Cost Estimate
Cost Estimate
Cost Estimate
ON-SITE
Sitework
Clear & Grub & Destump 20 ac $6,000 $118,200
Cut Onsite (but reused) cy $3 $0
Fill from On-site (from cut) cy $4 $0
Fill (from off-site) cy $10 $0
Rock Excavation cy $50 $0
Rough Grade sy $2 $0
Erosion Control 2,486 lf $4 $9,944
Utilities
Trench Rock Excavation cy $100 $0
Double Catch-Basin ea $2,200 $0
Regular Catch-Basin 51 ea $1,350 $68,850
Drainage Manhole 45 ea $1,350 $60,750
Stormceptor 5 ea $10,000 $50,000
12" CPP 2,109 ft $20 $42,180
15" CPP 961 ft $22 $21,142
18" CPP 362 ft $25 $9,050
21" CPP ft $28 $0
24" CPP 388 ft $30 $11,640
30" CPP 623 ft $35 $21,805
Basin fencing 1,255 ft $15 $18,825
Basin Outlet Structures 2 ea $2,500 $5,000
Miscellaneous
Landscaping 1 allow $200,000 $200,000
Ret. Wall (modular) sf $22 $0
Guardrail 2,456 lf $10 $24,560
P/8000/8852/17528028.xls
Fairfield at Marlborough Rizzo Associates, Inc.
Marlborough, Massachusetts Page 2 of 3
Preliminary Sitework Estimate
360-Unit Layout dated 8/23/04
OFF-SITE (Main Access)
Off-Site work (Access Road)
Clear & Grub & Destump 1 ac $6,000 $6,000
Cut Onsite (but reused) 0 cy $3 $0
Fill from Off-site 1,800 cy $8 $14,400
Rough Grade 3,000 sy $3 $9,000
Erosion Control 1,050 lf $4 $4,200
Utilities
Double Catch-Basin 2 ea $2,200 $4,400
Regular Catch-Basin 2 ea $1,350 $2,700
Drainage Manhole 2 ea $1,350 $2,700
Stormceptor 1 ea $10,000 $10,000
12" RCP 650 ft $30 $19,500
R&R Structures 3 ea $50 $150
Miscellaneous
Landscaping 1 allow $20,000 $20,000
Steel Arch Bridge 1 ls $300,000 $300,000
Wetlands Replication 1 ls $59,000 $59,000
R&R Lightpole 1 ea $2,500 $2,500
Replace Basin Outlet Structure 1 ea $5,000 $5,000
Sewer Capcity Mitigation Fee 53,856 gl $8 $430,848
Say $5,800,000
Not Included:
Buildings
Pool
The on-site retaining wall number is for fill retaining walls only. Ledge retaining walls is accounted
for in the ledge excavation numbers.
This estimate reflects the layout shown on the Grading Plan by Rizzo Assoc.
dated July 12, 2002, revised October 21, 2002.
P/8000/8852/17528028.xls
Trench Trench Trench Area,
Depth Width SF
Drainage 5 4 20.00
Water 6 2 12.00
Sewer 6 3 18.00
Gas 3 2.5 7.50
T/E/C 3 3.5 10.50
Ledge Drain Drain Ledge, Water Water Ledge, Sewer Sewer Ledge, Gas Gas Ledge, T/E/C T/E/C
Area Depth Length CY Length CY Length CY Length CY Length Ledge, CY Total