Engineering Risk Benefit Analysis
Engineering Risk Benefit Analysis
Engineering Risk Benefit Analysis
1.155, 2.943, 3.577, 6.938, 10.816, 13.621, 16.862, 22.82, ESD.72, ESD.721
Spring 2007
P(m/L3) = 0.6
P(m/L4) = 0.3
A clairvoyant, CV, is always correct, i.e., P[CV says L2 /L2 materializes] = 1.0 = P[s/L2] P[CV says L3 /L2 materializes] = 0.0 = P[m/L2] P[CV says L4 /L2 materializes] = 0.0 = P[w/L2] Receiving the CVs report removes all uncertainty.
DA 2. The Value of Perfect Information 3
P[L2 materializes/survey says L2] = 0.706, because the survey is not perfect.
DA 2. The Value of Perfect Information 4
P(CVsaysL 2 / Limaterializes)xP(Limaterializes)
2
1.0
DA 2. The Value of Perfect Information
L1 $150K
6
Modifications
In a decision tree, the order of the nodes is chronological. With perfect information, the uncertainty is resolved before the decision is made (a chance node is followed by a decision node). The evaluation is done a priori (before the CV is hired). Therefore, the DM believes that the CV will predict L2 with probability 0.3, L3 with probability 0.5, and L4 with probability 0.2.
DA 2. The Value of Perfect Information 7
L2 $300K L3 $100K
w, 0.2
L4 -$100K
CV
O
=$195K
1.0
L1 $150K
L2 $300K L3 $100K
w, 0.2
L4 -$100K
CV
O
=$195K
1.0
L1 $150K
12
General Tree
If the DM faces uncertainty in a decision (uncertainty nodes after the decision node), the impact of perfect information will be evaluated by redrawing the tree and reordering the decision and chance nodes.
The evaluation of perfect information is done a priori. The DM has not yet consulted the clairvoyant. The DM is considering whether to actually do it.
DA 2. The Value of Perfect Information 13