Pre Operating CFADS
Pre Operating CFADS
Pre Operating CFADS
Screenshot 3: Extract of Cashflow Next, we demonstrate how to model transparent construction funding so that the required funding line recognises that there are these early cashflows available. Usually in a Bank Base Case these cashflows might be sensitised or even switched off so that the financiers have the confidence that there are sufficient funds to complete the project without the need of early testing cashflows.
Plus any pre-operating costs: Screenshot 2: Input page (Operations) The project has 12 months of construction and the target commercial operation date is on 1-Jan-10 (COD). There is a ramp-up of production which starts 4 months prior to COD (Sep09). Hence the project will generate pre-operating revenue as well as the pre-operating operating costs. Pre-operating cashflow can be utilized to fund the construction costs and their effect on cashflows are reducing utilization of capital funds (Debt / Equity) possibly improving equity return (i.e. equity raisings could be reduced) possibly improving project return and debt ratios Pre-ops Variable OpEx (row #13 Screenshot 3) Pre-ops Fixed OpEx (row #15 Screenshot 3) Tax paid during construction (row #19 Screenshot 3)
Model the above costs in a worksheet, as demonstrated in Screenshot 4. Note: add other costs such as working capital adjustments during construction if applicable.
www.navigatorPF.com
Pre-ops Revenue (row #24) Initial Equity (row #27) Debt (row #30) Additional Equity (row #33) Screenshot 6: Extract of Cashflow However, there may be some exceptions where certain preoperating costs can be capitalized and depreciated over a certain period. For example, in this case study the pre-ops Variable OpEx is shown to be capitalized and depreciated for five (5) years. In this case the cost would appear in the income statement / balance sheet such as shown in Screenshot 8.
Screenshot 5: Sources of Funds Lets focus on period Sep-09 (4 months prior to COD, Col R): Row #21: Total cost to be funded is $5,474 Row #24: Pre-operating revenue is $486 Row #25: Remaining costs to be funded after utilizing the pre-operating revenue is $4,989 Row #30: Debt utilized in this period is $4,989 Screenshot 7: Input page (Depreciation)
Note that if the pre-operating revenue is not utilized, then the drawn debt during this period would be higher ($5,474).
www.navigatorPF.com