Acceptance Record Basic Function
Acceptance Record Basic Function
Acceptance Record Basic Function
Acceptance Record
Basic Functions
ZTE CORPORATION
Acceptance Record for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Basic Functions
1. Explanations
This Acceptance Record is written in accordance with YDN 065-1997
General Technical Specification Manual for for Telephone ZXJ10V10.0 MPT Switching (V03.03Eu)
Equipments,
Installation
Digital SPC Switching System, Maintenance Manual for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System, Operation Manual for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Volume I Data
Configuration & Management, Operation Manual for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Volume II Background
Operation & Management, Operation Manual for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Volume III OPR Console, Operation
Manual for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Volume V Billing. It contains test contents concerning data configuration, timer
configuration, alarm configuration and basic switchover functions during the project implementation or expansion, and is used for the acceptance of the ZXJ10V10.0 Digital SPC Switching System. In this Acceptance Record, each test item is numbered in the format: ItemSubitem- Test Content- Test Level. Test levels include Level A and B.
Caution: A: Mandatory items tested under the condition that the hardware environment is available B: Optional items tested only when required in the contract under the condition that the hardware environment is available The Test No. corresponds to that in the Test Acceptance Guide. For the test method, see Test Acceptance Guide for ZXJ10V10.0 (V03.03Eu)
Digital SPC Switching System Basic Functions. The Test No on each page
of the Test Acceptance Guide can be used as the index for a quick search for the relevant test method. If the actual acceptance contains items not included in this Record, acceptance should be performed according to relevant specifications. If necessary, you can record down the date of test, test person or other remarks in the Remarks column in this Acceptance Record.
-1-
Acceptance Record for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Basic Functions
Customer Personnel
-2-
Acceptance Record for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Basic Functions
Remarks
Customer: Date:
ZTE: Date:
-3-
Acceptance Record for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Basic Functions
3. Acceptance Records
Test No. System check 1-1-1-A 1-1-2-A 1-1-3-A 1-1-4-A 1-1-5-A 1-1-6-A 1-1-7-A 1-1-8-A Check of office data Check of physical configuration data Check of user data Check of trunk and route data Check of SS7 signaling data Check of V5 signaling data Check of alarm panel Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Test Content Test Result Conclusion Remarks
Test of operation & maintenance network 2-1-1-A Operating conditions of the network server Operating conditions of the 2-1-2-A OAM terminal and peripheral equipments 2-1-3-A 2-1-4-A 2-2-1-A 2-2-2-A 2-3-1-A 2-3-2-A 2-2-3-A Performance of LAN Frontend-background communication Add/modify/delete an operator type Add/modify/delete an operator Data backup Data recovery Maintenance report & log Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed
-4-
Acceptance Record for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Basic Functions
Test of warning functions 3-1-1-A Configuration of alarm panel The rack diagram should be able 3-1-2-A to reflect alarm information and alarm levels. 3-1-3-A 3-1-4-A 3-1-5-A 3-1-6-A 3-2-1-A 3-2-2-A 3-2-3-A 3-3-1-A 3-3-2-A 3-4-1-A 3-4-2-A 3-4-3-B Audible & visible alarm signals on the alarm panel Audible alarm signals on the alarm panel can be removed Alarm signals are removed once a failure is recovered Alarm information can be saved for later inquiry View current alarms View historical alarms View warnings Inhibit alarms based on the rack position Inhibit alarms by alarm type Enable/Disable infrared alarms (Periodically) Enable/Disable infrared alarms (At a Specified Time) Set temperature/humidity alarm range Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed
Hardware test- device switchover & reboot 4-1-1-A 4-1-2-A 4-1-3-A 4-1-4-A MP switchover & reboot DSN/DSNI reboot SP/SPI switchover & reboot FBI switchover & reboot switchover & Passed Failed Passed Failed Passed Failed Passed Failed
-5-
Acceptance Record for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Basic Functions
Hardware test- device switchover & reboot 4-1-5-A SYCK switchover & reboot Passed Failed
Test of Basic Call Processing Functions 5-1-1-A 5-1-2-A 5-1-3-A 5-1-4-A Intra-office calls Outgoing local, domestic and international toll calls Intra-office emergency calls Incoming local and Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed
long-distance calls Local tandem calls (incoming local, domestic, internationals calls) Domestic and international toll
5-1-5-A
5-1-6-A
5-1-7-A
Test of traffic statistics 6-1-1-A 6-2-1-A 6-2-2-A 6-2-3-A 6-2-4-A 6-2-5-A 6-3-1-A Statistical task maintenance & result Real-time statistics observation Real-time call observation Check of SS7 signaling link efficiency Display CPU usage Display status of common Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed
-6-
Acceptance Record for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Basic Functions
(Continued) Test No. Test of charging functions 7-1-1-A 7-1-2-A 7-1-3-A 7-1-4-A 7-1-5-A 7-1-6-A 7-1-7-A Settlement & summary based on multimetering and CDR Test of exception ticket conversion Test of resettlement ticket conversion Test of ticket inquiry Test of billing data backup, cleanup and recovery Test of ticket receiving Add/Delete a subscriber for billing observation Display 7-1-8-A subscribers for billing observation, display/delete CDRs of subscribers for billing observation 7-1-9-A 7-2-1-A Billing log management Check the billing accuracy via billing observation Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed Test Content Test Result Conclusion Remarks
Test of 112 Line Tester 8-1-1-A 8-1-2-A 8-1-3-A Accept user's complaints Designated subscriber line test Routine test Passed Failed Passed Failed Passed Failed
Test of Diagnostic Test 9-1-1-A 9-1-2-A 9-1-3-A 9-1-4-A 9-1-5-A Test of inter-module Passed Failed Passed Failed Passed Failed Passed Failed Passed Failed -7-
communication/voice channels Test of DSN Test of DTU Test of ASIG Test of communication links from units to MP
Acceptance Record for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Basic Functions
(Continued) Test No. 9-1-6-A Test Content Test of voice channels from units to TNet Test Result Conclusion Passed Failed Remarks
Test of trunk setup 10-1-1-A 10-1-2-A 10-1-3-A 10-2-1-A Trunks of available exchanges are normal View trunk circuit status Block/unblock trunk circuit Add/delete/modify a number in proper positions upon needs Passed Failed Passed Failed Passed Failed Passed Failed
-8-
Acceptance Record for ZXJ10V10.0 (V03.03Eu) Digital SPC Switching System Basic Functions
4. Conclusion
Explanations:
General conclusion:
Customer: Date:
ZTE: Date:
-9-