Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

The Plane That Ate The Canadian Military

Download as pdf or txt
Download as pdf or txt
You are on page 1of 32

Canadian Centre for Policy Alternatives April 2014

The Plane That Ate the Canadian Military


Life-Cycle Cost of F-35 Fleet Could Reach $126 Billion
Michael Byers

www.policyalternatives.ca

RESEARCH

ANALYSIS

SOLUTIONS

About the author

Michael Byersholds the Canada Research Chair in Global Politics and International Law at the University of British Columbia. Prior to 2005, he was Professor of Law and Director of the Center for Canadian Studies at Duke University. Dr. Byers is the author or editor of seven books and hundreds of articles, including Canadas F-35 purchase is a costly mistake, (2011) 17 Canadian Foreign Policy Journal 217227 (with Stewart Webb).
ISBN978-1-77125-127-3 This report is available free of charge at www. policyalternatives.ca. Printed copies may be ordered through the CCPA National Office for $10. Please make a donation... Help us to continue to offer our publications free online. With your support we can continue to produce high quality researchand make sure it gets into the hands of citizens, journalists, policy makers and progressive organizations. Visit www.policyalternatives.ca or call 613-563-1341 for more information. The CCPA is an independent policy research organization. This report has been subjected to peer review and meets the research standards of the Centre.

The opinions and recommendations in this report, and any errors, are those of the authors, and do not necessarily reflect the views of the funders of this report.

5 The Plane That Ate the Canadian Military

5 Summary 6 1. Introduction 7 2. History 9 3. Operating and Other Costs Not Acknowledged by DND 12 4. Acquisition Cost Sensitivities and Risk 16 5. Sustainment Cost Sensitivities and Risk 17 6. Operating Cost Sensitivities and Risk 18 7. Contingency Planning Is Inadequate or Absent 20 8. Recommendations
21 Appendix I 22 Appendix II 25 Appendix III 26 Notes

The Plane That Ate the Canadian Military


Life-Cycle Cost of F-35 Fleet Could Reach $126 Billion

I hope no one is assessing [the F-35 procurement] as low risk. Auditor General Sheila Fraser, October 20101

Summary
The Harper government anticipates a total project cost of $45.69 billion for a eet of 65 F-35s, including an operating cost of $19.857 billion. However, those gures are based on the operating cost of CF-18s rather than the actual operating cost of F-35s. Information on the latter is readily available from the U.S. government. The actual operating cost of a eet of F-35s would be $29.786 billion, leading to a total project cost of $55.619 billion. The Harper government has also failed to acknowledge the considerable cost risks and uncertainty associated with a eet of F-35srisks that are amplied by the developmental character and the unusually high operating and sustainment costs of these particular aircraft. Once cost risks and uncertainty are taken into account, the total project cost of a eet of F35s could be as high as $126 billion.

The Plane That Ate the Canadian Military

1. Introduction
In August 2013, the Department of National Defence (DND) released the Next Generation Fighter Capability Annual Update (DND Update).2 The DND Update anticipates a total project cost of $45.69 billion for a eet of 65 F-35s, including an operating cost of $19.857 billion. The DND Update does not provide any information on the cost of aircraft other than the F-35. Moreover, the DND Update makes the mistake of using the operating cost of CF-18s to project, on a dollar-to-dollar basis, the operating cost of F-35s. In fact, the operating cost of CF-18s is approximately one-third less than the operating cost of F-35s (as projected by the U.S. government).3 The actual operating cost of a eet of F-35s would be $29.786 billion, leading to a total project cost of $55.619 billion. In other words, correcting just this error adds approximately $10 billion to the total project cost of a Canadian eet of F-35s. The Harper government has also failed to include a number of other costs, including the full cost of munitions as well as the cost of modifying Canadas mid-air refuelling eet and adding drag chutes to the F-35s to enable them to use Arctic runways. Together, these costs add $1.055 billion, bringing the total project cost (including the actual operating cost) to $56.674 billion. Last but not least, the Harper government has failed to acknowledge the considerable cost risks and uncertainty associated with a eet of F35s. Some of these risks would apply to any model of aircraft, but they are amplied because the F-35 is still under development and has higher operating and sustainment costs than alternative aircraft. As this report demonstrates, higher operating and sustainment costs make the F-35 especially vulnerable to changes in exchange rate, ination, cost of aviation fuel, and yearly ying rate. This report builds upon a section on cost risks and uncertainty in the DND Update. Specically, it extrapolates DNDs information and analysis into two entirely possible moderate and serious scenarios. It is important to realize that neither of the scenarios even approaches a worst-case scenario, which might involvefor examplea 60-cent dollar, 10 percent ination rate, and $3/litre aviation fuel. But they do demonstrate how an accumulation of much smaller changes could easily cause the cost of an F-35 procurement to more than double. It is also important to realize that the greatly increased costs resulting from the accumulation of small changes in the moderate and serious scenarios could just as easily result from a single large change to a single

Canadian Centre for Policy Alternatives

factor, such as the exchange rate or ination rate, within the historic parameters of a 60-cent dollar or 10 percent ination rate. Cost risks and sensitivity are exceedingly important when planning a procurement that will stretch over more than a decade and involve many billions of tax dollars. Of course, cost sensitivities can also lead to positive outcomes, such as better exchange rates and lower ination, that would result in a lower overall project cost. However, from a planning perspective it is more sagacious to assess and guard against negative risk. Cost risks and sensitivity take on even greater importance in light of reports that the Harper government is postponing the decision on the replacement of Canadas CF-18s until after 2015, which would stretch the time frame for the procurement further.4 A line-by-line explanation of the nancial implications of this reports moderate and serious scenarios is provided in Appendix II. But the bottom line is this: Once actual operating cost and cost risks and uncertainty are taken into account, a eet of F-35s could cost $126 billion. That is $81 billion more than the $45 billion currently projected by the Harper government. An additional $81 billion in unplanned cost could destroy the Canadian military, which would be forced to carry most of that cost through reduced expenditures on other equipment, maintenance, infrastructure, salaries and training. Even the moderate scenario, which carries an additional $45 billion in unplanned cost, would have profoundly negative, across-the-board impacts on the men and women who serve.

2. History
The cost of F-35s rst became an issue in July 2010 when the Harper government announced it would purchase 65 of the aircraft for $9 billion, with $7 billion in maintenance cost bringing the total cost to $16 billion over a 20-year period.5 In March 2011, the Parliamentary Budget Office (PBO) released a report examining the increasing weight of ghter jets and the cost-per-pound of their production. These historic trends were then used to estimate a total project cost of $29.3 billion for the F-35s.6 The PBO number includes $11.4 billion in acquisition cost and $17.9 billion in sustainment cost and upgrades over a 30-year perioda decade longer than the period used by the Harper government in July 2010.

The Plane That Ate the Canadian Military

The Harper government responded harshly to the PBO report, with MP Laurie Hawn, then Parliamentary Secretary to the Minister of National Defence, dismissing the analysis as speculative and illogical.7 Two weeks later, the governments refusal to provide Parliament with details about the cost of F-35s contributed to its defeat in a non-condence vote.8 In April 2012, Auditor General Michael Ferguson produced a report that criticised DND for having failed to exercise due diligence in managing the process to replace the CF-18 jets.9 He concluded: Full life-cycle costs were understated in the estimates provided to support the governments 2010 decision to buy the F-35. Some costs were not fully provided to parliamentarians. More specically, the Auditor General found that the Harper government had been operating with two numbers: citing a number of $14.7 billion when responding to the 2011 PBO report publicly, while using a number of $25.1 billion internally. Finally, he noted that the Harper government had chosen not to include operating cost in its public estimate, despite this information being specically required by DND and the Treasury Board, and requested by Parliament in 2010. The Harper government responded to the Auditor Generals report by suspending the F-35 procurement, ordering the Royal Canadian Air Force (RCAF) to conduct an options analysis re-evaluating the F-35 and alternative aircraft, and setting a $9 billion limit for the acquisition cost.10 An Independent Review Panel was established and tasked with overseeing the RCAF report.11 The Harper government also commissioned accounting rm KPMG to clarify the cost of an F-35 procurement. In November 2012, the rm released Next Generation Fighter Capability: Independent Review of Life Cycle Cost (KPMG Review). The KPMG Review projects a 30-year life-cycle cost of $45.8 billion, including $982 million for attrition, i.e. the replacement of aircraft lost through accidents.12 It also includes an operating cost for the F-35s, though it bases this cost on the operating cost of Canadas existing eet of CF-18s. The DND Update, released in August 2013, applies the KPMG methodology and 30-year time frame to the full life-cycle cost of the F-35s.13 Like the KPMG Review, the DND Update bases the operating cost of the F-35 on the operating cost of the CF-18. The DND Update then estimates the total project cost of the F-35s at $45.6 billion, including $1 billion for attrition. Signicantly, the DND Update includes a section on cost risks and uncertainty that examines some of the cost sensitivities involved in the possible purchase of F-35s, such as changes in the Canada-U.S. exchange rate,

Canadian Centre for Policy Alternatives

ination rate, cost of aviation fuel, yearly ying rate, and rate of aircraft production by Lockheed Martin. The present report addresses the actual operating cost of F-35s as well as several other costs overlooked in the DND Update. It also extrapolates from the DND Updates tentative foray into cost risks and uncertainty, extending its information and analysis into moderate and serious scenarios. The two scenarios involve entirely possible circumstances that are far from worst-case. Yet they are sufficient to raise serious questions about the wisdom and nancial feasibility of an F-35 procurement, as well as the Harper governments lack of attention to substantial nancial risks.

3. Operating and Other Costs Not Acknowledged by DND


(a) Actual Operating Cost of F-35s
The 2012 Auditor Generals report, the 2013 KPMG Review and the 2013 DND Update all assume that the operating cost of F-35s will be the same as that of CF-18s. For example, the KPMG Review states that the operating data used for the calculation of F-35 operating cost is based on CF-18 data and, in most cases, it has not been normalized/adjusted to reect F-35 differences.14 It further statespresumably relying on Lockheed Martins early projections that the operating cost of the F-35 would be lower than that of the aircraft it would replacethat based on the nature of these adjustments and DNDs preliminary analysis, the adjustments would likely reduce the operating cost estimate.15 The DND Update explains that:
The operating cost estimate for the CF-18 has been used as an analog for the operating costs of the F-35A.... Should F-35 eet operating costs be higher than expected, the Department has the ability to manage the costs through altering eet operations or reallocating funds within its annual budget.16

The use of the CF-18 operating cost is fanciful. Although the F-35 was originally expected to have lower sustainment and operating costs than legacy aircraft like the CF-18, the costs based on evidence to date have become signicantly higher than those of legacy aircraft, including the CF-18. In 2011, the U.S. Government Accountability Office (GAO) wrote:
Current JSF [Joint Strike Fighter or F-35] life-cycle cost estimates are considerably higher than the legacy aircraft it will replace; this has major im-

The Plane That Ate the Canadian Military

plications for future demands on military operating and support budgets and plans for recapitalizing ghter forces.17

More recently, the U.S. GAO identies a cost of US$35,200 per ying hour for the F-35.18 Similarly, the U.S. Department of Defenses latest Selected Acquisition Report for the F-35 identies a cost of US$31,900 per ying hour.19 In comparison, the latest Selected Acquisition Report for the Boeing Super Hornet enables one to identify an operating cost of US$15,600 per hour for that aircraft20based on an annual cost in 2000 dollars, divided by ying time, and then converted to 2012 dollars.21 Boeing, which also manufactured the CF-18, told the CBC in 2013 that Super Hornets are 25 percent less expensive to operate than CF-18s.22 By extrapolation, this means CF-18s cost approximately US$20,800 per ying hour to operate. In 2012, MP Laurie Hawn, a former CF-18 squadron commander and Parliamentary Secretary to the Minister of National Defence, told the Hill Times that the CF-18 operating cost is approximately $19,000 per ying hour.23 The 25 percent difference in operating cost between the Super Hornet and the CF-18 makes sense given that the CF-18s are at the very end of their lifespan and in need of more day-to-day maintenance. The present report multiplies the DND Updates number for the operating cost of an F-35 eet (i.e. the operating cost of the existing CF-18 eet) by 1.5 to provide a more realistic estimate; one that is based on the roughly 2-to3 ratio of CF-18 to F-35 operating cost identied above. The resulting estimate$31,200 per houris still conservative, compared to the US$35,200 from the U.S. GAO and the US$31,900 from the U.S. Department of Defence. Moreover, even the U.S. numbers for the operating cost of the F-35 could be low, given the serious, ongoing uncertainties concerning new stealth materials and complex computingincluding 24 million lines of code, fused sensors, and a head-up display helmet.

(b) Munitions
Initially, DND anticipated spending $270300 million on weapons and bombs to equip a eet of F-35s.24 But in 2013, that amount was reduced to $52 million, with the DND Update stating:
Weapons currently in the Canadian Armed Forces inventory that can be employed on the F-35A eet will be retained. In the case of the F-35A, the project acquisition cost estimate provides for the acquisition of an initial stock

10

Canadian Centre for Policy Alternatives

of gun ammunition and countermeasures (e.g., ares), as the existing stock of CF-18 gun ammunition and ares are incompatible with the F-35A. Over the life cycle of the replacement eet, the acquisition of newer weapons will be considered and funded as separate projects.25

The approach taken in the DND Update is misleading. Any weapons that foreseeably need to be acquired for the F-35s during their operational lifespan should be included within the total life-cycle cost of the eet rather than treated as separate projects. For this reason, this report uses the low end of DNDs initial estimate for weapons ($270 million), which, after deducting the current estimate of $52 million, results in the addition of $218 million to the tabulations below.

(c) Refuelling Modications


In September 2012, a brieng note prepared for then Defence Minister Peter MacKay warned that the ability to refuel ghter jets in mid-air is critical to the defence of Canada and should be closely linked to the purchase of any replacement for the CF-18s.26 Of all the possible replacements for the CF-18, the F-35 is the only aircraft that is incompatible with Canadas existing refuelling eet. According to Postmedia, which obtained the brieng note through an Access to Information request, DND previously indicated that it would cost $420 million to modify Canadas refuelling eet to make it compatible with the F-35.27 This gure should therefore be included in the total life-cycle cost of an F-35 eet. The alternatives that are sometimes invokedrelying on the U.S. Air Force or private companies to provide this essential servicecan hardly be taken seriously.

(d) Drag Chute


Canadas CF-18s are equipped with tail hooks that enable them to land on short and often icy runways at Forward Operating Locations such as Inuvik and Rankin Inlet. There is no tail hook on the F-35A, the version Canada has been planning to purchase, although tail hooks are standard on all the alternative aircraft. For this reason, both Canada and Norway would likely add a drag chute to the F-35A.28 The actual cost of the drag chute is not yet known, and it is possible that Canada will simply adopt a design developed in Norway. But even just installing Norwegian designed drag chutes would

The Plane That Ate the Canadian Military

11

add to the life-cycle cost of Canadas eet. For this reason, $200 million has been added to the tabulations below.

(e) Computer Programming Facility


If Canada chooses the F-35, it will pay one-third of a $650 million computer programming facility for the software intensive aircraft.29 The facility, which is already being developed by Britain and Australia with the participation of Canadian military officers, was the subject of a September 2012 brieng note written for then Associate Defence Minister Bernard Valcourt and obtained by David Pugliese of the Ottawa Citizen through an Access to Information request. As Pugliese points out, Canadas share of the cost will be included in a submission to the Treasury Board for a new ghter aircraft once the government nishes its review of that purchase.30 However, the programming facility would not be counted as part of the acquisition cost of the aircraft themselves, and therefore would not fall within the strictures of the Harper governments $9 billion limit. Just as signicantly, no such programming facility would be required for the other possible replacements for the CF-18s. For all these reasons, $217 million (one-third of the $650 million cost of the facility) has been added to the tabulations below.

4. Acquisition Cost Sensitivities and Risk


(a) Exchange Rate and Acquisition Cost
The DND Update identies an acquisition cost of $8.99 billion, just under the limit of $9 billion set by the Harper government. In achieving that number, it uses a long-run exchange rate of $1 Canadian = $0.92 U.S., which was the rate in May 2013.31 At the same time, it acknowledges that:
Foreign exchange is a major, uncontrollable risk to the program cost estimate. The Canadian/United States exchange rate is quite volatile, having uctuated by over 40 per cent over the last 10 years, and has had swings of over 10 per cent in a single year.

The DND Update explains that, if the Canadian dollar were valued at 78 cents per U.S. dollar, instead of 92 cents, this would add $1.6 billion to the acquisition cost of an F-35 eet.32 This report uses the 78 cents per U.S. dollar exchange rate for its serious scenario estimate. For its moderate scen-

12

Canadian Centre for Policy Alternatives

ario estimate, this report uses an exchange rate of 85 cents per U.S. dollar, which would add $800 million to the acquisition cost.

(b) Ination and Acquisition Cost


The DND Update relies on May 2013 ination data from the F-35 Joint Program Office in the United States and from the National Defence Economic Model in Canada. It explains that a 1 percent increase in the ination rate would add approximately $500 million to the acquisition cost of a eet of F-35s.33 It does not consider the possibility of higher increases in ination. Like exchange rates, ination rates are unpredictable, especially for a purchase that will stretch over a decade. Although Canada has recently beneted from overall ination rates of around 2 percent, ination rates have exceeded 10 percent several times within the past fty years. Therefore, a 1 percent increase in ination is a rather optimistic measure of risk. In this report, the moderate scenario uses a 2 percent increase that adds approximately $1 billion to the acquisition cost. The serious scenario uses a 4 percent increase that adds approximately $2 billion to the acquisition cost.

(c) Shifting of Some Development Cost from the U.S. to Canada


The Harper government claims the U.S. government will pay almost all of the development cost of the F-35now over US$55 billionand that Canada would only pay the production cost of the planes acquired.34 If so, U.S. taxpayers would effectively be providing Canadian taxpayers with a massive subsidy, which raises the question as to whether the U.S. Congress would tolerate this. The question is highly relevant because Canada would be purchasing the planes through the U.S. government, not directly from Lockheed Martin. Moreover, if development problems were to extend into the period during which aircraft were being delivered to Canada, that development cost might be re-categorized as sustainment costadding to the numbers discussed in the section on sustainment cost below. If so, that added cost would not be subject to the protection the Harper government claims from the rising development cost of the F-35. In this report, the moderate scenario assumes the Harper government is correct, and that no signicant portion of the development cost would be shifted to Canada. However, the serious scenario foresees that a por-

The Plane That Ate the Canadian Military

13

tion of the development cost would be shifted to Canada. For the purposes of generating actual numbers, it assumes a relatively conservative amount of $1.8 billion, or the equivalent of a 20 percent increase in the acquisition cost of an F-35 eet.

(d) Lower Than Expected Learned and Production Efficiency Factors


A single F-35 currently costs $170180 million to produce.35 However, the Harper government claims it could obtain each F-35 at the much lower cost of $75 million, as the planes would be produced during a period of peak efficiency.36 The reduction in actual per-plane cost is supposed to result from an incremental learning effect whereby experience accumulated by producing the same system year after year leads to efficiencies and reduced cost. However, the F-35 program is experiencing serious, ongoing problems with the airframe, head-up display helmet, and especially software that could limitor at least delaythe cost reductions achieved through the learning effect.37 Consequently, Canada could end up purchasing its aircraft while the production cost-per-plane is still signicantly higher than the projected $75 million. Conceivably, Canada could delay purchasing F-35s until the price drops. However, doing so would risk a capability gap after the aging CF-18s are retired in 2020. Alternatively, it is possible that the lifespan of some of the CF18s could be extended through further upgrades, though this too would be costly and would not address the growing risk of metal fatigue. In any event, every delay in replacing the CF-18s adds to the eventual acquisition cost of replacements through ination. Delays combined with ination (and inaccurate projections of ination) have recently caused major problems in another Canadian military procurement, namely the Joint Support Ship project.38 The DND Update explains that just a 3 percent decrease in learning effect would increase the acquisition cost by approximately $1.6 billion.39 This report uses that 3 percent decrease (a $1.6 billion cost increase) in its moderate scenario, doubling it to 6 percent and $3.2 billion for its serious scenario.

(e) Reduction in Overall Number of F-35s Ordered


Per-plane acquisition cost depends on economies of scale, which differ from learning effect in being size-driven rather than time-driven. The DND Update acknowledges that the United States and its allies have reduced the numbers of F-35s they are ordering, with possible cost conse-

14

Canadian Centre for Policy Alternatives

quences for Canada: [I]f partner nations delay the timing of their purchases and/or reduce the number of aircraft they purchase up to and during, the period Canada would be purchasing its aircraft, the unit price for Canadian orders may be higher.40 The DND Update assesses the maximum decrease in purchases at 250 aircraft, which would result in an increase in the acquisition cost for Canada of approximately $600 million.41 However, the reduction in total orders could be larger. The United States has dramatically reduced the number of F-35s it is purchasing in the early years of the program, which could lead to a signicant reduction in its planned total of 2,443 aircraft.42 It bears remembering that only 187 of 750 originally planned F-22s were ever built, with the production line for the F-35s sister aircraft shut down for budgetary reasons in 2009.43 The United Kingdom has indicated that it will purchase fewer than the 138 F-35s it originally planned, and some reports suggest it might only acquire 50 aircraft.44 The Netherlands has gone from 85 to 37 aircraft and Italy from 131 to 90.45 Denmark and Turkey have gone from decided purchasers to undecided potential purchasers.46 Australia originally planned to purchase 100 F-35s, but then purchased 24 Super Hornets, which may well lead to a reduction in its F-35 order.47 In April 2014, Australia announced the purchase of 58 F-35s, taking its total to 72 F-35sstill short of the 100 F-35s originally planned.48 The uncertainty is increased by the existence of some movement in the opposite direction, with South Korea announcing in March 2014 that it will purchase F-35s rather than Boeing F-15 Silent Eagles.49 But only 40 F-35s will be bought, down one-third from an initially planned 60 aircraft. This report, in its moderate scenario, uses the same 250-plane reduction that DND concluded would lead to an increase of $600 million in the acquisition cost. In its serious scenario, this report uses a 500-plane reduction that would add $1.2 billion to the acquisition cost.

(f) Attrition Cost Should Be Included in Acquisition Cost


Unlike every other national government involved in the F-35 program, the Harper government does not consider attrition cost to be part of the acquisition cost of a eet of F-35s.50 Its approach to this issue is contrary to the expert advice of DNDs research branch, Defence Research and Development Canada, which in 2011 predicted that some of the F-35s would be lost before all 65 of the aircraft could be delivered.51 This means attrition planning

The Plane That Ate the Canadian Military

15

must be a necessary and integral part of achieving the minimum number of planes necessary for an operational eet. The DND Update follows the Harper governments approach of excluding attrition cost from acquisition cost, while noting that between 7 and 11 replacement aircraft would likely be required over the lifespan of any eet, at an additional acquisition cost of approximately $1 billion.52 This report follows the approach taken by the other countries, consistent with the advice from Defence Research and Development Canada. Attrition cost is a necessary and integral part of the acquisitionand, for this reason, this report subjects the $1 billion attrition cost to the same extrapolations of nancial risk as were applied to the initial 65 aircraft earlier in this section. This generates an additional cost of $1 billion (total $2 billion for attrition) for the moderate scenario and an additional cost of $1.9 billion (total $2.9 billion for attrition) for the serious scenario.

5. Sustainment Cost Sensitivities and Risk


Sustainment cost includes the repair, modication and upgrading of aircraft over their operational lifespans. The DND Update identies a sustainment cost of $15.06 billion for an F-35 eet. However, uncertainties concerning that sustainment cost pose substantial nancial risks for Canada.

(a) Exchange Rate and Sustainment Cost


The DND Update explains that an exchange rate of 78 cents would add $2.1 billion to the sustainment cost.53 This report uses an exchange rate of 78 cents in its serious scenario. In its moderate scenario, this report uses an exchange rate of 85 cents that adds $1.05 billion to the sustainment cost.

(b) Ination and Sustainment Cost


The DND Update explains that a 1 percent increase in ination would increase the sustainment cost by almost $3.1 billion over the 30-year life cycle of an F-35 eet.54 This report, in its moderate scenario, uses a 2 percent increase in ination that adds $6.2 billion to the sustainment cost. In its serious scenario, this report uses a 4 percent increase that adds $12.4 billion to the sustainment cost.

16

Canadian Centre for Policy Alternatives

(c) Yearly Flying Rate and Sustainment Cost


The DND Update explains that the CF-18 eet has a planned yearly ying rate of approximately 15,000 hours, and that the planned yearly ying rate of an F-35 eet would be about 11,700 hours.55 The lower number of hours is based on the assumption that more of the F-35 training will be done in simulators. But planning to park the planes may provide false economies. The F-35 development program already made the mistake of relying on computer simulation for much of the testing process, only to discover many unforeseen problems following actual ights.56 Moreover, international tensions could easily lead to an increased training tempo or increased patrols, and therefore a higher yearly ying rate. The DND Update explains that increasing the yearly ying rate by 4,000 hours would add approximately $2 billion in sustainment cost.57 This report uses an increase of 4,000 hours in its serious scenario. In its moderate scenario, this report uses an increase of 2,000 hours that adds approximately $1 billion in sustainment cost.

(d) Technology Transfer and Sustainment Cost


Lockheed Martin has already said that it would not provide Canada with access to all of the key technological information, such as software code, needed for repairing and upgrading the F-35.58 The company could therefore take advantage of a monopoly position to impose an articially high sustainment cost. Although it is impossible to estimate the amount that might be overcharged, it is noteworthy that Dassault has offered to transfer all of the technology involved in the Rafale if the French-made ghter jet is chosen to replace the CF-18.59

6. Operating Cost Sensitivities and Risk


Operating cost includes fuel, day-to-day maintenance, and salaries for pilots, mechanics, and other necessary personnel. The DND Update identies an operating cost of $19.857 billion for a eet of F-35s. Section 3(a) of this report has already explained the discrepancy between that estimate and the actual operating cost of a eet of F-35s. This section explains how cost sensitivities concerning the operating cost of the F-35 pose substantial nancial risks for Canada.

The Plane That Ate the Canadian Military

17

(a) Ination and Operating Cost


The DND Update explains that a 1 percent increase in ination over the life cycle of an F-35 eet would add approximately $5.4 billion to the operating cost.60 This report, in its moderate scenario, uses a 2 percent increase in ination that adds $10.8 billion to the operating cost. In its serious scenario, this report uses a 4 percent increase in ination that adds $21.6 billion to the operating cost.

(b) Yearly Flying Rate and Operating Cost


The DND Update explains that increasing the yearly ying rate by 4,000 hours would add $1.5 billion to the operating cost over the life cycle of an F-35 eet.61 This report uses an increase in yearly ying rate of 4,000 hours in its serious scenario. In its moderate scenario, this report uses an increase in yearly ying rate of 2,000 hours that adds $750 million to the operating cost.

(c) Price of Aviation Fuel and Operating Cost


The DND Update assumes an average price of $0.879 per litre for aviation fuel over a 30-year period, while noting that a 10 percent increase in that average price would add $430 million to the operating cost.62 Given the decreasing availability of conventional oil, increases of more than 10 percent seem likely over a 30-year period. Indeed, the price of aviation fuel has doubled in the last decade.63 This report, in its moderate scenario, uses a 50 percent increase in the average price of aviation fuel that adds $2.15 billion to the operating cost. In its serious scenario, this report uses a 100 percent increase in the average price of aviation fuel that adds $4.3 billion to the operating cost.

7. Contingency Planning Is Inadequate or Absent


(a) Acquisition Cost and Contingency Planning
The implications of cost sensitivities for the acquisition cost of a eet of F35s were discussed in Section 4 of this report. Under the moderate scenario, the total acquisition cost rises to $12.99 billion, or $200 million per plane.

18

Canadian Centre for Policy Alternatives

Under the serious scenario, the total acquisition cost rises to $18.79 billion, or $289 million per plane. As the DND Update explains, the Harper governments only contingency plan for increases in acquisition cost involves a reduction in the number of planes purchased.64 In other words, if the cost-per-plane rises, Canada will purchase fewer planes in order to stay within the $9 billion acquisition limit. DND originally sought 80 F-35s; the reduction to 65 aircraft occurred in 2010.65 DND has repeatedly stated that 65 is the minimum number of ghter jets needed for an operationally capable eet.66 If Canada decides to purchase F-35s, the possible increases in acquisition cost identied in this report could force a future government to choose between exceeding the $9 billion limit in order to buy 65 F-35s, or settling for a smaller, operationally incapable eet. Under the moderate scenario developed here, Canada could only purchase 45 planes while staying under the $9 billion limit. Under the serious scenario, Canada could purchase only 34 planes.

(b) Sustainment Cost and Contingency Planning


In August 2013, DND increased the contingency for sustainment cost to $3.496 billion, but only to take into account additional uncertainties concerning sustainment cost projections produced by the F-35 Joint Program Office in the United States. The increased contingency does not address the considerable cost risks and uncertainty identied in this report. As a result, the only contingency measure available for these risks, within the limits of the DND Updates cost projections, would be to sustain only a portion of the eet. This would amount to a post-purchase reduction in eet size.

(c) Operating Cost and Contingency Planning


There is no contingency included in DNDs numbers for operating cost, with the plan being to avoid any cost overruns through a reduction in ying hours. However, taking such an approach to cost overruns of 250350 percent would result in almost no ying. The Canadian Forces would, instead, have to pay for a substantial portion of the cost overruns through reduced expenditures on other equipment, maintenance, infrastructure, salaries and training.

The Plane That Ate the Canadian Military

19

8. Recommendations
This report demonstrates that the Harper government is understating the total project cost of a eet of F-35s by $11 billion, even without taking cost risks and uncertainty into account. Once cost risks and uncertainty are taken into account, the possible total project cost rises to $90 billion in a moderate risk scenario and $126 billion in a serious risk scenario. With this information now at hand, the Harper government should: Update its cost projection by including the actual operating cost of F-35s, the full cost of munitions, and the cost of modifying Canadas mid-air refuelling eet, adding drag chutes to the F-35s, and paying Canadas share of the computer programming facility; Expand the Department of National Defences tentative 2013 foray into the cost risks and uncertainty associated with the F-35 by conducting the type of analysis carried out in this report; Conduct the same analysis of cost risks and uncertainty with regard to alternative aircraft; Make those analyses available for public scrutiny and debate in advance of any decision to acquire F-35s.

20

Canadian Centre for Policy Alternatives

Appendix I
Operating and Other Actual Costs Not Acknowledged in DND Update

Operating Cost Operating cost (DND Update, based on CF-18 eet): $19.857 billion Actual operating cost of F-35 eet (add $9.929 billion, based on numbers from Boeing, MP Laurie Hawn, U.S. GAO & U.S. DOD): $29.786 billion Total project cost (DND Update): $45.69 billion Adjusted total project cost (including actual operating cost): $55.619 billion Other Actual Costs Not Acknowledged in the DND Update Munitions (added life-cycle cost): $0.218 billion Modifying mid-air refuelling eet: $0.42 billion Adding drag chute to F-35s: $0.20 billion Computer programming facility: $0.217 billion Total additional actual costs not acknowledged in DND Update: $1.055 billion Total project cost (DND update): $45.69 billion Adjusted total project cost (including all actual costs): $56.674 billion

The Plane That Ate the Canadian Military

21

Appendix II
Cost Risks and Uncertainty in Moderate and Serious Scenarios

Note: All bold numbers are taken from the 2013 DND Update; all italic numbers are extrapolated from the calculations of risk in that same document. Development Cost (DND Update; already paid)$0.606 billion Acquisition Cost (DND Update)$8.99 billion moderate scenario: 85 cent dollaradds $0.8 billion 2 percent ination increaseadds $1 billion 3 percent decrease in learning and production efficiency adds $1.6 billion Reduction of 250 planes in initial ordersadds $0.6 billion Total adjusted acquisition (moderate scenario) = $12.99 billion ($200 million per plane) serious scenario: 78 cent dollaradds $1.6 billion 4 percent ination increaseadds $2 billion Some development cost imposed on Canadaadds $1.8 billion 6 percent decrease in learning and production efficiency adds $3.2 billion Reduction of 500 planes in initial ordersadds $1.2 billion Total adjusted acquisition (serious scenario) = $18.79 billion ($289 million per plane)

22

Canadian Centre for Policy Alternatives

Sustainment Cost (DND Update)$15.055 billion moderate scenario: 85 cent dollaradds $1.05 billion 2 percent ination increaseadds $6.2 billion Increase yearly ying rate by 2,000 hoursadds $1 billion Total adjusted sustainment (moderate scenario) = $23.305 billion serious scenario: 78 cent dollaradds $2.1 billion 4 percent ination increaseadds $12.4 billion Increase yearly ying rate by 4,000 hoursadds $2 billion Total adjusted sustainment (serious scenario) = $31.555 billion Operating Cost (DND Update)$19.857 billion Note: $19.857 billion is the operating cost of the CF-18 eet, which needs to be multiplied by 1.5 to reect the actual operating cost of an F-35 eet. This provides an operating cost of $29.786 billion, without any of the adjustments below. moderate scenario, starting with $19.857 billion (cf-18 cost): 2 percent ination increaseadds $10.8 billion Increase yearly ying rate by 2,000 hoursadds $0.75 billion 50 percent increase in price of aviation fueladds $2.15 billion Total adjusted operating cost (moderate scenario) = $33.557 billion (adjusted CF-18 operating cost) 1.5 = $50.336 billion serious scenario, starting with $19.857 billion (cf-18 cost): 4 percent ination increaseadds $21.6 billion Increase yearly ying rate by 4,000 hoursadds $1.5 billion 100 percent increase in price of aviation fueladds $4.3 billion Total adjusted operating cost (serious scenario) = $47.257 billion (adjusted CF-18 operating cost) 1.5 = $70.886 billion

The Plane That Ate the Canadian Military

23

Disposal Cost at End of Aircraft Lifespan (DND Update) $0.168 billion additional actual costs not acknowledged in dnd update Munitions (added life-cycle cost): $0.218 billion Modifying mid-air refuelling eet: $0.42 billion Adding drag chute to F-35s: $0.20 billion Computer programming facility: $0.217 billion Total additional actual costs not acknowledged in DND Update: $1.055 billion Total Life-Cycle Cost (DND Update)$44.676 billion Adjusted Total Life-Cycle Cost (moderate scenario): $88.46 billion Adjusted Total Life-Cycle Cost (serious scenario): $123.06 billion Attrition (DND Update)$1.015 billion Adjusted Attrition (moderate scenario): $2 billion Adjusted Attrition (serious scenario): $2.9 billion Total Project Cost (DND Update)$45.69 billion Adjusted Total Project Cost (moderate scenario): $90.46 billion Adjusted Total Project Cost (serious scenario): $125.96 billion

24

Canadian Centre for Policy Alternatives

Appendix III
Total Project Cost Estimates for Canadian Fleet of F-35s
Figure 1Total Project Cost Estimates (Billions)
$140 $126 Billion $120 $100 $80 $60 $45 Billion $40 $25 Billion $20 $0 $16 Billion $29 Billion $45 Billion $56 Billion $57 Billion

$90 Billion

rp e (p r Go ub ve lic rn 20 g me 10 ur nt e) Ha rp e (in r G te ov rn e al rn g me ur nt e) 20 1 Bu 1 Pa dg rli et am O en ce t

NoteAll figures rounded to nearest billion

The Plane That Ate the Canadian Military

tu Ad al ju to ste ta d Ad l c fo co ju os r st st t pl ed us f m or a od ct er ua at l t Ad e ot ris al j u co st k st ed pl fo us r se act rio ua us l to r ta is l k

20

Ad j

te us op ted er fo at r a in c g tu co al st

KP

13

20

13

DN

Up

da

20

10

Ha

ac

25

Notes

1 David Pugliese, Auditor General Fraser warns about F-35. Her report nds DND low-balled cost on Chinooks, Ottawa Citizen, 26 October 2010, available at: http://blogs.ottawacitizen. com/2010/10/26/auditor-general-fraser-warns-about-f-35-her-report-finds-dnd-low-balled-coston-chinooks/ 2 Department of National Defence, Next Generation Fighter Capability2013 Annual Update, 9 August 2013, available at: http://www.forces.gc.ca/assets/FORCES_Internet/docs/en/aboutreports-pubs/ngfc-annual-update-2013.pdf 3 See citations, Section 3(a) below. 4 Tim Naumetz, Feds to delay F-35 decision until after next federal election, The Hill Times, 26 March 2014, available at: http://www.hilltimes.com/news/politics/2014/03/26/feds-to-delayf-35-decision-until-after-next-federal-election/37978?mcl=694&muid=2086 5 CTV News, Tories defend sole-sourced $16B jet purchase, 16 July 2010, available at: http:// www.ctvnews.ca/tories-defend-sole-sourced-16b-jet-purchase-1.533465 6 Parliamentary Budget Office, An Estimate of the Fiscal Impact of Canadas Proposed Acquisition of the F-35 Lightning II Joint Strike Fighter, 10 March 2011, available at: http://www.parl. gc.ca/PBO-DPB/documents/F-35_Cost_Estimate_EN.pdf 7 Murray Brewster, Budget officers numbers on F-35 illogical, Conservatives say, Canadian Press, 11 March 2011, available at: http://www.thestar.com/news/canada/2011/03/11/budget_ officers_numbers_on_f35_illogical_conservatives_say.html 8 Associated Press, Canadian government collapses in no-condence vote, 26 March 2011, available at: http://www.theguardian.com/world/2011/mar/26/canadian-government-no-confidence-vote 9 Office of the Auditor General of Canada, 2012 Spring Report of the Auditor General of Canada: Chapter 2, Replacing Canadas Fighter Jets, 3 April 2012, available at: http://www.oag-bvg. gc.ca/internet/docs/parl_oag_201204_02_e.pdf 10 See, e.g.: Department of National Defence, StatementGovernment of Canada announces comprehensive response to Chapter 2 of the 2012 Spring Report of the Auditor General of Can-

26

Canadian Centre for Policy Alternatives

ada, 3 April 2012, available at: http://www.forces.gc.ca/en/news/article.page?doc=governmentof-canada-announces-comprehensive-response-to-chapter-2-of-the-2012-spring-report-of-theauditor-general-of-canada/hir3oy82 11 Steven Chase, Tories seek alternatives to F-35 jet as cost soars to more than $40-billion, The Globe and Mail, 6 December 2012, available at: http://www.theglobeandmail.com/news/ politics/tories-seek-alternatives-to-f-35-jet-as-cost-soars-to-more-than-40-billion/article6064818/ 12 KPMG, Next Generation Fighter Capability: Independent Review of Life Cycle Cost, 27 November 2012, available at: https://www.tbs-sct.gc.ca/reports-rapports/ngfc-cng/irlc-eiccv/irlceiccv-eng.pdf 13 DND Update, supra, note 2 14 KPMG Review, supra, note 12, p. 2 15 KPMG Review, supra, note 12, p. 2 16 DND Update, supra, note 2, p. 42 17 U.S. Government Accountability Office, Joint Strike Fighter: Restructuring Places Program on Firmer Footing, but Progress Still Lags, 7 April 2011, p. 9, available at: http://www.gao.gov/ assets/320/317548.pdf 18 U.S. Government Accountability Office, Joint Strike Fighter: DOD Actions Needed to Further Enhance Restructuring and Address Affordability Risks, 14 June 2012, p. 11, available at: http:// gao.gov/assets/600/591608.pdf 19 U.S. Department of Defense, Selected Acquisition Report: F-35 Joint Strike Fighter Aircraft, 23 May 2013, available at: http://www.dod.mil/pubs/foi/logistics_material_readiness/acq_bud_ fin/SARs/2012-sars/13-F-0884_SARs_as_of_Dec_2012/DoD/F-35_December_2012_SAR.pdf 20 U.S. Department of Defense, Selected Acquisition Report: F/A-18E/F Super Hornet Aircraft, 21 May 2013, available at: http://www.dod.mil/pubs/foi/logistics_material_readiness/acq_bud_ fin/SARs/2012-sars/13-F-0884_SARs_as_of_Dec_2012/Navy/F-A-18E-F_December_2012_SAR.pdf 21 Bill Sweetman, Math Is Hard, Aviation Week blog, 24 January 2014, available at: http://www.aviationweek.com/Blogs.aspx?plckBlogId=Blog:27ec4a53-dcc8-42d0-bd3a01329aef79a7&plckPostId=Blog%3A27ec4a53-dcc8-42d0-bd3a-01329aef79a7Post%3Ae14a3e0c3267-4c81-a2fd-01dff925bdf3 22 Terry Milewski, Boeing touts ghter jet to rival F-35at half the price, CBC News, 27 February 2013, available at: http://www.cbc.ca/news/politics/boeing-touts-fighter-jet-to-rival-f-35at-half-the-price-1.1320636 23 Tim Naumetz, Conservative MP Hawn estimates CF-18 costs $12,000 less per ying hour than F-35 ghter jet, Hill Times, 17 May 2012, available at: http://www.hilltimes.com/news/ politics/2012/05/17/conservative-mp-hawn-estimates-cf-18-costs-%2412000-less-per-flyinghour-than-f-35/30780 24 Murray Brewster, National Defence to buy fewer bombs if F-35 selected as new air force ghter, Canadian Press, 14 February 2013, available at: http://montreal.ctvnews.ca/national-defenceto-buy-fewer-bombs-if-f-35-selected-as-new-air-force-fighter-1.1157706 25 DND Update, supra, note 2, p. 19 26 Lee Berthiaume, Air force brass say air-to-air refuelling critical for next ghter, F-35 incompatible with current systems, Postmedia, 14 June 2013, available at: http://o.canada.com/ news/air-force-brass-say-air-to-air-refuelling-critical-for-next-fighter-f-35-incompatible-withcurrent-systems/

The Plane That Ate the Canadian Military

27

27 Lee Berthiaume, Air force brass say air-to-air refuelling critical for next ghter, F-35 incompatible with current systems, Postmedia, 14 June 2013, available at: http://o.canada.com/ news/air-force-brass-say-air-to-air-refuelling-critical-for-next-fighter-f-35-incompatible-withcurrent-systems/ 28 Jerome Lessard, F-35 chute production may land in town, The Intelligencer (Belleville), 8 November 2013, available at: http://www.intelligencer.ca/2013/11/08/f-35-chute-productionmay-land-in-town 29 David Pugliese, Canada still involved in F-35 programming, Postmedia News, 19 August 2013, http://www2.canada.com/montrealgazette/news/archives/story.html?id=6d55ab05-a85f4ca0-9efd-79df42400eba 30 David Pugliese, Canada still involved in F-35 programming, Postmedia News, 19 August 2013, http://www2.canada.com/montrealgazette/news/archives/story.html?id=6d55ab05-a85f4ca0-9efd-79df42400eba 31 DND Update, supra, note 2, p. 31 32 DND Update, supra, note 2, p. 32 33 DND Update, supra, note 2, p. 34 34 CBC News, Harper vows modest cuts but offers few details, 10 April 2011, available at: http://www.cbc.ca/news/politics/harper-vows-modest-cuts-but-offers-few-details-1.1077028. See also: Alan Williams, Lets be honest about the price tag on those planes, Ottawa Citizen, 23 March 2011, available at: http://www2.canada.com/ottawacitizen/story.html?id=a790b5dafc84-4582-ab60-32122897cb4d 35 Winslow Wheeler, The Latest Word on F-35 Unit Cost, Project on Government Oversight, 3 January 2014, available at: http://www.pogo.org/blog/2014/01/the-latest-word-on-f-35-unit-cost.html 36 John Ivison, Political reality may force Tories to change broken record routine on F-35, National Post, 13 February 2012, available at: http://fullcomment.nationalpost.com/2012/02/13/f35-john-ivison/ 37 See, e.g.: U.S. Department of Defense, Director of Operational Test Evaluation, F-35 Joint Strike Fighter (JSF), January 2013, available at: http://www.dote.osd.mil/pub/reports/FY2013/ pdf/dod/2013f35jsf.pdf 38 Lee Berthiaume, Government may have underestimated cost of new resupply ships, Postmedia, 13 February 2013, available at: http://o.canada.com/news/national/government-mayhave-underestimated-cost-of-new-resupply-ships/ 39 DND Update, supra, note 2, p. 33 40 DND Update, supra, note 2, p. 34 41 DND Update, supra, note 2, p. 34 42 Tony Capaccio, Lockheed F-35 Said to Be Cut by 13 Planes in Pentagons Budget, Bloomberg News, 25 January 2012, available at: http://www.bloomberg.com/news/2012-01-25/lockheed-f-35said-to-be-cut-by-13-planes-in-pentagon-s-plan.html ; Bloomberg News, Pentagon to trim plans for F-35 jet order, 16 February 2014, available at: http://www.washingtonpost.com/politics/pentagonto-trim-plans-for-f-35-jet-order/2014/02/16/2310f400-974c-11e3-8461-8a24c7bf0653_story.html 43 R. Jeffrey Smith, High-Priced F-22 Fighter Has Major Shortcomings, Washington Post, 10 July 2009, available at: http://www.washingtonpost.com/wp-dyn/content/article/2009/07/09/ AR2009070903020.html

28

Canadian Centre for Policy Alternatives

44 Rhys Jones, Britain wont decide on F-35 ghter numbers till 2015, Reuters, 7 February 2012, available at: http://www.reuters.com/article/2012/02/07/us-lockheed-britain-fidUSTRE8160ZB20120207 45 David Pugliese, Drop in Numbers of F-35s Being Ordered Could Mean Increased Costs For a Canadian F-35, Ottawa Citizen, 22 September 2013, available at: http://blogs.ottawacitizen. com/2013/09/22/drop-in-numbers-of-f-35s-being-ordered-could-mean-increased-costs-for-acanadian-f-35/ 46Ibid. 47 Lania Vasek, F-35 Joint Strike Fighter delays could force Australia to revert to Super Hornet, The Australian, 6 January 2012, available at: http://www.theaustralian.com.au/nationalaffairs/policy/further-f-35-joint-strike-fighter-delays-could-force-australia-to-revert-to-the-superhornet/story-e6frg8yo-1226238241670 48 BBC News, Australia to buy 58 new F-35 ghter jets, 23 April 2014, available at: http://www. bbc.com/news/business-27122188 49 Doug Cameron & Jeyup S. Kwaak, Lockheed Martin to Get $6.8 Billion Order From South Korea, Wall Street Journal, 24 March 2014, available at: http://online.wsj.com/news/articles/ SB10001424052702303949704579458803559185982 50F-35 Fighters: Top General Walt Natynczyk Says 65 Is Minimum Number Of Jets Needed By Air Force, Canadian Press, 3 November 2011, available at: http://www.huffingtonpost. ca/2011/11/03/top-commander-says-65-is-f35-jets-enough_n_1073984.html 51 Lee Berthiaume, National Defence expected to lose some F-35s before all 65 delivered: Report, Postmedia News, 28 April 2013, available at: http://news.nationalpost.com/2013/04/28/ national-defence-expected-to-lose-some-f-35s-before-all-65-delivered-report/ 52 DND Update, supra, note 2, p. 14 53 DND Update, supra, note 2, p. 37 54 DND Update, supra, note 2, p. 37 55 DND Update, supra, note 2, p. 37 56 W.J. Hennigan & Ralph Vartabedian, F-35 ghter jet struggles to take off, Los Angeles Times, 12 June 2013, available at: http://www.latimes.com/business/la-fi-0612-fighter-jet-testing-20130612dto,0,4701367.htmlstory#axzz2yPXvAlsn 57 DND Update, supra, note 2, p. 37 58 Canadian Press, Dassault Aviation ramps up CF-18 replacement pitch, 22 January 2014, available at: http://www.cbc.ca/news/politics/dassault-aviation-ramps-up-cf-18-replacementpitch-1.2507029 59 Canadian Press, Dassault Aviation ramps up CF-18 replacement pitch, 22 January 2014, available at: http://www.cbc.ca/news/politics/dassault-aviation-ramps-up-cf-18-replacementpitch-1.2507029 60 DND Update, supra, note 2, p. 38 61 DND Update, supra, note 2, p. 38 62 DND Update, supra, note 2, p. 38

The Plane That Ate the Canadian Military

29

63 See: U.S. Energy Information Administration, U.S. Aviation Gasoline Retail Sales by Reners, available at: http://www.eia.gov/dnav/pet/hist/LeafHandler.ashx?n=PET&s=EMA_EPPV_ PTG_NUS_DPG&f=M 64 DND Update, supra, note 2, p. 41 65 Lee Berthiaume, F-35 debate: All you need to know before it hits parliament, Postmedia News, 22 April 2012, available at: http://news.nationalpost.com/2012/04/22/qa-all-you-need-toknow-before-the-f-35-debate-hits-parliament/ 66F-35 Fighters: Top General Walt Natynczyk Says 65 Is Minimum Number Of Jets Needed By Air Force, Canadian Press, 3 November 2011, available at: http://www.huffingtonpost. ca/2011/11/03/top-commander-says-65-is-f35-jets-enough_n_1073984.html

30

Canadian Centre for Policy Alternatives

You might also like