Assignment Project Management
Assignment Project Management
TABLE OF CONTENTS
1. Introduction --------------------------------------------------------------02 2. Action Plan for Building a Cell Phone Tower ----------------------02 3. Description of Activity --------------------------------------------------03 4. Gantt Chart ---------------------------------------------------------------04 5. Project Network (using Activity on Node-AON) ------------------05 6. Calculation of Critical path --------------------------------------------05 7. Slack calculation ---------------------------------------------------------05 8. Project scheduling (PERT analysis) ----------------------------------07 9. Cost/Time trade-off: Crashing ----------------------------------------09 10.Conclusion ----------------------------------------------------------------13
1.1) Introduction:
Being a project management student we have been assigned to submit a project proposal on constructing a Cell Phone Tower within the given period of time and resources. As we know the goals of project management should be performance based, time savings and cost effective, our ultimate goal for this project will be the same. From the definition we know project is the part of an overall program. A program is an exceptionally large long range objective thats broken down into a set of projects. The purpose of this project is to provide sound network coverage in the selected zone. The vital characteristics of a perfect project are projects exits for limited amount of time, having a definite starting and ending date, getting an opportunity to bring together the talents and skills of a wide group of people and so on. We think our project fulfill the entire basic requirement for being a perfect project.
E F G
Finalize the tower sketch and design Selecting location and getting permission Collection of hardware and accessories Hire engineer, worker and manage electricity supply Constructing the base tower Assembling hardware Activating the tower
None
01/04/2013
04/04/2013
05/04/2013
09/04/2013
100
05/04/2013
11/04/2013
700
B, C
12/04/2013
14/04/2013
10
D D E, F
7 4 2
35 10 5
DATE
03/04/2013 04/04/2013 05/04/2013 06/04/2013 09/04/2013 10/04/2013 11/04/2013 12/04/2013 13/04/2013 14/04/2013 15/04/2013 16/04/2013 17/04/2013 19/04/2013 20/04/2013 21/04/2013 22/04/2013 23/04/2013 07/04/2013 08/04/2013 18/04/2013
01/04/2013
A B C D E F G
02/04/2013
Activi ty ID
Figure:1 1
B=5
E=7
Start
A=4
D=3
G=2
Finish
C=7
F=4
From the above probable path, the longest path is ACDEG= 23 days. So ACDEG is the critical path of the project.
slack = LST - EST or LFT EFT. Also we know that the activities which have 0 slack are on critical path. From the above data and the following figure we can easily calculate the slack of each EFT EST activity; those are given in following table: (Figure: 2)
Figure: 2
4 B=5
14 E=7
21
LST
LFT
6 0 Start 0 A=4 4
11 11 D=3 14
14
21 21 G=2 23 Finish 23
4 4 C=7 11
11
14 14 F=4 18
21
11
17
21
Activity A B C D E F G
Slack 0 2 0 0 0 3 0
Critical Path* * * * * *
From the earlier calculation, we observed that all activity of the critical path having the zero slack. Activity B and F having slack 2 & 3 that means B and F can delay by 2 or 3 days without hampering the project life path.
1.8)
PERT, Elaboration form is Program Evaluation and Review Technique. The critical path analysis is well suited to projects that are repetitive in nature or involve activities whose duration times can be estimated with relative certainty. Some other projects, in practice, have activities whose duration times may not be known with much degree certainty. A method that designed to treat activity duration times as random variables is called Program Evaluation Review Technique (PERT).
Where, Te= Expected time To= Optimistic time Tm= Most likely time Tp= Pessimistic time
Where,
Activity ID A B C D E F G
O (To) 2 3 4 1 4 2 1
M (Tm) 3 4 6 3 6 3 2
P (Tp) 5 6 9 4 9 5 3
Using the mean values of the activities we can draw the network as following: (Figure: 3)
Figure: 3 3.17 7.34 B=4. 17 5.17 0 Start 0 3.17 A=3. 17 3.17 3.17 C=6. 17 3.17 9.34 9.34 9.34 9.34 9.34 12.17 D=2. 83 12.17 12.17 15.34 F=3. 17 15.17 18.34 12.17 18.34
18.34
Using the mean activity times, we construct the pert network and calculate the slack.
Calculation of Slack:
Activity ID A B C D E F G LST-EST 0-0=0 5.17-3.17= 2 3.17-3.17= 0 9.34-9.34= 0 12.17-12.17= 0 15.17-12.17= 3 18.34-18.34=0 LFT-EFT 3.17-3.17 =0 9.34-7.34= 2 9.34-9.34= 0 12.17-12.17= 0 18.34-18.34=0 18.34-15.34= 3 20.34-20.34=0 Slack 0 2 0 0 0 3 0 Critical Path* * * * * *
From the above table and network the critical path has found as ACDEG. The critical path time is a normal random variable. This mean expected project completion time is 20.34 days. Now we have to calculate Path Probabilities, W know the formula
Where, Specified time = If 23 days, Path Mean = (3.17+6.17+2.83+6.17+2) = 20.34 Standard deviation of critical path time,
From the z table we find the value of Z=1.18 is 97.06%. It says that there is a possibility 97.06% of being finished the project activity by 23 days.
10
Activity ID A B C D E F G Total
The normal schedule is following network that results from using normal time and normal cost for each activity. (Figure: 4)
Figure: 4 B=5 E=7
Start
A=4
D=3
G=2
Finish
C=7
F=4
Thus if we use normal time and cost, the project will be completed in 23 days at a cost of Tk.9,10,000.00
Start
A=3
D=2
G=1
Finish
C=5
F=3
11
In our problem the critical path is A-C-D-E-G. The cost to crash each of these by one day are 10 for A, 25 for C, 5 for D, 7.5 for E & 2 for G. Now we choose to crash G by 1 day. In this case activity G, it cant be crashed further because it reached the crash point. (Figure: 6)
Start
A=4
D=3
G=1*
Finish
C=7
F=4
The critical path is A-C-D-E-G. The cost to crash each of these are by one day 10 for A, 25 for C, 5 for D, & 7.5 for E. Now we choose to crash D by 1 day. In this case activity D, it cant be crashed further because it reached the crash point. (Figure: 7)
Figure: 7 B=5 E=7
Start
A=4
D=2*
G=1*
Finish
C=7
F=4
Again, the critical path is A-C-D-E-G. The costs to crash each of these by one day are 10 for A, 25 for C & 7.5 for E. Now we choose to crash E by 1 day. In this case activity E, it can be crashed further because it has not reached the crash point. (Figure: 8)
Figure: 8 B=5 E=6
Start
A=4
D=2*
G=1*
Finish
C=7
F=4
12
As activity has not reached at crash point, it has to be crashed further. So we will see it in new network (Figure: 9):
Figure: 9 B=5 Start A=4 C=7 D=2* F=4 E=5* G=1* Finish
Again, the critical path is A-C-D-E-G. The cost to crash each of that by one day are 10 for A & 25 for C. Now we choose to crash A by 1 day. In this case activity A, it cant be crashed further because it reached the crash point. (Figure: 10)
Figure: 10 B=5 E=5*
Start
A=3*
D=2*
G=1*
Finish
C=7
F=4
Now it is time for to crash only activity C in new network, but Activity C can be crashed further,( Figure: 11)
Figure: 11 B=5 Start A=3* D=2* E=5* G=1* Finish
C=6
F=4
Again activity C is crashed in new network and then all activity in critical path reached their crash limit. (Figure: 12)
Figure: 12 B=5 Start A=3* D=2* E=5* G=1* Finish
C=5*
F=4
13
1.10) Conclusion:
We are confident that our proposed project is very much realistic. We also believe that this project is very much competitive in the current market. We hope this project will be accepted by the higher authority and finally it will add value to the business.
14