Law381 All Topics
Law381 All Topics
Law381 All Topics
TABLE OF CONTENTS
1.0 INTRODUCTION TO LAW381.................................................................................1
2.0 FUNDAMENTAL OF CONSTRUCTION LAW..............................................................2
3.0 OVERVIEW OF THE MALAYSIAN LEGAL SYSTEM....................................................5
4.0 THE MALAYSIAN JUDICIAL SYSTEM........................................................................9
5.0 THE LAW OF CONTRACT I............................................................................... .....11
6.0 THE LAW OF CONTRACT II ..................................................................................17
7.0 THE LAW OF CONTRACT III..................................................................................25
8.0 THE LAW OF TORT I........................................................................................... ..30
9.0 THE LAW OF TORT II....................................................................................... .....36
10.0 THE LAW OF TORT III................................................................................. ........44
11.0LAND LAW I .................................................................................................. .....52
12.0 LAND LAW II ............................................................................................. ........58
SYNOPSIS
• To introduce what is LAW381 all about
• To inform the expectations of the lecturer towards the whole semester
• To aware the students on the process of teaching and learning
PROPOSITION
• 10% - coursework and presentation
• 10% - 20% tutorial (every week)
• 10% - attendance and participation in class
• 60% - 70% - examination
• Passing marks 50%
• Percentage of failures 20% - 30%
ZULHABRI Ismail
Department of Building Page 1
CONSTRUCTION LAW
• Come early to my class – if you come later than me you are considered
‘late’
2.0 FUNDAMENTAL OF CONSTRUCTION LAW
SYNOPSIS
To provide an introduction and overview on construction law.
CONSTRUCTION LAW
“Construction law is neither a legal term of art not technical one. It is
used to cover the whole field of law which, in one way or another, affects
the construction industry...” Prof John Uff (2001).
CATEGORIES OF LAW
Sources of Construction Law can be categorized into the following:-
• Written: Legal source of law refers to all that law that has been
reduced to, or is present in the written form (Harbans Singh, 2005).
• Unwritten: Constitutes that part of the local law that is not
recognised as “written law”.
Section 3 of the Interpretation Acts 1948 and 1967 (Act 388) defines “written
law” to mean:
WRITTEN LAW
Legislation - Acts of parliament / statutes
Example of Statutes/Acts Apply To Construction
1. Arbitration Act 2005.
2. Architects Act 1967 (Revised 1973) Act 117.
3. Companies Act 1965 (Revised 1973 – Reprint 1988) Act 125.
ZULHABRI Ismail
Department of Building Page 2
CONSTRUCTION LAW
4. Contracts Act 1950 (Revised 1974 – Reprint 1997) Act 563 &
(Amendment) 1976 Act 136.
5. Convention on the Recognition and Enforcement of Foreign Arbitral
Awards Act 1985 Act 320 Act A329.
6. Drainage Works Act 1954 (Revised 1988) Act 354.
7. Environment Quality Act 1974 Act 127.
8. Factories and Machinery Act 1967 (Revised 1974 – Reprint 1997) Act 139.
9. Fire Services Act 1988 Act 341.
10.Government Contracts Act 1949 (Revised 1973) Act 120.
11.Housing Developers (Control and Licensing) Act 1966 (Revised 1973 –
Reprint 1982) Act 118.
12.Limitation Act 1953 (Revised 1981) Act 254.
13.National Land Code 1965 Act 56/1965.
14.Occupational Safety and Health Act 1994 Act 514.
15.Sale of Goods Act 1957 (Revised 1989) Act 382.
16.Strata Titles Act 1985 Act 318.
17.Street, Drainage and Building Act 1974 Act 133.
18.Town and Country Planning Act 1976 Act 172.
ZULHABRI Ismail
Department of Building Page 3
CONSTRUCTION LAW
(3) An action upon any judgment shall not be brought after the expiration of
twelve years from the date on which the judgment became enforceable and
no arrears of interest in respect of any judgment debt shall be recovered after
the expiration of six years from the date on which the interest became due.
UNWRITTEN
1. Judicial decisions
2. Local case law.
3. Doctrine of ‘Stare Decisis’ / judicial precedent.
4. Applicable English law
a. Common law
i. Common law principles.
b. Case laws.
c. Equitable principles
i. The principle of ‘fairness’.
d. Statutes
e. Statutes of General Application.
5. Trade custom / usage
a. Particular to the construction industry.
b. Implication / interpretation of terms.
6. Use of Foreign Cases
ZULHABRI Ismail
Department of Building Page 4
CONSTRUCTION LAW
SYNOPSIS
The purpose of this lecture is to discuss the overall principles underpinned
the Malaysian law.
CONTENT
1. The Concept of Law in Malaysia
2. Purpose of law
3. Composition of law
4. Federal v State constitution
5. Sources of Malaysian Law
6. Judicial Precedent
PURPOSE OF LAW
1. To attain justice in society.
2. Encourage the doing of what is right or just in a particular set of
circumstances.
COMPOSITION OF LAW
1. The parliament – written law.
2. Federal court – unwritten law.
3. Federal and State constitution
4. The written constitution in Malaysia – Federal Constitution.
ZULHABRI Ismail
Department of Building Page 5
CONSTRUCTION LAW
Held – Case dismissed on the grounds that it was fair and reasonable.
WRITTEN LAW
Section 3 of the Interpretation Acts 1948 and 1967 (Act 388) defines “written
law” to mean:
1. The federal Constitution and the Constitutions of the States and
subsidiary legislation…;
2. Acts of Parliament and subsidiary legislation…; and
3. Ordinances and Enactments (including any federal or state law styling
itself an Ordinance or Enactment) and subsidiary legislation…; and
4. Any other legislative enactments or legislative instruments (including Acts
of Parliament of the United Kingdom of Great Britain and Northern Ireland
and Orders in Council and other subsidiary legislation made thereunder)
which are in force in Malaysia or any part thereof.
Acts
A federal laws that post Malayan Union (September 1959).
Ordinance
• A federal laws that are enacted by parliament between the period of
the Malayan Union (1946-10 September 1959).
• The laws in Sarawak are called Ordinances.
ZULHABRI Ismail
Department of Building Page 6
CONSTRUCTION LAW
Enactments
• Laws made by the State Legislative Assemblies (except in Sarawak).
• A law made by the Legislature of a State.
Legislation
• Acts of Parliament – Statutes, subsidiary/delegated legislation.
• State laws – Ordinance & enactments.
• Legislation - Acts of parliament
• Statutes
UNWRITTEN LAW
1. Judicial decisions
2. Local case law.
3. Doctrine of ‘Stare Decisis’ / judicial precedent.
4. Applicable English law
a. Common law
i. Common law principles.
b. Case laws.
c. Equitable principles
i. The principle of “fairness”.
d. Statutes
e. Statutes of General Application.
5. Trade custom / usage
a. Particular to the construction industry.
b. Implication / interpretation of terms.
6. Use of Foreign Cases
JUDICIAL PRECEDENT
Sources of law where past decisions of the judges create law for future
judges to follow. Also known as case law, which is one of the primary
sources of English law and Malaysian law.
ZULHABRI Ismail
Department of Building Page 7
CONSTRUCTION LAW
ZULHABRI Ismail
Department of Building Page 8
CONSTRUCTION LAW
Persuasive precedent
• Not binding, but the judge way considers it and decides that it is a correct
principle to follow; secondary sources.
• Normally comes from lower courts judgment; decision of the judicial
committee of the Privy Council; obiter dicta; dissenting judgment or
judgment of courts in other countries.
Distinguishing
• Judge finds that the facts of the case he is deciding are different for him to
draw distinction between the present case and the previous precedent. He
is not bound by the previous case.
• In Trenberth v NWB (1980) Walton J said that the decision in Woollerton &
Wilson v Costain (1970) was incorrect and cannot be relied upon.
Overruling
Referring to the situation of the court in later case states that the legal rule
decided in an earlier case is wrong. Its may occur when a higher court
overrules a decision made in an earlier case by a lower court.
The House of Lords uses its power under the practice statement to overrule a
past decision of its own; in Pepper v Hart (1993) the HL overruled the earlier
decision in Davis v Johnson (1979).
Judicial Precedent
Reversing
The higher court overturns the decision of a lower court on appeal in the
same case.
For instance, the CA may disagree with the legal ruling of the high court and
come to a different view of law and reverse the decision made; Aldersons v
Beetham (2003).
SYNOPSIS
The purpose of this lecture is to discuss the legal principles underpinned the
Malaysian courts.
ZULHABRI Ismail
Department of Building Page 9
CONSTRUCTION LAW
1. Prior to 1st January 1985 the superior courts system in Malaysia was the
following:-
a. The Privy Council
b. The Supreme Court
c. The High Court Malaya and the
High Court Borneo.
2. After 1985 - the abolishment of appeals to
the Privy Council.
3. Resulted in a change from the three-tiered
system to a two-tiered system (Supreme
Court and the two (2) High Courts).
4. In 1994 the Court of Appeal was established.
The Supreme Court was renamed the
Federal Court. As a consequence, the three-
tiered system of the superior courts was
restored.
HIRARCHY OF COURTS
ZULHABRI Ismail
Department of Building Page 10
CONSTRUCTION LAW
SYNOPSIS
The purpose of this lecture is to discuss the following:-
1. The elements of valid and enforceable construction contracts
2. The important of legally binding construction contracts.
ZULHABRI Ismail
Department of Building Page 11
CONSTRUCTION LAW
Sri Kajang Rock Products Sdn Bhd v Mayban Finance Bhd (1992)
VC George J stated that to constitute a valid contract, there must be:-
1. Separate and define parties thereto; those parties must be in
agreement,
2. that there is consensus ad idem;
3. Those parties must intend to create legal relations in the sense that
the promises of each side are to be enforceable simply because they
are contractual promises;
4. And the promises of each party must be supported by consideration.
TYPES OF CONTRACT
Contractual relationships arise in three ways:-
1. Through the agreement between the parties (consensual contract).
2. Through one party performing some act in reliance upon a promise,
often implied, by the other (a unilateral contract).
3. Though the execution of a deed (previously called a specialty contract)
containing the promise, e.g. purchasing a house.
4. Consensual and unilateral contracts are called simple contracts.
5. A deed [specialty] is a contract “under seal”.
OFFER
The nature of offers
• A person making an offer is called an offeror.
• The person to whom the offer is made, and who thus can accept it is
called the offeree.
• The offer is a statement of intent by the offeror to be legally bound by the
terms of the offer if it is accepted, and the contract exists once
acceptance has taken place.
Rules of offer
• To one or a number of persons.
• Must be communicated [s.4 (1)].
• All terms must be brought to notice of offeree.
• May specify conditions to be followed [s.7 (b)] i.e. may be in any form.
ZULHABRI Ismail
Department of Building Page 12
CONSTRUCTION LAW
Lapse of offer
• If not accepted within the time stated [s.6 (b)].
• If no time stated, not accepted within reasonable time.
• If counter offer made [s.7].
• Death before acceptance [s.6].
• Invitation to Treat is not an Offer.
ZULHABRI Ismail
Department of Building Page 13
CONSTRUCTION LAW
ACCEPTANCE
Rules of acceptance
• Must be communicated to offeror [s.2(a)].
• Must be unconditional [s.7(a)].
• Must be made in the method described [s.7(b)].
• Can only be made by party to whom the offer was made.
• Must be made within prescribed time – before lapsed, revoked or rejected.
• Cannot be revoked without consent of the offeror [s.5(2)].
ZULHABRI Ismail
Department of Building Page 14
CONSTRUCTION LAW
Shop fitters, following their successful tender, contracted with the architects
in a building contract to sub-contract to the builders. The builders, under
instruction from the architects, issued an order for work to the shop fitters.
They did this on their own standard form that included a clause that they
would not pay for work until they themselves had been paid [pay when paid].
The shop fitters later sued for payment.
It was held that the shop fitter’s action failed. The builders’ standard form /
[pay when paid clause] was a counter-offer that the shop fitters had
accepted by carrying on with the work.
It was held that because there was a total disagreement over a major term,
the judge in the case found it impossible to recognise that a contract existed.
He did order that BSC be paid for what they had supplied based on quantum
meruit.
Macon Works & Trading Sdn Bhd v Phang Hon Chin & Anor (1976)
The defendants were owners of a piece of land. The agreement to sell the
land to the plaintiff was unsuccessful and subsequently an option was given
to purchase the land to A. The option was an open dated, exercisable only
after the plaintiff showed no more interest in the land. The plaintiffs claimed
for specific performance of the agreement.
The court held that the option was void for lack of consideration. Since no
time was fixed, the offer would lapse after the expiration of a reasonable
ZULHABRI Ismail
Department of Building Page 15
CONSTRUCTION LAW
time. An offer lapses after a reasonable time not because this must be
implied in the offer but because failure to accept within a reasonable time
implies rejection by the offeree.
Certainty [s.30]
Terms that are certain or capable of being made certain.
Capacity [s.11]
Legal capacity
• Must be age of majority, sound mind and not barred by law.
• Void if made by minors, drunkards and mental incapacity.
Legality [s.24]
Void contract if object of agreement is:
• Forbidden by the law.
• Such that it defeats any law.
• Such that it involves injury to person or property.
• Immoral or opposed to public policy.
• Legality [s.24]
• In restraint of marriage [s.27].
• In restraint of trade [s.28].
• In restraint of legal proceedings [s.29].
ZULHABRI Ismail
Department of Building Page 16
CONSTRUCTION LAW
SYNOPSIS
The purpose of this lecture is to discuss the following:-
1. Privity of contract.
2. Conditions and warranties.
3. Standard contracts and exemption clauses.
4. Vitiating factors - voidable contracts.
PRIVITY OF CONTRACT
Definition
“As a general rule, contractual rights and liabilities affect only the parties to
the contract and a person who is not party can neither sue nor be sued on
the contract.” (Ainah, 2005).
Dunlop Pneumatic Tyre Co. Ltd. V Selfridge & Co. Ltd. (1914)
In the contract Dew & Co., wholesalers, agreed to buy tyres from Dunlop.
They did so on the express undertaking that they would not sale below
certain fixed prices. They also undertook to obtain the same price-fixing
agreements from their clients. Dew sold tyres on to Selfridge on these terms
but Selfridge broke the agreement and sold tyres at discount prices. Dunlop
sought an injunction.
ZULHABRI Ismail
Department of Building Page 17
CONSTRUCTION LAW
It was held that Dunlop application for injunction was failed for lack of Privity.
In the House of Lords Lord Haldane said:-
“Only a person who is a party to a contract can sue on it. Our law knows
nothing of a jus quaesitum tertio arising by way of contract. Such a right
may be conferred by way of property, as, for example, under a trust,
but it cannot be conferred on a stranger to a contract as a right to
enforce the contract in personam.”
It was held that even though he was named in the agreement, he failed
because he had given no consideration for the agreement himself.
ZULHABRI Ismail
Department of Building Page 18
CONSTRUCTION LAW
TERMS OF A CONTRACT
Contents of a Contract
Contents of a contract are made up of terms either expressed or expressly
stated; and / or Implied
Terms implied
Terms implied by fact
• Implied by custom or habit.
• Implied by trade or professional custom.
• Implied to give sense and meaning to the agreement.
• Implied to give business efficacy to a commercial contract; The
Moorcock.
• Implied because of the prior conduct of the contracting parties;
Hillas v Arcos
The court held that there was an implied undertaking that the ship
would not be damaged. Bowen LJ explained that:-
ZULHABRI Ismail
Department of Building Page 19
CONSTRUCTION LAW
“In business what the transactions such as this, what the law desires to
effect by the implication is to give such business efficacy…as must have
been intended at all events by both parties who are businessmen.”
The House of Lords held that, while the option clause lacked specific detail,
nevertheless it was un the same terms as the contract of sale that had been
completed. It was therefore implicit in the original contract that the
option be carried out in the same terms if the claimant wished to exercise it.
Warranty
“…is a stipulation collateral to the main purpose of the contract, the
breach of which gives rise to a claim for damages but not a right to
reject the goods and treat the contract as repudiated” Sale of Goods
Act 1957 (Act 382), Section 12(3).
ZULHABRI Ismail
Department of Building Page 20
CONSTRUCTION LAW
Any other term in a contract that does not go to the root of the contract.
It was held that the failure on the part of the defendants to supply a
furnace which would meet the required temperature constitute a
breach of the condition of the contract entitling the plaintiffs to treat such
breach as a breach of warranty. Judgment was given for the plaintiffs
Other industries
• Banking – standard formats of contracts
• Insurance
• Air travel
ZULHABRI Ismail
Department of Building Page 21
CONSTRUCTION LAW
VITIATING FACTORS
Definition
“Vitiate” means “to spoil or reduce the effect” (Oxford, 2003).
Voidable
Contracts Act 1950
Section 10 of the Contracts Act provides “All agreements are contracts if
they are made by the free consent of the parties competent to contract”.
Section 14 states that “Consent is said to be free when it is not caused by”:-
• Coercion [s.15]
• Undue influence [s.16, 20 ]
• Fraud [s.17]
• Misrepresentation [s.18]
• Mistake [s.21, 22 and 23]
Coercion [s.15]
ZULHABRI Ismail
Department of Building Page 22
CONSTRUCTION LAW
Coercion
Under common law, the principle is slightly differ, it is based on duress
[including economic duress], meaning the contract has resulted from “actual
or threatened violence”.
Lord Denning in Lloyds Bank Ltd v Bundy (1975) suggested two doctrines:
Economic duress and inequality of bargaining power.
Fraud [s.17]
• Section 17
ZULHABRI Ismail
Department of Building Page 23
CONSTRUCTION LAW
Misrepresentation [s.18]
• Section 18
The court held that the company was awarded damages under section 2(1)
of the Misrepresentation Act 1967. The Spice Girls had no reasonable
grounds to believe that there would be five of them to perform the contract.
Void Contracts
Definition
• The contract does not exist / nullity.
• Contract having no validity.
• Not enforceable in law (s.2(g); 24).
• Incapable of confirmation.
ZULHABRI Ismail
Department of Building Page 24
CONSTRUCTION LAW
SYNOPSIS
This lecture will discuss the following legal area:-
• Discharge from further performance under the contracts
• Remedies
The parties can only be freed from their mutual obligations under the
contract by the discharge of the contract.
Discharge of a Contract
Vincent Powell-Smith (2000) stated that discharge of a contract refers to “the
carrying out of an obligation imposed by contract or statute.”
ZULHABRI Ismail
Department of Building Page 25
CONSTRUCTION LAW
Discharge by Performance
Vincent Powell-Smith (2000) - Partial Performance by one party may be
sufficient evidence of his intention to be bound by the terms of a
contract if he has not made formal acceptance. Whether or not
performance is complete is a matter for the courts to decide in each
case…the courts will, however, grant relief to the contractor who can show,
in such a case that he has achieved ‘substantial performance’, i.e. the work
is complete save for some minor omissions or defects.
Discharge by Breach
Breach of contract
Failure to fulfil a contractual obligation which entitles the innocent party
to a remedy.
The obligation, or term, may be expressed or implied at common law by
statute or statutory instrument (Osborn Law Dictionary, 2001).
General principles
• The rule of contract – Both parties to the contract must perform
their promises and obligations strictly according to the terms of
the contract.
• If default – breach of contract. Thus, the entire transaction should be
aborted, the respective parties returned to their original position
and discharge from further performance.
• An intention not to go on with the contract: Repudiated / renounced
the contract.
• A refusal to perform a contract before the performance is due:
anticipatory breach.
• A refusal to perform a contract when performance is due: discharge.
ZULHABRI Ismail
Department of Building Page 26
CONSTRUCTION LAW
If the innocent party has rendered services or had supplied goods, he may
recover a reasonable sum for such services or goods rendered. If the
innocent party has paid money under the contract, he may be entitled to
recover the sum paid.
ZULHABRI Ismail
Department of Building Page 27
CONSTRUCTION LAW
But where only one party wants to back out of the contract then that party
will need to give some consideration, as in accord and satisfied, unless
estoppel applies.
Where form is an issue the discharge will need evidence in writing [estoppel].
ZULHABRI Ismail
Department of Building Page 28
CONSTRUCTION LAW
Frustrating Events
• Where the intervening event makes performance impossible.
• Where performance of the contract becomes illegal.
• Where the contract becomes commercially sterilised.
• Frustration under the Act
Under section 57(1) of the Contract Act 1950 “an agreement to do an act
impossible in itself is void”.
ZULHABRI Ismail
Department of Building Page 29
CONSTRUCTION LAW
House of Lords held that the extension of time provision did not prevent
frustration but a contract resumed after the war time interruption would be
fundamentally different from what had been envisaged this
development was sufficient to bring the contract to an end.
The House of Lords held that the claim must fail. The contract had not been
frustrated. What had happened was squarely within the risk assumed by
the contractors.
SYNOPSIS
Generally, this lecture will discuss the legal principle of the law of torts and
its relation to the construction industry.
ZULHABRI Ismail
Department of Building Page 30
CONSTRUCTION LAW
INTRODUCTION
“The law of tort is mostly to be found in the common law…Tort can be
defined as a civil wrong independent of contract; or as breach of a legal duty
owed to person generally. The practical consequences of the law of tort are
concerned with the adjustment of losses. Where the elements of fault and
damage exist, the law determines who should bear the resulting financial
loss.”
(Prof. John Uff, 2002, p.419)
Abdul Aziz and Abdul Rashid (2000) clarified what has been suggested by
Basu (1977) in relation to the definition of tort as the following:
1. Perlanggaran hak-hak persendirian (keselamatan diri, nama baik,
milikan, kecederaan).
2. Pencabulan sesuatu kewajipan di bawah “common law”.
3. Perlanggaran sesuatu kewajipan yang berbangkit daripada sesuatu hak
umum.
4. Perlanggaran sesuatu hak “in rem” (dihormati oleh semua orang) dan
bukan “in persona” (hak keatas individu) yang mana semua ahli
masyarakat tidak melakukan kerosakan kepada jiran-jiran mereka
tanpa sebab yang dibenarkan oleh undang-undang.
The standard model for liability in tort in the modern day would be that the
defendant’s act (or omission) has, through the defendant’s fault, caused
damage to the claimant of a type which is recognised as attracting liability.
AIMS
There are two aims of the law of torts that also point towards the major
remedies available, damages and injunctions.
ZULHABRI Ismail
Department of Building Page 31
CONSTRUCTION LAW
CATEGORIES OF TORT
Actionable per se
Trespass and forcible injury.
Normally entitlement to compensation accurse as of right without the
requirement to prove damage occurred.
Personal security
Concerns the safety of the individual, including.
Trespass or possibly trespass to the person, land or goods.
Possibly defamation [damaging someone reputation i.e. libel (publish in
permanent form e.g. newspaper, film etc. and slander (in an oral form
e.g. radio or TV)].
Negligence.
Other developments in personal injury i.e. claims for psychiatric
damages etc.
Possibly concepts as privacy.
ZULHABRI Ismail
Department of Building Page 32
CONSTRUCTION LAW
Teh Khew On & Anor v. Yeoh & Wu Development Sdn. Bhd. & Ors. (1995) 2
MLJ 663.
The plaintiffs claimed against the first defendant (“the builder”) in contract
for defective works in the construction of the house purchased by the
plaintiffs. They also claimed against the second defendant (“the architect”)
and the third defendant (“the engineer”) for damages in negligence. The
learned Judge found the builder liable for breach of contract but dismissed
the claim against the architect and the engineer with whom the plaintiffs had
no contractual relationship, the claim being for pure economic loss [Held by
Peh Swee Chin J (as he then was) that] .
The law of contract does not prevent action in the law of tort BUT the
obligations in tort CANNOT BE GREATER than those found in the contract.
ZULHABRI Ismail
Department of Building Page 33
CONSTRUCTION LAW
8.8 THE SAME ACT CAN GIVE RISE TO LIABILITY IN CONTRACT AND IN
TORT
• A person who buys a defective tool that causes him to lose his fingers
may sue the supplier for breach of contract, or the manufacturer for the
tort of negligence.
• Where there is an existing contract between employer and contractor /
builder or architect, the contract does not prevent the plaintiff obtaining
judgment also in tort.
• The plaintiff may sue for either breach of contract or negligence, or both,
but he cannot recover damages twice over [Res judicata / issue estoppel].
But not to sue the same party for the same reason for both contract and
tort.
• Res judicata / issue estoppel means a matter which has been adjudicated
on and the plaintiff may not bring a subsequent claim which involves re-
opening a matter already decided nor may a plaintiff bring a claim which
seeks some relief which was or should have been included in the claim
already decided.
General Principles
Damages or relief arising from any cause of action must be claimed once and
for all. It follows that any claim for damages whether in tort of for breach of
contract, must claim for all future anticipated loss, which will be assessed at
the date of hearing (Batty v Metropolitan Realisations [1978] QB 554).
ZULHABRI Ismail
Department of Building Page 34
CONSTRUCTION LAW
Not apply where the plaintiff is forced to accept the risk [Smith v Baker
(1891) AC 325] for instance in sporting situation if physical harm is likely i.e.
rugby [Simms v Leigh RFC [1969] 2 All ER 923; and football Condo v Basi
[1985] 2 All ER 453].
Volenti failed in the case because worker was given no proper warning of
when the crane was in use and so was unaware of the danger. He was aware
of risk of stones falling, but there was no voluntary assumption of risk in the
circumstances.
B. Inevitable accident
A defendant is never liable for a pure accident. Pure accident means one
beyond the defendant’s control for instance [Stanley v Powell (1891) 1 QB
86] someone has killed during a grouse shoot. It was shown that the man
was not shot directly. The bullet ricocheted off a tree before it hit him.
C. Act of God
In construction, concerns with extreme weather conditions. However, they
must he unforeseeable condition, not merely bad weather [Nicholls v
Marsland (1876)].
D. Common benefit
Dunne v North Western Gas Board [1964] 2 QB 806.
A gas main exploded without any negligence on the part of the Gas Board.
The Court doubted whether the Board had accumulated the gas for their own
benefit; it was for the benefit of the consumers and there was no liability.
ZULHABRI Ismail
Department of Building Page 35
CONSTRUCTION LAW
F. Fault of the plaintiff – the plaintiff responsible for the damage suffered.
9.1 SYNOPSIS
This lecture is continuation from the last lecture. Therefore, students should
remember what has been discussed earlier and make sense what will be
discussed in this lecture. This lecture will encompass the legal principles of
trespass, nuisance and strict liability or Rylands v Fletcher liability.
9.2 TRESPASS
Occurs where there is direct interference with the person, goods or land of
another. It is actionable per se i.e. there is no need to prove damage as a
consequence of the tort [actionable].
Types of trespass to the person: assault and battery and false imprisonment.
It is more usually dealt with under criminal law.
ZULHABRI Ismail
Department of Building Page 36
CONSTRUCTION LAW
It is no defence that the trespasser intended no harm or did not know that he
was trespassing, he must not violate any occupiers’ property rights.
The general rule is that the possessor of land also possesses the soil beneath
and the column of air above the land [section 5 and 44(1) of the NLC, 1965].
The latin phrase is Quicquid plantatur solo, solo cedit : whatever is affixed to
the soil, belongs to the soil.
Unauthorised entry below the surface of the plaintiff’s land at any depths will
also constitute a trespass.
ZULHABRI Ismail
Department of Building Page 37
CONSTRUCTION LAW
Thus tunneling through or digging into the subsoil below the plaintiff’s land is
actionable if such activity is carried out without the owner’s consent.
Minimal Disturbance?
As far as architects, engineers and building contractors are concerned, even
the slightest encroachment is actionable, however innocent the situation.
For instance, it is trespass in the case of building operations to allow any soil
disturbance, or anything to overhang or fall onto or be thrown over the land.
Contractor – a trespasser?
A contractor is said to have a license to be upon the site of the works. He
may become a trespasser if he remains on the land or leaves materials there
after his work is finished or after his employment has been determined.
ZULHABRI Ismail
Department of Building Page 38
CONSTRUCTION LAW
9.4 NUISANCE
Concerned with the protection of the reasonable use and enjoyment of land.
ZULHABRI Ismail
Department of Building Page 39
CONSTRUCTION LAW
Tate & Lyle Industries Ltd v Greater London Council [1983] 1 All ER 1159
The House of Lords characterised an interference with navigation rights in
the River Thames as physical damage, making it actionable public nuisance.
PRIVATE NUISANCE
• Is a civil wrong.
• It is committed when one person unlawfully interferes with the use or
enjoyment of another person’s land.
• The person suffering the harm is the owner or occupier.
• Not actionable per se.
• Actual damage must be proved.
• Interference will be unlawful only if it is unreasonable and substantial.
• It aims to balance the right of individuals to use their own land as they
wish with that of their neighbours who do not wish to be unreasonably
disturbed.
ZULHABRI Ismail
Department of Building Page 40
CONSTRUCTION LAW
ZULHABRI Ismail
Department of Building Page 41
CONSTRUCTION LAW
Here, following heavy rain, a large natural earth mound on a hillside slipped
and damaged the claimant’ cottage. The defendants were liable because
they were aware of the possibility of it happening and did nothing to prevent
it.
Page Motors Ltd v Epsom & Ewell Borough Council (1982) 80 LGR 337
Here, the council was liable in nuisance for failing to deal with gypsies who
camped out on council land and then interfered with the claimant’s business.
The local authority may serve an abatement notice on the person creating
the nuisance or, in some case, on the owner of the property from which the
nuisance originates.
ZULHABRI Ismail
Department of Building Page 42
CONSTRUCTION LAW
The Court found in favour of Fletcher and ordered Rylands to pay for all the
property damage to the mine.
The Court agreed that Rylands had a duty in maintaining the reservoir and of
being liable for all harm caused by it with broad scope of liability.
The large volumes of water were not naturally present in that form, but were
brought on to the land. Such a large volume or water could quite obviously
do damage if it escaped.
Lord Cairns identified that storage of water in these quantities did amount to
a non natural use of land. Finally , in the event, the water did escape through
the mineshafts causing considerable damage to the claimant.
Rylands in construction
Hoare v McAlpine (1923)
Where a contractor drove a large number of piles into soil and, due to the
vibrations produced, caused damaged to an old house belonging to the
plaintiff, the contractor was held liable, without proof of negligence.
ZULHABRI Ismail
Department of Building Page 43
CONSTRUCTION LAW
the respondent’s land. Some earth fell onto the respondent’s land and
damaged the respondent’s nursery.
The court held that the appellant used his land for a non-natural use and was
therefore liable under the rule in Rylands.
10.1 SYNOPSIS
ZULHABRI Ismail
Department of Building Page 44
CONSTRUCTION LAW
Negligence can be described as the breach of a legal duty to take care which
results in damage to the plaintiff.
It is not actionable per se, and therefore loss must be proved by the plaintiff
as a result of a breach of duty of care committed by the defendant.
Facts
The claimant claimed to suffer shock and gastroenteritis after drinking ginger
beer from an opaque bottle out of which a decomposing snail had fallen
when the dregs were poured. A friend had brought her the drink, so she
could not sue in contract. She claimed £500 from the manufacturer for his
negligence and was successful.
ZULHABRI Ismail
Department of Building Page 45
CONSTRUCTION LAW
Hedley Byrne & Co Ltd v Heller & Partners Ltd [1964] AC 465
In this case, the House of Lords recognised another duty situation. It was
held that a duty of care arises whenever a party reasonably relies upon
another to provide information or advice and the person providing the
information knows or ought to know that the inquirer is relying on him. In
such a situation, a negligent misstatement can give rise to an action in
negligence for damages.
ZULHABRI Ismail
Department of Building Page 46
CONSTRUCTION LAW
Held
It was held that the number of blind persons walking about the street alone
was sufficient to require the defendants to have them in contemplation and
to take precautions appropriate to their condition.
The CA held that, since the architect had led the contractor to rely on him
and ensure compliance with the by-laws, the contractor was entitled to
recover from the architect the damages that he had to pay the employer.
ZULHABRI Ismail
Department of Building Page 47
CONSTRUCTION LAW
It was held that the cricket club was not negligent. There was only a small
risk that the ball would be hit so far or cause injury if it did.
It was held by the House of Lords that the D was negligent. It owed a higher
standard of care to the plaintiff because of the increased seriousness of the
injury risked.
Precautions
Latimer v AEC (1952)
A flood has caused a factory floor to be greased-covered. Although the
employers did everything they could to get rid of the effects of the flood, the
plaintiff slipped and injured himself. The plaintiff argued that the factory
ought to have been closed because of the flood.
It was held that the company had not been negligent because the risk of
injury on that slippery floor was not sufficient to justify the closure.
It was held that the risk they took in an attempt to save life was held not to
be breach of the duty of care which they owed to the plaintiff.
ZULHABRI Ismail
Department of Building Page 48
CONSTRUCTION LAW
Hedley Byrne & Co Ltd v Heller & Partners Ltd [1964] AC 465
In Hedley, liability may arise where the negligent misstatement causes
economic loss (purely financial). The duty of care could exist on the
following:-
• There was a ‘special relationship’ based on an assumption of
responsibility between the parties.
• The plaintiff relied on the defendant’s skill and judgment.
P was not able to recover for the loss of profit on melts which could not take
place because of the power failure (pure economic loss).
ZULHABRI Ismail
Department of Building Page 49
CONSTRUCTION LAW
Section 12 of the Civil Law Act 1956 (Revised 1972) provides to the effect
that in a case of contributory negligence, the damages recoverable by the
plaintiff are to be reduced “to such extent as the court thinks just and
equitable having regard to the claimant’s share in the responsibility for the
damage”.
ZULHABRI Ismail
Department of Building Page 50
CONSTRUCTION LAW
Mersey Docks & Harbour Board v Coggins and Griffiths (Liverpool) Ltd [1947]
AC 1
A crane driver negligently damaged goods in the course of his work. The
Harbour Board hired him out to stevedores to act as their servant. The
Harbour Board was still liable for his negligence since he would not accept
control from the stevedores.
In Wheat v Lacon & Co Ltd, Lord Denning said that an “occupier” is a person
who has a sufficient degree of control over premises to put him under a duty
of care towards those who come lawfully upon the premises.
ZULHABRI Ismail
Department of Building Page 51
CONSTRUCTION LAW
Remedies
Two main remedies in tort:-
• Damages
• Injunction
11.0LAND LAW I
11.1 SYNOPSIS
• Torrens system
11.2OVERVIEW
11.3 INTRODUCTION
The land law of Malaysia are contained in four main pieces of legislation.
ZULHABRI Ismail
Department of Building Page 52
CONSTRUCTION LAW
2 The National Land Code (Penang and Malacce Titles) Act 1963.
11.5 LAND
The general rule is that the possessor of land also possesses the soil beneath
and the column of air above the land [section 5 and 44(1) of the NLC, 1965].
The latin phrase” Quicquid plantatur solo, solo cedit” meaning whatever is
affixed to the soil, belongs to the soil.
Definition of land
a) the surface of the earth and all substances forming that surface;
c) all vegetation and other natural products, whether for not requiring the
periodical application of labour to their production, and whether on or
below the surface;
ZULHABRI Ismail
Department of Building Page 53
CONSTRUCTION LAW
11.6 FIXTURE
Fixture is a real property and form part of land. The English law in Holland v
Hodgson (1872) provides two tests for establishing whether an item is a
fixture or a chattel:-
a. An objective test.
a. An objective test.
b. The inquiry is directed at the intention of the person who affixes the item.
ZULHABRI Ismail
Department of Building Page 54
CONSTRUCTION LAW
• On the sale of land, chattels may be removed but fixtures must be left for
the new owner.
Goh Chong Hin & Anor v The Consolidated Malay Rubber Estates Ltd
In April 1921 Goh Chong Hin (GCH) executed a charge in favour a money
lender (chargee) secured by a few pieces of rubber estate land. On June
1921, GCH executed a bill of sale assigning to the respondents certain
machinery in one of GCH’s factories which was charged. On October 1923,
the money lender (chargee) took possession of the rubber estate. On
December 1923, the respondent applied for an order to seize and sell the
machinery by virtue of his bill of sale. The chargee in possession opposed the
application.
The court held that, the ordinary English law of fixtures applies in this
country. It is well settled by that law that prima facie machinery affixed to
earth becomes a fixture and part of the land. Even if the machinery was set
up after the date of the charge, it nevertheless accrued to the land and
became part of the chargee’s security.
The appellants are the owner of holdings under which are constructed tanks
for the storage of petrol. The tanks are buried two feet below ground level
and covered with concrete. To remove them, the concrete has to be taken
up, the earth excavated, the concrete manhole boxes removed, all pipes
connections unbolted and the tank with its concrete sinker weights then
raised with blocks and tackle. The respondent, in determining the annual
value of the holdings, included the value attributable to the underground
storage tanks. On appeal, the appellants contended that the tanks did not
fall within the definition of “building” and as such could not be or form part of
“a holding” and were not rateable.
ZULHABRI Ismail
Department of Building Page 55
CONSTRUCTION LAW
The respondent contended that the tanks had become part of the land as
fixtures and as such were within the definition of “holding” and therefore
rateable.
It was held that the underground tanks are land within the definition of
“land” in the NLC 1965 as they are rateable.
It was held that the storage tanks were buildings, being structures connected
with platforms and pillars and was accordingly rateable. The storage tanks
were annexed to the land for its better use and enjoyment and formed part
of it and were accordingly rateable. The storage tanks enhanced the value of
the holdings on which they stood and as they were not machinery used for
industrial purposes under NLC, thus rateable.
Registration of land
Charged land which was not registered cannot be foreclosed; Sime Bank Bhd
v Mohd Hassan Sulaiman (2000). The effects of registration are defeasibility.
Section 340(1) states that “The title or interest of any person or body for the
time being registered as proprietor of any land, or in whose name any lease,
charge or easement is for the time being registered, shall, subject to the
following provisions of this section, be indefeasible.”
The fact that the register document of title was in the name of the appellant
was conclusive evidence that the title to the land was vested in the
appellant. Under the Torrens system, the register is everything and it
would be wrong to allow an investigation as to the right of the person to
appear upon the register when he holds the certificate of title.
ZULHABRI Ismail
Department of Building Page 56
CONSTRUCTION LAW
Fraud
In Tai Lee Finance Co Sdn Bhd v Official Assignee (1983), the court held that
fraud under S.340 of the NLC “must be actual fraud and mere knowledge of
the existence of an unregistered interest shall not of itself be imputed as
fraud within the meaning envisaged by section S.340.”
In Assets Co v Mere Roihi (1905) it was held that “fraud” means actual and
not constructive or equitable fraud on the part of the person whose title or
interest is being impeached. It must involve dishonesty of some sort
which was committed prior to or at the time registeration.
Misrepresentation
1. The suggestion as to a fact, of that which is not true by one who does
not believe it to be true;
Forgery
In Chew Lip Seng v Perwira Habib Bank (M) Bhd, the plaintiff granted a
declaration that the charge of the property of the defendant bank was not
executed by him and that the signature on the charge document was forgery.
The high court also ordered for the charge to be cancelled and the title of the
deed of the property returned to the plaintiff.
ZULHABRI Ismail
Department of Building Page 57
CONSTRUCTION LAW
12.1 SYNOPSIS
The purpose of this lecture is to discuss and make aware on the following
area :-
Alienation of land.
Form of title.
Condition of land.
Dealings.
Restraint of Dealing.
Definition
A. Freehold land
ZULHABRI Ismail
Department of Building Page 58
CONSTRUCTION LAW
B. Leasehold land
C. Tenancies
Freehold Land
Leasehold Land
Good security.
Tenancies
No security.
ZULHABRI Ismail
Department of Building Page 59
CONSTRUCTION LAW
Others
Final form of title under which lands are alienated after they have been
surveyed, whereby qualified title [hak milik sementara] for the purpose
to enable land to be alienated and to enable titles to be issued in the of sub-
division, partition or amalgamation lands in advance of the completion of a
survey.
All alienated lands are subject to conditions limiting them to one of the
following categories of land use:-
a. Agriculture
b. Building; and
c. Industry
The land designated for a prescribed land use cannot be used for any other
purpose unless there is a conversion of land use. Breach of condition of land
use shall result in the land being liable for forfeiture by the state.
12.4 DEALINGS
Transfers
ZULHABRI Ismail
Department of Building Page 60
CONSTRUCTION LAW
Section 214 of the NLC provides that the whole, but not part only, of any
alienated land; undivided share in alienated land; any charge; and tenancies
shall be capable of transfer.
Leases
The parties must have intended to create a lease and not a license,
evidenced by a written agreement or conduct.
Charges
Land is the most tangible form of security and its supply is inelastic. Land is
most sought after security by lenders whether they are :-
Chettiers [Goh Chong Hin & Anor v The Consolidated Malay Rubber
Estates Ltd ]
Finance companies.
Bankers.
The registration of charge confers upon the chargee a legal interest in the
land.
It was held that charge is an interest in land especially in view of the fact
that it renders the land liable as a security which the chargee could enforce
by way of the sale of the land in the event of default by the chargor.
ZULHABRI Ismail
Department of Building Page 61
CONSTRUCTION LAW
Liens
In Paramoo v Zeno Ltd (1968) is was held that the intention to create lien
may be gathered from the fact that the issue document of title to the land
is deposited with the lender as a security for the loan and for no other
purposes.
Easements
An easement under the NLC can only arise by way of express grant under
Section 284 of the NLC.
Section 283(1) of the NLC states that he rights capable of being granted as
easements are:-
(a) any right to do something in, over or upon the servient land; and
The rights do not include to take anything from the servient land or
right to the exclusive possession.
Essential characteristics
ZULHABRI Ismail
Department of Building Page 62
CONSTRUCTION LAW
12.5.1 CAVEATS
• The Latin cavere, means "warning" (or more literally, "let him beware").
Types of Caveat
Private Caveats
Trust Caveats
Lien-holder Caveats
Registrar’s Caveats
Private Caveats
Trust Caveats
ZULHABRI Ismail
Department of Building Page 63
CONSTRUCTION LAW
Lien-Holder's Caveats
May only lodge by a person with whom the document of title has been
deposited as security for a loan.
Registrar's Caveat
For persons who do not have any caveatable interest under the NLC.
For judgment creditors, they may obtain a prohibitory order for the
purpose of imposing restraint on dealings over land owned by the
judgment debtors.
REFERENCES
ZULHABRI Ismail
Department of Building Page 64
CONSTRUCTION LAW
Lee Mei Pheng (2005), General Principles of Malaysian Law, Penerbit Fajar
Bakti Sdb Bhd.
National Land Code (Act 56 of 1965) & Regulations, International Law Book
Services.
Salleh Buang (2001), The Malaysian Torrens System, Dewan Bahasa dan
Pustaka.
ZULHABRI Ismail
Department of Building Page 65