Tariq LNG
Tariq LNG
Tariq LNG
selection
Dr Tariq Shukri, Foster Wheeler, UK, discusses available LNG technologies and the important criteria for selection.
echnology selection starts at an early stage in the life of a baseload LNG project and is typically addressed at the feasibility study and pre-FEED definition stages. Process routes must be chosen for the process, utilities and offsite units of the plant, which include proprietary and nonproprietary technologies. This also applies to the upstream part of the chain, which supplies the gas to the plant. Potential options must be identified and evaluation criteria established. The selection could be between alternative processing technologies for the operating units, the type of major equipment, or utilities schemes. This article presents an overview of the LNG process and an introduction to the main processes available for the liquefaction section of a baseload LNG plant. It also discusses some selection issues relating to the main technologies that affect LNG plant configuration.
Liquefaction technology
The refrigeration and liquefaction section is the key element of the LNG plant. There are several licensed processes available with varying degrees of application and experience. There are others proposed or under development but are not considered here. The basic principles for cooling and liquefying the gas using refrigerants involve matching as closely as possible the cooling/heating curves of the process gas and the refrigerant. This results in a more efficient thermodynamic process requiring less power per unit of LNG produced. This applies to all liquefaction processes. Typical cooling curves are shown in Figure 2. However, the way this is achieved and the equipment used play a major part in the overall efficiency, operability, reliability and cost of the plant. The liquefaction section typically accounts for 30 - 40% of the capital cost of the overall plant. Key equipment items include the compressors used to circulate the refrigerants, the compressor drivers and the heat exchangers used to cool and liquefy the gas and exchange
parameter as it can be made either from pure or mixed components. With a mixed refrigerant the composition can be adjusted to suit the process conditions. The heat exchangers used, for example, the spiral/coil wound heat exchangers (CWHE) or the plate fin heat exchangers (PFHE), have very large surface areas and a large number of passes, enabling close temperature approaches. The main available liquefaction processes are described below. The MCRTM process will be described in greatest detail. Many of the principles apply to other processes. The main differences will be highlighted.
This process accounts for a very significant proportion of the worlds baseload LNG production capacity. Train capacities of up to 4.7 million tpy were built or are under construction. It is illustrated in Figure 3 as part of an overall LNG plant flow scheme. There are two main refrigerant cycles. The precooling cycle uses a pure component, propane. The liquefaction and sub-cooling cycle uses a mixed refrigerant (MR) made up of nitrogen, methane, ethane and propane. The precooling cycle uses propane at three or four pressure levels and can cool the process gas down to -40 C. It is also used to cool and partially liquefy the MR. The cooling is achieved in kettle-type exchangers with propane refrigerant boiling and evaporating in a pool on the shell side, and with the process streams flowing in immersed tube passes. A centrifugal compressor with side streams recovers the evaporated C3 streams and compresses the vapour to 15 - 25 bara to be condensed against water or air and recycled to the propane kettles. In the MR cycle, the partially liquefied refrigerant is separated into vapour and liquid streams that are used to liquefy and sub-cool the process stream from typically -35 C to between -150 C - -160 C. This is carried out in a proprietary spiral wound exchanger, the main cryogenic heat exchanger (MCHE). The MCHE consists of two or three tube bundles arranged in a vertical shell, with the process gas and refrigerants entering the tubes at the bottom which then flow upward under pressure. The process gas passes through all the bundles to emerge liquefied at the top. The liquid MR stream is extracted after the warm or middle bundle and is flashed across a Joule Thomson valve or hydraulic expander onto the shell side. It flows downwards and evaporates, providing the bulk of cooling for the lower bundles. The vapour MR stream passes to the top (cold bundle) and is liquefied and sub-cooled, and is flashed across a JT valve into the shell side over the top of the cold bundle. It flows downwards to provide the cooling duty for the top bundle and, after mixing with liquid MR, part of the duty for the lower bundles. The overall vaporised MR stream from the bottom of the MCHE is recovered and compressed by the MR compressor to 45 - 48 bara. It is cooled and partially liquefied first by water or air and then by the propane refrigerant, and recycled to the MCHE. In earlier plants all stages of the MR compression were normally centrifugal, however, in some recent plants axial compressors have been used for the LP stage and centrifugal for the HP stage. Recent plants use Frame 6 and/or
achieved in a cascade process using three pure component refrigerants; propane, ethylene and methane, each at two or three pressure levels. This is carried out in a series of brazed aluminium PFHEs arranged in vertical cold boxes. Precooling could be carried out in a core-in-kettle type exchanger. The refrigerants are circulated using centrifugal compressors. Each refrigerant has parallel compression trains. Frame 5 gas turbine drivers were used.
Pure component cascade process Air cooling (compared to sea water cooling) Fluid medium heating (compared to steam) Larger train capacity
Cons Proprietary/more expensive Require careful design to ensure good 2-phase flow distribution in multiple exchanger configurations Suitable only at high flow rates. Proven, efficient and cost Less reliable/strict effective maintenance cycle/ more complicated control /fixed speed Efficient, flexible & more Untried in LNG at speeds available needed/require large power plant. Simpler compression system. More complex operation. Adjusting composition allows process matching Potential higher availability More equipment and with parallel compression complicated compression system Lower cooling system Less efficient process CAPEX /higher operating costs Eliminates the need for Higher reboiler costs steam generation & water treatment Lower specific costs Some equipment/ (CAPEX per tonne LNG) processes may require further development
produce LNG, is not solely related to the thermodynamic efficiency of the liquefaction process but also to the efficiency of the main equipment such as the main refrigerant compressors and drivers. Site conditions may favour one type of process over another. For example, with very cold ambient temperatures multi-mixed refrigerant processes may offer the optimum solution. Process requirements and configuration will have an influence on selection. A requirement for greater LPG recovery may suit processes with lower precooling temperatures. Wider feed gas range will require better process adaptability and may favour mixed refrigerant processes with the added flexibility of changing refrigerant composition. Refrigerants made up from components that can be produced in the process (in the fractionation unit) will obviate the need for external supply to make up refrigerant losses.
Other processes
The above processes are used in current LNG plants or are applied in LNG projects in progress. There are other processes developed or in development for baseload LNG applications, which can be or are being considered in feasibility studies or for future projects but are not discussed here. The trend is to extend the capability of existing processes and develop new processes to support large LNG capacities of over 5 million tpy per train. Larger train capacities result in lower specific costs.
Equipment
All the main processes are licensed processes, and some also use proprietary equipment. The main spiral wound heat exchangers used by APCI and Linde are both proprietary. Tube leakage problems experienced previously with some designs of spiral wound exchangers have been addressed several years ago and minimised. The PFHEs used by some processes are non-proprietary and can be offered by different vendors. Installations on large capacity plants comprising multiple parallel exchangers require more careful design for two phase (vapour and liquid) flow conditions within the unit. Some other considerations for equipment selection are given in Table 1.
Process selection
Technology selection of process and equipment will be based on technical and economic considerations. Foster Wheeler has carried out selection studies as part of major LNG projects and proposals during the various phases of feasibility, FEED and detailed engineering. In addition to an extensive in-house LNG database, contacts are made with the liquefaction licensors and main equipment vendors to obtain data and develop designs to enable valid comparisons and optimum selections. Depending on the stage of project development, sufficient process details must be developed to define main equipment and operating parameters to evaluate options using relevant criteria. Technical considerations include process and equipment experience, reliability, process efficiency, site conditions and environmental impact. Economic issues include capital cost, operating cost and lifecycle costing. All of these aspects will need to be evaluated to arrive at the optimum solution. Technical risks associated with a process relate to the track record of the process in operation, and any developments required for the project for example, capacity increase. Process efficiency, for example, energy required to
Other selections
Another important area is deciding the heating and cooling media types as they directly impact process and equipment. Cooling medium is normally a choice between air and water in a direct or indirect system. For the heating medium, steam or hot oil systems can be considered. For example a selection of air for cooling, oil for heating and gas turbine drivers eliminates the need for a steam generation system including water treatment, and a cooling water system which may include a costly seawater intake. The above criteria are typical of the main issues that must be considered when selecting the technology for an LNG plant.