Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Supervision Guide For Electrical Engineering Works (30 Jan 2012)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 37

SUPERVISION GUIDE

For Electrical Engineering Works

Jan 2012 Edition

architectural I civil I electrical I mechanical I structural

Contents

Introduction

Pg 1

Material Selection

Pg 2

Timber Mock-Up

Pg 4

Sample Units

Pg 7

HDB Requirements

Pg 9

In-Process Checking

Pg 12

Good Practices / Common Defects

Pg 15

Inspection, Testing and Handover Annex HDB Forms for Audit Tests

Pg 24

Pg 28

HDB shall not be responsible for any errors or omission in this supervision guide. No reproduction of any part of this guide is allowed without the explicit approval of HDB. Jan 2012 Housing & Development Board

Jan 2012 Housing & Development Board

Introduction

This book serves to guide our Consultants in supervising electrical engineering works for new HDB development projects. HDBs general requirements and some examples cited are only for reference purposes. The Consultants shall develop their own comprehensive supervision system and specific checklists/forms for each project. The Consultant shall submit the following to HDB Project Director according to the proposed timeline to ensure timely completion of works: S/n 1 2 3 4 5 Description QPs responsibility in checking different stages of works Inspection forms for electrical engineering works for Site Supervisors Material selection and testing Workshop drawings Instructions and records Upon resolution of each item / issue * Timeline Before start of Contract Before work starts

* HDB Project Director is to be consulted on the issues in advance if necessary.

Jan 2012 Housing & Development Board

Material Selection

Material List A wide selection of products which have met HDBs requirements are found in the HDB Material List. The list serves to help Consultants choose products with good track records in quality and reliability for use in HDB Residential Housing. The HDB Material List can be viewed from the web address: http://ml.eptc.sg. The HDB Material List includes accessories, cables, circuit breaker, consumer control unit, fire alarm system, isolator, lightning protection system, luminaries, mechanical control system and switchgear equipment. Consultants may also propose products which are not in HDB Material List. However, these products are subject to HDBs concurrence and must meet the specified performance / quality criteria. Approval of Material The Consultant shall approve all electrical material samples as specified in the Contract before setting up of timber mock up and sample units. Before approving any product, the Consultant must ensure that it conforms to Specifications and Drawings, the relevant Code of Practice and any other statutory requirements. The approved samples must bear the Consultants endorsement and be displayed in the site offices sample display room for verification against those installed on site. The Consultant shall supervise and ensure all electrical fittings are carried out with the approved material and using approved installation methods.

Jan 2012 Housing & Development Board

Material Testing The Consultant shall randomly select material listed in Schedule of Material Tests at the site for testing in a timely manner. Selected samples are to be marked for identification before sending to the relevant test laboratory. The test laboratory must be accredited for the test in question. The tests are to ascertain that the material complies with the performance standard stated in the Specifications. All test results must be reviewed by the Consultant. If there is a test failure, Consultant must inform HDB immediately and follow up with a re-test at no additional cost to HDB. If the re-test fails, Consultant shall recommend follow-up actions for HDBs concurrence.

Jan 2012 Housing & Development Board

Timber Mock-Up

Purpose With the extensive use of precast components in HDB residential building, it is important to provide timber mock-ups on site at the beginning of construction. This allows adjustments to be made to the workshop drawings before precast production and thus prevents abortive works. Problems related to design, maintenance and practicality of the proposed layout could also be addressed during the timber mock-up inspection. The mock-up is to be constructed accurately to scale. The mock-up should show the proposed locations of sanitary pipes and electrical points in the kitchen, toilets, air-con ledge and service yard so that openings and recesses for concealed services could be confirmed.

Some common issues to look out for are: a) b) c) d) e) f) floor waste/trap not obstructed by structural beam; lighting points not obstructed by ceiling-mounted clothes drying rack; use of external clothes drying rack not hindered by air-con ledge; sufficient clearance for access to the air-con ledge for installation and maintenance of the air-con compressors; toilet vent and other fittings do not obstruct future installation of shower screen; and any other practical considerations.

Timeline to Construct The Consultant shall ensure that the Contractor erects the timber mock-up for each unit type within three months from the start of the Contract.

Inspection

The Consultant shall inspect and verify the position of all electrical provisions before approving the precast drawings.

Jan 2012 Housing & Development Board

The following are some of the items to be checked by the Consultant: a) The switch socket outlets and switches are to be provided according to drawings and located in suitable positions. Provision of the water heater point should be close to the proposed location of the storage heater.

b)

Water heater point


Proposed location of storage heater

Concealed Pipes : Blue : Cold water Black : Overflow discharge Red : Hot water

Jan 2012 Housing & Development Board

c)

The location of the switch socket outlet, bib tap and discharge point shall be coordinated for the placement of washing machine in the service yard.

Bib tap 1050mm from finished floor level (FFL) Switch socket outlet with splash proof cover 1200mm from FFL Min. 650mm wide Discharge point

Jan 2012 Housing & Development Board

Sample Units

Purpose Sample units are set up to ensure that the position, height and quantity of electrical accessories are constructed according to specifications, drawings and sales brochure before mass production. In the event of discrepancies between drawings and sales brochures, the latter will take precedence. The sample units would also serve as a reference for workmanship standard.

Timeline for Setting Up Construction of the sample units should commence when structural work reaches the 5th storey and be completed within two to three months. A sample unit is to be provided for each flat type and approved by Consultant with HDB PD concurrence.

Sample Finishes

Switches should be positioned away from the edge of walls to avoid causing wall cracks.

Min. 100mm

Jan 2012 Housing & Development Board

The height of the switch socket outlets at the living room / bedrooms should be 450mm from the finished floor level (FFL), measured from the centre line of the socket outlets. Exceptions are at the kitchen and service yard where the height of switch socket outlets should not exceed 1200mm.

Correct height of switch socket outlets at living room / bedrooms

450mm from FFL

The heater switch should be positioned beside the light switches to the bathroom for ease of operation.

Heater switch at wrong position

Light switches

Jan 2012 Housing & Development Board

HDB Requirements

Location of Embedded Conduit inside the Flats To facilitate the drilling of walls in a safe manner, residents will be given a No drill zone notice, informing them of the typical routing of embedded conduits within walls. The Consultant must pay special attention to ensure that the running of these embedded conduits in walls comply with the No drill zone.

No Drill Zone
For walls, flat owners are not allowed to drill any holes within 150mm bandwidth vertically above and below, and 150mm bandwidth horizontally to the left and right of electrical accessories such as socket outlets, lighting switches and heater points. For areas with more than one accessory mounted together, the horizontal bandwidth, (annotated *D in the diagram below) should be 150mm multiplied by the number of electrical accessories. For ceilings, drilling for the mounting of light fittings, ceiling fans, etc must not exceed 40mm in depth.

Jan 2012 Housing & Development Board

Running conduits at an angle is prohibited as part of the embedded conduits would be outside the protected no drill zone.

Embedded conduit outside no drill zone

Down Conductor of Lightning Protection System HDB uses aluminium lightning tape on the roof top and aluminium down conductor on the surface of external wall/column. The aluminium down conductor is connected to the copper tape using bi-metallic aluminium/copper connector at a height of 2.5m. In areas which are accessible to the public, the copper tape shall be embedded to prevent theft.

Copper tape embedded at area accessible by the public

Jan 2012 Housing & Development Board

10

TV System All distribution amplifiers are to be properly secured with locking device and engraved with serial number. All tee units in the telecom riser and distribution amplifiers are to be sprayed with paint to prevent theft.

Earth System
For every earth inspection pit, the Consultant should ensure information such as block number, street name, type of earthing, value of earth, earthing point number (e.g. 1 of 2) and date of testing are engraved on a durable identification tag. The tag is to be fixed on top of the earth inspection pit below the cover. The tag must remain visible after the inspection pit is filled with sand.

Identification tag

Jan 2012 Housing & Development Board

11

6 In-Process Checking
Purpose The Consultant needs to monitor and control the quality and finish of the electrical installations. Before work proceeds, the Consultant shall verify that the electrical sub-contractor is registered by BCA as minimum L2 grade contractor and also registered by IES/ACES as Qualified Electrical Contractor.

It is important to check for irregularities while the works are in progress to ensure works are carried out by qualified workers according to approved work method, specifications, drawings and sample unit.

Inspection by Consultant The Consultant shall ensure that the following are checked before proceeding to next stage of work: The following are some of the items to be checked by the Consultant: a) b) c) d) Embedded conduit routing at 2nd storey floor slab; Metal trunking at 1st storey ceiling; Lightning Protection System down-conductor locations; Coordinate service layout of the M&E services at the roof.

The Consultant shall visit the sites to check that all electrical installations are installed correctly. This will ensure that non-conformances are detected early and reduce rectification or abortive works.

Checklist The scope for Site Supervisors / Registered Technical Officers encompasses supervision of multiple trades as well as safety, and housekeeping. They are usually not specialised in M&E works, hence it is important for the Consultant to guide them closely in the supervision of electrical installation works. The Consultant shall develop their own checklists for the project and train the Site Supervisors to check on critical work including but not restricted to the following:

Jan 2012 Housing & Development Board

12

S/n (a)

Critical Items to be included in Checklist Ground Floor to 3rd Storey Check and ensure that the locations of electrical fittings in the sample unit and access corridor are correct. Check and verify critical structural dimension of the lift shaft. Typical Storey Check and ensure that the locations of electrical fittings in the units and access corridor are correct. Check that the correct light fittings are used at common areas and positioned correctly to provide the required lighting distribution. Check for natural lighting at areas blocked by the lift shaft / staircase core / central rubbish chute, during downcast weather. If necessary, Consultant is to provide photocell circuit control to automatically light up areas which are affected by downcast weather to achieve the minimum average lighting level as shown below:
Item a b c d e Area 1st storey area 1st storey lift lobby Upper storey access corridor Upper storey lift lobby Stairway Min. Ave. Lighting Level (Lux) 30 80 15 40 30

(b)

(c)

Roof Check and verify the location of the air terminal of Lightning Protection System is correct. Site Work and Landscape Check and verify that the lighting level on the service road and footpath meets the minimum of 10 lux. Check and ensure that the location of the lamp post meets the design guideline. Check to ensure that the outdoor lights do not shine into the windows of lower floor units.

(d)

The inspection records shall be monitored until all items are properly closed and endorsed by the Consultant.
Jan 2012 Housing & Development Board

13

Audits by HDB HDB may carry out audits on the electrical installation. The Consultant shall respond to HDBs audit within two weeks. The Consultant shall not rely on HDBs audit but carry out their own regular audits to ensure the quality of the electrical installations.

CONQUAS M&E installation work forms part of the assessment in Construction Quality Assessment System (CONQUAS) by BCA. For public housing, the M&E score constitutes 5% of total score. The Consultant shall ensure that the finishes of the electrical installations are of high workmanship and quality; fittings properly aligned. No stain marks and visible damages / defects shall be found at the switches, socket outlets and Consumers Control Unit (CCU).

Jan 2012 Housing & Development Board

14

Good Practices / Common Defects

Electrical Conduits Care must be taken to ensure that embedded conduits are properly supported, with no ingress of water. The embedded conduits are to be gradually bent with not more than two 90 bends between two points. This is to allow subsequent pulling of cable through the embedded conduit.

There shall only be a maximum of 2 overlapping conduits so that concrete cover would be sufficient. Proper conduit accessories are to be used.

Max. of 2 overlapping conduits

Proper extension box for lighting point area

Jan 2012 Housing & Development Board

15

For recesses in the precast wall, Consultant shall ensure that the conduit up-turn is aligned properly with the recess.

In addition, all concealed cabling must be properly protected in conduit or trunking.

Jan 2012 Housing & Development Board

16

The Consultant shall also inspect the concrete cover for the embedded conduit. Galvanised iron (GI) pipes are to be used if the concrete cover is less than 50mm thick.

Inadequate cover for PVC conduit

GI conduit used for concrete cover that is less than 50mm

Consultant can consider casting the socket outlets separately to ensure that the socket outlets are in level position first before erecting the brick wall. This will contribute to better quality by reducing hacking of the brick wall later for the installation of conduits.

Jan 2012 Housing & Development Board

17

The recesses on concrete block walls shall not be created by hacking. It can be created by purpose-made building blocks as illustrated below: U & L-shaped blocks to form vertical recess; U-shaped block to form horizontal recess; and I-shaped block to form horizontal recesses for both sides of the wall.

U & L

Untidy recess created by hacking

Jan 2012 Housing & Development Board

18

Other than pre-shaped concrete blocks, Contractor is also encouraged to use special Ferrolite panels to increase productivity and minimise hacking: (a) Ferrolite panels with built-in recesses for electrical fittings and concealed electrical conduits :

Recess for conduits and light switch at 1200mm from FFL

Recess for conduits and switch socket outlets at 450mm from FFL

(b)

Small Ferrolite infill panel for consistency in material.

Small Ferrolite panel for infill wall

Jan 2012 Housing & Development Board

19

Separation of Electrical and Data Outlets There are instances where the switch socket outlet and TV / Telephone outlet are next to one another. Proper segregation should be maintained between the two to prevent interference.

Proper separation of outlets

Insufficient separation between outlets

Jan 2012 Housing & Development Board

20

Arrangement of SP PowerGrid (SPPG) Meter Box Where two or more residential units share an electrical riser, the Consultant shall ensure that the meter boxes are positioned properly for easy identification by the respective owners.

Location of Consumers Control Unit (CCU) The Consultant shall ensure that the CCU is positioned away from the main door so that the latter will not hit the CCU when it is fully opened.

Door hits CCU when fully opened

Jan 2012 Housing & Development Board

21

Lightning Protection System The Consultant shall check the location of the aluminium air terminal of the Lightning Protection System and ensure that they are located appropriately with consideration of the ladder or railing installed at the roof.

The Consultant shall take precaution to ensure running of lightning conductors on roof features will not result in re-entrant loop as shown below:

Jan 2012 Housing & Development Board

22

In a situation where re-entrant loop occurs, the Consultant may consider closing of the open side of the loop as illustrated below.

Provision for Future Electronic Parking System HDB may implement Electronic Parking System (EPS) near the ingress/egress of the precinct in future. The Consultant is to ensure that underground pipes are provided at the correct locations to meet HDB Car Parks Sections requirements. This is to avoid future hacking of the road/slabs. UPVC pipes with draw-wire is only required at road and slab crossings leading to the proposed EPS locations. The pipes should terminate with sealed capping above the slab. They are not required at turfed areas and within the MSCP compound as the future cabling will be surface-mounted for routing within the building.

Jan 2012 Housing & Development Board

23

Inspection, Testing and Handover

Introduction On completion of the electrical installations, the Consultant shall carry out appropriate tests and inspections to verify that the electrical installations meet all requirements of relevant codes and Technical Specifications. The Consultant shall commission the electrical services one month before the handover of each block / precinct.

Tests by HDB Before the block can be considered complete, the Consultant shall arrange with our Technical Management (M&E) team for the following tests: a) Tests related to Wiring Regulation b) Residential Unit Wiring (100% Test) Main Switchboard (Audit Testing) Public Lighting Circuit (Audit Testing) Outdoor Lighting Circuit (Audit Testing)

Others (Audit Testing) Lightning Protection System Alert Alarm System TV System Telecom Wiring

Please refer to the flowchart on the following page for procedures on testing and seeking clearances for M&E Works.

Jan 2012 Housing & Development Board

24

Audit Test & Completion Clearance for M&E Works


Start

Contractor
1. Check and test the completed M&E work and submit test report to Consultant. 2. Arrange with Consultant to inspect and test the completed work.

Consultant
1. Verify, inspect and test the completed work. 2. Check and endorse test report and submit to TM(M&E) with necessary documents and certificates.
HDB-TMME-IC Form Not in order

TM(M&E)
Check form
In order

TM(M&E)
Conduct audit?
Yes

No

TM(M&E)
1. Give test date to Consultant and Contractor. 2. Conduct audit check / testing of the completed work on appointment date. 3. Send audit report to Consultant and HDB PD highlighting serious defects for action.
HDB-TMME-AF Form

Consultant
1. Ensure all defects are rectified. 2. Inform TM(M&E) on date of completion of defects rectification. 3. Recommend to HDB PD to impose demerit points on Contractor for serious defects.
HDB-TMME-AR Form

TM (M&E)
Issue M&E completion clearance to HDB PD for handover.

End
Jan 2012 Housing & Development Board

25

Submissions to HDB The application for HDB audit test shall be made at least one month before the handover of each phase. The following prescribed forms shall be used for HDB audit tests: Item a b c d e f HDB Forms HDB-TMME-IC HDB-TMME-AD HDB-TMME-AF HDB-TMME-AR HDB-TMME-CC(ND) HDB-TMMECC(NDPW) Description of Forms Declaration of completion of M&E works Appointment for M&E audit testing / electrical unit testing M&E audit test report M&E audit test report reply Completion clearance of M&E services Completion clearance of M&E Services for precinct work only Used By Consultant HDB HDB Consultant HDB HDB

The above forms are enclosed in the Annex for your reference. The latest forms and sample HDB test reports can be obtained from HDB Technical Management (M&E).

Jan 2012 Housing & Development Board

26

The following Certificates and Test Reports are also to be included with the application for audit tests:

S/n a

Item Residential Unit

Forms Certificate of Fitness of Residential Unit / Certificate of Compliance by LEW Unit Wiring Test Report by LEW

b c d e f

Main Switchboard Public Lighting Lightning Protection Outdoor Lighting TV System

Test Report by LEW Test Report by LEW Test Report by LEW Test Report by LEW Test Report by PE

All g formsTelecommunication and Certificates of Supervision by PE/LEW submitted to other authorities Test Report by Licensed Installer shall also be submitted together with the above where applicable. h Alert Alarm System Test Report by PE

Other Considerations Unlike private projects, HDB projects are generally handed over on block by block basis. The Consultants must ensure that Temporary Occupation Permit is obtained and the block has passed the employers inspection before certifying completion for the block. Electricity supply to ESS should be energized at least four months before first block is handed over. The Consultant shall provide HDB the information to call quotation for the Registered Inspector for Mechanical & Electrical Fire Safety Works six months before the first block handover. TV system for the block shall be verified by SCV for takeover, activation and maintenance before handing over of the block.

Jan 2012 Housing & Development Board

27

Annex : Forms for HDB Audit Tests


HDB TMME IC (Pg 1/2)
HDB-TMME-IC

DECLARATION OF COMPLETION OF M&E WORKS


Deputy Director, Development & Construction Productivity Section 3 (Technical Management M&E) Building Quality Group Housing & Development Board HDB Hub, West Wing, 15th Storey 480 Lorong 6 Toa Payoh Singapore 310480 Block No.: Contract Title: Main Contractor Name: Contractor Rep: Contact Tel. no./HP: A Completion of M&E Works Address: Instructions: 1. Fill in where applicable. 2. * Delete if not applicable.

Fax: 68543208 Project Ref. No.:

I/We declare the M&E works ticked have been completed and tested satisfactorily. Relevant test reports, certificates and drawings are enclosed. Tick if applicable System/Service Installation drawings enclosed Checklists enclosed Test reports & certs enclosed PE: PE: PE: PE: PE: PE: PE: Section II: Mechanical Services Water Supply System Gas Supply System Sanitary System / Ejector Pump * Refuse Handling Equipment Submersible Pump For Rainwater Others (please specify) Section III: Electrical Services Unit Wiring MATV Telecom Wiring Electrical Installation (i) Main Switchboard (ii) Public Lighting (iii) Outdoor Lighting (iv) Exit / Emergency Lighting Standby Generator Lightning Protection System Intruder Alarm / Integrated Security System Others (please specify) B Application for inspection and clearance by Technical Management (M&E) Section I/We declare that the above works are ready for inspection and clearance by Technical Management (M&E) Section. Confirmation by Main Contractor: Verified by Consultant PE: LEW: PE: LEW: LEW: Remarks

Section I: Systems related to Fire Safety Automatic/Manual Fire Alarm System * Dry Rising Main / Down Comer / Wet Rising Main System * Hose Reel System Sprinkler System Mechanical Ventilation / AirConditioning System * Smoke Control / Smoke Purging / Fume Extract / Pressurization System * Lift / Escalator Installation *

Signed by: ___________________________________________ Name: Date: ___________________________________________ ___________________________________________

Signed by: ___________________________________________ Name: Date: ___________________________________________ ___________________________________________

Form HDB-TMME-IC Feb12

Jan 2012 Housing & Development Board

28

Annex : Forms for HDB Audit Tests


HDB TMME IC (Pg 2/2)
HDB-TMME-IC

Addendum to Declaration of Completion of M&E Works Please provide and fill in the following details to facilitate correspondence Contract Title: Block No: Block OCD: Type of Project : NT / D&B / MUP / HIP / RUP / HUP / IPD / PLD / SPT * (e.g. Large Commercial premises) Street Name: Block PACD: Email: HDB PD/Officer-in-charge Contact no. Main Contractor: Rep. name: Subcontractor: Rep. name: Design LEW name: Licence No.: Licensing LEW name: Licence No.: Licensing Telecom Installers name: Licence No.: Consultant Project Manager-in-charge: Email: Contact no. Email: Contact no. Email: Contact no. Email: Contact no. Email: Contact no. Email: Contact no. Email: Contact no.

Consultant Engineer-in-charge:

Notes on declaration of completion of M&E work and appointment for audit testing and unit wiring testing 1 2 3 4 5 6 7 8 9 10 11 12 13 Consultant is satisfied that the works have been satisfactory completed by Contractor when submitting the declaration. Consultant has also inspected and tested the works and is satisfied that the works completed have complied to HDB and all statutory requirements. All test reports and certificates submitted are in order and have been verified and endorsed by Consultant. Consultant confirm the works have been installed according to installed drawings provided. Contractor have rectified all defects pointed by Consultant before HDB audits and if defects are not rectifed during HDB audits, Consultant would recommend to impose demerit points on the Contractor. For any serious defects affecting safety detected by Consultant or HDB audit, Contractor would be liable for demerit points to be imposed. Consultant shall ensure all defects are not repeated and shall be rectified within 3 days. Consultant shall inform HDB when defects have been rectifed to obtain HDB clearance. Consultant shall report recalcitrant LEW to EMA for committing serious defects on electrical safety. Contractor shall provide qualified assistants to receive instruction during HDB audits. HDB audit would be considered fail if no assistant is present and Consultant shall recommend to impose demerit points on the Contractor. For unit wiring testing, Contractor shall provide at least four assistants for HDB to conduct unit wiring testings. COC, form CS/5 and Form E and single line drawings shall be submitted to HDB before the unit wiring testing. Appointment with HDB to audit the completed work or test unit wiring the work can be made with TM(M&E), HDB by phone (Tel. 64903163) or personally between 2 pm to 4 pm at HDB Hub, West Wing at 17 th storey. Any cancellation of audit/test appointment shall be made at least one day in advance, otherwise Consultant will recommend demerit points to be imposed on Contractor for no show. If testing requires shutdown of supply, Contractor shall provide confirmed copy of shutdown date/time at least one day before the testing appointment to be faxed to TM(M&E), HDB.

Form HDB-TMME-IC Feb12

Jan 2012 Housing & Development Board

29

Annex : Forms for HDB Audit Tests


HDB TMME AD
Appointment for M&E Audit Testing / Electrical Unit Testing
To: Consultant Engineer-in-charge Consultant Project Manager Contractor HDB-TMME-AD

Copy to: HDB PD/Officer-in-charge

Based on your declaration of completion of the M&E work, appointment has been made to audit test the following M&E system on the date and time as stated below. Please arrange for Contractor to provide the approved as-installed drawings and manpower to be present to receive instructions during the audit testing.

Contract Title: Address: Block No.: Type of Installation MSB * Unit wiring * PL / FSC / LPS * OLS / ESS * SUBMAIN EXTENSION * Other services (Pls. State) * Fire safety system (Pls. State)* Mechanical services (Pls. State)* Block No. Date & Time of Appointment Postal Code: Remark

Officer Name Date Development & Construction Productivity Section 3 (Technical Management M&E) Tel. no.: 64903163

Note: * Delete where necessary MSB Main Switchboard, PL Public Lighting, FSC Final Sub-Circuit, LPS Lightning Protection System, OLS Outdoor Lighting System

Jan 2012 Housing & Development Board

30

Annex : Forms for HDB Audit Tests


HDB TMME AF
HDB-TMME-AF

HOUSING & DEVELOPMENT BOARD BUILDING QUALITY GROUP M & E AUDIT TEST REPORT CONTRACT TITLE: BLOCK: MAIN CONTRACTOR: STREET NAME: CONTRACTORS REP. NAME:

To : Consultant : _____________________________ Thru Project Mgr : _______________________

Attn :

______________________________

1.The audit test for ______________________________________, has been carried out on ____________ 2. The findings are listed below :

3. The audit test is passed/failed/pending verification. 4. Please follow-up on the items listed above and reply to us using TMME-AR form by __________________. Note: For items not installed according to the contracts, please follow-up if RVO is necessary. For serious defective work, please warn the contractor and recommend to impose demerit points if necessary.

_______________________________ Building Quality Group _____________________________

Date:______________________________ cc PD

Development & Construction Productivity Section 3 (Technical Management M&E)

Note : All the rectification details and dates must be stated clearly on your reply in TMME-AR form

Jan 2012 Housing & Development Board

31

Annex : Forms for HDB Audit Tests


HDB TMME AR
HDB-TMME-AR Your Ref : Our Ref : Date : TEL (DID) : EMAIL :

Building Quality Group Development & Construction Productivity Section 3 (Technical Management M&E) Attn: __________________________ Dear Sir M&E AUDIT TEST REPORT REPLY Contract Title: Block: Type of installation: Street Name: Contractor:

1 2

Please refer to your audit test report dated ______________. This is to inform you that the following items listed in the audit test report have been approved/rectified (i) Modifications (item(s) ________________________) have been approved and updated in drawings. RVO is / is not* required. Modifications (item(s) _________________________) have not been approved and were rectified on _________ (Date). Defects (item(s) _____________________________) have been rectified on ____________ (Date).

(ii)

(iii)

3.

We will / will not* be taking the following action: (i) (ii) Contractor will be warned not to repeat the defects. PD will be recommended to impose demerit points.

Remarks: _____________________________________________________________ _____________________________________________________________ Yours faithfully

Name & Designation Consultant Name * delete where not applicable tick if applicable

cc Project Manager : cc Project Director (HDB):

Jan 2012 Housing & Development Board

32

Annex : Forms for HDB Audit Tests


HDB TMME CC(ND)
Your Ref : Our Ref Date Project Director: ____________________ Dept: ____________________________ Tel Fax : 452-20-22-0314 : : : 68543208
HDB-TMM&E-CC(ND)

Completion Clearance of Mechanical & Electrical Services Contract : ______________________________________ Blk No : ______________

S/N

System

Testing/ Status Audit Check

Remarks

Date of Report Submitted

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Units Main Switch Board Public Lighting System (Excluding Linkway system) Lightning Protection System Final Sub-Circuit (Excluding Linkway system) Telecom TV System Lift Transfer Pumping System Booster Pumping System Refuse Chute Flushing System Refuse Handling Equipment Rain Water Sump Pump Ejector System Dry/Wet Rising Main System Manual/Automatic Fire Alarm System Automatic Sprinkler Protection System Hose Reel System Mechanical Ventilation System Others (R.I.s Form : NA/Submitted)

YUE WENG KWONG Principal Technical Officer Development & Construction Productivity Section 3 (Technical Management M&E) Building Quality Group

cc PE Er Soh Swee Seng SE Rajasararan s/o Lechimanah PE Er Denis Wong Attn:

(Name of Consultant)

Note : Test/Audit Check X No Test/Audit Check NA Not Applicable

Jan 2012 Housing & Development Board

33

Annex : Forms for HDB Audit Tests


HDB TMME CC(NDPW)
HDB-TMM&E-CC(NDPW)

Your Ref : Our Ref Date Project Director: _________________________ Dept: _________________________________ Tel Fax : 452-20-22-0314 : : : 68543208

Completion Clearance of Mechanical & Electrical Services (For Precinct Work only)

Contract : ______________________________________ Blk No : __________

S/N

System

Testing/ Status Audit Check

Remarks

Date of Report Submitted

1 2 3

Linkway Lighting Outdoor Lighting Others

YUE WENG KWONG Principal Technical Officer Development & Construction Productivity Section 3 (Technical Management M&E) Building Quality Group Note : Test/Audit Check X No Test/Audit Check NA Not Applicable

cc PE Er Soh Swee Seng PE Er Denis Wong Attn:

(Name of Consultant)

Jan 2012 Housing & Development Board

34

Together, we provide excellent project management to deliver quality homes in a sustainable environment.
Dr Johnny Wong, Er. Director (Building Quality), HDB

Jan 2012 Edition

You might also like