TM 9-6115-484-14 Mep-Pu-810a/b Part 3
TM 9-6115-484-14 Mep-Pu-810a/b Part 3
TM 9-6115-484-14 Mep-Pu-810a/b Part 3
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
a. Lay out and park the load cables for each phase (A, B, & C) between the PU Tie Output parking
stations and the Primary Switching Center (PSC).
b. Connect each phase cable to the appropriate phase connection on the Primary Switching Center
(PSC).
NOTE 1: For complete set-up of the Primary Switching Center (PSC), refer to Radian Inc. Commercial
Technical Manual CTM 01646.1R1260, Chapter 2.6.
NOTE 2: For Unit Isolation Procedure (any unit) - Plant with PSC, and Unit Re-Installation
Procedure – Plant with PSC, refer to Chapter 5.9, Sections 5.9.6.15 and 5.9.6.16.
d. Open the Tie Output connector loadbreak covers on the first PU.
e. Connect the Tie Output Cables to the appropriate phase connectors; ensure there are no cross-
phase connections.
h. Connect the first (A) (B) communication cable to “B” receptacle on first PU.
j. Connect the first (A) (B) communication cable to “A” receptacle on second PU.
5-94
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
k. Connect the second (A) (B) communication cable to “B” receptacle on second PU.
m. Connect the second (A) (B) communication cable to “A” receptacle on third PU.
n. Connect third (A) (B) communication cable to “B” receptacle on third PU.
p. Connect the third (A) (B) communication cable to “A” receptacle on fourth PU.
q. Connect the fourth (A) (B) communication cable to “B” receptacle on fourth PU.
r. Leave the loose end of the fourth cable loose and capped.
(1) Press the [▲] key to get to the top-level menu “1 REPORT STATUS”.
(4) Press the [►] key 2 times to display “6.3 POWER SYSTEM SETTINGS”.
(6) Verify the “P” and “N” values match Chapter 5.1 Table 5.1.3.4-1 CT Ratio Settings.
(10) Verify the 50TP “PU” and “TD” settings in Chapter 5.1 Table 5.1.3.4-2 Instantaneous Trip
Settings. In order to edit values, Press the “Edit” key. Select correct value, and press
“Edit” again to save changes. Ensure light is off otherwise you can accidentally change
value again.
(11) Press the [►] key to display “5.1.1.2 50TN”.
5-95
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(16) Press the [►] key to display “5.1.2 51 SETTINGS”.
(18) Verify the 51P “PU”, “TD”, and “C” settings in Chapter 5.1 Table 5.1.3.4-3 Time
Overcurrent Settings.
(21) Press the [▲] key 3 times to display “5 PROTECTION LOGIC USER”.
c. Use the following procedure to verify the Generator 1 and Generator 2 GSC+ settings:
NOTE: Refer to the “EMCPII+ Reference Chart”, located on the interior Generator Control Panel
Door (Look-up)
(2) Press SERVICE MODE key to enter service mode. OP1 is showing on the lower display.
(4) Press SELECT key. “PE -“ with the first dash flashing is showing.
(5) Press SCROLL RIGHT key. “PE 1 -“ with the second dash flashing is showing.
(6) Press SCROLL DOWN key. “PE 13 –“ with the third dash flashing is showing.
(7) Press SCROLL UP key. “PE 132 –“ with the fourth dash flashing is showing.
(8) Press SCROLL DOWN key. “PE 1323 –“ with the fifth dash flashing is showing.
(9) Press SCROLL RIGHT key. “PE13231” with all digits not flashing is showing.
(12) Press SCROLL UP key until “OP5-0” is showing on the lower display.
(13) Press SELECT key. “POO1” followed with the value of the setpoint is showing.
(14) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Chapter 5.1 Table 5.1.3.4-4 OP5 Settings for the parameter values to be verified.
Repeat until the desired setpoints are verified.
5-96
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(18) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Chapter 5.1 Table 5.1.3.4-5 OP5-1 Settings for the parameter values to be verified.
Repeat until the desired setpoints are verified.
(22) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Chapter 5.1 Table 5.1.3.4-6 OP6 Settings for the parameter values to be verified.
Repeat until the desired setpoints are verified.
NOTE: If an incorrect setpoint value is displayed, the value must be changed to match the DPGDS
setpoint value as follows:
(a) With the setpoint with the incorrect value showing on the display, press the
SELECT key. The incorrect value flashes on the display.
(b) Press SCROLL UP or SCROLL DOWN key until the correct value appears
flashing on the display.
(c) Press ENTER. The correct value stops flashing on the display.
e. At the AVR verify the operation settings using Chapter 5.1 Table 5.1.3.4-7 AVR
Parameter/Setpoints:
(4) Press the [▲] key to change the value to “0015”. Enables parameter editing.
(5) Press the [◄►] key to accept change and display the parameter number.
(6) Press the [▲] key to the next parameter needed to change.
(9) Press the [◄►] key to accept change and display the parameter number.
(10) Repeat steps ‘5’ through ‘9’ for the each parameter needing to be changed.
5-97
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE: Parameters 20, 21, 22, 36, 37, and 38 are displayed but not used.
NOTE: Parameters 23 to 29, 39 to 49, 59 and 61 to 89 are not displayed and not used.
(14) Press the [▼] key to change the value to “0009”. Disables DVR parameter editing.
(15) Press the [◄►] key to accept change and display the parameter number.
Starting from the left rear of the PU and working around the PU in a clockwise direction, perform the
checks identified in Chapter 5.1 Table 5.1.3.5-1 Pre-Operation Checklist. (Gen. 1 is on the left and Gen. 2
is on the right):
WARNING
ENSURE ALL PERSONNEL ARE CLEAR AND THE PU DOORS ARE CLOSED
PRIOR TO STARTING A GENERATOR.
WARNING
WARNING
5-98
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
6 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
7 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
8 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
9 Close BCS-G1, toggle the Phase Rotation Test Light switch, verify that light ABC lights,
open BCSG1
12 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
13 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
14 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
15 Close BCS-G2, toggle the Phase Rotation Test Light switch, verify that light ABC lights,
open BCSG2
① If the wrong frequency light is on, open the Master Control Door and change the Frequency
Selector Switch (FSS) to the desired frequency.
5-99
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Remove the ORT from its case and set it up on a flat and level surface.
b. Remove the mouse from the case and plug it into the mouse (PS2) port on the back of the ORT.
c. If 120VAC power is available, connect the ORT power supply cord to the 120VAC power. The
ORT can operate up to three hours on its batteries.
d. Connect one end of the 150-foot patch cable to the ORT networking port on the PU.
e. Route the cable from the ORT to the PU and connect the cable to the ORT port.
h. Select the EquipID pop-up screen and enter the necessary information for the units. This
includes the Trailer ID number, the Engine ID number, and the Generator ID number for each
PU.
i. Select the Oneline pop-up screen and enter the descriptor for the main load connected to the
feeders.
Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
5-100
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
① With the SMS in the OFF position, the 50/60Hz lights indicate the position of the Frequency
Selector Switch (FSS). If the wrong light is on, open the door and change the switch position.
② No more than one switch can be in the same position in any multi-PU line-up. With the SMS in
OFF, none of the USI lights will be on and any previously set address on the PU is cleared.
a. Turn on the ORT and log in as administrator using the procedures of PSC Manual (Table 3.3.2-1
DPGDS ORT ADMINISTRATOR LOG-IN PROCEDURE).
NOTE: if “vista.ht” does not appear on the menu, refer to the windows 98 procedure contained in
APPENDIX C of S&C instruction sheet 681-515 to create it.
e. Click on “Connect”.
NOTE: Do Not Connect the communication cable before completing step “e”. Otherwise Windows NT
will search for a new device on the ORT COM port.
5-101
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
f. Connect the communication cable between the ORT to the left (Ways 3 and 4) Overcurrent
Relay (OCR).
NOTE: Refer to S&C Instruction Sheet 681-515 page 14, PROGRAMMING to change settings.
l. Return to the main menu and test the “Trip Function” of each interrupter using the Test Trip
Menu.
m. Return to the Main Menu and “Disconnect” using Windows HyperTerminal when desired
programming action is complete.
o. Repeat steps e. through l, for the right OCR (Ways 5 and 6).
WARNING
5-102
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. At the external switchgear, close the associated connection for each PU supplying power to the
switchgear and close and pad lock the PSC interconnect switches when using more than one
primary switch.
b. At the external switchgear, close the connections between the external switchgears.
NOTE: 1: For complete set-up of the Primary Switching Center (PSC), refer to USAF TO 35F14-1-1
and USA TM9-6115-725-14&P.
NOTE: 2: For Unit Isolation Procedure (any unit) - Plant with PSC, and Unit Re-Installation
Procedure – Plant with PSC, refer to Section 5.9, Section 5.9.6.15, and Section 5.9.6.16.
d. Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
① Hold the MSES in an ENABLE position until the selected USI indicator energizes. The switch
returns to the center position when released. This sets the PU networking address and enables
the control and monitoring.
② No more than one of each indicator can be on for multi-PU operations. The light on should match
USS position. The USI light will de-energize after the SMS has been in OFF for 3 seconds.
f. Observe the generator starts and accelerates to operating voltage and frequency.
g. At the A-unit MCP, place the Sync Source Switch (SSS) in the GEN 1 position.
5-103
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
n. Observe the engine starts and accelerates to operating voltage and frequency.
o. At the A-unit MCP, place the Sync Source Switch (SSS) in the GEN 2 position.
p. Close BCSG2 when the two green triangular LEDs at 12 o’clock on the Synchroscope are
energized by cycling BCSG2 to the CLOSE position. For detailed instructions on manual
synchronizing refer to Chapter 5.9 Section 5.9.6.14.
w. Observe the generator starts and accelerates to operating voltage and frequency.
x. At the B-unit MCP, place the Sync Source Switch (SSS) in the GEN 1 position.
y. Close BCSG1 when the two green triangular LEDs at 12 o’clock on the Synchroscope are
energized by cycling BCSG1 to the CLOSE position. For detailed instructions on manual
synchronizing refer to Chapter 5.9 Section 5.9.6.14.
aa. Observe the generator starts and accelerates to operating voltage and frequency.
bb. At the B-unit MCP, place the Sync Source Switch (SSS) in the GEN 2 position.
cc. Close BCSG2 when the two green triangular LEDs at 12 o’clock on the Synchroscope are
energized by cycling BCSG2 to the CLOSE position. For detailed instructions on manual
synchronizing refer to Chapter 5.9 Section 5.9.6.14.
gg. At the external switchgear, close the connections of loads to the switchgear.
5-104
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Note: If adjustment is needed for KVAR balance, start with the generator that is the furthest from the average
KVAR (either too low or too high). Make minor adjustments of the Voltage Adjust Rheostat (VAR) until the
KVAR sharing between generators are within +/– 10% of the average plant KVAR load. This adjustment will
typically be required only once during initial power plant setup and is intended to compensate for meter
variations among generators.
CAUTION
Improper adjustment of the VAR can cause a reverse KVAR shutdown of a generator.
In this mode of operation the ORT provides no remote operation capability. It will provide monitoring of
the generator parameters.
a. Unload all generators by opening all feeder breakers. This must be done locally from the LCP or
ORT.
WARNING
NEVER REMOVE POWER CABLES BY HAND, USE HOT STICK AND HIGH
VOLTAGE GLOVES. NEVER TOUCH A HIGH VOLTAGE LEAD OR TERMINAL UNTIL
IT HAS BEEN DISCHARGED TO GROUND. FAILURE TO OBSERVE THE WARNING
MAY RESULT IN DEATH BY ELECTROCUTION.
5-105
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CAUTION
a. Disconnect the (A)(B) communication cables from between the PUs, Reinstall the
communication cable receptacle covers, and store inside the PUs (one per unit).
b. Disconnect the fuel hose from the PU fuel connection and the fuel supply.
c. Drain any fuel from the hoses into an auxiliary fuel supply and store the hoses.
a. Remove ground connections from the PU and store with the ground rod.
c. Remove the parking stations from their operating positions and reinstall them in their
transportation locations on the inside of the PU rear side access doors.
The Power Unit may be safely shipped with oil, fuel, and coolant at maximum capacities or less. Draining
fluids is not required unless federal, state, or local regulations prohibit shipment with fluids present. Refer
to Section 14.3.1.1, Section 13.4.5.5 and Section 6.5.3 for procedures for draining the oil, coolant and fuel
liquids respectively.
5-106
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CHAPTER 5.6
OPERATING INSTRUCTIONS
5.6.3.1 GROUNDING............................................................................................................112
5.6.5.2 DESCRIPTION..........................................................................................................127
5-107
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-108
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF FIGURES
FIGURE TITLE PAGE
FIGURE 5.6.3.1-1 MEP-PU-810A GROUND POINTS 112
5-109
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF TABLES
TABLE TITLE PAGE
TABLE 5.6.3.6-1 PRE-OPERATION RUN INSTRUCTION SEQUENCE 120
5-110
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5.6 SINGLE/ MULTIPLE PU, PRIME POWER, EXTERNAL SWITCH, AUTOMATIC MODE
a. Safety precautions must be observed while operating or maintaining the PU. Safety
precautions must be observed to ensure that the operator/technician cannot have contact with the
following:
b. Minor Troubleshooting can be performed while both engines are running as long as safety
precautions are taken. Refer to the appropriate troubleshooting section for recommendations.
a. Position the PU in such a way as to allow the plant operator to have full vision of the operator
control panels on the unit.
b. Level the MEP-PU-810B front to rear with the trailer leveling hand crank.
c. Position the PU to provide a minimum of 10 feet of clearance for maintenance access on all
sides of each unit. Ensure that there are no overhead obstructions around the exhaust outlets.
WARNING
FUEL SPILLAGE CAN OCCUR IF THE POWER UNIT LEVEL IS GREATER THAN + 5
DEGREES.
d. Ensure that the ground is capable of supporting the weight of the PU. The site surface should be
as level as possible (+ 5 degrees).
5-111
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5.6.3 INITIAL PLANT SETUP
5.6.3.1 GROUNDING
WARNING
a. Drive an 8-foot ground rod into the earth and should be within 6 feet of the PU and at a location
that minimizes the tripping hazard, until only 6 inches (15 cm) protrudes above the surface.
c. Connect all of the grounding rods together with a #2 AWG copper conductor creating a central
ground grid.
d. Using a #2 AWG copper conductor, secure one end of a ground cable to one of the slotted
ground studs on the PU, see Figure 5.6.3.1-1 or Figure 5.6.3.1-3. Secure the other end of the
ground cable to the ground rod.
f. Test Ground Resistance using Ground Resistance Test Equipment. Resistance must be 25Ω or
less. Refer to Annex H for special equipment required for this task.
g. Remove parking stand plates from their transportation positions inside each rear, side PU door
and slide them into their respective operating positions on the sides of the PDC.
h. Connect the parking stand ground wires to either of the two chassis ground lugs on the PU.
GROUND POINT
GROUND POINT
5-112
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
ENSURE THAT THE FUEL LINES ARE PROTECTED FROM ALL ELECTRICAL
CABLES AND ARE ROUTED TO MINIMIZE THE POTENTIAL FOR PHYSICAL
DAMAGE OR CAUSING A TRIPPING HAZARD.
a. Lay out the fuel hoses between the PU, the fuel manifold, and the fuel bladders to establish the
fuel supply system. See Chapter 5.1 Figure 5.1.3.2-1 External Fuel Supply.
b. Install the external fuel hose for the PU to the Fuel Transfer Pump at the Tow end of the PU.
c. Connect the other end of the fuel hose to the fuel manifold outlets.
d. Connect the 3” hose, with quick-disconnect hose ends, from the fuel manifold to the fuel
bladders.
f. Open only the appropriate fuel manifold valves (once connected to the PU) to supply fuel to the
power units and check for leaks.
5-113
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5.6.3.3 DISTRIBUTION AND CONTROL CABLING
WARNING
WARNING
WARNING
a. Lay out and park the load cables for each phase (A, B, & C) between the PU Tie Output parking
stations and the Primary Switching Center (PSC).
b. Connect each phase cable to the appropriate phase connection on the Primary Switching Center
(PSC).
NOTE: 1: For complete set-up of the Primary Switching Center (PSC), refer to USAF TO 35F14-1-1
and USA TM9-6115-725-14&P.
NOTE: 2: For Unit Isolation Procedure (any unit) - Plant with PSC, and Unit Re-Installation
Procedure – Plant with PSC, refer to Section 5.9, Section 5.9.6.15, and Section 5.9.6.16.
d. Open the Tie Output connector loadbreak covers on the first PU.
e. Connect the Tie Output Cables to the appropriate phase connectors; ensure there are no cross-
phase connections.
h. Connect the first (A) (B) communication cable to “B” receptacle on first PU.
j. Connect the first (A) (B) communication cable to “A” receptacle on second PU.
5-114
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
k. Connect the second (A) (B) communication cable to “B” receptacle on second PU.
m. Connect the second (A) (B) communication cable to “A” receptacle on third PU.
n. Connect the third (A) (B) communication cable to “B” receptacle on third PU.
p. Connect the third (A) (B) communication cable to “A” receptacle on fourth PU.
q. Connect the fourth (A) (B) communication cable to “B” receptacle on fourth PU.
(1) Press the [▲] key to get to the top-level menu “1 REPORT STATUS”.
(4) Press the [►] key 2 times to display “6.3 POWER SYSTEM SETTINGS”.
(6) Verify the “P” and “N” values match Chapter 5.1 Table 5.1.3.4-1 CT Ratio Settings.
(10) Verify the 50TP “PU” and “TD” settings in Chapter 5.1 Table 5.1.3.4-2 Instantaneous Trip
Settings. In order to edit values, Press the “Edit” key. Select correct value, and press
“Edit” again to save changes. Ensure light is off otherwise you can accidentally change
value again.
5-115
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(18) Verify the 51P “PU”, “TD”, and “C” settings in Chapter 5.1 Table 5.1.3.4-3 Time
Overcurrent Settings.
(21) Press the [▲] key 3 times to display “5 PROTECTION LOGIC USER”.
c. Use the following procedure to verify the Generator 1 and Generator 2 GSC+ settings:
NOTE: Refer to the “EMCPII+ Reference Chart”, located on the interior Generator Control Panel
Door (Look-up)
(2) Press SERVICE MODE key to enter service mode. OP1 is showing on the lower display.
(4) Press SELECT key. “PE -“ with the first dash flashing is showing.
(5) Press SCROLL RIGHT key. “PE 1 -“ with the second dash flashing is showing.
(6) Press SCROLL DOWN key. “PE 13 –“ with the third dash flashing is showing.
(7) Press SCROLL UP key. “PE 132 –“ with the fourth dash flashing is showing.
(8) Press SCROLL DOWN key. “PE 1323 –“ with the fifth dash flashing is showing.
(9) Press SCROLL RIGHT key. “PE13231” with all digits not flashing is showing.
(12) Press SCROLL UP key until “OP5-0” is showing on the lower display.
(13) Press SELECT key. “POO1” followed with the value of the setpoint is showing.
(14) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Chapter 5.1 Table 5.1.3.4-4 OP5 Settings for the parameter values to be verified.
Repeat until the desired setpoints are verified.
(18) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Chapter 5.1 Table 5.1.3.4-5 OP5-1 Settings for the parameter values to be verified.
Repeat until the desired setpoints are verified.
5-116
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(22) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Chapter 5.1 Table 5.1.3.4-6 OP6 Settings for the parameter values to be verified.
Repeat until the desired setpoints are verified.
NOTE: If an incorrect setpoint value is displayed, the value must be changed to match the DPGDS
setpoint value as follows:
(a) With the setpoint with the incorrect value showing on the display, press the
SELECT key. The incorrect value flashes on the display.
(b) Press SCROLL UP or SCROLL DOWN key until the correct value appears
flashing on the display.
(c) Press ENTER. The correct value stops flashing on the display.
e. At the AVR verify the operation settings using Chapter 5.1 Table 5.1.3.4-7 AVR
Parameter/Setpoints:
(4) Press the [▲] key to change the value to “0015”. Enables parameter editing.
(5) Press the [◄►] key to accept change and display the parameter number.
(6) Press the [▲] key to the next parameter needed to change.
(9) Press the [◄►] key to accept change and display the parameter number.
(10) Repeat steps ‘5’ through ‘9’ for the each parameter needing to be changed.
5-117
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE: Parameters 20, 21, 22, 36, 37, and 38 are displayed but not used.
NOTE: Parameters 23 to 29, 39 to 49, 59 and 61 to 89 are not displayed and not used.
(14) Press the [▼] key to change the value to “0009”. Disables DVR parameter editing.
(15) Press the [◄►] key to accept change and display the parameter number.
5-118
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5.6.3.5 PRE-OPERATION CHECKS
Starting from the left rear of the PU and working around the PU in a clockwise direction, perform the
checks identified in Chapter 5.1 Table 5.1.3.5-1 Pre-Operation Checklist. (Gen. 1 is on the left and Gen. 2
is on the right):
WARNING
ENSURE ALL PERSONNEL ARE CLEAR AND THE PU DOORS ARE CLOSED
PRIOR TO STARTING A GENERATOR.
WARNING
WARNING
WARNING
5-119
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
6 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
7 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
8 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
9 Close BCS-G1, toggle the Phase Rotation Test Light switch, verify that light ABC lights,
open BCSG1
12 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
13 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
14 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
15 Close BCS-G2, toggle the Phase Rotation Test Light switch, verify that light ABC lights,
open BCSG2
① If the wrong frequency light is on, open the Master Control Door and change the Frequency
Selector Switch (FSS) to the desired frequency.
5-120
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Remove the ORT from its case and set it up on a flat and level surface.
b. Remove the mouse from the case and plug it into the mouse (PS2) port on the back of the ORT.
c. If 120VAC power is available, connect the ORT power supply cord to the 120VAC power. The
ORT can operate up to three hours on its batteries.
d. Connect one end of the 150-foot patch cable to the ORT networking port on the PU.
e. Route the cable from the ORT to the PU and connect the cable to the ORT port.
h. Select the EquipID pop-up screen and enter the necessary information for the units. This
includes the Trailer ID number, the Engine ID number, and the Generator ID number for each
PU.
i. Select the Oneline pop-up screen and enter the descriptor for the main load connected to the
feeders.
5-121
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5.6.3.8 CONTROLS SETUP
Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
a. Turn on the ORT and log in as administrator using the procedures of PSC Manual (Table 3.3.2-1
DPGDS ORT ADMINISTRATOR LOG-IN PROCEDURE).
NOTE: If “vista.ht” does not appear on the menu, refer to the Windows 98 procedure contained in
APPENDIX C of S&C instruction sheet 681-515 to create it.
5-122
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
e. Click on “Connect”.
NOTE: Do Not Connect the communication cable before completing step “e”. Otherwise Windows NT
will search for a new device on the ORT COM port.
f. Connect the communication cable between the ORT to the left (Ways 3 and 4) Overcurrent
Relay (OCR).
NOTE: Refer to S&C Instruction Sheet 681-515 page 14, PROGRAMMING to change settings.
l. Return to the main menu and test the “Trip Function” of each interrupter using the Test Trip
Menu.
m. Return to the Main Menu and “Disconnect” using Windows HyperTerminal when desired
programming action is complete.
o. Repeat steps e. through l. for the right OCR (Ways 5 and 6).
5-123
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
ONCE THE SYSTEM STATUS LIGHTS TURN GREEN AND THE MSES IS ENABLED,
THE PU WILL START. ENSURE PERSONNEL ARE CLEAR OF THE PU.
WARNING
ONLY ONE PU MAY BE SELECTED TO ANY ONE USS POSITION DURING MULTIPLE
PU OPERATIONS. OPERATING WITH MORE THAN ONE UNIT AT THE SAME ID
CAUSE UNSAFE AND ERRATIC OPERATIONAL CONDITIONS.
WARNING
a. At the Primary Switching Center (PSC), close the associated connection for each PU supplying
power to the switchgear and close and pad lock the PSC interconnect switches when using more
than one primary switch.
5-124
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE: 1: For complete set-up of the Primary Switching Center (PSC), refer to USAF TO 35F14-1-1
and USA TM9-6115-725-14&P.
NOTE: 2: For Unit Isolation Procedure (any unit) - Plant with PSC, and Unit Re-Installation
Procedure – Plant with PSC, refer to Section 5.9, Section 5.9.6.15, and Section 5.9.6.16.
d. Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
① Hold the MSES in an ENABLE position until the selected USI indicator energizes. The switch
returns to the center position when released. This sets the PU networking address and enables
the control and monitoring.
② No more than one of each indicator can be on for multi-PU operations. The light on should match
USS position. The USI light will de-energize after the SMS has been in OFF for 3 seconds.
③ With the SMS in AUTO any generator started, manually or automatically, will automatically
parallel to the bus. To prevent the generator from paralleling to the bus put the generator’s
breaker in the Pull-To-Lock position.
NOTE: The automatic economizing feature will shutdown one generator every 3 minutes until the
system load is at or below the 360KW/450KVA per generator threshold.
e. At A-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
5-125
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
k. At A-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
m. At B-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
o. At B-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
q. At C-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
s. At C-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
u. At D-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
w. At D-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
y. At the external switchgear, close all switches/breakers connecting the external switchgear to the
load (s).
Note: If adjustment is needed for KVAR balance, start with the generator that is the furthest from the average
KVAR (either too low or too high). Make minor adjustments of the Voltage Adjust Rheostat (VAR) until the
KVAR sharing between generators are within +/– 10% of the average plant KVAR load. This adjustment will
typically be required only once during initial power plant setup and is intended to compensate for meter
variations among generators.
CAUTION
Improper adjustment of the VAR can cause a reverse KVAR shutdown of a generator.
5.6.5 PLANT OPERATIONS (AUTOMATIC MODE)
5-126
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
This mode of operation places control of all generator starting, stopping, synchronizing, and load
management under the auspices of the Programmable Logic Controller (PLC) system. As long as the
SMS is in AUTO, any generator started, manually or automatically, is automatically synchronized to the
system bus. Care must be taken when starting a generator manually when the SMS is in AUTO. Either
place the associated BCS in Pull-To-Lock (prevent closing to the bus) or ensure it has the red target
visible (allow paralleling to the bus) before starting the engine. The only exception is automatic operation
of the feeder breakers. Auto Mode does not automatically close feeder breakers; it only enables remote
operation of the feeder breakers from the ORT.
5.6.5.2 DESCRIPTION
The master controller (the designated “A” unit) will control all connected generators based on the total
system KW/KVA load. The controller shuts down one of the generators after 3 minutes should the system
load drop below a level where the remaining generator load would not exceed 85% (360kW) if a
generator is shutdown. If the load of the remaining generator exceeds 85% (360kW) for one minute, a
standby generator is started and paralleled to the bus. A change of system load is recognized by the
control system and appropriate action is taken to maintain generator load in the 85% (360 KW/450 KVA)
range. The system never automatically shuts down the final generator under normal operating conditions.
The shutdown of the final generator must be done following manual operating procedures. The default
configuration is Economizing Mode on. The economizing mode can be turned off from the ORT. Through
the ORT, the AUTO shut down is disabled but the AUTO start-up remains active to prevent overloading
the online generator(s).
Start-Up Sequence: The automatic controls will continuously monitor the system load. As load on the
system increases, the controls automatically start and place additional units on line in the following
sequence at 1-minute intervals:
Shutdown Sequence: Based on the loading experienced, the controller shuts down generator sets that
are not needed. For the purpose of explanation, we will assume that all generator sets are on line
following an initial startup. Based on load, the controls shut down generator sets in the following
sequence at 3-minute intervals:
5-127
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
f. Remaining generator from PU “C”.
g. Remaining generator from PU “B”.
a. Unload all generators by opening all feeder breakers. This must be done locally from the LCP or
ORT.
WARNING
NEVER REMOVE POWER CABLES BY HAND, USE HOT STICK AND HIGH VOLTAGE
GLOVES. NEVER TOUCH A HIGH VOLTAGE LEAD OR TERMINAL UNTIL IT HAS BEEN
DISCHARGED TO GROUND. FAILURE TO OBSERVE THE WARNING MAY RESULT IN
DEATH BY ELECTROCUTION.
CAUTION
ALLOW ALL OPERATING ENGINES TO SHUT DOWN AND COOL DOWN COMPLETELY.
a. Disconnect the (A)(B) communication cables from between the PUs, Reinstall the
communication receptacle covers, and store inside the PUs (one per unit).
5-128
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
b. Disconnect the fuel hose from the PU fuel connection and the fuel supply.
c. Drain any fuel from the hoses into an auxiliary fuel supply and store the hoses.
a. Remove ground connections from the PU and store with the ground rod.
c. Remove the parking stations from their operating positions and reinstall them in their
transportation locations on the inside of the PU rear side access doors.
The Power Unit may be safely shipped with oil, fuel, and coolant at maximum capacities or less. Draining
fluids is not required unless federal, state, or local regulations prohibit shipment with fluids present. Refer
to Section 14.3.1.1, Section 13.4.5.5 and Section 6.5.3 for procedures for draining the oil, coolant and fuel
liquids respectively.
5-129
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-130
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CHAPTER 5.7
OPERATING INSTRUCTIONS
5-131
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-132
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF FIGURES
5-133
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF TABLES
5-134
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Safety precautions must be observed while operating or maintaining the PU. Safety
precautions must be observed to ensure that the operator/technician cannot have contact with the
following:
b. Minor Troubleshooting can be performed while both engines are running as long as safety
precautions are taken. Refer to the appropriate troubleshooting section for recommendations.
The MEP-012 will be operated as a droop generator. As it is loaded from 0-750KW, its frequency
droops by a set ratio. The generator’s frequency adjust potentiometer is then raised to maintain
the desired frequency. Operating multiple droop generators together requires the operator to
adjust generator frequency potentiometers to distribute the load proportionally among generators.
Additionally, the operator must constantly adjust generator frequencies to maintain the required
frequency whenever loads are added or shed.
Both kinds of generators may be operated together; however, close attention must be paid to the
system load and the droop unit’s frequency. The isochronous generator will set system
frequency and try to assume its full capacity. This requires the operator to lower the droop unit
frequency to transfer the load to the isochronous generator. That unit carries load increases up
to the capacity of the droop unit. Additional load above the total capacity of both generators will
obviously require an additional generator. Load decreases below the full capacity rating of just
the isochronous unit will require the operator to shutdown the droop unit.
5-135
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The recommended method of operating MEP-PU-810s and MEP-012s together is to place the
MEP-PU-810 generators on the bus and allow them to carry the normal load. When the system
load approaches the rated capacity of the MEP-PU-810 generator(s), add MEP-012 generators
as required to provide the necessary capacity. As the load drops off, shutdown the MEP-012
generator(s).
CAUTION
THE MEP-PU-810 WILL TRY TO ASSUME ITS RATED LOAD WHEN PARALLELED
WITH ANOTHER GENERATOR THAT IS OPERATING IN DROOP. VOLTAGE AND
FREQUENCY ADJUSTMENTS ON THE DROOP PLANT MUST BE USED TO
CONTROL THE LOAD SHARING BETWEEN THE PLANT AND THE MEP-PU-810.
There may be situations where the recommended method of operation is not ideal. In these
situations, understanding the way isochronous and droop generators work and operational
experience are useful in achieving a line-up that is best for the application.
a. Position the PU in such a way as to allow the plant operator to have full vision of the operator
control panels on the unit.
b. Level the MEP-PU-810B front to rear with the trailer leveling hand crank.
c. Position the PU to provide a minimum of 10 feet of clearance for maintenance access on all
sides of each unit. Ensure that there are no overhead obstructions around the exhaust outlets.
WARNING
FUEL SPILLAGE CAN OCCUR IF THE POWER UNIT LEVEL IS GREATER THAN + 5
DEGREES.
d. Ensure that the ground is capable of supporting the weight of the PU. The site surface should be
as level as possible (+ 5 degrees).
5-136
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5.7.4.1 GROUNDING
WARNING
THERE CAN ONLY BE ONE GROUNDING POINT FOR THE PU. WHEN USING A
NEUTRAL GROUND RESISTER (NGR), IT MUST USE THE PU GROUND ROD TO
AVOID CREATING A GROUND LOOP.
a. Drive an 8-foot ground rod into the earth and should be within 6 feet of the PU and at a location
that minimizes the tripping hazard, until only 6 inches (15 cm) protrudes above the surface.
c. Connect all of the grounding rods together with a #2 AWG copper conductor creating a central
ground grid.
d. Using a #2 AWG copper conductor, secure one end of a ground cable to one of the slotted
ground studs on the PU, see Figure 5.7.4.1-1 or Figure 5.7.4.1-3. Secure the other end of the
ground cable to the ground rod.
f. Test Ground Resistance using Ground Resistance Test Equipment. Resistance must be 25Ω or
less. Refer to Annex H for special equipment required for this task.
g. Remove parking stand plates from their transportation positions inside each rear, side PU door
and slide them into their respective operating positions on the sides of the PDC.
h. Connect the parking stand ground wires to either of the two chassis ground lugs on the PU.
5-137
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-138
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
ENSURE THAT THE FUEL LINES ARE PROTECTED FROM ALL ELECTRICAL
CABLES AND ARE ROUTED TO MINIMIZE THE POTENTIAL FOR PHYSICAL
DAMAGE OR CAUSING A TRIPPING HAZARD.
a. Lay out the fuel hoses between the PU, the fuel manifold, and the fuel bladders to establish the
fuel supply system see Figure 5.7.4.2-1.
b. Install the external fuel hose for the PU to the Fuel Transfer Pump at the Tow end of the PU.
c. Connect the other end of the fuel hose to the fuel manifold outlets.
d. Connect the 3” hose, with quick-disconnect hose ends, from the fuel manifold to the fuel
bladders.
f. Open only the appropriate fuel manifold valves (once connected to the PU) to supply fuel to the
power units and check for leaks.
5-139
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
a. Lay out and park the load cables for each phase (A, B, & C) between the PU Tie Output parking
stations and the load.
b. Connect each phase cable to the appropriate phase connection on the Primary Switching Center
(PSC).
NOTE: 1: For complete set-up of the Primary Switching Center (PSC), refer to USAF TO 35F14-1-1
and USA TM9-6115-725-14&P.
NOTE: 2: For Unit Isolation Procedure (any unit) - Plant with PSC, and Unit Re-Installation
Procedure – Plant with PSC, refer to Section 5.9, Section 5.9.6.15, and Section 5.9.6.16.
d. Open the Tie Output connector loadbreak covers on the first PU.
e. Connect the Tie Output Cables to the appropriate phase connectors; ensure there are no cross-
phase connections.
h. Connect the first (A) (B) communication cable to “B” receptacle on first PU.
5-140
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
j. Connect the first (A) (B) communication cable to “A” receptacle on second PU.
k. Connect the second (A) (B) communication cable to “B” receptacle on second PU.
m. Connect the second (A) (B) communication cable to “A” receptacle on third PU.
n. Connect the third (A) (B) communication cable to “B” receptacle on third PU.
p. Connect the third (A) (B) communication cable to “A” receptacle on fourth PU.
q. Connect the fourth (A) (B) communication cable to “B” receptacle on fourth PU.
5-141
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(1) Press the [▲] key to get to the top-level menu “1 REPORT STATUS”.
(4) Press the [►] key 2 times to display “6.3 POWER SYSTEM SETTINGS”.
(6) Verify the “P” and “N” values match the following table:
(10) Verify the 50TP “PU” and “TD” settings in Table 5.7.4.4-2. In order to edit values, Press
the “Edit” key. Select correct value, and press “Edit” again to save changes. Ensure
light is off otherwise you can accidentally change value again.
5-142
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(18) Verify the 51P “PU”, “TD”, and “C” settings in Table 5.7.4.4-3.
(21) Press the [▲] key 3 times to display “5 PROTECTION LOGIC USER”.
c. Use the following procedure to verify the Generator 1 and Generator 2 GSC+ settings in step “d”:
NOTE: Refer to the “EMCPII+ Reference Chart”, located on the interior Generator Control Panel
Door (Look-up)
(2) Press SERVICE MODE key to enter service mode. OP1 is showing on the lower display.
(4) Press SELECT key. “PE -“ with the first dash flashing is showing.
(5) Press SCROLL RIGHT key. “PE 1 -“ with the second dash flashing is showing.
(6) Press SCROLL DOWN key. “PE 13 –“ with the third dash flashing is showing.
(7) Press SCROLL UP key. “PE 132 –“ with the fourth dash flashing is showing.
(8) Press SCROLL DOWN key. “PE 1323 –“ with the fifth dash flashing is showing.
(9) Press SCROLL RIGHT key. “PE13231” with all digits not flashing is showing.
(12) Press SCROLL UP key until “OP5-0” is showing on the lower display.
(13) Press SELECT key. “POO1” followed with the value of the setpoint is showing.
(14) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Table 5.7.4.4-4 for the parameter values to be verified. Repeat until the desired
setpoints are verified.
5-143
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(18) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Table 5.7.4.4-5 for the parameter values to be verified. Repeat until the desired
setpoints are verified.
(22) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Table 5.7.4.4-6 OP6 Setpoints for the parameter values to be verified. Repeat until the
desired setpoints are verified.
NOTE: If an incorrect setpoint value is displayed, the value must be changed to match the DPGDS
setpoint value as follows:
(a) With the setpoint with the incorrect value showing on the display, press the
SELECT key. The incorrect value flashes on the display.
(b) Press SCROLL UP or SCROLL DOWN key until the correct value appears
flashing on the display.
(c) Press ENTER. The correct value stops flashing on the display.
5-144
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE 5.7.4.4-4 OP5-0 SETPOINTS
SETPOINTS OP5-0 ENGINE/GENERATOR PROGRAMMING①
FACTORY DPGDS
SETPOINT-NAME-DESCRIPTIONS RANGE OF VALUES
DEFAULT SETPOINT
P001 - Fuel Solenoid Type: type of fuel system solenoid 0- ETR fuel solenoid
0 0
used on the genset. 1- ETS fuel solenoid
P002 - Units Shown: type of measurement units shown 0-for English units (PSI, ºF)
0 0
on the GSC+ display. 1-for metric units (kPa, ºC).
P003 - Shutdown Override For Engine Fault: GSC+ 0-for engine shutdown
response to a low engine oil pressure or high coolant 1-for alarm only (shutdown override, no 0 0
temperature fault. engine shutdown).
P004 - Shutdown Override For Sensor Fault: GSC+ 0-for alarm only shutdown override, no
response to a diagnostic fault with the engine oil pressure engine shutdown). 0 0
sensor, coolant temperature sensor, oil temperature
sensor, sensor power supply or coolant loss sensor. 1-for engine shutdown.
P005 - Coolant Loss Sensor Installed: tells whether or 0-for gensets without a coolant loss sensor
not the optional engine coolant loss sensor is installed on 0 1
the genset. 1-for gensets with coolant loss sensor
5-145
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
P020④ - AC Voltage: nominal AC voltage of the generator. 700, 150, 300, 500, 600, 750, 3.0k,
The GSC+ measures the AC voltage and shows it on the 4.5k, 5.20k, 5.25k, 9.0k, 15.0k, 18.0k, 700 5.20k
display. 30.0k
P021 - AC Current Full Scale: nominal full scale AC current 75, 100, 150, 200, 300, 400, 600, 800,
of the generator. AC current full scale is equal to the ratio of 1000, 1200, 1500, 2000, 2500, 3000, 600A 100A
the external current transformers in the generator housing. and 4000A
5-146
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
① The setpoints (stored or being programmed) must match the specified DPGDS setpoints.
② When oil pressure drops to within 5PSI (34kPa) of the P013 or P014 setpoint, a low oil pressure alarm
is issued by the GSC+.
③ When coolant temperature rises to within 11ºF (6ºC) of the P015 setpoint, a high coolant temperature
alarm is issued by the GSC+.
④ The values other than the default (700V) are for switchgear applications and require the use of external
potential transformers and the removal of the AC voltage range jumper located in the relay module.
The DPGDS unit is factory configured for the 5.20 K value. See the Caterpillar Electronic Modular
Control Panel II+ manual topic AC Voltage Range Selection in the Testing and Adjusting section.
⑤ After setpoint P022 is reprogrammed, the GSC+ must be power cycled (powered down and then
powered up)
5-147
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-148
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE 5.7.4.4-5 OP5-1 SETPOINTS (CONTINUED)
SETPOINTS OP5-1 PROTECTIVE RELAYING PROGRAMMING①
FACTORY 60HZ 50HZ
SETPOINT-NAME-DESCRIPTION RANGE OF VALUES
DEFAULT SETPOINT SETPOINT
P118 - Generator Overfrequency Shutdown Time
Delay: amount of time the GSC+ waits before 0 through 120 seconds② in increments 10 seconds 10 seconds 10 seconds
issuing an overfrequency shutdown. of 1
P119 - Generator Underfrequency Alarm Enable: 0 - disabled
the GSC+ enables or disables the generator 1 1 1
underfrequency alarm function. 1 - enabled
5-149
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-150
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-151
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
③ Battleshort and 50Hz Mode are unique features to DPGDS for spare indicators 2 and 3.
5-152
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(4) Press the [▲] key to change the value to “0015”. Enables parameter editing.
(5) Press the [◄►] key to accept change and display the parameter number.
(6) Press the [▲] key to the next parameter needed to change.
(9) Press the [◄►] key to accept change and display the parameter number.
(10) Repeat steps ‘5’ through ‘9’ for the each parameter needing to be changed.
NOTE: Parameters 20, 21, 22, 36, 37, and 38 are displayed but not used.
NOTE: Parameters 23 to 29, 39 to 49, 59 and 61 to 89 are not displayed and not used.
5-153
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
33③ KVAR Reference Program Per Unit 00.00-01.00 0000 0.10 0.10
①- Default value for output voltage is different depending on regulator sensing voltage. If the regulator is
designed for 120 volts sensing, then the default output voltage is 4160 volts. All other sensing types
have the default output voltage set to 480 volts.
②- Digital Voltage Regulators with earlier software (KD and earlier) have 1 less digit to the right of the
decimal point.
③- Optional feature.
④- New parameter on serial number prefix KE and later Digital Voltage Regulators.
⑤- Previous range of 0001-099.9 and default value of 002.0
⑥-Previous range of 0001-099.9 and default value of 002.0
(14) Press the [▼] key to change the value to “0009”. Disables DVR parameter editing.
(15) Press the [◄►] key to accept change and display the parameter number.
5-154
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Starting from the left rear of the PU and working around the PU in a clockwise direction, perform the
following checks (Gen. 1 is on the left and Gen. 2 is on the right):
5-155
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
① The Battery Parallel Switch should be left in the OFF position except in extreme conditions where
the additional DC power is required to crank an engine. Once started, return the switch to the OFF
position.
5-156
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
ENSURE ALL PERSONNEL ARE CLEAR AND THE PU DOORS ARE CLOSED
PRIOR TO STARTING A GENERATOR.
WARNING
WARNING
WARNING
5-157
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
6 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
7 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
8 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
9 Close BCS-G1, toggle the Phase Rotation Test Light switch, verify that light ABC lights,
open BCSG1
12 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
13 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
14 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
15 Close BCS-G2, toggle the Phase Rotation Test Light switch, verify that light ABC lights,
open BCSG2
① If the wrong frequency light is on, open the Master Control Door and change the Frequency
Selector Switch (FSS) to the desired frequency.
5-158
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Remove the ORT from its case and set it up on a flat and level surface.
b. Remove the mouse from the case and plug it into the mouse (PS2) port on the back of the ORT.
c. If 120VAC power is available, connect the ORT power supply cord to the 120 VAC power. The
ORT can operate up to three hours on its batteries.
d. Connect one end of the 150-foot patch cable to the ORT networking port on the PU.
e. Route the cable from the ORT to the PU and connect the cable to the ORT port.
h. Select the Equip ID pop-up screen and enter the necessary information for the units. This
includes the Trailer ID number, the Engine ID number, and the Generator ID number for each
PU.
i. Select the Oneline pop-up screen and enter the descriptor for the main load connected to the
feeders.
5-159
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
① With the SMS in the OFF position, the 50/60Hz lights indicate the position of the Frequency
Selector Switch (FSS). If the wrong light is on, open the door and change the switch position.
② No more than one switch can be in the same position in any multi-PU line-up. With the SMS in
OFF, none of the USI lights will be on and any previously set address on the PU is cleared.
5-160
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CAUTION
WARNING
WARNING
CAUTION
NOTE: The MEP-PU-810 must be connected to the MEP-012A common bus (PDC or PSC).
a. Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
5-161
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
b. Observe the generator starts and accelerates to operating voltage and frequency.
c. At the A-unit MCP, place the Sync Source Switch (SSS) in the GEN 1 position.
g. Close BCST breaker when the two green triangular LEDs at 12 o’clock on the Synchroscope are
energized by cycling BCST to the CLOSE position. For detailed instructions on manual
synchronizing, refer to Section 5.9.6.14.
j. At the MEP-012 control panel, slowly reduce the generator frequency to transfer up to a
maximum of 420KW to the Unit-A Generator 1.
m. Observe the engine starts and accelerates to operating voltage and frequency.
n. At the A-unit MCP, place the Sync Source Switch (SSS) in the GEN 2 position.
5-162
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
o. Close BCSG2 breaker when the two green triangular LEDs at 12 o’clock on the Synchroscope
are energized by cycling BCSG2 to the CLOSE position. For detailed instructions on manual
synchronizing, refer to Section 5.9.6.14.
r. At the MEP-012 control panel, slowly reduce the generator frequency to transfer an additional
load up to a maximum of 420KW to the Unit-A Generator 2.
t. Repeat steps ‘b’ through ‘s’ for each PU (B – D) put into the plant lineup, increasing the maximum
capacity by 420KW for each PU generator added to the bus see Table 5.7.5.1-2.
u. Ensure generators have assumed load. After the MEP-PU-810 have stabilized proceed with the
following if necessary:
v. Observe the KW, PF and KVAR of each MEP-PU-810 generator at the LCP.
Note: If adjustment is needed for KVAR balance, start with the generator that is the furthest from the average
KVAR (either too low or too high). Make minor adjustments of the Voltage Adjust Rheostat (VAR) until the
KVAR sharing between generators are within +/– 10% of the average plant KVAR load. This adjustment will
typically be required only once during initial power plant setup and is intended to compensate for meter
variations among generators.
CAUTION
Improper adjustment of the VAR can cause a reverse KVAR shutdown of a generator.
TABLE 5.7.5.1-2 GENERATOR CAPACITIES
QUANTITY ONLINE 1 2 3 4 5 6 7 8
5-163
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
This procedure is for operation of a MEP-012 with an existing MEP-PU-810 power plant that is operating
in Prime Power mode (paralleling a MEP-012 to a MEP-PU-810 plant). The procedure assumes that the
Prime Power plant is on-line carrying the load and the MEP-012 is properly connected to the existing
plant.
a. Complete the setup of each MEP-012 generator per the MEP-012 Instruction Manual.
b. At the external switchgear, close the disconnect switch (multiple PU lineup). At the PU MCP
close the Tie Breaker (single PU lineup only).
c. At the MEP-012 control panel, start the generator.
d. Match the MEP-012 voltage to the bus voltage.
e. Manually synchronize the MEP-012 into the PU plant.
f. At the MEP-012 control panel, slowly increase the generator frequency control to transfer load,
up to the maximum capacity of the MEP-012 generator.
g. Repeat steps b through f for each additional MEP-012 being paralleled into the PU plant (multiple
PU lineups only).
h. Maintain only the number of MEP-012 generators on the bus necessary to carry the system load.
Extra MEP-012 generators should be unloaded and shutdown until required.
5-164
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CAUTION
CAUTION
WARNING
WARNING
WARNING
ONCE THE SYSTEM STATUS LIGHTS TURN GREEN AND THE MSES IS ENABLED,
THE PU WILL START. ENSURE PERSONNEL ARE CLEAR OF THE PU.
WARNING
ONLY ONE PU MAY BE SELECTED TO ANY ONE USS POSITION DURING MULTIPLE
PU OPERATIONS. OPERATING WITH MORE THAN ONE UNIT AT THE SAME ID
CAUSE UNSAFE AND ERRATIC OPERATIONAL CONDITIONS.
5-165
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
This procedure is for operation of a MEP-PU-810 with an existing power plant that is operating in Droop
(paralleling a MEP-PU-810 to a MEP-012 plant). The procedure assumes that the Droop plant is on-line
carrying the load and the PU is properly connected to the existing plant.
a. Complete the plant startup following the Automatic Mode start up procedures described in
Section 5.7.5.2, then proceed as follows:
b. Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
① Hold the MSES in an ENABLE position until the selected USI indicator energizes. The switch
returns to the center position when released. This sets the PU networking address and enables
the control and monitoring.
② No more than one of each indicator can be on for multi-PU operations. The light on should match
USS position. The USI light will de-energize after the SMS has been in OFF for 3 seconds.
③ With the SMS in AUTO any generator started, manually or automatically, will automatically
parallel to the bus. To prevent the generator from paralleling to the bus put the generator’s
breaker in the Pull-To-Lock position.
c. At A-unit GCPG1, place the Engine Control Switch (ECS) to the AUTO position.
d. Ensure that the ECS on all other units is in the OFF position.
e. Move the Master Start Enable Switch (MSES) the ENABLE position and hold until the engine
starts to crank.
f. Observe that the Tie Breaker closes, Engine/Generator 1 starts, synchronizes and closes to the
bus.
g. At the PU system ORT, disable the PU plant Economizing feature. This will prevent the plant
from dropping PU generators offline during light loading conditions.
5-166
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
h. Adjust the voltage and frequency on the MEP-012A to achieve and stabilize the desired load
share.
j. Ensure generators have assumed load. After the load has stabilized on the MEP-PU-810,
proceed with the following if necessary:
k. Observe the KW, PF and KVAR of each generator at the LCP of each MEP-PU-810.
Note: If adjustment is needed for KVAR balance, start with the generator that is the furthest from the average
KVAR (either too low or too high). Make minor adjustments of the Voltage Adjust Rheostat (VAR) until the
KVAR sharing between generators are within +/– 10% of the average plant KVAR load. This adjustment will
typically be required only once during initial power plant setup and is intended to compensate for meter
variations among generators.
CAUTION
Improper adjustment of the VAR can cause a reverse KVAR shutdown of a generator.
This procedure is for operation of a MEP-012 with an existing MEP-PU-810 power plant that is operating
in Prime Power mode (paralleling a MEP-012 to a MEP-PU-810 plant). The procedure assumes that the
Prime Power plant is on-line carrying the load and the MEP-012 is properly connected to the existing
plant.
a. At the MEP-PU-810 system ORT, disable the PU plant Economizing feature. This will prevent
the plant from dropping PU generators offline under light loading conditions due to the MEP-012
generator(s) being online.
b. Complete the setup of each MEP-012 generator per the MEP-012 Instruction Manual.
c. At the external switchgear, close the disconnect switch (multiple PU lineup). At the PU MCP
close the Tie Breaker (single PU lineup only).
d. At the MEP-012 control panel, start the generator.
e. Match the MEP-012 voltage to the bus voltage.
f. Manually synchronize the MEP-012 into the PU system.
g. At the MEP-012 control panel, slowly increase the generator frequency control to transfer load
up to the desired capacity of the MEP-012 generator.
h. Repeat steps c through g for each additional MEP-012 being paralleled into the PU system
(multiple PU lineups only).
j. Maintain only the number of MEP-012 generators on the bus necessary to carry the system load.
Extra MEP-012 generators should be unloaded and shutdown until required.
NOTE: If the PUs exceed their nominal 85% loading setpoint, an idle PU generator will start and
parallel to the bus. This oncoming generator will affect the load on all online generators
including the MEP-012(s). Manual load correction by the operator will be required. This
feature is embedded in the automatic operation of the MEP-PU-810 and cannot be disabled.
5-167
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
In this manual mode of operation, the ORT provides no remote operation capability. It will provide
monitoring of the generator parameters.
a. Reduce the load on the MEP-PU-810 plant to zero by adjusting voltage and frequency of the
Droop Plant.
b. Open all load connections. If the PU is in Manual Mode, this must be done locally using the Local
Control Panels (LCPs). If the PU is in Automatic, this can be done remotely using the ORT or
locally using the Local Control Panels (LCPs).
WARNING
NEVER REMOVE POWER CABLES BY HAND, USE HOT STICK AND HIGH
VOLTAGE GLOVES. NEVER TOUCH A HIGH VOLTAGE LEAD OR TERMINAL UNTIL
IT HAS BEEN DISCHARGED TO GROUND. FAILURE TO OBSERVE THE WARNING
MAY RESULT IN DEATH BY ELECTROCUTION.
CAUTION
a. Disconnect the (A)(B) communication cables from between the PUs, Reinstall the
communincation cable receptacle covers, and store inside the PUs (one per unit).
5-168
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
d. Disconnect all load cables used in operation of the PUs.
b. Disconnect the fuel hose from the PU fuel connection and the fuel supply.
c. Drain any fuel from the hoses into an auxiliary fuel supply and store the hoses.
a. Remove ground connections from the PU and store with the ground rod.
c. Remove the parking stations from their operating positions and reinstall them in their
transportation locations on the inside of the PU rear side access doors.
The Power Unit may be safely shipped with oil, fuel, and coolant at maximum capacities or less. Draining
fluids is not required unless federal, state, or local regulations prohibit shipment with fluids present. Refer
to Section 14.3.1.1, Section 13.4.5.5 and Section 6.5.3 for procedures for draining the oil, coolant and fuel
liquids respectively.
5-169
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-170
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CHAPTER 5.8
OPERATING INSTRUCTIONS
TABLE OF CONTENTS
5-171
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE OF CONTENTS
5-172
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF FIGURES
5-173
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF TABLES
5-174
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Safety precautions must be observed while operating or maintaining the PU. Safety
precautions must be observed to ensure that the operator/technician cannot have contact with the
following:
b. Minor Troubleshooting can be performed while both engines are running as long as safety
precautions are taken. Refer to the appropriate troubleshooting section for recommendations.
a. Position the PU in such a way as to allow the plant operator to have full vision of the operator
control panels on the unit.
b. Level the MEP-PU-810B front to rear with the trailer leveling hand crank.
c. Position the PU to provide a minimum of 10 feet of clearance for maintenance access on all
sides of each unit. Ensure that there are no overhead obstructions around the exhaust outlets.
WARNING
FUEL SPILLAGE CAN OCCUR IF THE POWER UNIT LEVEL IS GREATER THAN + 5
DEGREES.
d. Ensure that the ground is capable of supporting the weight of the PU. The site surface should be
as level as possible (+ 5 degrees).
5-175
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5.8.3.1 GROUNDING
WARNING
a. Drive an 8-foot ground rod into the earth and should be within 6 feet of the PU and at a location
that minimizes the tripping hazard, until only 6 inches (15 cm) protrudes above the surface.
c. Connect all of the grounding rods together with a #2 AWG copper conductor creating a central
ground grid.
d. Using a #2 AWG copper conductor, secure one end of a ground cable to one of the slotted
ground studs on the PU, see Figure 5.8.3.1-1 or Figure 5.8.3.1-3. Secure the other end of the
ground cable to the ground rod.
f. Test Ground Resistance using Ground Resistance Test Equipment. Resistance must be 25Ω or
less. Refer to Annex H for special equipment required for this task.
g. Remove parking stand plates from their transportation positions inside each rear, side PU door
and slide them into their respective operating positions on the sides of the PDC.
h. Connect the parking stand ground wires to either of the two chassis ground lugs on the PU.
5-176
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-177
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
ENSURE THAT THE FUEL LINES ARE PROTECTED FROM ALL ELECTRICAL
CABLES AND ARE ROUTED TO MINIMIZE THE POTENTIAL FOR PHYSICAL
DAMAGE OR CAUSING A TRIPPING HAZARD.
a. Lay out the fuel hoses between the PU, the fuel manifold, and the fuel bladders to establish the
fuel supply system. See Chapter 5.1 Figure 5.1.3.2-1 External Fuel Supply.
b. Install the external fuel hose for the PU to the Fuel Transfer Pump at the Tow end of the PU.
c. Connect the other end of the fuel hose to the fuel manifold outlets.
d. Connect the 3” hose, with quick-disconnect hose ends, from the fuel manifold to the fuel
bladders.
f. Open only the appropriate fuel manifold valves (once connected to the PU) to supply fuel to the
power units and check for leaks.
WARNING
a. Lay out and park the load cables for each phase (A, B, & C) between the PU Tie Output parking
stations and the load.
b. Connect each load cable to the appropriate phase connection on the utility bus. Ensure there
are no cross-phase connections.
d. Open the Tie Output connector loadbreak covers on the first PU.
e. Connect the Tie Output Cables to the appropriate phase connectors; ensure there are no cross-
phase connections.
h. Connect the first (A) (B) communication cable to “B” receptacle on first PU.
5-178
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
j. Connect the first (A) (B) communication cable to “A” receptacle on second PU.
k. Connect the second (A) (B) communication cable to “B” receptacle on second PU.
m. Connect the second (A) (B) communication cable to “A” receptacle on third PU.
n. Connect the third (A) (B) communication cable to “B” receptacle on third PU.
p. Connect the third (A) (B) communication cable to “A” receptacle on fourth PU.
q. Connect the fourth (A) (B) communication cable to “B” receptacle on fourth PU.
r. Leave the loose end of the fourth cable loose and capped.
(1) Press the [▲] key to get to the top-level menu “1 REPORT STATUS”.
(4) Press the [►] key 2 times to display “6.3 POWER SYSTEM SETTINGS”.
(6) Verify the “P” and “N” values match Chapter 5.1 Table 5.1.3.4-1, CT Ratio Settings.
(10) Verify the 50TP “PU” and “TD” settings match Chapter 5.1 Table 5.1.3.4-2, Instantaneous
Trip Settings. In order to edit values, Press the “Edit” key. Select correct value, and
press “Edit” again to save changes. Ensure light is off otherwise you can accidentally
change value again.
5-179
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(18) Verify the 51P “PU”, “TD”, and “C” settings in Chapter 5.1 Table 5.1.3.4-3 Time
Overcurrent Settings.
(21) Press the [▲] key 3 times to display “5 PROTECTION LOGIC USER”.
c. Use the following procedure to verify the Generator 1 and Generator 2 GSC+ settings:
NOTE: Refer to the “EMCPII+ Reference Chart”, located on the interior Generator Control Panel
Door (Look-up)
(2) Press SERVICE MODE key to enter service mode. OP1 is showing on the lower display.
(4) Press SELECT key. “PE -“ with the first dash flashing is showing.
(5) Press SCROLL RIGHT key. “PE 1 -“ with the second dash flashing is showing.
(6) Press SCROLL DOWN key. “PE 13 –“ with the third dash flashing is showing.
(7) Press SCROLL UP key. “PE 132 –“ with the fourth dash flashing is showing.
(8) Press SCROLL DOWN key. “PE 1323 –“ with the fifth dash flashing is showing.
(9) Press SCROLL RIGHT key. “PE13231” with all digits not flashing is showing.
(12) Press SCROLL UP key until “OP5-0” is showing on the lower display.
(13) Press SELECT key. “POO1” followed with the value of the setpoint is showing.
(14) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Chapter 5.1 Table 5.1.3.4-4 OP5-0 Setpoints for the parameter values to be verified.
Repeat until all OP5-0 setpoints are verified.
5-180
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(18) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Chapter 5.1 Table 5.1.3.4-5 OP5-1 Setpoints for the parameter values to be verified.
Repeat until all OP5-1 Setpoints are verified.
(22) Press SCROLL UP or SCROLL DWON key. The next setpoint with its value is showing.
Using Chapter 5.1 Table 5.1.3.4-6 OP6 Setpoints for the parameter values to be verified.
Repeat until all OP6 Setpoints are verified.
NOTE: If an incorrect setpoint value is displayed, the value must be changed to match the DPGDS
setpoint value as follows:
(a) With the setpoint with the incorrect value showing on the display, press the
SELECT key. The incorrect value flashes on the display.
(b) Press SCROLL UP or SCROLL DOWN key until the correct value appears
flashing on the display.
(c) Press ENTER. The correct value stops flashing on the display.
(d) Press SCROLL UP or SCROLL DOWN key to continue to verify the remaining
parameter values.
e. At the AVR verify the operation settings using Chapter 5.1 Table 5.1.3.4-7 AVR
Parameter/Sepoints:
(4) Press the [▲] key to change the value to “0015”. Enables parameter editing.
(5) Press the [◄►] key to accept change and display the parameter number.
(6) Press the [▲] key to the next parameter needed to change.
(9) Press the [◄►] key to accept change and display the parameter number.
5-181
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(10) Repeat steps ‘5’ through ‘9’ for the each parameter needing to be changed.
NOTE: Parameters 20, 21, 22, 36, 37, and 38 are displayed but not used.
(14) Press the [▼] key to change the value to “0009”. Disables DVR parameter editing.
(15) Press the [◄►] key to accept change and display the parameter number.
Starting from the left rear of the PU and working around the PU in a clockwise direction, perform the
checks indentified in Chapter 5.1 Table 5.1.3.5-1 Pre-Operation Checklist. (Gen. 1 is on the left and Gen.
2 is on the right):
5-182
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
ENSURE ALL PERSONNEL ARE CLEAR AND THE PU DOORS ARE CLOSED
PRIOR TO STARTING A GENERATOR.
WARNING
WARNING
WARNING
WARNING
5-183
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
6 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
7 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
8 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
9 Close BCSG1, toggle the Phase Rotation Test Light switch, verify that light ABC lights,
open BCSG1
12 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
13 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
14 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
15 Close BCST, toggle the Phase Rotation Test Light switch, verify that light ABC lights, open
BCST
16 Close BCSG2, toggle the Phase Rotation Test Switch, verify that light ABC lights, open
BCSG2
① If the wrong frequency light is on, open the Master Control Door and change the Frequency
Selector Switch (FSS) to the desired frequency.
5-184
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Remove the ORT from its case and set it up on a flat and level surface.
b. Remove the mouse from the case and plug it into the mouse (PS2) port on the back of the ORT.
c. If 120VAC power is available, connect the ORT power supply cord to the 120VAC power. The
ORT can operate up to three hours on its batteries.
d. Connect one end of the 150-foot patch cable to the ORT networking port on the PU.
e. Route the cable from the ORT to the PU and connect the cable to the ORT port.
h. Select the EquipID pop-up screen and enter the necessary information for the units. This
includes the Trailer ID number, the Engine ID number, and the Generator ID number for each
PU.
i. Select the Oneline pop-up screen and enter the descriptor for the main load connected to the
feeders.
5-185
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5.8.3.8 CONTROLS SETUP
Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
Inside MCP FSS 50/60 Hertz① 50/60 Hertz① 50/60 Hertz① 50/60 Hertz①
Emergency
Generator Control Pulled-Out Pulled-Out Pulled-Out Pulled-Out
Stop
Panel GCPG1
ECS OFF OFF OFF OFF
Emergency
Generator Control Pulled-Out Pulled-Out Pulled-Out Pulled-Out
Stop
Panel GCPG2
ECS OFF OFF OFF OFF
① With the SMS in the OFF position, the 50/60Hz lights indicate the position of the Frequency
Selector Switch (FSS). If the wrong light is on, open the door and change the switch position.
② No more than one switch can be in the same position in any multi-PU line-up. With the SMS in
OFF, none of the USI lights will be on and any previously set address on the PU is cleared.
5-186
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5.8.4.1 GENERAL
CAUTION
DO NOT SET THE DESIRED LOAD ON THE ORT SLIDEBAR FOR A UTILITY
PARALLEL PU OR PLANT TO A VALUE THAT EXCEEDS THE TOTAL AVAILABLE
LOAD. PARALLELED PRIME POWER GENERATORS MAY BE REVERSE
POWERED AND TRIP OFFLINE. PLANT OPERATORS MUST MONITOR THE TOTAL
PLANT LOAD TO PREVENT THE UTILITY PARALLEL PU OR PLANT FROM OVER-
POWERING THE SYSTEM. SET THE DESIRED LOAD ON THE ORT SLIDEBAR FOR
A UTILITY PARALLEL PU OR PLANT TO A VALUE THAT PREVENTS OVERLOAD
OF THE PRIME POWER GENERATORS. FAILURE TO FOLLOW THIS CAUTION
MAY RESULT IN POWER FAILURE .
Operating PUs in parallel with a utility source should be done with the PUs operating in Automatic
mode. This provides the operator with control over the amount of load the generators will carry.
Operating PUs in Manual mode with a utility source limits the units to carrying only 25KW per
generator. The PUs can be started and put online manually, but should be operated automatically
using an ORT.
Use Section 5.5.4 (Multi-PU Prime Power Manual Startup) to start a plant manually. Use Section
5.9.6.12 to change the units to Auto mode to allow changing the load.
WARNING
WARNING
5-187
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
ONCE THE SYSTEM STATUS LIGHTS TURN GREEN AND THE MSES IS ENABLED,
THE PU WILL START. ENSURE PERSONNEL ARE CLEAR OF THE PU.
WARNING
ONLY ONE PU MAY BE SELECTED TO ANY ONE USS POSITION DURING MULTIPLE
PU OPERATIONS. OPERATING WITH MORE THAN ONE UNIT AT THE SAME ID
CAUSE UNSAFE AND ERRATIC OPERATIONAL CONDITIONS.
a. At the utility connection, close the associated connection for each PU supplying power to the
utility.
b. Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
Generator BCS-G2 Red Target Red Target Red Target Red Target
Control Panel 2
GCPG2 ECS-2 AUTO AUTO AUTO AUTO
① Hold the MSES in an ENABLE position until the selected USI indicator energizes. The switch
returns to the center position when released. This sets the PU networking address and enables
the control and monitoring.
② No more than one of each indicator can be on for multi-PU operations. The light on should match
USS position. The USI light will de-energize after the SMS has been in OFF for 3 seconds.
③ With the SMS in AUTO any generator started, manually or automatically, will automatically
parallel to the bus. To prevent the generator from paralleling to the bus put the generator’s
breaker in the Pull-To-Lock position.
5-188
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
d. At A-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
e. At A-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
g. At B-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
h. At B-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
j. At C-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
k. At C-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
m. At D-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
n. At D-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
w. Observe that each generator assumes 25KW when it parallels to the system bus.
x. From the ORT, set the desired load for all generators running. The load is set on a per generator
basis.
5-189
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
y. Ensure generators have assumed load. After the desired load has been stabilized, proceed with
the following if necessary:
Note: If adjustment is needed for KVAR balance, start with the generator that is the furthest from the average
KVAR (either too low or too high). Make minor adjustments of the Voltage Adjust Rheostat (VAR) until the
KVAR sharing between generators are within +/– 10% of the average plant KVAR load. This adjustment will
typically be required only once during initial power plant setup and is intended to compensate for meter
variations among generators.
CAUTION
Improper adjustment of the VAR can cause a reverse KVAR shutdown of a generator.
NOTE: The automatic economizing feature is disabled while a generator is operating in Utility
Parallel mode.
The power plant must be in Auto Mode to be operated remotely or to adjust the load on the generators.
a. Unload all generators by opening all Tie breakers. This must be done locally from the LCP or
ORT.
WARNING
NEVER REMOVE POWER CABLES BY HAND, USE HOT STICK AND HIGH
VOLTAGE GLOVES. NEVER TOUCH A HIGH VOLTAGE LEAD OR TERMINAL UNTIL
IT HAS BEEN DISCHARGED TO GROUND. FAILURE TO OBSERVE THE WARNING
MAY RESULT IN DEATH BY ELECTROCUTION.
5-190
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CAUTION
a. Disconnect the (A)(B) communication cables from between the PUs, Reinstall the
communications cable receptacle covers, and store inside the PUs (one per unit).
b. Disconnect the fuel hose from the PU fuel connection and the fuel supply.
c. Drain any fuel from the hoses into an auxiliary fuel supply and store the hoses.
a. Remove ground connections from the PU and store with the ground rod.
c. Remove the parking stations from their operating positions and reinstall them in their
transportation locations on the inside of the PU rear side access doors.
The Power Unit may be safely shipped with oil, fuel, and coolant at maximum capacities or less. Draining
fluids is not required unless federal, state, or local regulations prohibit shipment with fluids present. Refer
to Section 14.3.1.1, Section 13.4.5.5 and Section 6.5.3 for procedures for draining the oil, coolant and fuel
liquids respectively.
5-191
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-192
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CHAPTER 5.9
OPERATING INSTRUCTIONS
5-193
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE OF CONTENTS
5.9.6.10 ADD AND REMOVE GENERATOR FROM PLANT LINE-UP WITH ORT 217
5.9.6.14 UNIT ISOLATION PROCEDURE (ANY UNIT) – PLANT WITH PSC 219
5-194
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF TABLES
5-195
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Safety precautions must be observed while operating and or maintaining the power unit. Refer
to the appropriate troubleshooting section for recommendations Safety precautions must be
observed to ensure that the operator/technician cannot have contact with the following:
b. Minor Troubleshooting can be performed while both engines are running as long as safety
precautions are taken. Refer to the appropriate troubleshooting section for recommendations.
WARNING
WARNING
5-196
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
b. At the AVR verify/change the operation settings for 60 Hz using Table 5.9.2.2-1:
e. Press the [▲] key to change the value to “0015”. Enables parameter editing.
f. Press the [◄►] key to accept change and display the parameter number.
j. Press the [◄►] key to accept change and display the parameter number.
k. Repeat steps ‘g’ through ‘j’ for each parameter needing to be changed.
5-197
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
33③ KVAR Reference Program Per Unit 00.00-01.00 0000 .10 .10
5-198
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
①- Default value for output voltage is different depending on regulator sensing voltage. If the regulator is
designed for 120 volts sensing, then the default output voltage is 4160 volts. All other sensing types
have the default output voltage set to 480 volts.
②- Digital Voltage Regulators with earlier software (KD and earlier) have 1 less digit to the right of the
decimal point.
③- Optional feature.
④- New parameter on serial number prefix KE and later Digital Voltage Regulators.
⑤- Previous range of 0001-099.9 and default value of 002.0
⑥-Previous range of 0001-099.9 and default value of 002.0
NOTE: Parameters 20, 21, 22, 36, 37, and 38 are displayed but not used.
n. Press the [▼] key to change the value to “0009”. Disables parameter editing.
o. Press the [◄►] key to accept change and display the parameter number.
At GSCG1, verify/change the operation settings for 60 Hz using Table 5.9.2.3-1 and Table 5.9.2.3-2:
b. Press SERVICE MODE key to enter service mode. “OP1” is showing on the lower display.
5-199
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
e. Press SELECT key. “PE -“ with the first dash flashing is showing.
f. Press SCROLL RIGHT key. “PE 1 -“ with the second dash flashing is showing.
g. Press SCROLL DOWN key. “PE 13 –“ with the third dash flashing is showing.
h. Press SCROLL UP key. “PE 132 –“ with the fourth dash flashing is showing.
i. Press SCROLL DOWN key. “PE 1323 –“ with the fifth dash flashing is showing.
j. Press SCROLL RIGHT key. “PE13231” with all digits not flashing is showing.
o. Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
p. Press SELECT key. The value of the setpoint is flashing. Use the GSC Setpoints Table 5.9.2.3-1
for the values to verify/change in each parameter.
q. Press SCROLL UP or SCROLL DOWN key to adjust the value of the setpoint.
NOTE: To adjust the value of some setpoints, it is necessary to press and release the scroll key
several times in order for the value to change. To rapidly scroll through a large range of
values, press and hold the appropriate scroll key.
s. Repeat steps ‘o’ through ‘r’ until all the desired setpoints are adjusted.
u. Repeat steps ‘m’ through ‘s’ for “OP5-1” using Table 5.9.2.3-2.
5-200
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
P005 - Coolant Loss Sensor Installed: tells whether or 0-for gensets without a coolant loss sensor
not the optional engine coolant loss sensor is installed on 0 1
the genset. 1-for gensets with coolant loss sensor
5-201
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
P020④ - AC Voltage: nominal AC voltage of the generator. 700, 150, 300, 500, 600, 750, 3.0k,
The GSC+ measures the AC voltage and shows it on the 4.5k, 5.20k, 5.25k, 9.0k, 15.0k, 18.0k, 700 5.20k
display. 30.0k
P021 - AC Current Full Scale: nominal full scale AC current 75, 100, 150, 200, 300, 400, 600, 800,
of the generator. AC current full scale is equal to the ratio of 1000, 1200, 1500, 2000, 2500, 3000, 600A 100A
the external current transformers in the generator housing. and 4000A
5-202
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
① The setpoints (stored or being programmed) must match the specified DPGDS setpoints.
② When oil pressure drops to within 5PSI (34kPa) of the P013 or P014 setpoint, a low oil pressure alarm
is issued by the GSC+.
③ When coolant temperature rises to within 11ºF (6ºC) of the P015 setpoint, a high coolant temperature
alarm is issued by the GSC+.
④ The values other than the default (700V) are for switchgear applications and require the use of external
potential transformers and the removal of the AC voltage range jumper located in the relay module.
The DPGDS unit is factory configured for the 5.20 K value. See the Caterpillar Electronic Modular
Control Panel II+ manual topic AC Voltage Range Selection in the Testing and Adjusting section.
⑤ After setpoint P022 is reprogrammed, the GSC+ must be power cycled (powered down and then
powered up)
5-203
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-204
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-205
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-206
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-207
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
③ Battleshort and 50Hz Mode are unique features to DPGDS for spare indicators 2 and 3.
5-208
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Turn on DC power.
b. At the AVR verify/change the operation settings for 50Hz using Table 5.9.2.2-1:
e. Press the [▲] key to change the value to “0015”. Enables parameter editing.
f. Press the [◄►] key to accept change and display the parameter number.
j. Press the [◄►] key to accept change and display the parameter number.
k. Repeat steps ‘g’ through ‘j’ for the each parameter needing to be changed.
n. Press the [▼] key to change the value to “0009”. Disables parameter editing.
o. Press the [◄►] key to accept change and display the parameter number.
5-209
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
At GSC G1, verify/change the operation settings for 50 Hz using Table 5.9.2.3-1 and Table 5.9.2.3-2.
b. Press SERVICE MODE key to enter service mode. “OP1” is showing on the lower display.
e. Press SELECT key. “PE -“ with the first dash flashing is showing.
f. Press SCROLL RIGHT key. “PE 1 -“ with the second dash flashing is showing.
g. Press SCROLL DOWN key. “PE 13 –“ with the third dash flashing is showing.
h. Press SCROLL UP key. “PE 132 –“ with the fourth dash flashing is showing.
i. Press SCROLL DOWN key. “PE 1323 –“ with the fifth dash flashing is showing.
j. Press SCROLL RIGHT key. “PE13231” with all digits not flashing is showing.
o. Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
p. Press SELECT key. The value of the setpoint is flashing. Use the GSC+ Setpoints Table for the
values to verify/change in each parameter.
q. Press SCROLL UP or SCROLL DOWN key to adjust the value of the setpoint.
NOTE: To adjust the value of some setpoints, it is necessary to press and release the scroll key
several times in order for the value to change. To rapidly scroll through a large range of
values, press and hold the appropriate scroll key.
s. Repeat steps ‘o’ through ‘r’ until all the desired setpoints are adjusted.
5-210
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
In a multi-PU plant operating in the automatic mode, the PU designated as the “A” unit (PU-A) controls
the Economizing function of the plant. There must always be one, and only one, PU designated as PU-A
for the plant to operate properly. Each of the other PUs in the plant must also be uniquely designated
(PU-B, PU-C, etc.). If it becomes necessary to shutdown PU-A, another unit must be designated as PU-
A. It may be applied to any unit that is connected to the system network. However, there can be only one
(1) PU per plant configured with an individual address.
b. Place the SMS in the MANUAL position for all units in the plant.
c. Place the ECS in the MANUAL/START position for all units in the plant.
d. Place the SMS in the OFF position on all units in the plant—wait for the USI light to go out.
e. Place the USS in the desired position (A, B, C, or D). Note the general procedure in the Section
above.
f. Place the SMS in the MANUAL position for all units in the plant.
g. Place the MSES in the ENABLE position and hold until the USI energizes.
h. Verify that the correct unit selector indicator is lit for each unit.
i. Place the ECS in the AUTO position on each unit in the plant.
j. Place the SMS in the AUTO position on each unit in the plant.
NOTE: After re-designation of any PU, the system defaults to ECONOMIZER MODE.
5-211
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
(1) Press the UP arrow twice to get to “1.1 RECLOSER OFF” display.
(2) Press the DOWN arrow key once to get to “1.2 TARGETS YES” display.
(3) Press RIGHT arrow key twice to get to “1.3 ALARMS YES” display.
b. At the MCP:
(2) Observe the red SSL de-energizes and the generator will sync and close to the bus if the
engine is still running.
WARNING
5-212
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
NOTE: This procedure assumes the PUs in the plant are operating in Automatic and that PSC1 is
chosen to power down prior to re-closing the interconnect. The procedure may also be used
for isolation of PSC2 by substituting “PSC2” for “PSC1” and “PSC1” for “PSC2”.
a. At the ORT, open the GCGG1 and GCGG2 breakers for all Power Units connected to PSC 1.
c. Unlock, open and reset the interconnecting switches on PSC 1 and PSC 2.
f. At the ORT, close all generator breakers on all Power Units connected to PSC 1.
NOTE: For Interconnection and Operating Procedures of the Primary Switching Center (PSC), refer
to USAF TO 35F14-1-1/USA TM9-6115-725-14&P.
5-213
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
At the GCP for the generator to be added to the bus, perform the following:
NOTE: This procedure assumes that the DC Power is on, and the Generator Pre-Operation inspection has
been performed.
b. Observe the idle generator starts and accelerates to operating voltage and frequency.
c. Check Voltage and Frequency (3915 VAC, 50 hz or 4295 VAC, 60 hz). Adjust as necessary
using FAR and VAR.
f. Observe that the BVFM energizes and shows the bus voltage.
g. Observe that the green rectangular LEDs at 3 and 9 on the synchroscope are on. This indicates
that the synchroscope sees both running and incoming buses as being energized.
h. Observe that the synchroscope appears to be rotating slowly in the clockwise direction. The
LEDs composing the circular pattern on the sync scope sequentially illuminate in a clockwise
rotation pattern.
i. When the triangular green LED at 12 o-clock energizes, close the BCSG breaker switch.
NOTE: You will have to wait until the triangular green LED to reach 12 0-clock.
5-214
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
j. Observe that the breaker closed LED energizes and the open LED de-energizes.
a. Select the PU Control Screen for the generator to be added to the bus.
f. Observe the generator breaker closes and the generator assumes load.
g. Return to the OVERVIEW screen and verify the generators are sharing load equally.
NOTE: If the added generator reduces the individual generator load below the economizing
threshold, then the control system will automatically shutdown a generator after three
minutes.
CAUTION
At the GCP for the generator you want to shutdown, perform the following:
a. Open the generator’s breaker by turning the BCS to TRIP and releasing when the green indicator
light energizes.
5-215
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
c. Observe the generator continues to run for 5 minutes then shuts down.
CAUTION
b. At the GCP for the off going generator, open the generator’s breaker by turning the BCS to TRIP
and releasing when the green indicator light energizes.
c. At the GCP for the off going generator, place the ECS in STOP/COOLDOWN.
e. Observe the generator continues to run for 5 minutes then shuts down.
f. At the GCP for the off going generator, place the ECS in OFF/RESET.
CAUTION
g. Return to the OVERVIEW screen and verify the remaining generators are sharing load equally.
h. Observe the generator continues to run for 5 minutes then shuts down.
5-216
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE: The repeated pressing of the Silence button is required for multiple alarms or faults. The
Silence button will silence only one alarm/fault per action.
NOTE: The repeated pressing of the BSPB is required for multiple alarms or faults. The BSPB will
silence only one alarm/fault per action.
NOTE: This screen cannot be exited until all alarms are acknowledged. Acknowledging alarms on
the ORT also silences the buzzer(s) on the PU(s).
5.9.6.10 ADD AND REMOVE GENERATOR FROM PLANT LINE-UP WITH ORT
a. Select the PU Control Screen for the generator to be added to the bus.
f. Observe the generator breaker closes and the generator assumes load.
h. Select the PU Control Screen for the generator desiring to take offline.
5-217
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
n. Return to the OVERVIEW screen and verify the generators are sharing load equally.
o. Observe the generator continues to run for 5 minutes then shuts down.
NOTE: Disabling economizing only stops the control system from shutting down generators during
light load conditions. To prevent overloading generators the “add” feature remains active and
cannot be disabled.
WARNING
5-218
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
a. Place the System Mode Switch (SMS) in “Manual” on all units in the plant.
OBSERVE:
• System Status Light (SSL) green LEDs on all units are not illuminated indicating that the units
are operating in Manual Mode and that there are no faults or alarms.
b. Start all off-line Engine/Generator sets on the units NOT being isolated.
OBSERVE:
e. Connect (A) (B) Communication cables as required to maintain the load share bus.
• If the unit being isolated is an end unit on the communication bus (Unit A or Unit D), no
additional (A) (B) Communication cable connections are required.
• If the unit being isolated is an inner unit on the communication bus (Unit B or Unit C),
connect an (A) (B) Communication cable between the output connector (B) on Unit D to the
input connector (A) on Unit A.
f. Disconnect the (A) (B) Communication cable(s) on the unit being isolated.
g. Ensure that there is an (A) (B) Communication cable connected to the output connector (B) on
unit that is now the right end unit on the communication bus and that the input connector end of
that (A) (B) Communication cable is capped.
5-219
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
h. If the ORT cable is connected to the unit being isolated, move the cable to another unit.
OBSERVE:
• Remaining on-line Engine/Generator sets in the plant share the load equally
i. Place the ECS for both Engine/Generator sets in the “Cool down” position on the unit being
isolated.
OBSERVE:
k. Turn off the DC Control Power Circuit Breaker on the unit being isolated.
l. Open the ESG input switch for the unit being isolated.
m. Place the ESG input switch for the unit being isolated in the “Grounded” position if so equipped.
n. Place the BCST on the unit being isolated in the “Pull-to-Lock” position.
o. On the external switchgear, visually confirm, through the viewing windows, that the ESG switch is
in the grounded position.
NOTE: At this point the Tie Power cables are completely de-energized. However, safe working
practice requires the use of personal protective equipment until a circuit is grounded. If the
ESG is equipped with internal circuit grounding, then step “n” can be accomplished without
the use of Hot Stick or lineman’s gloves. If the ESG is not equipped with internal circuit
grounding, then personal protective equipment should be used.
p. Using a Hot Stick and lineman’s gloves, disconnect and Park the Tie load cables.
q. Re-designate the MEP-PU-810s to ensure that one and only one unit is designated A, B, C or D.
There must be a unit designated as “A”.
r. Place the System Mode Switch (SMS) on all units in the plant to the “Automatic” position. DO
NOT pause in the “OFF” position when transitioning the SMS from “Manual” to “Automatic".
s. Cycle the Master Start Enable Switch (MSES) on all units in the plant to the “Enable” position
and hold for 3 seconds.
a. Ensure the switch for the PSC input to be used is open (“Grounded” if so equipped)
b. Connect the load power cables between the MEP-PU-810 Tie output and the PSC input.
5-220
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
d. Connect the (A) (B) Communication cable(s) with other units in the plant.
NOTE: If the unit being installed is an end unit, ensure a (A) (B) Communication cable is connected
to the output side connector.
NOTE: If the unit being installed is replacing center unit, disconnect the (A) (B) Communication cable
that is connecting the two end units at the input side of the left most unit.
f. Setup the unit to operate in the same mode as the unit(s) that the (A) (B) Communication
cable(s) are connected to (either Automatic / Prime Power or Automatic / Utility Parallel)
OBSERVE:
• System Status Light (SSC) on all Units: both green lights are on steady indicating the
Engine/Generator sets are available in Automatic mode; the amber and red lights are off
indicating no active alarms or faults.
OBSERVE:
• The Tie breaker closes as soon as power is received from the PSC.
• The MEP-PU-810 internal bus is energized and common with the power plant bus.
i. Designate the unit according to the plant setup, ensure one and only one unit is designated “A”,
“B”, “C”, or “D”.
k. Cycle the MSS to the “ENABLE” position and hold until an engine cranks.
OBSERVE:
b. Start any idle generators on the PU that are to remain operating per Section 5.9.5.1.
5-221
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
h. Verify the generators on the remaining PU are carrying the load properly.
i. Take the generators on the PU being isolated offline per Section 5.9.5.4.
j. Using a Hot Stick and lineman’s gloves, disconnect and park the Tie Load Cables on the
operating PU.
k. Verify that the isolated PU feeders are not looped to any operating feeders.
l. Using a Hot Stick and lineman’s gloves, disconnect and park the Feeder Load Cables on the
isolated PU.
m. If either of the feeders on the operating PU is unused, the disconnected feeder cables from the
isolated PU may be relocated to that feeder.
r. If the remaining PU is designated as “B”, follow the procedure in Section 5.9.3 for re-designating
that unit as “A”.
This procedure assumes that the operating PU is operating as Unit “A” in AUTOMATIC.
a. Place the operating PU in MANUAL by putting its SMS in MANUAL without stopping in OFF.
c. Position and Ground the incoming PU and perform the startup checks for the unit per Chapter
5.3.
d. Turn on the PU’s DC power by pushing in on the DC Control Power Circuit Breaker.
g. Connect the (A) (B) Communication cable between the PUs; ‘B-plug’ on operating unit to ‘A-plug’
on incoming unit.
h. Connect the other (A) (B) Communication cable into the incoming PU’s ‘B-plug’, leaving the
loose end capped.
5-222
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
j. Cycle the incoming tie breaker switch to display the red target.
o. Cycle both generator and feeder breaker switches to display red targets.
r. Cycle the incoming unit MSES and observe the “B” USI energizes.
t. At 3-minute intervals, depending on the load, the automatic system shuts down unnecessary
generators.
5-223
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-224
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
CHAPTER 5.10
OPERATING INSTRUCTIONS
5-225
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
TABLE OF CONTENTS
5-226
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
LIST OF FIGURES
5-227
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
LIST OF TABLES
5-228
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
This procedure is for parallel operation of two MEP-PU-810 power plants. One plant must be operated in
Prime Power Mode (Plant 1) and the second plant must be operated in Utility Parallel Mode (Plant 2).
The procedure assumes that both plants will be connected to external switchgear (PSC or US Army
CCV). Once the two plants are setup and operating in parallel, the Utility Parallel plant will produce a
fixed power that is specified by the operator and the Prime Power plant will provide power to make up the
difference between the total load requirement and the power being produced by the Utility Parallel plant.
Each plant is remotely controlled by its own ORT.
a. Safety precautions must be observed while operating or maintaining the PU. Safety
precautions must be observed to ensure that the operator/technician cannot have contact with the
following:
b. Minor Troubleshooting can be performed while both engines are running as long as safety
precautions are taken. Refer to the appropriate troubleshooting section for recommendations.
a. Position the PU in such a way as to allow the plant operator to have full vision of the operator
control panels on the unit.
b. Level the MEP-PU-810B front to rear with the trailer leveling hand crank.
c. Position the PU to provide a minimum of 10 feet of clearance for maintenance access on all
sides of each unit. Ensure that there are no overhead obstructions around the exhaust outlets.
WARNING
FUEL SPILLAGE CAN OCCUR IF THE POWER UNIT LEVEL IS GREATER THAN + 5
DEGREES.
d. Ensure that the ground is capable of supporting the weight of the PU. The site surface should be
as level as possible (+ 5 degrees).
5-229
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
5.10.1.3.1 GROUNDING
WARNING
THERE CAN ONLY BE ONE GROUNDING POINT FOR THE PU. WHEN USING A
NEUTRAL GROUND RESISTER (NGR), IT MUST USE THE PU GROUND ROD TO
AVOID CREATING A GROUND LOOP.
a. Drive an 8-foot ground rod into the earth and should be within 6 feet of the PU and at a location
that minimizes the tripping hazard, until only 6 inches (15 cm) protrudes above the surface.
c. Connect all of the grounding rods together with a #2 AWG copper conductor creating a central
ground grid.
d. Using a #2 AWG copper conductor, secure one end of a ground cable to one of the slotted
ground studs on the PU, see Figure 5.1.3.1-1 or Figure 5.1.3.1-3. Secure the other end of the
ground cable to the ground rod.
f. Test Ground Resistance using Ground Resistance Test Equipment. Resistance must be 25Ω or
less. Refer to Annex H for special equipment required for this task.
g. Remove parking stand plates from their transportation positions inside each rear, side PU door
and slide them into their respective operating positions on the sides of the PDC.
h. Connect the parking stand ground wires to either of the two chassis ground lugs on the PU.
5-230
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
5-231
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
WARNING
ENSURE THAT THE FUEL LINES ARE PROTECTED FROM ALL ELECTRICAL
CABLES AND ARE ROUTED TO MINIMIZE THE POTENTIAL FOR PHYSICAL
DAMAGE OR CAUSING A TRIPPING HAZARD.
a. Lay out the fuel hoses between the PU, the fuel manifold, and the fuel bladders to establish the
fuel supply system see Figure 5.10.3.2-1.
b. Install the external fuel hose for the PU to the Fuel Transfer Pump at the Tow end of the PU.
c. Connect the other end of the fuel hose to the fuel manifold outlets.
d. Connect the 3” hose, with quick-disconnect hose ends, from the fuel manifold to the fuel
bladders.
f. Open only the appropriate fuel manifold valves (once connected to the PU) to supply fuel to the
power units and check for leaks.
5-232
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
WARNING
WARNING
WARNING
a. Lay out and park the load cables for each phase (A, B, & C) between the PU Tie Output parking
stations and the load.
b. Connect each phase cable to the appropriate phase connection on the Primary Switching Center
(PSC).
NOTE 1: For complete set-up of the Primary Switching Center (PSC), refer to Radian Inc. Commercial
Technical Manual CTM 01646.1R1260, Chapter 2.6.
NOTE 2: For Unit Isolation Procedure (any unit) - Plant with PSC, and Unit Re-Installation
Procedure – Plant with PSC, refer to Chapter 5.9, Sections 5.9.6.15 and 5.9.6.16.
d. Open the Tie Output connector loadbreak covers on the first PU.
e. Connect the Tie Output Cables to the appropriate phase connectors; ensure there are no cross-
phase connections.
h. Connect “B” end of the first (A) (B) communication cable to “B” receptacle on first PU.
5-233
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
j. Connect the first (A) (B) communication cable to “A” receptacle on second PU.
k. Connect the second (A) (B) communication cable to “B” receptacle on second PU.
n. Connect the second (A) (B) communication cable to “A” receptacle on third PU.
o. Connect the third (A) (B) communication cable to “B” receptacle on third PU.
q. Connect the third (A) (B) communication cable to “A” receptacle on fourth PU.
r. Connect the fourth (A) (B) communication cable to “B” receptacle on fourth PU.
5-234
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
(1) Press the [▲] key to get to the top-level menu “1 REPORT STATUS”.
(4) Press the [►] key 2 times to display “6.3 POWER SYSTEM SETTINGS”.
(6) Verify the “P” and “N” values match the following table:
(10) Verify the 50TP “PU” and “TD” settings in Table 5.10.1.3.4-2. In order to edit values,
Press the “Edit” key. Select correct value, and press “Edit” again to save changes.
Ensure light is off otherwise you can accidentally change value again.
5-235
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
(18) Verify the 51P “PU”, “TD”, and “C” settings in Table 5.10.1.3.4-3.
(21) Press the [▲] key 3 times to display “5 PROTECTION LOGIC USER”.
c. Use the following procedure to verify the Generator 1 and Generator 2 GSC+ settings:
NOTE: Refer to the “EMCPII+ Reference Chart”, located on the interior Generator Control Panel
Door (Look-up)
(2) Press SERVICE MODE key to enter service mode. OP1 is showing on the lower display.
(4) Press SELECT key. “PE -“ with the first dash flashing is showing.
(5) Press SCROLL RIGHT key. “PE 1 -“ with the second dash flashing is showing.
(6) Press SCROLL DOWN key. “PE 13 –“ with the third dash flashing is showing.
(7) Press SCROLL UP key. “PE 132 –“ with the fourth dash flashing is showing.
(8) Press SCROLL DOWN key. “PE 1323 –“ with the fifth dash flashing is showing.
(9) Press SCROLL RIGHT key. “PE13231” with all digits not flashing is showing.
(12) Press SCROLL UP key until “OP5-0” is showing on the lower display.
(13) Press SELECT key. “POO1” followed with the value of the setpoint is showing.
(14) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use table 5.10.3.4-4 for the parameter values to be verified.
5-236
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
(15) Repeat step “15” until the desired setpoints are verified.
NOTE: If an incorrect setpoint value is displayed, the value must be changed to match the DPGDS
setpoint value as follows:
(a) With the setpoint with the incorrect value showing on the display, press the
SELECT key. The incorrect value flashes on the display.
(b) Press SCROLL UP or SCROLL DOWN key until the correct value appears
flashing on the display.
(c) Press ENTER. The correct value stops flashing on the display.
(d) Press SCROLL UP or SCROLL DOWN key to continue to verify the remaining
parameter values.
d. At GSC G1 and GSC G2, verify the operation settings using the following table:
5-237
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
TABLE 5.10.1.3.4-4 OP5-0 SETPOINTS
SETPOINTS OP5-0 ENGINE/GENERATOR PROGRAMMING①
FACTORY DPGDS
SETPOINT-NAME-DESCRIPTIONS RANGE OF VALUES
DEFAULT SETPOINT
P001 - Fuel Solenoid Type: type of fuel system solenoid 0- ETR fuel solenoid
0 0
used on the genset. 1- ETS fuel solenoid
P002 - Units Shown: type of measurement units shown 0-for English units (PSI, ºF)
0 0
on the GSC+ display. 1-for metric units (kPa, ºC).
P003 - Shutdown Override For Engine Fault: GSC+ 0-for engine shutdown
response to a low engine oil pressure or high coolant 1-for alarm only (shutdown override, no 0 0
temperature fault. engine shutdown).
P004 - Shutdown Override For Sensor Fault: GSC+ 0-for alarm only shutdown override, no
response to a diagnostic fault with the engine oil pressure engine shutdown). 0 0
sensor, coolant temperature sensor, oil temperature
sensor, sensor power supply or coolant loss sensor. 1-for engine shutdown.
P005 - Coolant Loss Sensor Installed: tells whether or 0-for gensets without a coolant loss sensor
not the optional engine coolant loss sensor is installed on 0 1
the genset. 1-for gensets with coolant loss sensor
5-238
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
P020④ - AC Voltage: nominal AC voltage of the generator. 700, 150, 300, 500, 600, 750, 3.0k,
The GSC+ measures the AC voltage and shows it on the 4.5k, 5.20k, 5.25k, 9.0k, 15.0k, 18.0k, 700 5.20k
display. 30.0k
P021 - AC Current Full Scale: nominal full scale AC current 75, 100, 150, 200, 300, 400, 600, 800,
of the generator. AC current full scale is equal to the ratio of 1000, 1200, 1500, 2000, 2500, 3000, 600A 100A
the external current transformers in the generator housing. and 4000A
5-239
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
① The setpoints (stored or being programmed) must match the specified DPGDS setpoints.
② When oil pressure drops to within 5PSI (34kPa) of the P013 or P014 setpoint, a low oil pressure alarm
is issued by the GSC+.
③ When coolant temperature rises to within 11ºF (6ºC) of the P015 setpoint, a high coolant temperature
alarm is issued by the GSC+.
④ The values other than the default (700V) are for switchgear applications and require the use of external
potential transformers and the removal of the AC voltage range jumper located in the relay module.
The DPGDS unit is factory configured for the 5.20 K value. See the Caterpillar Electronic Modular
Control Panel II+ manual topic AC Voltage Range Selection in the Testing and Adjusting section.
⑤ After setpoint P022 is reprogrammed, the GSC+ must be power cycled (powered down and then
powered up)
5-240
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
5-241
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
TABLE 5.10.1.3.4-5 OP5-1 SETPOINTS (CONTINUED)
SETPOINTS OP5-1 PROTECTIVE RELAYING PROGRAMMING①
FACTORY 60HZ 50HZ
SETPOINT-NAME-DESCRIPTION RANGE OF VALUES
DEFAULT SETPOINT SETPOINT
P118 - Generator Overfrequency Shutdown Time
Delay: amount of time the GSC+ waits before 0 through 120 seconds② in increments 10 seconds 10 seconds 10 seconds
issuing an overfrequency shutdown. of 1
P119 - Generator Underfrequency Alarm Enable: 0 - disabled
the GSC+ enables or disables the generator 1 1 1
underfrequency alarm function. 1 - enabled
5-242
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
5-243
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
5-244
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
③ Battleshort and 50Hz Mode are unique features to DPGDS for spare indicators 2 and 3.
5-245
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
(4) Press the [▲] key to change the value to “0015”. Enables parameter editing.
(5) Press the [◄►] key to accept change and display the parameter number.
(6) Press the [▲] key to the next parameter needed to change.
(9) Press the [◄►] key to accept change and display the parameter number.
(10) Repeat steps ‘5’ through ‘9’ for the each parameter needing to be changed.
NOTE: Parameters 20, 21, 22, 36, 37, and 38 are displayed but not used.
NOTE: Parameters 23 to 29, 39 to 49, 59 and 61 to 89 are not displayed and not used.
5-246
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
33③ KVAR Reference Program Per Unit 00.00-01.00 0000 0.10 0.10
①- Default value for output voltage is different depending on regulator sensing voltage. If the regulator is
designed for 120 volts sensing, then the default output voltage is 4160 volts. All other sensing types
have the default output voltage set to 480 volts.
②- Digital Voltage Regulators with earlier software (KD and earlier) have 1 less digit to the right of the
decimal point.
③- Optional feature.
④- New parameter on serial number prefix KE and later Digital Voltage Regulators.
⑤- Previous range of 0001-099.9 and default value of 002.0
⑥-Previous range of 0001-099.9 and default value of 002.0
(14) Press the [▼] key to change the value to “0009”. Disables DVR parameter editing.
(15) Press the [◄►] key to accept change and display the parameter number.
5-247
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
Starting from the left rear of the PU and working around the PU in a clockwise direction, perform the
following checks (Gen. 1 is on the left and Gen. 2 is on the right):
5-248
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
① The Battery Parallel Switch should be left in the OFF position except in extreme conditions where
the additional DC power is required to crank an engine. Once started, return the switch to the OFF
position.
5-249
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
WARNING
ENSURE ALL PERSONNEL ARE CLEAR AND THE PU DOORS ARE CLOSED
PRIOR TO STARTING A GENERATOR.
WARNING
WARNING
WARNING
5-250
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
6 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
7 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
8 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
9 Close BCS-G1, toggle the Phase Rotation Test Light switch, verify that light ABC lights,
open BCSG1
12 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
13 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
14 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
15 Close BCS-G2, toggle the Phase Rotation Test Light switch, verify that light ABC lights,
open BCSG2
① If the wrong frequency light is on, open the Master Control Door and change the Frequency
Selector Switch (FSS) to the desired frequency.
5-251
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
a. Remove the ORT from its case and set it up on a flat and level surface.
b. Remove the mouse from the case and plug it into the mouse (PS2) port on the back of the ORT.
c. If 120VAC power is available, connect the ORT power supply cord to the 120VAC power. The
ORT can operate up to three hours on its batteries.
d. Connect one end of the 150-foot patch cable to the ORT networking port on the PU.
e. Route the cable from the ORT to the PU and connect the cable to the ORT port.
h. Select the EquipID pop-up screen and enter the necessary information for the units. This
includes the Trailer ID number, the Engine ID number, and the Generator ID number for each
PU.
i. Select the Oneline pop-up screen and enter the descriptor for the main load connected to the
feeders.
5-252
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
TABLE 5.10.1.3.8-1
PDC CONTROL SWITCH SETUP
PANEL SWITCH 1ST PU 2ND PU 3RD PU 4TH PU
Pushed In Pushed In Pushed In Pushed In
DC Power
(ON) (ON) (ON) (ON)
SMS OFF OFF OFF OFF
PRIME PRIME PRIME PRIME
GMS
POWER POWER POWER POWER
MASTER CONTROL PANEL PRIME PRIME PRIME PRIME
AVRS
MCP POWER POWER POWER POWER
60Hz Light ON① ON① ON① ON①
USS A② B② C② D②
BSS NORMAL NORMAL NORMAL NORMAL
SSS OFF OFF OFF OFF
SSL All OFF All OFF All OFF All OFF
50/60 50/60 50/60 50/60
INSIDE MCP FSS
Hertz① Hertz① Hertz① Hertz①
Emergency
GENERATOR CONTROL Pulled-Out Pulled-Out Pulled-Out Pulled-Out
Stop
PANEL GCPG1
ECS OFF OFF OFF OFF
Emergency
GENERATOR CONTROL Pulled-Out Pulled-Out Pulled-Out Pulled-Out
Stop
PANEL GCPG2
ECS OFF OFF OFF OFF
① With the SMS in the OFF position, the 50/60Hz lights indicate the position of the Frequency
Selector Switch (FSS). If the wrong light is on, open the door and change the switch position.
② No more than one switch can be in the same position in any multi-PU line-up. With the SMS in
OFF, none of the USI lights will be on and any previously set address on the PU is cleared.
5-253
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
5.10.1.4 PLANT STARTUP
WARNING
WARNING
WARNING
ONCE THE SYSTEM STATUS LIGHTS TURN GREEN AND THE MSES IS ENABLED,
THE PU WILL START. ENSURE PERSONNEL ARE CLEAR OF THE PU.
WARNING
ONLY ONE PU MAY BE SELECTED TO ANY ONE USS POSITION DURING MULTIPLE
PU OPERATIONS. OPERATING WITH MORE THAN ONE UNIT AT THE SAME ID
CAUSE UNSAFE AND ERRATIC OPERATIONAL CONDITIONS.
a. At the external switchgear, close the associated connection for each PU supplying power to the
switchgear.
b. At the external switchgear, close the connections between the external switchgears.
c. At the external switchgear, open all the connections of loads to the external switchgear.
NOTE: 1: For complete set-up of the Primary Switching Center (PSC), refer to USAF TO 35F14-1-1
/USA TM9-6115-725-14&P.
NOTE: 2: For Unit Isolation Procedure (any unit) - Plant with PSC, and Unit Re-Installation
Procedure – Plant with PSC, refer to Section 5.9, Section 5.9.6.15, and Section 5.9.6.16.
d. Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
5-254
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
① Hold the MSES in an ENABLE position until the selected USI indicator energizes. The switch
returns to the center position when released. This sets the PU networking address and enables
the control and monitoring.
② No more than one of each indicator can be on for multi-PU operations. The light on should match
USS position. The USI light will de-energize after the SMS has been in OFF for 3 seconds.
③ With the SMS in AUTO any generator started, manually or automatically, will automatically
parallel to the bus. To prevent the generator from paralleling to the bus put the generator’s
breaker in the Pull-To-Lock position.
NOTE: The automatic economizing feature will shutdown one generator every 3 minutes until the
system load is at or below the 360KW/450KVA per generator threshold.
e. At A-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
k. At A-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
5-255
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
m. At B-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
o. At B-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
q. At C-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
s. At C-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
u. At D-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
w. At D-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
y. At the external switchgear, close load connections to supply power to the loads.
z. Ensure generators have assumed load. After the load has stabilized, proceed with the following if
necessary:
aa. Observe the KW, PF and KVAR of each generator at the LCP.
Note: If adjustment is needed for KVAR balance, start with the generator that is the furthest from the average
KVAR (either too low or too high). Make minor adjustments of the Voltage Adjust Rheostat (VAR) until the
KVAR sharing between generators are within +/– 10% of the average plant KVAR load. This adjustment will
typically be required only once during initial power plant setup and is intended to compensate for meter
variations among generators.
CAUTION
Improper adjustment of the VAR can cause a reverse KVAR shutdown of a generator.
5-256
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
This mode of operation places control of all generator starting, stopping, synchronizing, and load
management under the auspices of the Programmable Logic Controller (PLC) system. As long as the
SMS is in AUTO, any generator started, manually or automatically, is automatically synchronized to the
system bus. Care must be taken when starting a generator manually when the SMS is in AUTO. Either
place the associated BCS in Pull-To-Lock (prevent closing to the bus) or ensure it has the red target
visible (allow paralleling to the bus) before starting the engine. The only exception is automatic operation
of the feeder breakers. Auto Mode does not automatically close feeder breakers; it only enables remote
operation of the feeder breakers from the ORT.
5.10.1.5.2 DESCRIPTION
The master controller (the designated “A” unit) will control all connected generators based on the total
system KW/KVA load. The controller shuts down one of the generators after 3 minutes should the system
load drop below a level where the remaining generator load would not exceed 85% (360kW) if a
generator is shutdown. If the load of the remaining generator exceeds 85% (360kW) for one minute, a
standby generator is started and paralleled to the bus. A change of system load is recognized by the
control system and appropriate action is taken to maintain generator load in the 85% (360 KW/450 KVA)
range. The system never automatically shuts down the final generator under normal operating conditions.
The shutdown of the final generator must be done following manual operating procedures. The default
configuration is Economizing Mode on. The economizing mode can be turned off from the ORT. Through
the ORT, the AUTO shut down is disabled but the AUTO start-up remains active to prevent overloading
the online generator(s).
Start-Up Sequence: The automatic controls will continuously monitor the system load. As load on the
system increases, the controls automatically start and place additional units on line in the following
sequence at 1-minute intervals:
5-257
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
Shutdown Sequence: Based on the loading experienced, the controller shuts down generator sets that
are not needed. For the purpose of explanation, we will assume that all generator sets are on line
following an initial startup. Based on load, the controls shut down generator sets in the following
sequence at 3-minute intervals:
a. Safety precautions must be observed while operating or maintaining the PU. Safety
precautions must be observed to ensure that the operator/technician cannot have contact with the
following:
b. Minor troubleshooting can be performed while both engines are running as long as safety
precautions are taken. Refer to the appropriate troubleshooting section for Recommendations.
a. Position the PU in such a way as to allow the plant operator to have full vision of the operator
control panels on the unit.
b. Level the MEP-PU-810B front to rear with the trailer leveling hand crank.
c. Position the PU to provide a minimum of 10 feet of clearance for maintenance access on all
sides of each unit. Ensure that there are no overhead obstructions around the exhaust outlets.
WARNING
FUEL SPILLAGE CAN OCCUR IF THE POWER UNIT LEVEL IS GREATER THAN + 5
DEGREES.
5-258
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
d. Ensure that the ground is capable of supporting the weight of the PU. The site surface should be
as level as possible (+ 5 degrees).
5.10.2.3.1 GROUNDING
WARNING
THERE CAN ONLY BE ONE GROUNDING POINT FOR THE PU. WHEN USING A
NEUTRAL GROUND RESISTER (NGR), IT MUST USE THE PU GROUND ROD TO
AVOID CREATING A GROUND LOOP.
a. Drive an 8-foot ground rod into the earth and should be within 6 feet of the PU and at a location
that minimizes the tripping hazard, until only 6 inches (15 cm) protrudes above the surface.
c. Connect all of the grounding rods together with a #2 AWG copper conductor creating a central
ground grid.
d. Using a #2 AWG copper conductor, secure one end of a ground cable to one of the slotted
ground studs on the PU, see Figure 5.1.3.1-1 or Figure 5.1.3.1-3. Secure the other end of the
ground cable to the ground rod.
f. Test Ground Resistance using Ground Resistance Test Equipment. Resistance must be 25Ω or
less. Refer to Annex H for special equipment required for this task.
g. Remove parking stand plates from their transportation positions inside each rear, side PU door
and slide them into their respective operating positions on the sides of the PDC.
h. Connect the parking stand ground wires to either of the two chassis ground lugs on the PU.
5-259
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
GROUND POINT
GROUND POINT
5-260
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
WARNING
ENSURE THAT THE FUEL LINES ARE PROTECTED FROM ALL ELECTRICAL
CABLES AND ARE ROUTED TO MINIMIZE THE POTENTIAL FOR PHYSICAL
DAMAGE OR CAUSING A TRIPPING HAZARD.
a. Lay out the fuel hoses between the PU, the fuel manifold, and the fuel bladders to establish the
fuel supply system see Figure 5.10.2.3.2-1.
b. Install the external fuel hose for the PU to the Fuel Transfer Pump at the Tow end of the PU.
c. Connect the other end of the fuel hose to the fuel manifold outlets.
d. Connect the 3” hose, with quick-disconnect hose ends, from the fuel manifold to the fuel
bladders.
f. Open only the appropriate fuel manifold valves (once connected to the PU) to supply fuel to the
power units and check for leaks.
5-261
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
WARNING
WARNING
HIGH VOLTAGE MAY CAUSE SEVERE INJURY OR DEATH UPON CONTACT DURING
CHECKOUT OR MAINTENANCE OF THIS EQUIPMENT. USE CAUTION AND AVOID
CONTACT WITH ENERGIZED COMPONENTS. USE HOT STICK WHEN LOAD CABLES
ARE HANDLED.
WARNING
a. Lay out and park the load cables for each phase (A, B, & C) between the PU Tie Output parking
stations and the load.
b. Connect each phase cable to the appropriate phase connection on the Primary Switching Center
(PSC).
NOTE: 1: For complete set-up of the Primary Switching Center (PSC), refer to USAF TO 35F14-1-1
and USA TM9-6115-725-14&P.
NOTE: 2: For Unit Isolation Procedure (any unit) - Plant with PSC, and Unit Re-Installation
Procedure – Plant with PSC, refer to Section 5.9, Section 5.9.6.15, and Section 5.9.6.16.
d. Open the Tie Output connector loadbreak covers on the first PU.
e. Connect the Tie Output Cables to the appropriate phase connectors; ensure there are no cross-
phase connections.
h. Connect the first (A) (B) communication cable to “B” receptacle on first PU.
5-262
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
j. Connect the first (A) (B) communication cable to “A” receptacle on second PU.
k. Connect the second (A) (B) communication cable to “B” receptacle on second PU.
m. Connect the second (A) (B) communication cable to “A” receptacle on third PU.
n. Connect the third (A) (B) communication cable to “B” receptacle on third PU.
p. Connect third (A) (B) communication cable to “A” receptacle on fourth PU.
q. Connect the fourth (A) (B) communication cable to “B” receptacle on fourth PU.
r. Leave the loose end of the fourth cable loose and capped.
(1) Press the [▲] key to get to the top-level menu “1 REPORT STATUS”.
(4) Press the [►] key 2 times to display “6.3 POWER SYSTEM SETTINGS”.
(6) Verify the “P” and “N” values match the following table:
(10) Verify the 50TP “PU” and “TD” settings in Table 5.10.2.3.4-2. In order to edit values,
Press the “Edit” key. Select correct value, and press “Edit” again when correct. Ensure
light is off otherwise you can accidentally change value again.
5-263
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
(12) Verify the 50TN “PU” and “TD” settings in Table 5.10.2.3.4-2.
(18) Verify the 51P “PU”, “TD”, and “C” settings in Table 5.10.2.3.4-3.
(20) Verify the 51N “PU”, “TD”, and “C” settings in Table 5.10.2.3.4-3.
(21) Press the [▲] key 3 times to display “5 PROTECTION LOGIC USER”.
c. Use the following procedure to verify the Generator 1 GSC+ settings in step “d”:
NOTE: Refer to the “EMCPII+ Reference Chart”, located on the interior Generator Control Panel
Door (Look-up)
(2) Press SERVICE MODE key to enter service mode. OP1 is showing on the lower display.
(4) Press SELECT key. “PE -“ with the first dash flashing is showing.
(5) Press SCROLL RIGHT key. “PE 1 -“ with the second dash flashing is showing.
5-264
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
(6) Press SCROLL DOWN key. “PE 13 –“ with the third dash flashing is showing.
(7) Press SCROLL UP key. “PE 132 –“ with the fourth dash flashing is showing.
(8) Press SCROLL DOWN key. “PE 1323 –“ with the fifth dash flashing is showing.
(9) Press SCROLL RIGHT key. “PE13231” with all digits not flashing is showing.
(12) Press SCROLL UP key until “OP5-0” is showing on the lower display.
(13) Press SELECT key. “POO1” followed with the value of the setpoint is showing.
(14) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Table 5.10.2.3.4-4 for the parameter values to be verified.
(15) Repeat step “15” until the desired setpoints are verified.
NOTE: If an incorrect setpoint value is displayed, the value must be changed to match the DPGDS
setpoint value as follows:
(a) With the setpoint with the incorrect value showing on the display, press the
SELECT key. The incorrect value flashes on the display.
(b) Press SCROLL UP or SCROLL DOWN key until the correct value appears
flashing on the display.
(c) Press ENTER. The correct value stops flashing on the display.
(d) Press SCROLL UP or SCROLL DOWN key to continue to verify the remaining
parameter values.
d. At GSC G1, verify the operation settings using the following table:
5-265
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
TABLE 5.10.2.3.4-4 OP5-0 SETPOINTS
SETPOINTS OP5-0 ENGINE/GENERATOR PROGRAMMING①
FACTORY DPGDS
SETPOINT-NAME-DESCRIPTIONS RANGE OF VALUES
DEFAULT SETPOINT
P001 - Fuel Solenoid Type: type of fuel system solenoid 0- ETR fuel solenoid
0 0
used on the genset. 1- ETS fuel solenoid
P002 - Units Shown: type of measurement units shown 0-for English units (PSI, ºF)
0 0
on the GSC+ display. 1-for metric units (kPa, ºC).
P003 - Shutdown Override For Engine Fault: GSC+ 0-for engine shutdown
response to a low engine oil pressure or high coolant 1-for alarm only (shutdown override, no 0 0
temperature fault. engine shutdown).
P004 - Shutdown Override For Sensor Fault: GSC+ 0-for alarm only shutdown override, no
response to a diagnostic fault with the engine oil pressure engine shutdown). 0 0
sensor, coolant temperature sensor, oil temperature
sensor, sensor power supply or coolant loss sensor. 1-for engine shutdown.
P005 - Coolant Loss Sensor Installed: tells whether or 0-for gensets without a coolant loss sensor
not the optional engine coolant loss sensor is installed on 0 1
the genset. 1-for gensets with coolant loss sensor
5-266
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
P020④ - AC Voltage: nominal AC voltage of the generator. 700, 150, 300, 500, 600, 750, 3.0k,
The GSC+ measures the AC voltage and shows it on the 4.5k, 5.20k, 5.25k, 9.0k, 15.0k, 18.0k, 700 5.20k
display. 30.0k
P021 - AC Current Full Scale: nominal full scale AC current 75, 100, 150, 200, 300, 400, 600, 800,
of the generator. AC current full scale is equal to the ratio of 1000, 1200, 1500, 2000, 2500, 3000, 600A 100A
the external current transformers in the generator housing. and 4000A
5-267
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
① The setpoints (stored or being programmed) must match the specified DPGDS setpoints.
② When oil pressure drops to within 5PSI (34kPa) of the P013 or P014 setpoint, a low oil pressure alarm
is issued by the GSC+.
③ When coolant temperature rises to within 11ºF (6ºC) of the P015 setpoint, a high coolant temperature
alarm is issued by the GSC+.
④ The values other than the default (700V) are for switchgear applications and require the use of external
potential transformers and the removal of the AC voltage range jumper located in the relay module.
The DPGDS unit is factory configured for the 5.20 K value. See the Caterpillar Electronic Modular
Control Panel II+ manual topic AC Voltage Range Selection in the Testing and Adjusting section.
⑤ After setpoint P022 is reprogrammed, the GSC+ must be power cycled (powered down and then
powered up)
5-268
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
5-269
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
TABLE 5.10.2.3.4-5 OP5-1 SETPOINTS (CONTINUED)
SETPOINTS OP5-1 PROTECTIVE RELAYING PROGRAMMING①
FACTORY 60HZ 50HZ
SETPOINT-NAME-DESCRIPTION RANGE OF VALUES
DEFAULT SETPOINT SETPOINT
P118 - Generator Overfrequency Shutdown Time
Delay: amount of time the GSC+ waits before 0 through 120 seconds② in increments 10 seconds 10 seconds 10 seconds
issuing an overfrequency shutdown. of 1
P119 - Generator Underfrequency Alarm Enable: 0 - disabled
the GSC+ enables or disables the generator 1 1 1
underfrequency alarm function. 1 - enabled
5-270
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
5-271
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
5-272
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
③ Battleshort and 50Hz Mode are unique features to DPGDS for spare indicators 2 and 3.
5-273
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
(4) Press the [▲] key to change the value to “0015”. Enables parameter editing.
(5) Press the [◄►] key to accept change and display the parameter number.
(6) Press the [▲] key to the next parameter needed to change.
(9) Press the [◄►] key to accept change and display the parameter number.
(10) Repeat steps ‘5’ through ‘9’ for the each parameter needing to be changed.
NOTE: Parameters 20, 21, 22, 36, 37, and 38 are displayed but not used.
NOTE: Parameters 23 to 29, 39 to 49, 59 and 61 to 89 are not displayed and not used.
5-274
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
33③ KVAR Reference Program Per Unit 00.00-01.00 0000 0.10 0.10
①- Default value for output voltage is different depending on regulator sensing voltage. If the regulator is
designed for 120 volts sensing, then the default output voltage is 4160 volts. All other sensing types
have the default output voltage set to 480 volts.
②- Digital Voltage Regulators with earlier software (KD and earlier) have 1 less digit to the right of the
decimal point.
③- Optional feature.
④- New parameter on serial number prefix KE and later Digital Voltage Regulators.
⑤- Previous range of 0001-099.9 and default value of 002.0
⑥-Previous range of 0001-099.9 and default value of 002.0
(14) Press the [▼] key to change the value to “0009”. Disables DVR parameter editing.
(15) Press the [◄►] key to accept change and display the parameter number.
5-275
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
Starting from the left rear of the PU and working around the PU in a clockwise direction, perform the
following checks (Gen. 1 is on the left and Gen. 2 is on the right):
5-276
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
① The Battery Parallel Switch should be left in the OFF position except in extreme conditions where
the additional DC power is required to crank an engine. Once started, return the switch to the OFF
position.
5-277
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
WARNING
ENSURE ALL PERSONNEL ARE CLEAR AND THE PU DOORS ARE CLOSED
PRIOR TO STARTING A GENERATOR.
WARNING
WARNING
WARNING
5-278
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
6 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
7 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
8 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
9 Close BCS-G1, toggle the Phase Rotation Test Light switch, verify that light ABC lights,
open BCSG1
12 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
13 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
14 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
15 Close BCS-G2, toggle the Phase Rotation Test Light switch, verify that light ABC lights,
open BCSG2
① If the wrong frequency light is on, open the Master Control Door and change the Frequency
Selector Switch (FSS) to the desired frequency.
5-279
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
a. Remove the ORT from its case and set it up on a flat and level surface.
b. Remove the mouse from the case and plug it into the mouse (PS2) port on the back of the ORT.
c. If 120VAC power is available, connect the ORT power supply cord to the 120VAC power. The
ORT can operate up to three hours on its batteries.
d. Connect one end of the 150-foot patch cable to the ORT networking port on the PU.
e. Route the cable from the ORT to the PU and connect the cable to the ORT port.
h. Select the EquipID pop-up screen and enter the necessary information for the units. This
includes the Trailer ID number, the Engine ID number, and the Generator ID number for each
PU.
i. Select the Oneline pop-up screen and enter the descriptor for the main load connected to the
feeders.
5-280
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
5.10.2.3.8 CONTROLS SETUP
Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
TABLE 5.10.2.3.8-1
PDC CONTROL SWITCH SETUP
PANEL SWITCH 1ST PU 2ND PU 3RD PU 4TH PU
Pushed In Pushed In Pushed In Pushed In
DC Power
(ON) (ON) (ON) (ON)
SMS OFF OFF OFF OFF
UTILITY UTILITY UTILITY UTILITY
GMS
PARALLEL PARALLEL PARALLEL PARALLEL
UTILITY UTILITY UTILITY UTILITY
MASTER CONTROL PANEL AVRS
PARALLEL PARALLEL PARALLEL PARALLEL
MCP
60Hz Light ON① ON① ON① ON①
USS A② B② C② D②
BSS NORMAL NORMAL NORMAL NORMAL
SSS OFF OFF OFF OFF
SSL All OFF All OFF All OFF All OFF
50/60 50/60 50/60 50/60
INSIDE MCP FSS
Hertz① Hertz① Hertz① Hertz①
Emergency
GENERATOR CONTROL Pulled-Out Pulled-Out Pulled-Out Pulled-Out
Stop
PANEL GCPG1
ECS OFF OFF OFF OFF
Emergency
GENERATOR CONTROL Pulled-Out Pulled-Out Pulled-Out Pulled-Out
Stop
PANEL GCPG2
ECS OFF OFF OFF OFF
① With the SMS in the OFF position, the 50/60Hz lights indicate the position of the Frequency
Selector Switch (FSS). If the wrong light is on, open the door and change the switch position.
② No more than one switch can be in the same position in any multi-PU line-up. With the SMS in
OFF, none of the USI lights will be on and any previously set address on the PU is cleared.
5-281
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
5.10.2.4.1 GENERAL
WARNING
WARNING
CAUTION
DO NOT SET THE DESIRED LOAD ON THE ORT SLIDEBAR FOR A UTILITY
PARALLEL PU OR PLANT TO A VALUE THAT EXCEEDS THE TOTAL AVAILABLE
LOAD. PARALLELED PRIME POWER GENERATORS MAY BE REVERSE
POWERED AND TRIP OFFLINE. PLANT OPERATORS MUST MONITOR THE TOTAL
PLANT LOAD TO PREVENT THE UTILITY PARALLEL PU OR PLANT FROM OVER-
POWERING THE SYSTEM. SET THE DESIRED LOAD ON THE ORT SLIDEBAR FOR
A UTILITY PARALLEL PU OR PLANT TO A VALUE THAT PREVENTS OVERLOAD
OF THE PRIME POWER GENERATORS. FAILURE TO FOLLOW THIS CAUTION
MAY RESULT IN DESTRUCTION OF CONNECTED EQUIPMENT.
CAUTION
SETTING THE DESIRED LOAD ON THE ORT FOR A UTILITY PARALLEL PLANT TO
A VALUE THAT CAUSES THE PLANT OUTPUT TO REDUCE THE LOAD ON A
PARALLELED PRIME POWER PLANT BELOW ECONOMIZER SETTINGS WILL
CAUSE PRIME POWER PLANT GENERATORS TO SHUT DOWN.
Operating one PU utility parallel power plant with another PU power plant should be done with the PUs
operating in automatic mode. This provides the operator with control over the amount of load the
generators will carry. Operating PUs in manual in the Utility Parallel Mode limits the units to carrying only
25KW per generator. The PUs can be started and put online manually, but should be operated
automatically using an ORT.
5-282
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
Use Section 5.5.4 (Starting up a Multi-PU Prime Power Plant in Manual Mode) procedure 2.5 to start the
plant manually. Use Section 5.9.6.12 to change the units to Auto Mode to allow changing the load.
WARNING
ONCE THE SYSTEM STATUS LIGHTS TURN GREEN AND THE MSES IS ENABLED,
THE PU WILL START. ENSURE PERSONNEL ARE CLEAR OF THE PU.
WARNING
ONLY ONE PU MAY BE SELECTED TO ANY ONE USS POSITION DURING MULTIPLE
PU OPERATIONS. OPERATING WITH MORE THAN ONE UNIT AT THE SAME ID
CAUSE UNSAFE AND ERRATIC OPERATIONAL CONDITIONS.
Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
TABLE 5.10.2.4.3-1
SWITCH SETUP – AUTOMATIC MODE
PANEL SWITCH 1ST PU 2ND PU 3RD PU 4TH PU
BCS-T Red Target Red Target Red Target Red Target
MASTER CONTROL PANEL
MCP
SMS AUTO③ AUTO③ AUTO③ AUTO③
USS A B C D
GENERATOR CONTROL BCS-G1 Red Target Red Target Red Target Red Target
PANEL 1 GCPG1 ECS-1 AUTO AUTO AUTO AUTO
GENERATOR CONTROL BCS-G2 Red Target Red Target Red Target Red Target
PANEL 2 GCPG2 ECS-2 AUTO AUTO AUTO AUTO
MASTER CONTROL PANEL MSES Enable① Enable① Enable① Enable①
MCP USI A①, ② B①, ② C① , ② D① , ②
① Hold the MSES in an ENABLE position until the selected USI indicator energizes. The switch
returns to the center position when released. This sets the PU networking address and enables
the control and monitoring.
② No more than one of each indicator can be on for multi-PU operations. The light on should match
USS position. The USI light will de-energize after the SMS has been in OFF for 3 seconds.
③ With the SMS in AUTO any generator started, manually or automatically, will automatically
parallel to the bus. To prevent the generator from paralleling to the bus put the generator’s
breaker in the Pull-To-Lock position.
5-283
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
a. At A-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
g. At A-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
i. At B-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
k. At B-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
m. At C-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
o. At C-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
q. At D-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
s. At D-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
u. Observe that each generator assumes 25KW when it parallels to the bus.
v. From the ORT, set the desired load for each generator to carry. The load value shown on the
ORT is on a per generator basis.
w. At the external switchgear, close load connections to supply power to the loads.
5-284
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
x. Ensure generators have assumed load. After the load has stabilized, proceed with the following if
necessary:
Note: If adjustment is needed for KVAR balance, start with the generator that is the furthest from the average
KVAR (either too low or too high). Make minor adjustments of the Voltage Adjust Rheostat (VAR) until the
KVAR sharing between generators are within +/– 10% of the average plant KVAR load. This adjustment will
typically be required only once during initial power plant setup and is intended to compensate for meter
variations among generators.
CAUTION
Improper adjustment of the VAR can cause a reverse KVAR shutdown of a generator.
NOTE: The automatic economizing feature is disabled while a generator is operating in Utility
Parallel mode.
The power plant must be in Auto Mode to be operated remotely or adjust the load on the generators.
a. Ensure there is sufficient Plant 1 generator capacity online to carry the combined Plant 1 and
Plant 2 load.
c. Open each Plant 2 generator breaker from the ORT or locally from its respective LCP.
d. Place each Plant 2 PU in manual by placing its respective SMS in MANUAL without stopping in
OFF.
f. Place all Plant 2 generators in cooldown by placing all Plant 2 SMS switches in OFF.
j. Unload all Plant 1 generators by opening all load breakers, either at the external switchgear or at
the PU if the PU feeder breakers are used.
k. Place each Plant 1 PU in manual by placing its respective SMS in MANUAL without stopping in
OFF.
5-285
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
m. Place all Plant 1 generators in cooldown by placing all SMS switches to OFF.
r. Open all the external switchgear generator disconnect switches for Plant 1 and Plant 2.
WARNING
NEVER REMOVE POWER CABLES BY HAND, USE HOT STICK AND HIGH
VOLTAGE GLOVES. NEVER TOUCH A HIGH VOLTAGE LEAD OR TERMINAL UNTIL
IT HAS BEEN DISCHARGED TO GROUND. FAILURE TO OBSERVE THE WARNING
MAY RESULT IN DEATH BY ELECTROCUTION.
CAUTION
a. Disconnect the (A)(B) communication cables from between the PUs, Reinstall the
communication cable receptacle covers, and store inside the PUs (one per unit).
b. Disconnect the fuel hose from the PU fuel connection and the fuel supply.
c. Drain any fuel from the hoses into an auxiliary fuel supply and store the hoses.
a. Remove ground connections from the PU and store with the ground rod.
5-286
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
c. Remove the parking stations from their operating positions and reinstall them in their
transportation locations on the inside of the PU rear side access doors.
The Power Unit may be safely shipped with oil, fuel, and coolant at maximum capacities or less. Draining
fluids is not required unless federal, state, or local regulations prohibit shipment with fluids present. Refer
to Section 14.3.1.1, Section 13.4.5.5 and Section 6.5.3 for procedures for draining the oil, coolant and fuel
liquids respectively
5-287
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM: 01646.1R0253/1R0254
5-288
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CHAPTER 5.11
OPERATING INSTRUCTIONS
5-289
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5.11.5.2 DESCRIPTION ...........................................................................................................315
5-290
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF FIGURES
FIGURE TITLE PAGE
FIGURE 5.11.3.1-1 MEP-PU-810A GROUND POINTS 295
FIGURE 5.11.3.2-1 EXTERNAL FUEL SUPPLY, TYPICAL FOR EACH 4 PU PLANT 296
5-291
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF TABLES
TABLE TITLE PAGE
TABLE 5.11.3.4-1 CT RATIO SETTINGS 290
5-292
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Safety precautions must be observed while operating or maintaining the PU. Safety
precautions must be observed to ensure that the operator/technician cannot have contact with the
following:
b. Minor Troubleshooting can be performed while both engines are running as long as
safety precautions are taken. Refer to the appropriate troubleshooting section for
recommendations.
a. Position the PU in such a way as to allow the plant operator to have full vision of the operator
control panels on the unit.
b. Level the MEP-PU-810B front to rear with the trailer leveling hand crank.
c. Position the PU to provide a minimum of 10 feet of clearance for maintenance access on all
sides of each unit. Ensure that there are no overhead obstructions around the exhaust outlets.
WARNING
FUEL SPILLAGE CAN OCCUR IF THE POWER UNIT LEVEL IS GREATER THAN + 5
DEGREES.
d. Ensure that the ground is capable of supporting the weight of the PU. The site surface should be
as level as possible (+ 5 degrees).
5-293
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5.11.3.1 GROUNDING
a. Drive an 8-foot ground rod into the earth. It should be within 6 feet of the PU and at a location
that minimizes the tripping hazard, until only 6 inches (15 cm) protrudes above the surface.
c. Connect all of the grounding rods together with a #2 AWG copper conductor creating a central
ground grid.
d. Using a #2 AWG copper conductor, secure one end of a ground cable to one of the slotted
ground studs on the PU, see Figure 5.11.3.1-1 or Figure 5.11.3.1-2. Secure the other end of the
ground cable to the ground rod.
f. Test Ground Resistance using Ground Resistance Test Equipment. Resistance must be 25Ω or
less. Refer to Annex H for special equipment required for this task.
g. Remove parking stand plates from their transportation positions inside each rear, side PU door
and slide them into their respective operating positions on the sides of the PDC.
h. Connect the parking stand ground wires to either of the two chassis ground lugs on the PU.
5-294
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-295
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
ENSURE THAT THE FUEL LINES ARE PROTECTED FROM ALL ELECTRICAL
CABLES AND ARE ROUTED TO MINIMIZE THE POTENTIAL FOR PHYSICAL
DAMAGE OR CAUSING A TRIPPING HAZARD.
a. Lay out the fuel hoses between the PU, the fuel manifold, and the fuel bladders to establish the
fuel supply system see. Figure 5.11.3.2-1. This is a typical set-up for each 4 PU plant.
b. Install the external fuel hose for the PU to the Fuel Transfer Pump at the Tow end of the PU.
c. Connect the other end of the fuel hose to the fuel manifold outlets.
d. Connect the 3” hose, with quick-disconnect hose ends, from the fuel manifold to the fuel
bladders.
f. Open only the appropriate fuel manifold valves (once connected to the PU) to supply fuel to the
power units and check for leaks.
5-296
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
a. Lay out and park the load cables for each phase (A, B, & C) on the PU Tie Output parking
stations on all PUs.
b. Connect each phase cable to the appropriate phase connection on the Primary Switching Center
(PSC). Refer to Figure 5.11.3.3-1 for Two-Plant and PSC layout diagram
d. Open the Tie Output connector loadbreak covers on the first PU.
e. Connect the Tie Output Cables to the appropriate phase connectors; ensure there are no cross-
phase connections.
i. Install the Multi-Plant Expansion Adapter between plant 1 D unit and plant 2 A unit (See figure
5.11.3.3-2). The Adapter is stored inside the PDC of the PU behind the door rails. Ensure that D
unit on plant two has the second communication cable installed and the loose end is capped.
5-297
FIGURE 5.11.3.3-1
ORT ORT
PLANT 1 PLANT 2
Plant Expansion
A B C D Adapter A B C D
G1 G2 G1 G2 G1 G2 G1 G2 G1 G2 G1 G2 G1 G2 G1 G2
52G1 52G2 52G1 52G2 52G1 52G2 52G1 52G2 52G1 52G2 52G1 52G2 52G1 52G2 52G1 52G2
52F2 52T 52F2 52T 52F2 52T 52F2 52T 52F2 52T 52F2 52T 52F2 52T 52F2 52T
TWO-PLANT LAYOUT DIAGRAM
5-298
PSC 1 PSC 2
PSC 3 PSC 4
6 5 4 3 2 6 5 4 3 2 1
1
LOAD
LOAD LOAD
LOAD
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-299
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(1) Press the [▲] key to get to the top-level menu “1 REPORT STATUS”.
(4) Press the [►] key 2 times to display “6.3 POWER SYSTEM SETTINGS”.
(6) Verify the “P” and “N” values match the following table:
(10) Verify the 50TP “PU” and “TD” settings in Table 5.11.3.4-2. In order to edit values, Press
the “Edit” key. Select correct value, and press “Edit” again to save changes. Ensure
light is off otherwise you can accidentally change value again.
5-290
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(18) Verify the 51P “PU”, “TD”, and “C” settings in Table 5.11.3.4-3.
(21) Press the [▲] key 3 times to display “5 PROTECTION LOGIC USER”.
c. Use the following procedure to verify the Generator 1 and Generator 2 GSC+ settings in step “d”:
NOTE: Refer to the “EMCPII+ Reference Chart”, located on the interior Generator Control Panel
Door (Look-up)
(2) Press SERVICE MODE key to enter service mode. OP1 is showing on the lower display.
(4) Press SELECT key. “PE -“ with the first dash flashing is showing.
(5) Press SCROLL RIGHT key. “PE 1 -“ with the second dash flashing is showing.
(6) Press SCROLL DOWN key. “PE 13 –“ with the third dash flashing is showing.
(7) Press SCROLL UP key. “PE 132 –“ with the fourth dash flashing is showing.
(8) Press SCROLL DOWN key. “PE 1323 –“ with the fifth dash flashing is showing.
(9) Press SCROLL RIGHT key. “PE13231” with all digits not flashing is showing.
(12) Press SCROLL UP key until “OP5-0” is showing on the lower display.
(13) Press SELECT key. “POO1” followed with the value of the setpoint is showing.
(14) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Table 5.11.3.4-4 for the parameter values to be verified. Repeat until the desired
setpoints are verified.
5-291
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(18) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use Table 5.11.3.4-5 OP5-1 Setpoints for the parameter values to be verified. Repeat until
all the desired setpoints are verified.
(21) Press SCROLL UP or SCROLL DOWN key. The next setpoint with its value is showing.
Use “OP6” Setpoints, Table 5.11.3.4-6 for the parameter values to be verified. Repeat until
all the desired setpoints are verified.
NOTE: If an incorrect setpoint value is displayed, the value must be changed to match the DPGDS
setpoint value as follows:
(a) With the setpoint with the incorrect value showing on the display, press the
SELECT key. The incorrect value flashes on the display.
(b) Press SCROLL UP or SCROLL DOWN key until the correct value appears
flashing on the display.
(c) Press ENTER. The correct value stops flashing on the display.
(d) Press SCROLL UP or SCROLL DOWN key to continue to verify the remaining
parameter values.
d. At GSC G1 and GSC G2, verify the operation settings using the following table:
5-292
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
P005 - Coolant Loss Sensor Installed: tells whether or 0-for gensets without a coolant loss sensor
not the optional engine coolant loss sensor is installed on 0 1
the genset. 1-for gensets with coolant loss sensor
5-293
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
P020④ - AC Voltage: nominal AC voltage of the generator. 700, 150, 300, 500, 600, 750, 3.0k,
The GSC+ measures the AC voltage and shows it on the 4.5k, 5.20k, 5.25k, 9.0k, 15.0k, 18.0k, 700 5.20k
display. 30.0k
P021 - AC Current Full Scale: nominal full scale AC current 75, 100, 150, 200, 300, 400, 600, 800,
of the generator. AC current full scale is equal to the ratio of 1000, 1200, 1500, 2000, 2500, 3000, 600A 100A
the external current transformers in the generator housing. and 4000A
5-294
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
① The setpoints (stored or being programmed) must match the specified DPGDS setpoints.
② When oil pressure drops to within 5PSI (34kPa) of the P013 or P014 setpoint, a low oil pressure alarm
is issued by the GSC+.
③ When coolant temperature rises to within 11ºF (6ºC) of the P015 setpoint, a high coolant temperature
alarm is issued by the GSC+.
④ The values other than the default (700V) are for switchgear applications and require the use of external
potential transformers and the removal of the AC voltage range jumper located in the relay module.
The DPGDS unit is factory configured for the 5.20 K value. See the Caterpillar Electronic Modular
Control Panel II+ manual topic AC Voltage Range Selection in the Testing and Adjusting section.
⑤ After setpoint P022 is reprogrammed, the GSC+ must be power cycled (powered down and then
powered up)
5-295
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-296
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE 5.11.3.4-5 OP5-1 SETPOINTS (CONTINUED)
SETPOINTS OP5-1 PROTECTIVE RELAYING PROGRAMMING①
FACTORY 60HZ 50HZ
SETPOINT-NAME-DESCRIPTION RANGE OF VALUES
DEFAULT SETPOINT SETPOINT
P118 - Generator Overfrequency Shutdown Time
Delay: amount of time the GSC+ waits before 0 through 120 seconds② in increments 10 seconds 10 seconds 10 seconds
issuing an overfrequency shutdown. of 1
P119 - Generator Underfrequency Alarm Enable: 0 - disabled
the GSC+ enables or disables the generator 1 1 1
underfrequency alarm function. 1 - enabled
5-297
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-298
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-299
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
③ Battleshort and 50Hz Mode are unique features to DPGDS for spare indicators 2 and 3.
5-300
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(4) Press the [▲] key to change the value to “0015”. Enables parameter editing.
(5) Press the [◄►] key to accept change and display the parameter number.
(6) Press the [▲] key to the next parameter needed to change.
(9) Press the [◄►] key to accept change and display the parameter number.
(10) Repeat steps ‘5’ through ‘9’ for the each parameter needing to be changed.
NOTE: Parameters 20, 21, 22, 36, 37, and 38 are displayed but not used.
NOTE: Parameters 23 to 29, 39 to 49, 59 and 61 to 89 are not displayed and not used.
5-301
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
33③ KVAR Reference Program Per Unit 00.00-01.00 0000 0.10 0.10
①- Default value for output voltage is different depending on regulator sensing voltage. If the regulator is designed for 120
volts sensing, then the default output voltage is 4160 volts. All other sensing types have the default output voltage set to 480 volts.
②- Digital Voltage Regulators with earlier software (KD and earlier) have 1 less digit to the right of the decimal point.
③- Optional feature.
④- New parameter on serial number prefix KE and later Digital Voltage Regulators.
(14) Press the [▼] key to change the value to “0009”. Disables DVR parameter editing.
5-302
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(15) Press the [◄►] key to accept change and display the parameter number.
5-303
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5.11.3.5 PRE-OPERATION CHECKS
Starting from the left rear of the PU and working around the PU in a clockwise direction, perform the
following checks (Gen. 1 is on the left and Gen. 2 is on the right):
5-304
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
① The Battery Parallel Switch should be left in the OFF position except in extreme conditions where
the additional DC power is required to crank an engine. Once started, return the switch to the OFF
position. If the battery parallel switch is left in the “ON” position, it could cause one of the generators in
the PU to shut down when the other generator is tyring to start.
5-305
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Turn on the ORT and log in as administrator using the procedures of PSC Manual (Table 3.3.2-1
DPGDS ORT ADMINISTRATOR LOG-IN PROCEDURE).
e. Connect the communication cable between the ORT to the left (Ways 3 and 4) Overcurrent
Relay (OCR).
NOTE: Refer to S&C Instruction Sheet 681-515 page 14, PROGRAMMING to change
settings.
The User Password “6601” must be entered to change control settings and test trip the
solenoids.
m. Type in Password-6601
r. Return to the main menu and test the “Trip Function” of each interrupter using the Test Trip
Menu.
s. Return to the Main Menu and “Disconnect” using Windows HyperTerminal when desired
programming action is complete.
5-306
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CAUTION
u. Repeat steps e. through t. for the right OCR (Ways 5 and 6).
5-307
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
ENSURE ALL PERSONNEL ARE CLEAR AND THE PU DOORS ARE CLOSED
PRIOR TO STARTING A GENERATOR.
WARNING
WARNING
WARNING
5-308
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
6 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
7 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
8 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
9 Close BCS-G1, toggle the Phase Rotation Test Light switch, verify that light ABC lights,
open BCS-G1
12 Verify the engine accelerates to 1800RPM Verify the engine accelerates to 1500RPM
13 Adjust the generator frequency to 60Hz Adjust the generator frequency to 50Hz using
using the Frequency Adjust Rheostat (FAR) the Frequency Adjust Rheostat (FAR)
14 Adjust the generator voltage to 4295VAC Adjust the generator voltage to 3915VAC
using the Voltage Adjust Rheostat (VAR) using the Voltage Adjust Rheostat (VAR)
15 Close BCS-G2, toggle the Phase Rotation Test Light switch, verify that light ABC lights
17 At each PDC toggle the Phase Rotation Test Light switch, verify that light ABC lights②
① If the wrong frequency light is on, open the Master Control Door and change the Frequency
Selector Switch (FSS) to the desired frequency with the SMS in OFF.
② If wrong phase rotation lights (CBA), shutdown plant and check for proper cable connections
5-309
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
Complete the switch arrangements according to the following Table, and verify the lamp
indicators:
CAUTION
ENSURE THAT THE PLANT EXPANSION ADAPTER IS INSTALLED BETWEEN PLANT 1 D UNIT
AND PLANT 2 A UNIT. DAMAGE TO THE PLANT OR IMPROPER OPERATION MAY OCCUR IF
THE DEVICE IS NOT INSTALLED
5-310
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Remove the ORT from its case and set it up on a flat and level surface.
b. Remove the mouse from the case and plug it into the mouse (PS2) port on the back of the ORT
(if needed).
c. If 120VAC power is available, connect the ORT power supply cord to the 120VAC power. The
ORT can operate up to three hours on its batteries.
d. Connect one end of the 150-foot patch cable to the ORT networking port on the back of ORT.
e. Route the cable from the ORT to the PU and connect the cable to the ORT port on the bottom of
PDC on Gen 1 side.
5-311
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
i.. Select the EquipID pop-up screen and enter the necessary information for the units. This
includes the Trailer ID number, the Engine ID number, and the Generator ID number for each
PU.
j. Select the Oneline pop-up screen and enter the descriptor for the main load connected to the
feeders.
WARNING
ONCE THE SYSTEM STATUS LIGHTS TURN GREEN AND THE MSES IS ENABLED,
THE PU WILL START. ENSURE PERSONNEL ARE CLEAR OF THE PU.
WARNING
WARNING
CAUTION
CAUTION
5-312
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. At the Primary Switching Center (PSC), close the associated connection for each PU supplying
power to the switchgear and close and pad lock the PSC interconnect switches when using more
than one primary switch.
d. Complete the switch arrangements according to the following Table, and verify the lamp
indicators. Set all units up before enabling the MSES at Master Control Panel.
NOTE: The automatic economizing feature will shutdown one generator every 3 minutes until the
system load is at or below the 350KW/470KVA per generator threshold.
NOTE: Enable all units MSES and observe the following:
PLANT 1
e. At A-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
5-313
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
g. At A-unit, observe the Tie breaker automatically closes.
k. At A-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
m. At B-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
o. At B-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
q. At C-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
s. At C-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
u. At D-unit, observe Generator 1 automatically starts and accelerates to operating voltage and
frequency.
w. At D-unit, observe Generator 2 automatically starts and accelerates to operating voltage and
frequency.
Plant 2
Observe steps e through x above.
y. At the external switchgear, close all switches/breakers connecting the external switchgear to the
load (s).
z. Ensure generators have assumed load. After the load has stabilized for both power
plants, proceed with the following if necessary:
aa. Observe the KW, PF and KVAR of each generator at the LCP.
5-314
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Note: If adjustment is needed for KVAR balance, start with the generator that is the furthest
from the average KVAR (either too low or too high). Make minor adjustments of the
Voltage Adjust Rheostat (VAR) until the KVAR sharing between generators are within +/–
10% of the average plant KVAR load. This adjustment will typically be required only once
during initial power plant setup and is intended to compensate for meter variations among
generators.
CAUTION
Improper adjustment of the VAR can cause a reverse KVAR shutdown of a generator.
This mode of operation places control of all generator starting, stopping, synchronizing, and load
management under the auspices of the Programmable Logic Controller (PLC) system. As long as the
SMS is in AUTO, any generator started, manually or automatically, is automatically synchronized to the
system bus. Care must be taken when starting a generator manually when the SMS is in AUTO. Either
place the associated BCS in Pull-To-Lock (prevent closing to the bus) or ensure it has the red target
visible (allow paralleling to the bus) before starting the engine. The only exception is automatic operation
of the feeder breakers. Auto Mode does not automatically close feeder breakers; it only enables remote
operation of the feeder breakers from the ORT.
5.11.5.2 DESCRIPTION
The master controller (the designated “A” unit in each plant) will control all connected generators, in their
respective plant based on the total system KW/KVA load. The controller shuts down one of the
generators after 3 minutes should the system load drop below a level where the remaining generator load
would not exceed 85% (350kW) if a generator is shutdown. If the load of the remaining generator
exceeds 85% (350kW) for one minute, a standby generator is started and paralleled to the bus. A change
of system load is recognized by the control system and appropriate action is taken to maintain generator
load in the 85% (350 KW/470 KVA) range. The system never automatically shuts down the final generator
under normal operating conditions. The shutdown of the final generator must be done following manual
operating procedures. The default configuration is Economizing Mode on. The economizing mode can be
turned off from the ORT. Through the ORT, the AUTO shut down is disabled but the AUTO start-up
remains active to prevent overloading the online generator(s).
b. Unload all generators by opening all feeder breakers. This must be done locally from the LCP or
ORT.
5-315
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
NEVER REMOVE POWER CABLES BY HAND, USE HOT STICK AND HIGH VOLTAGE
GLOVES. NEVER TOUCH A HIGH VOLTAGE LEAD OR TERMINAL UNTIL IT HAS BEEN
DISCHARGED TO GROUND. FAILURE TO OBSERVE THE WARNING MAY RESULT IN
DEATH BY ELECTROCUTION.
CAUTION
ALLOW ALL OPERATING ENGINES TO SHUT DOWN AND COOL DOWN COMPLETELY.
a. Disconnect the communication cables from between the PUs and store inside the PUs (one per
unit).
b. Disconnect the fuel hose from the PU fuel connection and the fuel supply.
c. Drain any fuel from the hoses into an auxiliary fuel supply and store the hoses.
a. Remove ground connections from the PU and store with the ground rod.
5-316
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
c. Remove the parking stations from their operating positions and reinstall them in their
transportation locations on the inside of the PU rear side access doors.
The Power Unit may be safely shipped with oil, fuel, and coolant at maximum capacities or less. Draining
fluids is not required unless federal, state, or local regulations prohibit shipment with fluids present. Refer
to Section 14.3.1.1, Section 13.4.5.5 and Section 6.5.3 for procedures for draining the oil, coolant and fuel
liquids respectively.
5-317
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
5-318
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CHAPTER 6
SCHEDULED MAINTENANCE
TABLE OF CONTENTS
6-1
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF TABLES
6-2
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF FIGURES
6-3
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
6-4
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
WARNING
WARNING
WARNING
SIDE PANELS ARE HEAVY. USE EXTREME CAUTION WHEN UNBOLTING AND
REMOVING.
WARNING
TOP PANELS ARE HEAVY. USE EXTREME CAUTION WHEN UNBOLTING AND
REMOVING.
6-5
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
WARNING
WARNING
WARNING
WARNING
WARNING
6-6
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
WARNING
WARNING
WARNING
WARNING
6-7
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
ALWAYS WEAR EYE PROTECTION WHEN YOU PERFORM ANY SERVICE WORK
ON A COOLING SYSTEM
WARNING
WARNING
WARNING
WARNING
WARNING
WARNING
6-8
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
DO NOT REMOVE FILLER CAP AFTER OPERATION UNTIL SYSTEM HAS COOLED
DOWN. FAILURE TO ALLOW ENGINE COOLANT TO COOL DOWN COULD RESULT
IN SECOND AND THIRD DEGREE BURNS. CAP MAY BE HALF-TURNED TO
RELIEVE PRESSURE AND THEN REMOVED TO INSPECT COOLANT LEVEL.
WARNING
PERSONAL INJURY CAN RESULT FROM HOT COOLANT, STEAM AND ALKALI.
WARNING
WARNING
WARNING
6-9
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
HOT OIL AND HOT COMPONENTS CAN CAUSE PERSONAL INJURY. DO NOT
ALLOW HOT OIL OR HOT COMPONENTS TO CONTACT THE SKIN. DO NOT DRAIN
THE OIL WHEN THE ENGINE IS COLD. AS THE OIL COOLS, SUSPENDED WASTE
PARTICLES SETTLE ON THE BOTTOM OF THE OIL PAN. THE WASTE PARTICLES
ARE NOT REMOVED WHEN DRAINING COLD OIL. DRAIN THE CRANKCASE WITH
THE ENGINE STOPPED. DRAIN THE CRANKCASE WITH THE OIL WARM. THIS
DRAINING METHOD ALLOWS THE WASTE PARTICLES THAT ARE SUSPENDED IN
THE OIL TO BE DRAINED PROPERLY.
WARNING
HYDRAULIC FLUID IS HOT AND UNDER HIGH PRESSURE. DO NOT PLACE ANY
PART OF YOUR BODY OVER ANY LEAK. SEVERE INJURY CAN OCCUR IF THIS
HAPPENS.
WARNING
DO NOT MIX PETROLEUM BASED OIL WITH BRAKE FLUID. THIS WILL CAUSE
SEAL SWELLING AND NON-FUNCTIONING BRAKES.
WARNING
THE HYDRAULIC PRESSURE HELD IN THE BREAKAWAY LEVER MAY CAUSE THE
LEVER TO SNAP QUICKLY. KEEP HANDS AND FINGERS CLEAR, AS YOU RESET
THE BREAKAWAY MECHANISM. WHEN TOWING, AVOID SHARP TURNS THAT
CAN CAUSE THE ACTUATOR TO BIND AGAINST THE TOW VEHICLE. THIS CAN
DAMAGE THE ACTUATOR AND TRAILER, CAUSING BRAKE FAILURE.
WARNING
WARNING
6-10
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
CAUTION
CAUTION
CAUTION
6-11
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CAUTION
CAUTION
CAUTION
CAUTION
6-12
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Safety precautions must be observed while any maintenance is being performed. Safety
precautions must be observed to ensure that the operator/technician cannot have contact with the
following:
b. Minor Troubleshooting can be performed while both engines are running as long as safety
precautions are taken. Refer to the appropriate troubleshooting section for recommendations.
c. Minor Maintenance can be performed while one generator is running and the other generator
set has been shutdown. Some examples of this maintenance are:
(1) The generator set that has been shut down must be rendered unable to start, and cool
enough for the maintenance to be performed. Procedures to render a generator set
unable to start are:
NOTE: The fuel transfer pump electrical power is normally fed directly from the G1 generator set
battery bank. If you disconnect the G1 battery bank, the external fuel transfer pump will not
function. Place the Fuel Pump Source Switch (S2) into the (G1 or G2 position) for the
generator set not receiving maintenance.
d. Major maintenance or service requires that the PU MUST be shutdown, isolated from any
power plant electrical bus or utility connection, isolated from any power plant control
system, and rendered unable to start. This is accomplished by performing the following:
6-13
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the Communication Cable must be routed to the next PU in order to reestablish
the communication network. In Automatic Mode of operation, if the PU being isolated is
designated as “A” unit then you must redesignate another PU as “A” in accordance with
Section 5.9.4. Re-desgnate a PU Without Plant Shutdown.
6-14
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. The required daily Before (B), During (D) and After (A) Preventive Maintenance Checks and
Services (PMCS) are identified in Table 6.2-1.
b. All Safety Warnings and Cautions in Section 6.1 apply to this Table.
GROUND TERMINALS:
X Ensure the Power Unit, Ground Grid and Load Cable Drain Lines are properly connected to 0.1
Ground.
EXHAUST:
• Check Muffler Flex Connector pipe between engine and roof for condition, leakage and
X X X security. 0.1
• During operation, be alert for development of excessively black, white, or blue exhaust
smoke.
COOLING SYSTEM:
X X X Check radiator for proper coolant level before starting. During operation, check radiator and 0.1
all cooling lines for leakage and security.
6-15
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
FUEL SYSTEM:
• During operation, check all Fuel lines for leakage and security.
X X X 0.2
• Clean fuel strainer at interval specified in Table 6.3-1, Preventive Maintenance Checks
and Services.
FUEL/SEPERATOR:
X X 0.1
Drain Water from Cup.
HYDRAULIC SYSTEM:
• During operation, check all hydraulic lines for leakage and security.
X X X • Replace the 3 Micron (Absolute), Filter at intervals specified in Table 6.3-1, Preventive 0.1
Maintenance Checks and Services.
• Check fluid level. Fluid level should be approximately ¾ full on the tank mounted fluid
level gauge. Look for leaks.
CABLING:
X X • Check for Proper Mechanical Connections and Phase Color Coding. 0.1
• Check for Cable Damage and proper Medium Voltage Cable Terminations.
EXTERNAL FUEL TRANSFER PUMP CONTROLS:
• During Operation, check all fuel lines, valves and pumps for leaks and security.
X X X • Ensure that the position of the External Fuel Transfer Pump Control switches, are in the 0.1
proper position.
• Inspect Fuel Solenoid Valve for leaks, damage.
MEP-PU-810B, DC LIGHTS:
X X 0.1
Check for proper operation.
6-16
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
6-17
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Table 6.3-1 identifies the scheduled preventive maintenance requirements for the MEP-PU-810. The Preventive Maintenance Checks and
Services (PMCS) are to be performed at the intervals identified. All Safety Warnings and Cautions in Section 6.1 apply to this Table.
b. Problems encountered during the MEP-PU-810 operations that do not present safety hazards or do not degrade operations must be identified for
correction during scheduled maintenance periods or at the end of operations, as appropriate.
CAUTION
PROBLEMS WHICH PRESENT SAFETY HAZARDS AND WHICH SIGNIFICANTLY DEGRADE OPERATIONS
REQUIRE THE STOPPING OF ALL OPERATIONS IMMEDIATELY. RECORD ALL DEFICIENCIES AND
SHORTCOMINGS, TOGETHER WITH THE CORRECTIVE ACTION TAKEN, ON THE APPLICABLE FORMS.
6-18
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE 6.3-1 PREVENTIVE MAINTENANCE CHECKS AND SERVICES (SCHEDULED PMCS) (CONTINUED)
INTERVAL (HOURS/GALLONS/YEARS)
INITIAL 250
3,000
(HOURS)
250 HOURS, 1,000 HOURS
(INCLUDE 8,000 16,000 6,000 HOURS
ITEMS TO BE ACTION 2,500 (GAL) HOURS OR 30,000
THE – HOURS OR HOURS OR 60,000 (GAL), COMMENTS
INSPECTED REQUIRED OR SEMI – (GAL),
STANDARD ANNUALLY 3 YEARS OR 6 YEARS
ANNUALLY ANNUALLY OR 3
250 H
YEARS
SERVICE)
See Section 15.4.5,
Section 15.4.6 and
HOSES AND CLAMPS Inspect, Replace ● Section 15.4.7 and
NOTE 1.
See Section 13.4.5
RADIATOR Inspect (Exterior) ● and NOTE 1.
ENGINE VALVE LASH See Section 15.4.8,
AND INJECTOR Inspect, Adjust ● ● and Section 15.4.9
TIMING and NOTE 1.
ENGINE SPEED
SENSOR, (FLYWHEEL Clean, Inspect, See Section 12.4.1.4
HOUSING MOUNTED - Adjust ● ● ● and NOTE 1.
MPU)
ENGINE PROTECTIVE See Section 12.4.1
DEVICES
Inspect ● and NOTE 1.
INSPECT RADIATOR See Section 13.4.3
CAP GASKET
Inspect ● and NOTE 1.
WATER
See Section 13.4.1
TEMPERATURE Replace ● and NOTE 1.
REGULATORS
CRANKSHAFT See Section 6.4.5 and
VIBRATION DAMPER
Inspect ● NOTE 1.
See Section 6.4.7 and
ENGINE MOUNTS Inspect ● NOTE 1.
ENGINE SPEED / Check, Clean, See Section 12.4.1.7
TIMING SENSORS Calibrate ● ● and NOTE 1.
See Section 15.4.2
TURBOCHARGER Inspect ● and NOTE 1.
6-19
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE 6.3-1 PREVENTIVE MAINTENANCE CHECKS AND SERVICES (SCHEDULED PMCS) (CONTINUED)
INTERVAL (HOURS/GALLONS/YEARS)
INITIAL 250
3,000
(HOURS)
250 HOURS, 1,000 HOURS
(INCLUDE 8,000 16,000 6,000 HOURS
ITEMS TO BE ACTION 2,500 (GAL) HOURS OR 30,000
THE – HOURS OR HOURS OR 60,000 (GAL), COMMENTS
INSPECTED REQUIRED OR SEMI – (GAL),
STANDARD ANNUALLY 3 YEARS OR 6 YEARS
ANNUALLY ANNUALLY OR 3
250 H
YEARS
SERVICE)
JACKET WATER See Section 13.4.2
PUMP
Inspect ● and NOTE 1.
See Section 9.4.6 and
STARTING MOTOR Inspect ● NOTE 1.
Test: ●
COOLING SYSTEM
Level 1 Test ● See Section 13.3 and
ELC NOTE 1.
Level 2 Test ●
Change
(At 6000 hours) ●
COOLING SYSTEM
Add See Section 13.3 and
ELC EXTENDER
(At 3000 hours) ● NOTE 1.
PACKAGE
HOUSING ACCESS
DOORS, RAIN CAPS
Inspect ● See Section 8.3.1
HYDRAULIC SYSTEM
STRAINER
Clean ● ● See Section 19.3.1
NOTE 1: For Additional information see SMCS Code: 1000;7500, in SEBU6959-01, or later version and SMCS Code: 1000;7500, in SEBU7163-01, or
later version.
NOTE 2: An annual fluid sample should be taken and analyzed. The fluid change schedule may be adjusted accordingly.
6-20
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Table 6.3.2.1-1 identifies the MEP-PU-810A Running Gear Scheduled Maintenance. The MEP-PU-810A Running Gear Scheduled Maintenance
is to be performed at the intervals identified. All Safety Warnings and Cautions in Section 6.1 apply to this Table.
b. Problems encountered during the MEP-PU-810A operations that do not present safety hazards or do not degrade operations must be identified
for correction during scheduled maintenance periods or at the end of operations, as appropriate.
CAUTION
PROBLEMS WHICH PRESENT SAFETY HAZARDS AND WHICH SIGNIFICANTLY DEGRADE OPERATIONS
REQUIRE THE STOPPING OF ALL OPERATIONS IMMEDIATELY. RECORD ALL DEFICIENCIES AND
SHORTCOMINGS, TOGETHER WITH THE CORRECTIVE ACTION TAKEN, ON THE APPLICABLE FORMS.
6-21
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Check breakaway chain and Must be serviced by a qualified mechanic familiar with
BREAKAWAY SYSTEM At Every Use this type of axle. See NOTE 1.
lever
Inspect for abnormal wear or Must be serviced by a qualified mechanic familiar with
HUB/DRUM ● this type of axle. See NOTE 1.
scoring
WHEEL BEARINGS & Inspect for corrosion or wear. Must be serviced by a qualified mechanic familiar with
● this type of axle. See NOTE 1.
CUPS Clean & repack
Inspect for leakage. Replace if Must be serviced by a qualified mechanic familiar with
SEALS ● this type of axle. See NOTE 1.
removed.
Tighten to specified torque Must be serviced by a qualified mechanic familiar with
WHEEL NUTS & BOLTS ● this type of axle. See NOTE 1.
values
Inspect for cracks, dents or Must be serviced by a qualified mechanic familiar with
WHEELS ● this type of axle. See NOTE 1.
distortion
TIRE INFLATION Inflate tires to manufacturer’s Must be serviced by a qualified mechanic familiar with
● this type of axle. See NOTE 1.
PRESSURE specification
Inspect for cuts, wear, bulging, Must be serviced by a qualified mechanic familiar with
TIRE CONDITION ● this type of axle. See NOTE 1.
etc.
6-22
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Table 6.3.2.2-1 identifies the MEP-PU-810B Running Gear Scheduled Maintenance. The MEP-PU-810B Running Gear Scheduled Maintenance
is to be performed at the intervals identified. All Safety Warnings and Cautions in Section 6.1 apply to this Table.
b. Problems encountered during the MEP-PU-810B operations that do not present safety hazards or do not degrade operations must be identified
for correction during scheduled maintenance periods or at the end of operations, as appropriate.
CAUTION
PROBLEMS WHICH PRESENT SAFETY HAZARDS AND WHICH SIGNIFICANTLY DEGRADE OPERATIONS
REQUIRE THE STOPPING OF ALL OPERATIONS IMMEDIATELY. RECORD ALL DEFICIENCIES AND
SHORTCOMINGS, TOGETHER WITH THE CORRECTIVE ACTION TAKEN, ON THE APPLICABLE FORMS.
6-23
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
6-24
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Table 6.3.3-1 identifies the SR4B Alternator Scheduled Maintenance. The SR4B Alternator Scheduled Maintenance is to be performed at the
intervals identified. All Safety Warnings and Cautions in Section 6.1 apply to this Table.
b. Problems encountered during the SR4B Alternator operations that do not present safety hazards or do not degrade operations must be identified
for correction during scheduled maintenance periods or at the end of operations, as appropriate.
CAUTION
PROBLEMS WHICH PRESENT SAFETY HAZARDS AND WHICH SIGNIFICANTLY DEGRADE OPERATIONS
REQUIRE THE STOPPING OF ALL OPERATIONS IMMEDIATELY. RECORD ALL DEFICIENCIES AND
SHORTCOMINGS, TOGETHER WITH THE CORRECTIVE ACTION TAKEN, ON THE APPLICABLE FORMS.
Every 2000 Hours Lubrication, Ball Bearings Do not over grease. Use only one ounce. See NOTE 1 and NOTE 2 for additional information.
• Rotating Rectifier - Check
Minimum 1 megohm + rated V / 1000 (Typically much higher)
Every 7500 Hours or Annually • Generator – Clean
See NOTE 1 and NOTE 2 for additional information.
• Insulation Check
NOTE 2: For Additional information see SMCS Code: 4450, in SEBU6918-02, or later version and SMCS Code: 4450, in SENR5359-01, or later
version.
6-25
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Table 6.3.4-1 identifies the Primary Distribution Center (PDC) Scheduled Maintenance. The Primary Distribution Center (PDC) Scheduled
Maintenance is to be performed at the intervals identified. All Safety Warnings and Cautions in Section 6.1 apply to this Table.
b. Problems encountered during the Primary Distribution Center (PDC) operations that do not present safety hazards or do not degrade operations
must be identified for correction during scheduled maintenance periods or at the end of operations, as appropriate.
CAUTION
PROBLEMS WHICH PRESENT SAFETY HAZARDS AND WHICH SIGNIFICANTLY DEGRADE OPERATIONS
REQUIRE THE STOPPING OF ALL OPERATIONS IMMEDIATELY. RECORD ALL DEFICIENCIES AND
SHORTCOMINGS, TOGETHER WITH THE CORRECTIVE ACTION TAKEN, ON THE APPLICABLE FORMS.
LOAD TERMINALS
• Damage ● ● See NOTE 1
• Cleanliness ● ● See NOTE 1
• Missing components ● ● See NOTE 1
Inspect for: ● ● See Section 6.4.8
• Damage ● ● See Section 6.4.8
SWITCHGEAR • Cleanliness ● ● See Section 6.4.8
• Missing components ● ● See Section 6.4.8
Perform: Re-torque BUS ● ● See Section 6.4.8
6-26
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
APPLYING HIGH VOLTAGES ACROSS THE CONTACTS OF THE VACUUM INTERRUPTERS MAY PRODUCE X-
RAYS. THE RADIATION MAY INCREASE WITH AN INCREASE IN THE VOLTAGE OR A DECREASE IN THE
DISTANCE BETWEEN THE OPEN CONTACTS. THE LEVELS OF RADIATION GENERATED AT THE
RECOMMENDED TEST VOLTAGES AND NORMAL BREAKER OPEN GAP SPACING ARE EXTREMELY LOW.
HOWEVER, AS A PRECAUTIONARY MEASURE IT IS RECOMMENDED THAT ALL PERSONNEL STAND AT LEAST
THREE FEET AWAY FROM THE BREAKER WHILE TESTING.
6-27
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
CAUTION
6.4.1.2. SERVICE
If leaks or damage are found at the fuel manifold requiring the fuel supply to be interrupted to the
PU the fuel transfer pump shall be shut-off prior to closing the fuel line.
6-28
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
CAUTION
The Front, Middle, Rear Engine / Alternator Support Assembly provides a means of attaching the
Engine/Alternator to the PU Frame Assembly.
Inspect the Front, Middle, Rear Engine / Alternator Support Assembly for the following conditions:
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See Section 6.1.d. for procedures.
b. Inspect the Front, Middle, Rear Engine / Alternator Support Assembly for improper mounting of
the Engine/Alternator.
c. Inspect the Front, Middle, Rear Engine / Alternator Support Assembly for deterioration of the
rubber mounts. Replace defective rubber mounts as necessary.
d. Inspect the Front, Middle, Rear Engine / Alternator Support Assembly for any crack weldments
on the frame.
WARNING
CAUTION
The oil pan assembly, being the lowest point of the engine assembly, provides a means for housing the
oil pump assembly and attachment of oil drain lines.
6-29
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See Section 6.1.d. for procedures.
b. Inspect the Oil Pan Assembly for cracks, nicks, dents or other damage that could cause leakage.
Make repairs as necessary.
c. Inspect the Oil Pan Assembly for evidence of leakage around gasket areas. Make repairs as
necessary.
d. Inspect the Oil Pan Assembly for evidence of leakage around threaded holes. Make repairs as
necessary.
e. Inspect the Oil Pan Assembly for evidence of leakage around the drain plug. Make repairs as
necessary.
6.4.4 INSPECT THE FRONT AND REAR CRANKSHAFT AND ACCESSORY DRIVE SEALS
WARNING
CAUTION
The front and rear crankshaft and accessory drive seals are provided to prevent engine oil from leaking
out of engine block where crankshaft and accessory drive shaft exit engine assembly.
Inspect the Front and Rear Crankshaft and Accessory Drive Seals for the following conditions:
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See Section 6.1.d. for procedures.
b. Inspect the Front and Rear Crankshaft and Accessory Drive Seals for evidence of leakage on the
floor or below the flywheel area and on the front end of the engine (Vibration Damper).
6-30
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
CAUTION
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See Section 6.1.d. for procedures.
WARNING
The Cylinder Head Grounding Stud must have a wire ground to the battery.
Inspect the Cylinder Head Grounding Stud for the following conditions:
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See Section 6.1.d. for procedures.
b. Inspect the Cylinder Head Grounding Studs wiring harness for damage.
c. Inspect the Cylinder Head Grounding Stud for corrosion on the stud.
6-31
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
CAUTION
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See Section 6.1.d. for procedures.
b. Inspect the Engine Mounts for signs of deterioration, if deterioration is found the mount should be
replaced.
c. Inspect the Engine Mounts for proper bolt torque, 150 Ft-Lbs.
WARNING
WARNING
6-32
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See Section 6.1.d. for procedures.
b. Remove the PDC from the PU. See Chapter 22 for reference.
d. Inspect the Internal AC Electrical System Bus for loose connections, physical damage and heat
damage.
e. Inspect the Internal AC Electrical System Bus and associated wiring for signs of insulation
breakdown such as cracked sleeves and burned insulation.
f. Inspect the Internal AC Electrical System Bus Mounting Bolts for proper torque. The torque
should be checked using the following guidelines:
• Annually or other time period required by USAF AFJMAN 32-1082, USA TM 5-684 and
current NETA Standards to verify tightness of accessible bolted electrical connections.
• The proper torque for the Bus mounting bolts is 20 ft. lbs.
6-33
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
CAUTION
If the crankcase breather is not maintained on a regular basis, the crankcase breather will become
plugged. A plugged crankcase breather will cause excessive crankcase pressure that may cause
crankcase seal leakage.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See Section 6.1.c. for procedures.
b. To service the Engine Crankcase Breather, loosen the Engine Crankcase Breather Hose Clamp
and remove the hose from the Engine Crankcase Breather.
c. Loosen and remove the Cover Clamp and Engine Crankcase Breather Cover.
d. Wash the Engine Crankcase Breather Element, in solvent that is clean and non-flammable.
Allow the Engine Crankcase Breather Element to dry before reinstalling it.
f. If the Engine Crankcase Breather cannot be cleaned, install a clean and dry element.
h. Reinstall the Engine Crankcase Breather Hose Clamp on the hose, connect the hose to the
Engine Crankcase Breather Cover and tighten the hose clamp.
The Fume Collector Box Vent Stack contains a rough grade of steel wool that must be cleaned
periodically to keep the vent stack from clogging.
To service the Fume Collector Box Vent Stack, proceed with the following:
6-34
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed
c. Flush the vent stack with one gallon of hot soapy water.
WARNING
The Cylinder Head Grounding Stud must have a wire ground to the battery.
To Service the Cylinder Head Grounding Stud, proceed with the following:
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See Section 6.1.d. for procedures.
b. To Service the Cylinder Head Grounding Stud, re-torque the Cylinder Head Grounding Stud to
35 ± 7 ft-lbs at every oil change. Ground wires and straps should be combined at engine
grounds. All grounds should be tight and free of corrosion.
c. To Service the Cylinder Head Grounding Stud, clean the Cylinder Head Grounding Stud and the
terminals for the cylinder head ground strap with a clean cloth.
d. If the connections are corroded, clean the connections with a solution of baking soda and water.
e. Keep the cylinder head grounding stud and the strap clean and coated with MPGM grease or
petroleum jelly.
6-35
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CYLINDER HEAD
GROUNDING
STUD
6-36
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
CAUTION
Fuel quality is critical to the performance and to the service life of the engine. Water in the fuel tank can
cause excessive fuel system wear. Condensation occurs during the heating and cooling of fuel. The
condensation occurs as the fuel passes through the system fuel system and the fuel returns to the fuel
tank. Draining the fuel tank regularly and obtaining fuel from reliable sources can help to eliminate water
in the fuel.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable rerouted to the
next PU. See Section 6.1.d. for procedures.
b. Inspect the Fuel Tank using a flashlight to view through the filler cap for sediment or water. The
fuel drain is located directly below the filler cap and any sediment or water should be visible. If
detected, Service.
c. To Service the Fuel Tank, empty the Fuel Tank with an external pump.
d. After the Fuel Tank is empty, remove the Fuel Tank Drain Plug and drain the sediment into a
suitable container.
CAUTION
THIS SERVICE MUST BE PERFORMED EVERY 6-MONTHS IF THE PU IS IN STORAGE. IT IS
CRITICAL THAT THE RTU BATTERY BE RECHARGED TO MAINTAIN PROGRAMMED VARIABLES
IN THE RTU MEMORY. IF THE RTU BATTERY IS ALLOWED TO DISCHARGE COMPLETELY, THE
RTU SOFTWARE WILL HAVE TO BE RELOADED BEFORE OPERATION.
a. If the PU is in storage and the batteries have been disconnected, reconnect the batteries.
6-37
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
b. Connect an external 120 VAC power source to the battery chargers and ensure the chargers are
supplying current to the batteries.
d. Turn on the DC Power Circuit Breaker (CB1). The PDC will be powered up and the RTU battery
will recharge through internal circuitry.
e. Leave the 120 VAC power source connected to the battery chargers and the CB1 on for a
minimum of 8 hours to recharge the RTU battery.
f. After 8 hours, Turn off CB1, disconnect the 120 VAC power source to the battery chargers, and
disconnect the PU batteries for continued storage.
NOTE: This service can be performed in conjunction with other service of the PU, has long as the
DC Power remains turned on for 8 continuous hours every 6-months.
6-38
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CHAPTER 7
UNSCHEDULED MAINTENANCE/TROUBLESHOOTING
TABLE OF CONTENTS
7-1
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE OF CONTENTS
7-2
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF TABLES
7-3
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF TABLES
7-4
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
7-5
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
WARNING
WARNING
WARNING
SIDE PANELS ARE HEAVY. USE EXTREME CAUTION WHEN UNBOLTING AND
REMOVING.
WARNING
TOP PANELS ARE HEAVY. USE EXTREME CAUTION WHEN UNBOLTING AND
REMOVING.
7-6
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
WARNING
WARNING
WARNING
WARNING
WARNING
7-7
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
WARNING
WARNING
WARNING
WARNING
7-8
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
ALWAYS WEAR EYE PROTECTION WHEN YOU PERFORM ANY SERVICE WORK
ON A COOLING SYSTEM
WARNING
WARNING
WARNING
WARNING
WARNING
WARNING
7-9
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
DO NOT REMOVE FILLER CAP AFTER OPERATION UNTIL SYSTEM HAS COOLED
DOWN. FAILURE TO ALLOW ENGINE COOLANT TO COOL DOWN COULD RESULT
IN SECOND AND THIRD DEGREE BURNS. CAP MAY BE HALF-TURNED TO
RELIEVE PRESSURE AND THEN REMOVED TO INSPECT COOLANT LEVEL.
WARNING
PERSONAL INJURY CAN RESULT FROM HOT COOLANT, STEAM AND ALKALI.
WARNING
WARNING
WARNING
7-10
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
HOT OIL AND HOT COMPONENTS CAN CAUSE PERSONAL INJURY. DO NOT
ALLOW HOT OIL OR HOT COMPONENTS TO CONTACT THE SKIN. DO NOT DRAIN
THE OIL WHEN THE ENGINE IS COLD. AS THE OIL COOLS, SUSPENDED WASTE
PARTICLES SETTLE ON THE BOTTOM OF THE OIL PAN. THE WASTE PARTICLES
ARE NOT REMOVED WHEN DRAINING COLD OIL. DRAIN THE CRANKCASE WITH
THE ENGINE STOPPED. DRAIN THE CRANKCASE WITH THE OIL WARM. THIS
DRAINING METHOD ALLOWS THE WASTE PARTICLES THAT ARE SUSPENDED IN
THE OIL TO BE DRAINED PROPERLY.
WARNING
WARNING
WARNING
HYDRAULIC FLUID IS HOT AND UNDER HIGH PRESSURE. DO NOT PLACE ANY
PART OF YOUR BODY OVER ANY LEAK. SEVERE INJURY CAN OCCUR IF THIS
HAPPENS.
WARNING
THE HYDRAULIC PRESSURE HELD IN THE SYSTEM MAY CAUSE THE LEVER TO
SNAP QUICKLY. KEEP HANDS AND FINGERS CLEAR, AS YOU RESET THE
BREAKAWAY MECHANISM. WHEN TOWING, AVOID SHARP TURNS THAT CAN
CAUSE THE ACTUATOR TO BIND AGAINST THE TOW VEHICLE. THIS CAN
DAMAGE THE ACTUATOR AND TRAILER, CAUSING BRAKE FAILURE.
WARNING
DO NOT MIX PETROLEUM BASED OIL WITH BRAKE FLUID. THIS WILL CAUSE
SEAL SWELLING AND NON-FUNCTIONING BRAKES.
7-11
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
THE HYDRAULIC PRESSURE HELD IN THE SYSTEM MAY CAUSE THE LEVER TO
SNAP QUICKLY. KEEP HANDS AND FINGERS CLEAR, AS YOU RESET THE
BREAKAWAY MECHANISM. WHEN TOWING, AVOID SHARP TURNS THAT CAN
CAUSE THE ACTUATOR TO BIND AGAINST THE TOW VEHICLE. THIS CAN
DAMAGE THE ACTUATOR AND TRAILER, CAUSING BRAKE FAILURE.
WARNING
WARNING
WARNING
7-12
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
CAUTION
CAUTION
CAUTION
CAUTION
7-13
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CAUTION
CAUTION
CAUTION
CAUTION
CAUTION
CAUTION
7-14
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CAUTION
CAUTION
a. Safety precautions must be observed while any maintenance is being performed. Safety
precautions must be observed to ensure that the operator/technician cannot have contact with the
following:
b. Minor troubleshooting can be performed while both engines are running as long as safety
precautions are taken.
c. Minor maintenance can be performed while one generator set is running and the other
generator set has been shutdown. Some examples of this maintenance are:
(1) The generator set that has been shut down must be rendered unable to start, and cool
enough for the maintenance to be performed. Procedures to render a generator set
unable to start are:
7-15
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(j) Disconnect the 7P1 and 7P2 Connectors located on the inside panel of the PDC.
(k) Close and Lock the generator set control panel.
NOTE: The fuel transfer pump electrical power is normally fed directly from the G1 generator set
battery bank. If you disconnect the G1 battery bank, the external fuel transfer pump will not
function. Place the Fuel Pump Source Switch (S2) into the (G1 or G2 position). Place the S2
in the (G1 or G2) position, for the generator set not receiving maintenance.
d. Major maintenance or service requires that the PU MUST be shutdown, isolated from any
power plant electrical bus or utility connection, isolated from any power plant control
system, and rendered unable to start. This is accomplished by performing the following:
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
7-16
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
All Safety Warnings and Cautions in Section 7.1 apply to this section.
The following Unscheduled Maintenance Procedures are located in Chapter 8 of this manual:
The following Unscheduled Maintenance Procedures are located in Chapter 9 of this manual:
7-17
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following Unscheduled Maintenance Procedures are located in Chapter 10 of this manual:
The following Unscheduled Maintenance Procedures are located in Chapter 11 of this manual:
The following Unscheduled Maintenance Procedures are located in Chapter 12 of this manual:
(3) Remove and install Controls and Instruments within the interior of PDC.
7-18
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following Unscheduled Maintenance Procedures are located in Chapter 13 of this manual:
There are no Unscheduled Maintenance Procedures for Chapter 14, Lubrication System.
The following Unscheduled Maintenance Procedures are located in Chapter 15 of this manual:
There are no Unscheduled Maintenance Procedures for Chapter 16, Air Intake and Exhaust System.
7-19
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
There are no Unscheduled Maintenance Procedures for Chapter 17, Remote Operator Terminal (ORT).
There are no Unscheduled Maintenance Procedures for Chapter 18, Running Gear/Trailer Assembly.
The following Unscheduled Maintenance Procedures are located in Chapter 19 of this manual:
j. Remove and install Engine Compartment Vent Fan Motor Fan Blades.
k. Remove and install Hydraulic Tank Low Level Shutdown Switch (HTLL).
The following Unscheduled Maintenance Procedures are located in Chapter 21 of this manual:
The following Unscheduled Maintenance Procedures are located in Chapter 22 of this manual:
7-20
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
All Safety Warnings and Cautions in Section 7.1 apply to this section.
7-21
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
7-22
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Table 7.3.1-1 contains Basic Engine Troubleshooting Procedures for locating and correcting operating troubles that may develop in the generator
set. Each malfunction, for either an individual component or entire system, is followed by a series of tests or inspections that will help determine
the probable cause and corrective actions to take.
Troubleshoot in accordance with Table 7.3.1-1. All Safety Warnings and Cautions in Section 7.1 apply to this table.
This manual cannot list all malfunctions that may occur, nor all tests or inspections and corrective actions. If a malfunction cannot be corrected by
listed corrective actions, notify supervisor and or contact Radian Inc.
NOTE: Although troubleshooting can be a daunting task. Troubleshooting can be made much easier if you start by isolating the fault first.
The first task is to determine if the system or device is getting the proper inputs AC voltage, AC current, DC voltage and DC current.
Check for loose wires and blown fuses. By isolating the fault by eliminating obvious problems will make the technicians job much
easier. When Caterpillar manuals are referenced, go to the SMCS CODE found in that manual.
2. Check Engine Timing; refer to Section 15.4.8, Section 15.4.9, Section 15.4.10 and Section
ENGINE CRANKS BUT 2. Incorrect Engine Timing
15.4.11 for reference.
WILL NOT START
3. Check for obstructions in the Air Plenum Assembly, refer to Section 16.3.2 for reference.
3. Intake Air • Check Air Filter for obstructions, replace Air Filter as necessary, refer to Section 16.3.2
for reference.
4. Engine Mounted Fuel Pump 4. Check Engine Mounted Fuel Pump; refer to Section 11.4.4 for reference.
7-23
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
4. Engine Mounted Fuel Pump 4. Check Engine Mounted Fuel Pump, refer to Section 11.4.4 for reference.
7-24
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
GENERATOR OUTPUT 2. Check the AVR for proper operations; refer to SENR5833-02 or later version, SMCS CODE:
2. Automatic Voltage Regulator (AVR)
4467 for reference.
FREQUENCY/VOLTAGE
CANNOT BE 3. Check the GSC+ for a shutdown fault, refer to RENR2227-02 or later version, for
3. Engine Fault
MAINTAINED. troubleshooting procedures.
LOW POWER OR LOSS 2. Check for high oil level; refer to Section 14.3.1 for reference.
2. Lubrication System
OF POWER. • Drain excess oil.
7-25
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
PROBLEM 10: 3. Muffler 3. Check the Muffler, refer to Section 8.4.7.1 for reference.
4. Open Fuel Shutoff Valve; refer to Figure 11.3.1-1 for reference.
EXCESSIVE FUEL • Check Fuel Level in Fuel Tank.
CONSUMPTION. • Prime Fuel System; refer to Section 11.3.5 for procedures.
4. Fuel System • Check Fuel Filters, refer to Section 11.3 for reference.
• Check Fuel Quality (Have Fuel Sample Checked), refer to SENR1067-02 or later
version, SMCS CODE: 1280-081 for procedures.
• Perform Fuel System Test and Adjusting; refer to SENR1067-02 or later version, SMCS
CODE: 1250-040 for procedures.
5. Check Engine Timing; refer to Section 15.4.8, Section 15.4.9, Section 15.4.10 and Section
5. Engine Timing
15.4.11 for reference.
7-26
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
1. Inspect Lubrication System for proper operation; refer to Section 14.3.2 for reference.
• Tighten all oil connections.
• Check for external oil leaks.
1. Lubrication System
• Check grade of oil being used against weather conditions that unit is being operated in.
• Inspect for Excessive Oil Consumption; refer to RENRRENR1067-02 or later version,
PROBLEM 11: SMCS CODE: 1348-040 for reference.
2. Check Turbocharger; refer to Caterpillar Manual SENR1068-01 or later version, SMCS
CODE: 1052-040.
EXCESSIVE OIL • Replace if turbocharger does not spin freely or damaged.
CONSUMPTION.
2. Turbocharger • Check turbocharger seals.
• Check turbocharger crossover and exhaust casing for wetness. If wet, turbocharger is
defective.
• Replace defective turbocharger.
3. Check engine crankcase breathers for obstructions, refer to SEBU7163-01 or later version,
3. Engine Crankcase Breathers
SMCS CODE: 1317-070 for reference.
1. Open Fuel Shutoff Valve; refer to Figure 11.3.1-1 for reference.
• Check Fuel Level in Fuel Tank.
• Prime Fuel System; refer to Section 11.3.5 for procedures.
1. Fuel System • Check Fuel Filters, refer to Section 11.3 for reference.
• Check Fuel Quality (Have Fuel Sample Checked), refer to SENR1067-02 or later
version, SMCS CODE: 1280-081 for procedures.
• Perform Fuel System Test and Adjusting; refer to SENR1067-02 or later version, SMCS
CODE: 1250-040 for procedures.
2. Inspect Lubrication System for proper operation; refer to Section 14.3.2 for reference.
PROBLEM 12: • Tighten all oil connections.
• Check for external oil leaks.
CRANKCASE SLUDGE. 2. Lubrication System
• Check grade of oil being used against weather conditions that unit is being operated in.
• Check the oil filter to see if it is clogged.
• Change oil filters more often and observe for proper oil temperature.
3. Check Cooling System for proper operation; refer to Section 13.4 for reference.
• Check coolant for low temperature.
• Check for faulty (stuck open) thermostat.
3. Coolant System
• Test engine coolant thermostats for proper operation. Refer to SENR1067-02, or later
version, SMCS CODE: 1355-081; 1355-081.
• Replace defective thermostats.
7-27
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
1. Check Cooling System for proper operation; refer to Section 13.4 for reference.
• Check coolant for low temperature.
• Check for faulty (stuck open) thermostat.
1. Coolant System • Check for proper coolant level and evidence of leaks.
• Test engine coolant thermostats for proper operation. Replace defective thermostats.
Refer to Caterpillar Manual SENR1067-02, Dated November 2001 or later, SMCS
CODE: 1355-081; 1355-081.
2. Open Fuel Shutoff Valve; refer to Figure 11.3.1-1 for reference.
• Check Fuel Level in Fuel Tank.
PROBLEM 13: • Prime Fuel System; refer to Section 11.3.5 for procedures.
2. Fuel System • Check Fuel Filters, refer to Section 11.3 for reference.
OIL DILUTION • Check Fuel Quality (Have Fuel Sample Checked), refer to SENR1067-02 or later
(CRANKCASE). version, SMCS CODE: 1280-081 for procedures.
• Perform Fuel System Test and Adjusting; refer to SENR1067-02 or later version, SMCS
CODE: 1250-040 for procedures.
3. Inspect Lubrication System for proper operation; refer to Section 14.3.2 for reference.
• Tighten all oil connections.
• Check for external oil leaks.
3. Lubrication System • Check grade of oil being used against weather conditions that unit is being operated in.
• Check the oil filter to see if it is clogged.
• Change oil filters more often and observe for proper oil temperature.
• Take oil sample from crankcase to see if there is evidence of coolant or fuel in the oil.
1. Inspect Lubrication System for proper operation; refer to Section 14.3.2 for reference.
• Tighten all oil connections.
• Check for external oil leaks.
1. Lubrication System
PROBLEM 14: • Check grade of oil being used against weather conditions that unit is being operated in.
• Check the oil filter to see if it is clogged.
LOW OIL PRESSURE. • Check oil level.
2. Engine Oil Pump 2. Check the Engine Oil Pump; refer to SENR1067-02 or later version, SMCS CODE:1304-040
3. Test Oil Pressure Sensor; refer to Caterpillar Manual RENR 2227-01 or later version, Section
3. Oil Pressure Sensor
P – 520.
7-28
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
1. Check Cooling System for proper operation; refer to Section 13.4 for reference.
• Check coolant for low temperature.
PROBLEM 15: • Check for faulty (stuck open) thermostat.
1. Thermostat • Check for proper coolant level and evidence of leaks.
• Test engine coolant thermostats for proper operation. Refer to SENR1067-02, or later
COOLANT
version, SMCS CODE: 1355-081; 1355-081.
TEMPERATURE TOO
LOW. • Replace defective thermostats.
2. Refer to Section 12.4.1.1 and RENR 2227-01, Section P – 516 or later version and
2. Coolant Temperature Sensor Troubleshooting Procedures are found in RENR1067-01 or later version. Replace if
defective.
1. Cooling System Check (Overheating), refer to RENR1067-02 or later version, SMCS CODE:
PROBLEM 16: 1350-535 for reference.
1. Coolant System
• Check the Radiator Cooling fan to see if it functioning properly. Refer to Section 19.4.3
for reference.
COOLANT
2. Check the water pump to see if it functioning properly. Refer to RENR1067-02 or later
TEMPERATURE TOO 2. Water Pump
version, SMCS CODE: 1361-040; 1361-081 for reference.
HIGH. 3. Check crankcase oil level. Use proper grade for weather conditions. Refer to Annex G,
3. Oil Level and Grade
Consumable Operating and Maintenance Supplies.
1. Check crankcase oil level. Use proper grade for weather conditions. Refer to Annex G,
1. Oil Level and Grade
PROBLEM 17: Consumable Operating and Maintenance Supplies.
2. Inspect increased oil temperature. Refer to RENR1067-02 or later version, SMCS CODE:
2. Engine Oil
OIL TEMPERATURE 1348-040.
TOO HIGH.
3. Engine Load 3. Check KW load on the GSC. Make appropriate loading corrections.
7-29
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
7-30
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
1. DC Control Power Circuit Breaker (CBCP) 1. Place CBCP to the ON (Push-in) position.
2. Battery Bank 2. Inspect the battery bank, refer to Section 9.4.1.1.
3. Verify the A/B Control Cable is connected.
3. Control Cables
• Verify the ORT Cable is connected.
4. Control Switch Positions 4. Verify Switch Setup. Refer to Section 5.2.3.8.
5. Engine Faults 5. Clear all Active Engine Faults.
6. Advanced Troubleshooting Procedures: 6. Perform the following Steps:
• GSC+ • Place CBCP to the ON (Push-in) position.
• PCM • Place both ECS in AUTO
• Verify there are no GSC+ shutdowns active.
• CCM
• Place the SMS in AUTO position.
• ATB • Verify that the SSL two green lights are illuminated.
PROBLEM 22: • PT1 • Place running engine ECS to OFF/RESET.
• PT2 • Move the MSES to the ENABLE position (momentary)
• PT3 • Verify that associated ARR relay energizes. Indicator LED that is located on the relay
ENGINE WILL NOT
• CT1 module should illuminate. Refer to FO-22.
START IN AUTO • If the ARR relay does not energize, check for 24VDC between terminal “A1 and “A2” at
• CT2 the coil.
• CT3 • Check for continuity across the ARR contacts. Lack of continuity across the contacts
• CB2 indicates a failed relay module, replace the relay module. A verification check may be
• CB4 done by swapping the relay with one of the spare (SPR) modules.
• Check for 24VDC at the coil; if voltage is present continue to next step. If 24VDC is not
• ECS present; refer to Table 7.3.3-1, Problem 10 to troubleshoot RTU problems.
• ESPB • Check that the engine starts in MANUAL.
• ARR1 • If the engine starts in MANUAL check the wiring from the associated ARR contact to the
• SR GSC+ module.
• If engine does not start refer to RENR 2227-02 or later version, Section 3:
• SMMS
Troubleshooting without a Diagnostic Code; or Section 4: Troubleshooting With a
• FSPR Diagnostic Code. And refer to RENR1200-01 or later version, SMCS CODE: 4490.
7-31
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
1. DC Control Power Circuit Breaker (CBCP) 1. Place CBCP to the ON (Push-in) position.
2. Battery Bank 2. Inspect the battery bank, refer to Section 9.4.1.1.
3. Verify the A/B Control Cable is connected.
3. Control Cables
• Verify the ORT Cable is connected.
4. Control Switch Positions 4. Verify Switch Setup. Refer to Section 5.2.3.8.
5. Engine Faults 5. Clear all Active Engine Faults.
6. Advanced Troubleshooting Procedures: 6. Perform the following Steps:
• GSC+ • Place CBCP to the ON (Push-in) position.
• PCM • Place both ECS in AUTO
• Verify there are no GSC+ shutdowns active.
• CCM
• Place the SMS in AUTO position.
• ATB • Verify that the SSL two green lights are illuminated.
PROBLEM 23: • PT1 • Place running engine ECS to OFF/RESET.
• PT2 • Move the MSES to the ENABLE position (momentary)
• PT3 • Verify that associated ARR relay energizes. Indicator LED that is located on the relay
ENGINE WILL NOT
module should illuminate. Refer to FO-22.
START IN MANUAL • CT1
• If the ARR relay does not energize, check for 24VDC between terminal “A1 and “A2” at
• CT2 the coil.
• CT3 • Check for continuity across the ARR contacts. Lack of continuity across the contacts
• CB2 indicates a failed relay module, replace the relay module. A verification check may be
• CB4 done by swapping the relay with one of the spare (SPR) modules.
• Check for 24VDC at the coil; if voltage is present continue to next step. If 24VDC is not
• ECS present; refer to Table 7.3.3-1, Problem 10 to troubleshoot RTU problems.
• ESPB • Check that the engine starts in MANUAL.
• ARR1 • If the engine starts in MANUAL check the wiring from the associated ARR contact to the
• SR GSC+ module.
• If engine does not start refer to RENR 2227-02 or later version, Section 3:
• SMMS Troubleshooting Without a Diagnostic Code; or Section 4: Troubleshooting With a
• FSPR Diagnostic Code. And refer to RENR1200-01 or later version, SMCS CODE: 4490.
7-32
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
1. DC Control Power Circuit Breaker (CBCP) 1. Place CBCP to the ON (Push-in) position.
2. Battery Bank 2. Inspect the battery bank, refer to Section 9.4.1.1.
3. Verify the A/B Control Cable is connected.
3. Control Cables
• Verify the ORT Cable is connected.
4. Control Switch Positions 4. Verify Switch Setup. Refer to Section 5.2.3.8.
7-33
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
7.3.2 BASIC EMCP+ TROUBLESHOOTING PROCEDURES
Table 7.3.2-1 contains Basic EMCP+ Troubleshooting Procedures for locating and correcting operating troubles that may develop in the generator
set. Each malfunction, for either an individual component or entire system, is followed by a series of tests or inspections that will help determine
the probable cause and corrective actions to take.
Troubleshoot in accordance with Table 7.3.2-1. All Safety Warnings and Cautions in Section 7.1 apply to this table.
This manual cannot list all malfunctions that may occur, nor all tests or inspections and corrective actions. If a malfunction cannot be corrected by
listed corrective actions, notify supervisor and or contact Radian Inc.
NOTE: Although troubleshooting can be a daunting task. Troubleshooting can be made much easier if you start by isolating the fault first.
The first task is to determine if the system or device is getting the proper inputs AC voltage, AC current, DC voltage and DC
current. Check for loose wires and blown fuses. By isolating the fault by eliminating obvious problems will make the technicians
job much easier.
1. DC Control Power Circuit Breaker (CBCP) 1. Place CBCP to the ON (Push-in) position.
PROBLEM
2. Battery Bank 2. Inspect the battery bank, refer to Section 9.4.1.1.
3. Check for 24VDC on the GSC+ between Terminals “RM B+” and “RM28”, refer to FO-12A
EMCP+ NOT or 12B. If GSC still doesn’t function refer problem to Caterpillar.
FUNCTIONING 3. EMCP+ not functioning properly • Refer to 3456 DPGDS Generator Set Engine – Supplement, Dated November 1998.
PROPERLY • RENR1200-01 or later version.
7-34
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Table 7.3.3-1 contains Basic Generator Operations Troubleshooting Procedures information for locating and correcting operating troubles that
may develop in the generator set. Each malfunction, for either an individual component or entire system, is followed by a series of tests or
inspections that will help determine the probable cause and corrective actions to take.
Troubleshoot in accordance with Table 7.3.3-1. All Safety Warnings and Cautions in Section 7.1 apply to this table.
This manual cannot list all malfunctions that may occur, nor all tests or inspections and corrective actions. If a malfunction cannot be corrected by
listed corrective actions, notify supervisor and or contact Radian Inc.
NOTE: Although troubleshooting can be a daunting task. Troubleshooting can be made much easier if you start by isolating the fault first.
The first task is to determine if the system or device is getting the proper inputs AC voltage, AC current, DC voltage and DC current.
Check for loose wires and blown fuses. By isolating the fault by eliminating obvious problems will make the technicians job much
easier.
NOTE: This section of the troubleshooting procedures is needed for component isolation purposes. These procedures make it possible to
rapidly determine what component may be out of adjustment or defective.
NOTE: While troubleshooting within this section, keep in mind that you cannot check continuity across the HUB. You must check continuity
up to and then past the HUB.
7-35
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
7-36
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE: Ensure there is an "A" unit connected, or the ORT will not allow adjustment of the base load
level.
7-37
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
7-38
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE 7.3.3-1 BASIC GENERATOR OPERATIONS TROUBLESHOOTING PROCEDURES (CONTINUED)
COMPONENTS
MALFUNCTION SYMPTOM TEST PROCEDURES
AFFECTED
7-39
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
• 52G1 NOTE: Troubleshooting procedure written for generator #1; substitute 2 or B for troubleshooting
generator #2.
• 52G2
• 15/25A (a) Place CBCP to the ON (Push-in) position.
• 15/25B (b) Check the overcurrent relay for proper operation and active faults; clear any active faults.
Refer to Section 12.4.2.1.2.
• 50/51G1
(c) Place affected engine ECS in STOP/COOLDOWN.
• 50/512 (d) Verify there are no GSC+ shutdowns active.
• PT6 (e) Place affected engine ECS in MANUAL.
• BCSG1 (f) Select the associated generator on SSS.
PROBLEM 5: (g) Verify that relay G1BR has energized by inspecting its indicator.
• BCSG2 (h) If G1BR is not picked up, use a multimeter on the VAC scale, check for 120VAC at terminals
• SSS 300A & CP20A.
Generator breaker does not WARNING
GENERATOR • SBR2
close.
OUTPUT BREAKER • BRG1
HIGH VOLTAGE, USE PROPER PROTECTIVE EQUIPMENT AND PROPER TEST
• BRG2 EQUIPMENT.
WILL NOT OPERATE
• OCR1
• OCR2 (i) If 120VAC is not present at these terminals check transformer PT6 and its fuses.
(j) Check that 52T1 is not energized. If 52T1 is energized go to Table 7.3.3-1, Problem 10.
• 52T1
(k) Place CBCP to the OFF (Pull-out) position.
• 52T2 (l) Check continuity between terminal 300A and terminal 332 with BCSG1 in the CLOSE
• 52C1 position. This will indicate whether the door switches’ contacts are operating.
• 52C2 (m) Check continuity between terminals 332 and 334. This tests the manual sync and dead-bus
close circuit.
• 25M1 (n) Pull-out BRG1 test lever and test for continuity to 52G1 terminal 2. Continuity indicates the
• 25M2 circuit to the breaker close coil is good.
(o) Reset BRG1 test lever.
(p) Test 52G1 circuits on the breaker itself, including the fuse, bridge rectifier, and the coil itself.
7-40
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
7-41
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE 7.3.3-1 BASIC GENERATOR OPERATIONS TROUBLESHOOTING PROCEDURES (CONTINUED)
COMPONENTS
MALFUNCTION SYMPTOM TEST PROCEDURES
AFFECTED
2. Breaker does not close automatically with System Bus energized:
NOTE: The tie breaker will only automatically close if there is another MEP-PU-810 connected to the
LS-Net connector on the ‘B’ side of the PDC.
7-42
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE 7.3.3-1 BASIC GENERATOR OPERATIONS TROUBLESHOOTING PROCEDURES (CONTINUED)
COMPONENTS
MALFUNCTION SYMPTOM TEST PROCEDURES
AFFECTED
4. Breaker does not close automatically with Tie Bus energized:
NOTE: The tie breaker will only automatically close if there is another MEP-PU-810 connected to the
LS-Net connector on the ‘A’ side of the PDC.
7-43
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
7-44
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(a) Check the status of the Battery Tie Switch (located at front of PU). If closed, open the switch
to isolate engine battery circuits.
2. Operating generator shuts
(b) Check DC voltage between terminals 1A & 2AB. A nominal voltage of 24VDC needs to be
down when second unit on PU
present.
starts.
(c) Lack of DC voltage indicates Engine 1 batteries are not supplying 24VDC to the PDC.
(d) Check DC voltage between terminals 1A & 30AB. A nominal voltage of 24VDC needs to be
present.
(e) Lack of DC voltage indicates Engine 2 batteries are not supplying 24VDC to the PDC.
NOTE 1: Diode Test Procedure: The “Diode Check Function” on a Digital Multimeter should be used because the normal “Ohms Function” on a
digital multimeter does not produce enough voltage to properly test a diode.
1. Reverse Bias – Diode blocks – meter will read (Open Circuit).
2. Forward bias – Diode conducts – meter will read 0.05VDC – 0.8VDC.
3. Incorrect readings: If the diode reads 0 in both directions, it is shorted. If the diode reads (Open Circuit) in both directions.
Replace the defective diode.
7-45
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
7-46
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
All Safety Warnings and Cautions in Section 7.1 apply to this section.
b. If the procedure does not work, replace the Fuel Primer Pump.
7-47
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
All Safety Warnings and Cautions in Section 7.1 apply to this table.
• Overheating
• Loss of coolant
• Overcooling
b. A problem in the cooling system should first be diagnosed by visual inspection. If the problem cannot be diagnosed, tools must be used to
find the cause of the problem.
7-48
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
7-49
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
7-50
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
All Safety Warnings and Cautions in Section 7.1 apply to this table.
1. Brake Adjustment Not Correct • Manual - Adjust Brakes; Automatic - Make Several Reverse Stops
2. Excessively Worn Brake Linings • Replace Shoe & Lining
3. Incorrect Lining • Install Correct Shoe & Lining
4. Grease or Fluid Soaked Lining • Repair Grease Seal or Wheel Cylinder. Install New Shoe and Lining
PROBLEM 2:
5. Frozen Master Cylinder or Wheel Cylinder Pistons • Recondition or Replace All Cylinders, Brake Fluid
WEAK BRAKES
6. Glazed Lining • Refurbish or Replace
7. Excessive Drum Wear • Replace
8. Trapped Air in Lines • Bleed System
9. Malfunctioning Actuating System • Troubleshoot System
PROBLEM 3: 1. Brake Adjustment Not Correct • Manual - Adjust Brakes; Automatic - Make Several Reverse Stops
HARSH BRAKES 2. Grease or Fluid on Linings • Replace Shoe & Lining
7-51
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
1. Under-adjustment • Adjust
PROBLEM 5: 2. Lack of Lubrication • Lubricate
NOISY BRAKES 3. Broken Brake Components • Replace Components
4. Incorrect Brake Components • Correct
7-52
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
All Safety Warnings and Cautions in Section 7.1 apply to this section.
To check the operation of the entire ABS system, hook a tractor to the trailer and charge the trailers air tank. Ensure that the petcock is closed
(Figure 18.3.2.2-1). Turn on the ignition key and ensure that the warning light (Figure 18.2.1.2.5-3) comes on briefly, and then goes out. Pull the
trailer at a speed above 6 mph and make a brake application until the tractor-trailer has come to a complete stop. Verify that the ABS light has
remained OFF. If the light remains OFF, the system is functioning properly. If the ABS system detected an error during the stop, the warning
light will be ON. If the light never comes on, then refer to the Troubleshooting Information – “No ABS Warning Light illumination”. If the light
stays ON with the ignition key ON, refer to the Troubleshooting Information – “ABS light stays ON when there is Power to the ABS System”.
NOTE 1: Disconnect power from the ABS system before testing continuity for opens or shorts, or making any repairs.
NOTE 3: Refer to Foldout FO-55 and FO-56 for a complete wiring diagram of the ABS system
This guide lists the most typical problems only. Consult Radian Inc for anything not addressed here.
• Power is required at Stop light circuit, pin 4, and air is needed to both the supply and service glad hands.
• Do NOT use a battery charger- to power the ABS.
• A Volt/Ohm Meter is needed for some of the troubleshooting procedures.
7-53
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
• Before disconnecting anything, remove electrical power and air pressure from the system.
• The numbers in parentheses ( ) refer to the callouts in the wiring layout shown in Figure 18.2.1.2.5-1.
Start Here:
All Safety Warnings and Cautions in Section 7.1 apply to this table.
Don't overlook the obvious. Check to make sure that you have power and that everything is connected properly.
a. Check the bulb to verify that it is functional. If not functional, replace it.
b. Verify that there is power to the ECU. Disconnect the main wire harness 19 pin connector and check for B+ (positive power) at
either pin #3 or pin #1. The voltage drop between the SAE. J560-7 way and the ECU should not exceed 2 volts. If no power exists
at either pin, then check continuity between these pins and the SAE J560-7 way connector red and blue circuits. Make necessary
PROBLEM 1: repairs and retest.
c. If the problem is still present, remove the main wire harness 19 pin connector at the ECU and verify continuity between pin #10 and
NO ABS WARNING LIGHT the light. The remaining light wire must be grounded to the trailer chassis or connected to the SAE J560-7 way connector ground
ILLUMINATION wire.
d. Check for continuity between the light wire and ground.
e. Repair as necessary and retest.
f. Listen for 2 clicks when reconnecting the main wire harness to the ECU and secure the connection with the attached metal latch.
g. ABS brakes only work when connected to a 12VDC system.
7-54
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. While the trailer is sitting still only, there is also a valve blow down (air exhausts from ABS relay valve).
PROBLEM 2: b. This is normal and indicates that the ABS system is Ok.
c. The ABS light will come on and go off.
ABS LIGHT COMES ON AND GOES OFF d. The valve blow down is an audio check of the solenoids (located on the top of the ABS relay valve).
e. If the ABS is powered up when traveling above 6 mph, the ABS light will stay off unless there is a fault.
a. This troubleshooting procedure requires that electrical power be connected, Refer to FO-51, for the following steps:
• Older tractors power ABS through the stop light circuit and the ABS light will come on when the brakes are applied. Verity that
there is adequate power at the trailer 7-way, pin 4 (1).
• There should be 12-14VDC for test purposes.
• If there is no power then the tractor wiring or coiled power cable needs repaired.
• If there is power at the 7-way, check for 10-14VDC at the power cord connector (2).
• If no power exists, then the trailer ABS power cord needs repair.
PROBLEM 3: • Most trailers have Integral ABS power in the main trailer wiring.
• Check the bulb to verity that it is functional. If not functional, replace it.
ABS LIGHT NEVER COMES ON OR IS
• Disconnect the ABS wire harness at the power Cord (2). Check for continuity through the light wiring (3). The resistance
VERY DIM
should be 3-6 Ohms. If this is not the case, then the light wiring needs to be repaired.
• Check connections for excessive pin spread and/or corrosion.
b. If the problem remains, disconnect the ABS ECU connector (4).
• Check for bent pins, repair and test.
• Test for continuity between pins in the valve connector and ABS ECU connector a multimeter.
• See FO-51 for pin assignments.
• Replace harness if bad, and ECU if problem continues to exist (5).
NOTE: Refer to Section 18.2.1.2.5 and 18.3.2 for additional information.
7-55
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This troubleshooting procedure requires that power be applied to the trailer for 30 seconds/off to verity. The ABS is powered through
the auxiliary circuit whenever the key is in the “on" position and the stop light circuit with the brakes applied.
NOTE: For some sensor faults the trailer must be driven above 6 mph for the light to go off.
b. Verify the voltage at the 7-way (pin #4) is 12-14 volts and that a valve blow down occurs when powering the ABS. If there is no
blow down, then verify that air pressure was applied to the service brakes.
c. If there is air pressure to the service bakes, then disconnect the solenoid connector (6) and check the resistance at the solenoid
pins:
• Readings across the two bottom pins should be 7-9 Ohms.
• Readings between either the bottom pin and the top pin should be 3.5-4.5 Ohms.
PROBLEM 4: • If resistance is okay, then check the female pins in the connector for excessive pin spread and/or corrosion.
• Repair and test.
ABS LIGHT STAYS ON WHEN THERE IS d. If there is a valve blow down, then a sensor is the most likely issue. The sensor gap could be too large. Try pushing the sensors
POWER TO THE ABS SYSTEM in until they touch the exciter (7).
e. If the problem remains, disconnect the sensor connectors from the sensors and measure the resistance between the two pins in
the sensor connector housing (8). The reading for each sensor should be between 980 and 2350 Ohms. Check for pin spread
and/or corrosion also. The sensor should be replaced, if an issue is found.
f. Measure the AC voltage at each sensor while rotating the wheel at a rate of 1 revolution every two seconds. The reading should
average greater than .200 Volts. If this is not the case, replace the sensor.
g. If the problem persists, disconnect the ECU connector (4).
• Check for bent pins.
• Repair and retest.
• Test for continuity between pins in the valve connector and ABS ECU connector a multimeter.
• See FO-51 for pin assignments.
• Replace harness if bad, and ECU if problem continues to exist (5).
7-56
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
7-57
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
All Safety Warnings and Cautions in Section 7.1 apply to this table.
1. Brake Adjustment Not Correct • Manually - Adjust Brakes; Automatic - Make Several Reverse Stops
2. Excessively Worn Brake Linings • Replace Shoe & Lining
3. Incorrect Lining • Install Correct Shoe & Lining
PROBLEM 2: 4. Grease or Fluid Soaked Lining • Repair Grease Seal or Wheel Cylinder. Install New Shoe and Lining
5. Frozen Master Cylinder or Wheel Cylinder Pistons • Recondition or Replace All Cylinders, Brake Fluid
WEAK BRAKES 6. Glazed Lining • Refurbish or Replace
7. Excessive Drum Wear • Replace
8. Trapped Air in Lines • Bleed System
9. Malfunctioning Actuating System • Troubleshoot System
PROBLEM 3:
1. Brake Adjustment Not Correct • Manually - Adjust Brakes; Automatic - Make Several Reverse Stops
HARSH BRAKES 2. Grease or Fluid on Linings • Replace Shoe & Lining
7-58
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
1. Under-adjustment • Adjust
PROBLEM 5: 2. Lack of Lubrication • Lubricate
NOISY BRAKES 3. Broken Brake Components • Replace Components
4. Incorrect Brake Components • Correct
• Replace Components
1. Loose, Bent or Broken Brake Components
• Adjust
PROBLEM 6: 2. Under-adjustment
• Machine or replace
LOCKING BRAKES 3. Out of Round Drums
4. Insufficient Air Pressure to release brakes • Check air lines for leaks
• Check towing vehicle for proper air pressure
7-59
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
All Safety Warnings and Cautions in Section 7.1 apply to this table.
a. Ensure hydraulic fluid level is correct and that the pump is not cavitating. Refer to Section 19.3 for additional information.
b. If all fan motors are turning slowly, you should ensure that the engine is turning at the correct RPM. The pumps and motors are all
the same displacement, therefore, motor speed is directly proportional the engine speed:
• At 60 Hz, the fan RPM should be 1750 RPM or greater.
• At 50 Hz, the fan RPM should be 1650 RPM or greater.
c. Next, check the Pressure Relief Valves. They are preset at the factory and cannot be changed. Refer to Section 19.4.1 for
reference.
SLOW FAN SPEED
d. If the problem still persists, then the pump should be tested for volumetric efficiency and repaired or replaced as necessary. Refer
to Section 19.4.2.1 for additional information.
e. If problem still persists, then the motor or motor(s) should be repaired or replaced. Refer to Section 19.4.2.1 for additional
information.
f. Check hydraulic fluid temperature, ensure the hydraulic fluid being used is within the proper temperature range for the location.
NOTE: If fans do not spin at all, then the suction line shutoff valves may be closed or oil level may be too low.
7-60
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CHAPTER 8
HOUSING ASSEMBLY REPAIR
TABLE OF CONTENTS
8-1
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
8.4.4.1 INSPECT THE “A” AND “B” MODEL TOP PANEL ASSEMBLY 20
8.4.4.2 REMOVE THE “A” AND “B” MODEL TOP PANEL ASSEMBLY 20
8.4.4.3 INSTALL THE “A” AND “B” MODEL TOP PANEL ASSEMBLY 21
8-2
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
8-3
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF FIGURES
8-4
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
• Safety
• Brief Description
• Service Requirements
• Component Repair Procedures
a. Safety precautions must be observed while any maintenance is being performed. Safety
precautions must be observed to ensure that the operator/technician cannot have contact with the
following:
b. Minor troubleshooting can be performed while both engines are running as long as safety
precautions are taken.
c. Minor maintenance can be performed while one generator set is running and the other
generator set has been shutdown. Some examples of this maintenance are:
(1) The generator set that has been shut down must be rendered unable to start, and cool
enough for the maintenance to be performed. Procedures to render a generator set
unable to start are:
8-5
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(j) Disconnect the 7P1 and 7P2 Connectors located on the inside panel of the PDC.
(k) Close and Lock the generator set control panel.
NOTE: The fuel transfer pump electrical power is normally fed directly from the G1 generator set
battery bank. If you disconnect the G1 battery bank, the external fuel transfer pump will not
function. Place the Fuel Pump Source Switch (FPSS) into the (G1 or G2 position). Place the
FPSS in the (G1 or G2) position, for the generator set not receiving maintenance.
d. Major maintenance or service requires that the PU MUST be shutdown, isolated from any
power plant electrical bus or utility connection, isolated from any power plant control
system, and rendered unable to start. This is accomplished by performing the following:
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: A Qualified Electrician needs to ensure load cables are not energized by opening the
circuit breaker of the Primary Switching Center (PSC), then disconnect Load Cables (Using
the proper safety gear) on the PU and place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
8-6
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The Power Unit Housing is a weather tight enclosure that provides easily removable access panels,
doors, and screens for major maintenance, overhaul, and replacement of all major mechanical and
electrical components. This includes easy access and removal of the Primary Distribution Center (PDC)
and both engine/generator sets. The housing provides ISO container features. Air intake and exhaust
openings allow operation with all doors closed. A three-step ladder is provided to assist personnel
access to the interior of the MEP-PU 810B model.
WARNING
WARNING
ACCESS DOORS AND PANELS ARE HEAVY. USE EXTREME CAUTION WHEN
UNBOLTING AND REMOVING. THIS TASK IS A TWO PERSON LIFT.
WARNING
Inspect the interior and exterior of the Power Unit Housing for the following:
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Inspect the interior and exterior of the Power Unit Housing for weather-stripping for cracks,
deterioration and signs of water leaks.
c. Inspect the interior and exterior of the Power Unit Housing for housing frame for cracks, dents,
corrosion, rust, and deterioration.
d. Inspect the interior and exterior of the Power Unit Housing for hardware for damage, missing
components, corrosion and broken locking mechanisms.
e. Inspect the Power Unit Housing air cleaner plenum assembly screens and upper and lower
plenum screens for debris, mounting and missing hardware.
8-7
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
f. Inspect the interior and exterior of the Power Unit Housing mounting hardware for corrosion and
missing components.
WARNING
WARNING
ACCESS DOORS AND PANELS ARE HEAVY. USE EXTREME CAUTION WHEN
UNBOLTING AND REMOVING. THIS TASK IS A TWO PERSON LIFT.
WARNING
Clean the interior and exterior of the Power Unit Housing as follows:
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Clean the interior and exterior of the Power Unit Housing using stiff brushes, clean cloths, and
cleaning detergent.
c. Repaint as necessary.
The following maintenance procedures are provided for the access doors and front side panels.
8-8
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Inspect
Remove
Install
Service
Repair
8-9
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Inspect the Access Doors and Front Side Panels for the following:
a. Inspect the Access Doors and Front Side Panels hinges for rust, bends, and ease of operation.
b. Inspect the Access Doors and Front Side Panels frames for corrosion, rust, dents, and binding.
c. Inspect the Access Doors and Front Side Panels latches for condition and proper operation.
d. Inspect the Access Doors and Front Side Panels interior door panels for mounting, sharp edges
and missing components.
e. Inspect the Access Doors and Front Side Panels mounting hardware for missing or damaged
components.
WARNING
WARNING
ACCESS DOORS AND PANELS ARE HEAVY. USE EXTREME CAUTION WHEN
UNBOLTING AND REMOVING. THIS TASK IS A TWO PERSON LIFT.
WARNING
To remove the Access Doors and Front Side Panels, proceed as follows:
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Remove and retain the mounting hardware that secures the Access Doors and Front Side
Panels to the Power Unit. Open the door latch use Figure 8.4.1-1 as reference.
c. Carefully remove the Access Doors and Front Side Panels. Use two people for removal of the
Access Doors and Front Side Panels.
8-10
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
ACCESS DOORS AND PANELS ARE HEAVY. USE EXTREME CAUTION WHEN
UNBOLTING AND REMOVING. THIS TASK IS A TWO PERSON LIFT.
WARNING
To install the Access Doors and Front Side Panels, proceed as follows:
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Carefully place door or front side panel in place. Use two people for installation of the Access
Doors and Front Side Panels.
Service the removed Access Doors and Front Side Panels by cleaning using stiff brushes, clean cloths,
and cleaning detergent.
To repair the removed the Access Doors and Front Side Panels, proceed as follows:
8-11
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
c. If locking door latch is damaged, remove latch by removing mounting hardware that secures the
latch to the access door. Replace the latch.
d. If sharp areas or burrs are found, use a file to smooth the area and repaint the area.
The following maintenance procedures are provided for the plenum assembly screens.
Inspect
Remove
Install
Service
Repair
8-12
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
8-13
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Remove and retain the mounting hardware that secures the Plenum Assembly Screens to the
Power Unit use Figure 8.4.2-1 and Figure 8.4.2.1-1 as reference.
c. Carefully lift screens (From on top of Power Unit) or drop plenum screens (From beneath the
Power Unit). This task requires two people to lift the Plenum Assembly Screens.
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
8-14
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
b. Carefully place the Plenum Assembly Screens back into position. Use two people for
installation of the Plenum Assembly Screens; use Figure 8.4.2-1 and Figure 8.4.2.1-1, as
references.
c. Replace the retained mounting hardware that secures the Plenum Assembly Screens to the PU.
Service the removed Plenum Assembly Screens by cleaning using stiff brushes, clean cloths, and
cleaning detergent.
b. Repaint as required .
8-15
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the side panels.
Inspect
Remove
Install
Service
Repair
8-16
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
8.4.3.1 INSPECT THE SIDE PANELS
a. Inspect the Side Panels for bent or distorted side panels, and ease of fit.
b. Inspect the Side Panels for corrosion, rust, dents, and binding.
WARNING
WARNING
SIDE PANELS ARE HEAVY. USE EXTREME CAUTION WHEN UNBOLTING AND
REMOVING.
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Remove and retain the mounting hardware that secures the Side Panels to the MEP-PU-810 use
Figure 8.4.3-1 for reference.
c. Carefully remove the Side Panel. Use two people for removing the Side Panels.
d. Check gaskets for cracks and deterioration and replace, if necessary, before re-installing the
Side Panels.
WARNING
8-17
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
SIDE PANELS ARE HEAVY. USE EXTREME CAUTION WHEN UNBOLTING AND
REMOVING.
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Check gaskets for cracks and deterioration and replace, if necessary, before re-installing the
Side Panels use Figure 8.4.3-1 for reference.
c. Carefully place the Side Panels back into position. Use two people for installation of the Side
Panels.
d. Install the retained mounting hardware that secures the Side Panels to the MEP-PU-810.
Service the Side Panels by cleaning using stiff brushes, clean cloths, and cleaning detergent.
b. Repaint as required .
8-18
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE: The rear roof section on the “B” model is permanent and cannot be removed.
The following maintenance procedures are provided for the top panel assembly.
Inspect
Repair
Install
Service
Repair
8-19
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
8.4.4.1 INSPECT THE “A” AND “B” MODEL TOP PANEL ASSEMBLY
a. Inspect the Top Panel Assembly for bent or damaged top panels, and leakage.
b. Inspect the Top Panel Assembly for corrosion, rust, and tightness of mounting hardware.
8.4.4.2 REMOVE THE “A” AND “B” MODEL TOP PANEL ASSEMBLY
NOTE: The Rear Roof Panel Section on the “B” model is permanently mounted and cannot be
removed.
WARNING
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Remove and retain the mounting hardware securing the Muffler to the Rear Roof Panel Section
use Figure 8.4.4-1 for reference.
c. Remove and retain the mounting hardware securing the Rear Roof Panel Section to the Power
Unit frame from inside the unit.
d. Remove the Muffler Assembly use Section 8.4.7, Muffler Assembly for reference.
e. Using a forklift or crane, carefully lift and remove the Rear Roof Panel Section.
f. Clean off sealing compound from Rear Roof Panel Section and Muffler.
8-20
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Remove and retain the mounting hardware securing the Muffler and the Front Roof Panel
Section.
c. Remove and retain the mounting hardware securing the Front Top Panel Section to the Power
Unit frame from inside the unit.
d. Remove the Muffler Assembly use Section 8.4.7, Muffler Assembly for reference.
e. Using a forklift or crane, carefully lift and remove the Front Top Panel Section.
f. Clean off sealing compound from the Front Top Panel Section and Muffler.
8.4.4.3 INSTALL THE “A” AND “B” MODEL TOP PANEL ASSEMBLY
WARNING
8-21
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d..
b. Using a forklift or crane, carefully lift and place the top rear panel on the unit.
c. Install the mounting hardware securing the Rear Roof Panel Section to the frame.
d. Install the Muffler Assembly use Section 8.4.7, Muffler Assembly for reference.
WARNING
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Using a forklift or crane, carefully lift and place the top front panel on the unit.
c. Install retained the mounting hardware securing the Front Roof Panel Section to the frame.
8-22
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
d. Install the Muffler Assembly use Section 8.4.7, Muffler Assembly for reference.
Service the removed Front Roof Panel Section by cleaning using stiff brushes, clean cloths, and cleaning
detergent.
b. Repaint as required.
8-23
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the battery box assembly:
Inspect
Remove
Install
Service
Repair
8-24
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
8-25
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
WARNING
WARNING
8-26
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
To remove the Battery Box Assembly, proceed as follows:
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Remove Items 3, 4, 5, and 6, use Figure 8.4.5-1, Figure 8.4.5-2 and Figure 8.4.5-3 for reference.
WARNING
WARNING
WARNING
WARNING
WARNING
8-27
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
To install the Battery Box Assembly, proceed as follows:
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
c. Reinstall Items 1, 2, and 7, use Figure 8.4.5-1, Figure 8.4.5-2 and Figure 8.4.5-3 for reference.
Service the Battery Box Assembly by cleaning using stiff brushes, clean cloths, and cleaning detergent.
b. Repaint as required.
8-28
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the Fuel Tank and Hydraulic Reservoir
Assemblies:
Inspect
Remove
Install
Service
Repair
Inspect the Fuel Tank and Hydraulic Reservoir Assemblies for the following:
a. Inspect the Fuel Tank and Hydraulic Reservoir Assemblies for damage and leaks.
b. Inspect the Fuel Tank and Hydraulic Reservoir Assemblies for security of attachment.
c. Inspect the Fuel Tank and Hydraulic Reservoir Assemblies for damaged, loose or missing
hardware.
8-29
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
8-30
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
8-31
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
8.4.6.2.1 REMOVE THE FUEL TANK
WARNING
WARNING
WARNING
WARNING
WARNING
CAUTION
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
8-32
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
b. Shut off respective Fuel Shutoff Valve on External Fuel Distribution Manifold use Figure 8.4.6.2-1
for reference.
c. Shut off the Fuel Tank Supply Shutoff Valve use Figure 8.4.6.2-2 for reference.
d. Drain the Fuel Tank into an approved container with a capacity of at least 120 gallons. Loosen
and Remove the plug on either side of the bottom of the fuel tank to drain fuel.
e. Place drain pan under the External Fuel Manifold Hose connection at the Power Unit.
f. Disconnect the External Fuel Manifold Supply Hose at the Fuel Solenoid Valve Strainer fitting
and cap hose, use Figure 8.4.6.2-3 for reference.
g. Place a Cap fitting on Fuel Solenoid Valve Strainer fitting, to prevent contamination.
i. Remove the Battery Box Assembly use, Section 8.4.5.2 for reference.
j. Tag and disconnect the Fuel Transfer Pump wires inside Float Control Box Assembly. Use FO-
43A, FO-43B, FO-44A, FO-44B and FO-43C for reference.
k. Tag and disconnect fuel solenoid valve wires inside Float Control Box Assembly.
l. Tag and disconnect the 6 Deutsch connectors for Fuel Control Box Wiring.
m. Remove and retain conduit nuts and remove conduit fittings from Float Control Box assembly.
n Remove and retain bolts securing Fuel Pump Bracket Assembly to the Fuel Tank and remove
the assembly.
o. Remove and retain both Top Plenum Screens per Section 8.4.2.
q. Remove and retain bolts, washers and nuts securing both Front Center Covers.
r. Disconnect two Fuel Supply hoses from rear of the fuel tank.
s. Disconnect two fuel return hoses from rear of the fuel tank.
u. Remove and retain the bolts and washers securing the Fuel Tank and remove the Fuel Tank.
8-33
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
8-34
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
CAUTION
NOTE: The following procedures are for either hydraulic reservoir. Repeat steps for second reservoir
if second reservoir removal is required.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
c. Cut the Tie Strap on the Hydraulic Reservoir Supply Shutoff Valve. Rotate the handle 90
degrees to close the valve. Use Figure 8.4.6.2.2-1 for reference.
d. Drain the Hydraulic Fluid Reservoir into approved container(s). Replace plug using thread-
sealing compound. Dispose of fluid per local facility procedures. Use Figure 8.4.6-1 as a
reference.
e. Remove and retain the hose clamp securing the Return Hose to access cover.
f. Disconnect the Return Hose at “T” fitting. Cap/plug both ends to prevent dirt from entering.
8-35
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
g. Disconnect the float level wire harness from the rear of tank.
h. Disconnect supply hose. Cap/plug both ends to prevent dirt from entering.
i. Disconnect Case Return Hose. Cap/plug both ends to prevent dirt from entering.
k. Remove and retain mounting bolts, nuts and washers and remove hydraulic reservoir.
WARNING
WARNING
WARNING
WARNING
WARNING
8-36
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
To install the fuel tank, proceed as follows: (Use Figure 8.4.6-1 as a reference)
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Using a forklift or crane, carefully raise the fuel tank into place. Use Figure 8.4.6-1 as a
reference.
c. Reinstall with retained bolts, washers, and nuts securing fuel tank.
d. Reinstall two fuel supply hoses from rear of the fuel tank using thread-sealing compound.
e. Reinstall two fuel return hoses from rear of the fuel tank using thread-sealing compound.
f. Reinstall Front Center Covers with retained bolts, washers and nuts.
h. Reinstall Fuel Pump Bracket Assembly to the Fuel Tank with retained bolts and washers.
i. Reinstall the Fuel Transfer Pump and Solenoid Valve conduit and attach to the Float Control
Box assembly with conduit nuts. Use FO-43A, FO-43B, FO-44A, FO-44B and FO-43C for
reference.
j. Reinstall Fuel Transfer Pump wires inside the Float Control Box Assembly box and remove tags.
k. Reinstall the Solenoid Valve wires inside the Float Control Box Assembly box and remove tags.
m. Remove cap covering the fitting on Fuel Solenoid Valve Strainer fitting.
n. Reinstall Fuel Manifold Hose to the Fuel Solenoid Valve Strainer fitting.
WARNING
WARNING
8-37
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Using a forklift or crane, lift hydraulic reservoir into place. Use Figure 8.4.6-1 as a reference.
c. Reinstall the Hydraulic Fluid Reservoir to the Power Unit using retained bolts, nuts and washers.
8-38
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Service the exterior of the Removable Tank Assemblies by cleaning using stiff brushes, clean cloths, and
cleaning detergent.
NOTE: Welding must be done by a certified welder, applying all safety requirements necessary for
fuel tank welding.
NOTE: The interior of the hydraulic reservoir must be maintained in an absolutely clean condition or
professionally cleaned to be absolutely clean of contamination.
8-39
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the muffler assembly:
Inspect
Remove
Install
Service
Repair
a. Inspect the Muffler Assembly, Rain-caps to ensure they open and close freely.
b. Inspect the Muffler Assembly to ensure the Exhaust Wrap is secure and not damaged.
8-40
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Remove and retain the mounting hardware between the Flex Connector and Muffler. Use
Figure 8.4.7-1 as a reference.
e. Connect lifting straps to the Muffler and lift the muffler from the PU with a minimum of 1 ton
capacity lifting device.
f. Remove all old or excess caulk and mastic from the PU.
WARNING
8-41
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 8.1.d.
b. Connect lifting straps to the Muffler and lift the Muffler with a minimum of 1-ton capacity lifting
device and place the Muffler into position on the Power Unit (Use Figure 8.4.7-1 as a reference).
e. Reinstall the gasket and retained mounting hardware between flex connector and muffler.
Service the exterior of the Muffler Assembly by cleaning using stiff brushes, clean cloths, and detergent.
8-42
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CHAPTER 9
DIRECT CURRENT (DC) SYSTEM REPAIR
TABLE OF CONTENTS
9.4.1 BATTERIES 9
9-1
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE OF CONTENTS
9-2
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE OF CONTENTS
9-3
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF FIGURES
9-4
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF TABLES
9-5
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The DC electrical system consists of relays, solenoids, motors, indicators and other components that
combine to start, stop control, and monitor the MEP-PU-810. This section contains maintenance
procedures for the DC electrical system. Test, adjust, replace and repair components of the DC system
in accordance with the following procedures.
Maintenance procedures are provided for the following Direct Current (DC) System Components:
• Batteries
• Battery Cables
• Battery Charger
• Wiring Harnesses
• Battery Bank DC Tie Switch
• Starter Motor and Starter Solenoid
• Fuel Transfer Pump
• DC Control Breaker
• DC Panel Light Bulbs and Fault Indicator Lights
a. Safety precautions must be observed while any maintenance is being performed. Safety
precautions must be observed to ensure that the operator/technician cannot have contact with the
following:
b. Minor troubleshooting can be performed while both engines are running as long as safety
precautions are taken.
c. Minor maintenance can be performed while one generator set is running and the other
generator set has been shutdown. Some examples of this maintenance are:
9-6
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(1) The generator set that has been shut down must be rendered unable to start, and cool
enough for the maintenance to be performed. Procedures to render a generator set
unable to start are:
NOTE: The fuel transfer pump electrical power is normally fed directly from the G1 generator set
battery bank. If you disconnect the G1 battery bank, the external fuel transfer pump will not
function. Place the Fuel Pump Source Switch (S2) into the (G1 or G2 position). Place the S2
in the (G1 or G2) position, for the generator set not receiving maintenance.
d. Major maintenance or service requires that the PU MUST be shutdown, isolated from any
power plant electrical bus or utility connection, isolated from any power plant control
system, and rendered unable to start. This is accomplished by performing the following:
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
9-7
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CHASSIS
GROUND
INTERCONNECT
SWITCH G1A+ 20A BATTERY
20A BATTERY G2A+ CHARGER
CHARGER
DC OUTPUT
DC OUTPUT
G1B+
NATO
CHASSIS PLUG
GROUND
G2B+
G2- FUEL
TRANSFER*
G1- CONTROL
G2- G1-
+ - + -
BATTERIES BATTERIES
(2) 8D (2) 8D
- + - +
The DC system has two functions, Starting and Control. Foldouts FO - 7 to FO – 12B are the DC
Electrical Schematics for Primary Distribution Center (PDC) control and Engine control systems.
There are no general DC System service requirements. However, each component that requires specific
services is listed in the Component Repair Procedures, Section 9.4.
9-8
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
9.4.1 BATTERIES
Inspect
Test
Remove
Install
Service
d. Inspect the Battery Terminals for corrosion and proper connection of cables.
e. Inspect the Battery Box hardware for damage, corrosion, and loose or missing components.
9-9
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. The batteries supplied with the PU are maintenance free. Water or electrolyte is not added to the
batteries.
b. Use the Caterpillar Battery Load Tester, 4C-4911, or equivalent, to test the battery condition.
Use the test equipment manufacturers instructions for testing batteries. Refer to Caterpillar
manual SEHS9249 for operation of the Caterpillar Operation Manual for the 4C-4911, Battery
Load Tester.
WARNING
WARNING
WARNING
WARNING
WARNING
9-10
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. This is accomplished by performing the following:
NOTE: The fuel transfer pump electrical power is normally fed directly from the G1 generator set
battery bank. If you disconnect the G1 battery bank, the external fuel transfer pump will not
function. Place the Fuel Pump Source Switch (S2) into the (G1 or G2 position). Place the S2 in
the (G1 or G2) position, for the generator set not receiving maintenance.
g. Remove batteries carefully using proper lifting technique and/or appropriate material handling
equipment.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See procedures and warnings in paragraph 9.4.1.3.
c. Reinstall battery on battery tray carefully using proper lifting technique and/or appropriate
material handling equipment.
9-11
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
b. If battery terminal corrosion is present, disconnect both negative battery cables, disconnect the
cable from corroded terminal, clean terminal with a solution of baking soda and water; then flush
with clean water, reconnect to cleaned terminal, reconnect both battery cables.
The following maintenance procedures are provided for the battery cables:
Inspect
Test
Remove
Install
Service
Inspect the Battery Cables as follows (Using FO – 37A and FO – 37B as a reference):
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See procedures and warnings in paragraph 9.1.4.3.
b. Check the cables for corrosion, insulation breaks, deterioration, or other damage.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See procedures and warnings in paragraph 9.1.4.3.
9-12
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
e. Disconnect both positive battery cables from the batteries.
f. Using a multimeter, set to OHMS (Ω) Rx1 scale, test continuity of each cable.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See procedures and warnings in paragraph 9.1.4.3.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See procedures and warnings in paragraph 9.1.4.3.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See procedures and warnings in paragraph 9.1.4.3.
b. If battery cable terminal corrosion is present, disconnect both negative battery cables;
disconnect corroded battery cable terminal, clean battery cable terminal with a solution of
baking soda and water; flush with clean water.
9-13
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the Battery Charger:
Inspect
Test
Remove
Install
Service
The MBC6 Battery Charger will switch modes (float or equalize) depending on the state of charge in the
battery and upon external loads. The mode switching decision is based on the charger output current at
the “+”’ and “-“ terminals. When the battery and/or other loads require much over 50% of rated current,
the charger switches to equalize mode and remains there until the battery is charged (and/or loads are
reduced) and the output current drops below 50% of rated current. At that point the charger will switch to
the float mode, with a corresponding reduction in output current, and remain in ‘float’ until the next
demand occurs.
For complete charger details, refer to the Master Control System Battery Charger Instruction Manual,
MBC6X-24V-20A-LA.
9-14
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
d. Inspect input AC Power Circuit Breaker (CB1) for proper mechanical function.
e. Inspect output DC Power Circuit Breaker (CB2) for proper mechanical function.
To test the Battery Charger, proceed as follows using Figure 9.4.3-1 as a reference:
a. Ensure that the Battery Charger input power cable is connected to an active source of 120VAC
electrical power.
b. Ensure that the battery bank is properly connected and the Battery Charger is properly
connected to the battery bank.
e. Observe that the DC Ammeter indicates a low rate of charging current flow.
9-15
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
9-16
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
b. Disconnect the 120 VAC battery charger power plug from the receptacle underneath the panel
board box.
c. Place a tag on the battery charger power plug noting that the battery charger has been removed.
d. Open the front cover to gain access to the inside of the charger.
e Tag and disconnect the Neutral, Hot and Ground wires at the AC terminal board and tape leads
to prevent shorting should the power plug get reconnected accidentally.
f. Unscrew conduit clamp nut holding AC wires to the charger and pull wire harness out of charger.
g. Tag and disconnect the + and – wires at DC terminal board and tape leads to prevent shorting
should the batteries get reconnected accidentally.
h. Unscrew conduit clamp nut holding DC wires to charger and pull wire harness out of charger.
i. Remove the 4 nuts securing the battery charger to station transformer. The charger is now free
to be lifted off the vibration mounts.
j. Reinstall the securing hardware and vibration mounts to prevent loss. Inspect hardware and
vibration mounts for damage, Replace if necessary.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 9.4.3.3.
b. Install and Secure the Battery Charger on the 4 vibration mounts using existing hardware.
d. Insert the DC power harness into the Battery Charger and secure with conduit clamp nut.
e. Remove tape and attach the wires to the DC terminal board. Remove tag.
f. Install the AC power harness into the charger and secure with conduit clamp nut.
g. Remove the marking tape and attach the wires to the AC terminal board.
h. Close the Battery Charger cover and reinstall the mounting screws.
i. Reconnect the positive and then the negative battery cables to the batteries. Remove marking
tag.
9-17
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
l. Plug in the 120VAC plug. Remove marking tag.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See procedures and warnings in paragraph 9.4.3.3.
b. Clean the exterior by wiping the surface with a rag and with water based degreaser.
d. Clean the interior of dust with low pressure compressed air or vacuum cleaner.
The following maintenance procedures are provided for the Wiring Harnesses:
Inspect
Test
Remove
Install
Repair
WARNING
WARNING
WARNING
9-18
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
To inspect the Wiring Harness, proceed as follows:
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
c. Check that all terminal lugs are securely attached to wire ends.
d. Ensure that the Wiring Harness are bundled and tied together securely.
e. Check security of all hangers, clamps, and hardware that secure the Wiring Harness to the
generator set or other support.
f. Check that no wire is in contact with any sharp edge or any heat producing surface of the engine
or exhaust system or other support.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 9.4.4.1.
9-19
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
b. Test the suspect wiring harness wires for continuity and internal shorts using a multimeter set to
check OHMS (Ω) Rx1 scale. Use FO-1 to FO-44C for reference.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 9.4.4.1.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 9.4.4.1.
b. Install the wire harness into the PU in the same physical place that the old harness was
removed.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 9.4.4.1.
b Repair wiring harnesses by splicing, and replacing damaged terminal lugs and connections, and
soldering damaged components.
9-20
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the Battery Bank DC Tie Switch:
Inspect
Test
Remove
Install
9-21
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. The Battery Bank DC Tie Switch is located at the front of the PU, above and centered between
the two hydraulic tanks, next to the NATO slave receptacle. Use Figure 9.4.5-1 for reference.
b. It is a two-position switch that is normally open. The operator can close the switch, which then
parallels the two battery banks together when additional cranking power is needed for starting
either generator set.
c. When the NATO slave receptacle is used for starting or charging, the Battery Bank DC Tie Switch
must be closed to start the roadside generator or charge its batteries.
WARNING
a. Check the Battery Bank DC Tie Switch for physical damage, deterioration, or missing parts.
c. Check that all terminal lugs are securely attached to terminals and to wire ends.
WARNING
WARNING
9-22
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. This is accomplished by performing the following:
NOTE 1: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
b. Tag and disconnect cables from the Battery Bank DC Tie Switch.
(1) Place the Battery Bank DC Tie Switch in the “ON” position, the meter should read 1
OHM or less.
(2) Place the Battery Bank DC Tie Switch in the “OFF” position, the meter should read
infinite Ohms.
d. Replace the Battery Bank DC Tie Switch if it fails any of the above tests.
9-23
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See procedures and warnings in paragraph 9.4.5.2.
b. Tag and disconnect cables from the Battery Bank DC Tie Switch.
c. Remove the handle set screw and remove handle. See Figure 9.4.5-2.
d. Remove the Battery Bank DC Tie Switch mounting nut and washer. See Figure 9.4.5-2.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See procedures and warnings in paragraph 9.4.5.2.
b. Place the Battery Bank DC Tie Switch into position. See Figure 9.4.5-1.
c. Reinstall the Battery Bank DC Tie Switch mounting nut and washer. See Figure 9.4.5-2
d. Reinstall the handle and Reinstall handle set screw. See Figure 9.4.5-2.
e. Remove tags and connect the Battery Cables to the Battery Bank DC Tie Switch.
9-24
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the Starter Motor and Starter Solenoid:
Inspect
Test
Remove
Install
Adjust
WARNING
WARNING
9-25
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. This is accomplished by performing the following:
NOTE 1: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
b. Corrosion on solenoid terminals. Disconnect battery cable and clean terminals as required.
9-26
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
CAUTION
CAUTION
TWO PEOPLE ARE REQUIRED TO PERFORM THIS TASK THE STARTER WEIGHS 70 LBS.
a. This maintenance requires that the PU MUST be shutdown, and cool enough for the test to be
performed, and Communication Cable (A) and (B) rerouted to the next PU. This is
accomplished by performing the following:
NOTE 1: When the DC Control Breaker is in the (OFF) position (Pulled – Out), all control power is
turned off to the PU. This will cause the HUB to stop functioning. This causes the network to
not see the equipment shutdown and all PU’s after it. When pulling major maintenance the
(A) (B) Communication Cable must be routed to the next PU in order to reestablish the
communication network.
9-27
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
b. Test of the starter motor and electrical solenoid assembly consists of a test of the complete unit
followed by a pinion clearance check and adjustment. Refer to Figure 9.4.6.2-1 for the following
steps:
c. Use a multimeter in the DC voltage range to find starting system components that do not function.
d. Move the Engine Control Switch (ECS) to the Manual Start position in order to activate the
starting solenoid. The starting solenoid’s operation can he heard as the pinion of the starting
motor is engaged with the ring gear on the engine flywheel.
e. If a solenoid for a starting motor will not operate, it is possible that the current from the battery did
not reach the solenoid. Fasten one lead of the multimeter to the connection (1) for the battery
cable on the solenoid. Put the other lead to a good ground. A zero reading indicates that there is
a broken circuit from the battery. More testing is necessary when there is a voltage reading on
the multimeter. Turn ECS to “OFF/RESET”.
f. The solenoid operation also closes the electric circuit to the motor. Connect one lead of the
multimeter to the solenoid connection (2) that is fastened to the motor. Put the other lead to a
good ground. Move the Engine Control Switch (ECS) to the Manual Start position to activate the
starting solenoid and look at the multimeter. A reading of 24VDC shows that the problem is in the
motor. The motor must be removed for further testing. A reading of 0VDC, on the multimeter
shows that the solenoid contacts do not close. This is an indication of the need for repair to the
solenoid or an adjustment to be made to the starting motor pinion clearance. Turn ECS to
“OFF/RESET”.
9-28
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
g. To test, fasten one multimeter lead to the connection (3) for the small wire at the solenoid and
fasten the other lead to the ground. Move the Engine Control Switch (ECS) to the Manual Start
position to activate the starting solenoid and look at the multimeter. A voltage reading shows that
the problem is in the solenoid. A 0VDC reading indicates that the problem is in the ECS or the
wires to the ECS. Turn ECS to “OFF/RESET”.
h. Refer to FO-15, D6, for this task. Fasten one multimeter lead to the ECS at the terminal ECSA
(1) for the wire from the battery. Fasten the other lead to a good ground. A 0VDC reading
indicates a broken circuit from the battery. Make a check of the circuit breaker and associated
wiring. If there is a voltage reading, the problem is in the ECS or in the wires for the ECS.
i. Starting motors that operate too slowly can have an overload because of too much friction in the
engine that is being started. Slow operation of the starting motors can also be caused by a short
circuit, loose connections and/or dirt in the motor.
WARNING
WARNING
WARNING
CAUTION
TWO PEOPLE ARE REQUIRED TO PERFORM THIS TASK THE STARTER WEIGHS 70 LBS.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. This is accomplished by performing the following:
9-29
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE 1: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
c. Remove the Fumes Disposal Collector mounting bolts and set Fumes Disposal Collector aside.
d. Tag and disconnect wiring from the Starter Motor and Starter Solenoid.
e Using Figure 9.4.6-1 as a reference, fasten a hoist to the starting motor. Remove the three
Starter mounting bolts that hold the starting motor to flywheel housing.
f. Remove Starter Motor and Starter Solenoid from the flywheel housing. The weight of the Starter
Motor and Starter Solenoid is 32 kg (70 lb).
9-30
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
9.4.6.4 INSTALL STARTER MOTOR AND STARTER SOLENOID
CAUTION
TWO PEOPLE ARE REQUIRED TO PERFORM THIS TASK THE STARTER WEIGHS 70 LBS.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See procedures and warnings in paragraph 9.4.6.3.
b. Using a hoist, position the Starter Motor and Starter Solenoid into the flywheel housing. The
weight of the Starter Motor and Starter Solenoid is 32 kg (70 lb).
c. Reinstall the mounting bolts, washers, and lock washers. Torque all mounting bolts and
electrical connections according to Table 9.4.6.4-1 using Figure 9.4.6.4-1, Figure 9.4.6.4-2 and
Figure 9.4.6.4-3.
9-31
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
9-32
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
9-33
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This procedure is conducted with the starter motor removed from the PU.
b. Use a screwdriver to turn the pinion on the exposed drive assembly in the drive housing. Tight
bearings, bent armature shaft, or a loose pole shoe screw will cause armature binding. If
armature does not turn freely, replace the starter. If armature rotates freely, conduct the testing
as follows:
• Reinstall the solenoid without connector (1) from the MOTOR connections (terminal) on the
solenoid to the motor. Use Figure 9.4.6.5-1 for reference.
9-34
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
• Connect a 24VDC Power Source, to the solenoid, to the "SW” terminal (2). Use Figure
9.4.6.5-1 for reference.
• Connect the other side of the 24VDC Power Source to connector (3). Use Figure 9.4.6.5-1
for reference.
• For a moment, connect a wire from the solenoid connection (terminal), which is marked
“MOTOR”, to the ground connection (terminal). The pinion will shift to the crank position and
the pinion will stay there until the battery is disconnected.
• Push the pinion toward the end with the commutator in order to remove free movement.
• Pinion clearance (6) must be 9.1 mm (0.358 inch). Use Figure 9.4.6.5-2 for reference.
• In order to adjust the pinion clearance, remove the plug and turn the shaft nut (4). Use
Figure 9.4.6.5-2 for reference.
• After the adjustment is completed, reinstall the plug over the nut (4) and reinstall the
connector (1) between the MOTOR terminal on the solenoid and the starter motor.
9-35
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the DC Control Power Circuit Breaker (CBCP):
Inspect
Test
Remove
Install
RETAINING NUT
See Figure 9.4.7-1 for reference. The DC Control Power Circuit Breaker (CBCP) provides G1 and G2 an
automatic safety disconnect of battery power from its circuits in case of short circuit or circuit overload.
9-36
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. This is accomplished by performing the following:
NOTE 1: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
9-37
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
c. Test the DC Control Breaker using a Multi-Amp MS-2 Circuit Breaker Tester or equivalent
according to the test equipment and breaker manufacturer instructions.
d. Ensure that the Circuit Breaker will continuously carry rated current. Must trip at 135% rated
current within one hour.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See procedures and warnings in paragraph 9.4.7.2.
a. This maintenance requires that the PU MUST be shutdown, rendered unable to start, cool
enough for the maintenance to be performed, and Communication Cable (A) and (B)
rerouted to the next PU. See procedures and warnings in paragraph 9.4.7.2.
b. Position the DC Control Power Circuit Breaker into the MCP and secure it with its retaining nut.
9-38
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the DC Panel Lights and Fault Indicator Lights:
Inspect
Test
Remove
Install
PANEL LIGHTS
PANEL LIGHTS
CONTACTOR
INDICATOR LIGHTS
CONTACTOR
INDICATOR LIGHTS
Inspect the DC Panel Lights and Fault Indicator Lights every 250 hours for the following conditions:
9-39
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
To test the DC Panel Lights and Fault Indicator Lights, proceed as follows:
a. Close the DC Control Power Circuit Breaker (Push-in). Push the “Press to Test” ring on each of
the fault indicator lamps that have that feature. The light should illuminate. If the light does not
illuminate or on lights that do-not have the press to test feature, remove the bulb and test it. Use
an ohmmeter to check continuity.
b. Test DC Panel Lights by placing the PANEL LIGHTS toggle switch to the ON position. The DC
Panel Lights should illuminate. If not, remove the bulb and test it using an ohmmeter to check
continuity.
9-40
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
CHAPTER 10
ALTERNATING CURRENT (AC) SYSTEM REPAIR
TABLE OF CONTENTS
10-1
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE OF CONTENTS
10.4.5 ALTERNATOR 31
10-2
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE OF CONTENTS
10-3
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
TABLE OF CONTENTS
10-4
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF FIGURES
10-5
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
LIST OF TABLES
10-6
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. Safety precautions must be observed while any maintenance is being performed. Safety
precautions must be observed to ensure that the operator/technician cannot have contact with the
following:
b. Minor troubleshooting can be performed while both engines are running as long as safety
precautions are taken.
c. Minor maintenance can be performed while one generator set is running and the other
generator set has been shutdown. Some examples of this maintenance are:
10-7
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(1) The generator set that has been shut down must be rendered unable to start, and cool
enough for the maintenance to be performed. Procedures to render a generator set
unable to start are:
NOTE: The fuel transfer pump electrical power is normally fed directly from the G1 generator set
battery bank. If you disconnect the G1 battery bank, the external fuel transfer pump will not
function. Place the Fuel Pump Source Switch (S2) into the (G1 or G2 position). Place the S2
in the (G1 or G2) position, for the generator set not receiving maintenance.
d. Major maintenance or service requires that the PU MUST be shutdown, isolated from any
power plant electrical bus or utility connection, isolated from any power plant control
system, and rendered unable to start. This is accomplished by performing the following:
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
10-8
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
• Alternator
• Distribution System
• AC Prints
a. The SR4B is a three phase, alternating current and brushless type generator. It is a four pole
design. The stationary main armature bolts to the engine flywheel housing. A flexible plate type
coupling connects the rotor shaft to the engine flywheel. The rotating main field is keyed directly
to the rotor shaft. The generator is self-ventilated with air entry through screened openings at the
rear of the generator and air discharge through screened openings at the drive-coupling end. The
fan attaches to rotor shaft. A bearing supports the exciter end of the rotor shaft.
b. The PU is configured for 840Kw at 60Hz at a .8 power factor, 4160/2400 VAC at 1800 rpm.
c. The PU is configured for 700Kw at 50Hz at a .8 power factor, 3800/2200 VAC at 1500 rpm.
f. Parking Stands are supplied for Medium Voltage Cables when disconnected from the PU.
• All contactors require a constant 120VAC signal to stay closed except for the Tie Breaker,
which has a mechanical interlock to keep it closed.
i. The AC & DC prints called Foldouts are structured as follows:
10-9
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
10-10
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE: The MEP-PU-810A and MEP-PU-810B use medium voltage vacuum breakers for the
distribution.
10-11
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The AC “System” does require service. Each subcomponent that requires a service will be addressed in
that section.
The following maintenance procedures are provided for the Station Power Transformer:
Inspect
Test:
• Test Fuses
• Insulation Resistance Test
• Turns Ratio Test
Remove
Install
10-12
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
10-13
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
b. Remove the four screws from the Tie Panel and swing it outward exposing the transformer fuse
block and Tie Breaker.
d. Visually inspect Fuse 12, Fuse 13 and Fuse 14 and fuse block for looseness, burning, corrosion,
and physical damage. Ensure fuses are properly rated (5A-4800 VAC).
• Corrosion
• Physical damage
• Loose connections
• Shorted, frayed, or broken wires
• Loose mountings
• Damage and signs of overheating
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.1.1.
b. Remove the four screws from the Tie Panel and swing it outward exposing the transformer fuse
block and load Tie Breaker.
10-14
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Test Fuses:
d. Visually inspect Fuse 12, Fuse 13 and Fuse 14 and fuse block for looseness, burning, corrosion,
and physical damage. Ensure fuses are properly rated (5A-4800 VAC).
e. Remove fuses from the fuse block using the proper fuse puller and high voltage gloves.
g. Perform appropriate tests if neccessary. (See Section 10.4.1.2.1 and/or Section 10.4.1.2.2)
h. Reinstall fuses using the proper fuse puller and high voltage gloves.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.1.1.
b. Remove the four screws from the Tie Panel and swing it outward exposing the transformer fuse
block and Tie Breaker.
g. Disconnect high voltage and low voltage leads from the transformer.
h. Using a multimeter set to OHMS (Ω) Rx1 scale, perform individual continuity checks on
transformer primary and secondary windings.
i. Connect a 500V Megger to either primary lead and to ground. Short the secondary terminals to
ground before connecting the Megger leads to primary terminals. Operate the Megger for 60
seconds and observe resistance. Reading on each transformer should be not less than 20
megohm. Short the primary lead to ground before disconnecting.
j. Short high voltage terminals to ground before connecting the Megger. Connect the Megger to
either secondary lead and to ground. Operate the Megger for 60 seconds and observe
resistance. Reading should be not less than 1 megohm. Short the secondary lead to ground
before disconnecting.
k. Connect Megger leads between primary and secondary windings. Operate the Megger for 60
seconds and observe resistance. Reading should not be less than 20 megohm. Short both
windings to ground before disconnecting.
10-15
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Turns ratio testing of transformers provides a direct means to detect loose or open connections, shorted
or open turns in the transformer windings, incorrect polarity connections, and to verify precisely the no-
load voltage ratio of the transformer, at all tap positions. The turns ratio of a transformer is defined as the
number of turns in one winding in relation to the number of turns in the other winding of the same phase,
which is also equal to the no-load voltage ratio.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.1.1.
b. Remove the four screws from the Load Tie Panel and swing it outward exposing the transformer
fuse block and Tie Breaker.
g. Tag and disconnect wiring leads from the transformer to include the panel board wiring.
h. Perform a TTR test using the test equipment’s manufactures procedures. The turns ratio is
required to be within ±1/2 percent or (.005), of the indicated nameplate voltage ratio.
• If the transformer fails any of the above requirements, remove and forward to next higher
level of maintenance.
• If the transformers meet above requirements, connect wiring leads and discard tags.
i. Reinstall access panel and both Battery Chargers with securing hardware.
a. Using a multimeter set to OHMS (Ω) Rx1 scale, perform individual continuity checks on
transformer primary and secondary windings.
b. Connect a 500V Megger to either primary lead and to ground. Short the secondary terminals to
ground before connecting Megger leads to primary terminals. Operate Megger for 60 seconds
and observe resistance. Reading on each transformer should be not less than 20 meg-ohms.
Short the primary lead to ground before disconnecting.
c. Short the high voltage terminals to ground before connecting Megger. Connect Megger to either
secondary lead and to ground. Operate the Megger for 60 seconds and observe resistance.
Reading should be not less than 1 meg-ohm. Short the secondary lead to ground before
disconnecting.
10-16
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
d. Connect Megger between primary and secondary windings. Operate the Megger for 60 seconds
and observe resistance. Reading should not be less than 20 meg-ohms. Short both windings to
ground before disconnecting.
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 10.4.1.1.
b. Remove the four screws from the Load Tie Panel and swing it outward exposing the transformer
fuse block and Tie Breaker.
10-17
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
h. Remove conduit and wires from the PDC and panel board.
i. Place a strap around the transformer and connect it to a lift. Remove mounting hardware and
carefully, remove the transformer from the PU. Extra care must be taken due to the
transformer’s weight and size of work area.
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures in paragraph 10.4.1.1.
b. Reinstall the transformer from either side of the PU, and secure with the mounting hardware.
10-18
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
f. Reinstall both Battery Chargers. See Section 9.4.3.4 for reference.
f. Reinstall the transformer fuses. Close the Tie Panel by swinging it inward and secure the door
with the four (4) mounting screws.
The following maintenance procedures are provided for the 208/120VAC Receptacles:
Inspect
Test
Remove
Install
10-19
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
There are two 120 VAC, 20-amp, single-phase, GFCI duplex receptacles and one 208 VAC, three-phase,
60 amp receptacle located under the trailer housing on the roadside of the unit. (See Figure 10.4.2-1).
There are also two 120VAC internal receptacles, located under the panel board, near the rear of the
alternator (See Figure 10.4.2-2).
b. Security of attachment.
10-20
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
10.4.2.2 TEST 208/120VAC RECEPTACLES
WARNING
a. With the system energized, press the (TEST) button on the receptacle.
c. Test receptacle with multimeter in “AC” mode. Ensure the receptacle is energized with the
RESET in and de-energized with the reset out (TRIPPED).
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
10-21
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
b. Place the correct circuit brekaer located in PU Distribution Center to the OFF position.
c. Ensure power is removed from the receptacles by checking for AC voltage with a multimeter.
10-22
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.2.2.3.
10-23
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the Wiring Harnesses:
Inspect
Test
Remove
Install
Repair
Harnesses interconnect elements of the AC electrical power generation and control system. Refer to the
drawing Fold-outs (FO) FO - 1 and FO – 44C to provide representations of components and circuit
interconnection within the generator set. For the following tasks, isolate the PU from the high voltage
source.
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
10-24
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(3) Isolate the PU from any power plant control system in accordance with Note 3.
(4) Pull to open the PU DC Power Control Breaker.
(5) Push to open both Emergency Stop Switches.
(6) Place both Engine Control Switches (ECS) in the OFF position.
(7) Place a DO NOT OPERATE tag on both generator control panels.
(8) Turn the Battery Bank Parallel Switch to the OFF position.
(9) De-energize both Battery Chargers.
(10)Disconnect the negative and positive cables from both Battery Banks.
(11)Place a DO NOT OPERATE tag on both Battery Banks.
(12)Place all Circuit Breakers in the LOCK OUT position.
(13)Disconnect both 7P1 and 7P2 Connectors located on the inside panel of the PDC.
(14)Close and Lock both generator set control panels.
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
c. Check that all terminal lugs and screws are securely attached to wire ends.
d. Ensure that wires are tied together as tightly as possible to avoid rubbing.
e. Check security of all hangers, clamps, and hardware that secure wiring harnesses to generator
set.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.3.1.
b. Check all suspect wires for continuity to ground. Refer to applicable wiring diagram FO - 1
through FO – 44C.
c. Test wires relating to malfunctioning circuit for continuity and internal shorts, where there is an
indication that a given harness is causing a malfunction.
10-25
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.3.1.
b. Remove all hangers, clamps, and ties attaching harness being removed from generator set.
c. Tag and disconnect all wires terminating in lugs from their mountings by removing nuts and
washers attached to their lugs.
d. Where wires are soldered to a connector, the connector is considered part of the harness and is
reinstalled with the harness. Remove screws, nuts, and washers, as necessary, to remove
multiple connectors.
e. Remove harness from generator set by withdrawing wires past any obstruction until wires are
free of generator set.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.3.1.
b. Refer to the appropriate wiring diagram FO - 1 through FO – 44C for the routing of harness being
reinstalled.
c. Carefully feed replacement wires in the harness past any obstruction into position as follows:
• Ensure there is no strain on any wire when it is in place and its connectors and mounting
lugs are attached to the generator set.
• Ensure no wire is bent over any sharp surface that might wear through wire insulation in
normal service.
• Ensure no wire is in contact with any heat producing part of the engine or exhaust system.
d. Attach multiple connectors using screws, nuts, and washers removed previously.
e. Attach all wires terminating in lugs to the correct stud or terminal by replacing mounting hardware
removed in the prior section.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.3.1.
10-26
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the Power Panel Board:
Inspect
Test
Remove
Install
10-27
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
10-28
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(10)Disconnect the negative and positive cables from both Battery Banks.
(11)Place a DO NOT OPERATE tag on both Battery Banks.
(12)Place all Circuit Breakers in the LOCK OUT position.
(13)Disconnect both 7P1 and 7P2 Connectors located on the inside panel of the PDC.
(14)Close and Lock both generator set control panels.
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
b. The MS-2 Circuit Breaker Tester or equivalent is required to test the circuit breakers.
c. Connect the test cables according to the test equipment manufactures recommendations.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.3.1.
b. Remove the 6 front cover-mounting screws and remove the front cover.
c. Remove the 5 interior cover-mounting screws and remove the interior cover.
d. Tag and disconnect the wiring from each circuit breaker and remove all conduit mounting
hardware and remove all conduit from the panel.
e. Disconnect wires, conduit hardware and box for switch, for interior lighting.
f. Remove the power distribution panel mounting bolts and remove the panel.
10-29
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
10.4.4.4 INSTALL PANEL BOARD
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.3.1.
b. Reinstall the power distribution panel and secure with mounting hardware.
c. Reinstall all conduits with mounting hardware. Reconnect all wiring and remove wire tags.
d. Reinstall wires, conduit hardware and box for switch, for interior lighting.
10-30
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
10.4.5 ALTERNATOR
Inspect
Test
Remove
Install
Generator Startup Checklist
a. Check that no wire is in contact with any sharp surface or any heat producing surface of the
engine or exhaust system.
d. Before initial start-up or after storage of a generator, use a Megger to check insulation resistance
for moisture and/or foreign material. See Section 10.4.5.2 for the procedure. A resistance
reading of one megohm or less is an indication that the winding has absorbed too much moisture.
Refer to SENR5359-01 or later version, SMCS CODE 4450 for additional reference.
10-31
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE: If an oven is used for drying, use a forced air rather than a radiant oven because radiant
ovens can cause localized overheating. If there is a possibility that insulation resistance has
lowered to a dangerous level, contact your local Caterpillar Dealer.
e. The Strip Heater is not connected for DPGDS, there are no thermostats installed. The strip
heater heats the windings to remove moisture and should be connected at all times in high
humidity conditions. Use the strip heater only when the unit is not operating. To power the space
heaters, connect an outside 115-volt or 220-volt cable to the space heater terminal block, located
on top of the alternator housing. Stop the drying procedure every hour and check the insulation
resistance. Remember, the only way to turn off the strip heaters is to unplug it from the power
source. Continue the drying process until the insulation resistance is acceptable.
f. Alternative drying methods are explained in the Caterpillar manual SENR5359-01 or SEHS9124-
01 or later versions.
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
WARNING
10-32
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
a. Periodically use a Megger to check generator main stator winding insulation resistance. The
frequency of the insulation resistance test is determined by the generator’s environment and by
previous Megger test indicators.
b. Test the main stator windings with a Megger in the following situations:
(3) Every three months if generator is operating in a humid environment or is not protected
from the elements by an enclosed area.
(4) Every six months if the generator is installed in an enclosed area with relatively low
humidity and minimal temperature variations.
(5) If generator has not been run under load for three months or more.
(6) Test every week and use space heaters if the generator is exposed to a seawater
environment or if the surrounding conditions are very humid (relative humidity above
75%) or if a recent test reading was less than three megohm. In applications where salt
and high humidity are present, space heaters must be operated whenever the generator
is not operating under load. This is the only way to maintain Megger test readings above
one megohm.
c. The insulation resistance check is described in Caterpillar Special Instruction Manual SEHS
9124-01. A reading of one megohm or less indicates that the winding has absorbed too much
moisture.
NOTE: This is a guideline only. It may be necessary to Megger more frequently if the environment is
extremely humid, salty or if the last Megger test was close to one megohm.
a. The presence of moisture, dust, grease and other foreign matter within the generator, causes the
insulation on the coils of wire (windings) to deteriorate. This deterioration reduces the resistance
of the insulation.
b. The insulation resistance (Megger) test measures the resistance of the insulation on the
windings. The insulation tester (Megger) produces a high potential voltage between the test
leads. During the test, a small current flows which the tester converts to a resistance reading.
This test is performed as part of periodic maintenance to detect the deterioration of the winding
insulation. A rapid decrease of insulation resistance over a short period of time indicates the
need for generator cleanup.
10-33
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
c. The Megger test should also be performed to detect the presence of moisture on any generators
that have not been used for a period of time. If moisture is present, the windings must be dried
prior to testing. If the measured insulation resistance is less than specified and the clean up or
drying procedure does not correct the discrepancy, the winding needs to be reconditioned or
replaced.
d. The specified insulation resistance is an approximate value. It is possible to operate the generator
with less than the specified value. However, a generator with low winding insulation resistance is
far more likely to have a failure than a generator with acceptable insulation resistance. The test
gives accurate results only when the generator windings are dry and at room temperature.
e. The minimum recommended insulation resistance of each winding must be one meg-ohm
(1,000,000 ohms) or greater.
Refer to SENR5359-01 or later version, SMCS CODE 4450 for test procedures. The following
test procedures are to be used as a guide only.
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
WARNING
10-34
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
b. Remove the upper most access panel from the PDC (generator side).
10-35
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
c. Discharge capacitive charges (with grounding stick) from all bus work and conductors.
d. Disconnect load cables T1, T2, T3, and T0 from PDC bus work.
e. Isolate Isolate the main armature (L4) from the voltage regulator by disconnecting J11 and
generator lead (T0) from the enclosure ground. Connector J11 is the deutsch connector on top of
the alternator housing.
g. Inspect all wiring, cables, and connectors for moisture, dirt and grime, etc. If moisture is present,
DO NOT TEST. Dry unit first in accordance with Special Instructions SEHS 9124-01, Cleaning
and Drying of Electrical Set Generators.
h. Connect one test lead of the insulation tester (Megger) to the generator enclosure (ground).
i. Connect the other test lead of the Megger to generator lead T1.
m. Reconnect load cables T1, T2, T3, and T0 to the PDC bus work.
n. Reconnect J11 connector and generator lead (T0) to the enclosure ground.
o. Record the results on Table 10.4.5-1, using Figure 10.4.5-2 for temperature correction.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.5.2.2.1.
b. Remove the upper most access panel from the PDC (generator side).
c. Discharge capacitive charges (with grounding stick) from all bus work and conductors.
d. Disconnect load cables T1, T2, T3, and T0 from bus work.
e. Isolate the exciter field (L1) from the voltage regulator by disconnecting J11 connector.
g. Connect one test lead of the Megger to the generator enclosure (ground).
10-36
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
h. Connect the other test lead of the Megger to generator exciter field lead F1 or F2 (pin 6 or 7 of
J11 connector).
j. Measure the resistance of the exciter field winding insulation to ground. The resistance must be
0.25 megohm (250,000 ohms) or greater.
l. Reconnect the load cables T1, T2, T3 and T0 to the PDC bus work.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.5.2.2.1.
b. Remove the upper most access panel from the PDC (generator side).
c. Discharge capacitive charges (with a grounding stick) from all bus work and conductors.
d. Disconnect load cables T1, T2, T3, and T0 from the PDC bus work.
f. Isolate the exciter armature (L2) from the rectifier circuit. Disconnect AC1, AC2, and AC3 from
the rectifier block. Refer to figure 10.4.6-2, pg. 10-58. Prevent these wires from touching one
another or contacting ground.
h. Connect the other test lead of the Megger to one of the exciter leads.
l. Reconnect the exciter armature (L2) AC1, AC2 and AC3 to the rectifier block. Torque screws to
20 – 25 in-lbs.
m. Reconnect the load cables T1, T2, T3 and T0 to the PDC bus work.
10-37
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.5.2.2.1.
b. Remove the upper most access panel from the PDC (generator side).
c. Discharge capacitive charges (with a grounding stick) from all bus work and conductors.
d. Disconnect load cables T1, T2, T3, and T0 from the PDC bus work.
f. Isolate the pilot exciter armature (L5) from the PDC AVR (Voltage Regulator) by disconnecting
PMG 11, 12, and 13 from termination points J11-1, J11-2, and J11-3 (Refer to FO 35A).
g. Connect one test lead of the Megger to the generator enclosure (ground).
h. Connect the other lead of the Megger to one lead of the pilot exciter armature (J11-1, 2 or 3).
l. Record the results on Table 10.4.5-1, using Figure 10.4.5-2 for temperature correction.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.5.2.2.1.
b. Remove the upper most access panel from the PDC (generator side).
c. Discharge capacitive charges (with a grounding stick) from all bus work and conductors.
d. Disconnect load cables T1, T2, T3, and T0 from bus work.
10-38
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
e. Isolate the PDC AVR (Voltage Regulator) by disconnecting the J11 connector.
g. Isolate the main rotor field (L3) from the rectifier circuit (diode block containing CR1 – CR6, Fig
10.4.6-2) by Disconnecting the positive and negative output wire from the diode block.
h. Connect one test lead of the Megger to one of the main field wires (either positive or negative).
i. Connect the other lead of the Megger to any part of the main rotor shaft. The bolts which hold the
rectifier block assembly onto the end of the main rotor is acceptable.
l. Record the results on Table 10.4.5-1, using Figure 10.4.5-2 for temperature correction.
m. Reinstall the positive and negative leads to the rectifer block. Torque to 20 to 25 in-lbs.
10-39
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
10-40
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Refer to Caterpillar SR4B Service Manual SENR5359-01, dated September 1999, or later.
Separating the generator from the engine and reattaching it are normally dealer level task. If this must be
done in the field, follow the instructions in the Caterpillar manual SENR 5359-01.
Refer to Caterpillar SR4B Service Manual SENR5359-01, dated September 1999, or later.
Separating the generator from the engine and reattaching it are normally dealer level task. If this must be
done in the field, follow the instructions in the Caterpillar manual SENR 5359-01.
10-41
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
10-42
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(See Table 10.4.5.5-1) This form is optional and may be used at your organization. The form is used to
create baseline information. It should be used whenever major maintenance is accomplished, such as an
overhaul or alternator replacement. The form should be kept on file and referred to during the life of the
equipment.
10-43
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the Varistor (CR8) and Rectifier Block Assembly
Inspect
Test
Remove
Install
RECTIFIER
BLOCK CR8
W/VARISTOR VARISTOR
CR7
10-44
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
10-45
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Refer to Caterpillar Manual SENR5359-01 or later for reference. The following test procedures
are to be used as a guide only.
WARNING
10-46
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
WARNING
WARNING
WARNING
To test the Rectifier Block and varistor (CR7) assembly, perform the following:
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
10-47
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(11)Place a DO NOT OPERATE tag on both Battery Banks.
(12)Place all Circuit Breakers in the LOCK OUT position.
(13)Disconnect both 7P1 and 7P2 Connectors located on the inside panel of the PDC.
(14)Close and Lock both generator set control panels.
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
b. The following procedure tests all six diodes within the block. Replace the rectifier block if any
meter reading differs from the one given. Refer to Figure 10.4.6-3 for referance.
f. Tag all leads then remove all leads from the rectifier block.
g. Place the black lead on the positive (+) rectifier terminal. Place the red test lead on the following
rectifier terminals: AC1, then AC2, and then AC3. All readings on the meter should be between
0.4 and 1.0. Refer to Figure 10.4.6-3 for referance.
h. Place the red lead on the negative (-) rectifier terminal. Place the black test lead on the following
rectifier terminals: AC1, then AC2, and then AC3. All readings on the meter should be between
0.4 and 1.0.
i. Place the red test lead on the positive (+) rectifier terminal. Place the black test lead on rectifier
terminals: AC1, then AC2, and then AC3. In all cases, the meter should be OL (overload).
j. Place the black test lead on the negative (-) rectifier terminal. Place the red test lead on rectifier
terminals: AC1, then AC2, and then AC3. In all cases, the meter should be OL (overload).
NOTE: A shorted diode can cause damage to the exciter rotor. If a diode is shorted, check the
exciter rotor. Refer to the Caterpillar manual SENR5359-01, Testing and Adjusting Section,
"Winding-Test".
NOTE: This rectifier block also contains Varistor "CR7". "CR7" can be checked by measuring the
resistance between the positive (+) rectifier terminal and the negative (-) rectifier terminal.
The resistance should be a minimum of 15,000 ohms.
10-48
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Refer to Caterpillar Manual SENR5359-01 or later for reference. The following test procedures
are to be used as a guide only.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.6.2.
b. To check the varistor (CR8), first disconnect the two leads from the (+) and (-) terminals of the
varistor, then measure the resistance between the positive (+) rectifier terminal and the negative
(-) rectifier terminal. The resistance reading should be 15,000 ohms or greater. Refer to Figure
10.4.6-4.
To remove the varistor and rectifier block assembly, perform the following:
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.6.2
c. Tag and Remove all wires on the rectifier block and varistor.
NOTE: The wires are not marked at the factory. The wires must be marked prior to removal.
d. Loosen the four bolts and Remove entire Heat Sink Assembly with rectifier block and varistor still
attached.
g. Place Thermal Compound (CAT part number 5P-8937) on new rectifier block as required
following manufacturer’s instructions.
h. Replace rectifier block or varistor on heat sink assembly using existing hardware.
i. Paint Stripe the nut and threads of the rectifier block or varistor mounting hardware to prevent
from loosening.
10-49
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
10.4.6.5 INSTALL VARISTOR AND RECTIFIER BLOCK ASSEMBLY
To install the varistor and rectifier block assembly, perform the following:
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.6.2.
b. Place Thread Lock Compound on Heat Sink bolt threads following the manufacturer’s
instructions.
c. Remount the entire heat sink assembly with rectifier block and varistor attached using the four
mounting bolts. Torque to 26 lbs/ft ± 3. Use Figure 10.4.6-1 and Figure 10.4.6-2 for reference.
d. Reconnect all wires to the rectifier block or varistor as required using new hardware provided and
Remove tags. Torque nuts and screws as follows:
h. Start the PU according to the Operation Section Chapter 5. Ensure that voltage is being
produced on all three phases. Shut down unit.
10-50
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the Medium Voltage Output Terminals:
Inspect
Test
Remove
Install
The Feeder Output Terminals (F1 and F2) are located on the lower street-side of the PDC. The Tie
Output Terminals are located on the lower curb-side of the PDC. The Feeder Output Terminals are used
to connect the PU to Secondary Distribution Center (SDC). In addition, the Tie Output Terminals are
used connect the PU to another PU, PSC or utility. See Figure 10.4.7-1 and Figure 10.4.7-2 for
reference.
10-51
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
10-52
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
c. Visually inspect all load terminal bushings for cracks, signs of overheating, and other damage.
d. Check terminal lug connections for secure mounting. Check wiring for signs of insulation
breakdown such as cracked sleeves and burned insulation.
e. Inspect all cable terminal bushings for cleanliness, cracks, signs of overheating, and secure
mounting. Check that the conductor terminal inside each bushing is clean and free from any
obstruction.
f. Apply a light coat of silicon lubricant to the exterior of the bushing well.
10-53
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
Refer to Caterpillar Manual SENR5359-01 or later for reference. The following test procedures
are to be used as a guide only.
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
WARNING
WARNING
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
10-54
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
b. Isolate the bushing by disconnecting the load cable from the rear of the bushing.
c. Turn off test equipment before connecting a 30 kV DC hi-pot tester to the load terminal.
d. Connect the positive lead of the 30 kV DC hi-pot tester to the center conductor of the load
terminal.
e. Connect negative lead of tester to outer shield of parallel or feeder cable terminal.
10-55
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
g. Slowly increase output voltage of tester to 5 kV and maintain for 1 minute. Record current meter
reading.
h. Slowly increase tester output to 10 kV for one minute and record current meter reading.
i. Slowly increase tester output to 15 kV and maintain for 15 minutes. Record readings at one
minute intervals.
j. After 15 minutes, slowly decrease tester output to zero volts and turn tester off.
m. Disconnect leads from load terminal. Compare all meter readings taken during test. Any sharp
increase in readings during waiting periods indicates insulation breakdown of load terminal and
terminal should be replaced.
1 2
3
4
6
5
(1) Load Terminal Insert (2) Load Terminal Bushing (3) Mounting Plate
(4) Protective Cover (5) Securing Cable (6) Load Terminal
(7) Load Terminal Mounting Bolt
10-56
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.7.2.
c. Remove protective cover (4), and load terminal insert (1), of the output terminal you wish to
remove.
d. Remove the mounting plate (3)and securing cable (5) mounting hardware for the entire bank of
output terminals.
e Remove the (3M) Heat Shrink Tubing from the terminal connection.
f. Remove the Load terminal mounting bolt (7) and load terminal (6).
10-57
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.7.2.
b. Reinstall the Load Terminal bushing (2). Reinstall load terminal mounting bolt (7), load terminal
(6) and (3M, BBI-3A Heat Shrinkable Tubing) or equivalant. (For torque requirements
manufactures reinstallation literature). Refer to Figure 10.4.7.3-1.
c. Reinstall the mounting plate (3)and securing cable (5) mounting hardware for the entire bank of
output terminals.
d. Reinstall the load terminal insert (1) and torque to manufactures specifications. (Special tool may
be required).
10-58
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the Surge Arresters:
Inspect
Test
Remove
Install
Surge Arresters are connected to the system bus bars, internal to the PDC. They are UltraSil heavy-duty
type UHS (MOV) Metal Oxide Varistors, rated at 3 kV, and 2.55 kV Maximum Continuous Overvoltage
(MCOV). The MOVs are contained in a silicone rubber housing. There is one arrester for each phase of
the bus, for a total of three.
10-59
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
WARNING
CAUTION
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
10-60
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
(3) Isolate the PU from any power plant control system in accordance with Note 3.
(4) Pull to open the PU DC Power Control Breaker.
(5) Push to open both Emergency Stop Switches.
(6) Place both Engine Control Switches (ECS) in the OFF position.
(7) Place a DO NOT OPERATE tag on both generator control panels.
(8) Turn the Battery Bank Parallel Switch to the OFF position.
(9) De-energize both Battery Chargers.
(10)Disconnect the negative and positive cables from both Battery Banks.
(11)Place a DO NOT OPERATE tag on both Battery Banks.
(12)Place all Circuit Breakers in the LOCK OUT position.
(13)Disconnect both 7P1 and 7P2 Connectors located on the inside panel of the PDC.
(14)Close and Lock both generator set control panels.
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
c. Visually inspect Surge Arrestors for cracks, signs of overheating, and other damage.
d. Check Surge Arrestor electrical connections for tightness. Check wiring for signs of insulation
breakdown such as cracked sleeves and burned insulation.
All UltraSil arresters have passed a complete series of production tests prior to shipment; therefore, no
field-testing is required.
10-61
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
10.4.8.3 REMOVE SURGE ARRESTER (SA1, SA2, SA3)
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.8.1.
b. Remove the lower left rear PDC panel. Refer to Figure 10.4.8-2 for reference.
e. Remove the hex nut, lock washer, and flat washer from the mounting bracket.
10-62
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
10.4.8.4 INSTALL SURGE ARRESTER (SA1, SA2, SA3)
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.8.1.
b. Install the arrester on the hanger bracket with the bolt washer and nut. Refer to Figure 10.4.8-2
for reference.
10-63
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the Instrument Potential Transformers (PT)
Inspect
Test
Remove
Install
PT 6A
PT 1A
PT 2A
PT 3A
See Figures 10.4.9-1 and 10.4.9-2 for reference. These transformers are used to step the
3800/4160VAC down to 110/120VAC for use by control system. The transformers are located behind the
cover plates on the PDC. Potential Transformers PT1, PT2 PT3, PT4 and PT5 are 5 Volt Amps (VA),
50/60 Hertz (HZ), with a 34.56:1 Ratio. PT6, PT7 and PT8 are dual primary fuse, 50 HZ with a 35:1 ratio.
The Potential Transformers are step-down transformers, which furnish voltage input for the various
generator control, metering, and fault protection circuits.
10-64
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
PT 7 PT 8
c. Check wiring for signs of insulation breakdown such as cracked sleeves and burned insulation.
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
10-65
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
WARNING
There are two recommended tests for the station transformer. They are the Insulation Resistance Test
and the Turns Ratio Test. Both tests are to be performed during maintenance. To test the transformer
perform the following:
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
10-66
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
c. Test fuses first. If fuses are good or bad, continue the test procedure.
a. Using a multimeter set to OHMS (Ω) Rx1 scale, perform individual continuity checks on
transformer primary and secondary windings.
b. Connect a 500V Megger to either primary lead and to ground. Short the secondary terminals to
ground before connecting Megger leads to primary terminals. Operate Megger for 60 seconds
and observe resistance. Reading on each transformer should be not less than 20 meg-ohms.
Short the primary lead to ground before disconnecting.
c. Short the high voltage terminals to ground before connecting Megger. Connect Megger to either
secondary lead and to ground. Operate the Megger for 60 seconds and observe resistance.
Reading should be not less than 1 meg-ohm. Short the secondary lead to ground before
disconnecting.
d. Connect Megger between primary and secondary windings. Operate the Megger for 60 seconds
and observe resistance. Reading should not be less than 20 meg-ohms. Short both windings to
ground before disconnecting.
10-67
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
b. Turns ratio testing of transformers provides a direct means to detect loose or open connections,
shorted or open turns in the transformer windings, incorrect polarity connections and to verify
precisely the no-load voltage ratio of the transformer at all tap positions.
c. Perform a TTR test using the test equipments manufactures procedures. The turns ratio is
required to be within ±1/2 percent or (.005), of the indicated nameplate voltage ratio.
Ep Np
= = TR
Es Ns
Ep =voltage primary
Es =voltage secondary
d. If the transformer fails any of the above requirements, remove and forward to next higher level of
maintenance.
e. If the transformers meet above requirements, connect wiring leads and discard tags.
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.9.2.
c. Remove access covers retaining screws and set access covers aside.
WARNING
d. Tag and disconnect all wires leading to and from the transformer.
e. Remove mounting hardware for fuses if necessary and hardware from PT and remove PT from
the switchgear panel in the PDC.
10-68
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.9.2.
b. Reinstall the transformer from front of the switchgear panels, and secure with the mounting
hardware.
10-69
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the Instrument Current Transformers (CT):
Inspect
Test
Remove
Install
GENERATOR
BREAKER CT
GENERATOR
BREAKER CT
LOAD TIE CT
FEEDER CT
FEEDER CT
See Figure 10.4.10-1 for reference. These transformers are used to step the various current level
primaries down to a 5-amp secondary for use by control system. The transformers are located between
the rear of the circuit breakers and the rear wall of the PDC. Some of the Generator CTs are partially
accessible through a bolted on panel on the rear wall of the PDC.
10-70
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
10-71
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
b. Remove the PDC from the PU. See Chapter 22 for reference.
e. Check wiring for signs of insulation breakdown such as cracked sleeves and burned insulation.
This Task is above this Echelon of Maintenance. (The PDC must be removed from the PU to perform this
task).
This Task is above this Echelon of Maintenance. (The PDC must be removed from the PU to perform
this task).
This Task is above this Echelon of Maintenance. The (The PDC must be removed from the PU to
perform this task).
10-72
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
The following maintenance procedures are provided for the Generator, Feeder and Tie Breakers:
Inspect
Test
Remove
Install
Generator
Breaker
Feeder Breaker
Tie Breaker
10-73
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
See Figure 10.4.11-1 for reference. The breakers installed within the PDC are actually vacuum
contactors; however, for consistency through the manual they are referred to as breakers. These
components use 120VAC as control voltage for opening and closing. All breakers require a constant
120VAC signal to stay closed except for the Tie Breaker. The Tie Breaker has a mechanical latch to
keep it closed even when the PU is off. This circuit also requires a 120VAC to open the breaker, which is
available from either side of the Tie Breaker. The breakers are located behind the cover plates on the
PDC.
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
Inspect the Generator, Feeder and Tie Breakers, for the following:
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
10-74
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
WARNING
10-75
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
WARNING
WARNING
PRIOR TO TROUBLESHOOTING THE POWER UNIT (PU), ENSURE THE TIE AND
FEEDER CABLES ARE ALL INSTALLED ON PARKING STANDS, TO PREVENT THE
POSSIBILITY OF UTILITY POWER BEING FED BACK INTO GENERATOR SET.
ENSURE EQUIPMENT IS PROPERLY TAGGED AND NOT ENERGIZED. RESIDUAL
VOLTAGE IS PRESENT AT THE GENERATOR LEADS WITH THE REGULATOR
TURNED OFF, REACHING SEVERAL HUNDRED VOLTS ON THE GENERATOR SET.
PROPER INSULATION AND ISOLATION OF METERING EQUIPMENT MUST BE
OBSERVED WHEN TESTING GENERATOR. USE PROPER TEST EQUIPMENT TO
CHECK FOR VOLTAGE BEFORE PROCEEDING. FAILURE TO COMPLY MAY
RESULT IN DEATH BY ELECTROCUTION.
WARNING
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. This is accomplished by performing the following:
NOTE 1: Also the PU must be completely electrically isolated from the power distribution bus and
any other electrical source that can back feed into the PU. All medium voltage cables need to
be placed on the standoff insulators by use of hot sticks and other safety gear.
10-76
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
NOTE 2: Ensure cables are not energized by opening the circuit breaker of the Primary Switching
Center (PSC), then disconnect Load Cables (Using the proper safety gear) on the PU and
place them on the Parking Stands.
NOTE 3: When the DC Control Power Circuit Breaker is in the (OFF) position (Pulled – Out), all control
power is turned off to the PU. This will cause the HUB to stop functioning. This causes the
network to not see the equipment shutdown and all PU’s after it. When pulling major
maintenance the (A) (B) Communication Cable must be routed to the next PU in order to
reestablish the communication network.
d. Remove the retaining screws to the access covers to the breaker needing to be removed. If
necessary remove the front, rear and adjacent panels to allow access to the breaker mounting
retaining screws and set access covers aside.
j. Remove the four breaker mounting bolts and remove the breaker from the front of the PDC.
NOTE: The Tie Breaker has a plate installed on the front visible portion of the mechanical
latch. Ensure the Breaker is tripped open before attempting removal of the plate. This plate
must be removed by loosening of the two bolts attaching it and saved for use on the new Tie
Breaker Mechanical Latch Assembly.
10-77
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
10.4.11.4 INSTALL GENERATOR, FEEDER AND TIE BREAKERS
a. This maintenance requires that the PU MUST be shutdown, isolated from any power plant
electrical bus or utility connection, isolated from any power plant control system, and rendered
unable to start. See procedures and warnings in paragraph 10.4.11.3.
b. Reinstall the breaker and the four breaker mounting bolts. Torque to 27 Ft-Lbs.
c. Reinstall the wiring harness and power cables. Ensure that the insulating material is reinstalled
on the power cables. Torque all power distribution bus bolts to 20 Ft-Lbs. Torque the power
cable to breaker connection to 20 Ft-Lbs.
d. Reinstall the Bakelite mounting bolts from the rear of the breaker section divider, torque to 20 in.
lbs.
e. Reinstall rear panels of the PDC and reinstall the retaining screws.
NOTE: The Contactor Dip Switch Settings must be verified prior to operation.
CONTROL
BOARD
10-78
USAF TO 35C2-3-518-1
USA TM 9-6115-484-14
DRS RADIAN CTM 01646.1R0253/1R0254
- Tag and Disconnect wires on the Control Board. See Figure 10.4.11.4-1.
- Tag and Disconnect wires for auxiliary switch.
- Remove Control Board mounting screws and pull Control Board out.
- Verify/Change Dip Switch settings. See Figure 10.4.11.4-2.
- Reinstall Control Board, secure with screws and attach wires to Control Board and Auxiliary
Switch.
g. Reinstall all of the front access covers removed with the retaining screws.
10-79