Development of Multi-Party Risk and Uncertainty Management Process
Development of Multi-Party Risk and Uncertainty Management Process
Development of Multi-Party Risk and Uncertainty Management Process
Development of Multi-party Risk and Uncertainty Management Process for an Infrastructure Project Jirapong Pipattanapiwong , .
Development of Multi-party Risk and Uncertainty Management Process for an Infrastructure Project
Jirapong Pipattanapiwong
A dissertation submitted to Kochi University of Technology in partial fulfillment of the requirements for the degree of
Doctor of Philosophy
Development of Multi-party Risk and Uncertainty Management Process for an Infrastructure Project
Jirapong Pipattanapiwong
A dissertation submitted to Kochi University of Technology in partial fulfillment of the requirements for the degree of
Doctor of Philosophy
Development of Multi-party Risk and Uncertainty Management Process for an Infrastructure Project
by
Jirapong Pipattanapiwong
B. Eng. (King Mongkuts Institute of Technology Ladkrabang, Thailand) 1998 M. Eng. (Asian Institute of Technology, Thailand) 2000
A dissertation submitted to Kochi University of Technology in partial fulfillment of the requirements for the degree of
Doctor of Philosophy
Advisor:
Examination Committee: Associate Professor, Dr. Tsunemi Watanabe (Chairman) Professor, Dr. Keizo Baba Professor, Dr. Shunji Kusayanagi Professor, Dr. Hajime Okamura Professor, Dr. Shinsuke Nakata
ii
Abstract
Many infrastructure projects in Southeast Asian countries still have not secured good project goal achievement. Such failure could be realized in terms of severe project delay. One major reason is because of common external and internal risks and uncertainties that are inherent in all stages of project i.e., from planning, bidding, contracting to construction stage.
To cope with these risks, several risk management process (RMP) have been introduced by many researchers. Generally, conventional RMP consists of three main processes i.e., risk identification, risk structuring and analysis, and risk response. However, there are still limitations associated with conventional RMP.
Conventional RMPs is designed for the events that have high probability and high impact by prioritizing risk based on expected impact. This results in redundant risk events and tendency in overlooking a risk event with very low frequency of occurrence but extremely high impact. In many cases, we may not have sufficient necessary experience to properly deal with this type of uncertainty because of insufficiency, inaccuracy, and inapplicability of historical data, and bounded rationality of human in subjective assessment. Inattention on catastrophic event (which is uncertainty event) is the first fundamental limitation.
The second fundamental limitation is realized in interpreting the output of conventional RMPs. Since output of conventional RMPs, which is normally presented as map of tradeoff between dimensionless expected impact and risk, does not represent how much project is dela yed, it is considered difficult to interpret the output and use in communication.
Third, since the conventional RMPs do not put attention on involvement of multiple parties, the risks and uncertainties caused by involved parties may not be solved
iii
efficiently. Conflict or problems among multiple parties often arise due to difference in their perceptions towards risks and uncertainties. With this limitation, the problem solving processes including problem awareness, problem identification, and problem solving cannot be completely executed by RMP.
The objective of this research is to overcome these fundamental limitations of conventional RMPs.
Chapter 1: Introduction This chapter provides general introduction and problem statement of infrastructure projects, brief description of limitations associated with conventional RMPs, objectives of research, and description of organization of dissertation.
Chapter 2: Reviews of Risk Management for Infrastructure Projects This chapter aims to provide comprehensive understanding of risk management concept in order to build foundation for MRUMP development and application. General review of conventional RMP is firstly provided. Then, overview of multi-party risk management process (MRMP) development and application is explained. The MRMP has been previously developed by incorporating involved parties in the scope. It is important to be aware that each party may have different viewpoint towards risks and uncertainties, which can constitute problem due to difference of perception associated with project goal. Finally, further risk management literatures have been reviewed to identify unresolved areas in risk management.
Chapter 3: Post-evaluation and Limitations of (M)RMP The discussion of the applicability of MRMP based on post-evaluation study of MRMP application is provided in this chapter. The post-evaluation study aims to follow up how major risks were actually managed in case study, to compare the actual ways of risk management and those suggested from the MRMP, and to study reasons for limitation of the MRMP if there is any. As a result of post-evaluation study, the fundamental and technical limitations of (M)RMP could be identified.
iv
Chapter 4: Risk/Uncertainty Map and Hierarchical Structure of Risk and Uncertainty To overcome the fundamental limitation regarding inattention on uncertainty, this research develops risk/uncertainty map for an infrastructure project financed by international lender. Moreover, to overcome technical limitation regarding little established risk structuring and analysis procedures, this research develops standard and organized risk structuring diagram called hierarchical structure of risk and uncertainty (HSRU) framework. The developed risk/uncertainty map aims to assist practitioners in better dealing with risks and uncertainties by accumulating the experience and lessons from past projects and updating the structure. In HSRU framework, the cause and effect events are hierarchically separated. This chapter provides explanation of common risk/uncertainty map and development of HSRU framework.
Chapter 5: Duration Valuation Process To overcome the fundamental limitation regarding interpretation difficulty of dimensionless output, this research develops duration valuation process (DVP) providing logical and systematic assessment procedure of probability and impact and offering dimensional presentation of output in form of cumulative distribution of project duration. The developed DVP consists of four main processes: development of HSRU, assessment and transformation of probability, assessment and transformation of impact, and simulation by using Monte Carlo simulation. The assessment of probability in the DVP is implemented by using questions designed based on basic probability theory such as conditional probability and multiplication rule. Productivity concept, work breakdown structure and scheduling concept, and classification of delay (total delay, date delay and progress delay) are employed as basis in quantification of impact in terms of delay. This chapter provides explanation of DVP and its demonstration.
Chapter 6: Multi-party Risk and Uncertainty Management Process To overcome the fundamental limitation regarding insufficient involvement of multiple parties, this research attempts to improve the previously proposed MRMP by integrating multiple parties views. From the MRMP application, each partys view for mutual
v
reference could be obtained. However, to obtain reference is just the first step to manage risk in a project. To complete risk management, it is necessary to go through following processes: problem awareness from knowing reference, problem
identification through communication among parties, and problem solving by integration of multiple parties views. Therefore, this research develops a prototype tool called multi-party risk and uncertainty management process (MRUMP) aiming to assist all parties in systematically and efficiently managing risks and uncertainties and encouraging all parties to communicate each other, identify problem, and cooperatively solve the problem. The MRUMP consists of five main systematic processes ranging from risk and uncertainty management planning, identification and structuring, assessment and analysis, response, and control processes. A number of systematic procedures and tools such as risk/uncertainty breakdown structure and uncertainty checklist are also provided in the MRUMP. The MRUMP is presented in form of implementing manual for application purpose. This chapter provides explanation of the MRUMP manual.
Chapter 7: Application of MRUMP The application of developed MRUMP is discussed in this chapter. The MRUMP has been applied to an infrastructure project financed by an international lender as a case study located in a Southeast Asian country. Purpose of application is to discuss its applicability and to draw lesson for further refinement. The application of this case study was scoped to early stage of construction and during construction of project. The executing agency, contractor and consultant involved in the project are focused. The top managements in project level of each party have been selected as assessors and their perceptions have been investigated.
From the MRUMP application assuming at the early stage of construction, by developing integrated HSRU and risk/uncertainty impact chart, based on all parties views, the difference of each partys view could be aware.
From error analysis, assessors experience, knowledge, position, and biases resulting in ignorance of risks/uncertainties and over and underestimation of probability and impact
vi
could be identified as causations and types of error associated with each source of error. Additionally, based on comparison between each partys perception with actual status, we realize that error may be mitigated by integrating all parties views. This research simulates a meeting among all parties for risk/uncertainty communication and problem solving. From the simulation of meeting, it enables all parties to communicate and identify the future problem, which may occur due to different in their views. Finally, with integration of all parties views, they are likely to derive the possible and constructive solution, which they are satisfied as much as possible. .
Based on second timing of application, the preferable reactive and proactive responses perceived by each party could be derived. By classifying response scenarios as common and unique responses, not only solution for specific case but also lesson learnt for further improvement of whole implementation system could be obtained.
According to practitioners comments on the MRUMP, they perceived its usefulness in using as communication tool, problem preventing and solving tool, and post evaluation of project.
Chapter 8: Conclusion and Recommendation This chapter provides conclusion regarding MRUMP development and application, its contributions and recommendations for future research.
vii
Acknowledgement
It is now when I am about to leave KUT, where I have spent three years conducting this research. This research would not be possible without direct and indirect assistance from many people. Sincerely, I would like to express my profound gratitude to my advisor, Dr. Tsunemi Watanabe for his valuable and helpful advice, warm encouragement, and continuing support throughout course of this research work. I would like to thank for his efforts leading me when I was struggling, for his patience explaining me when I was confused, and for his enthusiasm cheering me up when I was frustrated. It is very much fortunate to me having chance to be his student and staff since I studied master degree and worked at AIT. With my great honor to have Prof. Hajime Okamura, Prof. Keizo Baba, Prof. Shunji Kusayanagi, and Prof. Shinsuke Nakata serving as my research examination committees, I would like to thank for their useful discussions, constructive comments, and valuable suggestions. I also would like to thank Prof. Hideaki Araki, Director of Urban Public Design Center, Japan for useful information regarding land acquisition in Japan. I very much appreciate his kind hospitality during meeting with him at Tokyo. I would like to thank Mr. Kris R. Nielsen, Chairman of the Board, the Nielsen-Wurster Group, Inc. and Ms. Patric ia D. Galloway, Chief Executive Officer and President, the Nielsen-Wurster Group, Inc. and President of ASCE 2003-2004, for their kind discussions and comments. I would like to thank all interviewees and practitioners in the case study participating in the interviews for their kind cooperation and valuable information during my data collections. I would like to thank Mr. Sumet Luetrakul and Mr. Songkran Sorachaisumlit, my senior friends at AIT for their helps and discussions rega rding practical issues. Sincere thanks are also extended to other faculties and secretaries at Department of Infrastructure Systems Engineering for their warm welcome and assistances throughout
viii
my study at KUT. I would like to thank my Japanese teacher, Kubo sensei and her fa mily. She did not teach me only Japanese language but also Japanese culture. I would like to thank Ms. Hirota and Ms. Kataoka at IRC for their efforts in taking care of documents regarding my scholarship. Many thanks are extended to all my friends in construction management laboratory. I would like to thank research assistant, Ms. Kira, for her kind helps, all doctoral students, Mr. Goso, Mr. Niraula, Mr. Du, and Ms. Guo, for their experiences and discussions, all master students, Mr. Yoneda, Mr. Asato, and Mr. Miyazaki, for their helps and enjoyments. I also would like to extend my thanks to all my Japanese and foreign friends, and my Thai juniors in concrete, planning, surveying, and transportation laboratories. I appreciate all of their friendship and encouragement. All of our cooperative activities and experiences will always remain in my memory. I would like to convey my special thanks to Weerakitpanich family for their kind and warm hospitality when I visited Thailand. Last but not least, I would like to dedicate this work to all family members (my father, mother, sister and brother), who always concern, support and encourage me throughout my study and stay in Japan. I eternally love them.
ix
Table of Contents
Title
Abstract Acknowledgement Table of Contents List of Figure List of Table PART 1: Research Introduction and Reviews Chapter 1: Introduction 1.1 Introduction 1.2 Fundamental and Technical Limitations of Conventional RMP 1.3 Research Objectives 1.4 Organization of Dissertation Chapter 2: Reviews of Risk Management for Infrastructure Projects 2.1 Introduction 2.2 Necessity of Risk Management 2.3 Risk, Uncertainty, and Opportunity 2.4 Risk Management Process 2.4.1 Risk Identification Process 2.4.2 Risk Analysis Process 2.4.3 Risk Response Process 2.5 Risk Efficiency Concept 2.6 Risk Allocation 2.7 Practice of Risk Allocation 2.8 Principle of Risk Allocation 2.9 Risk Allocation Approach 2.9.1 Qualitative Approach 2.9.2 Quantitative Approach 2.10 Willingness to Take Risk 2.11 Risk Perception 2.12 Advantages and Disclaimer of Risk Management 2.13 Risk Management Summary
Page
iii viii x xvi xxi
1 1 2 5 8 11 11 11 12 16 18 19 21 24 25 28 32 35 35 37 38 39 42 42
Introduction to MRMP Essence and Procedure of MRMP Application of MRMP Discussion of MRMP Application Further Literature Review
44 45 48 54 55
Part 2: Development of MRUMP Chapter 3: Post-evaluation and Limitations of (M)RMP 3.1 Introduction 3.2 Objective of Post-evaluation Study of MRMP 3.3 First Post-evaluation Study 3.4 Second Post-evaluation Study 3.5 Applicability of MRMP 3.6 Limitations of (M)RMP 3.7 Category of Limitations 3.8 Fundamental Limitations 3.9 Technical Limitations 3.10 Summary Chapter 4: Risk/Uncertainty Map and Hierarchical Structure of Risk and Uncertainty 4.1 Introduction 4.2 Development of Risk/Uncertainty Map 4.3 Risk/Uncertainty Breakdown Structure and Checklist 4.4 Risks and Uncertainties in Case Studies 4.5 Framework of HSRU 4.6 Summary Chapter 5: Duration Valuation Process 5.1 Introduction 5.2 Previous Risk Analysis Model 5.3 Overview of DVP 5.3.1 Work Breakdown Structure and Network 5.3.2 Risk/Uncertainty Structure Diagram 5.3.3 Risk/Uncertainty and Activity Influential Relationship 5.3.4 Subjective Assessment of Uncertainty 5.3.5 Mechanism of Delay 5.4 Development of HS RU 5.5 Assessment and Transformation of Probability
59 59 59 60 61 61 62 63 64 69 70 72 72 72 73 74 82 84 85 85 86 88 89 90 90 91 91 94 95
xi
5.6 Assessment and Transformation of Impact to Duration 5.7 Simulation Process of Project Duration 5.8 Demonstration of DVP 5.8.1 Schedule Information 5.8.2 Hierarchical Structure of Risk and Uncertainty 5.8.3 Assessed and Transformed Probability and Impact 5.8.4 Simulation Result 5.9 Summary Part 3: MRUMP and Application Chapter 6: Multi-party Risk and Uncertainty Management Process 6.1 Introduction 6.2 Overview of MRUMP 6.3 Application Framework of MRUMP 6.4 Risk and Uncertainty Management Planning Process 6.4.1 Input of Risk and Uncertainty Management Planning Process 6.4.2 Procedure, Tool and Technique of Risk and Uncertainty Management Planning Process 6.4.3 Output of Risk and Uncertainty Management Planning Process 6.5 Risk and Uncertainty Identification and Structuring Process 6.5.1 Input of Risk and Uncertainty Identification and Structuring Process 6.5.2 Procedure, Tool and Technique of Risk and Uncertainty Identification and Structuring Process 6.5.3 Output of Risk and Uncertainty Identification and Structuring Process 6.6 Risk and Uncertainty Assessment and Analysis Process 6.6.1 Input of Risk and Uncertainty Assessment and Analysis Process 6.6.2 Procedure, Tool and Technique of Risk and Uncertainty Assessment and Analysis Process 6.6.3 Output of Risk and Uncertainty Assessment and Analysis Process 6.7 Risk and Uncertainty Response Process 6.7.1 Input of Risk and Uncertainty Response Process 6.7.2 Procedure, Tool and Technique of Risk and Uncertainty Response Process
108 105 105 107 109 109 110 `113 115 116 117 117 118 119 119 120 121 123 124
xii
6.7.3 Output of Risk and Uncertainty Response Process 6.8 Risk and Uncertainty Management Control Process 6.8.1 Input of Risk and Uncertainty Management Control Process 6.8.2 Procedure, Tool and Technique of Risk and Uncertainty Management Control Process 6.8.3 Output of Risk and Uncertainty Management Control Process 6.9 Summary Chapter 7: Application of MRUMP 7.1 Introduction 7.2 Overview of Case Study 7.3 Planning Risk and Uncertainty Management 7.3.1 Roles in Application 7.3.2 Timing Assumption of Application 7.3.3 Educating MRUMP 7.4 Identifying and Structuring Risk and Uncertainty 7.4.1 Gathering Project Information 7.4.2 Identifying Risks and Uncertainties 7.4.2.1 Executing Agencys Perception 7.4.2.2 Contractors Perception 7.4.2.3 Consultants Perception 7.4.3 Constructing Hierarchical Structure of Risk and Uncertainty 7.4.3.1 HSRU, Probability and Impact based on Executing Agencys Perception 7.4.3.2 HSRU, Probability, and Impact based on Contractors Perception 7.4.3.3 HSRU, Probability, and Impact based on Consultants Perception 7.5 Analyzing Risk and Uncertainty 7.5.1 Simulation Result based on Execut ing Agencys Assessment 7.5.2 Simulation Result based on Contractors Assessment 7.5.3 Simulation Result based on Consultants Assessment 7.5.4 Cumulative Distribution of Project Duration 7.5.5 Integrated HSRU 7.5.6 Risk/Uncertainty Impact Chart 7.6 Comparing Each Partys Analysis Result 7.7 Comparison with Actual Status 7.8 Discussion of Source of Error
128 129 129 129 130 131 132 132 132 133 133 134 135 135 136 136 137 137 139 140 141 143 148 154 156 157 158 159 160 163 163 169 172
xiii
7.9 Interpreting Result 7.10 Possible Solution at Early Stage of Construction 7.11 Developing Response Scenario 7.11.1 Selected Responded Risk/Uncertainty 7.11.2 Proposed Response Scenarios 7.12 Constructing Response Scenario Diagram and Assessing Probability and Impact 7.12.1 RSD, Probability, and Impact based on Executing Agencys Perception 7.12.2 RSD, Probability, and Impact based on Contractors Perception 7.12.3 RSD, Probability, and Impact based on Cons ultants Perception 7.13 Analyzing Response Scenario 7.13.1 Simulation Result of Response Scenario of All Parties 7.13.2 Duration-Risk Map 7.13.3 Integrated Response Scenario Diagram 7.13.4 RUIC of Response Scenario 7.14 Summary Part 4: Conclusions and Recommendations Chapter 8: Conclusions and Recommendations 8.1 Summary and Deliverables of Research 8.2 Application of MRUMP 8.3 Contributions of Research 8.4 Recommendations for Further Research References Appendices Appendix A: Risk/Uncertainty Checklist Appendix B: Common Hierarchical Structure of Risk and Uncertainty Appendix C1: Analysis of Executing Agencys Assessment Appendix C2: Analysis of Contractors Assessment Appendix C3: Analysis of Consultants Assessment Appendix D: Schedule Simulation Model Appendix E: Baseline Schedule and Risk/Uncertainty Impact Chart of All Parties
175 180 183 183 184 185 185 190 195 201 203 203 208 212 214 216 216 218 221 225 227
xiv
Appendix F: Analysis of Response Scenario Appendix G: Simulation Models of Response Scenario Appendix H: Excerpt of Related Contractual Conditions
xv
List of Figures
Figure
1.1 1.2 Research framework Organization of dissertation along with phase of methodological development of MRUMP Classification of risk and uncertainty based on identifiable/unidentifiable and quantifiable/unquantifiable characteristics Phase of risk Quantification of probability Probability- impact grid Risk efficiency concept Problematic risk allocation diagram Three main processes in the MRMP Frequency impact grid in the MRMP Example of risk structure diagram from the MRMP application Prototype of risk response diagram in the MRMP Risk response diagram of efficient response from contractors perception Variance-expected impact map of the major risk in construction stage Project progress of case study in the MRMP Distinction of uncertainty analysis and risk analysis Risk/uncertainty breakdown structure Example of risk/uncertainty map Example of framework of hierarchical structure of risk and uncertainty Input-process-output flow chart of DVP Influential relationship between risk/uncertainty and activity
Page
7 9
2.1
15
2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 2.11 2.12
16 21 21 25 27 46 47 49 51 51 53
60 66 74 82 84
5.1 5.2
89 91
xvi
5.3 5.4
Mechanism of delay in network (a) Sample of hierarchical structure of risk and uncertainty and (b) based on the Venn diagram of the HSRU in (a) the shaded area shows Pr(C (A B) Example of calibrating scale for probability assessment Example of questions in probability assessment Impact assessment procedure Scheduling network diagram of flyover bridge-2 work item Hierarchical structure of risk and uncertainty, uncertainty-activity dependency, and type of delay Probability and cumulative distributions of duration of flyover bridge-2 work item Overview of MRUMP Predefined framework of application of MRUMP Procedure of risk and uncertainty response process Prototype of proactive response scenario diagram Prototype of accept response scenario diagram Prototype of reactive response scenario diagram First and second timings of application along with project progress Work breakdown structure of project Hierarchical structure of risks and uncertainties impacting entire project (executing agency) Hierarchical structure of risks and uncertainties impacting entire project (contractor) Hierarchical structure of risks and uncertainties impacting site clearing and clearing and grubbing activities (contractor) Hierarchical structure of risks and uncertainties impacting piling activity (contractor) Hierarchical structure of risks and uncertainties impacting pile cap activity (contractor) Hierarchical structure of risks and uncertainties impacting entire project (consultant) Hierarchical structure of risks and uncertainties impacting site clearing and clearing and grubbing activities (consultant) Hierarchical structure of risks and uncertainties impacting piling and
94 96
6.1 6.2 6.3 6.4 6.5 6.6 7.1 7.2 7.3 7.4 7.5 7.6 7.7 7.8 7.9 7.10
106 112 122 127 127 127 135 136 142 144 145 146 147 149 150 151
xvii
7.11 7.12 7.13 7.14 7.15 7.16 7.17 7.18 7.19 7.20 7.21 7.22 7.23 7.24 7.25 7.26 7.27 7.28 7.29 7.30 7.31 7.32 7.33
pile cap activity (impact is expressed in project level) (consultant) Hierarchical structure of risks and uncertainties impacting piling activity (consultant) Hierarchical structure of risks and uncertainties impacting pile cap (at main bridge) activity (consultant) Example of probability and impact analysis procedure Probability distribution of project duration (executing agency) Probability distribution of project duration (contractor) Probability distribution of project duration (consultant) Cumulative distribution of project duration (all parties) Integrated HSRU Risk/uncertainty impact quantification chart (only critical activities) of all parties Cumulative distribution of project duration (all parties) and actual status Hierarchical structure of source, causation, and type of error Dialog of interpretation of cumulative distribution discussion Dialog of identified risks and uncertainties discussion Response scenario diagram of accept response perceived by executing agency Response scenario diagram of reactive response scenario 1 perceived by executing agency Response scenario diagram of reactive response scenario 2 perceived by executing agency Response scenario diagram of reactive response scenario 3 perceived by executing agency Response scenario diagram of reactive response scenario 4 perceived by executing agency Response scenario diagram of proactive response scenario 1 perceived by executing agency Response scenario diagram of proactive response scenario 2 perceived by executing agency Response scenario diagram of accept response scenario perceived by contractor Response scenario diagram of reactive response scenario 1 perceived by contractor Response scenario diagram of reactive response scenario 2
152 153 155 157 158 159 160 161 162 171 174 177 180 186 187 187 187 188 189 190 191 192 192
xviii
7.34 7.35 7.36 7.37 7.38 7.39 7.40 7.41 7.42 7.43 7.44 7.45 7.46 7.47 7.48 7.49 7.50 7.51 7.52 7.53 7.54 7.55 7.56
perceived by contractor Response scenario diagram of reactive response scenario 3 perceived by contractor Response scenario diagram of proactive response scenario 1 perceived by contractor Response scenario diagram of proactive response scenario 2 perceived by contractor Response scenario diagram of accept response scenario perceived by consultant Response scenario diagram of reactive response scenario 1 perceived by consultant Response scenario diagram of reactive response scenario 2 perceived by consultant Response scenario diagram of reactive response scenario 3 perceived by consultant Response scenario diagram of reactive response scenario 4 perceived by consultant Response scenario diagram of reactive response scenario 5 perceived by consultant Response scenario diagram of proactive response scenario 1 perceived by consultant Example of response scenario analysis procedure Cumulative distribution of project duration of each response scenario based on executing agencys perception Cumulative distribution of project duration of each response scenario based on contractors perception Cumulative distribution of project duration of each response scenario based on consultants perception Duration-risk map based on executing agencys perception Duration-risk map based on contractors perception Duration-risk map based on consultants perception Integrated RSD of accept response scenario Integrated RSD of reactive response scenario 1 Integrated RSD of reactive response scenario 2 Integrated RSD of reactive response scenario 3 Integrated RSD of reactive response scenario 4 Integrated RSD of proactive response scenario 1
193 194 194 196 197 197 198 199 200 200 202 204 205 206 207 207 208 209 209 210 210 211 211
xix
Integrated RSD of proactive response scenario 2 RUIC of response scenario based on executing agencys perception RUIC of response scenario based on contractors perception RUIC of response scenario based on consultants perception
xx
List of Tables
Table
2.1 2.2 2.3 2.4 4.1 Practice of utility related works in Japan Risk allocation matrix Summary of research findings from MRMP application Summary of risk management researches in construction Project information of case studies used in developing common HSRU Types of delay to construction work Example of probability assessment expression and scale Type of delay, impacted variable and percent variation Assessed and transformed probability and impact Summary of inputs, process, outputs of risk and uncertainty management planning process Summary of inputs, process, outputs of risk and uncertainty identification and structuring process Summary of inputs, process, outputs of risk and uncertainty assessment and analysis process Probability and impact of major uncertainty, consequential uncertainty and consequential impact Summary of inputs, process, outputs of risk and uncertainty response process Summary of inputs, process, outputs of risk and uncertainty management control process Summary of MRUMP The employer, consultant and source of funds of project Key information of project Probability and impact assessment of risks and uncertainties impacting entire project based on Figure 7.3 (executing agency)
Page
31 36 53 57 77
5.1 5.2 5.3 5.4 6.1 6.2 6.3 6.4 6.5 6.6 6.7 7.1 7.2 7.3
93 96 99 103 115 118 121 126 128 130 131 133 133 142
xxi
7.4 7.5
7.10
7.11 7.12
7.21
Probability and impact assessment of risks and uncertainties impacting entire project based on Figure 7.4 (contractor) Probability and impact assessment of risks and uncertainties impacting site clearing and clearing and grubbing activities based on Figure 7.5 (contractor) Probability and impact assessment of risks and uncertainties impacting piling activity based on Figure 7.6 (contractor) Probability and impact assessment of risks and uncertainties impacting pile cap activity based on Figure 7.7 (contractor) Probability and impact assessment of risks and uncertainties impacting entire project based on Figure 7.8 (consultant) Probability and impact assessment of risks and uncertainties impacting site clearing and clearing and grubbing activities based on Figure 7.9 (consultant) Probability and impact assessment of risks and uncertainties impacting piling and pile cap activity (impact is expressed in project level) based on Figure 7.10 (consultant) Probability and impact assessment of risks and uncertainties impacting piling activity based on Figure 7.11 (consultant) Probability and impact assessment of risks and uncertainties impacting pile cap (at main bridge) activity based on Figure 7.12 (consultant) Statistics information of simulation result based on executing agencys assessment Statistics Information of simulation result based on contractors assessment Statistics information of simulation result based on consultants assessment Characteristic of risk/uncertainty associated with each party Summary of probability and impact assessment of all parties Actual status of project Comparison of expected project duration with actual project duration Probability and impact assessment of risks and uncertainties associated with accept response scenario based on Figure 7.24 (executing agency) Probability and impact assessment of risks and uncertainties
144 145
151
152 153
187
xxii
7.22
7.23
7.24
7.25
7.26
7.27
7.28
7.29
7.30
7.31
7.32
7.33
associated with reactive response scenario 1 based on Figure 7.25 (executing agency) Probability and impact assessment of risks and uncertainties associated with reactive response scenario 2 based on Figure 7.26 (executing agency) Probability and impact assessment of risks and uncertainties associated with reactive response scenario 3 based on Figure 7.27 (executing agency) Probability and impact assessment of risks and uncertainties associated with reactive response scenario 4 based on Figure 7.28 (executing agency) Probability and impact assessment of risks and uncertainties associated with proactive response scenario 1 based on Figure 7.29 (executing agency) Probability and impact assessment of risks and uncertainties associated with proactive response scenario 2 based on Figure 7.30 (executing agency) Probability and impact assessment of risks and uncertainties associated with accept response scenario based on Figure 7.31 (contractor) Probability and impact assessment of risks and uncertainties associated with reactive response scenario 1 based on Figure 7.32 (contractor) Probability and impact assessment of risks and uncertainties associated with reactive response scenario 2 based on Figure 7.33 (contractor) Probability and impact assessment of risks and uncertainties associated with reactive response scenario 3 based on Figure 7.34 (contractor) Probability and impact assessment of risks and uncertainties associated with proactive response scenario 1 based on Figure 7.35 (contractor) Probability and impact assessment of risks and uncertainties associated with proactive response scenario 2 based on Figure 7.36 (contractor) Probability and impact assessment of risks and uncertainties associated with accept response scenario based on Figure 7.37
187
187
188
189
190
191
192
192
193
194
194
196
xxiii
7.34
7.35
7.36
7.37
7.38
7.39
(consultant) Probability and impact assessment of risks and uncertainties associated with reactive response scenario 1 based on Figure 7.38 (consultant) Probability and impact assessment of risks and uncertainties associated with reactive response scenario 2 based on Figure 7.39 (consultant) Probability and impact assessment of risks and uncertainties associated with reactive response scenario 3 based on Figure 7.40 (consultant) Probability and impact assessment of risks and uncertainties associated with reactive response scenario 4 based on Figure 7.41 (consultant) Probability and impact assessment of risks and uncertainties associated with reactive response scenario 5 based on Figure 7.42 (consultant) Probability and impact assessment of risks and uncertainties associated with proactive response scenario 1 based on Figure 7.43 (consultant) Statistics information of all response scenarios based on executing agencys perception Statistics information of all response scenarios based on contractors perception Statistics information of all response scenarios based on consultants perception
197
197
198
199
200
200
xxiv
Chapter 1
Introduction
1.1 Introduction
From this time forth, development of infrastructure projects is expected to play more significant role in economic development and advancement in developing countries. Many large projects are being implemented and in plan to be launched in near future. It is desirable for all parties directly involved in a project, i.e., policy maker, lender, executing agency, consultant and contractor, to effectively and efficiently implement the project. Since failure to achieve project goals and failure to efficiently execute the project probably affect not only parties directly involved in the project but also other stakeholders such as tax payers.
Problematically, many infrastructure projects in Southeast Asian countries still could not have achieved good project goals sufficiently. One of the most frequent failures is severe project delay. One of its major reasons is existence of common external and internal risks and uncertainties that are inherent in all stages of project i.e., from planning, bidding, contracting to construction stage.
Within project management context, this research defines the terms risk and uncertainty as follows. Risk means the event/condition that its occurrence is identifiable and provides negative effect to project objective, probability distribution of outcome is quantifiable, and it is controllable by one party. Uncertainty means the event/condition that its occurrence is unidentifiable and may provide positive or negative effect to project objective, probability distribution of outcome is unquantifiable, or it is uncontrollable by one party. (The extensive description of the definition and distinction between risk, uncertainty, and opportunity is provided in Chapter 2.)
In infrastructure projects, political and economical uncertainties are common ones in the
external category. Unreasonable project objectives (e.g., time and cost), delay in awarding and contracting, unfair contract conditions, incapable executing agency, late land acquisition, delay in contractors mobilization, incapable and inexperienced contractor, financial problem of contractor, adversarial attitude, inefficient
communication, cooperation and coordination, poor project and risk management, claim, conflict and dispute are those common source and consequential risks and uncertainties in the internal category.
To cope with these risks, several risk management processes (RMPs) have been developed by many researchers (Al-Bahar and Crandall 1990; Wideman 1992; Flanagan and Norman 1993; Duncan 1996; Kahkonen and Huovila 1996; Chapman and Ward 1997; ICE 1998; PMI 2000, and Pipattanapiwong and Watanabe 2000). Generally, conventional RMPs consist of three main processes i.e., risk identification, risk structuring and analysis, and risk response. As far as the scope and application of conventional RMPs are concerned, there are three fundamental limitations and a technical limitation that is necessary to be addressed.
1. Fundamental limitations
As far as we concern about the application of conventional RMPs, there are at l east
three fundamental limitations i.e., inattention on uncertainty (catastrophic event), difficulty in interpretation of dimensionless output, and inattention on involvement of multiple parties.
Inattention on catastrophic event (which is uncertainty event) is the first fundamental limitation. In risk prioritization, risk management is designed for the events that have high probability and high impact (Smith 1999). Conventional RMPs normally prioritize risk by calculating expected impact. This results in redundant risk events and tendency in overlooking a risk event with very low frequency of occurrence but extremely high impact (catastrophic event which is uncertainty event). In many cases, we may not have enough necessary experience to properly deal with this type of uncertainty because of insufficiency, inaccuracy, and inapplicability of historical data, and bounded rationality of human in subjective assessment.
The second fundamental limitation is realized in interpreting the output of convent ional RMPs. Since output of conventional RMPs is normally presented as map of dimens ionless expected impact and variance of impact, it does not represent how much project is delayed. With this dimensionless representation, it is considered difficult to interpret the output and use in communication.
Third, the conventional RMPs do not put attention on involvement of multiple parties. Conflict or problem among multiple parties often arises due to different in their views. Since the conventional RMPs basically consider only single partys view in its scope and application, we may not be able to complete the problem solving process starting from awareness and identification of problem to solving the problem. They do not encourage and provide opportunity for involved parties to communicate and build atmosphere of harmony among project parties.
2. Technical limitations
By considering technical issue of conventional RMPs, there is little established structuring and analysis procedure. As a result, this technical limitation increases
possibility of large margin of error associated with the expected impact and variance of impact map.
Regarding risk structuring process in conventional RMPs, unorganized structuring diagram, which does not clearly separate cause and effect events in diagram, is often obtained as the output. With this messiness, it is difficult to be used in further analysis and communication. In addition, the ad- hoc way of analysis is another issue associated with this technical limitation. Due to this illogical way of analysis, the assessment of probability of occurrence of an event that is caused by other events and its impact to project objectives may not be estimated logically. Consequently, the precision of analysis output is lowered.
As an initial step to challenge the third fundamental limitation of conventional RMPs, Pipattanapiwong and Watanabe (2000) developed the MRMP considering the importance of multi-party environment in infrastructure construction projects by incorporating all parties into its scope. Since in general infrastructure projects multiple parties are involved, it is important to be aware that each party may have different view towards risks and uncertainties, which can constitute problem and conflict negatively influencing project goals. Based on the MRMP application, each partys view could be obtained for mutual reference. However, the MRMP could complete only the step of problem awareness in entire problem solving process.
To obtain reference is just the first step to manage risk in a project. To complete risk management, it is necessary to go through following processes: problem awareness from knowing what is different as reference, problem identification through communication among parties, and problem solving by integration of multiple parties views. The communication function is also an important step stipulated in problem solving process available in risk management manual proposed by FIDIC (FIDIC 1997), nevertheless, its explanation is very limited to only statements of importance in keeping communication. It does not provide how to communicate among parties and does not tell what information necessary in commutation.
It is indispensable for all involved project parties to timely be aware of risks and uncertainties and efficiently communicate those perceived exposure of risks and uncertainties among all parties. Then, all parties views should be integrated, and they should cooperatively prepare both proactive and reactive measures in responding those prospective risks and uncertainties. In order to accomplish these tasks, tool, which can facilitate and assist all project parties in logically, systematically and efficiently managing risks and uncertainties by encouraging efficient communication, cooperation, and coordination among all parties throughout project implementation in a multi-party environment, is necessary.
1. to develop a prototype tool called multi-party risk and uncertainty management process (MRUMP) integrating all parties views in its scope and processes for better treatment of uncertainty, higher precision of output, representation of output in terms of day facilitation of problem solving by integrating multiple parties views, and
2. to apply the MRUMP to a real world infrastructure project as a case study for discussing its applicability. Associated with the first objective, in order to overcome the fundamental limitation regarding inattention on uncertainty, risk/uncertainty map is produced by accumulating experiences and lessons learnt related to risks and uncertainties occurred in past similar projects to be used as knowledge base for reference. Aiming to increase precision of output, a structuring framework called hierarchical structure of risk and uncertainty (HSRU) is proposed to be used in developing organized risk and uncertainty structure and assessing probability and impact.
To overcome difficulty in interpretation of dimensionless output, duration valuation process (DVP) is developed by provid ing logical probability and impact assessment procedure and dimensional presentation of output in form of cumulative distribution of project duration. Regarding issue of inattention on involvement of multiple parties, the previously proposed MRMP is improved by not just only incorporating involved parties but also integrating their views. After HSRU framework and DVP have been developed, they are assembled as main parts of the MRUMP. The MRUMP is considered as a logical, systematic and concise tool for assisting practitioners e.g., policy maker, le nder, owner, consultant and contractor in systematically and efficiently managing risks and uncertainties and encouraging parties to communicate each other, identify problem, and cooperatively solve the problem under risk and uncertainty condition and multi-party environment. For the purpose of application, the MRUMP is presented in form of implementing manual.
The scope of risk and uncertainty management discussed in this research is bounded to construction project environment with traditional contracting. To discuss the scope of application clearly, this research divides project implementation of this type of project into three main stages i.e., pre-construction stage (planning, biding, and contracting), early construction stage ( during construction preparation and during starting project after project commencement ), and during construction stage. In this application study, the application is scoped to early and during construction stages.
In MRUMP application, this research adopted case study approach, because the application can be comprehensively studied and feasibly manageable. An infrastructure project financed by an international lender in a Southeast Asian region was used as a case studied project. Three main parties involved in the project includ ing executing agency, contractor, and consultant were focused as main players in the application study.
Risk
Conventional RMP
Limitation
EI Risk-EI Map
Error
R/U map
HSRU framework
DVP
R/U map
R/U4 R/U5 R/U6
HSRU
U2 U1 U3
R/U2 R/U1
R/U3
Act DD
Application Planning
Response Process
Application Control
Pre-construction
By accomplishing these objectives within the boundary of research scope, the major premising deliverables of this research comprise of common risk/uncertainty map for an infrastructure project financed by an international lender, HSRU framework, DVP, MRUMP implementing manual, and lessons from real world practice of an infrastructure project financed by an international lender located in a Southeast Asian country.
Based on research objectives and scope, the framework of research is defined as shown in Figure 1.1.
Chapter 1 provides general introduction and problem statement of infrastructure projects, definition of risk and uncertainty, research objectives, and organization of dissertation along with phase of methodological development of MRUMP.
The starting point of MRUMP development was originated from previous development and application of MRMP (Pipattanapiwong and Watanabe 2000). Then, further extensive risk management literatures were reviewed to identify the unsolved areas in risk management. Chapter 2 provides comprehensive understanding of risk management concept including general review of conventional RMP, overview of MRMP development and application, and summary of further review of risk management literatures.
CHAPTER 4 & 5 Phase 3: R/U Map, HSRU, and DVP Development R/U map and HSRU framework development DVP development and demonstration R/U map HSRU framework DVP process
MRMP development MRMP application to case study MRMP process Case study result MRMP contributions
Phase 1: Further Risk Literature Review Review of risk management researches Unresolved areas: risk perception, risk communication
MRUMP application to case study MRUMP process Case study result MRUMP contributions
Discussion of applicability and improvement areas Fundamental and technical limitations of (M)RMP
Figure 1.2: Organization of dissertation along with phase of methodological development of MRUMP
While the further literatures have been being reviewed, the post-evaluation study of the MRMP also was conducted aiming to discuss the applicability of MRMP and find improvement areas. According to these extensive risk literatures review and MRMP post-evaluation study, fundamental and technical limitation associated with (M)RMP could be identified. The discussion of the applicability of MRMP based on post-evaluation study and limitations associated with (M)RMP are provided in Chapter 3.
For better dealing with risks and uncertainties, the common risk/uncertainty map of infrastructure projects financed by international lenders, HSRU framework and DVP have been developed. Chapter 4 provides explanation of common risk/uncertainty map of infrastructure projects financed by international lenders and development of HSRU framework. Chapter 5 explains the development and procedure of DVP, and its demonstration.
Subsequently, in order to have complete and holistic view of application, the developed components were combined with response process, application planning process, and application control process to form the MRUMP. After the MRUMP has been developed, it was applied to a real infrastructure project to discuss its applicability. Chapter 6 provides the explanation of MRUMP implementing manual. Then, the application of developed MRUMP is presented and discussed in Chapter 7. Finally, conclusions and recommendations are provided in Chapter 8.
10
Chapter 2
Thus, there is a considerable need to incorporate the risk management concepts into infrastructure construction practice in order to mitigate or eliminate risk consequence and enha nce the performance of project.
Here, the risk management is examined in the context of project management. Initially, the clarification of terms of risk, uncertainty, and opportunity, definition of risk in various fields and characteristics and measurement of risk are described. The risk
11
identification, risk analysis and risk response in the risk management process are then explained, respectively.
Risk is characterized by three components i.e. (1) the risk event : what might happen to the detriment or in favor of the project; (2) the probability of occurrence : the chance of the event occurring; and (3) the potential loss/gain : consequence of the event happening that can be specified as loss or gain. From the above characteristics, risk may be measured by multiplying probability of occurrence with its impact (Al- Bahar and Crandall 1990; Wideman 1992; and Raftery 1994). Careful attention should be put, however, in calculating expected value since measuring and ranking risks according to this calculated figure is sometimes misleading (Williams 1996). More detailed explanation of fallacy of expectation concept is available in later part of Chapter 3.
There are many researchers that define various definitions of risk. Al-Bahar (1990), Raftery (1994), Chapman (1997), Vaughan (1997), and PMI (2000) consider both down-side (loss) and up-side (gain) of risk. Niwa (1989), Chicken and Posner (1998), and APM (2000) consider only on the down-side of risk. Definitions that emphasize only down-side may not recognize the existence of opportunity.
Risk can be defined differently depending on fields. In insurance field, terms risk is defined as follows: the chance of loss, possibility of loss, uncertainty, dispersion of
12
actual from expected results, and probability of any outcome different from the one expected.
In decision making, Flanagan and Norman (1993) stated that a decision is made under risk when a decision maker can assess, either intuitively or rationally, the probability of a particular event occurring. By contrast, uncertainty might be defined as a situation in which there are no historic data or previous history relating to the situation being considered by the decision- maker. With additional statement, the risky situation is the situation when the probability distribution functions of the potential outcomes are known. Uncertain situation is situation that the potential outcomes cannot be described in terms of objectively known nor subjectively known probability distribution (Haimes, 1998).
In project management context, Niwa (1989) and Wideman (1992) define project risk as the chance of certain occurrences adversely affecting project objectives. Considering definition defined by well-known organization in project management, Project Management Institute define terms project risk in PMBOK 2000 as an uncertain event or condition tha t, if it occurs, has a positive or a negative effect on a project objective (PMI 2000). In UK, Association for Project Management defines terms risk in its body of knowledge as risks are those factors that may cause a failure to meet the projects objectives (APM 2000).
Normally, two variables i.e., probability of occurrence of an event and outcome including consequence (favorable or unfavorable) and its probability are keys for distinguishing between risk and uncertainty.
First, the probability of occurrence of an event is considered as the variable used to distinguish between risk and uncertainty. The uncertainty varies between certain, the case in which the probability of occurrence is 100%, and impossible, the case in which the probability of occurrence is 0%. From this viewpoint, the uncertainty exists when probability of occurrence of the event is not known (Jaafari 2001).
13
Second, the risk and uncertainty is distinguished by considering the knowledge of probability of outcome. In this distinction, risk exists when there is a range of possible outcome and the probability of outcome is known, whereas uncertainty exists when the probability of each outcome is not known (Smith 1999).
Third, uncertainty is realized when both the probability of occur rence of event and the consequence and probability of outcome are not known.
Considering the terms opportunity, the opportunity is realized when there is possibility that the outcome of event may turn to be favorable. This illustrates the distinction among uncertainty, risk and opportunity.
This research characterizes risk and uncertainty into three components i.e., 1) risk/uncertainty event, 2) probability of occurrence, and 3) outcome: potential loss/gain. Practically, the definition of risk and uncertainty are basically different based on position of parties in project. Since this research considers the importance of integration of multiple parties views in the scope, we also consider this issue in defining definition of risk and uncertainty here.
Based on risk components and position of parties, this research grounds on three characteristics of event/condition including 1) identifiable/unidentifiable, 2)
quantifiable /unquantifiable and 3) controllable/uncontrollable in defining the terms risk and uncertainty.
14
Quantifiable
Unidentifiable
Identifiable
Unquantifiable
Note: All classifications of event/condition will be called uncertainty to one party if it is uncontrollable by that party.
Figure 2.1: Classification of risk and uncertainty based on identifiable/unidentifiable and quantifiable/unquantifiable characteristics First, identifiable/unidentifiable characteristic means that whether the occurrence of event/condition can be perceived or not. Second, quantifiable/unquantifiable characteristic means that whether the probability distribution associated with outcome of event/condition can be assigned or not. Third, controllable/uncontrollable characteristic means that whether event/condition itself can be manipulated by ones decision and action or not.
Within project management context, this research defines the terms risk and uncertainty as followings.
Risk means the event/condition that its occurrence is identifiable and provides negative effect to project objective, probability distribution of its outcome is quantifiable, and it is controllable by one party. Uncertainty means the event/condition that its occurrence is unidentifiable and may provide positive or negative effect to project objective, probability distribution of its outcome is unquantifiable, or it is uncontrollable by one party.
15
According to this definition, for example, if how many days of delay of an construction activity caused by an event and its probability of occurrence and outcome can be estimated or quantified, this event would be called risk event rather than uncertainty event to one party if that party can control that event. On the other hand, if that event is not controllable by that party, the event is considered as uncertainty event to that party regardless its identifiable and quantifiable characteristics. The chart in Figure 2.1 presents the classification of risk and uncertainty based on indefinable/unidentifiable and quantifiable/unquantifiable characteristics (assuming that the event/condition is controllable by one party).
We can observe from the chart that the classified uncertainty event/condition has different degree of uncertainty according to the classification. The word known and unknown is often used to represent the identifiable/unidentifiable and
quantifiable/unquantifiable characteristics of event/condition as shown in Figure 2.1. Occasionally, this research also uses this expression in later chapters.
Based on Figure 2.2, this research considers that the management of risk is not only proactive but it can be the reactive approach to manage risk when it is already occurred. Moreover, the risk management can be viewed as not only problem preventing tool but also problem solving tool.
16
Risk Occurrence Probability of impact Potential degree of impact Figure 2.2: Phase of risk
There are two basic approaches to manage risks: informal and formal approaches (Smith 1999). The informal risk management approach views risks in a subjective manner. For example, to subjectively determine the contingency either in percentage or lump sum is considered a risk management technique of informal approach. Using solely the rule of thumb and intuition to deal with risk may not be sufficient. Thus, the risk management process (RMP) is introduced to assist a decision maker to better deal with the risk, although it does not totally replace the informal approaches. APM (2000) asserts that the project risk management is recognized as formal approach that opposes to an intuitive approach. RMP attempts to facilitate and utilize the decision makers intuition and experience in a more systematic and effective way as its processes are systematic, rational, logical, preventive and priority based on significant risk (Al- Bahar and Crandall 1990 and Smith 1999).
The RMP has been discussed by various researchers in different contexts such as general context (Chicken 1996 and Vaughan 1997), project context (Wideman 1992; Duncan 1996; Chapman and Ward 1997; ICE 1998, PMI 2000; and APM 2000) and construction context (Al-Bahar and Crandall 1990; Flanagan and Norman 1993 and Smith 1999).
Generally, the RMP is described as a systematic approach to deal with risk. The RMP should establish an appropriate context; set goals and objectives; identify and analyze risks; and review risk responses. In project context, the project risk management is the art and science of identifying, assessing and responding to project risk throughout the life cycle of a project and in the best interests of its objectives (Wideman 1992). As described in PMBOK 2000 edition, risk management is defined as the systematic
17
Regarding the processes in RMP, for example, PMI (2000) proposes six major processes in for risk management i.e., risk management planning, risk identification, qualitative risk analysis, quantitative risk analysis, risk response planning, and risk monitoring and control. Although detail of each conventional RMP (Al-Bahar 1990; Flanagan and Norman 1993; Kahkonen 1996; Chapman 1997; ICE 1998; and PMI 2000) is different in term of scope and number of processes, generally, they can be divided into three main processes i.e. risk identification, risk analysis and risk response. The descriptions of these three main processes are discussed in the following sections, respectively.
There are several tools i.e. questionnaire, risk checklist, expert system and techniques i.e. interviews, orientation, analysis of documents, inspection, and observation, which are used for identifying risk (Vaughan 1997). Additionally, checklists, assumptions analysis, and diagramming techniques can be used as tools and techniques in risk identification (PMI 2000).
18
The desirable output of risk identification is the identified risks involved with the project or determined objectives. These identified risks may be classified based on the sources of risks as following classification: dynamic or static, pure or speculative, and fundamental or particular (Vaughan 1997). The information related to identified risk can be recorded in forms of risk category summary sheet (Al- Bahar and Crandall 1990) or risk log (risk register) (Smith 1999) or risk standard data card (Aleshin 2001). By using these tools risk information are kept in the form of database.
The main input to risk analysis process is the identified risks from risk identification process. The probability and impact of identified risks are two key variables in assessing the risk. In assessment of risk, there are two general types: qualitative and quantitative risk assessment (Flanagan and Norman 1993 and Smith 1999). A typical qualitative risk assessment usually includes the following issues:
a brief description of the risk; the stages of the project when risk may occur; the elements of the project that could be affected; the factors that influence risk to occur; the relationship with other risks; the likelihood of risk occurring; and how risk could affect the project.
The direct judgment, ranking options, comparing options and descriptive analysis are also considered as the qualitative risk measurement (Flanagan and Norman 1993).
19
For quantitative risk assessment, probability analysis sensitivity analysis scenario analysis, simulation analysis, correlation analysis, portfolio theory, delphi method, influence diagrams, decision trees, are lists of available techniques (Flanagan and Norman 1993 and Smith 1999).
The ultimate deliverables of risk analysis process are probability of occurrence and impact level of risks. Figure 2.3 presents the conceptual flow diagram to quantify the probability of risk. Based on diagram in Figure 2.3, the proper way to quantify probability of risk (objective or subjective) depends on the recurring condition of project risks. Practically, the historical data that is necessary for conducting objective analysis is not available. Moreover, available historical data from past projects may not be applicable for currently analyzed project, since the project characteristic and environment are unique. In this case, it is inevitable to adopt subjective analysis, when we quantify the probability of occurrence. This issue is further explained in Chapter 3.
For the impact of risk, possible consequences of risk are defined and quantified in terms of (Smith 1999): increased cost: i.e. additional cost above the estimate of the final cost of the project; increased time: i.e. additional time beyond the completion date of the project through delays in construction; reduced quality and performance: i.e. the extent to which the project would fail to meet the user performance based on quality, standards and specification.
In conventional RMPs, after we quantify probability of occurrence and impact of risk, we will map these quantified probability and impact in probability- impact grid (Figure 2.4). By using this grid, we can obtain priority of risk that high probability and high impact will be considered high priority. This is how conventional RMP prioritize risk. This research does not totally agree with this way of prioritization, because they may overlook the importance of low probability and high impact risk. This research considers this as a source of error of conventional RMPs. More detailed explanation is available in Chapter 3.
20
Project Risks
Recurring Conditions
Non-recurring Conditions
Objective Analysis
Subjective Analysis
Probability of Occurrence
High
High priority
IMPACT
Medium
Medium priority
Low
L Low
L Medium
M High
Low priority
PROBABILITY
Response is an action or activity that is implemented to deal with a specific risk or combination of risks. Risk responses can be categorized into four different forms: 21
acceptance, reduction, avoidance and transfer (Flanagan and Norman 1993 and Vaughan 1997). All these risk response form are described in the following sections.
(1) Risk acceptance Risk acceptance or risk retention is the most common method to dealing with risk. Parties facing risks will not take any action to encounter with those risks if they employ this technique. When any risk response techniques including avoidance, reduction or transfer are not employed, the possibility of losses involved in that risk is retained.
The adoption of risk acceptance may be conscious or unconscious, as well as voluntary or involuntary. Conscious risk retention takes place when the risk is perceived and not transferred or reduced. On the other hand, when risk is not recognized, unconscious risk is retained. For voluntary risk, when risk is recognized implicit agreement to assume the losses is involved. Voluntary risk is retained because there are no alternatives more attractive. Risk is involuntarily retained when it is unconscious risk and also it cannot be avoided, transferred, or reduced.
Every party must decide which risks to retain and which to avoid or transfer on the basis of its margin for contingencies or ability to bear the loss. Generally, risks, which relate to small losses, should be retained.
Carter and Dohery (1974) described two retention methods, active and passive. Active retention sometimes is referred to as self- insurance, is a deliberate management strategy after a conscious evaluation of the possible losses and costs of alternative ways of handling risks. Second, passive retention, which sometimes is called non-insurance, occurs through neglect, ignorance or absence of decision. Flanagan and Norman (1993) stated that risks suitable for retention are those that occur frequently but have small losses.
(2) Risk reduction Risk may be reduced through loss prevention and control. Loss prevention attempts to deal with risk by preventing the loss or reducing the chance that it will occur. For
22
control techniques, the purpose is to control the severity of the loss if it does happen such as sprinkler systems. In some points of view, this technique is a desirable means to deal with risk. The risk would also be eliminated, if the possibility of loss could be completely eliminated. However, loss prevention can be considered insufficient to deal with risk, because it is impossible to prevent all losses and the cost of implementation loss prevention technique may be expensive than the losses themselves. An example of loss prevention is safety program or medical care. Baker, Ponniah, and Smith (1999) also added examples of risk reduction such as physical devices that can be improved by continually maintaining and updating the devices, which help prevent loss. Education and training within every department of a business are important, especially in reducing the harmful effects of risks within the working environment.
(3) Risk avoidance Avoidance is one method of dealing with risk. When an organization or parties or individual refuse to accept risk, then risk is avoided. This means the exposure of risk is not allowed to exist. For instance, if contractors want to avoid the risk associated with the ownership of some equipment, do not purchase this equipment but lease or rent it instead. If risk avoidance is used extensively, the opportunity to receive profit or achieve objectives may be decreased. A contractor not placing a bid or the owner not proceeding with project funding are two examples of eliminating risk totally. There are a number of ways through which risks can be avoided, for examples, tendering a very high bid, placing conditions on the bid, pre-contract negotiations as to which party takes certain risks, and not bidding on the high-risk portion of the contract (Baker, Ponniah, and Smith 1999).
(4) Risk transfer Risk may be transferred from one individual to a party who is willing to bear the risk. For speculative and pure risk, transfer may be applied. The process of hedging is an excellent example of the use of the transfer technique for dealing with speculative risks. Pure risks are often transferred through contracts. In construction practice, contractual transfers of risk are quite common. In addition, insurance is also a way of transferring risk. The normal concept of insurance is that a party offers specific payment (the
23
premium) for consideration, the second party contracts to indemnify the first party up to certain limit for the specified loss that may occur.
In addition, risk transfer can take two basic forms (Thompson and Perry 1992): (1) the property or activity responsible for the risk may be transferred, i.e. hire a subcontractor to work on a hazardous process; or (2) the property or activity may be retained, but the financial risk transferred, i.e. methods such as insurance. There are other ways of using insurance as a means of transferring the risk, for example, through risk sharing or establishing a captive insurance company. In risk sharing, transfer and retention are combined. When risks are shared, the possibility of loss is transferred from the individual to the group. When the risks are shared in the group, each member has to retain the risk that the other members in the group transferred.
Additionally, it is also useful to consider the timing of the response rather than being concerned too much about the type of response, which is whether the response is to be implemented before (proactive) or after (reactive) the risk occurrence.
When a specific risk occurred, the possible responses are listed up and evaluated to find the efficient response. This efficient response is the final output of the risk response process. Additionally, other desirable output can be a risk management plan.
24
Degree of Risk
Response A
More efficient
Notably, one-sided attitude regarding risk allocation, which one party tries to dispatch all risks to other parties, probably result in unfavorable effect to both transferees and transfer him/herself.
Traditionally, in construction project, owners seek to pass most of all risks to the contractors. Another practice is that the architect/engineer would design a structure in its finished condition, and if any thought was given to the construction problems that might be involved in building it, considerable care was taken not to express their opinions on these matters in the contract documents. Risks themselves are not transferred. Actually, they transfer the responsibility of those risks. This one-sided attitude towards transferring risks foster parties who are imposed by the risks practically through contract to defend with some defensive strategies including (Levitt and Ashley 1980): 25
1. imposing contingency charges (either explicitly or in inflated unit prices), 2. adopting conservative approaches to construction design and construction methods, 3. refusing to utilize design alternavtives involving new technology because of potential liabilities arising from undue cost or failure to perform, and 4. resorting to ligation or arbitration for any possible type of dispute, whether warranted or not.
Levitt and Ashley (1980) stated that allocation of construction risks between owners and their contractors has a significant impact on the total construction costs paid by owners. The owner may have to pay twice for risks, which the owner thought he/she already transferred to other parties mainly contractors. Because when the owner lost in court, the court will reallocate those risks to the owner. Eventually, the owner has to pay for his/her risks, whereas the contractors also are not making profit.
Up to this line, the past practice of risk allocation particularly in US is already addressed. Desirably, the importance of risk allocation should be recognized since unfair and misallocation of several inherent risks in construction contract inevitably affect all project parties most probably client, contractors, and consultant. In construction contracting practice, inappropriate risk allocation in contract has been still occurring. For example, unfair bid document causing unequal risk sharing is a typical problem in construction projects financed by the World Bank (Godavitarne 1995).
Inappropriate risk allocation, consequently, in this circumstance, all involved parties will suffer (Fisk 1997). Figure 2.6 describes the problematic issues related to risk allocation in contract along with bidding, contracting and construction processes.
26
Defensive strategies Extensive contingencies in bid Lowering works quality Project delay Cost overrun Poor quality Claim, dispute and litigation
Construction process
In 1998, the Hong Kong government launched commission on reviewing the General Conditions of Contract (GCC) regarding allocation and management of risk in the procurement and construction. The purpose of the review was to enable the owner to make policy decisions on specific issues, and to facilitate a revision of the procedures and the GCCs, if necessary. The Hong Kong government assigned a famous lawyer, Jeese B Grove, to review its general conditions of contract for construction works (Loyd 2001).
This move illustrated that the importance of contract conditions concerning risk allocation has been recently realized. Basically, the principal means practically used for contractual allocation or reallocation of risks is the construction contract (Fisk 1997). It is important that the contract clauses allocating the risk are clear and unambiguous. The meaning the owner wishes to convey should be what the contractor interprets (Hartman and Snelgrove 1996). If owner and contractor lack clear understanding of risk allocation, the contractor will assume that the risk events or consequences are not contractors responsibilities. Then, the risks may not be managed properly by contractor (Wang and Chou 2003).
The issue of risk allocation is tightly linked with how contents of construction contract are drafted. Therefore, appropriate balancing and allocating of risks through the contract
27
is necessarily required.
This section aims to disclose the practice of risk allocation in some countries by using examples of unforeseen ground conditions risk and utilities risk. The following explanation reveals the practice of allocating unforeseen ground condition and utility risks in some countries as examples based on previous literatures.
(1) Unforeseen ground conditions risk In infrastructure construction project, the unforeseen or unforeseeable effect of both physical conditions and artificial obstructions could result a devastating and dramatic impact on project progress and cost. At the design stage, it is impossible to do sufficient investigation of large infrastructure construction project sites to evaluate the possibility or probability of unforeseen circumstances (Elsden 2001). The contractor can only price these risks if he is given access to the relevant information that will allow him to assess potential impact of risks.
Moreover, parties who hold information such as geotechnical reports, services/utilities details, etc. will even deny the contractor to access this information. Because these parties consider that the contractor may later take action against them due to the misleading or inaccurate information. Within this case, if these parties wish to retain the knowledge of ground conditions they should also retain ownership of the risk and provide for an appropriate contingency in the stated cost of the project. On the other
28
hand, i f the contractor is required to assume the risk, all information must be made available to ensure that the contractor is given every opportunity to assess the risk (Macdonald 2001).
Regarding Hong Kong case, according to Mr. Groves report, since Hong Kong government does not follow international practice in this respect, the government was recommended to accept that risk and costs of unforeseen ground conditions risk. However, the Hong Kong government has rejected by the reasons that from past 30 years current practice had proved to be successful. The government also claimed that if the government accepts the risk, more contractual disputes are expected to occur and final project cost are likely to be higher. Nonetheless, the government tried to provide some solutions. Procedures to reduce the exposure of unforeseen ground conditions risk is introduced as a solution. It is to ensure that the design of every major project is reviewed by a panel of senior officials within the relevant department. A minimum amount (2 percent of the value of the works) will be specified for site investigation prior to tenders being sought. And all information will be made available to bidders including assumptions that had been made by the architect or engineer (Loyd 2001).
(2) Utility risk Another example is practice of allocating utility risk. The interference from utilities apparatus has much greater significance in particularly infrastructure construction project than other types of project such as building. The utility risk caused by interference from existing or future utility apparatus is largely outside the control of the contractor and also this risk is not insurable.
In UK practice, the owner usually pays the utility agencies to undertake the diversions. If the contractors need temporary diversions, to accommodate their temporary works for example, then the contractors have to arrange with the utility agencies and pay for the diversion. If the utility apparatus is not in the location shown, or if additional utility apparatus appear, then there is a clause spefified in the contract for contractor to claim for time and cost. In US practice, costs of necessary moves of existing utitility apparatus will be paid by the owner. Moreover, the owner is liable to the contractor for time and
29
In case of Japan, most of risks regarding the existing utilities during construction of public works are principlely taken by the owner. The contractor is not required to take such risks. The reasons why such risks are taken by the government are related to the characteristics of the contract ordering system and the general concept of public works contracts in Japan, the history of underground railways construction, laws, and regulation. The General Accounting Act was enacted in 1889 based on the concept that everything should be strictly led by public agencies (Ichikawa 2001).
The Japanese public agencies consider that such important utilities, which have been provided, charged and administered by them through the long history, should not be left entirely to be handled by private entitites i.e., contractors. This seems like a matter of pride. The Japanese public agencies also percieved that it is their responsibilities for removing disturbance to daily lives of citizens during construction. Furthermore, most utility agencies are not positive in dealing with matters associated with their utilities directly with contractors. As a result a clause written as responsibility for unforeseeable conditions to be entirely assumed by the Employer is stated in the Standard General Conditions for Public Works provided by the Cent ral Government (Ichikawa 2001).
On the other hand, the practice in Hong Kong is different. The contractor has to be responsible for utility risk. Associated with this practice, the Hong Kong government is recommended to follow other practice such as in US and UK. The utility apparatus and its schedule should be specified in tender documents. Changes from the tender information and interference from unscheduled utility appratus is a risk that should be borne by the government (Elsdent 2001).
Table 2.1 shows the typical flow for dealing with utilities for construction of underground railway station in Tokyo, Japan (Ichikawa 2001).
Some remarks could be noted from the practice related to allocation of risk. According
30
to literatures reviewed in this chapter, practices in allocating particular risks are different based on countries i.e., US, UK, Japan and Hong Kong. Especially, with the Hong Kong case, it illustrates the difficulty in proving the appropriate allocation of risk in contract, when contract condition is reedited. The concept or model used for validating such contract conditions may be necessary in order to convince all contractual parties with the most efficient and desirable contract conditions.
Next sections explain the principle of risk allocation and previous risk allocation approaches proposed by preceding researchers.
Table 2.1: Practice of utility related works in Japan ITEM 1) Establish plan for utility investigation based on utility arrangement drawings (plan) provided and supplied by public road administration department of relevant authority 2) Utility investigation 3) Establish plan on how utilities to be dealt with - Diversion of obstacles/utilities - Temporary support for utilities during construction 4) Consultation and agreement on how utilities to be dealt with between relevant utility undertakers, owners and/or public road administration departments 5) Execution of utility treatment works - Utility diversions WHO DOES Contractor WHO PAYS Employer
Contractor Contractor
Employer Employer
Employer (with cooperation by contractor) - Excavation and backfill by contractor - Diversion by - Electricity, telecommunications, gas, water by specialist nominated by relevant utility agencies - Sewer by contractor Contractor
Employer
Employer
Employer
31
In several literatures related to risk allocation, the authors would inevitably describe the common principle that the risks in a project should be apportioned to those project parties who can best manage them (Macdonald 2001), though, this principle is too conceptual.
The following described principle for risk allocation in construction is the very first proposed principle (Abrahamsan 1973), which has been discussed and referred by many successive researchers. The contracting party should bear the risk in any one of the following five cases: 1. if the risk is of loss due to his/her own willful misconduct or lack of reasonable efficiency or care, 2. if he can cover a risk by insurance and allow for the premium in settling his charges, and it is most convenient and practicable for the risk to be dealt with in this way, 3. if the preponderant economic benefit of running the risk accrues to him, 4. if it is in the interests of efficiency to place the risk on him, 5. if, when the risk eventuates, the loss happens to fall on him in the first instance, and there is no reason under any of the above headings to transfer the loss to another , or it is impracticable to do so.
Whereas this principle was widely supported to be a useful first step in discussing the issue of risk allocation, this stated principle still does not provide the complete solution (Ward 1991). It does not provide the guidelines as to how economic benefits (rewards) and risks ought to be matched. It just recognizes that these two terms should be matched.
32
It is ambiguous regarding the interest of efficiency (with respect to which party? and what objectives?) described in the fourth guideline. This principle ignores the pricing of risks and the differing risk attitudes of contractual parties. These guidelines provide a little assistance in allocating risks, which are uncontrollable and controllable by more than one party. In brief, this principle presupposes or assumes an atmosphere of trust between contracting parties, and a clear, mutual appreciation of all relevant project risks and their effects. In case either of these two conditions could not be met, the appropriate allocation of risks is often diverted to the investigation and clarification of the effectiveness of allocation mechanism such as through conditions in contract (Ward 1991).
Strauss (1979) discussed against the general principles of risk allocation that there are some risks that should be assumed by a solely perspective party. The risks that should be fully assigned to owner are as: site access and necessary right-of-way, accurate determination of quantities of work, changes initiated by the owner, unforeseeable and undisclosed conditions, unreasonable delay of earned progress payments, major catastrophes including flood and earthquakes. For the contractors, they should be fully responsible for the risks including: availability and costs of labor, materials, and equipment, timely completion, subcontractor and supplier failure, productivity of labor and equipment, construction mistakes and defective work, compliance with safety regulations, traffic maintenance as specified.
In addition to above principle, guidelines described by another researcher (Fisk 1997) that should be recognized as criteria used for sharing of risks inherent in a construction project are described as:
1. All risks are rightfully those of the owner unless and until contractually transferred to or assumed by the contractor or insurance underwriter for a fair compensation. 2. The principal guideline for transferring a risk is whether the receiving party has both the competence to assess the risk fairly and the expertise necessary to control or minimize it.
33
3. An additional guideline is the determination of whether the shift of the risk from the owner to another party will result in savings to the owner and the public.
In March 1998, Mr. Grove was asked by the Hong Kong Government to review the general conditions of contract for construction works. The following subjects in the conditions of contract were considered: ground conditions, physical impossibility, care of the works, delay caused by public utility works, fee and charges, new legislation, payments to sub-contractors and time bar provision in relation to claims. Mr. Grove identified the following common considerations related to risks allocation (Loyd 2001).
- Which party can best control the events that may lead to the risk occurring? - Which party can best manage the risk if it occurs? - Whether or not it is preferable for the employer to retail and involvement in the management of the risk. - Which party should carry the risk if it cannot be controlled? - Whether the premium charged by the transferee is likely to be reasonable and acceptable. - Whether the transferee is likely to be able to sustain the consequences if the risk occurs. - Whether, if the risk is transferred, it leads to the possibility of risks of different nature being transferred back to the employer.
Mr. Grove thought that if these considerations were applied it should be possible to achieve clear and realistic terms that were acceptable to the owner and contractors. Thus, contractors would prepare tender of which the tender prices did not contain contingencies for unclear terms or for significant risks, which were not possible to estimate with some clarity or which were unlikely to materialize.
Hartman and Snelgrove (1996) also stated that it is important that the contract clause allocating the risk be clear and unambiguous. The meaning the owner wishes to convey should be what the contractor interprets. Therefore, a balancing of the risk should be sought amongst owner, contractors, and other parties in order to utilize the incentive
34
value of bearing a risk while minimizing the contingency charged for accepting the risk. There will be a particular allocation of risk between these parties, which will be optimum in terms of final project cost to an owner. Again these guidelines can be useful for initially allocating a risk; however, more detail of evaluation is required. It is with expectation of this research that the proposed risk and uncertainty management tool can be used as a means for risk allocation during contract formation.
35
qualitative approach. The risk allocation matrix basically attempts to identify what type of risk is allocated to whom. Several studies (Erikson 1980; Kangari 1995; Snelgrove 1994, cited by Yamaguchi 2001) conducted the study to investigate the preference of involved project parties regarding the issue of who bears what construction risks in most commonly used delivery methods (Yamaguchi 2001).
Quantity Variations
Can be transferred to the contractor; however, client has obligation to undertake pre-contract exploration measures, and the designer has the responsibility to design for the conditions expected. Contractor can be expected to assume risk up to 15 to 25 percent. Where quantities are dependent upon unforeseen subsurface conditions, client must assume the risk.
Financial Failure Accidents at Site Defective Works Management Incompetence Funding Materials and Equipment Labor Problems Client-Furnished Equipment Delays in the Work Defective Design
Usually the contractors risk; however, client could incur some liability.
In addition, a research proposed the matrix presents the principal risk bearers in several types of procurement systems such as traditional, design and build, construction management, etc,. Also, a graphical model was proposed to determine apportion of risk among project parties by percentage (Kumaraswamy 1997). Table 2.2 shows an
36
example of risk allocation matrix (Fisk 1997). This risk allocation matrix has been slightly modified from original source by reorganizing types of risk into two categories i.e., external and internal risks. The risk allocation matrix could be used for primary assisting in allocating risks to project parties. It should be noted that there is no fixed rule to allocate the risk to only one party; however, as shown in the table some risks could be shared.
Cooperative risk allocation assumes that the stakeholders jointly search for an agreement that is mutually acceptable. Most cooperative risk allocation defined the optimum solution as where the total contingency costs of the project are minimized. Decision theory, computer simulation and cooperative game theory are examples of concept used in developing cooperative model. On the other hand, the competitive risk allocation is the allocation where each of the stakeholders employs the strategy that best achieve their own goals without any concern for the other stakeholders (Yamguchi 2001). The insurance theory for example is the concept, which the competitive risk allocation was relied on.
Another model considered that actual risk allocation is relied on the combination of cooperative and competitive allocation of risks. It means the solutions provide room for negotiation. The potential solutions together constitute the negotiation space. This
37
model linked the risk allocation in contract to insurance theory. Development of this model focused on the costs dur ing construction and the profit during operation and maintenance in PFI project. This model shows theoretical bases of risk allocation in PFI projects such as feasible risk allocation, conditions of project parties attitudes and assessment of a certain type of PFI projects and optimal risk allocation under the complete information (Yamguchi 2001).
The difficulties of this model are how to determine the allocation ratios of the varied costs during construction and the varied profits during operation and maintenance and the risk premium. Moreover, the optimal risk allocation of this model can be achieved under the assumption that all project parties have complete information. In practice such ideal situations where all project parties reveal their risk attitudes and assessment are rare. This model also does not discuss the optimal premium and government contribution. The authors disclaimers are that even this model may not be able to reflect real situations; however, it can be used as a benchmark or best practice to evaluate risk allocation. And to analyze the optimal premium, various types of cooperative game theory and premium calculation principles can provide such solution (Yamguchi 2001).
Additionally, to discuss the optimal risk allocation, this m odel used the negotiation space on the expected utility space between client and contractor. Then, the optimality is evaluated by using the concept of Pareto-optimal ratio (Yamguchi 2001). The concept of Pareto optimality is explained that the first objective can be enhanced only at the second objective is degraded (Haimes 1998). To use expected utility as the objectives in evaluating Pareto optimality may not be suitable, since to improve ones utility may not necessary degrade another ones utility. Furthermore, in many risky situations, people do not seem to behave in a way that is compatible with the maximization of expected utility (Shapira 1995).
38
take on risks. There are a number of factors that all parties will consider to bear the risks. The willingness to bear risk is appropriate only as it is based on a general attitude to risk, an adequate perception of project risk, a real ability to bear the consequences of a risk eventuating, and a real ability to manage the associated uncertainty and mitigate the risk. On the other hand, willingness to bear risk may be inappropriate when it is due to inadequate perception of project risk, a false ability to bear the consequences of a risk eventuating, a need to obtain work, and a false perception of the risk/return tradeoffs of transferring the risks to another party (Ward 1991).
Above abstracted statement illustrates the risk definition and how important of risk perception from of businesss or services viewpoint with including construction. Every risk evolves through three main phases: the potential risk, the actual occurrence, and the impact (Papageorge 1988).
For a risk to exist there must be a hazard and the perception of hazard is entirely subjective, what is hazardous to one man may not be perceived to be so by others. The hazard perception, which is related to aspect of previous experience, cultural values and training in field of expertise, is described as the individuals subjective view of particular hazard (Greene, Root, and Thrope 2000).
There are researches related to risk perception in other fields such as psychology. Most of those past researches studied the perception of general risks influencing wide range general people such as nuclear weapon and reactor accident, AIDS, and so on.
39
Related to health and safety field, aiming to improve communication between policy maker and public, Slovic (1987) developed techniques called psychometric diagram for assessing the complex and subtle opinions that people have about risk. The psychometric paradigm, which uses psychophysical scaling and multivariate analysis techniques to produce quantitative representations or cognitive maps of risk attitudes and perceptions, is famous technique in presenting risk perception and has been employed by many researchers.
Axelrod, Mcdaniels, and Slovic (1999) examined lay perceptions of ecological risk associated with natural hazards by using psychometric risk perception study to explore whether natural hazards are perceived to pose risk to natural environments. By exploring the individual difference on risk perception, Twigger-Ross and Breakwell (1999) examined the relationship between venturesomeness, past personal experience of specific hazards, and perceived characteristics of certain voluntary and involuntary hazardous activities of English adults in UK. Cha (2000) compared risk perception towards 70 environmental risks of three samples (Korea, Japan and US) by using psychometric diagram.
Risk characteristics i.e., known/unknown, calm/dread, controllable/uncontrollable, etc., have been identified and used as attributes in evaluating risk perception. Then, the perception of risk has been portrayed in psychometric diagram, of which each axis represents the characteristics of risk (Axelrod, Mcdaniels, and Slovic 1999; Twigger-Ross and Breakwell 1999; and Cha 2000). However, Fife-Schaw and Rowe (2000) identified limitations of psychometric diagram in monitoring changes in perceptions, the impact of risk communications, differences between groups, and other potentially more informative applications. Af Wahlberg (2001) evaluated three approaches to risk perception i.e., the psychometric, the Basic Risk Perception Model, and the social amplification of risk.
In risk management perspective, these previous researches seem to cover only the area of risk identification, which do not cover risk analysis and response processes. In field of construction, h owever, the area of risk perception is not intensively researched. To
40
understand risk perception will be beneficial for determining the risk attitude, which is a persons willingness to either take or avoid risks, and evaluating how to response risks in both proactive and reactive actions.
Nonetheless, when viewpoints of multiple parties have to be incorporated, only providing a set of efficient responses to them is probably insufficient. As a feature of the MRMP, the response characteristics evaluation enables the understanding of response characteristics to a risk perceived by involved parties, which is significant in a multi-party environment (Pipattanapiwong, Ogunlana and Watanabe 2003). However, to understand risk perception will be beneficial for determining the risk attitude, which is a persons willingness to either take or avoid risks, and evaluating how to response risks. Thus, it is necessary to investigate the risk perception of each involved parties towards responses portrayed in the degree of risk and expected impact map in order to determine efficient response that matches with the partys perception of risk. This is still not achieved by the MRMP.
Moreover, from the past literature review study, it was found that the area of risk perception is still not intensively studied in field of construction (Pipattanapiwong and Watanabe 2001), although there are a number of risk perception researches in other fields such as psychology, insurance and culture.
Infrastructure construction project is a one important stem for economic development particularly developing countries. Failure to achieve project performance according to several inherent risks inevitably affect all stakeholders i.e., public agencies, contractors, taxpayers and users. In infrastructure construction project, risks should be perceived by the stakeholders who are involving in the project, then the appropriate proactive or reactive risk response can be taken. If risk is not perceived and treated proactively, risk will be probably developed to the last phase of its potential loss or harm. In addition, when risk evolves to occurring stage, if its occurrence is perceived and it is treated by appropriate reactive risk response, its harm may be partly mitigated or totally eliminated. This emphasizes the importance of risk perception and risk management integration.
41
Additionally, risk analysis is not a substitute for professional experience and judgment. Contrarily, it assists professionals to make use of the full extent of their experience and knowledge by liberating them from the necessity of making simplifying assumptions in order to produce deterministic plans and forecasts. Risk analysis is supplement to, not a substitute for, professional judgment (Raftery 1994).
On the other hand, Raftery (1994) summarized the benefit of risk management by referring many writers, consultants and users of risk management agreement.
There is an overall reduction in risk exposure; Pre-planning should lead to the use of pre-evaluated and prompt responses to any risks which do materialize;
More explicit decision making on the project; Clear definition of specific risks associated with particular project; Full use is made of the skill and experience of project personnel; Good documentation ensures that corporate knowledge of project risks accumulates over time and does not remain with individuals;
Situations where there is little, no or unreliable data are not ones where it its not possible to carry out the analysis, they are situations where the analysis is more, not less, important.
42
relies mostly on intuitive and rule of thumb, which is not logic. Risk management process, which is systematic, rational, logical, and proactive approach, assists decision- maker to manage risk systematically and most efficiently. Main processes in risk management consist of risk identification, analysis and response. Risk management will not remove all risks, however, it provides explicit and better decisions for a decision- maker in making decision. Benefits of risk management process are as reducing of risk exposures, preplanning and providing prompt response to risks, incorporating experience in analysis, and offering more explicit decisions.
As a way to deal with complex characteristics of the infrastructure construction project itself and risks inherent in the external and internal of project, it is desirable to apply the concept of risk management into the practice throughout life cycle of infrastructure construction project. The chapter points out this necessity and summarizes the risk management concept including the clarification of uncertainty, risk and opportunity, definition of risk and overview of risk management process including risk identification, risk analysis and risk response processes. Additionally, practice and principle of risk allocation are also described in later parts.
Practically, the consequence of misallocation of risk in contract could adversely affect all involved parties as a result of high contingency, conservative design and construction method, lowering work quality, claim, dispute and litigation. This induces the issue of risk allocation should be put more attention. Some points could be noted from the principle and practice of risk allocation. The difference of risk allocation practice could be noticed in different countries like US, UK, Japan and Hong Kong. The risk allocation model used for validating contract conditions is necessary in order to convince all contractual parties with the fair contract conditions that can provide most efficient and desirable solutions.
The primary conceptual risk allocation principle is a useful first step in discussing the issue of risk allocation; however, this principle may not provide the complete solution. Several risk allocation approaches have been proposed based on the early conceptual risk allocation principle. Even though, those models could provide some ranges of
43
solutions, many assumptions are appended to those models. Sometimes, it could not represent the real situation in practice. Therefore, a risk allocation model, which can efficiently and systematically allocate the risks to all contractual project parties such in assisting validation of contract condition, is required. Development of such risk allocation model may be worthwhile for all contractual parties in infrastructure construction project in practice.
In the next sessions, the development and application of a RMP called multi-party risk management process (MRMP) is explained. This aims to provide more understanding of how RMP is developed and how RMP is applied.
Conventional RMP has been employed to assist decision- makers instead of using solely intuition. Nevertheless, as a fundamental limitation of the conventional RMP, only one partys view is generally considered and the objectives associated with multiple project participants may be overlooked in the analysis. Risk identification and response are considered and evaluated by one party. When a risk affects parties involved, it is important to answer the question of how to properly identify risk and what is the best response that is desirable for all parties.
Since responses to some risks taken by one party may create risks to other parties, risk-response-risk chain may be notified. The process of risk and response evaluation by involved parties is probably absent in the conventional RMP. In a multi-party environment such as infrastructure construction projects, the conventional RMP may
44
not be necessarily sufficient. A systematic process of managing risks in a multi-party environment is thus required.
Pipattanapiwong and Watanabe (2000) proposed a RMP entitled the multi-party risk management process ( MRMP) that considers the several parties views involved in project. The multiple parties involved in a project and their objectives are incorporated throughout the processes of the MRMP. Following sections summarize the development and application of the MRMP.
The MRMP has been developed and applied to a public bridge and elevated construction road project located in a Southeast Asian country as a case study. This case studied project was proportionally financed by local government (45%) and an international lender (55%). The aim of application was to demonstrate procedure and discuss applicability of the MRMP. In the case study, the procurement and construction stages have been studied. The perception of three main parties i.e., the executing agency, the contractor, and the consultant have been investigated.
45
Risk Identification
Obj.1 Obj.2 Obj.n R1 R2 R3 R4 R5 Rn
Purpose: to identify important each partys objectives and perceived risks that affect parties involved in project Tools & Techniques: questionnaire, risk checklist, analytical hierarchy process, frequency impact grid
Risk Structuring
R1 R4 Obj.1 R3 Obj.2 R2 R5
Purpose: to specify dependencies among risks and objectives and identify the major risks Tools & Techniques: questionnaire, influence diagram, graph theory
Purpose: to evaluate response to major risk and provide efficient response Tools & Techniques: questionnaire, expected impact and variance map
Impact
Efficient response
The proposed MRMP consists of three main systematic and logical processes as shown in input-process-output flow diagram in Figure 2.7. Associated with purpose of each process, the set of systematic and analytic tools and techniques such as analytical hierarchy process, risk checklist, frequency impact grid, graph theory, influence diagram, probability and impact analysis, and expected impact and variance map are employed as summarized in Figure 2.7. 46
IMPACT
Medium
Low
Very Low
3 Very Low
2 Very High
Low
Medium
High
FREQUENCY
Note: 1= First priority; 2 = Second priority; 3 = Third priority
The multiple parties involved in a project and their objectives are incorporated in each process. Priorities based on significance of risks and objectives are considered. The MRMP relies on quantitative measurement and analysis as well as attempts to utilize the decision- makers experiences and intuition in a systematic and efficient way.
The details of explanation of the MRMP process can be further reviewed in Pipattanapiwong and Watanabe ( 2000a and b) and Pipattanapiwong, Ogunlana, and Watanabe (2003). In the MRMP, after all practitioners identified risks and preliminarily assessed the frequency and impact of risks, their perceptions towards these two values are plotted in the frequency impact grid as shown in Figure 2.8. As we can see from frequency impact grid shown in Figure 2.8, the way MRMP prioritizing risk is similar to risk prioritization in conventional RMPs. Risk event that is assessed as more high frequency and more impact is regarded as more important.
47
To assess the probability, the scale is divided into five intervals from very low, low, medium, high and very high. Then, the simple number i.e., 1, 2, 3, 4, and 5 are assigned to each interval of frequency, respectively.
The procurement and construction stages of this project have been studied. Three main parties have been investigated: (1) the executing agency, (2) the contractor, and (3) the consultant. The other related parties such as the lender, the borrower government, facility public agencies, subcontractors, suppliers, public residents and other stakeholders are not emphasized in the analysis although they are considered as sources of risks that can affect these three main parties.
48
6.2 Late payment by Executing Agency 8.2 Contractor lacks of financial support from bank
6.4 Executing Agency interference such as acceleration of works 6.5 Executing Agency expects quality beyond standard and specifications 10.2.3 Lacking of coordination and different working system among engineer and foremen
10.2.1 Engineers and foremen lack of technical skill 10.1.1 Labor cost fluctuation 10.1.2 Low productivity of labor
5.1 Drawing needs innovative construction method and new materials and equipment 4.1 Works conditions differ from contract
Contractual Risk
49
1.3 Economic crisis 1.2 Interest rate fluctuation
3.1 Facility public agencies late in moving facility that obstruct construction
Political Risk
Economical Risk
Figure 2.9: Example of risk structure diagram from the MRMP application
The project was ongoing in the construction stage during the application of the MRMP. It should be noted that results of the MRMP have different implications depending on when it is applied. In this case study, although the procurement stage has been already completed, it was assumed that the analysis was conducted at a later part of the procurement stage. The objectives of this analysis are to study whether major risk could have been managed more efficiently or not and to draw lessons for a similar project in future. For the construction stage, the analysis was assumed to be conducted when major risks were just occurring.
As an output of risk structuring process, an example of risk structure is presented as Figure 2.9 in order to enable us in understanding the picture of risk structure and how complexity it is. This example of risk structure is developed according to contractors perception of risk against scheduling objective.
Since all parties similarly identified the contractors liquidity and financial problem risk as the major risk in the construction stage as well as its response evaluation yielded some interesting conclusions. Thus, the response evaluation of this major risk is further explained with the purpose to introduce how particularly the risk analysis and response process was implemented in case study. According to the risk analysis and response process, response alternatives to the major risk are listed up. Then, the source and consequence risks of the major risk associated with each proposed response alternative are identified by each party. As a result of identifying such risks, the risk response diagrams associated with each response alternative are consequently developed as shown in Figure 2.10. The prototype of risk response diagrams includes diagrams for (a) no-response, (b) accept, (c) proactive, and (d) reactive responses.
50
Source risk 1 Source risk 2 ... Source risk n (a) Source risk 1 Source risk 2 ... (Source risk 1) (Source risk 2) (Major risk) Proactive response Source risk n (c)
Source Risk
4. Late payment by Executing Agency
Consequence risk 1 Major risk Consequence risk 2 ... Consequence risk n (Consequence risk 1) (Consequence risk 2) ... (Consequence risk n)
Major Risk
3. Bank does not support loan to Contractor
Source risk 1 Source risk 2 ... Source risk n (b) Source risk 1 Source risk 2 ... Source risk n (d)
Reactive Response Major Risk (after taking response) (Contractors liquidity and financial problems)
Consequence risk 1 Major risk Accept response Consequence risk 2 ... Consequence risk n (Consequence risk 1) Major risk Reactive response (Major risk) (Consequence risk 2) ... (Consequence risk n)
Figure 2.11: Risk response diagram of efficient response from contractors perception
In case of the contractors liquidity and financial problem risk, the accept response and three more reactive responses have been proposed. The accept response was to accept the situation after the major risk occurred by not taking any action. Other three remaining responses were new capable contractor joins or takes over the current contractor, bank provides financial assistance to the contractor, and the executing agency terminates the contract.
51
Regarding the source risks, the economic crisis and bank does not support loan to contractor risks were source risks that have been identified by the all parties. Interest rate fluctuation, material price fluctuation and late payment by the executing agency risks were additional source risks identified by only the contractor. The risk analysis and response interviewing sheet was used to investigate each partys perception toward the impact and probability of those risks. All parties identified almost the same set of consequence risks. However, for examp le, lender interference and cancellation of loan risks were additionally identified by the executing agency. Furthermore, both the executing agency and consultant specifically identified conflict among contractors risks as consequence risk if the new capable contractor joins or takes over current contractor response was applied. Remarkably, the executing agency and the consultant assessed only the impact of conflict among contractors risk as very high, whereas the contractor even did not perceive this risk.
For example, the risk response diagram of the contractors liquidity and financial problem risk when new capable contractor joining or taking over current contractor based on contractors perception is shown in Figure 2.11. After each partys perception is investigated towards source risks, major risk, and consequence risks associated with each proposed response alternative, the evaluation result i.e., expected impact and variance of impact are calculated and plotted in expected impact and variance map. In the MRMP, the variance is employed to represent the degree of risk and the expected impact is employed to discuss the impact level of risk. The calculations of the expected impact and variance rely on the assumption that there are two possibilities of the major risk in each response scenario, i.e., occur or not occur. If the major risk occurs, the probability of occurrence is assigned. On the other hand, if the risk does not occur, the probability of occurrence is zero. The derived Eq. 2.1 and Eq. 2.2 are used for calculating expected impact and variance, respectively.
52
Variance
Variance
Variance
90 75 60 45 30 15 0 0 5 10 15 20 25 30
90 75 60 45 30 15 0 0 5 10 15 20 25 30
Expected Impact Contractor Major risk: Contractors liquidity and financial problem
Figure 2.12: Expected impact- variance map of the major risk in construction stage
Contractor (CT)
Contract price
Construction stage Executing Schedule, Agency Budget, Quality (EA) Contractor (CT) Consultant (CS) Schedule - CTs liquidity and financial problem - New capable CT joins or takes over the current CT
Schedule
- Multi-party risk-response-risk evaluation - Multi-party response efficiency evaluation - Response characteristics evaluation
These equations are subjected to n = number of response scenario, I = total impact level of major risk, and P = probability of occurrence. The expected impact-variance map, which consists of two dimensions i.e., expected impact in the horizontal axis and variance in the vertical axis, is used to present the efficiency condition of responses and discuss characteristics of response in a quantitative and graphical format.
53
When a major risk influences multiple parties, the response to the risk should be desirably efficient for all parties. In case of response evaluation of the contractors liquidity and financial problem risk, from the expected impact- variance map in Figure 2.12, the new capable contractor joins or takes over the current contractor response seemed to be desirable response for the all related parties including the executing agency, the contractor, and the consultant.
After going through risk identification, risk structuring, and risk analysis and response processes in the case studied project, the results revealed the significant risks associated with each party in the procurement and construction stages and the efficient responses to each significant risk. According to the results, the MRMP contributions are provided accordingly. The overall results of the MRMP application are summarized in Table 2.3.
Applying the MRMP will not remove all risks, however, it will enable decision making for mitigating the potential effect of certain risks, and providing the efficient response.
54
Improved project performance from such decision making will definitely bring the benefits to not only the main parties directly participating in execution of the project but also other stakeholders such as taxpayers and users of the infrastructure project.
According to the result of application, although the MRMP could provide extensive contributions from conventional RMP, there are still rooms for improvement. Regarding the subject of development and application of the MRMP, issues that should be further improved including complexity of risk structure due to inefficiency in structuring and quantification of probability of occurrence and impact of risk. Moreover, the application of the MRMP should be extended to discuss in issue of risk allocation in contract during contract formation stage.
Additionally, risk management related papers from 1997-2001 particularly published in main well-known journals in construction management field e.g., Journal of Construction Engineering and Management, Construction, Management, and
Economics, International Journal of Project Management, Engineering Construction and Architectural Management and etc., were reviewed. The arrangement of review results of the summary in this paper and that past study (Edwards and Bowen 1998) is different.
55
This section summarizes the past risk management researches by considering the risk management researches in the areas of risk category, risk management process development, subjective issues in risk management, usage of risk management process in practice, and project type that risk management process was applied associated with each process in risk management: risk identification, risk analysis and risk response. A tentative summary of intensive level of past risk management researches in construction is shown in Table 2.4.
The intensive levels of previous researches, which are evaluated from the number of researches that specifically discuss areas within determined reviewing framework in risk management, are represented as high, m edium and low, respectively. Noted that the contents in one paper can discuss more than one area.
Researches that studied the economic and financial risk, building, estimating and scheduling related risks, managerial risk, political and legal risks, cultural risk, social risk, health and safety risk, etc., are included in the risk category field.
Risk management process development field includes the researches that developed and proposed the process in risk management i.e., risk identification, risk analysis and risk response. Researches, which studied subjects related to subjective assessment, risk perception, risk attitude and risk communication, are included in the field of subjective issues in risk management. Researches, which conducted survey regarding usage of risk management in practice, are included in the survey of risk management usage. Researches, which focused on the application of the process in risk management to a specific type of project, are included in the field of type of application project.
From the tentative summary of past risk management researches in construction, the findings specify the areas of researches, which have and have not been intensively studied. Considering researches in risk category field, most of risk management researches in construction focused on risk identification and risk analysis to a specific risk i.e., economic and financial risk, bidding, estimating, and scheduling related risks. The reason why there are many researches intensively studied in identification and
56
analysis of these risks is probably because of the availability of objective data such as cost and duration, which could be simply used in conducting simulation or developing probability distribution for risk analysis. On the other hand, to conduct risk analysis of others risk categories such as managerial, political, cultural, social, design and so on, the objective data of these risks is unavailable or not simply to be quantified. To analyze these risks, the subjective judgment is essential.
The developments of risk identification and risk analysis process were intensively researched than the development of risk response process. There are several systematic tools and techniques available to be promptly used in risk identification. Several quantitative and qualitative techniques also are available for risk analysis. However, in risk response process, which includes the certain areas in risk response i.e., risk allocation, risk reduction, risk avoidance, risk retention and risk transfer, the less systematic and well developed frameworks have been provided.
Risk Identification Medium Low Medium Medium Medium Low Low High Low Low Low Low Low Medium Low
Risk Analysis High High Medium Low Low Low Low High Medium Low Low Low Medium Low Medium
Risk Response Low Low Low Low Low High Low Low Low Low Low Low Medium Low Low
Risk Category Economic, Financial, Bidding Risk Estimating, Scheduling Related Risk Managerial Risk Political and Legal Risk Cultural Related Risks Health and Safety Risk Social, Design, Force Majeure Risk Risk Management Process Development Subjective Issues Subjective Assessment Risk Perception Risk Attitude Risk Communication Survey of Risk Management Practice Type of Application Project BOT Infrastructure Project
57
The intensive level of past researches related to subjective issues in risk management such as subjective assessment, risk perception, risk attitude and risk communication seem to be tentatively low. The past researches rarely incorporated the subjective related issues such as risk perception, risk attitude and risk communication with the process in risk management. It seems also that there is no clear and systematic framework in quantifying for example perception to risks. In addition, the application of risk management to infrastructure construction project seems to be less intensive than other types of project scheme such as BOT project.
58
Chapter 3
In the post-evaluation, the evaluation result of response towards the contractors liquidity and financial problem risk was particularly focused in the construction stage. The data were mainly collected from the secondary data such as a final project report and unstructured interview with respondents from the same groups as those when the MRMP was initially applied: the executing agency, the contractor, and the consultant.
59
1380 days
Actual
10
15
20
25
30
35
40
1st Postevaluation
45 Month
2nd Postevaluation
MRMP application The contractor s financial problem risk Contractor Inviting a contractor negotiating to join with bank Possibility of
terminating contract
The entire project progress and important events regarding the contractors liquidity and financial problem risk occurred during project construction are presented in Figure 3.1. In this project, the percent progress was measured by the amount of payment paid to the contractor. The estimated baseline schedules (including original, 1st revision, and 2nd revision versions) are presented in dotted line. The actual project progress is presented in the bold line.
60
difficulty in working together with the new contractor. The conflict was mainly related to financial issues such as the payment from the executing agency.
Underestimation of impact of this consequence risk, the conflict between the two contractors, is potentially caused by a bias associated with wrong timing of the MRMP applicatio n. When the MRMP was applied, business of the response that the new contractor joins the current contractor was in progress. In order for the respondents
61
to justify their response, therefore, they might have underestimated impact of the consequence risk associated with this response and overestimated that associated with other responses. It is definitely important to apply any risk management technique when no predetermined solution is being developed or implemented.
When the MRMP was applied, the new contractor was not incorporated as another player assuming that the new contractor had a similar perception to the original contractor. But this assumption was wrong. The new contractor had been encountering the difficulty due to conflict with the original contractor and the bank. The new contractor still pursued the works, however, for needing a job during no-works period, keeping a good relationship with the original contractor, and building- up a high reputation. Thus, the objectives of the new contractor may not be the same as those of the original contractor. It was additionally found from the post evaluation that the new contractor did not have correct information on the project status when the new contractor was joining the original contractor. The original contractor withheld necessary information related to the amount of remaining works. Analysis of the new player should be carefully done because she or he may have different objectives from existing players and not have correct or sufficient information on the project status.
In this case study, when risk occurred in practice, all parties used no formal or systematic risk management process. The practitioners made their decisions based on only experience; and risks were managed individually not collectively. The limitations of the MRMP identified in this study needs to be solved to make the MRMP more applicable to analysis of a real construction project. Commitment to risk management by all major parties from early stage of the project is desirable. The MRMP seems to have a potential to support such a desirable practice.
62
risk analysis, and risk response processes. The aim of the RMPs is to assist decision maker in systematically and efficiently managing risks occurring in the project. Through the consisting processes of the RMPs, the expected impact and variance of impact are produced as outputs of the RMPs. These two values could be subsequently portrayed in expected impact-variance map to present the efficiency condition associated with each response. For example, the output of RMP plotted in this map can be seen from the result of the MRMP application in previous chapter (Figure 2.12).
Based on the study of conventional RMP, application and post-evaluation of the MRMP as well as the unresolved areas in risk management literatures, the detailed explanation of fundamental and technical limitations associated with conventional RMP and MRMP are provided in following sections. The contents of following sections are partly referred to Pipattanapiwong and Watanabe (2003).
63
Prioritization of risk based on the probability impact grid is discussed by several literatures (Al- Bahar, 1988; Williams, 1993; Chapman, 1997). The MRMP also employs concept of probability impact grid in distinction between major and minor risks. This issue is directly related to the fallacy of expected value concept. As a simple example, associated with the process of risk analysis, generally the RMP employs concept of expected value. The expected value is the product of multiplication of probability and impact (e.g., in terms of cost). For example, event A, its probability is 0.1, its cost impact is 1,000 dollars. The n, its expected cost impact is 100 dollars. For event B, its probability is 0.0001, its cost impact is 1,000,000 dollars. The expected cost impact could be calculated as 100 dollars, which is equal to the expected cost impact of event A. If we adopt the concept of expected impact in prioritization, this means that the priority of these two events is same. Even though, event B is the rare event that has high catastrophic impact. Therefore, there is possibility that the conventional RMP may neglect importance of low-probability and high- impact event and may mislead decision when this fashion of prioritization is adopted. Smith (1999) stated that for the event that has high impact and low probability, the consideration might not be necessary since it is too remote. Notably, they seem to neglect the importance of low-probability and high- impact event. Although this type of event rarely occurs or even almost no-possibility to occur, its occurrence would
64
substantially damage the project. It usually has been proved in many real projects that this type of event could significantly make project suffering with substantial delays, cost overrun, project being suspended, or even being abandoned.
It could be further discussed about the application of risk management associated with the low probability and high impact event. Based on the risk prioritization, Smith (1999) explained that the risk management is designed to use for identifying, assessing, and managing the events that have high probability and high impact. Many risk analysis techniques, which have been developed to basically deal with the event that has high probability, because the historical data of this kind of event is usually available. On the other hand, for low probability event, its historical data is normally unavailable; thus, it is inevitable to rely on subjective judgment for assessing its probability of occurrence and impact.
Based on the condition of event in probability impact grid, the area of risk analysis and uncertainty analysis then can be distinguished as shown in Figure 3.2. The uncertainty event is considered as the event that has low probability and high impact, because its occurrence is probably uncertain or even unknown. In this kind of event, we may not be able to assign the probability distribution by using historical data as doing in risk analysis.
According to the MRMP application and post-evaluation study, for example, the economic crisis risk, which could be considered as a low probability risk, actually occurred in the case studied project. It resulted substantially delay approximately 53 percent delay from its original contract duration. As an example, this could illustrate that the necessary attention should be put on this type of event. We should not discard this type of event during the risk prioritization and distinction, which is considered as one technical limitation in the conventional RMPs.
65
High
Low
Low
Furthermore, regarding this first fundamental limitation, we may ignore and may not be aware of significant risks and particularly uncertainties due to limited experience and bounded rationality of human in subjective assessment.
Most of the case, the historical data is usually unavailable and insufficient. In application of the MRMP, due to unavailability of objective data in evaluation of probability of occurrence and impact, the subjective assessment was inevitably adopted. Additionally, even for the high probability event that its historical data may be available and is possible to acquire; the issue of inapplicability of that available historical data is necessary to be considered. This data may not be accurate and applicable due to the uniqueness of project characteristic and environment. Because the project conditions and environment is usually unique, then the data from previous projects may not necessarily be applicable to current analyzed project. Therefore, the utilization of subjective data is indispensable when conducting both uncertainty and risk analysis.
In subjective assessment, bias is inevitable. The human judgmental ability is often defected by various biases, which distort the correct perception. The possible biases include availability, selective perception, illusory correlation, conservatism, law of small numbers, wishful thinking, illusion of control, logical construction, and hindsight bias (Flanagan and Norman 1993). Chapman (1997) stated that as a result of limited 66
information processing ability, people normally adopt heuristics when estimating uncertainty, which can lead to error in estimates. Three types of bias are listed up: adjustment and anchoring, availability, and presentational effects.
For example, from the MRMP application result, in construction stage of the case studied project, the contractors assessment of probability of occurrence of economic crisis risk was distorted by availability bias. Since the contractor was suffering from the financial problem caused by economic crisis during the MRMP application study, the contractor then overestimated probability of occurrence of economic crisis risk as high, even though the economic crisis is considered as rare event.
Indeed, t i is noted that the attention on the importance of low probability and high impact event should be drawn. We should not discard this type of event during the risk prioritization and distinction. Moreover, since it is difficult for practitioners with limited knowledge and experience to identify uncertainty, it is necessary to have a tool used for assisting practitioners for better treating uncertainty due to ignorance.
2) Interpretation difficulty of dimensionless output Theoretically, the essence of the conventional RMPs is based on the risk efficiency concept. As described by Chapman (1997), the output of the RMP based on risk efficiency concept is the tradeoff between two values i.e., expected impact, which is expected value of damage and preparation effort in terms of time or cost, and variance of this impact. For the MRMP, by relying on the risk efficiency concept, the major output of the MRMP is the expected impact-variance map used for graphically presenting the degree of risk by using terms expected impact and variance associated with each response scenario.
Inevitably, the MRMP relies on the subjective judgment in its processes, for the reason that the unavailability of objective data and the subjective issue could not be discarded from the risk management study. As a result, the terms expected impact and variance in expected impact-variance map are presented in dimensionless value. Although, when historical data is unavailable, to represent terms expected impact and variance in 67
dimensionless format is also common in other conventional RMPs. However, to further transform these values from dimensionless value to dimensional value such as in terms of duration and cost that can represent how project goal is achieved is desirable. This probably facilitates practitioners to interpret result simpler. For example, the impact is represented in terms of project delay and cost overrun associated with project duration and cost, the variance of impact means how much the actual project duration and cost is likely to deviate from expected duration or cost. Consequently, these two variables can be presented in the form of cumulative distribution function (CDF) as well as expected duration/cost-variance map.
3) Insufficient involvement of multiple parties Scope is particularly important where the system is controlled by many relatively independent decision makers, who usually have different objectives (Haimes 1998). Many researchers have proposed and discussed the RMPs to cope with risks occurring in construction project (Al-Bahar 1990; Flanagan 1993; Duncan 1996; Kahkonen 1996; Chapman 1997; and PMI 2000). However, these RMPs are discussed on the basis of one partys view in managing risks influencing his/her objectives. When a risk affects several parties involved in the project, particularly risk analysis and response evaluation processes in the conventional RMPs usually do not incorporate those involved parties views. Since construction project is considered as a multi-party environment, which several parties are involved, by neglecting the importance of other parties objectives and ways in managing the risks, this could increase degree of risk and difficulty in managing the entire project. Eventually, the project objectives can be deteriorated, and all parties will probably suffer.
Since the conventional RMP is a method developed to systematically obtain risk-efficient responses for a single party, it could be understood that the risk perception of other parties towards the response is beyond the scope of the RMPs. When a risk management study is undertaken from the viewpoint of one party, the most desirable response may be derived without significant difficulty (Pipattanapiwong, Ogunlana and Watanabe 2003). As explained in previous chapter, to overcome this limitation the MRMP has been proposed. Then, it has been applied to a real infrastructure construction 68
project to discuss its applicability. The basis of MRMP fulfills two Asian values: (1) the maintenance of harmony in group situations; and (2) the pursuit of profit for all involved parities. According to its application in a real infrastructure construction project, a number of features, which are extensively developed from the other conventional RMPs, include multi-party risk-response-risk, objective evaluation of each party, multi-party response efficiency, and response characteristics evaluations (Pipattanapiwong, Ogunlana and Watanabe 2003).
The MRMP considered the involvement of multiple parties in processes; however, the views of involved parties were not fully integrated. Without integration of multiple parties views, we may not be able to complete the problem solving process starting from awareness and identification of problem to solving the problem. In other words, MRMP does not sufficiently encourage and provide opportunity for involved parties to communicate and cooperatively solve problems.
Normally, conventional RMPs do not provide any structuring framework to facilitate practitioners in specifying dependencies among risks. Practitioners have to start in drawing risk structure from scratch. Due to this reason, practitioners may neglect important risks. Additionally, by starting from the scratch, practitioner may face difficulty and confus ion in specifying the dependency among risks that can result in messiness and complexity of risk structure. Figure 2.9 shows an example of risk structure diagram as a result f rom MRMP application. As a result of messiness and complexity of risk structure, the cause and effect events are not clearly separated.
69
subjective judgment in assessing probability and impact. In order to reduce this discrepancy, the logical procedure to subjectively assess probability and impact is necessary. Commonly, in conventional RMP, if subjective assessment is employed in the process, assessor is asked to assess the probability and impact by directly rating their value in the scale from very low to very high. With this way of rating, the assessment is not grounded on structuring framework and probability theory.
In summary, by considering this problematic technical issue of conventional RMPs regarding little established structuring and ana lysis procedure, this technical limitation increases possibility of large margin of error associated with the expected impact and variance of impact map.
3.10 Summary
The MRMP has been previously developed to challenge a fundamental limitation of the conventional RMP. The MRMP incorporates the involved parties in project and their objectives in each process of analysis. Then, it has been applied to a real infrastructure project financed by the ADB located in Southeast Asian country as a case study. Several contributions of the MRMP, which is extended from conventional RMP, consist of: objective evaluation of each party, multi-party risk-response-risk evaluation, multi-party response efficiency evaluation, and response characteristics evaluation. The post-evaluation of the MRMP application has been conducted to investigate the discrepancy between application result and real practice. Regarding the post-evaluation study, its result revealed areas, which the MRMP should be further improved, including the framework of risk perception and the improvement of risk analysis and response process. Additionally, risk allocation, which the MRMP was still limited in development and application, is another area that should be further studied.
It can be noted that there are some implication between results of application and post-evaluation of the MRMP application and results of risk management researches reviews in previous chapter. Based on the application and post-evaluation of the MRMP application, the issue of risk perception and risk response process development were
70
similarly pointed out to be improved or further studied. In addition, from the observation of risk management in practice particularly in the case study of the MRMP, the practitioners use solely the ir experience and subjective judgment in managing risks. It seemed that they do not have adequate understanding regarding the sophisticated risk analysis techniques. Therefore, the future risk management research should fulfill the gap in unresolved areas and also to satisfy the need in practice.
Even though, several RMPs have been developed and proposed, there are still fundamental and technical limitations associated with (M)RMP, which could falsify their consequent outputs. Based on the literature review and post-evaluation of the MRMP application, the fundamental limitations have been identified as inattention on catastrophic event (which is uncertainty event), interpretation difficulty of dimensionless output, and insufficient involvement of multip le parties. Regarding technical limitation, little established structuring and analysis procedure has been pointed out. Considering the theoretical issues to further develop the new RMP, it is desirable to put consideration on these limitations. This research aims to overcome these limitations associated with (M)RMP.
71
Chapter 4
This risk/uncertainty map has been developed based on the literatures related to construction field as well as experiences of real world project. Although, the scope of development of this risk/uncertainty map is initially bound to project financed by international lenders, it is also considered possible to be used as guideline in other types of construction projects.
Two main sources were used in developing prototype of risk/uncertainty map i.e., 72
literatures for risks/uncertainties related to construction projects in general and experiences of three infrastructure projects financed by international lenders. Initially, the risk/uncertainty breakdown structure (RUBS) was developed. Then, the risks and uncertainties preliminarily collected from various literatures (Healy 1981; Perry and Hayes 1985; Al-Bahar 1990; Zhi 1995; Edwards 1995; Fisk 1997 and Pipattanapiwong 2000) were arranged based on the categories of uncertainty in RUBS to develop the checklist of risks and uncertainties.
Afterwards, to develop prototype of risk/uncertainty map, past exp erience of three infrastructure projects financed by international lenders including subway construc tion project, bridge construction project and hydropower construction project were used in identifying risks/uncertainties as well as their relationships. Various data collection methods were employed in acquiring experience of these case studies. Project document review, in-depth interview with practitioners on-site, and site visit and observation were conducted for the bridge and hydropower construction projects. For subway project, the experience was mainly acquired from secondary data such as project report and news with additional expert interview.
This research also considers the importance of those stated common language and comprehension of risk on a project. The RUBS has been developed with consideration of mutually exclusive classification among risk/uncertainty categories. Based on integratio n of multiple parties, the risk/uncertainty categories related to all involved parties are also included in RUBS.
73
Political
Nature (weather)
Contractor
Physical
Miscellaneous
Activity
Labor Equipment
Sub-contractor & supplier
Material
Site
Work
There are 20 categories of uncertainties in four levels in developed RUBS. The RUBS is presented in Figure 4.1. Based on the categories categorized in RUBS, the checklist of risks and uncertainties is developed. It is available in Appendix A. Moreover, both RUBS and risk/uncertainty checklist are two important tools used in risk identification and structure processes.
74
Due to complexities and several involved parties, risk and uncertainty are substantially inherent in this type of infrastructure projects. World bank (1990) figures show that for 1,627 projects completed between 1974 and 1988, they experienced the delay varied between 50% to 80% (Bordoli and Baldwin 1998). In recent years, failure to achieve project objectives is still an issue needing considerable care and attention. 50%-delay of completion of a bridge construction project in country A, one-and-a-half year delay of opening of subway project in country A, and one-year progress delay of a hydropower project in country B are some of real world examples illustrating present situation of projects.
The implementation process of the construction projects financed by an international lender is generally different from typical public construction projects. The international lender is involved and many rules and contractual procedures are determined. The project cycle generally starts from project identification, preparation, appraisals, loan negotiations, commitments, project implementation, project supervision and ends with post evaluation and monitoring after completion.
The international competitive bidding (ICB) is their typ ical project procurement method. The contractual arrangement is more or less similar to traditional contracting contract. The traditional contracting procedure normally consists of a number of stages including project planning, bidding, contracting, and construction. Many contractors and consultants from various countries can participate in project, since project is opened internationally for those eligible countries specified in lender procurement guideline. Normally, they are members of that particular international lender. This makes project environment become international. Additionally, several guidelines and rules are enforcedly annexed for project implementation in procurement and construction stages. All of these characteristics further increase the degree of uncertainty, complexity, and difficulty in project implementation.
In case of world bank projects, incomplete design and detailed engineering, lack of transparency and usage of ambiguous bid evaluation criteria, delayed contract awarding, unfair bidding documents and unequal risk sharing, incapability of lowest bidders,
75
insufficient supervision and contract administration and incapable contractor are typical problems, which have occurred in procurement and construction stages (Godavitarne 1995). For ADB financing projects in Thailand, insufficient institutional capability, late land acquisition and right-of-way problem, procurement difficulties and lack of efficient coordination among agencies are experienced problems influencing project performance (ADBs post evaluation report 1999). They cause serious delay in procurement process of ADB project (Hayashi 1986).
Moreover, common problems in infrastructure projects occurring along with the traditional contractual procedure could be shortly listed up below. Planning stage: - Insufficient study for determining project duration - Relying on policy factor more than engineering factor in determining project duration Bidding stage: - One-sided attitude towards contractor in allocating risks in contract - Insufficient information to contractor for preparing bid - Insufficient time for provided bid preparation time - Insufficient attention on contract condition regarding risk responsibility during bidding - Inefficient communication about risk responsibility during bidding Contracting - Insufficient consideration on responsibility of risk allocated in contract condition during contracting - Inefficient communication about risk responsibility during contracting - Inappropriate timing of notice to proceed issuance Construction stage - Insufficient effort in planning and preparation of works before project commencement - Delay in submitting base-line schedule during the beginning of construction stage - Poor project scheduling, monitoring and control - Inefficient communication among project parties
76
Conflict among project parties Adversarial attitude towards others Poor cooperation and coordination among project parties
There are three case studies used in developing the prototype of risk/uncertainty map. All of them are projects financed by an international lender. The overview information of these three projects is summarized in Table 4.1. Table 4.1: Project information of case studies Case 1 Case 2 Subway Lender A 303 Billion Yen Country A Bridge Lender B 3.6 Billion Yen Country A
Brief description of risks and uncertainties occurred in these case studies are provided as following.
External risk/uncertainty
Economic:
Economic crisis It results in fluctuation of exchange rate difficulty in project finance. Country A has been facing sever economic crisis. For foreign investors, it is inevitable to owe certain exchange rate risk. The projects had been awarded just before the announcement of local currency floatation, since then it has been devaluation so rapidly. It is assumed such economic movement might not have been taken much into account at tender stage and the contractors have been forced to adopt urgent hedging method for future economic risk. In addition, severe economic condition and cancellation of many infrastructure projects may cause the shortage of liquidation in the cash flow of this project and raise the cost of capital excessively. Moreover, the economic crisis was the main causation for contractors financial problem.
77
Political:
Instability of government, late Cabinets approval, and inconsistent policy When the government has been changed, most probably the policy is also changed accordingly. This instability affected the plan of project. Example of disturbance by frequent government policy change has been experienced in these projects. Since then policy changes relating to finance, the effect of conceptual design change has continued to disturb the implementation of projects. Furthermore, inadequate budget from the
government, late the governments approval and inconsistency of the government policies also caused delay in awarding and signing contract. The impact of these causations could affect the execut ing agencys objectives such in procuring capable contractor and consultant and timely signing contract in the procurement stage.
Internal risk/uncertainty
Procurement process:
Late procurement of contractor, concessionaire, and consultant Due to executing agency cannot procure the consultant and designated contractor as planned such as construction supervision consultant, lift and escalator, depot, track work, M&E concessionaire. Such delayed procurement caused problems regarding with design interface that made project delayed.
Delay in signing contract among concessionaire contractors Due to the abrupt cancellation of the contract signing to purchase the trains and operating systems in concessionaire contract caused by disputes about stock allocation, the commercial service of subway was delayed. Consequently, the operation of whole project was likely to be delayed. .
Delay in awarding contract During bidding stage, a project has been delayed around one and a half year. This awarding of contract has been delayed due to following factors: bidders complaint,
78
unclear bid documents, late land acquisition, and late executing agency approval. The consequence associated with delay in awarding contract resulted in delay in signing contract and late commencement of work.
Contract:
Unclear contract This problem seemed to occur in both contracts between the executing agency and consultants and between executing agency and contractors. This ambiguous contract initiated a lot of problems during procurement and construction stage. The consultant did not know their duties clearly to perform their works. The possibility of conflict and dispute became high due to this problem. The design and construction contractual arrangement scheme between contractor and the executing agency might be the cause of ambiguous contract.
Defective preliminary design In subway project, the alignment of route and design of tunnel system seemed to be inappropriate. The tunnel should be single tunnel system rather than separated tunnel system. This caused problem and difficulty in construction and operation stage such as in construction of cross over between two tunnels. During the operation stage, the train may not be able to service according to determined timetable.
Executing agency:
Inexperienced executing agency in procurement and construction Inexperienced executing agency in the procurement process created other problems such as unfair prequalification criteria, unclear bid documents, bidders complaint and delay in awarding and signing contract. In case of subway project, due to this is the first subway project in Country A, the executing agency seemed to have not enough experience in subway construction, this resulted in delay in making decision.
79
Late land acquisition In these projects, entire land could not be acquired before commencement of work. The problems of land acquisition then occurred in construction stage such in tunnel construction. For example, when the conflict arose between the executing agency and a hotel, it was took place about one year to settle the conflict. Finally, the executing agency had to pay for additional cost for redesigning and relocating one station and project was delayed.
Consultant:
Incapable and inexperienced project consultants The executing agency had to employ the project consultant to act as his representative, and give consult to the executing agency. The capability of consultant that was considered significantly could influence the executing agencys decision. An ineffective preliminary design was an example of incapability of consultant problem. The role of consultant seemed to be crucial to project performance, when the executing agency did not have sufficient experience about project.
Contractor:
Traffic management problem In subway project, the traffic problems always occurred in the area of station construction. Most traffic disruptions are created around the construction site of underground train stations as they are constructed through cut-and cover techniques.
Contractors deficiency Difference in contractors qualification from specified in contract, contractors financial problem, failure to construct as drawing and specification and lack of coordination among contractors in joint venture were examples of contractors deficiency. Particularly, the contractors financial problem was the significant causations during construction stage.
80
Lack of coordination among engineers and foremen This caused low efficiency during executing the project since they could not coordinate each other well. This impacted in schedule, quality and budget of project.
Lender:
Less lenders participation Lender seemed to put more attention on procurement process and project financing. However, lender did not put much attention in preliminary design stage.
Commercial bank:
Lack of financial support from bank In a case study, bank stopped to provide loan to contractor. This was a factor made the contractor difficulty in executing project due to inadequate financial support.
Public complaint In these case studies, the public often complained about their inconvenience and property damage in the immediate vicinity of construction work.
Lack of other public utility agencies cooperation The executing agency often faced the difficult when working with other public utility agencies. During construction stage, some works were related to utilities diversion and traffic diversion, which were under various others authoritys control. It needed huge effort to get approval from them. The working method and sequence had to be changed if such approvals are delayed.
The example of risk/uncertainty map of these three case studies are shown in Figure 4.2.
81
Political Political
Inefficient Contract Contract Inconsistency bureaucratic system of policy Incompleteness Instability of of contract Late government approval
Inexperience
Owner Owner
Managerial incapability
Misinterpretation of contract
Technical incapability
Contractor Contractor
Exh. Rate fluctuation Interest rate fluctuation Technical incapability Poor coordination of CTs
Late approval Lack financial support Managerial incapability Late payment Financial problem
Financial problem
Bank Bank
From the literature review and experiences of past case studies, it is realized that there are many risks and uncertainties involved in the project throughout the project contractual procedure from project planning to construction. With the study of these past projects, they seem to experience some common risks and uncertainties. The risk/uncertainty maps based on the experiences of these case studies are provided in Appendix B.
82
be used as a basis in logically assessing probability and impact of risks and uncertainties. Figure 4.2 shows framework of HSRU.
HSRU is divided into four main layers based on hierarchical flow of source, consequence, occurrence, and outcome from upper to lower layer respectively. Source layer contains source of risk/uncertainty. Consequence layer contains consequent risk/uncertainty. Occurrence layer contains influential risk/uncertainty and influenced activity. Outcome layer shows type of delay. Based on the framework of HSRU, the cause event (including source and consequence layers) and effect event (including occurrence and outcome layers) can be obviously separated.
In the layer of cause event, multiple risks and uncertainties are connected as the flow of source of risk and uncertainty, intermediate consequent risk and uncertainty, and consequent risk and uncertainty. The risks and uncertainties in this layer are related to both uncontrollable condition called uncertainty condition such as political and economical issue, and controllable condition called risk condition such as mobilization of resource that is relevant to managerial issue.
In the effect event layer, it becomes more specific on a project, a work item, or an activity. The influential risk/uncertainty such as site accessibility, subcontractor availability, equipment availability, labor availability, work quantity and work progress are considered as the risk and uncertain condition directly influencing project, work item and activity. For the outcome layer, it presents the type and characteristic of effect such as date delay of an activity.
83
Executing Agency
Source
of risk/uncertainty
Source
Occurrence
Influential
risk/uncertainty
Effect event
Outcome
4.6 Summary
In this chapter, the development of risk/uncertainty map and framework of HSRU are explained. First, risk/uncertainty maps of common risks and uncertainties from three infrastructure projects financed by international lenders. The risk/uncertainty map together with RUBS and risk/uncertainty checklist can be used as a tool for assisting practitioners in identifying and structuring risks and uncertainties in future project. Significantly, by accumulating the experience and lessons from past projects and updating the structure, the risk/uncertainty map is considered as knowledge base used for better dealing with risks and uncertainties for both experienced and inexperienced practitioners. Second, by attempting to enhance the precision of RMP outputs, this research develops HSRU as structuring framework to be used as the basis in logically assessing probability and impact. With this framework, the cause and effect events are obviously separated. The HSRU framework is structured based on hierarchical flow of source, consequence, occurrence, and outcome.
84
Chapter 5
5.1 Introduction
Even though several risk management processes (RMPs) have been proposed to deal with risks occurring in construction projects more systematically and efficiently, there are at least two types of limitation: fundamental limitation and technical limitation of the RMP in practice. These limitations could falsify consequent output of the conventional RMPs and make RMP inefficient. Outputs of the RMP are expected impact and variance of impact associated with each risk response. Since these outputs are usually dimensionless values, they do not directly represent how goals of the project, for example, time and cost, are achieved associated with each response.
The objective of this chapter is to challenges the interpretation difficulty of dimensionless output as a fundamental limitation by developing a duration valuation process (DVP) as a measure to produce output which is easily to be interpreted. Then, the DVP is demonstrated by utilizing application results of the MRMP.
Subjective assessment of probability of occurrence and impact of event is unavoidable in risk and particularly uncertainty management study. Impact of a risk event to a specific project goal is generally assessed large, medium, or small. Thus, variance of impact and expected impact, the two main outputs of the conventional RMPs as well as the MRMP, are inevitably represented in dimensionless values. In order to easily interpret results of the RMP or MRMP, therefore, it is desirable to further transform these dimensionless values to those with dimension such as time and present them in terms of the cumulative distribution function (CDF) of project duration. This is the motivation for developing the DVP. Most of description of this chapter is referred to (Pipattanapiwong and Watanabe 2003c).
85
Various methods can be used for risk evaluation in the construction project. In general, they can be categorized as classical models i.e., probabilistic analysis and conceptual model i.e., fuzzy set analysis (Kangari and Riggs 1989). The recent models, which attempt to challenge the risk analysis study in variety of way, are shortly described as followings.
Hull (1990) described risk analysis models called Netbuild for time and Estbuild for cost developed by the Accountancy Estimating and Pricing Service (AEPS) of the Ministry of Defense Procurement Executive in UK. It is developed based on stochastic simulation network model with probabilistic node logic. Ranasinghe (1992) suggested an alternative analytical approach to simulation for quantifying risks in project time and economic variables built on the PNET algorithm and on the concept of a transitional correlation. The analytical approach was validated by using Monte Carlo simulation. The validation results demonstrated that the cumulative distribution functions for project time and economic variables generated by the analytical approach compare very favorably with those generated by Monte Carlo simulation.
Ogunlana, Chareonngam, and Tabucanon (1995) described a risk analysis model in proposed planning strategy for high-risk projects. It is based on the Analytical Hierarchy Process (AHP), because the project risks at the work package level are analyzed by incorporation of the subjective evaluation and the nature of risk factors is normally
86
subjective. Dawood (1998) proposed a methodology relied on risk management approach by considering the variations of activity duration and the dependence between activities and risk factors. Ben-Haim (1998) presented a new concept for improving the reliability of a project schedule influenced by uncertainty in the duration of its activities. The results showed that the technique applying the new concept requires minimal information, incorporates subjective information, is simple to use, and assists in the preparation of project schedules at a desirable level of reliability.
Chan and Kumaraswamy (1999) derived the model for predicting construction of housing project by applying multiple linear regression analysis of historical project data of a series of housing construction activity in Hong Kong. Mulholland and Christian (1999) discussed the development of a computer-based system for risk assessment in construction schedule, by adopting a HyperCard risk factor identification module and available statistical techniques in Excel spreadsheet. Wang and Demsetz (2000a and b) presented the simulation-based model called NETCOR focusing on the issue of correlation to evaluate schedule networks and demonstrated its application. By employing Monte Carlo simulation, Vuong and Watanabe (2001) developed risk analysis models used for quantifying uncertainty in project duration called T-RAM and cost called C-RAM and applied in Vietnamese construction projects. Isidore, Back, and Fry (2001) has pinpointed the importance of cost and schedule integration, then developed technique concerning the integration of r ange estimate and probabilistic scheduling by using a new procedure called the empirical cumulative density function (ECDF) technique in controlling the risks associated with projects.
Most of previous discussed risk analysis models adopted the probabilistic method and relied on the historical data used in simulation process (Dawood 1998, Mulholland and Christian 1999, Hull 1990, and Vuong and Watanabe 2001). However, in real construction projects, the historical data used for risk analysis is usually fragmented or even unavailable. Moreover, although many recent models attempt to study both schedule and cost risk analysis in a variety of ways, these models did not explicitly quantify the impact of risk to activity duration. One of the reasons is that the dependency between risks/uncertainties and activities was not clearly identified.
87
In most of previous models, the activity duration is estimated directly and independently from risks and uncertainties. By concerning the issues of quantification of probability and impact, a further development of conventional risk analysis is desirable. The DVP incorporates these issues in its development. The overview of DVP and its demonstration by using result of the MRMP application are described in the following sections.
The DVP relies on the basic set and probability theory in subjectively elicitation of probability. To transform the impact of risk and calculate the delay of an activity, it is based on the productivity rate of work generally used in activity duration estimation and delay mechanism of particular activity caused by specific risk/uncertainty. Monte Carlo simulation in spreadsheet based on the CPM scheduling technique is employed in conducting simulation of project duration. This is a favorite tool used for presentation of risk and uncertainty such in the form of cumulative distribution. The DVP consists of four main processes as shown in Figure 5.1.
88
Risk/ uncertainty Development of hierarchical structure of risk and uncertainty (HSRU) HSRU of project Assessment and transformation of probability of risk/uncertainty
Probability
A network is a diagram showing interconnected activities together with their relationships. It is used to determine the project duration, to learn about the project, to perform what if analyses, and to analyze and settle issues such as claim matter (Griffis 2000). According to Grey (1995), network is used to find the critical or longest possible path from start to finish in conventional schedule planning. In schedule risk analysis, by examining it in the same way, it also allow for analysis of risk/uncertainty in the definition of the network, its durations and its logical structure.
89
Considering this benefit, in examining schedule risk analysis, the DVP relies its basis on the concept of the WBS and scheduling network based on CPM method. After the scheduling network of project is developed in the form of precedence network diagram, which is favorite type of network in recent project management software, it is then modeled in the spreadsheet software such as Excel in order to be used in simulation process later on. The schedule risk model developed in spreadsheet is modeled by concerning the flexibility in changing activity duration, relationship, start and finish date as well as any suspended period, which is based on the mechanism of delay caused by specific risk/uncertainty event. The mechanism of delay is explained in later section.
90
HSRU
Activity Project
Site Clearing
Influential
Risk/Uncertainty
Piling
91
changing nature of critical path; and the effects of action taken to minimize potential delays. Bubshait and Cunningham (1998) studied and compared three delay measurement processes i.e., as-planned method, as-built method, and modified as-built method. It is suggested that the use of delay analysis methodologies is based on the availability of project control data and one method may not be used universally over another in all situation. Shi, Cheung, and Arditi (2001) also proposed the method, which consists of a set of equations, by contrasting the as-planned and as-built schedules. A purpose of these delay computation methods is to provide the information for determining responsibilities of delays, which can be used in claim settlement. However, a shortcoming of these methods is that they did not incorporate risk in computation. Bordoli and Baldwin (1998) categorized delay to construction work into six types including date delay, total delay, extended delay, progress delay, additional delay, and sequence delay. Table 5.1 shows the description, example of event and simulation method of each type of delay. Based on the types of delay categorized by Bordoli and Baldwin (1998), the DVP determines the mechanism of delay in network associated with each type of delay. This mechanism is used to calculate the duration of delay (T ) to be added up to base activity duration and any change due to additional and sequence delay. The Figure 5.3 summarizes mechanism of delay. For the DVP, four types of delay i.e., 1) date delay, 2) total delay, 3) extended delay, and 4) progress delay are focused during specifying dependency between risks/uncertainties with activity and identifying characteristic of activity delay. Next sections provide brief description of each process in the DVP, respectively.
92
B) Total delay
C) Extended delay
Adjustment to the calendar for the relevant activities Additional holidays representing the affected periods Increase in the duration of the relevant activity
D) Progress delay
E) Additional delay
F) Sequence delay
Adding activities to the network complete with logic links to existing activities Alterations to the logic links in the network to reflect the new sequence
93
Type of delay Base-line network A) Date delay A1) Start date delay A2) Finish date delay
Activity A
TB
Activity B
Activity B
Activity C
Activity A
TB
Activity C
B) Total delay
Activity A
Activity B1
TB TB
Activity B2
Activity C
C) Extended delay
Activity A
Activity B
Activity C
D) Progress delay
Activity A
Activity B
T B
Activity C
E) Additional delay
Activity A
Activity B
Activity X
Activity C
Activity A
Activity B
Activity C
Activity X
F) Sequence delay
Activity A
Activity B
Activity C
Activity B
94
Within this development process of the HSRU, two steps are undertaken. The first one is to identify risks/uncertainties based on the risk/uncertainty checklist categorized in accordance to risk/uncertainty breakdown structure (RUBS). The RUBS and the risk/uncertainty checklist have been developed from previous literatures and experiences from some past projects financed by an international lender. The mutually exclusive and collectively exhaustive issues amongst risks/uncertainties have been taken into consideration in the preparation of both the RUBS and risk/uncertainty checklist. Structuring risks/uncertainties is the successive step. The main idea is to find the consequential relationship amongst risks/uncertainties and represent in hierarchical flow from source of risk/uncertainty, consequent risk/uncertainty, influential risk/uncertainty, and types of delay. The developed HSRU is an important deliverable, which will be used in the successive processes.
To assess conditional probability, we do rely on the dependency among risks/uncertainties structured in HSRU.
95
Risk/ uncertainty A
Risk/ uncertainty B
Figure 5.4: (a) Sample of hierarchical structure of risk and uncertainty and (b) based on the Venn diagram of the HS RU in (a) the shaded area shows Pr(C (A B) Based on the sample HSRU and its Venn diagram presented in Figure 5.4, the probability of consequent uncertainty C could be derived as shown in Eq. 5.1.
Pr( C ( A B )) = Pr(C | ( A B)) Pr( A B )
(Eq. 5.1)
The assessment scale of probability is generally expressed in linguistic terms. One of expressions is extremely unlikely, very unlikely, unlikely, fairly likely, likely, highly likely as shown in Table 5.2 (ICE 1998). These defined linguistic terms represent the decision- makers perception of likelihood of occurrence, which will be transformed to the range from 0 to 1.
More than evens chance 50-85% Quite often occurs Small likelihood but could well happen Not expected to happen Just possible but very surprising 21-49% 1-20% Less than 1% Less than 0.01%
96
Likely
Fairly likely
Unlikely
Very unlikely
Extremely unlikely
A
Source of risk/ uncertainty
B
Financial support from bank 1. What is probability that given either economic condition or financial support from bank occur, contractors financial condition will occur? Extremely unlikely Highly likely
Economic condition
Consequent risk/uncertainty
Pr(C | ( A B )) =
Material
Influential risk/uncertainty
Availability
2. What is probability that either economic condition or financial support from bank occur? Extremely unlikely Highly likely
Pr( A B ) =
97
Since different assessor may have different perception towards the wording expression of probability scale, the probability scale then is previously calibrated before assessment. Example of calibrating scale of probability assessment is shown in Figure 5.5. After we calibrate the scale of probability assessment, the probability is elicited based on questions designed based on conditional probability and multiplication rule in probability theory. Figure 5.6 shows an example of questions in probability assessment.
d=
w p
d = d + d
In order to comprehensively assess and calculate the activity delay, it is desirable to clarify the type of delay. Because the impacted variables i.e., activity duration, work quantity, and production rate, vary according to types of delay. To quantify the delay, the decision- maker will assess the percent variation i.e., for activity duration, for work quantity, and for production rate of each variable as shown in Eq. 5.4 Eq. 5.6, respectively.
98
d = (1 + )d d
d = d =
(1 + ) w w p p w w (1 ) p p
Based on the type of delay categorized by Bordoli and Baldwin (1998), the DVP adopts four types of delay including date delay, total delay, extended delay, and progress delay. The description, impacted variables, and assessed percent variation of each type of delay are summarized in Table 5.3.
Table 5.3: Type of delay, impacted variable and percent variation Type of Delay Date delay Total delay Extended delay Progress delay Description Start and/or finish of activity is delayed. Activity is stopped or suspended. Work quantity is increased. Production rate is decreased. Impacted Variable Original duration (d ) Original duration (d ) Work quantity ( w ) Production rate ( p ) Percent Variation
Similar to probability assessment, the assessment scale of impact is also described in linguistic explanation. One of expressions is described as negligible, marginal, substantial, severe, disastrous. The decision- makers can assess the impact of uncertainty by determining the percent variation of each variable based on this scale. Figure 5.7 shows the impact assessment procedure. Additionally, the DVP employs three-point estimate i.e., optimistic, most likely, and pessimistic similar to PERT in defining triangular distribution of activity duration. However, in the DVP, these three points of duration are not directly assesses like in the PERT. Here, the optimistic duration is the original activity duration. The most likely duration is the expected impacted activity duration. Finally, the pessimistic duration is the original duration plus the delay.
99
Works stop?
Works increase?
Date delay
Total delay
Extended delay
Progress delay
Step 3: Assessing impact of uncertainty based on type of delay, What is the impact (variation of original duration, work quantity, and production rate) of influential uncertainty to activity?
Negligible 0-2% Duration: Work Quantity: Production Rate: Marginal 3-10% Substantial 11-30% Severe 31-50% Disastrous >50%
+L+ d D = d1 + d 2 n = di
i S
(Eq. 5.7)
100
Where D is the probabilistic project duration. d i is the probabilistic activity duration of the activities in critical path. S is the set of critical activity depending on realization of random variable. This simulation model is modeled in spreadsheet software. Simulation software is used in simulating the project duration.
101
Flyover Flyover Bridge-2 Bridge-2 1.04.00 1.04.00 Piling-2 1.04.01 S Pier-1 1.04.03 Piling-3 1.04.02 Pier-2 1.04.04 Girder-1 1.04.06 Ramp-1 1.04.09 Pier-3 1.04.05 Girder-2 1.04.07 Ramp-2 1.04.10 Finishing 1.04.11 Girder-3 1.04.08 F
Economic condition
Source of risk/uncertainty
Suppliers financial condition Subcontr. & supplier Financial condition Piling-2 Total delay Piling-3 Progress delay
Consequent risk/uncertainty
Material Availability
Influential risk/uncertainty
Figure 5.9: Hierarchical structure of risk and uncertainty, risk/uncertainty-activity relationship, and type of delay
scale respectively. The case studied project used in the MRMP was actually delayed approximately 50% of original contract duration. Thus, for impact assessment, the percent variation scale is defined as 10%, 20%, 30%, 40%, and 50% for very low to very high in assessment scale respectively. Table 5.4 summarizes the assessed and transformed probability and impact as well as three-point estimate of duration.
18.3 (30%) : Very high Piling-3 167.5 (50%) : Very high : Medium Girder-1 206.4 (50%) (30%) : Very high Girder-3 106 (50%) U1 = Contractor's financial condition (probability = very low (0.1)) U2 = Supplier's financial condition (probability = medium (0.5)) U3 = Technical capability (probability = medium (0.5))
Delay (5) = (Percent variation (2, 3, 4) * Original duration (7)) Expected impacted duration (8) = Original duration (7) +[Probability (6) * Delay (5)] Impacted duration (9) = Original duration (7) + Delay (5)
Based on the deterministic scheduling, the duration of flyover bridge-2 work item is 669 days. On the other hand, from the result of the simulation (2,000 iterations) that taking the risks/uncertainties into consideration, it was found that the expected duration is about 805 days. The minimum duration is about 703 days. The maximum duration is about 951 days. Moreover, for example, there is 80% probability that this work item will complete not later than 844 days.
103
Probability Distribution
.023 1.000
Probability
.017 .011 .006 Mean = 804.58 .000 702.26 758.19 814.13 870.07
926.01
700.00
756.25
812.50
868.75
925.00
Figure 5.10: Probability and cumulative distributions of duration of flyover bridge-2 work item
5.9 Summary
This chapter aims to challenge a limitation regarding difficulty in interpretation of the RMP output due to its presentation in dimensionless values. The DVP has been developed. Overview of processes in the DVP is described in this chapter. Then, it is demonstrated by using results of the MRMP application and post-evaluation. From the result of demonstration, as an example, the hierarchical structure of risk and uncertainty, influential relationship between risks/uncertainties and activity, type of delay, and probability and cumulative distributions of work item duration could be obtained. By using the DVP in this case study, the dimensionless value of RMP outputs could be transformed to dimensional value in term of duration and presented in cumulative distribution. With this information, the DVP could be regarded as a decision making tool for producing useful information used in managing the project risk/uncertainty.
104
Chapter 6
105
INPUT
PROCESS
OUTPUT
Purpose of application Involved parties Roles in application Focused project objective and scope Application assumption Application plan
Outputs from the 1st process Project information & documents Assessors perception
Identified risks/ uncertainties Hierarchical structure of risk and uncertainty (HSRU) Integrated HSRU
Outputs from the 2 process Schedule, cost & productivity information Assessors perception
nd
Probability & impact of risks and uncertainties Probability and cumulative distribution of project duration Risk/uncertainty impact chart (RUIC) Response scenarios and diagrams Probability and cumulative distribution of project duration of each scenario Expected impactstandard deviation map
Outputs from the 3rd process Lesson learnt from other cases Assessors perception
uncertainty Updated risk/uncertainty Updated HSRU Reassessed probability and impact Updated response scenarios and diagrams Updated application plan
106
1. risk/uncertainty management planning: is to set and define framework of application, 2. risk/uncertainty identification and structuring: is to identify and structure risks and uncertainties influencing project objectives, 3. risk/uncertainty assessment and analysis: is to assess and analyze identified risks and uncertainties based on developed HSRU, 4. risk/uncertainty response process: is to provide proactive and reactive response scenario s to risks/uncertainties, and 5. risk/uncertainty management control: is to administer, monitor, update and control risk and uncertainty management application.
The MRUMP is described based on the flow of input-process-output. The rectangular shape represents process and procedure. The rounded rectangular shapes represent inputs and outputs of process. Figure 6.1 provides overview of processes included in MRUMP. The following sections describe application framework, and step-by-step procedures together with tools and techniques of each process, respectively.
In the framework of application, the issues regarding timing of application based on the traditional contracting practice, purpose of application, and available information are considered important because application of MRUMP is directly related these mentioned issues. In different stages of project, the availability and detail of information
107
is different. When the project further proceeds from planning, bidding, contract forming to construction stage, we are able to know more information such as in case of schedule and productivity information. Figure 6.2 describes the purpose of application and available information in practice in each stage of traditional contracting.
Based on application framework, project stage is divided into three main stages including 1) pre-construction stage (from planning to contract signing), 2) early stage of construction (from contract signing to beginning period of project commencement) and 3) during construction.
Since each party (i.e., owner, consultant, and contractor) has different objectives in each stage of project, the purpose of application is then depended on position of involved parties. During pre-construction stage, owner and consultant, owner and consultant may use the MRUMP to assist in determining reasonable project objectives (project duration and cost) and in drafting contract clauses. In this stage, usually only experience of past similar project and rough estimation information is available.
During the bidding, the bidders may use the MRUMP in assisting them to make bid/no bid decision and determine the contingency amount in bid proposal for risk and uncertainty. Based on the bid documents that normally contain description of work, determined project duration, specified contract clauses and bill of quantity (BOQ) items, with their experience and available in- house schedule and cost information, they usually have more detail information than owner and consultant in doing analysis in this stage.
When project proceeds to construction stage, at the beginning of project normally the contractor has to submit the work program (schedule) to owner and consultant for approval. Then, it will be used as base- line schedule for project monitoring and control during construction. This schedule and productivity information is considered important in conducting analysis in both early and during construction stages. For the purpose of application during construction, at the early stage of construction, all parties may use the MRUMP to proactively prepare the measures for schedule deviation and cost overrun. The n, if it is necessary, project schedule and cost may be revised in order to be
108
responsive for future prospective risks and uncertainties. In case if the project is suffering from delay, the MRUMP may be used in assisting in determining time extension and additional cost in both early and during construction stage as reactive action.
Furthermore, the timing of application is very important when we assess and transform the impact of risks/uncertainties. Because in transforming process we have to rely on the available information (schedule and productivity information) that is directly depended on timing of application. In planning stage, normally, the detail schedule and productivity information is not available. In this case, we are able to assess the impact of risks/uncertainties influencing work items only in upper level of work breakdown structure (WBS). We may not be able to assess impact of risks/uncertainties in very detail. For example, we may be able to assess the impact to duration of an activity in unit of month or year rather than in day or week. In construction stage, when we have more schedule and productivity information, we are able to assess the impact of risks/uncertainties to duration, work quantity or production rate of activity in lower level of WBS.
109
1. Need of application The need of application is the first important input to entire process. Unless the need of application is clearly defined, we may not be able to set the framework of application. The need of application is related to purpose of application and is expressed as what that party(s) would like to obtain from the MRUMP application.
2. Project information and status To understand available project information and current project status enable in setting scope and assumption of application. Project information means available information at the time of assessment such as schedule and productivity information in construction stage.
6.4.2 Procedure, Tool and Technique of Risk and Uncertainty Management Planning Process
The procedural steps in this process are explained as follows.
1. Defining purpose of application To define the purpose of application, we have to understand the need of application. In assisting this task, MRUMP provides predefined purpose of application along the project stage in traditional contract as shown in Figure 6.2. It is desirable to identify the need of application collectively in multi-party environment.
2. Assigning role in application and decision-making Generally, in decision making process, three main roles are probably existed i.e., (1) experts or assessors, (2) evaluation analyst, and (3) decision makers (Schuyler 1996). Experts or assessors are ones who provide the judgments that is main input in the evaluation. The most knowledgeable people in the context we are considering should be seen as experts or assessors. Evaluation analysts are ones who have responsibility in developing analysis models that generate scenario outcomes and forecasts for each alternative. Decision makers roles are to review the forecasts and judge the credibility of analysis. Then, they select the alternative and implement it. This is usually made by
110
accepting teams recommendation. This explains the common and general responsibility of three main roles in decision making.
4. Defining focused project objective and scope Project objectives are expressed in terms of project schedule and cost. Scope of application may cover entire project scope, particular work items, or particular activity in WBS of project. To define the project objective and scope, it depends on the purpose of application, available information at time of assessment and precision of result desired by practitioners. The framework of application shown in Figure 6.2 can be used as guideline in defining the focused project objective and scope.
5. Setting assumption of application After purpose of application, involved parties, role in decision- making, focused project objectives and scopes are defined, the next step is to set the assumption of application regarding time frame of assessment and timing of assessment. Time frame of assessment means time projection period for assessment of probability and impact of risk and uncertainty. Timing of assessment means the point of time, when assessors are assumed to assess the probability and impact of risk and uncertainty.
6. Educating overview procedure of MRUMP It is desirable for assessor, analyst and decision- maker to understand the contents of MRUMP process in order to be able to follow the procedure throughout the application. Group seminar and presentation may be used in educating all involved participants regarding the concept and procedure of MRUMP. It is preferable to educate participants all of procedures described in each process. However, it is not mandatory and sometimes difficult due to limitation of participants background, knowledge and time. It also depends on the role and interest of particular practitioner. At least the overview of MRUMP (as shown in Figure 6.1) and summary tables of all processes should be provided.
111
Early construction
Purpose To owner & consultant: 1. Determining project objectives i.e., project duration and cost 2, Drafting contract clauses
Purpose To bidders: 1. Making bid/ no bid decision 2. Preparing bid proposal (schedule and price) To owner & consultant: 1. Evaluating bid proposal
Purpose To all: 1. Proactively preparing for schedule deviation and additional cost e.g. revising schedule and cost Available information To all: 1. Contract clauses 2. Schedule information 3. Productivity information
Purpose
To all: 1. Reactively preparing for delay and cost overrun e.g., settling time extension and additional cost
Available information To owner & consultant: 1. Experience of past project 2. Estimation information
Available information To all: 1. Bid documents 2. Estimation information 3. Proposed schedule 4. BOQ items
1. Predefined framework of application As shown in Figure 6.2, it explains the purpose of application of MRUMP together with common available information in each stage of project (based on traditional contracting) associated with each project party such as owner, consultant and contractor. This predefined framework of application is used for facilitating assessors, analyst, and decision- makers in defining purpose of application, focused project objectives and scope.
2. Overview MRUMP process diagram This diagram aims to provide overview of input-process-output flow of each process in MRUMP. As shown in the diagram in Figure 6.1, even though each process is connected in process by process basis, the practitioners are encouraged to perform follow up and feed back loop when finishing each process. This is to confirm the reliability of
112
assessment. Moreove r, it is encouraged to use this diagram in educating all involved participants of MRUMP.
1. Purpose of application For example, the MRUMP may be used by owner and consultant for determining project objectives (time and budget) in the very early of project as well as drafting contract condition in pre-bidding stage. Bidders may use it for determining contingency in their bid proposal. These are examples of purpose of application based on individual perspective. In contract formation, it may be used as negotiation tool by all parities. During construction stage, it may be used as problem preventing tool at the early stage of construction and problem solving tool when problems happening during construction.
2. Involved parties It depends on the purpose of application and stage of project in defining involved parties. As explained in previous section, during the early stage of project, normally only owner is the main party to perform tasks with assistance of consultant. When project progresses to bidding stage, another party, the bidders, participates in bidding. In contract formation stage, this is considered the starting point of multi-party environment that involved parties should consist of owner, consultant and contractor.
3. Assessors, analyst, and decision-maker It depends on the purpose of application and project scope in determining assessors, analyst and decision- maker. For example, if we are going to quantify project delay at the early stage of construction project, assessors may be top management level of all parties. In case of analyst, the consultant may be an appropriate positio n in performing this task. Otherwise, external party may be employed. For decision maker, it depends on which response scenario will be implemented.
113
4. Focused project objective and scope If we would like to estimate time extension of project due to expected delay of some activities during construction stage, the focused project objective is project time (schedule) and expected activities are considered as scope.
5. Assumption of application The time frame of assessment is defined according to purpose of application and scope. For example, at the early stage of construction, if we would like to quantify impact of risk and uncertainty causing project delay during construction. The assessment time frame in this application is set as during construction of project.
6. Application plan The final output of risk and uncertainty management planning process is an application plan aiming to summarize detail of all outputs such as purpose of application, involved parties, roles in application, focused project objective and scope, and assumption of application in form of documentation. This is to enable all parties involved to have the same understanding towards framework of application.
The inputs, procedure, tool and techniques and outputs are summarized in Table 6.1.
114
Table 6.1: Summary of inputs, process, outputs of risk and uncertainty management planning process
INPUT 1. Need of application 2. Project information and status PROCEDURE 1. Defining purpose of application 2. Assigning role in application and decision-making 3. Defining focused project and scope 4. Setting assumption of application 5. Educating overview procedure of MRUMP Examples Type, contract duration and cost, contract start and finish date An As DM Tool & Technique P 1. Predefined framework of application P 1. Meeting 1. Predefined framework of application A P P, R 1. Predefined framework of application P 1. Group seminar 2. Presentation 3. Overview of MRUMP Example Preparing preventive plan for schedule delay Owner, consultant, contractor Consulting engineer, site engineer, project manager Duration of project, duration of activity, cost of project, cost of activity During construction period A P P, R
OUTPUT 1. Purpose of application 2. Involved parties 3. Analyst, assessors, and decision-maker 4. Focused project objective(s) and scope
5. Assumption of application 6. Application plan Remark: An is analyst, As is assessor, DM is decision-maker P: Prime responsibility, A: Assisting, R: Reviewing
Significantly, this process attempts to challenge the unidentifiable condition of uncertainty by trying to change unknown known and unknown unknown to known
115
known and known unknown respectively. It is not completely impossible to identify unidentifiable uncertainty, when the proper and sufficient study is conducted with assistance of logical and systematic tool. With this elaborate study, the unidentifiable uncertainty due to negligence, lack of experience, and inadequate knowledge is possibly identified and realized. The success of this effort probably induces high possibility in great reduction of uncertainty, if practitioners provide enough care and attention by further analysis and management after realization of what threat may occur.
The grounded concept of this risk and uncertainty identification and structuring process is based on the hierarchical structure of risk and uncertainty (HSRU) framework explained in Chapter 4 and the first process (development of hierarchical structure of risk and uncertainty) of duration valuation process (DVP) explained in Chapter 5. Therefore, the implementing procedures are mainly focused in this chapter.
1. Project information and documents As shown in framework of application (Figure 6.2), the available information is different in different stage of project. Example s of project information are type of project, contract duration, contract cost, contract starting and finishing date, current project progress and status. Much of this information is available in contract documents e.g., contract, contract condition and supplementary, specification, addendum, bill of quantity (BOQ), submitted schedule, and drawing. Status of project is tracked from project progress report, meeting minutes, schedule information (e.g. work breakdown structure (WBS) base line construction schedule, and actual schedule).
2. Assessors perception In this step, the assessors perception is the recognition regarding the possible
116
occurrence of risks and uncertainties and their hierarchical structure in specified time frame as defined in assumption of application.
6.5.2 Procedure, Tool and Technique of Risk and Uncertainty Identification and Structuring Process
The procedure in risk and uncertainty identification and structuring process include:
1. Studying and reviewing project information and status 2. Identifying risks and uncertainties 3. Constructing hierarchical structure of risks and uncertainties 4. Reviewing identified risks and uncertainties and their hierarchical structures
The tools and techniques, which are used in assisting and facilitating analyst, assessor and decision- maker in this process, consist of:
1. Risk and uncertainty breakdown structure 2. Risk and uncertainty checklist 3. Hierarchical structure of risk and uncertainty 4. Documents review and site observation 5. Interview
1. Identified risks and uncertainties 2. Description of risks and uncertainties 3. Hierarchical structure of risks and uncertainties 4. Integrated HSRU
117
Table 6.2 summarizes inputs, process, outputs of risk and uncertainty identification and structuring process Table 6.2: Summary of inputs, process, outputs of risk and uncertainty identification and structuring process
INPUT 1. Outputs from the 1st process 2. Project information and documents 3. Assessors perception PROCEDURE 1. Studying and reviewing project information and status 2. Identifying risks and uncertainties Example See Table 6.1 Contract duration, contract cost, contract documents Recognition of occurrence of risks and uncertainties An As DM Tool & Technique A, P P, R P, R 1. Document review and site observation 2. Interview A P P, R 1. Risk and uncertainty breakdown structure 2. Risk and uncertainty checklist 3. Interview A P P, R 1. Hierarchical structure of risk and uncertainty 2. Interview A P P, R Example Land acquisition risk and uncertainty, mobilization of subcontractor risk and uncertainty Late land hand over, late mobilization of subcontractor
3. Constructing hierarchical structure of risks and uncertainties 4. Reviewing identified risks and uncertainties and their hierarchical structures OUTPUT 1. Identified risks and uncertainties
2. Description of risks and uncertainties 3. Hierarchical structure of risks and uncertainties 4. Integrated HSRU Remark: An is analyst, As is assessor, DM is decision-maker P: Prime responsibility, A: Assisting, R: Reviewing
The previous process tries to challenge the unidentifiable condition of uncertainty. We obtain identified risks and uncertainties, which are known known and known unknown respectively. In this process, we attempt to challenge the unquantifiable condition of likelihood of occurrence of uncertainty due to lack of knowledge and
118
information (in case of known unknown) or inapplicability of available information (in case of known known). Therefore, based on developed logical and systematic procedure in assessing probability and impact, this process tries to transform them to known known condition and event.
Additionally, with the reasons of unavailability of historical data and inapplicability of available historical data, the subjective judgment is inevitable in assessing probability and impact of risk and uncertainty. This process also relies on assessors subjective judgment in quantifying probability and impact of risk and uncertainty.
Much of explanation regarding conceptual background of this process is already provided in description of probability and impact assessment processes in DVP available in Chapter 5.
1. Outputs from the second process 2. Schedule, cost & productivity information 3. Assessors perception
6.6.2 Procedure, Tool and Technique of Risk and Uncertainty Assessment and Analysis Process
Procedures in risk and uncertainty assessment and analysis process are described step-by-step as followings.
1. Educating probability and impact assessment procedure 2. Calibrating probability and impact assessment scale 3. Assessing probability of risk and uncertainty based on developed HSRU, 4. Assessing impact of risk and uncertainty based on developed HSRU and type of
119
delay 5. Transforming assessed probability and impact to dimensional value 6. Building analysis model 7. Conducting simulation 8. Preparing presentation of analysis result
1. Hierarchical structure of risk and uncertainty framework 2. Work breakdown structure and CPM method 2. Monte Carlo simulation 2. Structured Interview
1. Probability and impact of risks and uncertainties 2. Probability and cumulative distribution of project duration 3. Risk/uncertainty impact chart
Table 6.3 summarizes inputs, process, outputs of risk and uncertainty assessment and analysis process
120
Table 6.3: Summary of inputs, process, outputs of risk and uncertainty assessment and analysis process
INPUT 1. Outputs from the second process 2. Schedule, cost & productivity information 3. Assessors perception Example Base-line schedule, CPM, production rate Perception on likelihood of occurrence such as likely to occur or unlikely to occur, perception on impact such as disastrous or negligible An As DM Tool & Technique P 1. Presentation A A A P P P P P A, R A, R P, R P, R P, R R R R R 1. CPM method 2. Spreadsheet software 1. Monte Carlo simulation Example 1. Example of scale 1. Structured interview 2. Example of scale 1. Structured interview 2. Example of scale
PROCEDURE 1. Educating probability and impact assessment procedure 2. Calibrating probability and impact assessment scale 3. Assessing probability of risks and uncertainties based on developed HSRU 4. Assessing impact of risks and uncertainties based on developed HSRU and type of delay 5. Transforming assessed probability and impact to dimensional values 6. Building analysis model
7. Conducting simulation P A, R 8. Preparing presentation of analysis result P R OUTPUT 1. Probability and impact of risks and uncertainties 2. Probability and cumulative d istribution of project duration 4. Risk/Uncertainty Impact Chart Remark: An is analyst, As is assessor, DM is decision-maker P: Prime responsibility, A: Assisting, R: Reviewing
121
Alternative responses
Proactive response
Related contract clauses Assess impact Identify consequential uncertainty and consequential impact Consequential uncertainty and impact IIU, ICU, and ICI
Scenario analysis Terms scenario is defined by Schuyler (1996) as a possible sequence of events and a future state of the world. In his definition of scenario analysis, he explained scenario analysis as a planning technique focusing on plausible alternative futures and management responses. With contrary to Schuyler, the adopted scenario analysis in this research will take the benefit of not only to develop insight about future threat to project but also to forecast how much extent project is likely to be affected.
122
Moreover, the MRUMP incorporates probabilistic analysis with scenario analysis. In developing alternative scenario, influential risk/uncertainty, future consequential risk/uncertainty, and consequential impact associated with i mplementation of each alternative response are identified. Then, each identified risk/uncertainty is analyzed based on developed response scenario.
Type and category of response There are three types of response i.e., proactive, accept, and reactive responses defined based on timing of implementation. This is whether it will be implemented before (as proactive measure) or after (as accept and reactive measure) occurrence of uncertainty. By considering the category of response, there are four categories including avoidance, mitigation, transfer, and retention. To define category of response is directly depended on who is the decision maker.
Contractual issue The contractual issue is also put in consideration when analysis of response. We can define the how to draft contract clause as decision variable during planning stage will be made by owner. Otherwise, after the contract is formed, the contract clause is defined as nominal variable. This is directly related to timing of application of DVP in project and who is the decision- maker. Associated with each response scenario, related contract clauses will be identified.
1. Outputs from the third process 2. Experience and lesson learnt from other projects 3. Assessors perception
123
6.7.2 Procedure, Tool and Technique of Risk and Uncertainty Response Process
The procedures in risk and uncertainty response process are explained as following.
1. Initiating response scenarios 2. Constructing response scenario diagram 3. Assessing probability and impact of risks and uncertainties in each response scenario
Probability assessment in case of proactive response scenario In this section, to reduce excessive wordings, uncertainty means risk/uncertainty. In case of proactive response scenario, two probabilities are quantified. First one is the new probability of major uncertainty. Second one is the probability of consequential uncertainty. The probability of these uncertainties is assessed given the condition that particular proactive response is implemented. For the new probability of major uncertainty, before the response is implemented, the conditional probability of major uncertainty (U) given occurrence of sources of uncertainty (SU) and probability of union between two sources of uncertainty are Pr(U/(SU1 SU2 )) and Pr(SU1 SU2 ), respectively. After assuming that response is taken, the conditional probability and probability of union are transformed to Pr(U/(SU1 SU2 )) and Pr(SU1 SU2 ), respectively. Based on multiplication rule in probability theory, new probability of major uncertainty (Pr(U(SU1 SU2 ))) is calculated by multiplying Pr(U/(SU1 SU2 )) with Pr(SU1 SU2 ). After new probability of major uncertainty i.e., Pr(U (SU1 SU2 )) is obtained, we then assess conditional probability of consequential uncertainty given the occurrence of major probability i.e., Pr(CU/(U (SU1 SU2 )). Finally, based on multiplication rule in probability theory, probability of consequential uncertainty (Pr(CU (U(SU1 SU2 )))) is calculated by multiplying Pr(CU/(U (SU1 SU2 )) with Pr(U (SU1 SU2 )).
124
Probability assessment in case of accept and reactive response scenarios With previously stated assumption, accept and reactive response is implemented after the occurrence of major uncertainty. After reactive response is implemented, the major uncertainty may be completely eliminated. Otherwise, it may reoccur with new probability of occurrence. With this assumption, in case when reoccurrence of major uncertainty is realized, we reassess the new probability of major uncertainty as, Pr(U).
For probability of occurring consequential uncertainty, the assessment procedure is quite similar to case of proactive response. After Pr(U) is obtained, then we assess the conditional probability Pr(CU/U). Finally, based on multiplication rule in probability theory, probability of consequential uncertainty (Pr(CUU)) is calculated by multiplying Pr(CU/U) with Pr(U). We can assess Pr(CU) directly, if the major uncertainty is assumed not to occur again.
Impact assessment Similar to the impact assessment procedure in DVP, the impact of influential uncertainty to activity (the level of activity depends on how much schedule and productivity information available) is assessed. However, in each response scenario, we assess impact of influential uncertainty based on following three uncertainties i.e., major uncertainty, new consequential uncertainty, and preparation effort in terms of time. To assess impact of each response scenario, we have to assess all these three types of impact.
Impact due to original major uncertainty is the impact that already occurred (IIU). When the reactive response is implemented, we have to reassess new impact of this major uncertainty (IIU). In case of other types of impact, we have to assess impact of consequential uncertainty (ICU) and preparation effort in implement ing response (IP ). To assess the impact, as similar to impact assessment in the DVP, we will assess the percent variation to activity duration, work quantity and production rate. However, mentioned in framework of application, in assessing the impact it depends on how much information available.
125
Table 6.4 summarizes basis of probability and impact assessment in each type of response scenario. Table 6.4: Probability and impact of major uncertainty, consequential uncertainty and consequential impact
Response Scenario Proactive response scenario Major uncertainty Consequential uncertainty Preparation effort Accept and reactive response scenario Major uncertainty Consequential uncertainty Preparation effort Pr(U) Pr(CU U) IIU ICU IP Pr(U (SU1 SU2 )) Pr(CU (U(SU1 SU2 ))) IIU ICU IP Probability Impact
4. Conducting simulation of project duration in each response scenario 5. Preparing presentation of analysis result
1. Prototype of response diagram The prototypes of proactive, accept, and reactive response scenario diagrams are shown in Figure 6.4, 6.5 and 6.6, respectively. Response scenario diagram is used as the basis in probability and impact assessment. Its function is similar to HSRU framework in the DVP. How to assess the change of probability of pre- identified source of uncertainty and major uncertainty and probability of new occurring consequential uncertainty is based on the structure of response scenario diagram and multiplication rule in probability theory. This basis is also similar to basis of probability assessment in the DVP.
2. Structured interview
126
SU 1
SU 1
IU
Activity
Type of delay
Proactive response
CU
IU
Activity
Type of delay
SU 2
Note: SU: Source of Uncertainty CU: Consequential Uncertainty P: Preparation effort U: Uncertainty
P
IU: Influential Uncertainty
IU
Activity
Type of delay
IU
Activity
Type of delay
SU 1 U SU 2 P
Note: SU: Source of Uncertainty CU: Consequential Uncertainty P: Preparation effort U: Uncertainty IU: Influential Uncertainty
Accept response
CU
IU
Activity
Type of delay
IU
Activity
Type of delay
IU
Activity
Type of delay
SU 1 U SU 2 P
Note: SU: Source of Uncertainty CU: Consequential Uncertainty P: Preparation effort U: Uncertainty IU: Influential Uncertainty
Reactive response
CU
IU
Activity
Type of delay
IU
Activity
Type of delay
127
1. Response scenarios 2. Response scenario diagram As previously mentioned, response scenario diagram is another important deliverable, which is mainly used in assessing probability and impact. Basically, it shows how condition (i.e., probability and impact) of risk and uncertainty will be changed when the response is implemented.
3. Probability and cumulative distribution of project objective of each scenario 4. Expected duration and standard deviation map
Table 6.5 summarizes inputs, process, and outputs of risk and uncertainty response process.
Table 6.5: Summary of inputs, process, outputs of risk and uncertainty response process
INPUT 1. Outputs from the third process 2. Experience and lesson learnt from other projects 3. Assessors perception PROCEDURE 1. Initiating response scenarios 2. Constructing response scenario diagrams Example
An A A
As P P
DM P, R P, R
3. Assessing probability and impact of risks and A P P, R uncertainties in each response scenario 4. Conducting simulation of project duration of P R R each response scenario 5. Preparing presentation of analysis result P R R OUTPUT 1. Response scenarios 2. Response scenario diagram 3. Probability and cumulative distribution of project duration of each response scenario 4. Expected duration and standard deviation map Remark: An is analyst, As is assessor, DM is decision-maker P: Prime responsibility, A: Assisting, R: Reviewing
Tool & Technique 1. Structured interview 2. Brainstorming 1. Prototype of response diagram 1. Structured interview 2. Example of scale 1. Monte Carlo simulation
Example
128
6.8.2 Procedure, Tool and Technique of Risk and Uncertainty Management Control Process
Followings are step-by-step procedures of risk and uncertainty management control process.
1. Monitoring and updating identified risks and uncertainties 2. Reviewing and updating HSRU 3. Reviewing assessment of probability and impact, and analysis of risks/uncertainties 4. Reviewing and updating response scenarios, assessment and analysis 5. Updating application plan
129
1. Status of identified risks and uncertainties 2. Updated risks and uncertainties 3. Reviewed HSRU 4. Reassessed probability and impact 5. Updated response scenario, diagram, and assessment 6. Updated application plan
Table 6.6 summarizes inputs, process, outputs of risk and uncertainty management control process.
Table 6.6: Summary of inputs, process, outputs of risk and uncertainty management control process
INPUT 1. Outputs from all process 2. Project status and new information PROCEDURE An As 1. Identifying and updating identified risks and A P uncertainties 2. Reviewing and updating HSRU A P 3. Reviewing assessment of probability and A P impact, and analysis of risks/uncertainties 4. Reviewing and updating response scenarios, A P and assessment and analysis 5. Updating application plan A P OUTPUT 1. Status of identified risks and uncertainties 2. Updated risks and uncertainties 3. Updated hierarchical structure of risks and uncertainties 4. Reassessed probability and impact 5. Updated response scenarios 6. Updated application plan Remark: An is analyst, As is assessor, DM is decision-maker P: Prime responsibility, A: Assisting, R: Reviewing Example
DM P, R P, R P, R P, R P, R
Example
130
6.9 Summary
To overcome limitations of conventional RMPs, the MRUMP has been developed. The MRUMP integrates all parties views in scope and processes. The risk/uncertainty map, HSRU framework, DVP and other processes i.e., response process, application planning process, and application control process are assembled together to form the MRUMP. A number of systematic procedures and tools such as RUBS and risk/uncertainty checklist are also included in the MRUMP. The implementing manual of MRUMP is provided in this chapter. This manual is initially developed for application in construction stage. The overview of the MRUMP is summarized in Table 6.7.
Table 6.7: Summary of MRUMP WHAT: WHO: WHERE: WHEN: MRUMP is a logical and systematic tool assisting all parties to systematically and efficiently manage risk and uncertainty. MRUMP aims to assist practitioners e.g., policy maker, lender, owner, consultant, and contractor who involved with the project. MRUMP is possibly used in both single and multi-party environment under risky and uncertain condition. MRUMP is expected to provide assistance in policy making, planning and problem preventing at early stage of project and problem preventing and solving at later stage of project. For better dealing with risks and uncertainties, MRUMP provides: - risk/uncertainty map as knowledge base of risk and uncertainty - HSRU framework for producing higher precision output, - DVP for presenting dimensional output, and - processes in integrating multiple parties views. MRUMP encourages parties to communicate each other, identify problem, and cooperatively solve the problem that increases possibility of project success. MRUMP consists of five main processes: 1. Risk and uncertainty management planning 2. Risk and uncertainty identification and structuring 3. Risk and uncertainty assessment and analysis 4. Risk and uncertainty response process 5. Risk and uncertainty management control For application purpose, MRUMP is provided in form of implementing manual describing necessary inputs, step-by-step procedure, and outputs of each process.
WHY:
HOW:
131
Chapter 7
Application of MRUMP
7.1 Introduction
This chapter demonstrates the application of MRUMP presenting how it has been implemented in a real world project as a case study. There are two objectives for conducting application study of the MRUMP. The first objective is to discuss the applicability of the MRUMP for further refinement and improvement. By applying the MRUMP to real world project, the second objective is to reveal how the project has been being practiced that is beneficial for both practitioners currently working on site and prospective practitioners of future projects.
As explained in previous chapter, the MRUMP consists of five major processes i.e., risk and uncertainty management planning, risk and uncertainty identification and structuring, risk and uncertainty assessment and analysis, risk and uncertainty response, and risk and uncertainty management control processes. The application of each process to the case study is provided in the following sections, respectively.
132
Table 7.1: The employer, consultant and source of funds of project Items Employer Consultant Source of funds Description An executing agency in Ministry of Transportation Association of consulting engineers (four local consultants and a foreign consultant) Budget from local government: 40% An international lender: 60%
Table 7.2: Key information of project Items Main works: Contract cost (no VAT; rate at Jan/2004) Contract duration: Contractor: Description Bridge (total length 3,400 m.), Junction, At-grade roads 7.2 Billion Yen 1,020 days Joint Venture A: (three foreign contractors and one local contractor)
In this application, the author performed the role of evaluation analyst. As evaluation analyst, following tasks were performed i.e., educating assessors regarding introduction, objective and overview of process, preparing documents and presentation for facilitating assessors during interview, arranging appointment and conducting interview, summarizing assessment, analyzing data, and providing analysis result to all assessors.
133
Top managements of each party, who act as the experts or assessors, also perform the role of decision makers. It should be understood that the purpose of the MRUMP is to assist the assessors and decision makers in assessing the risks and uncertainties and providing risks and uncertainties information for making decision. Therefore, to finalize the decision it is totally depended on the decision makers risk attitude. This is beyond the scope of the MRUMP. The outputs of the MRUMP are considered as additional information used in facilitating them in making decision. The party who is responsible for making decision is desirable to understand the situation and perception of other involved parties towards analyzed uncertainty and response scenario, which are provided by the MRUMP. Moreover, the MRUMP aims to encourage the harmony among all involved parties.
The first timing of application of the MRUMP is assumed as just beginning of project construction stage. The assessors were asked to identify the project uncertainties occurring from early stage to current stage of construction (around 25th month of project duration). For probability and impact assessment of project uncertainties it is assumed that the assessment is made at the early stage of construction. The assessors were asked to go back to the early stage of construction to do assessment, because the error analysis could be conducted by comparing their analysis result with known actual status of project up to current stage.
The second timing of application is from current stage to the end of construction. The assessors were asked to assess risks and uncertainties at the current stage. Figure 7.1 illustrates the first and second timing of application along with baseline and actual project progress.
134
Project Progress
100 90 80 70
Progress %
77%
60 50 40 30 20 10 0
1 5 10
Baseline
Actual 15 20 25
9%
Current Date
30
2 nd Time Frame of Assessment
34
Month
1 st Assessment Point
2 nd Assessment Point
Figure 7.1: First and second timings of application along with project progress
135
Junction 1.02.00
Viaduct 1.03.00
Incidentals 1.10.00
136
check list and hierarchical structure of risk and uncertainty framework. Following sections describe major risks/uncertainties based on assessors perception of each party.
The total land could not be acquired before date of issuance of the notice to proceed. There were two sources of uncertainty, which caused the occurrence of this land acquisition consequent uncertainty. The source of uncertainty through the first transition was initiated from the land price settlement in the land acquisition procedure. The settlement of land price to residents was delayed. This then induced the cooperation from residents uncertainty. The residents did not satisfy the offered price, which was derived from standard land price specified by a public agency that is responsible for determining standard land price. Moreover, due to the much different in land price of same characteristic of land, this made residents unsatisfactory. As a result, they delayed in moving out and relocating. The second source of uncertainty was related to budget approval from government. The budget for compensation cost was delayed in approval. The 5%, 15%, and 30% of budget was approved in the first three years before issuance of notice to proceed. After the notice to proceed was issued, the remaining 45% and 5% was released in next two years respectively. Because of this late land acquisition, the contractor could not access to construction site and commence works.
Similar to the executing agencys and the consultants views, the contractor also identified the land acquisition uncertainty occurred during the construction stage. The contractor explained that this uncertainty was realized just before signing the contract. There were three sources of this uncertainty i.e., cooperation from residents, timing of
137
project commencement, and budget constraint for compensation cost. The first source of uncertainty occurred when the respondents did not move out. The second source of uncertainty was perceived as improper timing in issuance of notice of proceed, while the substantial part of lands or necessary land according to proposed schedule still could not be acquired. The next source of uncertainty was the limited budget for compensation cost to residents.
The next consequent risk, which was the result from land acquisition uncertainty, is contractors mobilization risk. Since the contractor could not receive and access to the land, the contractor then decided not to mobilize the equipment, subcontractor and labor. This could delay the progress of entire project.
This consequent risk also was originated from land acquisition uncertainty. The contractor did not mobilize the technical key staff to the project, since he could not start construction.
The contractor pointed out the uncertainty of technical capability of subcontractor. This was particular to the local subcontractor. Since the contractor was subletting most of the works to the subcontractor, this uncertainty could result in delay of entire project.
This consequent uncertainty could affect the work progress, availability of subcontractor and work quality. It was originated from the competitive condition in
138
bidding. Since the competition level in bidding was very high, the contractor had to bid in low price. This tight contract price and budget resulted in difficulty in coordination among contractors in the joint venture.
The first uncertainty, which was identified by the consultant, was land acquisition uncertainty. There were two transitions of uncertainty that resulted in land acquisition uncertainty. The first one was originated from restructuring of government system. During the land acquisition process, the local government had been in restructuring process. As a result, the approval from executing agency was delayed, since responsible public officers were oft en changed. Furthermore, it resulted in late appointment of land price settlement committee, which directly induced the land acquisition uncertainty. The second transition was originated from political influence. which caused the uncertainty in commencement of project.
Due to the late land acquisition, the contractor then did not mobilize the equipment to the site at the early stage of project. Therefore, when the land could be sufficiently acquired, the contractor could not mobilize the equipment according to schedule. This caused the delay in availability of equipment.
The source of this uncertainty was land acquisition uncertainty. Due to late land acquisition, the contractor did not mobilize sufficient key staff to the project. Therefore, there were not sufficient technically capable staffs. This made the contractors technical capability uncertain. This impacted the work progress of technical oriented activities.
139
The consultant pointed out the coordination problem among contractors in joint venture. They could not corporate each other well. The in-house communication in joint venture seemed to be problematic. The responsibility for shared works was unclear. The source of this uncertainty was due to tight contract price and budget that resulted each contractor in strictly controlling their individual budget.
Because this project was the first project, of which the lead contractor of this joint venture received the contract in this country. The consultant identified the uncertainty of contractors local experience as the source of uncertainty that might result in uncertainty of availability of suppliers and subcontractors. This lead contractor might not have the business- network with local suppliers and subcontractors, which could make the procurement process of suppliers and subcontractors delayed.
Subsequently, relying on the developed HSRUs based on each partys perception, the probability and impact of risks and uncertainties were assessed by the practitioners (assessors) of each party. Before starting the assessment process, probability and impact assessment procedure was explained to assessors. The procedures of assessment, example of probability and impact scale, and example of questions were included in the explanation.
The structured HSRUs together with the assessed probability and impact perceived by
140
141
Land acquisition
Site accessibility
Influential Risk/Uncertainty
Influenced Project/Activity
Type of Delay
Figure 7.3: Hierarchical structure of risks and uncertainties impacting entire project (executing agency) Table 7.3: Probability and impact assessment of risks and uncertainties impacting entire project based on Figure 7.3 (executing agency)
Event
(1)
Uncertainty
(2)
B C D
0.95
0.95
20%
142
143
Site accessibility
Entire project
Influenced Project/Activity
Total delay
Type of Delay
Figure 7.4: Hierarchical structure of risks and uncertainties impacting entire project (contractor) Table 7.4: Probability and impact assessment of risks and uncertainties impacting entire project based on Figure 7.4(contractor)
Event
(1)
Uncertainty
(2)
B C D
0.95
0.95
10%
144
Commencement of project
Site clearing
Influenced Project/Activity
Date delay
Date delay
Type of Delay
Figure 7.5: Hierarchical structure of risks and uncertainties impacting site clearing and clearing and grubbing activities (contractor) Table 7.5: Probability and impact assessment of risks and uncertainties impacting site clearing and clearing and grubbing activities based on Figure 7.5 (contractor)
Event
(1)
Uncertainty
(2)
B C
0.95
0.95
100%
145
Source of Risk/Uncertainty & Consequent Risk/Uncertainty Budget constraint for compensation Commencement of project Contract price and budget Competitive condition in bidding
D
Technical capability of subcontractor (amount of equipment)
B
2 2
Work progress
Influential Risk/Uncertainty
Influenced Project/Activity
Progress delay
Type of Delay
Figure 7.6: Hierarchical structure of risks and uncertainties impacting piling activity (contractor) Table 7.6: Probability and impact assessment of risks and uncertainties impacting piling activity based on Figure 7.6 (contractor)
Event
(1)
Uncertainty
(2)
B C Event
(1)
0.95
1 P(D)
(3)
0.95
100% Impact
(4)
D Event
(1)
0.1
100%
E G
0.95
1.0
0.95
100%
146
Source of Risk/Uncertainty & Consequent Risk/Uncertainty Budget constraint for compensation Commencement of project
B
2
Work progress
Influential Risk/Uncertainty
Influenced Project/Activity
Date delay
Figure 7.7: Hierarchical structure of risks and uncertainties impacting pile cap activity (contractor) Table 7.7: Probability and impact assessment of risks and uncertainties impacting pile cap activity based on Figure 7.7 (contractor)
Event
(1)
Uncertainty
(2)
C F Event
(1)
0.95
0.95
100%
D F Event
(1)
0.95
1 P(E)
(3)
0.95
10% Impact
(4)
0.1
100%
147
148
Commencement of project
Site accessibility
Influential Risk/Uncertainty
Entire project
Influenced Project/Activity
Total delay
Type of Delay
Figure 7.8: Hierarchical structure of risks and uncertainties impacting entire project (consultant) Table 7.8: Probability and impact assessment of risks and uncertainties impacting entire project based on Figure 7.8 (consultant)
Event
(1)
Uncertainty
(2)
B C D
0.95
0.95
40%
149
Restructuring of government system Approval from executing agency Land price settlement committee Political influence
Commencement of project
Land acquisition
Equipment availability
Site clearing
Influenced Project/Activity
Date delay
Type of Delay
Figure 7.9: Hierarchical structure of risks and uncertainties impacting site clearing and clearing and grubbing activities (consultant) Table 7.9: Probability and impact assessment of risks and uncertainties impacting site clearing and clearing and grubbing activities based on Figure 7.9 (consultant) Event Uncertainty P(B|C) P(C) P(B C) Impact
(1) (2) (3) (4) (5) (6)
B C
0.95
0.90
0.855
100%
150
Source of Risk/Uncertainty
Subcontractor availability
Influential Risk/Uncertainty
Influenced Project/Activity
Type of Delay
Figure 7.10: Hierarchical structure of risks and uncertainties impacting piling and pile cap activity (impact is expressed in project level) (consultant) Table 7.10: Probability and impact assessment of risks and uncertainties impacting piling and pile cap activity (impact is expressed in project level) based on Figure 7.10 (consultant) Event Uncertainty P(A|B) P(B) P(A B) Impact
(1) (2) (3) (4) (5) (6)
A B
0.05
1.0
0.05
10%
151
Work progress
Influenced Project/Activity
Type of Delay
Figure 7.11: Hierarchical structure of risks and uncertainties impacting piling activity (consultant) Table 7.11: Probability and impact assessment of risks and uncertainties impacting piling activity based on Figure 7.11 (consultant) Event Uncertainty P(A|B) P(B) P(A B) Impact
(1) (2) (3) (4) (5) (6)
A B
0.05
0.05
20%
152
Restructuring of government system Approval from executing agency Land price settlement committee Political influence
Land acquisition
C
Influential Risk/Uncertainty
Work progress
Influenced Project/Activity
Type of Delay
Figure 7.12: Hierarchical structure of risks and uncertainties impacting pile cap (at main bridge) activity (consultant) Table 7.12: Probability and impact assessment of risks and uncertainties impacting pile cap (at main bridge) activity based on Figure 7.12 (consultant) Event Uncertainty P(B|D) P(D) P(B D) Impact
(1) (2) (3) (4) (5) (6)
B D Event
(1)
0.95
0.95
0.90
100%
C E
0.05
0.05
20%
153
In analysis, after we obtained the assessed value of probability and impact towards each consequent risk and uncertainty from each partys perception, first based on conditional probability and the multiplication rule in probability theory, we calculated joint probability in order to find the probability distribution of impact (in term of delay percentage). Then, we transformed the delay percentage to delay duration of each impacted activity (or in project level) and obtained probability distribution of activity duration (or project duration). Joint probability tables, joint impact tables, probability distribution of impact (delay percentage) tables and probability distribution (delay duration) tables of each impacted activity (or project) are provided in Appendix C. An example of analyzing procedure is shown in Figure 7.13.
Subsequently, we assigned obtained probability distribution of activity duration (here activity duration is random variable) in scheduling simulation model based on CPM method in spreadsheet software. The scheduling simulation models presenting dependency and type of delay between activity and uncertainty of each party are shown in Appendix D.
154
B Land acquisition
Site accessibility
Hierarchical structure of risks and uncertainties impacting entire project 1. Analysis of P(B/CD) P(CD) P(B(CD)=P(B/CD)P(CD) Impact (to project level) = = = = C -> D ->
Assumption: A will occur and provide impact only when B occurs due to either occcurece of C or D. P(A) = P(A (B(CD)) P(A/B (CD)) = 1 P(A'/(B(CD))') = 1 Table EA1.1: Joint probability table A A' Table EA1.2 Impact table B (CD) A A' 20 0 (B (CD))' 0 0
B (CD) 0.95 0
(B (CD))' 0 0.05
Table EA1.3: Summary of probability and cumulative distribution of impact (delay percentage) to entire project (executing agency) Impact (%) 0 20 Probability Cumulative 0.05 0.05 0.95 1 1 E[I] 0 19 19
Table EA1.4: Summary of probability and cumulative distribution of impacted duration of project (executing agency) Impected Component Project Original Duration (day) 1020 Delay (day) Impacted Duration Probability Cumulative (day) 0 1020 0.05 0.05 204 1224 0.95 1 1 E[I] 0 193.8 193.8 E[D] 51 1162.8 1213.8
155
Next, we conducted the simulation to obtain the simulated project duration. In this simulation process, we employed a simulation software in conducting Monte Carlo simulation. In assigning distribution, in this analysis we used custom distribution function to assign distribution, which we obtained previously, to each assumption cell. The custom distribution function is available in this simulation software. Then, we assigned the forecast cell to cell representing project duration. After that we run the simulation.
Consequently, we obtain the probability and cumulative distribution of project duration and statistics information. The results of simulation of each party are presented in following sections.
Table 7.13: Statistics information of simulation result based on executing agencys assessment Items Value Trials 10000 Mean 1,213.21 Median 1,224.00 Mode 1,224.00 Standard Deviation 45.66 Variance 2,085.24 Skewness -3.99 Kurtosis 16.96 Coeff. of Variability 0.04 Range Minimum 1,020.00 Range Maximum 1,224.00 Range Width 204.00 Mean Std. Error 0.46
156
Frequency Chart of Project Duration (Executing Agency) .947 Probability .710 .474 .237 .000 1,020 1,071 1,122 Day 1,173 1,224
Table 7.14: Statistics Information of simulation result based on contractors assessment Items Trials Mean Median Mode Standard Deviation Variance Skewness Kurtosis Coeff. of Variability Range Minimum Range Maximum Range Width Mean Std. Error Value 10000 1,570.63 1,558.00 1,558.00 69.42 4,818.88 0.70 3.83 0.04 1,312.10 1,822.00 509.90 0.69
157
Frequency Chart of Project Duration (Contractor) .542 Probability .407 .271 .136 .000 1,312 1,440 1,567 Day 1,695 1,822
Table 7.15: Statistics information of simulation result based on consultants assessment Items Trials Mean Median Mode Standard Deviation Variance Skewness Kurtosis Coeff. of Variability Range Minimum Range Maximum Range Width Mean Std. Error Value 10000 1,530.33 1,560.00 1,560.00 97.38 9,482.78 -3.26 13.76 0.06 1,079.00 1,684.20 605.20 0.97
158
Frequency Chart of Project Duration (Consultant) .504 .378 .252 .126 .000 1,079 1,230 1,382 Day 1,533 1,684
Probability
From the cumulative distributions plotted in Figure 7.17, it shows that the distribution based on executing agencys assessment is totally located on the left side of ones belong to both contractor and consultant, and its location is quite far from others. The distributions based on contractors and consultants assessment s are located closely and overlapped in some parts; however, the one belong to consultant mostly locates on the left side of contractors and has wider range of distribution.
159
Probability
160
Restructuring of government system Approval from executing agency : Contractors perception : Consultants perception Land price settlement Competitive condition in bidding
Political influence
Commencement of project
Land acquisition
161
Contractors mobilization of equipment Contractors mobilization of subcontractor Contractors local experience Contractors mobilization of key staff Equipment availability Subcontractor availability Clearing & grubbing Piling Pile cap (main bridge) Date delay Date delay Date delay
Site accessibility
Work progress
Work progress
Influential Risk/Uncertainty
Entire project
Site clearing
Piling
Influenced Project/Activity
Total delay
Date delay
Progress delay
Progress delay
Type of Delay
162
Figure 7.19: Risk/Uncertainty Impact Chart (Only Critical Activities) of all parties
162
As a result of all parties views shown in integrated HSRU (Figure 7.18), we can summarize risks and uncertainties associated with this case study into four categories including: (1) occurring risks and uncertainties: the risks and uncertainties that have been occurring (such as land acquisition risk/uncertainty in this case study), (2) subsequent risks and uncertainties: the risks and uncertainties that their occurrence is caused by the occurring risks and uncertainties and they occur during the occurrence of occurring risks and uncertainties (such as mobilization of subcontractor and equipment risk/uncertainty due to land acquisition risk/uncertainty in this case study), (3) lingering risks and uncertainties: the risks and uncertainties that their occurrence is caused by the occurring risks and uncertainties and they occur after the occurrence of the occurring risks and uncertainties is ended (such as mobilization of
163
key staff risk/uncertainty due to land acquisition risk/uncertainty in this case study), and (4) new future risks and uncertainties: the risks and uncertainties that their occurrence is not relevant to risks and uncertainties in other categories.
Furthermore, if we elaborately scrutinize each risk/uncertainty, the characteristic of particular risk/uncertainty is different based on position of each party. The characteristics mentioned here consist of: decision/non-decision,
responsibility/non-responsibility, and controllability/uncontrollability. Due to different characteristic of particular risk/uncertainty, uncertainty to one party may be risk to another party, and vice versa.
In addition to the clarification of risk and uncertainty, which has been made in the first chapter, by understanding the characteristics of risk/uncertainty, we can know what is risk or uncertainty to each party, whether that risk or uncertainty can be controlled by that party, whether that party has to be responsible for that risk or uncertainty, and whether that risk or uncertainty is directly related to that partys decision. Therefore, it is desirable for all parties to understand the characteristics of each risk and uncertainty in order to further provide the desirable solutions for all parties. The characteristics of major consequential risks and uncertainties (grouped into four categories described above) associated with each party in this case study are described in Table 7.16.
Moreover, we could grasp categories and characteristics of risk/uncertainty associated with each party as summarized in Table 7.16. Table 7.17 summarizes the result of probability and impact assessment of all parties purposefully for quantitative comparison of each partys perception towards probability and impact. From this table, we also can notice the difference of perception in assessing probability and impact.
164
Executing agency
Contractor
Consultant
Subsequent risk/uncertainty category 1. Mobilization of ND NR C/NC equipment 2. Mobilization of ND NR C/NC subcontractor Lingering risk/uncertainty category 1. Mobilization of key ND NR C/NC staff New future risk/uncertainty category 1. Technical capability ND NR C/NC of subcontractor 2. Coordination among contractors in JV ND NR NC
Un Un
D D
R R
C C
Ri Ri
ND ND
C5, C21, ITT8 C5, C21, NR C/NC Un ITT8 NR C/NC Un NR C/NC Un C5, C21, ITT8 C5, C21, ITT8
Un
Ri
ND
Un Un
D D
R R
C/NC Un C Ri
ND ND
NR C/NC Un NR NC
Un C21
Note D = Decision, ND = Non-Decision; R = Responsibility, NR = Non-Responsibility; C = Contrallability, NC = NonControllability; Ri = Risk, Un = Uncertainty Clause (C) C5: General obligations; C18: Notice to proceed; C19: Commencement time and time of completion; C20: Extension of time for completion; C21: Rate of progress; (Descriptions are provided in Appendix F) Instruction to Tenderers (ITT) ITT8: Supplementary documents to accompany the tender; (Descriptions are provided in Appendix F)
Table 7.17: Summary of probability and impact assessment of all parties Risk/Uncertainty 1. Land acquisition Executing Agency Prob. Imp. 0.95 20%
(Project)
2. Contractors mobilization of 0.95 100% 0.855 100% equipment 3. Contractors mobilization of 0.95 100% 0.05 10% (Project) subcontractor 4. Contractors mobilization of 0.95 10% 0.90 100% key staff 5. Technical capability of 0.1 100% subcontractor 6. Coordination among 0.95 100% 0.05 20% contractors in joint venture Note: Prob. = Joint probability based on multiplication rule; Imp. = Impact to project or activity (delay percentage of project duration)
165
The difference and similarity associated with HSRU, probability and impact are summarized as following:
The executing agency perceived only the land acquisition uncertainty that caused the site accessibility of project. Similar to executing agency, the contractor and consultant also perceived this uncertainty. Furthermore, the contractor and consultant also perceived the subsequent and lingering risks/uncertainties due to land acquisition uncertainty. These subsequent and lingering risks/uncertainties were not perceived by the executing agency.
Based on contractors perception, these subsequent risks include contractors mobilization of equipment and subcontractor. Based on consultants perception, only contractors mobilization of equipment was perceived. With this difference, the land acquisition is considered as the source of uncertainty to particularly contractor, since contractor has to make decision regarding mobilization of equipment and subcontractor with uncertain condition of amount and sequence of handed over land. On the other hand, the executing agency seemed to lack of understanding of contractors requirement in mobilizing equipment and subcontractor. Generally, for contractor, not only sufficient amount of land but also sequence of acquired land is significant criterion for making mobilization decision. This source of uncertainty should be addressed in deriving solution by both executing agency and contractor.
For lingering risk/uncertainty, both contractor and consultant perceived the contractors mobilization of key staff risk/uncertainty as lingering risk/uncertainty due to land acquisition uncertainty. Similar to subsequent risk/uncertainty, the executing agency did not perceive this lingering uncertainty. The contractor and consultant perceived that even though the land can be totally acquired and handed over, contractor may not be immediately transfer or employ new key staffs to project. The executing agency might not understand the staff allocation and recruitment constraint on the part of contractor.
For new future risk/uncertainty category, consultant also pointed out the contractors local experience that may influence the contractors mobilization of subcontractor in
166
pilling and pile cap activities. Contractor did not perceive this risk regarding his qualification. Contractor perceived only land acquisition uncertainty influencing his mobilization of subcontractor risk that it might impact the piling and pile cap activities. With this difference, the contractor might overlook self defectiveness (local experience) about difficulty in finding local subcontractor.
Contractor and consultant seemed to have similar concern regarding coordination among contractors in joint venture risk/uncertainty to progress of piling or pile cap activities. Moreover, contractor also perceived the technical capability of subcontractor uncertainty, which was not perceived by consultant. Since consultant did not directly interact with subcontractor, consultant might not know the level of subcontractors capability.
Next, the probability and impact associated with each risk/uncertainty based on each partys perception are compared. By comparing these two variables, we can understand the difference and similarity of their perception regarding how likely that risk/uncertainty will occur and magnitude of that risk/uncertainty.
As mentioned above, all parties perceived the occurrence of land acquisition risk/uncertainty. They also similarly perceived that this risk/uncertainty will likely to occur. However, their perception towards impact of this risk/uncertainty is different. Among these three parties, the consultant perceived the impact of land acquisition uncertainty was biggest. The impact of this land acquisition risk/uncertainty assessed by executing agency and contractor are one-second (1/2) and one- fourth (1/4) of consultants assessment respectively. This difference shows that although all parties perceived the occurrence of the land acquisition risk/uncertainty, the executing agency and contractor did not perceive its huge impact. Experience of past projects, knowledge, and bias associated with each party might make their perception different.
Regarding likelihood of occurrence of others risk/uncertainty, contractor and consultant perceived quite similar level of likelihood of occurrence of contractors mobilization of equipment and key staff as very high. However, their perceptions are different when
167
they assessed the likelihood of occurrence of contractors mobilization of subcontractor risk/uncertainty and coordination among contractors in joint venture risk/uncertainty. The consultant perceived their likelihood as very low. Since this contractor is considered big international company with high reputation, the uncertainties related to contractors responsibility is not common in practice for consultant. Moreover, consultant might believe in the reputation of contractor.
Regarding the impact of others risk/uncertainty, consultant perceived the impact of contractors mobilization of subcontractor and coordination among contractors in joint venture uncertainties much lower tha n contractors assessment. The reason of this difference may be similar to reason of previous case. The story is different in impact assessment of contractors mobilization of key staff risk/uncertainty. The contractor did not perceive the big impact of this risk, though consultant perceived its significance. The contractor might be overconfident in their capacity regarding number of key staff, whereas consultant might feel unconfident.
In summary, by quantitatively comparing the probability and impact of risk/uncertainty associated with each party perception, we are aware of the difference in their views. With this observation, we can answer the questions regarding the difference in location and range of cumulative distribution of project duration shown in Figure 7.17. The distribution based on executing agencys perception is totally located on the left side and far from ones belong to contractor and consultant, because the executing agency perceived only land acquisition risk. For contractor and consultant, although they perceived the same set of risks and uncertainties, their perceptions towards probability and impact are different. The consultant perceived big impact of land acquisition uncertainty, whereas the impact of contractor related uncertainties were perceived as low. This is contrary with contractors perception. This makes the cumulative distribution of project (shown in Figure 7.17) based on consultants perception is wider than contractors distribution. One possibility of this difference is that the case of nonoccurrence of land acquisition uncertainty was realized in simulation. The risk/uncertainty impact quantification chart (shown in Figure 7.19 and in Appendix E) illustrates this difference.
168
With both qualitative and quantitative observations towards all parties perception of identified risks or uncertainties and their probability and impact, the differences and similarities associated with their perceptions could be aware. By integrating multiple parties views in scope of application and comparing all parties perception (using overall integrated HSRU and RUIC) following benefits are realized: (1) understanding other parties uncertainties and constraints, (2) reducing possibility of ignorance of unperceived risks and uncertainties by realizing subsequent and lingering risks and uncertainties caused by risk/uncertainty as a result of a partys decision (or action) and recognizing risks and uncertainties related to third parties, (3) providing consideration of different degree of consequence of risks and uncertainties, and (4) providing objective evaluation of one party.
In order to accomplish the first purpose, the analysis result (expected project duration and cumulative distribution of project duration) based on each partys view is compared with actual status of project (project progress up to 25th month). Since we assumed that the assessment has been done at early construction stage of project and period of assessment has been framed from timing of assessment to current status (around 25th month of project), we can compare the analysis result based on each partys view with the actual status of project.
In reality, the executing agency provided approximately 490 days for time extension due to late land acquisition. The original schedule of project was then revised.
169
According to the first revision of schedule, the actual status up to 25th month is shown in following table.
Table 7.18: Actual status of project Items Original contract period 1st time extension New contract period Elapsed time Cumulative progress Schedule (based on 1st revision) Actual status (percent) Estimated project delay Description 1020 days 490 days 1510 days 750 days 9% 27 % -18 % (behind 1st revision schedule) 184 days (18% of original duration)
Based on observation of analysis result, the precision of analysis result comparing with actual status is different depending on parties perception. Table 7.19 shows the comparison of assessed expected project duration (means) with actual project duration (including time extension and progress delay up to 25th month).
Table 7.19: Comparison of expected project duration with actual project duration
Party Executing agency Contractor Consultant Expected Duration (day) 1,214 1,571 1,531 Error (day) 480 123 163 % Error 28 7 10
Note: Expected duration is means duration as a result from simulation. Error = Actual project duration (1,694 days) - Expected duration % Error = (Error/Actual project duration)*100
The level of precision of estimation is considered higher if the difference between estimated and actual values is close to zero. As we can observe from comparison in Table 7.19, the executing agencys assessed expected project duration is mostly deviated from actual project duration and very different from the contractors and consultants deviation. On the other hand, the deviation of contractors estimation from actual status is the smallest one.
170
Figure 7.20 shows range of cumulative distribution of project duration based on each partys perception compared with actual status. Although the contractors and consultants errors are not significantly different, the range of their distributions is different. Only the distribution based on contractors perception covers the actual project duration. For others distribution, the actual project duration is located outside the range of their distribution specifically the executing agencys distribution.
Cumulative Distribution (Assessment) and Actual Status 1,020 days Original Duration 1.00 .75 .50 .25 1,020 .00 1,079 1,000 1,312 1,225 1,450 1,675 1,900 Executing agency 1,224 1,510 days 1,694 days With Time With Time Extension Extension and Progress Delay 1,684 1,822 Consultant Contractor
Probability
Figure 7.20: Cumulative distribution of project duration (all parties) and actual status
Discussion regarding sources of error, which make the discrepancy between assessors assessment and actual status, as well as refinement of MRUMP and application are made in next section.
171
The discrepancy of analysis result and actual status is possibly due to variation of each partys perception associated with three main sources of error i.e., HSRU, probability, and impact of risks and uncertainties. Error analysis is conducted in this section.
For executing agency, lack of experience, inadequate knowledge and opposite position are possible causations of error making ignorance of risks and uncertainties regarding contractor (e.g., mobilization of equipment and subcontractor and inefficient coordination among contractors in joint venture). Based on the executing agencys perception, only the land acquisition uncertainty was perceived as consequent uncertainty, though in reality there were also other risks and uncertainties occurred. Mentioned above the causations of this first source of error may due relevant to experience, knowledge, and position. Since this contractor is considered as international contractor, which has strong financial status, the executing agency might not have experience about the risks and uncertainties related to contractor with high reputation. In practice, the executing agency is mainly responsible for project administration. The consultant is one who performs site supervision for executing agency. With this position, the executing agency might not know contractors constraint in mobilization of resources. Due to these causations, the executing agency might ignore risks and uncertainties related to contractor.
Moreover, the executing agency seemed to underestimate the impact of land acquisition uncertainty. Even though the executing agency could identify the land acquisition uncertainty, the executing agency seemed not expect the high impact of land acquisition problem. This may be because the executing agency never experienced significant impact of late land acquisition in his past experience.
172
For contractor, ignorance of risk related to selfs defectiveness (lack of local experience), which is possibly caused by position factor, resulted in incomplete HSRU. It is possible that one may overlook in objectively self-evaluation. Regarding deviation of probability, lack of experience and knowledge of local subcontractor possibly is the causation in underestimating probability of technical capability of subcontractor uncertainty. Due to lack of local experience and knowledge of local practice, the contractor seemed to underestimate the impact of land acquisition. Even though, the contractor is the big international contractor, this contractor just enters this country market.
For consultant, with his position the consultant did not directly involve with subcontractor; therefore, the consultant ignored uncertainty related to technical capability of subcontractor. The consultant also seemed to underestimate the probability of contractors mobilization of subcontractor and coordination among contractors in joint venture uncertainties, since consultant might not expect these uncertainties related to high reputation and well-known contractor. With the same reason, the consultant seemed to underestimate impact of coordination among contractors in joint venture uncertainty.
In addition to above observation, causations of variation of each source of error may be caused by (1) assessors bias, (2) timing assumption of assessment and (3) inefficient data collection e.g., time limitation of interview.
We can summarize the type and causation of error associated with each source of error according to above observation as following:
(1) ignorance of risks and uncertainties due to lack of experience, lack of knowledge and different position, (2) underestimation of probability of risks and uncertainties due to available past experience, lack of experience and lack of knowledge, (3) underestimation of impact of risks and uncertainties due to lack of experience,
173
Source of Error
HSRU
Impact
Assessor
Application
Experience
Knowledge
Position
Bias
Assumption
Procedure
Type of Error
Ignorance
Overestimation
Underestimation
(4) over and underestimation of probability and impact due to assessors subjective bias, and (5) error due to assumption and procedure in application.
Figure 7.21 shows this summary in hierarchical structure format. By understanding this source, causation, and type of error, we can further refine the MRUMP and improve future application.
Further, this comparison pinpoints the benefit of integration of multiple parties views. We can observe from the error analysis that error is possibly mitigated by integrating all parties views, because the comparison shows that one party could provide more realistic assessment of some risks and uncertainties than others and vice versa. By realizing this bene fit, the meeting among all parties together with analyst for risk/uncertainty communication and problem solving is simulated to demonstrate how the MRUMP application result can be employed in practice. Next section provides the simulation of meeting.
174
Based on the timing assumption of assessment in this application previously defined in early part of this chapter, we assumed that the application is implemented during the early stage of construction after project commencement date. Relying on this assumption, for the first purpose, the explanation of result interpretation is also assumed to be made after completion of assessment in early stage of construction.
For the second purpose, we assume the situation that there is a meeting for discussion about the result of the MRUMP application in the case study. The participants who participate in the meeting include analyst and all assessors from executing agency, contractor, and consultant. The analyst is performing the role of facilitator and mediator in the meeting to present the result of application and draw the discussion from all participants.
The result of application, which has been done up to the analysis process i.e., the cumulative distribution of project duration to all parties are focused in this interpretation. In interpreting the result of application, we usually start to look at result of cumulative distribution of project duration, since it tells us about the overview of project based on assessment and analysis of risks and uncertainties. Then, the fo llowing questions may come. How can we interpret this distribution? How can it be used? Normally, we can use the cumulative distribution of project duration in answering following two main questions:
175
Analyst:
In this meeting, I would like to present the result of the MRUMP application and have your discussion towards the result. First, I would like to briefly summarize what we have done in the application. Recently, the project is in the early stage of construction. We are trying to figure out what will happen to the project (in terms of project duration) in the future based on each partys perception. I have assisted all of you in conducting the identification and structuring of risks and uncertainties and assessment of probability and impact of those identified and structured risks and uncertainties. Each party has done these processes separately. In this meeting, everyone will know your own perception and others perception towards the exposure of risks and uncertainties to the project. Yes, we have gone through the number of steps. Now, I would like to know the result. First, I would like to know when will the project finish? Could you show me the result? Initially, I would like to remind and explain pre-specified assumption regarding base project duration used in analysis. As the original contract duration is 1,020 days. In analysis, we used this duration as base duration by assuming that this duration does not incorporate the exposure of newly identified risks and uncertainties. Even though, normally, to estimate this duration in practice, based on past experience, consideration of some risks such as weather condition is already incorporated. It means that our estimation of impact of newly identified risks and uncertainties are simply added to this base duration, doesnt it? Yes, thats right. Then, let me describe the result. According to the statistics information from simulation, the most likely project duration based on each partys perception are follows: - executing agencys perception: = 1,214 days - contractors perception: = 1,571 days, and - consultants perception: = 1,531 days. (see Table 7.13, 7.14, and 7.15) Based on each partys perception, project probably seems to suffer from serious delay. Yes, it seems to be like that. We will discuss why the result is showing like this and what causes delay of project later. Now let us focus on interpretation of this result first. So, I would like to simply know that what will be duration of project that we can have high possibility in completion?
Analyst:
Analyst:
176
Based on cumulative distribution of project duration in Figure 7.17, at 90% chance of completion, the project duration will be: - executing agencys perception: within 1,224 days - contractors perception: within 1,672 days, and - consultants perception: within 1,571 days. If I would rather to know that what will be the likelihood that project will be completed within 1,500 days?
Again, based on cumulative distribution of project duration in Figure 7.17, the probability that project will be completed within 1,500 days is: - executing agencys perception: 100% (exceed maximum range) - contractors perception: about 20%, and - consultants perception: about 10%. Figure 7.22: Dialog of interpretation of cumulative distribution discussion
What will be probability that project will be completed within desired project duration or completion date?
What will be project duration or project completion date corresponding to desired probability of completion?
Dialog in Figure 7.22 attempts to present how the cumulative distribution of project duration is interpreted. I t demonstrates how the result of the MRUMP application particular the interpretation of cumulative distribution of project is utilized. According to the explanation in that dialog, two points are identified.
First, we can notice that the result of estimated project duration of each party is much different from original duration. The reason is relevant to defined assumption that using the original duration as a base duration. Moreover, new risks and uncertainties have been identified and their impacts cause much delay. Regarding this matter, the following question, which should be addressed in meeting, is what are those risks and uncertainties that cause delay of project? 177
: Consultants perception
Commencement of project
Land acquisition
178
Contractors mobilization of equipment Contractors mobilization of subcontractor Contractors local experience Contractors mobilization of key staff Equipment availability Subcontractor availability Work progress Site clearing Clearing & grubbing Piling Pile cap (main bridge) Pile cap (main bridge) Date delay Date delay Date delay Date delay Progress delay
Site accessibility
Work progress
Influential Risk/Uncertainty
Entire project
Piling
Influenced Project/Activity
Total delay
Progress delay
Type of Delay
The project seems to suffer from serious delay. What are those risks and uncertainties that cause delay of project? From the application result, I summarize HSRUs of all parties into one structure as shown in Figure 7.18. It is called integrated HSRU. From this structure, we can know the impacted activity/project and its type of delay, influential risks/uncertainties causing that delay, and consequent and source of risks and uncertainties. This structure shows you overall picture where delay will occur and what causes delay. From this integrated HSRU, we can understand the holistic view of what will happen to project according to all parties perception. For example, all parties perceive that the site accessibility of project is uncertain that cause project start date delay. This is due to risk or uncertainty regarding late land acquisition that is resulted from several consequent and source risks and uncertainties such as inappropriate timing of project commencement, lack of cooperation from residents, constraint of compensation budget and etc. Furthermore, the contractor and consultant identified other risks and uncertainties. Yes, I similarly identified the land acquisition uncertainty influencing site accessibility of project. Moreover, I also perceived the subsequent and lingering effects of land acquisition uncertainty. For subsequent effect, I perceived that due to late land acquisition, I may have to delay in mobilization of equipment and subcontractor. For lingering effect, I may have to delay in mobilization of key staff. Of course these effects may result in date delay and progress delay of some activities. I also perceived the subsequent and lingering effects of late land acquisition that cause delay in contractors mobilization of and equipment and key staff, respectively. To me, I perceived only the site accessibility uncertainty due to late land acquisition. Regarding subsequent and lingering effects of late land acquisition, since I understand that it is with contractors responsibility to mobilize necessary staff, equipment and subcontractor and these resources should be available when land is handed over. Another example based on contractors perception is that the contractor perceived there may be progress delay in piling activity due to incapable subcontractor and inefficient coordination among contractors in joint venture.
Analyst:
179
Yes, I also perceived the work progress of piling activity may be delayed similar to what mentioned by contractor. However, I could identify only inefficient coordination among contractors in joint venture as the consequent uncertainty, but not the incapable subcontractor.
Analyst:
As you can see from the integrated HSRU in Figure 7.18, your structure towards what will cause project delay is in some extent different from party to party. Additionally, based on your risk/uncertainty impact quantification chart in Figure 7.19, your perceptions towards impact to activities also are different. This is the first reason explaining difference in the estimated project duration based on each partys perception. In brief, your perception toward risks and uncertainties are different. Then, we can be aware of problem and identify source of problem. Next, we have to integrate each other to propose solution that satisfies all parties as much as possible. Figure 7.23: Dialog of identified risks and uncertainties discussion
The second point is regarding the difference of the result of each party. As we can see from the result described in Figure 7.22, the estimated project duration based on executing agencys perception is much different from contractors and consultants estimation. This draws the second question that why the result of each party is different. The dialog in Figure 7.23 discusses these matters.
According to the dialog in Figure 7.23, all parties could be aware of problem and identify the source of problem by employing the integrated HSRU (Figure 7.18) and RUIC (Figure.719) based on each partys perception. Then, in next section, all parties are encouraged to integrate their views together in seeking solution to problem that satisfies all parties as much as possible.
parties suppose to be aware of different viewpoints among them. By gathering all parties view in problem awareness stage, the reference for problem identification could be obtained. Then, by comparing all parties perceptions to find difference, in problem identification stage they are encouraged to communicate and identify problem. Finally, the integration of all parties is necessary in problem solving stage, which is demonstrated in this section.
The problem solving stage aims to find solution that satisfies all parties as much as possible. In this stage, all involved parties views should be integrated. Moreover, they should communicate each other by using reference information such as integrated HSRU and RUIC.
In this case study, based on previous observation and discussion, it could be noted that the future problem to project was related to contractors mobilization of equipment and subcontractor as subsequent risk/uncertainty due to uncertain condition of land acquisition. As described in Table 7.16, it is executing agencys responsibility to acquire land and it is responsibility of contractor to mobilize the equipment and subcontractor. The problem might not occur or become significant, if there was no influential relation linking these risks/uncertainties. However, practically contractors decision regarding when equipment and subcontractor should be mobilized mainly depends on amount and sequence of handed over land. Both executing agency and contractor had different views.
Considering contractual condition regarding land acquisition and mobilization, Clause 19.2 stated that: If the Contractor suffers delay or incurs cost from failure on the part of the Employer to give possession, the Employer shall grant an extension of time for the complement of the Works, provided that the Contractor shall not claim any cost for such delay.
The executing agency also further added following condition to this clause i.e., the Employer may require the Contractor to amend the Works Program submitted in accordance with Sub-Clause 5.9, from time to time to suit the precise times after further
181
portions of the Site becomes available, and the Contractor shall modify his program accordingly which shall identify the minimum period required to complete the Works under the new circumstances.
It could be interpreted that the executing agency would grant only time extension in corresponding to late land acquisition. The contractor had to consume the incurred cost due to this uncertainty. Furthermore, the contractor had to execute works according to sequence of land handed over by the executing agency (referred to additional clause described above).
Tied with this contractual condition, since contractor might not be able to claim for incurred cost due to late land acquisition, it was not desirable for contractor to mobilize equipment and subcontractor to site when land was still not handed over. As stated above, for contractor, not only amount of land but also sequence of land was important in making decision to start works. It seemed that this governed contract condition might not be compatible with contractors practice. If the amount and sequence of land handed over to contractor by executing agency was not enough and not in workable order for contractor, the possibility of delay in mobilization of equipment and subcontractor and conflict between the executing agency and contractor might become high.
Therefore, as a possible solution to this problem, both parties should communicate and exchange the information necessary for both parties. They should cooperate together in preparing land acquisition plan and construction schedule. With efficient
communication and cooperation, the executing agency might be able to understand the priority of land that should be acquired in order to enable contractors workability. The contractor also might be able to know whe n equipment and subcontractor should be mobilized to site. If both parties performed this solution, the impact (delay) of mobilization of equipment and subcontractor uncertainty might be reduced or totally eliminated.
In summary, with this opportunity, from the MRUMP application the risks and uncertainties information were collected and made available as reference to all parties.
182
And they were encouraged to express their opinion towards each identified risk and uncertainty as well as towards others perception in matter of difference and similarity in risk perception and matter of characteristics of risk and uncertainty. With this practice, the different views among parties could be aware. Thus, by using gathered risk/uncertainty reference, they were able to communicate and discuss more about the future project situation such as what risks and uncertainties were source of uncertainty and should be put attention in the future. Then the problem could be identified. Significantly, with integration of all parties, this understanding enables all parties to propose solution that is desirable to all parties as much as possible in problem solving stage.
These risks/uncertainties are focused in this response process. Following sections explain the application result of response process.
183
1.1 Do nothing about late land acquisition 1.2 Do nothing about late mobilization of subcontractor and equipment 1.3 Do nothing about late mobilization of key staffs 1.4 Do nothing about inefficient coordination among contractors in joint venture
2.1 Contractor increases number of subcontractors and equipment, prepares and implements mobilization plan of subcontractors and equipment. 2.2 Contractor increases and mobilizes more management and engineering staffs. 2.3 Each contractors management level improve coordination and focus on joint ventures and projects benefit. 2.4 Contractor enhances managerial capability of staff.
3. Preventive measure
3.1 Executing agency acquires most or total of land before project commencement date specified in notice to proceed. 3.2 Executing agency drafts contract condition related to late land acquisition based on the international standard form of contract (FIDIC) by providing time extension and cost incurred due to late land acquisition. 3.3 Executing agency put more importance on contractors local experience and personnel and equipment performance by adding item to evaluate contractors local
184
experience and assigning more weight on personnel and equipment it em in prequalification evaluation.
7.12 Constructing Response Scenario Diagram and Assessing Probability and Impact
The response scenario diagram (RSD) presents the consequential relationship between focused risks/uncertainties, proposed response scenario, consequential risks/uncertainty and impact, and outcome associated with the implementation of that response scenario. After response scenarios have been proposed, their RSDs then were developed based on each partys perception. Subsequently, assessors from all parties provided their assessment on probability and impact based on constructed RSD. The RSDs and assessment result of probability and impact associated with each response scenario based on each partys perception are presented in following sections.
185
Accept Response Scenario : Accept current situation (provide only time extension) (executing agency)
Land acquisition
B
Mobilization of Subcontractor
A
Subcontractor availability Project Date delay
C
Mobilization of subcontractor Accept Coordination among contractors in JV Claim, conflict, and dispute
Figure 7.24: Response scenario diagram of accept response perceived by executing agency Table 7.20: Probability and impact assessment of risks and uncertainties associated with accept response scenario based on Figure 7.24 (executing agency) Risk/Uncertainty Probability Impact Mobilization of 0.95 100% of remaining subcontractor (B) duration Claim, conflict, and dispute 0.2 Approximately 3 years (C)
186
B
Mobilization of subcontractor Mobilization of subcontractor Increasing no. of sub. Coordination with new subcontractor
A
Subcontractor availability Project Date delay
Figure 7.25: Response scenario diagram of reactive response scenario 1 perceived by executing agency
B
Mobilization of key staff Increasing no. of key staff Mobilization of key staff
A
Work progress Project Progress delay
Figure 7.26: Response scenario diagram of reactive response scenario 2 perceived by executing agency
Reactive Response Scenario 3: Improving contractors coordination (executing agency)
B
Coordination among contractors in JV Improving coordination Coordination among contractors in JV
A
Work progress Project Progress delay
Figure 7.27: Response scenario diagram of reactive response scenario 3 perceived by executing agency Table 7.21: Probability and impact assessment of risks and uncertainties associated with reactive response scenario 1 based on Figure 7.25 (executing agency) Risk/Uncertainty Probability Impact Mobilization of subcontractor(B) 0.95 65% of remaining duration Table 7.22: Probability and impact assessment of risks and uncertainties associated with reactive response scenario 2 based on Figure 7.26 (executing agency) Risk/Uncertainty Probability Impact Mobilization of key staff(B) 0.95 65% of remaining duration
Table 7.23: Probability and impact assessment of risks and uncertainties associated with reactive response scenario 3 based on Figure 7.27 (executing agency) Risk/Uncertainty Probability Impact Coordination among contractors 0.95 65% of remaining duration in JV(B) 187
Reactive Response Scenario 4: Enhancing managerial capability of contractors staff (executing agency)
B
Mobilization of subcontractor Coordination among contractors in JV
A
Work progress Project Progress delay
C
Mobilization of key staff Enhancing managerial capability of contractors staff Capability of new management staff
Figure 7.28: Response scenario diagram of reactive response scenario 4 perceived by executing agency Table 7.24: Probability and impact assessment of risks and uncertainties associated with reactive response scenario 4 based on Figure 7.28 (executing agency) Risk/Uncertainty Probability Impact Coordination among 0.5 14% of remaining duration contractors in JV (B) Capability of new 0.05 5% of remaining duration management staff (C)
188
Proactive Response Scenario 1: Acquiring most or total of land before commencement (executing agency)
B
Contractors Mobilization
A
Subcontractor and equipment availability Project Date delay
C
Acquiring land before project starts Land acquisition Claim, conflict and dispute
Figure 7.29: Response scenario diagram of proactive response scenario 1 perceived by executing agency Table 7.25: Probability and impact assessment of risks and uncertainties associated with proactive response scenario 1 based on Figure 7.29 (executing agency) Risk/Uncertainty Probability Impact Contractors mobilization 0.5 18% of remaining duration (B) Claim, conflict, and dispute 0.2 Approximately 3 years Time for land acquisition Approximately 2 years
189
Proactive Response Scenario 2: Adopting contract condition of FIDIC (allow time and cost for late land acquisition) (executing agency)
B
Land Acquisition
A
Site accessibility Project Total delay
D
Adopting FIDIC condition Land acquisition Contractors Mobilization
C
Subcontractor and equipment availability Project Date delay
Figure 7.30: Response scenario diagram of proactive response scenario 2 perceived by executing agency Table 7.26: Probability and impact assessment of risks and uncertainties associated with proactive response scenario 2 based on Figure 7.30 (executing agency) Risk/Uncertainty Probability Impact Land acquisition (B) 0.95 45% of original duration Contractors mobilization 0.5 18% of original duration (D) For proactive response scenario 3 (improving prequalification criteria regarding contractors experience and personnel and equipment items), the executing agency did not perceive its applicability. The executing agency perceived financial factor is more important that the criteria regarding local experience and personnel and equipment items.
190
Accept Response Scenario 1: Accept current situation (provide only time extension) (contractor)
B
Land acquisition Mobilization of Subcontractor
A
Subcontractor availability Project Date delay
D
Mobilization of key staffs Mobilization of key staffs
C
Work progress Project Progress delay
E
Mobilization of subcontractor Accept Coordination among contractors in JV Conflict among contractors in JV
F
Claim, conflict, and dispute
Time extension
Contract clauses
Figure 7.31: Response scenario diagram of accept response scenario perceived by contractor Table 7.27: Probability and impact assessment of risks and uncertainties associated with accept response scenario based on Figure 7.31 (contractor) Risk/Uncertainty Probability Impact Mobilization of 0.95 100% of original duration subcontractor (B) Mobilization of key staffs 0.95 100% of original duration (D) Conflict among contractors 0.95 100% of original duration in JV (E) Claim, conflict and dispute 0.5 Approximately 3 years (F)
191
B
Mobilization of subcontractor
A
Subcontractor availability Project Date delay
Mobilization of subcontractor
Increase in cost
Figure 7.32: Response scenario diagram of reactive response scenario 1 perceived by contractor
B
Mobilization of key staff
A
Work progress Project Progress delay
Figure 7.33: Response scenario diagram of reactive response scenario 2 perceived by contractor Table 7.28: Probability and impact assessment of risks and uncertainties associated with reactive response scenario 1 based on Figure 7.32 (contractor) Risk/Uncertainty Probability Impact Mobilization of 0.05 0.1% of original duration subcontractor (B) Table 7.29: Probability and impact assessment of risks and uncertainties associated with reactive response scenario 2 based on Figure 7.33 (contractor) Risk/Uncertainty Probability Impact Mobilization of key staff 0.95 50% of original duration (B)
192
B
Coordination among contractors in JV Improving coordination Coordination among contractors in JV
A
Work progress Project Progress delay
Figure 7.34: Response scenario diagram of reactive response scenario 3 perceived by contractor Table 7.30: Probability and impact assessment of risks and uncertainties associated with reactive response scenario 3 based on Figure 7.34 (contractor) Risk/Uncertainty Probability Impact Coordination among 0.95 50% of original duration contractors in JV (B) For reactive response scenario 4 (enhancing managerial capability of contractors staff), contractor did not provide his perception towards this response scenario. However, the contractor added comment regarding the mana gerial capability of executing agency that if the managerial capability of executing agencys management staff is enhanced by replacement of new staff, there may be coordination and cooperation problem among parties. All parties may face difficulty in working together.
193
Proactive Response Scenario 1: Acquiring most or total of land before commencement (contractor)
B
Coordination among parties
C
Acquiring land before project starts Land acquisition Coordination among contractors in JV
A
Work progress Project Progress delay
D
Contractual matters
Figure 7.35: Response scenario diagram of proactive response scenario 1 perceived by contractor
Proactive Response Scenario 2: Adopting contract condition of FIDIC (allow time and incurred cost for late land acquisition) (contractor)
B
Land Acquisition Adopting FIDIC condition Land acquisition
A
Site accessibility Project Total delay
D
Claim & conflict
C
Work progress Project Progress delay
Figure 7.36: Response scenario diagram of proactive response scenario 2 perceived by contractor Table 7.31: Probability and impact assessment of risks and uncertainties associated with proactive response scenario 1 based on Figure 7.35 (contractor) Risk/Uncertainty Probability Impact Coordination among parties (B) 0.80 20% of original duration Coordination among (P(B CD)) contractors in JV (C) Contractual matters (D) Table 7.32: Probability and impact assessment of risks and uncertainties associated with proactive response scenario 2 based on Figure 7.36 (contractor) Risk/Uncertainty Probability Impact Land acquisition (B) 0.95 45% of original duration Claim and conflict (D) 0.95 10% of original duration
194
For the proactive response scenario 3 (improving prequalification criteria regarding contractors experience and personnel and equipment items), the contractor perceived the possibility that the contractor may not be qualified.
195
Accept Response Scenario 1: Accept current situation (provide only time extension) (consultant)
Land acquisition
B
Mobilization of Subcontractor
C
Mobilization of subcontractor Accept Mobilization of key staffs
A
Subcontractor availability Project Date delay
D
Coordination among contractors in JV Coordination among contractors in JV
Time extension
Contract clauses
Figure 7.37: Response scenario diagram of accept response scenario perceived by consultant Table 7.33: Probability and impact assessment of risks and uncertainties associated with accept response scenario based on Figure 7.37 (consultant) Risk/Uncertainty Probability Impact Mobilization of subcontractor (B) 0.95 100% of remaining Mobilization of key staff (C) (P(B CD)) duration Coordination among contractors in JV (D)
196
B
Mobilization of subcontractor Increasing no. of sub. Financial viability Work load of staff Mobilization of subcontractor
A
Subcontractor availability Project Date delay
Figure 7.38: Response scenario diagram of reactive response scenario 1 perceived by consultant
B
Mobilization of key staff Increasing no. of key staff Financial viability Inefficiency of staff utilization with unnecessary cost Mobilization of key staff
A
Work progress Project Progress delay
Figure 7.39: Response scenario diagram of reactive response scenario 2 perceived by consultant Table 7.34: Probability and impact assessment of risks and uncertainties associated with reactive response scenario 1 based on Figure 7.38 (consultant) Risk/Uncertainty Probability Impact Mobilization of 0.95 50% of remaining duration subcontractor (B) Table 7.35: Probability and impact assessment of risks and uncertainties associated with reactive response scenario 1 based on Figure 7.39 (consultant) Risk/Uncertainty Probability Impact Mobilization of key staff 0.95 50% of remaining duration (B)
197
B
Mobilization of subcontractor Mobilization of Subcontractor
C
Mobilization of key staffs
A
Work progress Project Progress delay
D
Coordination among contractors in JV
Figure 7.40: Response scenario diagram of reactive response scenario 3 perceived by consultant Table 7.36: Probability and impact assessment of risks and uncertainties associated with reactive response scenario 3 based on Figure 7.40 (consultant) Risk/Uncertainty Probability Impact Mobilization of subcontractor (B) 0.80 Mobilization of key staff 5% of remaining duration (C) (P(B CD)) Coordination among contractors in JV (D)
198
B
Mobilization of Subcontractor
C
Mobilization of subcontractor Mobilization of key staff
A
Work progress Project Progress delay
D
Coordination among contractors in JV
Figure 7.41: Response scenario diagram of reactive response scenario 4 perceived by consultant Table 7.37: Probability and impact assessment of risks and uncertainties associated with reactive response scenario 4 based on Figure 7.41 (consultant) Risk/Uncertainty Probability Impact Mobilization of subcontractor (B) 0.80 Mobilization of key staff 30% of remaining duration (C) (P(B CD)) Coordination among contractors in JV (D)
199
B
Mobilization of subcontractor Mobilization of Subcontractor
A
Work progress Project Progress delay
C
Mobilization of key staff Increasing no. of sub. and key staff Mobilization of key staff
Financial viability
Figure 7.42: Response scenario diagram of reactive response scenario 5 perceived by consultant
Proactive Response Scenario 1: Acquiring most or total of land before commencement (consultant)
B
Acquiring land before project starts Land acquisition Contractors mobilization
A
Work progress Project Progress delay
Figure 7.43: Response scenario diagram of proactive response scenario 1 perceived by consultant Table 7.38: Probability and impact assessment of risks and uncertainties associated with reactive response scenario 5 based on Figure 7.42 (consultant) Risk/Uncertainty Probability Impact Mobilization of 0.05 subcontractor (B) 0.1% of remaining duration P(BC) Mobilization of key staff (C) Table 7.39: Probability and impact assessment of risks and uncertainties associated with proactive response scenario 1 based on Figure 7.43 (consultant) Risk/Uncertainty Probability Impact Contractors mobilization 0.05 5% of original duration (B)
200
Regarding proactive response scenario 2 (adopting FIDIC contract conditions for land acquisition), the consultant commented that this response may not be applicable because the condition does not conform with local regulation.
For proactive response scenario 3 (improving prequalification criteria regarding contractors local experience and personnel and equipment items), the consultant also perceived that this response may not be applicable.
As similar to analys is process, we assigned the obtained probability distribution to project duration. In the simulation model, the project duration is characterized from three main types of duration i.e., elapsed time, impacted duration due to risk/uncertainty, and preparation time or other nominal impact. The simulation models of each response scenario are shown in Appendix G.
The simulation results associated with each response scenario of all parties are provided in next sections.
201
Accept Response Scenario: Accept current situation (provide only time extension) (Executing Agency)
Land acquisition
B
Mobilization of key staffs Mobilization of Subcontractor
A
Subcontractor availability Project Date delay
C
Mobilization of subcontractor Accept Coordination among contractors in JV Claim, conflict, and dispute
Risk response diagram of `Accept` response scenario 1. Analysis of influential uncertainty B -> A
P(B) = 0.95 Impact = 100% of remaining duraton Note: The progress is reduced around 50%. Or it equals to 100% delay of project duration. Assumption P(A/B) = 1 P(A'/B') = 1 Table EA Ac-1.1: Joint probability table B A A' Table EA Ac-1.2: Impact table B A A' 100 0 B' 0 0 0.95 0 B' 0 0.05
Table EA Ac-1.3: Summary of probability and cumulative distribution of impact (delay percentage) to entire project (executing agency) Impact (%) Probability 0 0.05 100 0.95 1 Cumulative 0.05 1 E[I] 0 95 95
Table EA Ac-1.4: Summary of probability and cumulative distribution of impacted duration of project (executing agency) Impected Component Delay (day) Impacted Duration (day) 0 270 270 540 Probability 0.05 0.95 1 Cumulative 0.05 1 E[I] 0 256.5 256.5 E[D] 13.5 513 526.5
Project Remaining Duration (day) 270 Note: the remaing duration is 270 days (1020 - (25mth*30days)) 2. Analysis of consequential uncertainty
1. Claim, conflict and dispute C P(C) = 0.2 Impact = 1095 days (3 years) Note: It depends on project manager of each party. It may consume many years for dispute resolution. Table EA Ac-1.5: Probability and impact table Prob. Impact (day) E[D] C 0.2 1095 219 C' 0.8 0 0 219 2. Coordination among parties The productivity of work may be reduced due to ineffecient coordination among parties. 3. Conflict among contractors in JV Conflict due to coordination problem among contractors in joint venture may occur. However, the impact may be very small.
202
Based on the executing agencys perception, the statistics information of each response scenario is shown in Table 7.40 and the cumulative distribution of project duration is shown in Figure 7.45. Based on the contractors perception, the statistics information of each response scenario is shown in Table 7.41 and the cumulative distribution of project duration is shown in Figure 7.46. Based on the consultants perception, the statistics information of each response scenario is shown in Table 7.42 and the cumulative distribution of project duration is shown in Figure 7.47.
The duration-risk map associated with each response scenario of executing agency, contractor, and consultant are provided in Figure 7.48, Figure 7.49, and Figure 7.50, respectively.
203
1.000 EA-Accept EA-Reactive-1 .750 EA-Reactive-2 EA-Reactive-3 .500 EA-Reactive-4 EA-Proactive-1-1 .250 EA-Proactive-1-2 EA-Proactive-2 .000 1,000.00 1,562.50 2,125.00 2,687.50 3,250.00
Figure 7.45: Cumulative distribution of project duration of each response scenario based on executing agencys perception Table 7.40: Statistics information of all response scenarios based on executing agencys perception
Statistics Value Trials Mean Median Mode Standard Deviation Variance Skewness Kurtosis Coeff. of Variability Range Minimum Range Maximum Range Width Mean Std. Error Accept Reactive 1 Reactive 2 Reactive 3 Reactive 4 Proactive 1-1 Proactive 1-2 Proactive 2 10000 10000 10000 10000 10000 10000 10000 10000 1,988.82 1,676.88 1,676.58 1,676.64 1,529.42 2,065.51 1,842.68 1,549.74 1,780.00 1,685.50 1,685.50 1,685.50 1,523.50 1,933.60 1,933.60 1,479.00 1,780.00 1,685.50 1,685.50 1,685.50 1,510.00 1,750.00 1,933.60 1,662.60 445.39 37.92 38.54 38.43 19.16 451.82 91.80 133.46 198,374.44 1,438.18 1,485.32 1,477.01 367.27 204,145.32 8,427.31 17,811.70 1.42 -4.17 -4.09 -4.10 0.04 1.37 -0.02 -1.64 3.16 18.41 17.74 17.85 1.11 3.13 1.00 7.11 0.22 0.02 0.02 0.02 0.01 0.22 0.05 0.09 1,510.00 1,510.00 1,510.00 1,510.00 1,510.00 1,750.00 1,750.00 1,020.00 2,875.00 1,685.50 1,685.50 1,685.50 1,561.30 3,028.60 1,933.60 1,662.60 1,365.00 175.50 175.50 175.50 51.30 1,278.60 183.60 642.60 4.45 0.38 0.39 0.38 0.19 4.52 0.92 1.33
204
1.000 CT-Accept
.750
CT-Reactive-1
.250
CT-Proactive-1
Figure 7.46: Cumulative distribution of project duration of each response scenario based on contractors perception Table 7.41: Statistics information of all response scenarios based on contractors perception
Statistics Value Trials Mean Median Mode Standard Deviation Variance Skewness Kurtosis Coeff. of Variability Range Minimum Range Maximum Range Width Mean Std. Error Accept Reactive 1 Reactive 2 Reactive 3 Proactive 1-1 Proactive 2 10000 10000 10000 10000 10000 10000 2,830.27 1,510.01 1,638.17 1,638.14 1,914.61 1,552.78 2,875.00 1,510.00 1,645.00 1,645.00 1,954.00 1,581.00 3,415.00 1,510.00 1,645.00 1,645.00 1,954.00 1,581.00 556.52 0.06 29.59 29.65 80.53 102.86 309,709.08 0.00 875.61 878.89 6,484.94 10,580.75 -0.02 3.99 -4.10 -4.09 -1.55 -3.86 1.13 -0.57 17.81 17.74 3.42 16.49 0.20 0.00 0.02 0.02 0.04 0.07 1,780.00 1,510.00 1,510.00 1,510.00 1,750.00 1,020.00 3,415.00 1,510.27 1,645.00 1,645.00 1,954.00 1,581.00 1,635.00 0.27 135.00 135.00 204.00 561.00 5.57 0.00 0.30 0.30 0.81 1.03
205
1.000 CS-Accept
.500
CS-Reactive-3
Figure 7.47: Cumulative distribution of project duration of each response scenario based on consultants perception Table 7.42: Statistics information of all response scenarios based on consultants perception
Statistics Value Trials Mean Median Mode Standard Deviation Variance Skewness Kurtosis Coeff. of Variability Range Minimum Range Maximum Range Width Mean Std. Error Accept Reactive 1 Reactive 2 Reactive 3 Reactive 4 Reactive 5 10000 10000 10000 10000 10000 10000 1,766.34 1,638.45 1,638.26 1,520.79 1,574.14 1,510.01 1,780.00 1,645.00 1,645.00 1,523.50 1,591.00 1,510.00 1,780.00 1,645.00 1,645.00 1,523.50 1,591.00 1,510.00 59.18 29.00 29.40 5.41 32.88 0.06 3,502.44 841.13 864.13 29.23 1,081.32 0.00 -4.10 -4.20 -4.13 -1.50 -1.44 4.12 17.81 18.67 18.09 3.24 3.07 -3.55 0.03 0.02 0.02 0.00 0.02 0.00 1,510.00 1,510.00 1,510.00 1,510.00 1,510.00 1,510.00 1,780.00 1,645.00 1,645.00 1,523.50 1,591.00 1,510.27 270.00 135.00 135.00 13.50 81.00 0.27 0.59 0.29 0.29 0.05 0.33 0.00 Proactive 1 10000 1,022.33 1,020.00 1,020.00 10.65 113.44 4.35 19.93 0.01 1,020.00 1,071.00 51.00 0.11
206
Duration-Risk Map (Executing Agency) 600 500 Risk (S.D.) (day) 400 300 200 100 0 1000
Proactive 2
207
600
Accept
500 Risk (S.D.) (day) 400 300 200 100 0 1000
208
Land acquisition Mobilization of Subcontractor Mobilization of key staffs Mobilization of key staffs Mobilization of subcontractor Accept Coordination among contractors in JV Conflict among contractors in JV Work progress Progress delay Subcontractor availability Project Date delay
Project
Time extension Coordination among parties Contract clauses Penalty (liquidated damage)
: Executing agencys perception : Contractor s perception
: Consultants perception
Mobilization of subcontractor
Subcontractor availability
Project
Date delay
Mobilization of subcontractor
Increase in cost
: Consultants perception
209
Work progress
Project
Progress delay
Limitation of controllability and communication Inefficiency of staff utilization with unnecessary cost
: Contractors perception
: Consultant s perception
Improving coordination
Mobilization of Subcontractor
Work progress
Project
Progress delay
: Consultants perception
210
Capability of new management staff Enhancing managerial capability of contractors staff Work progress Mobilization of Subcontractor Project Progress delay
: Consultants perception
Contractors Mobilization
Project
Date delay
Work progress
Project
Progress delay
: Contractors perception
: Consultants perception
211
Land Acquisition
Site accessibility
Project
Total delay
Land acquisition
Contractors Mobilization
Project
Date delay
Work progress
Project
Progress delay
Dispute
: Contractors perception
: Consultants perception
212
0
0
5
60
6
72
7
84
8Y
96 M
25 25 25 25 25
9 9 9 9 9
66.2
Mob. of sub Mob. of staff Coord. among CTs Coord. among CTs Cap. of new staff Org. duration
34 34
3 7.3 17.6
Land acq. CTs Mob.
24
0
0
5
60
6
72
7
84
8Y
96 M
25 25 25 25
Org. duration
9 9 9 9
16.3 16.3
Mob. of sub
25.7
18.2
94.2
50.33
4.3 4.3
16.3 16.3
54.6 54.6
34
5.5
24
63.5
Coord. among parties Acquiring time Coord. among CTs Contractual matters
Proactive 2
34
17.8
Land acq. Claim & conflict
51.8
213
0
0
5
60
6
72
7
84
8Y
96 M
25 25 25 25 25 25
Org. duration
9 9 9 9 9 9
58.9 54.6
54.6
Mob. of staff
Mob. of sub & staff; Coord. among CTs Mob. of sub & staff
34
0.1
24
7.14 Summary
This chapter provides the explanation of MRUMP application. From the comparison of all parties views with actual status of case study in the first application, it was found that: consultants view was considered to be the most realistic, overall assessment covered most of major risks and uncertainties actually occurred, and all parties views should be integrated in problem solving process. Risk/uncertainty meeting is proposed as a means in integrating multiple parties views. In this meeting, assessors from all parties and analyst will participate. Analyst will show assessment result and facilitate all assessors in awareness of difference, identification of difference, and solving the difference. From the simulation of meeting in the first application, all parties were enabled to propose possible solution. Based on result of the first application, to proactively solve problem at early stage of construction, executing agency and contractor should cooperatively prepare land acquisition plan and construction schedule.
214
Moreover, the analyst should further conduct analysis of risks and uncertainties associated with this response.
From the second application, it was found that all parties were thinking about possibility of dispute. With this situation, the problem seemed to evolve to uncontrollable and unmanageable stage. Therefore, based on this application, the MRUMP should be applied in preventing the problem as early as possible before the problem become more serious and uncontrollable.
215
Chapter 8
As the ultimate goal, this research aims to overcome these limitations associated with conventional RMPs and MRMP. To achieve this goal, a series of objectives have been set. Following major deliverables have been developed to accomplish these objectives including: 1) risk/uncertainty map, 2) hierarchical structure of risk and uncertainty (HSRU) framewo rk, 3) duration valuation process (DVP), and 4) multi-party risk and uncertainty management process (MRUMP).
The risk/uncertainty map for infrastructure project financed by international lender has been developed to overcome the first fundamental limitation by providing accumulated experience of risks and uncertainties as knowledge base. Then, we can reduce the error
216
due to ignorance of risks and uncertainties and deal with risks and uncertainties better. The unnecessary and insufficient risk identificatio n process and inefficient risk structuring process of (M)RMP as technical limitations are improved by development of HSRU framework. HSRU framework is a standard and organized risk structuring diagram aiming to assist practitioners in better assessment and analysis of probability and impact of risks and uncertainties. The cause and effect events are hierarchically separated in HSRU along with the flow of source of risk/uncertainty, consequent risk/uncertainty, influential risk/uncertainty, activity, and type of delay. Second, to overcome the constraint in interpreting dimensionless output of (M)RMP, the DVP has been developed. DVP aims to provide logical and systematic assessment procedure of probability and impact and to offer dimensional presentation of output in form of cumulative distribution of project duration. The developed DVP consists of four main processes consisting of: 1) development of HSRU, 2) assessment and transformation of probability, 3) assessment and transformation of impact, and 4) simulation by using Monte Carlo simulation. To assess probability, DVP designs assessing questions based on basic probability theory such as conditional probability and multiplication rule. Productivity concept, work breakdown structure and scheduling concept, and classification of delay (total delay, date delay and progress delay) are basis in quantification of impact in terms of delay. Based on the HSRU framework and probability and impact assessment procedures in DVP, the illogical and unsystematic probability and impact assessment procedure as a technical limitation of (M)RMP can be improved resulting in higher precision of output. By employing simulation method, the dimensional output in form of cumulative distribution is obtained. With this information, we can know not only expected value (means value) but also minimum and maximum range of project duration. Chapter 5 provides explanation of DVP and its demonstration. To overcome the limitation regarding inattention on involvement of multiple parties, this research improve s the previously proposed MRMP with integration of multiple parties views. From the MRMP application, each partys view for mutual reference could be obtained. However, to obtain reference is just the first step to manage risk in a project. To complete risk management, it is necessary to go through following processes: problem awareness from knowing reference, problem identification through
217
communication among parties, and problem solving by integration of multiple parties views. Therefore, this research develops a prototype tool called multi-party risk and uncertainty management process (MRUMP) aiming to assist all parties in systematically and efficiently managing risks and uncertainties and encourage all parties to communicate each other, identify problem, and cooperatively solve the problem. The HSRU framework, DVP and other processes i.e., response process, application planning process, and application control process are assembled together to form the MRUMP. The MRUMP consists of five main processes including: 1) risk and uncertainty management planning, 2) risk and uncertainty identification and structuring, 3) risk and uncertainty assessment and analysis, 4) risk and uncertainty response, and 5) risk and uncertainty management control.
A number of systematic procedures and tools such as risk/uncertainty breakdown structure (RUBS) and risk/uncertainty checklist are also provided in the MRUMP. The MRUMP is presented in form of implementing manual fo r hands-on application purpose. Chapter 6 provides explanation of the MRUMP manual.
The MRUMP has been applied to an infrastructure project financed by an international lender as a case study located in a Southeast Asian country as the accomplishment of the last research objective. There are at least two major benefits for conducting the application. First, we could discuss its applicability and draw lesson for further refinement from application study. Second, by applying the MRUMP, we could reveal how the project has been being practiced that is beneficial for both practitioners currently working on site and prospective practitioners for future project.
Based on framework of application, the application of this case study was scoped to two periods i.e., early stage of construction and during construction of project. The executing agency, contractor, and consultant involved in the project have been focused 218
as main players in application. The top managements in project level of each party have been selected as assessors and their perceptions have been investigated in the application.
For the application at early stage of construction period, the assessors were asked to identify the risks and uncertainties, which may occur from early stage to current stage of construction, and assess probability and impact of identified risks and uncertainties at the early stage of construction. The reason of this assumption is because we aim to conduct the error analysis by comparing their analysis results with known actual status of project up to current stage.
From the application at the early stage of construction, we could obtain all parties perceptions towards HSRU presenting source of risk/uncertainty, consequential risk/uncertainty, and influential risk/uncertainty associated with activities and project and type of delay. In addition, we could know their perceptions towards probability and impact of risks/uncertainties. Then, by conducing the analysis and simulation, the cumulative distribution of project based on all parties perception could be obtained.
By developing integrated HSRU based on all parties perception, occurring, subsequent, lingering, and future risks and uncertainties could be identified. All parties could compare their perceptions towards the impact of risks/uncertainties to activities by using risk/uncertainty impact chart (RUIC). This chart presents how much project is delayed and how critical path is changed. With this information, the difference of each partys view could be aware.
Moreover, in error analysis, difference is also realized when we compare analysis result of each party with actual status of case study. Assessors experience, knowledge, position and biases resulting in ignorance of risks/uncertainties, and over- and under-estimation of probability and impact could be identified as causations and types
219
of error associated with each source of error. By understanding these sources, causations, and types of error, we can further refine the MRUMP and improve future application.
Additionally, we could observe from the error analysis that we might be able to mitigate error by integrating all parties views, because the comparison shows that one party could provide more realistic assessment of some risks and uncertainties than others and vice versa. By realizing this benefit, the meeting among all parties together with analyst for risk/uncertainty communication and problem solving is simulated to demonstrate how the MRUMP application result can be made use in practice.
From the simulation of meeting, after each party could understand and be aware of others views then, with this reference, it enables all parties to communicate and identify the future problem, which may occur due to different in their views. The integrated HSRU and RUIC can be used for assisting this purpose. Finally, with integration of all parties views, they were enabled to derive the possible and constructive solution that satisfied them as much as possible.
2. Duri ng construction
The second timing period of application is from current stage to the end of construction. The purpose of this application is to discuss the reactive and proactive response scenarios for problems currently occurring in the project. The assessors were asked to provide their perceptions towards created response scenarios and possible future risks/uncertainties based on current situation and contractual condition. Then, response scenario diagrams, which present consequential relationship between created response scenario and risks/uncertainties, have been developed based on their perceptions. With this qualitative analysis, the preferable reactive and proactive responses perceived by each party could be derived.
Furthermore, based on the application result of this case study, we could categorize proposed reactive and proactive response scenarios into two categories i.e., 1) unique response, which was applicable for this specific case study and 2) common response,
220
which was applicable for entire implementation system. By understanding these unique response scenarios, it enabled practitioners to make decision regarding solution to problem more efficient. The common responses as lesson learnt from this project also could be used for further improvement of implementation system. Based on this application, the MRUMP is considered useful and applicable for problem preventing and solving in construction stage. According to practitioners comment on the MRUMP, they perceived its usefulness in using as communication and problem preventing and solving tool among relevant parties during construction stage. In addition to this comment, the lesson learnt from current project could be used as post evaluation information that is beneficial for project implementation reform, policy making and project planning for future projects as well as for inexperienced practitioners.
The importance of multiple parties involvement and contractual role is put into consideration in this research. This research explicitly integrates the multiple parties into the scope and processes. With this integration, a number of benefits can be obtained.
First, by integrating multiple parties views in the scope of MRUMP and simulating meeting for risk/uncertainty communication, understanding among parties toward
221
others views and efficiency of problem solving tend to be enhanced. The MRUMP enables all parties to know each partys view regarding risks and uncertainties. Afterward, it increases the opportunity to communicate each other towards perceived risks and uncertainties and to identify the problem occurring due to difference in their views. Consequently, by integrating all parties, it enables all parties to prepare proactive and reactive measures in responding those prospective risks and uncertainties. This encourages the creation of harmony among project parties that builds cooperative atmosphere and enhance project performance.
Second, by knowing integrated views of all parties, unperceived risks and uncertainties during identification process can be revealed. The integrated HSRU demonstrates this function. Its presentation shows the risks/uncertainties, which may occur and are identified by one party due to the ignorance, but it is identified by other parties. From application of MRUMP, new future risks/uncertainties, subsequent and lingering risks/uncertainties caused by one partys decision and action, and indirect third party related risk/uncertainty were ignored by one party, but they could be identified by other parties.
Third, with RUIC, all parties are able to understand the difference of each partys perception towards the magnitude and characteristic of impact of risks and uncertainties. It provides understanding of how much project is delayed and how critical path of schedule is changed. With this integration, it enables all parties to elaborate the outcome of risks and uncertainties to activities and project more realistically.
Fourth, with due consideration of totally exhaustive issue in development of RUBS and risk/uncertainty checklist, risk/uncertainty categories related to all parties are also included in RUBS and risk/uncertainty checklist. By incorporating all parties in risk and uncertainty identification process, the MRUMP provides objective self evaluation of one party when all parties perceptions are integrated. The application result also illustrates this feature.
222
2. Attention on uncertainty
First, the MRUMP does not neglect the importance of low probability but high impact event, which is called uncertainty here. On the other hand, to prioritize risks, the conventional RMPs normally rely on concept of expected impact that may overlook the importance of this type of event. From application, consultant assessed the mobilization of subcontractor uncertainty as low probability but high impact. With the attention on this type of event in MRUMP, it was not discarded during the analysis. In reality, this event actually occurred.
Second, the possibility of ignorance of risks/uncertainties can be reduced by using the risk/uncertainty map in identifying and structuring risks/uncertainties. From time to time, we are encouraged to accumulate risks/uncertainties from experience and periodically update its structure in order to build structure as complete as possible. We can use it as knowledge base for both experienced and inexperienced practitioners in better dealing with risk/uncertainty in future project, respectively.
Third, the DVP provides cumulative distribution of project objective e.g., duration as information for practitioners in better dealing with uncertainty. By adopting the advantage of simulation, we can know the minimum and maximum range of distribution, which enables us to recognize the worst case scenario (maximum value). Since conventional RMPs normally center the attention on expected value, the worst case scenario is often overlooked.
With DVP, the probability and impact of risks and uncertainties to project objective can be derived logically and systematically. The DVP provides a logical and systematic procedure to assess the probability and impact of risk/uncertainty, which can enhance the reliability of assessment and analysis. For probability, the questions are designed based on basic probability theory such as conditional probability and multiplication rule. The conditional probability is assessed based on developed HSRU. For impact, it is
223
based on classification of delay in assessing variation of duration, w ork quantity and productivity rate associated with project or activity. The dependency between risk/uncertainty and activity are specified based on developed HSRU.
First, the MRUMP enables practitioners to sufficiently prepare for proactive and reactive management measures to prospective risks and uncertainties with consideration of contractual condition among parties. Here, risk and uncertainty management is viewed as both problem preventing and solving tools. Therefore, the managerial response scenarios are created based on timing of implementation and divided into two categories i.e., 1) proactive managerial response scenario and 2) reactive managerial response scenario. For proactive managerial response scenario, it is related to planning and monitoring functions in management. For reactive managerial response, it is related to controlling function in management. In developing response scenario, the contractual issue is also considered as decision variable or nominal value depending on the stage of project.
Second, since this research realizes the necessity of lesson learnt and feedback system for future project, the initiated managerial responses scenario are grouped into 1) common response, which is applicable for entire implementation system or several projects and 2) unique response, which is particular to the problem in that focused project. With this way of categorization, it can facilitate the practitioners in understanding areas of improvement of implementation system and cautions for particular project. The derived response scenarios from application illustrate this benefit.
Conclusively, based on holistic view, overall contributions attempt to assist all parties in better dealing with risks and uncertainties. Moreover, all parties are encouraged to identify and solve the problem due to possible and potential risks and uncertainties before it eventually becomes unmanageable to all parties and threat to project performance. With this consideration, the MRUMP is considered as proactive more than
224
reactive tool in problem solving process, though it can be used as both purposes.
The first recommendation for further research is related to refinement of probability and impact assessment procedure in the DVP. According to application of the MRUMP in this research, one of source of error is associated with the bias of assessors. More study may be done by incorporating more other techniques in eliciting probability. Additionally, to refine this procedure, the scope of study should be extended to cover the psychological issues.
Second, to overcome the interpretation difficulty of dimensionless output of (M)RMP, this research firstly focuses on project duration by trying to transform subjectively assessed impact to impact in terms of project delay. By employing simulation technique, the DVP can produce cumulative distribution of project duration as a main output. By focusing on only time objective may not be necessary sufficient to have the complete view of impact of risks and uncertainties. Next, this research recommends that cost objective should be focused. Based on the framework of DVP development, cost valuation process (CVP) should be developed. Afterward, both DVP and CVP should be used jointly in transforming dimensionless impact in order to enhance our understanding of magnitude of impact associated with risks and uncertainties.
Third, for the application purpose, this research presents the MRUMP in form of implement ing manual. Since this is the first prototype, various standardized forms and examples of inputs and outputs are not completely provided. Further study may improve and refine explanation and presentation of inputs, processes and outputs described in MRUMP implementing manual. Moreover, with consideration of benefit of information technology, the software based on the framework of MRUMP may be developed in order to enhance the efficiency in application of MRUMP.
225
In this research, the scope of MRUMP application has been framed only in the construction stage for problem preventing and solving purposes. Expectedly, the practitioners may employ the MRUMP in other application purposes such as policy making and planning, negotiation in contract formation, alternative dispute solution (e.g., mediation and dispute review board) in both pre- and during construction stages of project. Further research may be conducted to apply the MRUMP for other application purposes. Then, its applicability in these areas should be discussed.
226
References
Abrahamson, M.: Contractual Risks in Tunneling: How they should be Shared, Tunnels and Tunneling, November, pp. 587-598, 1973.
ADB, Post Evaluation Report for Thailand, Asian Development Bank, 1999.
Af Wahlberg, A. E., The Theoretical Features of Some Current Approaches to Risk Perception, Journal of Risk Research, 4 (3), pp. 237-250, 2001.
Al-Bahar, J. F. and Crandall, K. C.: Systematic Risk Management Approach for Construction Projects, Journal of Construction Engineering and Management, Vol. 106, No. 3, September: 533-546, 1990.
Aleshin, A.: Risk Management of International Projects in Russia, International Journal of Project Management 19, 207-222, 2001.
Ang, A. H-S. and Tang, W. H., Probability Concepts in Engineering Planning and Design, Volume 1 Basic Principles, John Wiley & Sons, Inc., US, 1975.
APM, Project Management Body of Knowledge, Fourth Edition, Edited by Dixon, M., Association for Project Management, UK, 2000.
Axelrod, L. J., Mcdaniels, T. and Slovic, P., Perceptions of Ecological Risk from Natural Hazards, Journal of Risk Research, 2 (1), pp. 31-53, 1999.
Baker, S., Ponniah, D., and Smith, S., Risk Response Techniques Employed Currently for Major Projects, Construction Management and Economics, 17, pp. 205-213, 1999.
Ben-Haim, Y. and Laufer, A., Robust reliability of projects with activity-duration uncertainty, Journal of Construction Engineering and Management, Vol. 124, No. 2, March/April, pp.125-132, 1998. 227
Benjamin, J. R. and Cornell, C. A., Probability, Statistics, and Decision for Civil Engineers, McGraw-Hill Book Company, US, 1970. Bordoli, D. W. and Baldwin, A. N., A methodology for assessing construction project delays, Construction Management and Economics, Vol. 16, pp.327-337, 1998.
Bubshait, A. A. and Cunningham, M. J., Comparison of Delay Analysis Methodologies, Journal of Construction Engineering and Management, Vol. 124, No. 4, Jul/August, 1998.
Carter, R. L. and Doherty, N. A., Handbook of Risk Management, Kluwer-Harrap Handbooks, London, 1974.
Chan, D. W. M. and Kumaraswamy, M. M., Modeling and predicting construction durations in Hong Kong public housing, Construction Management and Economics; Vol. 17, No. 3, May, pp.351-362, 1999. Chapman, C. and Ward, S.: Project Risk Management: Process, Techniques and Insights, John Wiley & Sons, Inc., Canada, 1997.
Cha, Y., Risk Perception in Korea: a Comparison with Japan an the United States, Journal of Risk Research, 3 (4), pp. 321-332, 200
Chicken, C. J. and Posner, T., The Philosophy of Risk, Thomas Telford, London, UK, 1998.
Dawood, N., Estimating project and activity duration: a risk management approach using network analysis, Construction Management and Economics; Vol. 16, No. 3, May, pp.41-48, 1998.
228
Devore, J. L., Probability and Statistics for Engineering and the Sciences, 5th Ed., Thomson Learning, US, 2000.
Duncan, W. R.: A Guide to the Project Management Body of Knowledge, Project Management Institute, 1996.
Edwards, L., Practical Risk Management in the Construction Industry, Thomas Telford Publications, London, 1995.
Edwards, P. J. and Bowen, P. A.: Risk and Risk Management in Construction: Review and Future Directions for Research, Engineering Construction and Architectural Management, Vol. 5, No. 4, pp. 339-349, 1998.
Elsden, J. P.: Utilities The Unmanageable Risk, the International Construction Law Review, Vol. 18, Part 2, April, pp. 476-484, 2001.
Fife-Schaw, C. and Rowe, G., Extending the Application of the Psycho metric Approach for Assessing Public Perceptions of Food Risk: Some Methodological Considerations, Research Note, Journal of Risk Research, 3 (2), pp. 167-179, 2000.
FIDIC, Risk Management Manual, International Federation of Consulting Engineers (FIDIC), Switzerland, 1997.
Fisk, R. E.: Construction Project Administration, 5ed., Prentice-Hall Inc., Upper Saddle River, New Jersey, 1997.
Flanagan, R. and Norman, G.: Risk Management and Construction, Blackwell Scientific Publications, UK, 1993.
Godavitarne, C.: World Bank Concerns, Policies and Practices Related to Procurement and Contract Management, International Conference on Contract management in Construction Industry, Delhi, India, pp. 55-59, 1995.
229
Greene, A., Root, D., and Thorpe, T., The Comfort Blanket of Risk Assessment: An Investigation into the Subjective Assessment of Risk, Proceedings of the 16th Association of Researchers in Construction Management (ARCOM) annual conference, 6th 8th September, 2000, Glasgow Caledonian University, Glasgow, Scotland, 1: 241-249
Grey, S., Practical Risk Assessment for Project Management, John Wiley & Sons Ltd, 1995.
Griffis, F. H. and Farr, J. V. (2000) Construction planning for engineers, McGraw-Hill Companies, Inc., Singapore.
Haimes, Y. Y.: Risk Modeling, Assessment, and Management, John Wiley & Sons, Inc., Canada, 1998.
Hartman, F. and Snelgrove, P.: Risk Allocation in Lump-Sum Contracts: Concept of Latent Dispute, Journal of Construction Engineering and Management, Vol. 122, No. 3, September, pp. 291-296, 1996.
Hayashi, L. A., Handbook on Problems in Procurement for Projects Financed by the Asian Development Bank, Central Projects Services Office, Asian Development Bank, October, 1986.
Healy, N. J., Risk Management in Giant Civil Engineering Projects, Thesis presented to the University of Manchester Institute of Science and Technology, 1981
Hillson, D., The Risk Breakdown Structure (RBS) as an Aid to Effective Risk management, Presented at the Fifth European Project Management Conference, PMI Europe 2002, Cannes France, 19-20 June 2002, organized by PMI France-Sub.
230
Holloway, C. A., Decision Making under Uncertainty: Models and Choices, Prentice-Hall, US, 1979.
Hornby, A. S., Oxford Advanced Learners Dictionary of Current English, Fifth Edition, Editor: Crowther, J., Oxford University Press, Clays Ltd, England, 1995.
Hull, J. K. (1990) Application of risk analysis techniques in proposal assessment, Project Management, Vol. 8, No. 3, August, pp.152-157.
Ichikawa, H.: Dealing with Utilities during Construction in Major Cities in Japan, the International Construction Law Review, Vol. 18, Part 2, April, pp. 485-491, 2001. ICE, Risk Analysis and Management for Projects, Institution of Civil Engineers and the Faculty and Institute of Actuaries, Thomas Telford, UK, 1998.
Isidore, L. J., Back, W. E. and Fry, G. T., Integrated probabilistic schedules and estimates from project simulated data, Construction Management and Economics; Vol. 19, No. 4, July, pp.417-426, 2001. Jaafari, A. : Management of risks, uncertainties and opportunities on projects: time for a fundamental shift, International Journal of Project Management, Vol. 19, pp. 89-101, 2001.
Kahkonen, K. and Huovila, P., (1996). Systematic Risk Management in Construction Project, VTT Building Technology, P.O. Box 1801, SF-02044 VTT, Finland URL:http://web.bham.ac.uk/d.j.crook.lean/iglc4/huovila/risk2.htm
Kangari, R. and Riggs, L. S. (1989) Construction risk assessment by linguistics, IEEE Transactions on Engineering Management, Vol. 36, No. 2, May, pp.126-131.
Kumaraswamy, M. M.: Appropriate Appraisal and Apportionment of Megaproject Risks, Journal of Professional Issues in Engineering Education and Practice, Vol. 123, No. 2, April, 1997.
231
Levitt, R. E. and Ashley, D. B.: Allocating Risk and Incentive in Construction, Journal of the Construction Division, Vol. 106, No. CO3, September: 297-305, 1980.
Loyd, L. H.: The Grove Report: the Background to the Conference on Whose Risk?, the International Construction Law Review, Vol. 18, Part 2, April, pp. 302-311, 2001.
Lu, M. and AbouRizk, S. M., Simplified CPM/PERT simulation model, Journal of Construction Engineering and Management, Vol. 126, No. 3, May/June, pp.219-226, 2000. Macdonald, C. C.: Allocation of Risk in Major Infrastructure Projects Why do we get it so wrong?, the International Construction Law Review, Vol. 18, Part 2, April, pp. 345-352, 2001.
Marriott, A, QC.: Whose Risk? Reforming the Construction Industry in Hong Kong, the International Construction Law Review, Vol. 18, Part 2, April, pp. 312-323, 2001.
Mulholland, B. and Christian, J. (1999) Risk assessment in construction schedule, Journal of Construction Engineering and Management, Vol. 125, No. 1,
January/February, pp.8-15.
Niwa, K.: Knowledge-Based Risk Management in Engineering: A Case Study in Human-Computer Cooperative Systems, John Wiley & Sons, Inc., Canada, 1989.
Ogunlana, S. O., Chareonngam, C. and Tabucanon, M. T. (1995) Planning strategy and risk management for a high-risk project, Engineering Magazine, Vol. 48, No. 10, October, pp.58-66, 1995. Papageorge, T. E.: Risk Management for Building Professionals, R. S. Means Company, Inc., US, 1988.
Perry, J. G. and Hayes, R. W., Construction Projects-Know the Risks, CME, Charted Mechanical Engineer, London, Vol. 32, No. 2, February, pp. 42-45, 1985.
232
Pipattanapiwong, J., Multi-party Risk Management Process (MRMP) for a Construction Project Financed by an International Lender, Master Thesis No. ST-00-43, Asian Institute of Technology, 2000.
Pipattanapiwong, J. and Watanabe, T.: Multi-party Risk Management Process (MRMP) for a Construction Project Financed by an International Lender, Proceedings of the 16th Association of Researchers in Construction Management (ARCOM) annual conference, 6th 8th September, 2000, Glasgow Caledonian University, Glasgow, Scotland, 1: 219-228.
Pipattanapiwong, J. and Watanabe, T. : Risk Management for an International Project: a Case Study of Infrastructure Construction Project Financed by the Asian Development Bank (ADB) in Thailand, Proceedings of the 18th Annual Forum on Construction Management Issue, JSCE, Tokyo, Japan, pp. 207-216, 2000.
Pipattanapiwong, J. and Watanabe, T., Review of risk management for an infrastructure construction project. In: Proceedings of the 24th JSCE Conference on Infrastructure Planning, 23rd25th November 2001; Kochi University of Technology, Japan.
Pipattanapiwong, J., Watanabe, T. and Kusayanagi S., Applicability of Multi-party Risk Management Process (MRMP), Proceedings of the 57th JSCE Annual Conference, 25th 27th September, 2002, Hokkaido University, Hokkaido, Japan.
Pipattanapiwong, J., Ogunlana, S. and Watanabe, T., Multi-party risk management process for a public-private partnership construction project in Asia. In: Akintoye, A., Beck, M., and Hardcastle, C., eds. Public private partnerships: managing risks and opportunities, UK: Blackwell Science Ltd, 2003; 353-368
Pipattanapiwong, J. and Watanabe, T., Sources of error in conventional risk management process, Proceedings of the 58th JSCE Annual Conference, 24th 26th September, 2003, Tokushima University, Tokushima, Japan.
233
Pipattanapiwong, J. and Watanabe, T., Risk and Impact Valuation Process to Project Duration, The International Symposium on Construction and Project Management, Human Resources Development under Glocalization, 16th 17th October, 2003, JSCE, Tokyo, Japan.
Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide) 2000 Edition, Project Management Institute, Four Campus Boulevard, Newtown Square, PA19073-3299 USA, 2000.
Raftery, J. : Risk Analysis in Project Management, E & FN SPON, An Imprint of Chapman & Hall, London SE1 8HN, UK, 1994.
Ranasinghe, M. and Russell, A. D., Analytical approach for economic risk quantification of large engineering projects: validation, Construction Management and Economics; Vol. 10, pp.45-68, 1992. Schuyler, J. R., Decision Analysis in Projects, Project Management Institute, 1996.
Shapira, Z.: Risk Taking: A Managerial Perspective, Russell Sage Foundation, US, 1995.
Shi, J. J., Cheung, S. O., and Arditi, D., Construction delay computation method, Journal of Construction Engineering and Management, Vol. 127, No. 1, January/February, pp.60-65, 2001. Slovic, P., Perception of Risk, Science, 236, pp. 280-285, 1987.
Strauss, M. W., Evaluating Influence Diagrams, Operations Research, Vol. 34, No. 6, Novemeber-December, pp. 871-882, 1979.
Tah, J. H. M. and Carr, V., Information Modeling for a Construction Project Risk
234
Management System, Engineering, Construction and Architectural Management, 7 | 2, pp. 107-119, 2000.
Thompson, P. and Perry, J., Engineering Construction Risks: A Guide to Project Risk Analysis and Risk Management, Thomas Telford, London, 1992.
Twigger-Ross, C. L. and Breakwell, G. M., Relating Risk Experience, Venturesomeness and Risk Perception, Journal of Risk Research, 2 (1), pp. 73-83, 1999.
Vaughan, E. J. : Risk Management, John Wiley & Sons, Inc., US, 1997.
Vuong, T. and Watanabe, T. (2001) Risk analysis models for project cost and duration in Vietnamese construction projects. In: Alum A. K. M. et al. ed. (2001) Proceeding of the Third International Conference on Construction Project Management: From Fragmentation To Integration; Mar 29-30; Singapore. pp.337-347.
Wang, M. and Chou, H., Risk Allocation and Risk Handling of Highway Projects in Taiwan, Journal of Mana gement in Engineering, Vol. 19, No. 2, April 1, 2003.
Wang, W. C. and Demsetz, L. A., Model for Evaluating Networks under Correlated Uncertainty NETCOR, Journal of Construction Engineering and Management, Vol. 126, No. 6, November/December, pp. 458-466, 2000.
Wang, W. C. and Demsetz, L. A., Application Example for Evaluating Networks Considering Correlation, Journal of Construction Engineering and Management, Vol. 126, No. 6, November/December, pp. 467-474, 2000.
Ward, S. C., Chapman, C. B., and Curtis, B.: On the Allocation of Risk in Construction Projects, International Journal of Project Management, Vol. 9, No. 3, August, pp. 140-147, 1991.
235
Ward, S. and Chapman, C.: Transforming Project Risk Management into Project Uncertainty Management, Internatio nal Journal of Project Management, 21, pp. 97-105, 2003.
Wideman, R. M. : Project & Program Risk Management: A Guide to Managing Project Risks and Opportunities, Project Management Institute, 1992.
Williams, T. M. : The Two-Dimensionality of Project Risk, International Journal of Project Management, Vol. 14, No. 3, pp. 231-237, 1996.
Yamaguchi, H., Uher, T. E. and Runeson, G.: Risk Allocation in PFI Projects, Proceedings of the 17th Association of Researchers in Construction Management (ARCOM) annual conference, September, 2001, University of Salford, UK, pp: 885-894.
Zhi, H., Risk Management for Overseas Construction Projects, International Journal of Project Management, Vol. 13, No. 4, pp. 231-237, 1995.
236