Chhuba HEP Final Civil Design
Chhuba HEP Final Civil Design
Chhuba HEP Final Civil Design
\
|
=
2gE .L. .C .E E
Q
B Weir, Trench of Width
d 2 1
=
2gE .L. .C .E E
Q
B Weir, Trench of Width
d 2 1
=
Check for Discharging Capacity of Trench Weir
Length of Water Way: 15.0 m
Design Discharge: 3.66 cumec
Top Width of Trench (T): 1.25 m
Let the water depth along the section of channel be "d"
Area A = T x d = 1.25 x d
Velocity head at the end of the Trench (H
v
)
Where "n" is a constant depending on bottom profile of Trench = 0.5
Velocity head (H
v
): 0.27 d
3.658 = 4.6d^(3/2)
d = 0.86 m
Say 0.9 m.
Depth of Trench provided at Intake Location: 2.10 m
The Provided Depth of Trench at start: 1.10 m
Hence, provide waterway of 1.1 m at the start of the trench increasing to 2.1 m towards the intake end.
The bed slope of Tranch weir shall be proposed as 1V:15H
Check for Adequacy of Waterway
Average Depth of Trench = (1.1 + 2.1 )/2 m = 1.60 m
Average Flow Area = 1.25 x 1.6 sq.m = 2.00 Sq.m
Wetted Perimeter = (2 x 1.6 )+ 1.25 m = 4.45 m
Bed Slope of Trench = (2.1 - 1.1)/15 = 0.0667
Discharging Capacity of Trench, Q = 16.83 cumec > 3.658 cumec, Hence, adequate.
Check for Adequacy of Capacity with 50% Area Clogged
Average Depth of Trench = 1.6 /2 m = 0.80 m
Average Flow Area = 0.8 x 1.25 sq.m = 1.00 Sq.m
Wetted Perimeter = (2 x 0.8 )+ 1.25 m = 2.85 m
Bed Slope of Trench = (2.1 - 1.1)/15 = 0.0667
Discharging Capacity of Trench for 50 % clogging, Q
50
=
7.14 cumec > 3.658 cumec, Hence, adequate.
Using Manning's formula with value of n = 0.018,
Q = A2gHv = 2d(2g0.27 d)
1.25 x 2
2d
.
1 0.5
0.5
Hv
+
=
2T
A
.
1 n
n
Hv
+
=
Input Data
Design Discharge for Power = 2.36 cumec
Flow Required for Silt Flushing in Desilting tank= 20%
Flow required for leakage and overloading = 15%
Total Design Discharge = 3.19 cumec
Restricted Velocity = 2.0 m/s
Rugosity Coeffieicent = 0.018
Average Bed Level at Weir = El.1311.0 m
Length of intake channel = 137.00 m
Intake Channel Design
Area required = Q/V = 3.19/2= 1.59 Sq.m
Providing Base Width, B = 2.00 m
Providing depth, D = 1.00 m
Cross sectional area provided = B x D = 2.00 Sq.m
Velocity = 1.59 m/s
Wetted perimeter = 2D + B = 4.00 m
Wetted radius = 0.50 m
S
1/2
= 0.046
S= 0.002
= 1 in 500
Invert level of intake Channel at trench weir = El.1308.90 m
Invert level of intake Channel at Starting of desilting tank = 1308.9 - 137 x 0.002
= El.1308.60 m
Hydraulic Design of Intake Channel
Input Data
Design Discharge for Power = 2.36 cumecs
Flow Required for Silt Flushing = 20%
Flow required for leakage and overloading = 15%
Average Design Discharge, Q = 2.95 cumecs
Particle size to be removed= 0.20 mm and above
Flow velocity, v
f
= 0.22 m/s
Settling velocity,v
s
= 2.75 cm/s
Length of bypass Channel including transition= 51.00 m
Design Calculation:
Width proposed, W= 4.50 m
Depth required, D = Q/(W x vf)= 2.90 m
Adopted depth , D = 3.00 m
Hence, horizontal velocity = Q/(W x D) = 0.22 m/s
Moderated settling velocity, v
m
= v
s(
(1 - 0.132)/(D^(0.5)))
= 2.54 cm/s
= 0.025 m/s
Settling length = (flow through velocity/moderate settling velocity) x depth
= 25.80 m
Say = 26.00 m
Invert Level of HRP at intake = 1308.6 - 51 x 0.002
= El.1308.50 m
Provide 26 m long settling basin with trapezoidal bottom and silt gutter of 600 mm x 600 mm.
Hydraulic Design of Desilting Tank
The connection between the rectangular channel and desilting basin at inlet has been provided by way of 3.5m long expansion transition and outlet by way of 3.5 m
long contraction transition.
Input Data
Design Discharge for Power = 2.36 cumec
Flow required for leakage and overloading = 15%
Total Design Discharge for HRP, Q = 2.71 cumec
Rugosity coefficient = 0.012
Allowable velocity = 2.0 m/s
Length of HRP = 2291.00 m
Invert level of HRP at entry = El.1308.50 m
Design Calculation:
Invert level of HRP at forebay = El.1304.30 m
Applying Manning's formula
where,
V =allowable velocity = 2.00 m/s
N= Manning's coefficient = 0.012
R=hydraulic mean depth
S=bed slope of the HRP = 0.0018 545.4761905
= 1 in 540
Thus,
R=(V x N/S
1/2
)
3/2
= 0.42 m
Check for discharging capacity of the pipe
Assumed D= 1.50 m
Assumed Radius = 0.75 m
Assuming depth of flow, d = 0.80 D
= angle projected by unwetted perimeter at the center of the pipe
B
A C
h= unwetted height above FSL = D (1- 0.8) = 0.30 m
wetted height above c/l of pipe, h
1
= D/2 - h = 0.450 m
Let D be the diameter of the Head Race Pipe.
Hydraulic Design of Head Race Pipe
+ + = |
|
| tan 1 . 1
cos 2
1
0847 . 0 tan 21 . 1
2
1
D H
(
+
|
|
.
|
\
|
= |
|
tan 077 . 0
cos
791 . 0
2
D H
Width of Transition (b
e
) = 1.00
D = Diameter of Pressure Shaft = 1.00
(1.1 D)
2
= 1.21 (1.1 D) = 1.10 m
(0.291D)
2
= 0.08 (0.291D) = 0.29 m
Therefore the equation of Entrance Profile for the Roof and floor will be,
X
2
Y
2
1.21 0.08
Section
b
e
= Width of Transition = 1.00
(0.55 b
e
)
2
= 0.30
(0.2143 b
e
)
2
= 0.05
Therefore the equation of Entrance Profile for the Side flare will be,
X
2
Y
2
0.30 0.05
(0.55 b
e
) = 0.55 m
(0.2143 b
e
) = 0.21 m
1.42 m
2.24 Sq.m Hence Ok
Where,
2.71 m/s
0.866 > 0.33
2.30 m
1300.20
MDDL = 1302.50
1300.20
1299.41
0.50
Design for spillway forebay
Q = CLH
3/2
Where,
Design discharge,Q = 2.71 cumec
Coefficient of discharge,C = 1.7
H= 0.50 m
Thus,
L= Q/(CH
3/2
)
L= 4.52 m
Approach Apron at Bellmouth Entrance = m
m
Elevation of CL of Intake = m
Bottom Level of the Bellmouth Entrance = m
In order to prevent vortices formation, sufficient submergence depth (h) has to be maintained above the central line of intake. The Criteria
V = Velocity at Entrance of the Intake =
Froude Number (F) =
Submergence Required (h) =
Submergence Required above c/l of Intake = m
Width of the Intake at Entrance
Plan
Width of the Intake = [b
e
+2(0.2143b
e
)] =
Provided Area at Entrance of Intake =
Minimum Submergence:
Details of side flaring entry in plan
Where,
m
'1
The inlet should be streamlined to minimise the losses. The profile of roof and floor should approximate to that of a jet from the horizontal
Where,
m
'1
m
Geometry of Bellmouth Entrance in Roof, Floor and Side Flares
( ) ( )
1
291 . 0 1 . 1
2
2
2
2
= +
D
Y
D
X
( ) ( )
1
2143 . 0 55 . 0
2
2
2
2
= +
e e
b
Y
b
X
gD
V
F Number Froude = ) (
Economical diameter of Penstock by Sarkaria's formula
where,
Q = 2.71 cumec
H=net head = 1305.50 m
hence,D = 0.46 m
Providing length of spillway of 4.6 m.
Chhuba SHEP (7 MW), Sikkim - Head Loss
Head Loss in Intake Channel
Length of Intake Channel = 137.00 m
Friction Loss in Intake Channel
H
IC
=
V= 1.6 m/s
N= 0.016
R=
Head Loss in Bypass Channel
Length of Bypass Channel = 51.00 m
Friction Loss in Bypass Channel
H
BPC
=
V= 1.6 m/s
N= 0.016
R=
Head Loss in HRP
Length of HRP = 2291.00 m
Friction Loss in HRP
H
HRP
=
V= 1.79 m/s
N= 0.012
R=
Total major head loss upto forebay =
Minor head losses upto forebay =
=
Total head loss from HRP to forebay Structure = 4.11 m
Invert Level of HRP at forebay = 1304.30 m
1305.50 m
25%
3.29 m
0.82 m
0.46 m
Thus, friction loss in Head Race Pipe= 2.98 m
0.50 m
Thus, friction loss in intake channel, H
BPC
= 0.08 m
L= 2291.00 m
0.50 m
L= 51.00 m
HFL at forebay =
Thus, friction loss in intake channel, H
IC
= 0.22 m
L= 137.00 m
Head Loss in Penstock
1. Friction Loss in Penstock
Length of Penstock= 981.00 m
Friction Loss in Penstock
V= 3.5 m/s
N= 0.012
R=
Thus, friction loss in Penstock, H
P
=
2. Entrance Loss
where,
K
en
= 0.5
2.7 m/s
Thus, entrance loss in the penstock =
3. Trash rack Loss
where,
K
tr
= 0
2.7 m/s
Thus, trash rack loss in the penstock =
4. Bend loss
where,
K
b
= 0.16
No. of bend = 17
3.5 m/s
Thus, bend loss in the penstock =
5. Valve Loss
a. Gate valve loss
where,
K
gv
= 0.5
3.5 m/s
Thus, gate valve loss in the penstock =
b.Butterfly valve loss
where,
K
bv
= 0.5
3.5 m/s
Thus, butterfly valve loss in the penstock =
6. Transition and Bifurcation loss =
Total head loss in penstock = 13.66 m
Turbine Centre Line Level = 960.00 m
Gross Head = 345.50 m
Net Head = 331.84 m
V=
0.30 m
0.50 m
V=
0.30 m
V=
1.66 m
0.00 m
V=
V=
0.19 m
H
P
=
L= 981.00 m
0.25 m
10.71 m
Chhuba SHEP (7 MW), Sikkim
ECONOMICAL DIAMETER OF PENSTOCK. (As per IS 11625-1986)
Input Data:
1558.000 Rs/m
3
5509.000 Rs/m
3
3.50 Rs
150.000 Rs/Kg
0.910
0.950
1305.500 m
960.000 m
345.880 m
0.011
0.540
2.71 m
3
/sec
2 Nos
1.36 m
3
/sec
130 N/mm
2
D
22/3
= 1.42110324
D = 1.00 m
1.00 m
Economical diameter of Penstock is Given by,
Result:
The Economical Diameter of the Penstock is :
Annual Load factor (p
f) :
Design Discharge :
No. of Units :
Discharge through penstock (Q) :
Permissible stress for IS 2002-Grade 3 Material (a) :
From IS 11625-1986, Clause No.6
Ratio of annual fixed Operatiion and maintenance charges
to construction cost of penstock (p) :
0.015
Joint efficiency of Penstock (e
j
) :
Percentage by which the Head is increased due to Water
Hammer :
11%
Full Reservoir Level (FRL) :
Level Of the Center line of Penstock :
Head on penstock including Water Hammer (H) :
Percentage by which the steel in penstock is overweight
due to provision of stiffeners,Corrosion allowance,etc (i) :
0.025
Rugosity coefficient in Manning's formula (n) :
Overall efficiency of Plant (e) :
Unit cost of Excavation (Ce) :
Unit cost of Concrete lining (Cc) :
Cost of 1Kwh Energy (Cp) :
Cost of Steel (Cs) :
p
e
i HCs
Cc Ce
Cp ep n Q
D
j a
f
(
(
+
+ +
=
.
) 1 ( 121
6 . 0 39 . 1
* * * * 10 * 36 . 2
2 3 6
3
22
o
Chhuba SHEP (7 MW), Sikkim - Hydraulic Design of Penstock
Input Data
Design Discharge for Power generation = 2.36 cumec
Flow required for overloading and leakage = 15%
Total Design Discharge for Penstock, Q = 2.71 cumec
Rugosity coefficient = 0.012
Limiting velocity in Penstock = 4.0 m/s
FSL at forebay = 1305.50 m
Thickness of steel liner, t = 18 mm (assumed)
Time Constant (Closure time) = 12 s
Length of penstock = 981.00 m
C/L of turbine = 960.00 m
Diameter of Penstock Before Banifold:
Area of Penstock required = Q/V = 0.68 Sq.m
D = 0.93 m
Hence, adopted D = 1.00 m
Thus, area provided = 0.79 Sq.m
Diameter of Penstock After Bifurcation:
Area of Penstock required = (Q/2)/V = 0.34 Sq.m
D = 0.66 m
Thus, dia = 0.70 m
Let D be the diameter of the Penstock before bifurcation.
Hence, provide 1 m as the diameter of the penstock.
Let D be the diameter of the Penstock after bifurcation.
Hence, provide 0.7 m as the diameter of the penstock.
Thickness of Penstock
FSL at forebay = 1305.50 m
C/L of turbine = 960.00 m
Internal steady head, h
1
= FSL - c/l of turbine =
345.50 m
v = Q/A = 3.5 m/s
Ratio of dia. of penstock to thickness of steel liner = 55.56
Refering to Allevi's Chart
a = 3800
Pipe line constant (in ft units) = (av)/(2gh
1
)
= 0.60
Time constant (in ft units)= (aT)/(2L)
= 7.08
Ratio fo pressure rise to initial steady state = 2 x K x P
P (as being measured from the graph) = 0.09
Hence,
2 x K x P = 2 x 0.6 x 0.09
= 11%
Initial Steady head = 345.50 m
Add for water hammer = 11% of steady head = 38.01 m
Total head = 383.51 m
Design of thickness of Penstock
Thickness = (PD)/(2)
where P=
= H
= 1000.00 kg/m3
H = 383.51 m
Thus, P= 383505 kg/m2
D= diameter of the Penstock = 1.00 m
= Permissible stress in Penstock = 130 MPa
= 13000000 kg/m2
Hence,
Thickness of Penstock = (PD)/(2) = 0.01475 m
= 1.475 cm
Adding 2mm for corrosion = 1.7 cm
Adopted thickness of the penstock = 18 mm
water pressure with 11 %
pressure rise
(Allevi's Chart -fig. 8.33, Manual on Development of Small Hydroelectric Projects -
design of Civil Works, page - 139.)
Chhuba SHEP (7 MW), Sikkim - Tail Race Channel
Input data:
Design discharge: 2.36 cumec
Flow for overloading: 15%
Design with 15 % overlaoding : 2.71 cumec
Provided base width: 3.50 m
Provided depth: 1.00 m
Rugosity coefficient: 0.018
Velocity limit: 1.50 m/s
Area = 3.50 sq.m
Velocity = 0.78 m/s
Wetted Perimeter = 5.50 m
Hydraulic radius = 0.64 m
Using Manning's formula
S
1/2
= 0.0255
S= 0.0007
= 1 in 1538
Provide slope of 1 in 1538
Design Calculation: