The Plane That Ate The Canadian Military
The Plane That Ate The Canadian Military
The Plane That Ate The Canadian Military
www.policyalternatives.ca
RESEARCH
ANALYSIS
SOLUTIONS
Michael Byersholds the Canada Research Chair in Global Politics and International Law at the University of British Columbia. Prior to 2005, he was Professor of Law and Director of the Center for Canadian Studies at Duke University. Dr. Byers is the author or editor of seven books and hundreds of articles, including Canadas F-35 purchase is a costly mistake, (2011) 17 Canadian Foreign Policy Journal 217227 (with Stewart Webb).
ISBN978-1-77125-127-3 This report is available free of charge at www. policyalternatives.ca. Printed copies may be ordered through the CCPA National Office for $10. Please make a donation... Help us to continue to offer our publications free online. With your support we can continue to produce high quality researchand make sure it gets into the hands of citizens, journalists, policy makers and progressive organizations. Visit www.policyalternatives.ca or call 613-563-1341 for more information. The CCPA is an independent policy research organization. This report has been subjected to peer review and meets the research standards of the Centre.
The opinions and recommendations in this report, and any errors, are those of the authors, and do not necessarily reflect the views of the funders of this report.
5 Summary 6 1. Introduction 7 2. History 9 3. Operating and Other Costs Not Acknowledged by DND 12 4. Acquisition Cost Sensitivities and Risk 16 5. Sustainment Cost Sensitivities and Risk 17 6. Operating Cost Sensitivities and Risk 18 7. Contingency Planning Is Inadequate or Absent 20 8. Recommendations
21 Appendix I 22 Appendix II 25 Appendix III 26 Notes
I hope no one is assessing [the F-35 procurement] as low risk. Auditor General Sheila Fraser, October 20101
Summary
The Harper government anticipates a total project cost of $45.69 billion for a eet of 65 F-35s, including an operating cost of $19.857 billion. However, those gures are based on the operating cost of CF-18s rather than the actual operating cost of F-35s. Information on the latter is readily available from the U.S. government. The actual operating cost of a eet of F-35s would be $29.786 billion, leading to a total project cost of $55.619 billion. The Harper government has also failed to acknowledge the considerable cost risks and uncertainty associated with a eet of F-35srisks that are amplied by the developmental character and the unusually high operating and sustainment costs of these particular aircraft. Once cost risks and uncertainty are taken into account, the total project cost of a eet of F35s could be as high as $126 billion.
1. Introduction
In August 2013, the Department of National Defence (DND) released the Next Generation Fighter Capability Annual Update (DND Update).2 The DND Update anticipates a total project cost of $45.69 billion for a eet of 65 F-35s, including an operating cost of $19.857 billion. The DND Update does not provide any information on the cost of aircraft other than the F-35. Moreover, the DND Update makes the mistake of using the operating cost of CF-18s to project, on a dollar-to-dollar basis, the operating cost of F-35s. In fact, the operating cost of CF-18s is approximately one-third less than the operating cost of F-35s (as projected by the U.S. government).3 The actual operating cost of a eet of F-35s would be $29.786 billion, leading to a total project cost of $55.619 billion. In other words, correcting just this error adds approximately $10 billion to the total project cost of a Canadian eet of F-35s. The Harper government has also failed to include a number of other costs, including the full cost of munitions as well as the cost of modifying Canadas mid-air refuelling eet and adding drag chutes to the F-35s to enable them to use Arctic runways. Together, these costs add $1.055 billion, bringing the total project cost (including the actual operating cost) to $56.674 billion. Last but not least, the Harper government has failed to acknowledge the considerable cost risks and uncertainty associated with a eet of F35s. Some of these risks would apply to any model of aircraft, but they are amplied because the F-35 is still under development and has higher operating and sustainment costs than alternative aircraft. As this report demonstrates, higher operating and sustainment costs make the F-35 especially vulnerable to changes in exchange rate, ination, cost of aviation fuel, and yearly ying rate. This report builds upon a section on cost risks and uncertainty in the DND Update. Specically, it extrapolates DNDs information and analysis into two entirely possible moderate and serious scenarios. It is important to realize that neither of the scenarios even approaches a worst-case scenario, which might involvefor examplea 60-cent dollar, 10 percent ination rate, and $3/litre aviation fuel. But they do demonstrate how an accumulation of much smaller changes could easily cause the cost of an F-35 procurement to more than double. It is also important to realize that the greatly increased costs resulting from the accumulation of small changes in the moderate and serious scenarios could just as easily result from a single large change to a single
factor, such as the exchange rate or ination rate, within the historic parameters of a 60-cent dollar or 10 percent ination rate. Cost risks and sensitivity are exceedingly important when planning a procurement that will stretch over more than a decade and involve many billions of tax dollars. Of course, cost sensitivities can also lead to positive outcomes, such as better exchange rates and lower ination, that would result in a lower overall project cost. However, from a planning perspective it is more sagacious to assess and guard against negative risk. Cost risks and sensitivity take on even greater importance in light of reports that the Harper government is postponing the decision on the replacement of Canadas CF-18s until after 2015, which would stretch the time frame for the procurement further.4 A line-by-line explanation of the nancial implications of this reports moderate and serious scenarios is provided in Appendix II. But the bottom line is this: Once actual operating cost and cost risks and uncertainty are taken into account, a eet of F-35s could cost $126 billion. That is $81 billion more than the $45 billion currently projected by the Harper government. An additional $81 billion in unplanned cost could destroy the Canadian military, which would be forced to carry most of that cost through reduced expenditures on other equipment, maintenance, infrastructure, salaries and training. Even the moderate scenario, which carries an additional $45 billion in unplanned cost, would have profoundly negative, across-the-board impacts on the men and women who serve.
2. History
The cost of F-35s rst became an issue in July 2010 when the Harper government announced it would purchase 65 of the aircraft for $9 billion, with $7 billion in maintenance cost bringing the total cost to $16 billion over a 20-year period.5 In March 2011, the Parliamentary Budget Office (PBO) released a report examining the increasing weight of ghter jets and the cost-per-pound of their production. These historic trends were then used to estimate a total project cost of $29.3 billion for the F-35s.6 The PBO number includes $11.4 billion in acquisition cost and $17.9 billion in sustainment cost and upgrades over a 30-year perioda decade longer than the period used by the Harper government in July 2010.
The Harper government responded harshly to the PBO report, with MP Laurie Hawn, then Parliamentary Secretary to the Minister of National Defence, dismissing the analysis as speculative and illogical.7 Two weeks later, the governments refusal to provide Parliament with details about the cost of F-35s contributed to its defeat in a non-condence vote.8 In April 2012, Auditor General Michael Ferguson produced a report that criticised DND for having failed to exercise due diligence in managing the process to replace the CF-18 jets.9 He concluded: Full life-cycle costs were understated in the estimates provided to support the governments 2010 decision to buy the F-35. Some costs were not fully provided to parliamentarians. More specically, the Auditor General found that the Harper government had been operating with two numbers: citing a number of $14.7 billion when responding to the 2011 PBO report publicly, while using a number of $25.1 billion internally. Finally, he noted that the Harper government had chosen not to include operating cost in its public estimate, despite this information being specically required by DND and the Treasury Board, and requested by Parliament in 2010. The Harper government responded to the Auditor Generals report by suspending the F-35 procurement, ordering the Royal Canadian Air Force (RCAF) to conduct an options analysis re-evaluating the F-35 and alternative aircraft, and setting a $9 billion limit for the acquisition cost.10 An Independent Review Panel was established and tasked with overseeing the RCAF report.11 The Harper government also commissioned accounting rm KPMG to clarify the cost of an F-35 procurement. In November 2012, the rm released Next Generation Fighter Capability: Independent Review of Life Cycle Cost (KPMG Review). The KPMG Review projects a 30-year life-cycle cost of $45.8 billion, including $982 million for attrition, i.e. the replacement of aircraft lost through accidents.12 It also includes an operating cost for the F-35s, though it bases this cost on the operating cost of Canadas existing eet of CF-18s. The DND Update, released in August 2013, applies the KPMG methodology and 30-year time frame to the full life-cycle cost of the F-35s.13 Like the KPMG Review, the DND Update bases the operating cost of the F-35 on the operating cost of the CF-18. The DND Update then estimates the total project cost of the F-35s at $45.6 billion, including $1 billion for attrition. Signicantly, the DND Update includes a section on cost risks and uncertainty that examines some of the cost sensitivities involved in the possible purchase of F-35s, such as changes in the Canada-U.S. exchange rate,
ination rate, cost of aviation fuel, yearly ying rate, and rate of aircraft production by Lockheed Martin. The present report addresses the actual operating cost of F-35s as well as several other costs overlooked in the DND Update. It also extrapolates from the DND Updates tentative foray into cost risks and uncertainty, extending its information and analysis into moderate and serious scenarios. The two scenarios involve entirely possible circumstances that are far from worst-case. Yet they are sufficient to raise serious questions about the wisdom and nancial feasibility of an F-35 procurement, as well as the Harper governments lack of attention to substantial nancial risks.
The use of the CF-18 operating cost is fanciful. Although the F-35 was originally expected to have lower sustainment and operating costs than legacy aircraft like the CF-18, the costs based on evidence to date have become signicantly higher than those of legacy aircraft, including the CF-18. In 2011, the U.S. Government Accountability Office (GAO) wrote:
Current JSF [Joint Strike Fighter or F-35] life-cycle cost estimates are considerably higher than the legacy aircraft it will replace; this has major im-
plications for future demands on military operating and support budgets and plans for recapitalizing ghter forces.17
More recently, the U.S. GAO identies a cost of US$35,200 per ying hour for the F-35.18 Similarly, the U.S. Department of Defenses latest Selected Acquisition Report for the F-35 identies a cost of US$31,900 per ying hour.19 In comparison, the latest Selected Acquisition Report for the Boeing Super Hornet enables one to identify an operating cost of US$15,600 per hour for that aircraft20based on an annual cost in 2000 dollars, divided by ying time, and then converted to 2012 dollars.21 Boeing, which also manufactured the CF-18, told the CBC in 2013 that Super Hornets are 25 percent less expensive to operate than CF-18s.22 By extrapolation, this means CF-18s cost approximately US$20,800 per ying hour to operate. In 2012, MP Laurie Hawn, a former CF-18 squadron commander and Parliamentary Secretary to the Minister of National Defence, told the Hill Times that the CF-18 operating cost is approximately $19,000 per ying hour.23 The 25 percent difference in operating cost between the Super Hornet and the CF-18 makes sense given that the CF-18s are at the very end of their lifespan and in need of more day-to-day maintenance. The present report multiplies the DND Updates number for the operating cost of an F-35 eet (i.e. the operating cost of the existing CF-18 eet) by 1.5 to provide a more realistic estimate; one that is based on the roughly 2-to3 ratio of CF-18 to F-35 operating cost identied above. The resulting estimate$31,200 per houris still conservative, compared to the US$35,200 from the U.S. GAO and the US$31,900 from the U.S. Department of Defence. Moreover, even the U.S. numbers for the operating cost of the F-35 could be low, given the serious, ongoing uncertainties concerning new stealth materials and complex computingincluding 24 million lines of code, fused sensors, and a head-up display helmet.
(b) Munitions
Initially, DND anticipated spending $270300 million on weapons and bombs to equip a eet of F-35s.24 But in 2013, that amount was reduced to $52 million, with the DND Update stating:
Weapons currently in the Canadian Armed Forces inventory that can be employed on the F-35A eet will be retained. In the case of the F-35A, the project acquisition cost estimate provides for the acquisition of an initial stock
10
of gun ammunition and countermeasures (e.g., ares), as the existing stock of CF-18 gun ammunition and ares are incompatible with the F-35A. Over the life cycle of the replacement eet, the acquisition of newer weapons will be considered and funded as separate projects.25
The approach taken in the DND Update is misleading. Any weapons that foreseeably need to be acquired for the F-35s during their operational lifespan should be included within the total life-cycle cost of the eet rather than treated as separate projects. For this reason, this report uses the low end of DNDs initial estimate for weapons ($270 million), which, after deducting the current estimate of $52 million, results in the addition of $218 million to the tabulations below.
11
add to the life-cycle cost of Canadas eet. For this reason, $200 million has been added to the tabulations below.
The DND Update explains that, if the Canadian dollar were valued at 78 cents per U.S. dollar, instead of 92 cents, this would add $1.6 billion to the acquisition cost of an F-35 eet.32 This report uses the 78 cents per U.S. dollar exchange rate for its serious scenario estimate. For its moderate scen-
12
ario estimate, this report uses an exchange rate of 85 cents per U.S. dollar, which would add $800 million to the acquisition cost.
13
tion of the development cost would be shifted to Canada. For the purposes of generating actual numbers, it assumes a relatively conservative amount of $1.8 billion, or the equivalent of a 20 percent increase in the acquisition cost of an F-35 eet.
14
quences for Canada: [I]f partner nations delay the timing of their purchases and/or reduce the number of aircraft they purchase up to and during, the period Canada would be purchasing its aircraft, the unit price for Canadian orders may be higher.40 The DND Update assesses the maximum decrease in purchases at 250 aircraft, which would result in an increase in the acquisition cost for Canada of approximately $600 million.41 However, the reduction in total orders could be larger. The United States has dramatically reduced the number of F-35s it is purchasing in the early years of the program, which could lead to a signicant reduction in its planned total of 2,443 aircraft.42 It bears remembering that only 187 of 750 originally planned F-22s were ever built, with the production line for the F-35s sister aircraft shut down for budgetary reasons in 2009.43 The United Kingdom has indicated that it will purchase fewer than the 138 F-35s it originally planned, and some reports suggest it might only acquire 50 aircraft.44 The Netherlands has gone from 85 to 37 aircraft and Italy from 131 to 90.45 Denmark and Turkey have gone from decided purchasers to undecided potential purchasers.46 Australia originally planned to purchase 100 F-35s, but then purchased 24 Super Hornets, which may well lead to a reduction in its F-35 order.47 In April 2014, Australia announced the purchase of 58 F-35s, taking its total to 72 F-35sstill short of the 100 F-35s originally planned.48 The uncertainty is increased by the existence of some movement in the opposite direction, with South Korea announcing in March 2014 that it will purchase F-35s rather than Boeing F-15 Silent Eagles.49 But only 40 F-35s will be bought, down one-third from an initially planned 60 aircraft. This report, in its moderate scenario, uses the same 250-plane reduction that DND concluded would lead to an increase of $600 million in the acquisition cost. In its serious scenario, this report uses a 500-plane reduction that would add $1.2 billion to the acquisition cost.
15
must be a necessary and integral part of achieving the minimum number of planes necessary for an operational eet. The DND Update follows the Harper governments approach of excluding attrition cost from acquisition cost, while noting that between 7 and 11 replacement aircraft would likely be required over the lifespan of any eet, at an additional acquisition cost of approximately $1 billion.52 This report follows the approach taken by the other countries, consistent with the advice from Defence Research and Development Canada. Attrition cost is a necessary and integral part of the acquisitionand, for this reason, this report subjects the $1 billion attrition cost to the same extrapolations of nancial risk as were applied to the initial 65 aircraft earlier in this section. This generates an additional cost of $1 billion (total $2 billion for attrition) for the moderate scenario and an additional cost of $1.9 billion (total $2.9 billion for attrition) for the serious scenario.
16
17
18
Under the serious scenario, the total acquisition cost rises to $18.79 billion, or $289 million per plane. As the DND Update explains, the Harper governments only contingency plan for increases in acquisition cost involves a reduction in the number of planes purchased.64 In other words, if the cost-per-plane rises, Canada will purchase fewer planes in order to stay within the $9 billion acquisition limit. DND originally sought 80 F-35s; the reduction to 65 aircraft occurred in 2010.65 DND has repeatedly stated that 65 is the minimum number of ghter jets needed for an operationally capable eet.66 If Canada decides to purchase F-35s, the possible increases in acquisition cost identied in this report could force a future government to choose between exceeding the $9 billion limit in order to buy 65 F-35s, or settling for a smaller, operationally incapable eet. Under the moderate scenario developed here, Canada could only purchase 45 planes while staying under the $9 billion limit. Under the serious scenario, Canada could purchase only 34 planes.
19
8. Recommendations
This report demonstrates that the Harper government is understating the total project cost of a eet of F-35s by $11 billion, even without taking cost risks and uncertainty into account. Once cost risks and uncertainty are taken into account, the possible total project cost rises to $90 billion in a moderate risk scenario and $126 billion in a serious risk scenario. With this information now at hand, the Harper government should: Update its cost projection by including the actual operating cost of F-35s, the full cost of munitions, and the cost of modifying Canadas mid-air refuelling eet, adding drag chutes to the F-35s, and paying Canadas share of the computer programming facility; Expand the Department of National Defences tentative 2013 foray into the cost risks and uncertainty associated with the F-35 by conducting the type of analysis carried out in this report; Conduct the same analysis of cost risks and uncertainty with regard to alternative aircraft; Make those analyses available for public scrutiny and debate in advance of any decision to acquire F-35s.
20
Appendix I
Operating and Other Actual Costs Not Acknowledged in DND Update
Operating Cost Operating cost (DND Update, based on CF-18 eet): $19.857 billion Actual operating cost of F-35 eet (add $9.929 billion, based on numbers from Boeing, MP Laurie Hawn, U.S. GAO & U.S. DOD): $29.786 billion Total project cost (DND Update): $45.69 billion Adjusted total project cost (including actual operating cost): $55.619 billion Other Actual Costs Not Acknowledged in the DND Update Munitions (added life-cycle cost): $0.218 billion Modifying mid-air refuelling eet: $0.42 billion Adding drag chute to F-35s: $0.20 billion Computer programming facility: $0.217 billion Total additional actual costs not acknowledged in DND Update: $1.055 billion Total project cost (DND update): $45.69 billion Adjusted total project cost (including all actual costs): $56.674 billion
21
Appendix II
Cost Risks and Uncertainty in Moderate and Serious Scenarios
Note: All bold numbers are taken from the 2013 DND Update; all italic numbers are extrapolated from the calculations of risk in that same document. Development Cost (DND Update; already paid)$0.606 billion Acquisition Cost (DND Update)$8.99 billion moderate scenario: 85 cent dollaradds $0.8 billion 2 percent ination increaseadds $1 billion 3 percent decrease in learning and production efficiency adds $1.6 billion Reduction of 250 planes in initial ordersadds $0.6 billion Total adjusted acquisition (moderate scenario) = $12.99 billion ($200 million per plane) serious scenario: 78 cent dollaradds $1.6 billion 4 percent ination increaseadds $2 billion Some development cost imposed on Canadaadds $1.8 billion 6 percent decrease in learning and production efficiency adds $3.2 billion Reduction of 500 planes in initial ordersadds $1.2 billion Total adjusted acquisition (serious scenario) = $18.79 billion ($289 million per plane)
22
Sustainment Cost (DND Update)$15.055 billion moderate scenario: 85 cent dollaradds $1.05 billion 2 percent ination increaseadds $6.2 billion Increase yearly ying rate by 2,000 hoursadds $1 billion Total adjusted sustainment (moderate scenario) = $23.305 billion serious scenario: 78 cent dollaradds $2.1 billion 4 percent ination increaseadds $12.4 billion Increase yearly ying rate by 4,000 hoursadds $2 billion Total adjusted sustainment (serious scenario) = $31.555 billion Operating Cost (DND Update)$19.857 billion Note: $19.857 billion is the operating cost of the CF-18 eet, which needs to be multiplied by 1.5 to reect the actual operating cost of an F-35 eet. This provides an operating cost of $29.786 billion, without any of the adjustments below. moderate scenario, starting with $19.857 billion (cf-18 cost): 2 percent ination increaseadds $10.8 billion Increase yearly ying rate by 2,000 hoursadds $0.75 billion 50 percent increase in price of aviation fueladds $2.15 billion Total adjusted operating cost (moderate scenario) = $33.557 billion (adjusted CF-18 operating cost) 1.5 = $50.336 billion serious scenario, starting with $19.857 billion (cf-18 cost): 4 percent ination increaseadds $21.6 billion Increase yearly ying rate by 4,000 hoursadds $1.5 billion 100 percent increase in price of aviation fueladds $4.3 billion Total adjusted operating cost (serious scenario) = $47.257 billion (adjusted CF-18 operating cost) 1.5 = $70.886 billion
23
Disposal Cost at End of Aircraft Lifespan (DND Update) $0.168 billion additional actual costs not acknowledged in dnd update Munitions (added life-cycle cost): $0.218 billion Modifying mid-air refuelling eet: $0.42 billion Adding drag chute to F-35s: $0.20 billion Computer programming facility: $0.217 billion Total additional actual costs not acknowledged in DND Update: $1.055 billion Total Life-Cycle Cost (DND Update)$44.676 billion Adjusted Total Life-Cycle Cost (moderate scenario): $88.46 billion Adjusted Total Life-Cycle Cost (serious scenario): $123.06 billion Attrition (DND Update)$1.015 billion Adjusted Attrition (moderate scenario): $2 billion Adjusted Attrition (serious scenario): $2.9 billion Total Project Cost (DND Update)$45.69 billion Adjusted Total Project Cost (moderate scenario): $90.46 billion Adjusted Total Project Cost (serious scenario): $125.96 billion
24
Appendix III
Total Project Cost Estimates for Canadian Fleet of F-35s
Figure 1Total Project Cost Estimates (Billions)
$140 $126 Billion $120 $100 $80 $60 $45 Billion $40 $25 Billion $20 $0 $16 Billion $29 Billion $45 Billion $56 Billion $57 Billion
$90 Billion
20
Ad j
te us op ted er fo at r a in c g tu co al st
KP
13
20
13
DN
Up
da
20
10
Ha
ac
25
Notes
1 David Pugliese, Auditor General Fraser warns about F-35. Her report nds DND low-balled cost on Chinooks, Ottawa Citizen, 26 October 2010, available at: http://blogs.ottawacitizen. com/2010/10/26/auditor-general-fraser-warns-about-f-35-her-report-finds-dnd-low-balled-coston-chinooks/ 2 Department of National Defence, Next Generation Fighter Capability2013 Annual Update, 9 August 2013, available at: http://www.forces.gc.ca/assets/FORCES_Internet/docs/en/aboutreports-pubs/ngfc-annual-update-2013.pdf 3 See citations, Section 3(a) below. 4 Tim Naumetz, Feds to delay F-35 decision until after next federal election, The Hill Times, 26 March 2014, available at: http://www.hilltimes.com/news/politics/2014/03/26/feds-to-delayf-35-decision-until-after-next-federal-election/37978?mcl=694&muid=2086 5 CTV News, Tories defend sole-sourced $16B jet purchase, 16 July 2010, available at: http:// www.ctvnews.ca/tories-defend-sole-sourced-16b-jet-purchase-1.533465 6 Parliamentary Budget Office, An Estimate of the Fiscal Impact of Canadas Proposed Acquisition of the F-35 Lightning II Joint Strike Fighter, 10 March 2011, available at: http://www.parl. gc.ca/PBO-DPB/documents/F-35_Cost_Estimate_EN.pdf 7 Murray Brewster, Budget officers numbers on F-35 illogical, Conservatives say, Canadian Press, 11 March 2011, available at: http://www.thestar.com/news/canada/2011/03/11/budget_ officers_numbers_on_f35_illogical_conservatives_say.html 8 Associated Press, Canadian government collapses in no-condence vote, 26 March 2011, available at: http://www.theguardian.com/world/2011/mar/26/canadian-government-no-confidence-vote 9 Office of the Auditor General of Canada, 2012 Spring Report of the Auditor General of Canada: Chapter 2, Replacing Canadas Fighter Jets, 3 April 2012, available at: http://www.oag-bvg. gc.ca/internet/docs/parl_oag_201204_02_e.pdf 10 See, e.g.: Department of National Defence, StatementGovernment of Canada announces comprehensive response to Chapter 2 of the 2012 Spring Report of the Auditor General of Can-
26
ada, 3 April 2012, available at: http://www.forces.gc.ca/en/news/article.page?doc=governmentof-canada-announces-comprehensive-response-to-chapter-2-of-the-2012-spring-report-of-theauditor-general-of-canada/hir3oy82 11 Steven Chase, Tories seek alternatives to F-35 jet as cost soars to more than $40-billion, The Globe and Mail, 6 December 2012, available at: http://www.theglobeandmail.com/news/ politics/tories-seek-alternatives-to-f-35-jet-as-cost-soars-to-more-than-40-billion/article6064818/ 12 KPMG, Next Generation Fighter Capability: Independent Review of Life Cycle Cost, 27 November 2012, available at: https://www.tbs-sct.gc.ca/reports-rapports/ngfc-cng/irlc-eiccv/irlceiccv-eng.pdf 13 DND Update, supra, note 2 14 KPMG Review, supra, note 12, p. 2 15 KPMG Review, supra, note 12, p. 2 16 DND Update, supra, note 2, p. 42 17 U.S. Government Accountability Office, Joint Strike Fighter: Restructuring Places Program on Firmer Footing, but Progress Still Lags, 7 April 2011, p. 9, available at: http://www.gao.gov/ assets/320/317548.pdf 18 U.S. Government Accountability Office, Joint Strike Fighter: DOD Actions Needed to Further Enhance Restructuring and Address Affordability Risks, 14 June 2012, p. 11, available at: http:// gao.gov/assets/600/591608.pdf 19 U.S. Department of Defense, Selected Acquisition Report: F-35 Joint Strike Fighter Aircraft, 23 May 2013, available at: http://www.dod.mil/pubs/foi/logistics_material_readiness/acq_bud_ fin/SARs/2012-sars/13-F-0884_SARs_as_of_Dec_2012/DoD/F-35_December_2012_SAR.pdf 20 U.S. Department of Defense, Selected Acquisition Report: F/A-18E/F Super Hornet Aircraft, 21 May 2013, available at: http://www.dod.mil/pubs/foi/logistics_material_readiness/acq_bud_ fin/SARs/2012-sars/13-F-0884_SARs_as_of_Dec_2012/Navy/F-A-18E-F_December_2012_SAR.pdf 21 Bill Sweetman, Math Is Hard, Aviation Week blog, 24 January 2014, available at: http://www.aviationweek.com/Blogs.aspx?plckBlogId=Blog:27ec4a53-dcc8-42d0-bd3a01329aef79a7&plckPostId=Blog%3A27ec4a53-dcc8-42d0-bd3a-01329aef79a7Post%3Ae14a3e0c3267-4c81-a2fd-01dff925bdf3 22 Terry Milewski, Boeing touts ghter jet to rival F-35at half the price, CBC News, 27 February 2013, available at: http://www.cbc.ca/news/politics/boeing-touts-fighter-jet-to-rival-f-35at-half-the-price-1.1320636 23 Tim Naumetz, Conservative MP Hawn estimates CF-18 costs $12,000 less per ying hour than F-35 ghter jet, Hill Times, 17 May 2012, available at: http://www.hilltimes.com/news/ politics/2012/05/17/conservative-mp-hawn-estimates-cf-18-costs-%2412000-less-per-flyinghour-than-f-35/30780 24 Murray Brewster, National Defence to buy fewer bombs if F-35 selected as new air force ghter, Canadian Press, 14 February 2013, available at: http://montreal.ctvnews.ca/national-defenceto-buy-fewer-bombs-if-f-35-selected-as-new-air-force-fighter-1.1157706 25 DND Update, supra, note 2, p. 19 26 Lee Berthiaume, Air force brass say air-to-air refuelling critical for next ghter, F-35 incompatible with current systems, Postmedia, 14 June 2013, available at: http://o.canada.com/ news/air-force-brass-say-air-to-air-refuelling-critical-for-next-fighter-f-35-incompatible-withcurrent-systems/
27
27 Lee Berthiaume, Air force brass say air-to-air refuelling critical for next ghter, F-35 incompatible with current systems, Postmedia, 14 June 2013, available at: http://o.canada.com/ news/air-force-brass-say-air-to-air-refuelling-critical-for-next-fighter-f-35-incompatible-withcurrent-systems/ 28 Jerome Lessard, F-35 chute production may land in town, The Intelligencer (Belleville), 8 November 2013, available at: http://www.intelligencer.ca/2013/11/08/f-35-chute-productionmay-land-in-town 29 David Pugliese, Canada still involved in F-35 programming, Postmedia News, 19 August 2013, http://www2.canada.com/montrealgazette/news/archives/story.html?id=6d55ab05-a85f4ca0-9efd-79df42400eba 30 David Pugliese, Canada still involved in F-35 programming, Postmedia News, 19 August 2013, http://www2.canada.com/montrealgazette/news/archives/story.html?id=6d55ab05-a85f4ca0-9efd-79df42400eba 31 DND Update, supra, note 2, p. 31 32 DND Update, supra, note 2, p. 32 33 DND Update, supra, note 2, p. 34 34 CBC News, Harper vows modest cuts but offers few details, 10 April 2011, available at: http://www.cbc.ca/news/politics/harper-vows-modest-cuts-but-offers-few-details-1.1077028. See also: Alan Williams, Lets be honest about the price tag on those planes, Ottawa Citizen, 23 March 2011, available at: http://www2.canada.com/ottawacitizen/story.html?id=a790b5dafc84-4582-ab60-32122897cb4d 35 Winslow Wheeler, The Latest Word on F-35 Unit Cost, Project on Government Oversight, 3 January 2014, available at: http://www.pogo.org/blog/2014/01/the-latest-word-on-f-35-unit-cost.html 36 John Ivison, Political reality may force Tories to change broken record routine on F-35, National Post, 13 February 2012, available at: http://fullcomment.nationalpost.com/2012/02/13/f35-john-ivison/ 37 See, e.g.: U.S. Department of Defense, Director of Operational Test Evaluation, F-35 Joint Strike Fighter (JSF), January 2013, available at: http://www.dote.osd.mil/pub/reports/FY2013/ pdf/dod/2013f35jsf.pdf 38 Lee Berthiaume, Government may have underestimated cost of new resupply ships, Postmedia, 13 February 2013, available at: http://o.canada.com/news/national/government-mayhave-underestimated-cost-of-new-resupply-ships/ 39 DND Update, supra, note 2, p. 33 40 DND Update, supra, note 2, p. 34 41 DND Update, supra, note 2, p. 34 42 Tony Capaccio, Lockheed F-35 Said to Be Cut by 13 Planes in Pentagons Budget, Bloomberg News, 25 January 2012, available at: http://www.bloomberg.com/news/2012-01-25/lockheed-f-35said-to-be-cut-by-13-planes-in-pentagon-s-plan.html ; Bloomberg News, Pentagon to trim plans for F-35 jet order, 16 February 2014, available at: http://www.washingtonpost.com/politics/pentagonto-trim-plans-for-f-35-jet-order/2014/02/16/2310f400-974c-11e3-8461-8a24c7bf0653_story.html 43 R. Jeffrey Smith, High-Priced F-22 Fighter Has Major Shortcomings, Washington Post, 10 July 2009, available at: http://www.washingtonpost.com/wp-dyn/content/article/2009/07/09/ AR2009070903020.html
28
44 Rhys Jones, Britain wont decide on F-35 ghter numbers till 2015, Reuters, 7 February 2012, available at: http://www.reuters.com/article/2012/02/07/us-lockheed-britain-fidUSTRE8160ZB20120207 45 David Pugliese, Drop in Numbers of F-35s Being Ordered Could Mean Increased Costs For a Canadian F-35, Ottawa Citizen, 22 September 2013, available at: http://blogs.ottawacitizen. com/2013/09/22/drop-in-numbers-of-f-35s-being-ordered-could-mean-increased-costs-for-acanadian-f-35/ 46Ibid. 47 Lania Vasek, F-35 Joint Strike Fighter delays could force Australia to revert to Super Hornet, The Australian, 6 January 2012, available at: http://www.theaustralian.com.au/nationalaffairs/policy/further-f-35-joint-strike-fighter-delays-could-force-australia-to-revert-to-the-superhornet/story-e6frg8yo-1226238241670 48 BBC News, Australia to buy 58 new F-35 ghter jets, 23 April 2014, available at: http://www. bbc.com/news/business-27122188 49 Doug Cameron & Jeyup S. Kwaak, Lockheed Martin to Get $6.8 Billion Order From South Korea, Wall Street Journal, 24 March 2014, available at: http://online.wsj.com/news/articles/ SB10001424052702303949704579458803559185982 50F-35 Fighters: Top General Walt Natynczyk Says 65 Is Minimum Number Of Jets Needed By Air Force, Canadian Press, 3 November 2011, available at: http://www.huffingtonpost. ca/2011/11/03/top-commander-says-65-is-f35-jets-enough_n_1073984.html 51 Lee Berthiaume, National Defence expected to lose some F-35s before all 65 delivered: Report, Postmedia News, 28 April 2013, available at: http://news.nationalpost.com/2013/04/28/ national-defence-expected-to-lose-some-f-35s-before-all-65-delivered-report/ 52 DND Update, supra, note 2, p. 14 53 DND Update, supra, note 2, p. 37 54 DND Update, supra, note 2, p. 37 55 DND Update, supra, note 2, p. 37 56 W.J. Hennigan & Ralph Vartabedian, F-35 ghter jet struggles to take off, Los Angeles Times, 12 June 2013, available at: http://www.latimes.com/business/la-fi-0612-fighter-jet-testing-20130612dto,0,4701367.htmlstory#axzz2yPXvAlsn 57 DND Update, supra, note 2, p. 37 58 Canadian Press, Dassault Aviation ramps up CF-18 replacement pitch, 22 January 2014, available at: http://www.cbc.ca/news/politics/dassault-aviation-ramps-up-cf-18-replacementpitch-1.2507029 59 Canadian Press, Dassault Aviation ramps up CF-18 replacement pitch, 22 January 2014, available at: http://www.cbc.ca/news/politics/dassault-aviation-ramps-up-cf-18-replacementpitch-1.2507029 60 DND Update, supra, note 2, p. 38 61 DND Update, supra, note 2, p. 38 62 DND Update, supra, note 2, p. 38
29
63 See: U.S. Energy Information Administration, U.S. Aviation Gasoline Retail Sales by Reners, available at: http://www.eia.gov/dnav/pet/hist/LeafHandler.ashx?n=PET&s=EMA_EPPV_ PTG_NUS_DPG&f=M 64 DND Update, supra, note 2, p. 41 65 Lee Berthiaume, F-35 debate: All you need to know before it hits parliament, Postmedia News, 22 April 2012, available at: http://news.nationalpost.com/2012/04/22/qa-all-you-need-toknow-before-the-f-35-debate-hits-parliament/ 66F-35 Fighters: Top General Walt Natynczyk Says 65 Is Minimum Number Of Jets Needed By Air Force, Canadian Press, 3 November 2011, available at: http://www.huffingtonpost. ca/2011/11/03/top-commander-says-65-is-f35-jets-enough_n_1073984.html
30