
00.00 %
00.00 %
00.00 %
00.00 %
Construction
48.0 %
00.00 %
00.00 %
00.00 %
00.00 %
00.00 %
Pre-commissioning &
Commissioning
5.0 %
00.00 %
00.00 %
00.00 %
00.00 %
00.00 %
Optional
2.0 %
00.00 %
00.00 %
00.00 %
00.00 %
00.00 %
100.0 %
0.00 %
0.00 %
0.00 %
0.00 %
0.00 %
Total Project
3. QUANTITATIVE PROGRESS
This Month
Activity
Unit
Cumulative
Quantity
Planned
Actual
Planned
Actual
Survey Work
M/L
36000
0.0
0.0
0.0
0.0
M/L
36000
0.0
0.0
0.0
0.0
Trench Excavation
M/L
36000
0.0
0.0
0.0
0.0
M/L
36000
0.0
0.0
0.0
0.0
M/L
36000
0.0
0.0
0.0
0.0
Welding Of Pipes
Joint
3000
0.0
0.0
0.0
0.0
Joint
3000
0.0
0.0
0.0
0.0
Joint
3000
0.0
0.0
0.0
0.0
Sand Pre-Padding
M/L
36000
0.0
0.0
0.0
0.0
Lowering Of Pipeline
M/L
36000
0.0
0.0
0.0
0.0
Sand Padding
M/L
36000
0.0
0.0
0.0
0.0
100
0.0
0.0
0.0
0.0
Each
84
0.0
0.0
0.0
0.0
HDD Crossings
Each
0.0
0.0
0.0
0.0
Final Backfilling
M/L
36000
0.0
0.0
0.0
0.0
Tie-in Of Sections
DOC
NO
3392-MPR-0003
DOUMENT TITLE
DATE
June 28,2012
4. EXECUTIVE SUMMARY
4-1 Engineering
4-2 Procurement
Construction
1.
Completion of the grading for the route of 16" Jet A1 Fuel P/L with total length of 0.0 km.
2.
3.
106.48 Km of 16" coated pipes had been transported from coating plant to the field site,
LSTK Contractor is requested to expedite the delivery of the remaining 16" pipes with
productivity not less than 1.5 km / day to overcome the delay in the pipe transportation
activity.
4.
0.00 Km of 16" coated pipes had been stringed along the route.
5.
Finalized the welding activity for 0.00 Km of 16" pipes out of 36 km.
6.
7.
Finalized the field joint coating (FBE) with total quantity 0.00 km out of 36 km.
8.
Finalized the lowering activity with total quantity 0.00 km out of 36 km.
9.
10.
Finalized the sand padding activity with total quantity 0.0 km out of 36 km.
11.
Finalized the final backfilling activity with total quantity 0.0 km out of 36 km
12.
Finalized the rock cap cover activity with total quantity 0.0 km out of 36 km
DOC
NO
3392-MPR-0003
DOUMENT TITLE
DATE
June 28,2012
5. SAFETY STATISTICS
Near
Miss
FAI
MTC
FAT
LTI
RDI
MVA's
Fires
Others
*
Manpower
204
Manhours
(This Month)
12240
Year to date
(MH)
12240
Project to date
(MH)
12240
FAI : First Aid Incident / MTC : Medical Treatment Case / FAT : Fatality / LTI : Lost Time Injury-Illness /
RDI : Restricted Duty Incident
* Other Incident (Spill, damage to property, environment, etc)
7. INTERFACE STATUS
Petrojet already attended the meeting with Kahramaa to finalize the necessary permit and
requirements by Kahramaa approved consultant as a first stage to get QP approval to execute the
option # (1) at BSV-3 (Pole mounted Transformer ) .
DOC
NO
3392-MPR-0003
DOUMENT TITLE
DATE
June 28,2012
No.
Sub-Contracting Description
Status
Engineering Consultant
TCF construction
Security sub-contractor
N.D.T
10
Cathodic Protection
11
12
Commissioning
Remarks
Already
Awarded
DOC
NO
3392-MPR-0003
DOUMENT TITLE
DATE
June 28,2012
Unit
Quantity
Q.ty
Survey Work
M/L
36000
M/L
36000
Trench Excavation
M/L
36000
Transportation Of Coated
Pipes
M/L
36000
M/L
36000
Welding Of Pipes
Joint
3000
Joint
3000
Joint
3000
Sand Pre-Padding
M/L
36000
Lowering Of Pipeline
M/L
36000
Sand Padding
M/L
36000
100
Each
84
HDD Crossings
Each
Final Backfilling
M/L
36000
Tie-in Of Sections
Cumulative Planned up
to end of next month
Q.ty
DOC
NO
3392-MPR-0003
DOUMENT TITLE
DATE
June 28,2012
EPIC Contractor is requested to take the corrective action and maximize the
resources to mitigate the severe delay of the engineering phase .
EPIC Contractor is requested to expedite the finalizing of the (WPS) which will
be followed with the PQR and welders qualifications .
12. ATTACHMENTS