Pile Driving
Pile Driving
Pile Driving
Lesson 7
7-1
7-1
Student Manual
Learning Outcomes
Monitor and verify proper marking of the piles per contract documents and standards Verify & document contractor compliance with applicable tolerances Monitor, verify and document pile driving operations Identify applicable 455 specifications
7-2
7-2
Student Manual
Inspectors Role
Verify Contractor Compliance with Project Plans and Specifications Monitor and Maintain Record of Driving Determine When to Stop Driving
7-3
As discussed earlier, the Inspector has numerous responsibilities throughout the pile driving operations. During this phase of pile driving, the Inspector needs to verify compliance with the project Plans and Specifications for pile plan location, axial alignment and record the driving event. During the driving of the pile, there are specific duties, such as hammer and pile cushion inspection, together with the recording of the operation, blows, stroke height/pressure, etc.
7-3
Student Manual
Inspectors Checklist
7-4
A full size checklist is at the end of this lesson and in the Appendices.
7-4
Student Manual
7-5
Student Manual
455-5.15.2 Position: Ensure that the final position of the pile head at cut-off elevation is no more than 3 inches laterally in the X or Y coordinate from the plan position indicated in the plans. 455-5.15.3 Axial Alignment: Ensure that the axial alignment of the driven piles does not deviate by more than 1/4 in/ft from the vertical or batter line indicated in the plans.
7-6
7-6
Student Manual
7-7
7-7
Student Manual
455-5.15.2 Plan
Maximum Allowable Tolerance 3 In Any One Direction
7-8
Student Manual
1.0
7-9
7-9
Student Manual
7-10
7-10
Student Manual
455-5.15.4 Elevation
No more than 1 above Cutoff Elevation Cutoff Elevation No more than 4 below Cutoff Elevation
7-11
7-11
Student Manual
455-5.1.1 Predrilling of Pile Holes: 12 inch square piles 15 to 17 inches 14 inch square piles 18 to 20 inches 18 inch square piles 22 to 26 inches 20 inch square piles 24 to 29 inches 24 inch square piles 30 to 34 inches 30 inch square piles 36 to 43 inches The Contractor is not paid for Predrilled Holes. These are up to 10 ft or 20 % of the pile length (whichever is greater) starter holes. However, it is important that the Inspector recognize that whatever depth of predrilled hole was used in the Test Pile program is the depth used in production piles. Therefore, if 6 foot predrilled holes were used in the Test pile program and the Contractor wants to do 20 foot predrilled holes during production, this is not permitted. The Inspector should inform the Contractor it is not permitted, contact the PA and document the depth of hole predrilled.
7-12
Student Manual
7-13
455-5.1.1 Predrilling of Pile Holes: Predrilled pile holes are either starter holes to the depth described in this section or holes drilled through embankment/fill material down to the natural ground surface... .When using concrete or other high displacement piles, drill pile holes through fill, new or existing, to at least the elevation of the natural ground surface. In the setting of permanent and test piling, the Contractor may initially predrill holes to a depth up to 10 feet or 20% of the pile length whichever is greater, except that, where installing piles in compacted fill, predrill the holes to the elevation of the natural ground surface
7-13
Student Manual
455-5.1.1 Predrilling of Pile Holes: (Continued) For other pile sizes, use the diameter of the drills shown in the plans or approved by the Engineer. Accurately drill the pile holes with the hole centered over the plan location of the piling. Maintain the location and vertical alignment within the tolerances allowed for the piling.
7-14
7-14
Student Manual
7-15
7-15
Student Manual
7-16
Student Manual
455-5.1.1 Predrilling of Pile Holes: (Continued) . Perform such work the Engineer allows but does not require at no expense to the Department. When the Engineer requires such work, the Department will pay for such work as Preformed Pile Holes as described in 455-5.9.
7-17
7-17
Student Manual
The Contractor is paid for Preformed Holes if they are shown in the Project plans. Remember, Preforming depths are typically shown in the Pile Data Table and are given as an Elevation. Preformed Hole Depth, for recording purposes, is the depth or length of Preformed Hole drilled by the Contractor. Therefore, the Inspector needs to verify that the preformed Hole was drilled to the elevation specified and then record that length for pay purposes.
7-18
Student Manual
7-19
Student Manual
455-5.9.1 Description: (Continued) .Fill all voids between the pile and soil remaining after driving through preformed holes with clean A-3 sand or sand meeting the requirements of 902-3.3, after the pile has achieved the required minimum tip elevation, unless grouting of preformed pile holes is shown in the plans. If pile driving is interrupted during sand placement, drive the pile at least 20 additional blows after filling all of the voids between the pile and soil with sand at no additional compensation.
7-20
7-20
Student Manual
7-21
455-5.9.3 Conditions Under Which Payment Will Be Made: a) Inability to drive piles to the required penetration with driving and jetting equipment. (b) To penetrate a hard layer or layers of rock or strong stratum that the Engineer considers not sufficiently thick to support the structure. (c) To obtain greater penetration into dense (strong) material and into dense material containing holes, cavities or unstable soft layers. (d) To obtain penetration into a stratum in which it is desired to found the structure. (e) To minimize the effects of vibrations or heave on adjacent existing structures.
(f) To obtain a penetration up to 20 feet except where the Contract Documents show a required pile penetration in excess of 20 feet. (g) To minimize the effects of ground heave on adjacent piles.
7-21
Student Manual
7-22
Student Manual
7-23
7-23
Student Manual
7-24
Student Manual
Learning Outcome
Which, Predrilling or Preforming, is the Contractor Paid for accomplishing?
The tolerance for plan position is ______. A. B. C. D. 3 inches 4 inches 5 inches 6 inches
7-25
7-25
Student Manual
Learning Outcome
Which holes, Predrill or Preform, are to have hole diameters approximately 2 inches larger than the largest dimension across the pile cross-section.
The tolerance for axial alignment for driven piles is ______. A. 2 inches/ft.
B. 1 inch/ft. C. inch/ft. D. inch/ft.
7-26
7-26
Student Manual
7-27
Generally, projects designed in English units will specify blows per foot, therefore the pile should be marked in 1 foot intervals.
7-27
Student Manual
7-28
7-28
Student Manual
7-29
7-29
Student Manual
7-30
Student Manual
7-31
7-31
Student Manual
455-7.7.2 Extensions to be Driven or Those 21 feet or Longer: Construct extensions to be driven or extensions 21 feet or longer in length in accordance with the details shown in the plans and in a manner including the requirements, sequences, and procedures outlined below:
7-32
(a) Cast a splice section in accordance with Section 450 with the dowel steel in the correct position and alignment. (b) Drill dowel holes using an approved steel template that will position and align the drill bit during drilling. Drill holes a minimum of 2 inches deeper than the length of the dowel to be inserted. (c) Clean the drilled dowel holes by inserting a high pressure air hose to the bottom of the hole and blowing the hole clean from the bottom upward. Eliminate any oil, dust, water, and other deleterious materials from the holes and the concrete surfaces to be joined. (d) Place forms around joints between the pile sections. (e) Mix the adhesive components in accordance with the manufacturers directions. Do not mix sand or any other filler material with the epoxy components unless it is prepackaged by the manufacturer for this specific purpose. Use adhesives meeting the requirements of Section 926 for Type B Epoxy Compounds. (f) After ensuring that all concrete surfaces are dry, fill the dowel holes with the adhesive material. (g) Insert the dowels of the spliced section into the adhesive filled holes of the bottom section and position the spliced section so that the axes of the two sections are in concentric alignment and the ends of the abutting sections are spaced 1/2 inch apart. The Contractor may use small steel spacers of the required thickness provided they have 3 inches or more of cover after completing the splice. Fill the space between the abutting sections completely with the adhesive. (h) Secure the spliced sections in alignment until the adhesive is cured in accordance with the manufacturers directions for the time appropriate with the prevailing ambient temperatures. Do not utilize the crane to secure the pile extension during the adhesive cure time. Utilize alignment braces to maintain the proper pile alignment during the epoxy cure time. (i) After curing is completed, remove alignment braces and forms and clean and dress the spliced area to match the pile dimensions.
7-32
Student Manual
7-33
7-33
Student Manual
455-7.8 Pre-Planned Splices: Splices shall be made by the doweled splice method contained in the Standard Indexes or may be made using proprietary splices which are listed on the Departments QPL. Splice test piles in the same manner as the production piles. Include in the pile installation plan, the chosen method of splicing and the approximate locations of the splice.
7-34
7-34
Student Manual
7-35
Student Manual
7-36
7-36
Student Manual
7-37
(a) Cast a splice section in accordance with Section 450 with the dowel steel in the correct position and alignment. (b) Drill dowel holes using an approved steel template that will position and align the drill bit during drilling. Drill holes a minimum of 2 inches deeper than the length of the dowel to be inserted. (c) Clean the drilled dowel holes by inserting a high pressure air hose to the bottom of the hole and blowing the hole clean from the bottom upward. Eliminate any oil, dust, water, and other deleterious materials from the holes and the concrete surfaces to be joined. (d) Place forms around joints between the pile sections. (e) Mix the adhesive components in accordance with the manufacturers directions. Do not mix sand or any other filler material with the epoxy components unless it is prepackaged by the manufacturer for this specific purpose. Use adhesives meeting the requirements of Section 926 for Type B Epoxy Compounds. (f) After ensuring that all concrete surfaces are dry, fill the dowel holes with the adhesive material. (g) Insert the dowels of the spliced section into the adhesive filled holes of the bottom section and position the spliced section so that the axes of the two sections are in concentric alignment and the ends of the abutting sections are spaced 1/2 inch apart. The Contractor may use small steel spacers of the required thickness provided they have 3 inches or more of cover after completing the splice. Fill the space between the abutting sections completely with the adhesive. (h) Secure the spliced sections in alignment until the adhesive is cured in accordance with the manufacturers directions for the time appropriate with the prevailing ambient temperatures. Do not utilize the crane to secure the pile extension during the adhesive cure time. Utilize alignment braces to maintain the proper pile alignment during the epoxy cure time. (i) After curing is completed, remove alignment braces and forms and clean and dress the spliced area to match the pile dimensions.
7-37
Student Manual
7-38
Student Manual
455-8.9 Filling Pipe Piles: When required by the plans, fill pipe piles with the specified materials. Use clean concrete sands and concrete meeting the requirements of Section 346. Place concrete in pipes containing water using methods in accordance with 455-15.9 with modified tremie and pump line sizes. Concrete may be placed directly into pipes which are dry.
7-39
7-39
Student Manual
7-40
Student Manual
455-5.8 Penetration
455-5.8 Penetration Requirements: Measure the penetration of piles from the elevation of natural ground, scour elevation shown in the plans, or the bottom of excavation, whichever is lower. When the Contract Documents show a minimum pile tip elevation or a minimum depth of penetration, drive the tip of the pile to this minimum elevation or this minimum penetration depth. In all such cases, the Engineer will accept the bearing of a pile only if the Contractor achieves the required bearing when the tip of the pile is at or below the specified minimum tip elevation or depth of penetration and below the bottom of the preformed or predrilled pile hole.
7-41
Penetration is measured as the difference between the lowest of these three elevations and the tip of the pile. NOTE- The bottom of predrilled or preformed holes does not count as the bottom of an excavation.
7-41
Student Manual
455-5.8 Penetration
455-5.8 Penetration Requirements: (Continued) . When the plans do not show a minimum depth of penetration, scour elevation, or minimum tip elevation, ensure that the required penetration is at least 10 feet into firm bearing material or at least 20 feet into soft material unless otherwise permitted by the Engineer. If a scour elevation is shown in the plans, achieve these penetrations below the scour elevation. The Engineer may accept a penetration between 15 and 20 feet when there is an accumulation of five consecutive feet or more of firm bearing material.
7-42
7-42
Student Manual
455-5.8 Penetration
455-5.8 Penetration Requirements: (Continued) . Firm bearing material is any material offering a driving resistance greater than or equal to 30 tons/ft2 of gross pile area as determined by the Wave Equation (455-5.11.2). Soft material is any material offering less than these resistances. The gross pile area is the actual pile tip crosssectional area for solid concrete piles, the product of the width and depth for H piles, and the area within the outside perimeter for pipe piles and voided concrete piles.
7-43
7-43
Student Manual
455-5.8 Penetration
455-5.8 Penetration Requirements: (Continued) . Firm bearing material is any material offering a driving resistance greater than or equal to 30 tons/ft2 of gross pile area as determined by the Dynamic Load Testing (455-5.11.4). Soft material is any material offering less than these resistances. The gross pile area is the actual pile tip crosssectional area for solid concrete piles, the product of the width and depth for H piles, and the area within the outside perimeter for pipe piles and voided concrete piles.
7-44
7-44
Student Manual
455-5.8 Penetration
455-5.8 Penetration Requirements: (Continued) . Do not drive piles beyond practical refusal (20 blows per inch). To meet the requirements in this Subarticle, provide penetration aids, such as jetting or preformed pile holes, when piles cannot be driven to the required penetration without reaching practical refusal.
7-45
7-45
Student Manual
7-46
Prior to starting the Project, the Inspector should ask the PA how they want a decrease in blow counts, with an increased stroke height, handled. Typically, because an increased stroke height equates to more energy being imparted to the pile, less blows are required, as you will see in Driving Criteria Letters for Blow Count vs Stroke Height criteria.
7-46
Student Manual
Data Recording
The Pile Driving Record, which includes: Hammer blows for each interval Stroke Height or bounce chamber pressure for each interval Making appropriate notes concerning driving operations
7-47
7-47
Student Manual
The Driving criteria Letter may provide a start of driving stroke height, fuel setting or pressure. This is quite common when dealing with concrete piles, especially if easy or soft driving initially is anticipated. Soft or little resistance at the tip and a big stroke height can result in excess tension in a concrete pile and damage the tip. Remember to document all fuel settings and changes.
7-48
Student Manual
7-49
Shown above is a fixed four step fuel pump on a Delmag hammer. Generally open end diesel hammers are equipped with 4 fuel settings that enable the operator to control the stroke height. Fuel setting #1 is the lowest, and thereby produces the least combustion, hence the lowest stroke height. Typically, the higher the fuel setting the higher the stroke. A lanyard is connected to the pump and adjustments made by someone on the ground pulling the lanyard.
7-49
Student Manual
7-50
Shown above is an adjustable pressure pump for fuel setting on an ICE hammer. Closed end diesel, air/steam and hydraulic hammers are pressure operated and allow for a more precise setting of the hammer energy delivered than the open end diesel or drop hammer. Controls such as these are used to adjust the pressure being delivered to the hammer.
7-50
Student Manual
7-51
The various types of hammers have various ways to control the stroke. With drop hammers the stroke height is controlled by the operator lifting the weight. Open end diesel stroke height is a function of the fuel setting and resistance to driving, so in a sense is not really set. On air/steam the slide bar (shown above) provides for the setting of a constant stroke height. Generally there are two settings allowing for a full stroke and a short stroke, which is usually no less than 2 ft.
7-51
Student Manual
Display
7-52
7-52
Student Manual
7-53
For closed end diesel hammers, the pressure is displayed on the Bounce Chamber pressure gauge. With these systems, the Inspector depresses the panel button, typically with their foot, for approx. 10 seconds, during each increment, and records the average pressure being displayed during that time. Dont forget to measure the hose.
BOUNCE CHAMBER PRESSURE - p.s.i.g.
LINK-BELT SPEEDER
25 23 21 19 17 15 13 11 16,000 18,000
t t. 0f o5 Ho se
MODEL 520 DIESEL PILE HAMMER BOUNCE CHAMBER PRESSURE vs. EQUIVALENT WH ENERGY SEA LEVEL TO 2000 ELEVATION
Up
Up
8 to
t. 0f
Ho
se
Up
t 10 f to 1
. Ho
se
20,000
22,000
24,000
26,000
7-53
Student Manual
Indicators
Hollow sound, white smoke No smoke or little gray smoke Inconsistent ram strokes, little gray smoke or black smoke Inconsistent ram strokes, little gray smoke or black smoke Blows per minute rate is lower than specified Blows per minute rate is lower than specified Hollow sound, white smoke Low strokes Pawl does not engage piston Pawl engages but doesn't lift piston Paint and oil on cooling fins start to burn/sound changes
7-54
7-54
Student Manual
Indicators
Hollow sound, white smoke No smoke or little gray smoke Inconsistent ram strokes, little gray smoke or black smoke Inconsistent ram strokes, little gray smoke or black smoke Blows per minute rate is lower than specified Blows per minute rate is lower than specified Hollow sound, white smoke Low strokes Pawl does not engage piston Pawl engages but doesn't lift piston Paint and oil on cooling fins start to burn/sound changes Not visible from exterior
7-55
7-55
Student Manual
7-56
Student Manual
Common Problems Hoses getting caught in leads Fittings leaking Electrical connections Sensors visually evident
Indicators
7-57
7-57
Student Manual
7-58
Student Manual
The above pile driving criteria are based on a hammer driving system consisting of an ICE Model 60-S, single-acting, diesel hammer with a hammer cushion comprised of 0.5 inches of aluminum and 2 inches of blue nylon. Hammer cushions should be inspected on weekly, or appropriate intervals and maintained in accordance with 455-5.3.1. Preforming for the production piles should be conducted in the same manner as the test pile program. If there is a change in the driving system for the piles or the preforming depth and/or techniques, notify the Engineer so new driving criteria can be determined.
7-59
The Inspector should check the Driving Criteria Letter as it may specify a different inspection schedule than the standard specifications. Note that the bottom highlighted area states no changes without the Engineers approval. For example: If the Contractor replaced a micarta cushion with the same type and thickness, thats OK. However, if they replaced the micarta with say hamortex and aluminum plates, this would be a change needing the Engineers approval.
7-59
Student Manual
7-60
7-60
Student Manual
7-61
Student Manual
7-62
7-62
Student Manual
7-63
7-63
Student Manual
7-64
The 455 specifications require a new pile cushion be used for each pile. A Note should be made in the Pile Driving Record when changing pile cushions as generally the blow count will increase as the new cushion compresses giving a false sense of increased bearing capacity. If the pile is getting close to taking up (achieving bearing) and the pile cushion has to be changed, the Engineer may want the have a certain number of hammer blows put on the new cushion prior to getting back on the pile and commencing driving
7-64
Student Manual
7-65
7-65
Student Manual
Burning Cushion
7-66
7-66
Student Manual
7-67
Remember, steel piles are more susceptible to damage from compressive stresses than from tension.
7-67
Student Manual
Steel Piles
Typical causes of damage Transporting Steel Strength Lifting Driving (Compression) Welding Splices
7-68
Types of damage
Pile moving out of position Bending during driving Buckling Abrupt blow count change Accordion Splitting
7-68
Student Manual
7-69
7-69
Student Manual
Concrete Piles
Typical causes of damage Possible indicators during driving Types of damage Spalling- slabing Microcracks Transverse cracks Longitudinal cracks
Casting/stressing Cushions burning or compressed Concrete Strength Concrete Curing Puffs of concrete dust coming out of side of pile Transporting Pile walking out of position Lifting Driving (major cause) Post driving Construction
Hammer pile alignment bad Combination cracks Abrupt blow count change Tip damage
7-70
7-70
Student Manual
7-71
Student Manual
455-5.10.5 Pile Heave: (Continued) . Redrive all piles that have heaved 1/4 inch or more unless the Engineer determines that the heave is not detrimental to pile capacity. The Department will pay for all work in conjunction with redriving piles due to pile heave under the Pile Redrive Item.
7-72
7-72
Student Manual
Learning Outcome
Unless otherwise approved by the Engineer, used pile cushions may be utilized to drive up to how many additional piles? A. None
B. 1 C. 2 D. No limit
Pile Heave refers to ___________. A. The unloading of piles from the transport vehicle.
B. The downward movement of a previously driven pile. C. The upward movement of a previously driven pile. D. The act of loading the pile into fixed leads.
7-73
7-73
Student Manual
Learning Outcome
Hammer cushions should be inspected before driving begins and at approx. _____ intervals during driving. A. daily
B. hourly C. weekly D. monthly
True or False: Pile cushions are to be replaced when they are Compressed more than 25% of their original thickness? A. True
B. False
7-74
7-74
Student Manual
Learning Outcomes
Monitor and verify proper marking of the piles per contract documents and standards Verify & document contractor compliance with applicable tolerances Monitor, verify and document pile driving operations Identify applicable 455 specifications
7-75
7-75
Student Manual
Questions?
ANY QUESTIONS ?
7-76
7-76
EARLY REQUIREMENTS
1. 2. 3. 4. Do you have a copy of the Plans including latest revisions & located relevant items? (ex: Pile Date Table) Do you have and reviewed the accepted Pile Installation Plan? Are Dynamic Load Tests required and if so, is the PDA Engineer coordinated with? Have you downloaded and installed the current version of the FDOT Pile Technician Program on your field computer? 5. Have you setup Structure Files and Bent/Pier Models in the program? 6. Have you made the Initial Pile Data entries and Standard Notes entries in the program? 7. Have you scheduled or attended a Pre-Driving meeting with the PA/Geotechnical Engineer?
Yes No 1 1 2 2 3 3 4 4 5 5 6 6 7 7 8 9 10 11 12 13 A1 A2 A3 B1 B2 B3 C1 C2 D1 D2 D3 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 8 9 10 11 12 13 A1 A2 A3 B1 B2 B3 C1 C2 D1 D2 D3 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
NA
Version 1.0-06/12
41. 42.
41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58
41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58
43. 44. 45. 46. 47. 48. 49. 50. 51. 52. 53. 54.
POST INSTALLATION
55. Has the Contractor met the tolerances required? (455-5.15, Allowable Tolerances) 56. Has the Contractor initiated a plan to protect driven piles from fill placement operations? (455-10) 57. Have you been provided the final post-driving elevations and entered them in the Pile Technician Program and/or Pile Driving Record? 58. Have you verified that the two piles meet the tolerances of section 455-5.15?
Version 1.0-06/12