TCVN 6474-2007 Eng
TCVN 6474-2007 Eng
TCVN 6474-2007 Eng
= density of sea water, 1,027 kg/m
3
C
D
= drag coefficient, in steady flow (dimensionless)
u
c
= current velocity vector normal to the plane of projected
area, in m/s
TCVN 6474-2:2007
65
A
c
= projected area exposed to current, in m
2
.
1.4.4 Wind
The wind conditions for various design conditions are to be established from
collected wind data and should be consistent with other environmental parameters
assumed to occur simultaneously. In general, the wind speed is to be based on a
recurrence period of 100 years.
The environmental report is to present wind statistics for the site of installation. The
statistics are to be based on the analysis and interpretation of wind data by a
recognized consultant. The report is to include a wind rose or table showing the
frequency distributions of wind velocity and direction and a table or graph showing
the recurrence period of extreme winds. The percentage of time for which the
operational phase limiting wind velocity is expected to be exceeded during a year
and during the worst month or season is to be identified.
1.4.4.1 Wind Load
The wind loading can be considered either as a steady wind force or as a
combination of steady and time-varying load, as described below:
(1) When wind force is considered as a constant (steady) force, the wind velocity
based on the 1-minute average velocity is to be used in calculating the wind load.
(2) Effect of the wind gust spectrum can be taken into account by considering
wind loading as a combination of steady load and a time-varying component
calculated from a suitable wind spectrum. For this approach, the wind velocity
based on 1-hour average speed is to be used for steady wind load calculation. The
first approach is preferred to this approach when the wind energy spectrum cannot
be derived with confidence.
Wind pressure, pw, on a particular windage of a floating vessel may be calculated
as drag forces using the following equations:
P
w
= 0.610 C
s
C
h
V
r
2
N/m
2
V
r
in m/s
= 0.0623 C
s
C
h
V
r
2
kgf/m
2
V
r
in m/s
= 0.00338 C
s
C
h
V
r
2
lbf/ft
2
V
r
in knots
TCVN 6474-2:2007
66
where
C
s
= Shape Coefficient (dimensionless), given in table 2-1
C
h
= Height Coefficient (dimensionless), given in table 2-2.
The height coefficient, Ch, in the above formulation accounts for the wind velocity
(Vw) profile in the vertical plane. The height coefficient, Ch, is given by the
following equation:
2
=
z
h
r
V
C
V
or
2
=
h
r
z
C
z
, but C
h
1
where the velocity of wind, V
z
, at a height, z, is to be calculated as follows:
=
z r
r
z
V V
z
V
r
= velocity of wind at an reference elevation, Z
r
, of 10 m
= 0.09 - 0.16 for 1-minute average wind
0.125 for 1-hour average wind.
The corresponding wind force, Fw, on the windage is
F
w
= p
w
. A
w
where:
A
w
= projected area of windage on a plane normal to the
direction of the wind, in m
2
The total wind force is then obtained by summing up the wind forces on each
windage
Representative values of C
h
are given in Table 2-2 of this standard. Wind profiles
for the specific site of the Floating Installation should be used.
The shape coefficients for typical structural shapes are presented in Table 2-1 of
this standard. To convert the wind velocity, V
t
, at a reference of 10 m (33 feet)
above sea level for a given time average, t, to velocity of another time average, the
following relationship may be used:
( ) 1 t h
V fV =
TCVN 6474-2:2007
67
Example values of the factor f for a specific waters are listed in Table 2-3 . Values
specific to the site of the Floating Installation are to be used.
Wind forces on Floating Installations other than ship-type are to be calculated by
the summation of wind forces on individual areas using the above formulas.
If the 1-hour average wind speed is used, the wind's dynamic effect should be
separately considered. The wind energy spectrum, as recommended in API RP 2A,
may be used.
1.4.5 Waves
Wave criteria are to be described in terms of wave energy spectra, significant wave
height and associated period for the location at which the Floating Installation is to
operate. Waves are to be considered as coming from any direction relative to the
vessel. Consideration is to be given to waves of less than the maximum height
because the wave-induced motion responses at waves with certain periods may be
larger in some cases due to the dynamic behavior of the system as a whole (floating
storage unit/ mooring system).
1.4.5.1 Wave Forces
The wave forces acting on a floating vessel consist of three components, i.e., first
order forces at wave frequencies, second order forces at frequencies lower than the
wave frequencies and a steady component of the second order forces. This steady
component of the wave force is called Mean Drift Force. The calculation of wave
loading is necessary for assessing the vessel motion responses and the mooring
system. It requires calculations of dynamic characteristics of the vessel and the
hydrodynamic loading on the vessel for a given environmental condition
For structures consisting of slender members that do not significantly alter the
incident wave field, semi-empirical formulations, such as Morison's equation, may
be used. For calculation of wave loads on structural configurations that
significantly alter the incident wave field, appropriate methods which account for
both the incident wave force (e.g., Froude-Krylov force) and the forces resulting
from wave diffraction are to be used. In general, application of Morison's equation
may be used for structures comprising slender members with diameters (or
TCVN 6474-2:2007
68
equivalent diameters giving the same cross-sectional areas parallel to the flow) less
than 20 percent of the wave lengths.
For a column-stabilized type of vessel consisting of large (columns and pontoons)
and small (brace members) cylindrical members, a combination of diffraction and
Morison's equation can be used for calculation of hydrodynamic characteristics and
hydrodynamic loading. The designer may refer to TCVN 5310: 2001.
Alternatively, the suitable model test results or full scale measurements can be
used.
Wave force calculations should account for shallow water effects which increase
current due to blockage effects, change the system natural frequency due to
nonlinear behavior of moorings and alter wave kinematics.
1.4.5.2 Wave-induced Vessel Motion Responses
The wave-induced response of a vessel consists of three categories of response, i.e.,
first order (wave frequency) motions, low frequency or slowly varying motions and
steady drift.
(1) First Order Motions: These motions have six degrees of freedom (surge, sway,
heave, roll, pitch and yaw see definitions in Part 1) and are at wave
frequencies that can be obtained from model tests in regular or random waves
or by computer analysis in frequency or time domain.
(2) Low Frequency Motions: These motions are induced by low frequency
components of second order wave forces. The low frequency motions of
surge, sway and yaw can be substantial, particularly at frequencies near the
natural frequency of the system. The low frequency motion-induced mooring
line tension in most systems with a tanker-type vessel is a dominating design
load for the mooring system. The low frequency motions are to be calculated
for any moored vessel by using appropriate motion analysis software or by
model test results of a similar vessel.
(3) Steady (Mean) Drift: As mentioned above, a vessel subjected to waves
experiences a steady drift along with the first and second order motions. The
mean wave drift force and yawing moment are induced by the steady
component of the second order wave forces. Mean drift forces and yawing
TCVN 6474-2:2007
69
moments are to be calculated using appropriate motion analysis computer
programs or extrapolated from model test results of a similar vessel.
1.4.6 Directionality
The directionality of environmental conditions can be considered if properly
documented by a detailed environmental report.
1.4.7 Soil Conditions
Soil data should be taken in the vicinity of the foundation system site. An
interpretation of such data is to be submitted by a recognized geotechnical
consultant. To establish the soil characteristics of the site, the foundation system
borings or probings are to be taken at all foundation locations to a suitable depth of
at least the anticipated depth of any piles or anchor penetrations plus a
consideration for the soil variability. As an alternative, sub-bottom profile runs may
be taken and correlated with at least two borings or probings in the vicinity of
anchor locations and an interpretation may be made by a recognized geotechnical
consultant to adequately establish the soil profile at all anchoring locations.
Table 2-1: Shape Coefficients Cs for Windages
Shape C
s
Sphere 0,4
Cylindrical Shapes 0,5
Hull above waterline 1,0
Deck House 1,0
Isolated structural shapes (Cranes, channels, beams, angles, etc.) 1,5
Under deck areas (smooth) 1,0
Under deck areas (exposed beams and girders) 1,3
Rig derrick 1,25
TCVN 6474-2:2007
70
Table 2-2: Height Coefficients C
h
for Windages
Height above Waterline Ch
m ft 1 min 1 hour
0 to < 15,3 0 to <50 1,00 1,00
15,3 to < 30,5 50 to <100 1,18 1,23
30,5 to < 46,0 100 to <150 1,31 1,40
46,0 to < 61,0 150 to <200 1,40 1,52
61,0 to < 76,0 200 to <250 1,47 1,62
76,0 to < 91,5 250 to <300 1,53 1,71
91,5 to < 106,5 300 to <350 1,58 1,78
Table 2-3: Wind Velocity Conversion Factor
Wind Duration factor f
1 hour 1,000
10 min 1,060
1 min 1,180
15 s 1,260
5 s 1,310
3 s 1,330
71
NATIONAL STANDARD TCVN 6474 -3 : 2007
Second edition
RULES FOR CLASSIFICATION AND TECHNICAL SUPERVISION OF
FLOATING STORAGE UNITS
PART 3 :TECHNICAL REQUIREMENTS
Reference standards and definitions: see Part 1 ,TCVN 6474-1: 2007
1 Technical requirements for floating storage units
1.1 All Vessels
1.1.1 General
1.1.1.1 This chapter cover the requirements for vessels (ship type and column stabilized) as
defined in Part 1. Other tyes ,as defined in 2.2.4 Part 1,will be considered on a
case-by-case basis.
1.1.1.2 This chapter cover the requirements for vessel that are newly designed or are
undergoing a major conversion that affects the principal dimensions of the floating
installation.The application of the requirements to existing vessel not undergoing
major conversion will be considered by VR based on the service history, age,
condition of the exsting floating installation.
1.1.1.3 The designer is required to submit to VR for review all applicable design
documentation, such as reports,calculation,plans and other documentation
necessary to verify the structural streng of the floating installation it self .The
submitted design documentation is to include the design environmetal condition
TCVN 6474 -3:2007
72
(see 1.4 Part 2).
1.1.2 Lightweight Data.
The lightweight and center of gravity are to be determined for vessels of all types .An
inclining test will be required for the first floating installation of a series, when as
near to completion as practical, to determine accurately the lightweight and position
of center of gravity . An inclining test procedure is to be submitted for review prior
to the test, which is to be witnessed by a Surveyor of VR .
1.1.3 Load Line
1.1.3.1 Every vessel is to have marks that designate the maximum permissible draft to which
the vessel may be loaded. Such markings are to be placed at suitable visible
locations on the hull or structure to the satisfaction of the Bureau. On column-
stabilized vessels, where practical, these marks are to be visible to the person in
charge of liquid transfer operations .
1.1.3.2 Except where otherwise permitted by the flag and coastal States, load line marks are
to be established under the terms of the International Convention of Load Lines,
1966. Where minimum freeboards cannot be computed by the normal methods laid
down by the convention, such as in the case of a column-stabilized unit, they are to
be determined on the basis of compliance with intact or damage stability
requirement for afloat modes of operation .
1.1.3.3 The vessels arrangements are to comply with all applicable regulations of the
International Convention on Load Lines.
1.1.4 Operating Manual
As for every kind of vessel ,Operating Manual include information as following, if
applicable , to be able to conduct operator to operate vessel in safety way:
1.1.4.1 A general description of the unit, including major dimensions, lightship
characteristics;
TCVN 6474 -3:2007
73
1.1.4.2 Summaries of approved modes of operation including for each mode of operation:
(1) Limiting environmental conditions, including wave height and period, wind
velocity, current velocity, minimum air and sea temperatures, soil
penetration, air gap and water depth;
(2)Design deck loadings, mooring loads, icing loads, variable load, total
elevated load, cantilever load, rated capacities of derricks, cranes and
elevating systems and types of helicopter for which the helideck is designed;
(3)Draft or draft range;
(4)Maximum allowable KG versus draft curves or equivalent and associated
limitations or assumptions upon which the allowable KG is based;
(5)Position (open or closed) of watertight and weathertight closures
1.1.4.3 General arrangements;
1.1.4.4 Watertight and weathertight boundaries, location of unprotected openings, and
watertight and weathertight closures;
1.1.4.5 Drawings indicating ballast system and type, location and quantities of permanent
ballast;
1.1.4.6 Schematic diagrams of the bilge, ballast and ballast control system;
1.1.4.7 Allowable deck loadings;
1.1.4.8 Capacity, centers of gravity and free surface correction for each tank;
1.1.4.9 Capacity and centers of gravity of each void provided with sounding arrangements
but not provided with means of draining;
1.1.4.10 Location and means of draining voids ;
1.1.4.11 Hydrostatic curves or equivalent;
TCVN 6474 -3:2007
74
1.1.4.12 Hazardous areas;
1.1.4.13 Simplified electrical one line diagrams of main power and emergency power
systems;
1.1.4.14 Diagram of fuel oil filling pipes ;
1.1.4.15 Recommended sequence of emergency shut-downs;
1.1.4.16 Fire extinguishing arrangements;
1.1.4.17 Life saving appliance arangements and Escape route plan ;
1.1.4.18 Light ship data ;
1.1.4.19 Technical information of helicopter used for helideck design ;
1.1.4.20 Plans and description of the mooring system and instructions for mooring ;
1.1.4.21 Plans and description of the dynamic positioning system and instructions for
positioning ;
1.1.4.22 Stability information booklet;
1.1.4.23 Loading Manual ;
1.1.4.24 Other instruction if Bureau require.
1.1.5 Loading Manual (Operating Manual) .
1.1.5.1 For a ship-type vessel, a loading manual is to be prepared and submitted for review
pertaining to the safe operation of the vessel from a strength point of view. This
loading manual is to be prepared for the guidance of and use by the personnel
responsible for loading the vessel. The manual is to include means for determining
the effects of various loaded, transitional and ballasted conditions upon the hull
girder bending moment . In addition, a loading instrument suitable for the intended
service is to be installed on the vessel. The check conditions for the loading
instrument and other relevant data are to be submitted for review .
TCVN 6474 -3:2007
75
1.1.5.2 An operating manual is required for the marine operation of all Floating Installations,
containing the information listed in Section 1.1.6 of the Mobile Offshore Drilling
Unit Rules , as applicable. The above mentioned loading manual may be included
in the overall operating manual or issued as a separate document. The loading
manual, if issued as a separate document, is to be referenced in the overall
operating manual.
1.1.5.3 Sections pertaining to each vessel type for additional requirements.
1.1.6 Trim and Stability Booklet (Operating Manual)
1.1.6.1 In addition to the loading manual described in (1.1.4), a ship-type floating
installation is to be provided with sufficient information to guide the master and
other responsible personnel in the safe loading, transfer and discharge of cargo and
ballast with respect to the hulls trim and stability. The information is to include
various loaded, transitional and ballasted example conditions over the full range of
operating drafts together with stability criteria to enable the responsible personnel
to evaluate the intact and damage stability of any other proposed condition of
loading.
1.1.6.2 This information may be prepared as a separate trim and stability booklet or may be
included in the overall operating manual. If issued as a separate document, the trim
and stability booklet is to be referenced in the overall operating manual.
1.1.6.3 Sections pertaining to each vessel type for additional requirements .
1.1.7 Engineering Analysis.
1.1.7.1 Documentation necessary to verify the adequacy of the hull structure is to be
submitted for review. The needed extent and types of analyses and the
sophistication of such analyses vary, depending on one or a combination of the
following factors:
(1) The design basis of the hull structure versus the conditions to be encountered
at the installation site;
TCVN 6474 -3:2007
76
(2) The relative lack of experience with the hull structures arrangement, local
details, loading patterns, failure mode sensitivities ;
(3) Potential deleterious interactions with other subsystems of the floating offshore
installation ;
1.1.7.2 The required structural analyses are to employ the loads associated with the
environmental conditions determined in association with Part 2. These conditions
include those expected during the operational life of the Floating Installation on site
and those expected during the transport of the structure to the installation site.
1.1.8 Mooring Systems and Equipment
1.1.8.1 Position mooring systems are to meet the requirements of Part 4. For temporary
mooring equipment, see Chapter 25 ,TCVN 6259-2A:2003.Temporary mooring
equipment is equipment used in port or proteced water area.
1.1.9 Material
1.1.9.1 Steels are hull structure materials to be complied with the requirements given in
Chapter 3, 4, 5, 6 of Pt 7A TCVN 6259-7 : 2003 and TCVN 5317:2001.
1.1.9.2 It is the responsibility of the Owner to comply with the requirements of Vietnam
Register relating to selecting materials, issuing certificates and surveys.
1.1.9.3 Where aluminum alloys are used for secondary structures such as helicopter decks,
deckhouses, superstructures or other structural components they are to comply with
the relevant requirements of Pt 7A, Ch 8 of TCVN 6259-7 :2003.
1.1.9.4 If used steel and other material is different to above kinds of material ,their technical
properties are to be submitted to Bureau for approval .
1.1.9.5 Air and sea-water temperature in design is based on selecting materials should be
minimum average temperature in day at operational location accordance to 50 years
period.
1.1.9.6 Considerations should be given to other materials based on the their property
TCVN 6474 -3:2007
77
accordance to each special application.
1.1.9.7 Selected materials are complied with the design requirements accordance to static
stress, fugue stress, cracking resistant ability and corrosion resistant ability.
1.1.9.8 Grades used in structure are selected to standards of thickness, positions in structure
and minimum designed temperature of seawater and air.
1.1.10 Underwater marking
1.1.10.1 The underwater structure of a unit intended to be surveyed on an in-water basis
should have its main frames, bulkheads and joints etc. clearly identified by suitable
marking. Details are to be submitted for approval.
1.1.10.2 Underwater marking should consist of raised lines, numerals dud letters. Besides
painting, another material marking should be added.
1.1.10.3 If marking is to be carried out by welding the welds should be made with
continuous runs and the quality of welding and workmanship should be to an
equivalent standard as the main hull structure. Marking by welding is not permitted
in highly stressed areas or over existing butts or seams. The welding procedures
and consumables are to be submitted for approval.
1.1.11 Corrosion Protection
1.1.11.1 Steelwork is to be suitably protected against corrosion (except inside of oil tank).
This protection may be by coating or by a system of cathodic protection or by any
other approved method. The method is to be suitable for the position and purpose.
1.1.11.2 VR recommend that submerged hull should be protected by impressed current
cathodic protection- ICCP with the life is not less than 20 year.
1.1.11.3 The following plans and information are to be submitted:
(1) Evidence that any primers used will have no deleterious effect on subsequent
welding or on subsequent coatings;
TCVN 6474 -3:2007
78
(2) Details of the painting specification with regard to:
(a) The generic type of the coating and its suitability for the intended environment.
(b) The methods to be used to prepare the surface before the coating is applied and
the standard to be achieved.
(c) The method of application of the coating ;
(d) The number of coats to be applied and the total dry film thickness;
(3) Details of the areas to be coated .
1.1.11.4 Where a coating is to be applied in accommodation spaces, machinery spaces and
areas of similar fire risk, a statement that the coating is not formulated on a
nitrocellulose or other highly flammable base and has low flame spread
characteristic.
1.1.11.5 When a coating contains aluminum and is intended to be used on decks or in areas
where flammable gases may accumulate a statement from an independent
laboratory confirming that appropriate tests have shown that the coating does not
increase incentive sparking hazard in the area to which it is to be applied.
1.1.11.6 Proposals for the protection of wire ropes will be considered on their merits bearing
in mind the purpose of the rope, its construction and its intended life. In general, all
steel wire ropes will be required to be protected with a zinc coating.
1.1.11.7 The cathodic protection system should be designed for a period commensurate with
the design life of the structure and it should be capable of polarizing the steelwork
to a sufficient level in order to minimize corrosion.
1.1.11.8 Impressed current cathodic protection systems are not to be fitted in any tank.
1.1.11.9 Particular attention is to be given to the locations of anodes in tanks that can
contain explosive or other flammable vapour.
1.1.11.10 Aluminum and aluminum alloy anodes are permitted in tanks that may contain
TCVN 6474 -3:2007
79
explosive or flammable vapour but only at locations where the potential energy of
the anode does not exceed 275 J (28kgfm).
1.1.11.11 Aluminum anodes are not to be located under tank hatches or other openings
unless protected by adjacent structure .
1.1.11.12 Magnesium or magnesium alloy anodes are permitted only in tanks intended
solely for water ballast, in which case adequate venting must be provided.
1.1.11.13 The arrangements for glands, where cables pass through the shell, are to
include a small cofferdam. Cables to anodes are not to be led through tanks
intended for the carriage of low flash point oils. Where cables are led through
cofferdams or clean ballast tanks, they are to be enclosed in a substantial steel tube.
1.1.11.14 Where bimetallic connections are made measures are to be incorporated to
preclude galvanic corrosion.
1.1.11.15 Where possible items such as risers and pipelines should be electrically
insulated from the unit.
1.1.11.16 Storage tanks and other compartments require corrosion protection where the
stored product may be corrosive. Particular attention should be paid to the
likelihood of water in the bottom of hydrocarbon storage tanks and the elects of
bacterial induced corrosion. Proposals for suitable protective measures are to be
submitted for approval.
1.1.11.17 Where it is proposed to use inhibitors, biocides or other chemicals for the
protection of closed flooded compartments, full details, including :
(1) Compatibility, with each other and ;
(2) Evidence of satisfactory service experience or ;
(3) Suitable laboratory test results or ;
(4) Any other data to substantiate the suitability for the intended purpose are to be
TCVN 6474 -3:2007
80
submitted for consideration.
1.1.11.18 Cable and insulating material for impressed current anode systems should be
resistant to chloride, hydrocarbons and any, other chemicals with which they, may
come into connect.
1.1.11.19 For impressed current anode systems the electrical connection between the
anode cable and the anode body is to be watertight and mechanically and
electrically sound.
1.1.11.20 Potential surveys are to be carried out at agreed intervals. Should the results of
any potential survey are not meet the requirements then remedial action is to be
carried out at the earliest opportunity .
1.1.11.21 Design of cathodic protection systems should be approved by VR .
1.2 Ship Type Vesels
1.2.1 General
1.2.1.1 The design and construction of the hull, superstructure and deckhouses of ship-type
installations are to be based on all applicable requirements of the Steel Vessel
Rules. However, the design criteria for those structures, as given in the Steel Vessel
Rules, can be modified to reflect the different structural performance and demands
expected of a vessel engaged in unrestricted service compared to a vessel
positioned at a particular site on a long-term basis or a vessel with a specific and
invariant route
1.2.1.2 To reflect the site-dependent nature of the floating offshore installation is
accomplished through the introduction of a series of Environmental Severity
Factors (ESFs), Reference is to be made to Appendix 2 for the applicable structural
design and analysis criteria that have been modified to reflect site-specific service
conditions.
1.2.1.3 The design criteria for an oil-tanker-type vessel are located in TCVN 6259:2003.
TCVN 6259-2A:2003 is applicable to vessels of 90 meters or more in length while
TCVN 6474 -3:2007
81
TCVN 6259-2B:2003 applies to vessels under 90 meters in length. In addition, the
applicable criteria contained in the Load Line, SOLAS and MARPOL Conventions
issued by the International Maritime Organization are to be considered.
1.2.2 Definitions
The definition of a ship-type vessel is given in Part 1. See TCVN 6259-2:2003
for definition of primary vessel characteristics .
1.2.3 Longitudinal Strength
1.2.3.1 Longitudinal strength is to be based onTCVN 6259-2:2003 . The total hull girder
bending moment, Mt is the sum of the maximum still water bending moment\\ and
corresponding wave-induced bending moment (Mw) determined from 1.3 , Part 2
of this Guide considering both the expected on-site conditions and transit
conditions to the installation site. In lieu of directly calculated wave-induced hull
girder bending moments (vertical) and shear forces, recourse can be made to the
use of the Environmental Severity Factor (ESF) approach described in Appendix
1,Part 9 . The ESF approach can be applied to modify the Steel Vessel Rules
wave-induced hull girder bending moment and shear force formulas according to
TCVN 6259-2:2003 (see Appendix 2 ,Part 9 ).
1.2.3.2 Due account is to be given to the influence of mooring equipment and riser weights
in contributing to the vertical still water bending moments and shear forces
1.2.3.3 For all vessels of 90 m (295 ft) or more in length ,TCVN 6259-2:2003 requires that
a loading manual based on still-water conditions be prepared and submitted for
review.
1.2.3.4 The influence of mooring equipment and riser weights in contributing to the vertical
still water bending moments and shear forces (z) is to be considered properly
1.2.4 Stability , Division and Loadline
1.2.4.1 Requirement of stability for ship-type vessel is described in TCVN 6259-10:2003
TCVN 6474 -3:2007
82
1.2.4.2 Requirement of division for ship-type vessel is described in TCVN 6259 - 9:2003
1.2.4.3 Requirement of Loadline for ship-type vessel is described in TCVN 6259 - 11:2003
1.2.4.4 The intact and damage stability of the vessel are to be evaluated in accordance with
TCVN 5312:2001 . In addition, the requirements of the 1966 Load Line
Convention and MARPOL 73/78 are to be considered. See 1.1.5 for general
requirements pertaining to the makeup and issuance of loading guidance with
respect to stability
1.2.5 Structural Arrangement
1.2.5.1 The structural arrangement of the vessel are to comply with applicable requirements
of TCVN 6259-2:2003 . Reference should also be made to the 1966 Load Line
Convention and MARPOL 73/78
1.2.6 Structural Design of the Hull
1.2.6.1 The design of the hull is to be based on the applicable portions of TCVN 6259-
2:2003 . Where the conditions at the installation site are less demanding than those
for unrestricted service that are the basis of TCVN 6259-2:2003 , the design
criteria for various components of the hull structure may be reduced to reflect these
differences. However, when the installation site conditions produce demands that
are more severe, it is mandatory that the design criteria are to be increased
appropriately.
1.2.6.2 Appendix 1, Part 9 presents an explanation of the Environmental Severity Factor
(ESF) concept, which is used to adjust the unrestricted service criteria of TCVN
6259-2:2003 . Appendix 2, Part 9 present criteria from TCVN 6259-2:2003 that
are modified to show the introduction of the ESFs into the criteria.
1.2.6.3 In the application of the modified criteria, no minimum required value of any net
scantling is to be less than 85 percent of the value obtained, had all the Beta Values
been set equal to 1.0 (which is the unrestricted service condition).
1.2.6.4 The loads arising from the static tank testing condition are also to be directly
TCVN 6474 -3:2007
83
considered in the design. In some instances, such cases might control the design,
especially when the overflow heights are greater than normally encountered in oil
transport service, or the severity of environmentally-induced load components and
cargo specific gravity are less than usual.
1.2.6.5 Hull Design for Additional Loads and Load Effects .
(1) The loads addressed in this Subsection are those required in the design of a
vessel in Appendix II & IV , Part 9 . Specifically, these loads are those arising
from liquid sloshing in hydrocarbon storage or ballast tanks, green water on
deck, bow impact due to wave group action above the waterline, bow flare
slamming during vertical entry of the bow structure into the water and bottom
slamming. All of these can be treated directly by reference to Appendix II &
IV, Part 9 . However, when it is permitted to design for these loads and load
effects on the site-specific basis, the formulations given in Appendix II & IV ,
Part 9 can be modified to reflect the introduction of the previously mentioned
Environmental Severity Factors (ESFs-Beta-type) into the Rule criteria.
(2) Sloshing of Produced or Ballast Liquids
For ship-type vessels, it is typical that the tanks may be subjected to partial
filling levels. For tanks where partial filling is intended, sloshing analyses are
to be performed. Firstly, the sloshing analysis is to determine if the anticipated
filling levels in each tank are close to the vessels natural pitch and roll motion
periods. It is recommended that the natural periods of the fluid motions in each
tank for each anticipated filling level are at least 20 percent greater or smaller
than that of the relevant vessels motion. This range of vessel natural periods
constitutes the critical range. If the natural periods of the tanks and vessel are
sufficiently separated, then no further analyses are required. However, when
the tanks are to be loaded within critical filling levels, then additional
analyses are to be performed in order to determine the adequacy of the structure
for the internal pressures due to sloshing
(3) For vessel lengths of 150 m (492 feet) and above, the extent of sloshing analyses
TCVN 6474 -3:2007
84
is indicated in Appendix IV, Part 9 . For vessels less than 150 m in length, the
extent of sloshing analyses is according to recognised standards .
(4) However, it should be borne in mind that the sloshing assessment criteria given
in Appendix IV, Part 9 are derived considering an unrestrained freely floating
hull subjected to wave energy spectra representing the open ocean .Mooring
restrain ,potential hull weathervaning different wave energy characterizations (
e.g.,energy spectra for ocean swells ,tropical cyclonic storms and water depth
effects) may need to be additionally considered by the designer when
establishing sloshing induced loading.
(5) When it is permitted to base the design on a site-specific modification, green
water loads on deck , bow impact , slamming is to be modified as Appendix II,
Part 9 .
1.2.6.6 Superstructures and Deckhouses.
The designs of superstructures and deckhouses are to comply with the
requirements of TCVN 6259-2:2005.
1.2.6.7 Helicopter Decks
The helicopter deck structure is to be in accordance withTVCN 5310:2001 and
technical regulation for offshore helicopter decks .
1.2.6.8 Protection of Deck Openings
The machinery casings, all deck openings, hatch covers and companionway
sills are to comply with 6259-2:2003.
1.2.6.9 Bulwarks, Rails, Freeing Ports, Ventilators and Portlights
Bulwarks, rails, freeing ports, portlights and ventilators are to meet the
requirements of TCVN 6259-2:2003.
1.2.6.10 Materials and Welding
TCVN 6474 -3:2007
85
(1) Materials and welding is to be in accordance with TCVN 6259-6:2003 and
TCVN 6259-7:2003 .The weld type and sizing are to be shown on the
scantling drawings or in the form of a welding schedule and are to comply
with TCVN that govern the steel selection.
(2) The topsides facilities (production deck) are to be constructed from steel
selected in accordance with TCVN 7230: 2003.
(3) Tower mooring systems and SPM are to be constructed from steel selected
in accordance with TCVN 5317: 2001.
1.2.6.11 Machinery and Equipment Foundations
Foundations for equipment subjected to high cyclic loading, such as mooring
winches, chain stoppers and foundations for rotating process equipment, are to be
analyzed to ensure satisfactory strength and fatigue resistance. Calculations and
drawings showing weld details are to be submitted to VR for review.
1.2.7 Engineering Analyses of the Hull Structure
1.2.7.1 General
Documentation necessary to verify the structural strength of the vessel is to be
submitted for review. The criteria in this Subsection relate to the analyses required to
verify the scantling selected in the basic hull design in 1.2.6 as above. Except as
provided in TCVN 6259-2:2005 , the results of analyses that are required in this
Subsection cannot be used to reduce the scantlings established from 1.2.6 .
Depending on the specific features of the offshore installation, additional analyses to
verify and help design other portions of the hull structure will be required. Such
additional analyses include those for the deck structural components supporting
deck-mounted equipment and the hull structure interface with the position mooring
system. Analysis criteria for these two situations are given in 1.2.8 .
1.2.7.2 Strength Analysis of the Hull Structure
(1) For vessels of 150 m (492 feet) in length and above, the required extent of a Finite
TCVN 6474 -3:2007
86
Element Method (FEM) strength analysis is indicated in Appendix III, Part 9 . For
vessels less than 150 m in length, it is recommended that a Finite Element Method
(FEM) analysis be performed if the vessel is of double hull construction or of
unusual design . When the design is permitted to be based on site-specific
environmental conditions, the load components from the Steel Vessel Rules to be
used in the strength analyses can be adjusted as explained in 1.2.6 and Appendix II,
Part 9 .
(2) Generally, the strength analysis is performed to determine the load distribution in the
structure. An appropriate three-dimensional FEM model is to be analyzed for this
purpose. To determine the stress distribution in major supporting structures,
particularly at intersections of two or more members, fine mesh FEM models are to
be analyzed using the boundary displacements and load from the 3D FEM model.
To examine stress concentrations, such as at intersections of longitudinal stiffeners
with transverses and at cutouts, fine mesh 3D FEM models are to be analyzed.
In the strength analyses, the following loading conditions are to be used:
(3) General Cargo Load Patterns. The FEM analysis is to be performed in accordance
with the load patterns specified in Appendix IV, Part 9 . The load patterns included
in the Steel Vessel Rules have been developed to simulate the most severe load
effects in selected structural components. The actual loading patterns for the vessel
are to be reviewed to ensure that there are no other patterns producing more severe
loading. If any worse governing load patterns than those specified in the Steel
Vessel Rules exist, these load patterns are to be included in the analyses.
(4) Tank Test Loading Conditions. In addition to the specified load patterns and cargo
densities above, conditions representing tank testing are also to be investigated.
For ESF values of 1.0 and greater, the tank load patterns of Load Cases No. 5 and 6
specified in Appendix IV, Part 9 are to be analyzed considering static conditions and
seawater (Specific Gravity =1.025). The tanks are to be loaded considering the
actual height of the overflow pipe, which is not to be taken less than 2.44 m (8 feet)
above the deck at side. The external drafts for these Load Cases are to be taken as 25
TCVN 6474 -3:2007
87
percent of the design draft. However, notes (1) and (2) of the following paragraph are
applicable.
For ESF values of less than 1.0, the same load patterns of Load Cases No. 1 to 8
specified in Part 5, Chapter 1 of the Steel Vessel Rules are to be analyzed
considering static conditions and seawater (Specific Gravity =1.025). The tanks are
to be loaded considering the actual height of the overflow pipe, which is not to be
taken less than 2.44 m (8 feet) above the deck at side. The external drafts for these
Load Cases are to be taken as follows:
Load Case Percent of Design Draft
1 55 (1)
2 100 (3)
3 67
4 67
5 25 (1)
6 25 (1) (2)
7 100 (3)
8 100 (3)
1) Where the actual tank test condition with the tank loading pattern as
the center row of tanks results in a draft less than specified, the actual
tank test draft is to be used
2 ) For a vessel with two outer longitudinal bulkheads only (inner skin),
i.e., one tank across between the inner skin bulkheads, the minimum
actual tank test draft is to be used.
3 ) The actual tank test patterns will most likely not result in 100 percent
TCVN 6474 -3:2007
88
draft, but the 100 percent draft is specified as the design condition to
maximize external pressure loads.
Site tank tests are to be conducted. These tank test cases are to be
analyzed using the 1-year return period design operation condition
loads and a minimum specific gravity of cargo fluid of 0.9. The tank
pressure is to be calculated with the actual tank test pressure head on
site. The external drafts for these load cases are to be specified
according to the Loading or Operational Manual, or are to be agreed
upon between VR and the Owner or Client to determine the design
condition in terms of still water bending moments and shear forces
along the length of the cargo block.
(5) Transit Conditions. The transit condition is to be analyzed using the actual tank
loading patterns in association with the anticipated environmental conditions to be
encountered during the voyage (see 1.3, part 2).
1.2.7.3 Fatigue Analysis
For all vessels of 150 m and above, the extent of fatigue analysis required is
indicated in Appendix IV, Part 9 . For vessels of less than 150 m, the recognized
requirements are applicable.
The fatigue strength of welded joints and details at terminations, which may or may
not be located in highly stressed areas are to be assessed, especially where higher
strength steel is used. These fatigue and/or fracture mechanics analyses, based on the
combined effect of loading, material properties, and flaw characteristics are
performed to predict the service life of the structure and determine the most effective
inspection plan. Special attention is to be given to structural notches, cutouts,
bracket toes, and abrupt changes of structural sections.
Consideration is also to be given to the following analyses:
(1) The cumulated fatigue damage during the voyage from the fabrication or
previous site to the operation site is to be included in the overall fatigue
TCVN 6474 -3:2007
89
damage assessment.
(2) The stress range due to loading and unloading cycles is to be accounted for
in the overall fatigue damage assessment, if it is significant. For any
structural detail, a minimum criterion for computing the stress range is to
consider the tanks at 90 percent full load capacity and at its residual capacity,
with adjacent tanks also at their residual capacity. A maximum fluid specific
gravity of 0.9 is to be adopted for calculating the pressure range. The stress
range is also to account for pressure range variation due to sloshing of the
fluid inside the tank at the various filling levels, if it is significant.
1.2.7.4 Acceptance Criteria.
The total assessment of the structure is to be performed against the failure
modes of material yielding, buckling and ultimate strength and fatigue. The
reference acceptance criteria of each mode are given as follows:
(1) Material Yielding
The criteria are indicated in Appendix VI ,Part 9.
(2) Buckling and Ultimate Strength
The criteria are indicated in TCVN 6259-2:2003 .
(3) Fatigue
The required target fatigue life is 20 years.
In the absence of more detailed environmental data, stress ranges are to be
obtained in consideration of the unrestricted service environment. When the
site-specific wave environment is used and produces less severe fatigue demand
than the unrestricted service environment of the Steel Vessel Rules, credit can
be given to the less severe environment by increasing the expected fatigue life.
For site-specific environmental conditions producing more severe fatigue
demand than the Steel Vessel Rule basis, the site-specific environmental data
TCVN 6474 -3:2007
90
are to be used, and the calculated fatigue life is to be not less than 20 years
Due to the structural redundancy and relative ease of inspection inherent in
typical hull structures of ship-type vessels, there is no further need to apply
additional factors of safety above what is already built into the fatigue
classification curves cited in the above reference. However, for areas of the
structure which are non-inspectable or critical, such as in way of the
connections to the mooring or production systems ), additional factors of safety
should be considered.
For existing vessels that are employed in floating installation service, the
estimated remaining fatigue lives of the critical structural details are to be
assessed and the supporting calculations submitted for review. Special
consideration is to be given to the effects of corrosion and wastage on the
remaining fatigue life of existing structures.
Any areas determined to be critical to the structure are to be free of cracks. The
effects of stress risers should be determined and minimized. Critical areas may
require special analysis and survey.
1.2.8 Analysis and Design of Other Major Hull Structural Features
The analysis and design criteria to be applied to the other pertinent features of the
hull structural design are to conform to recognized practices acceptable to the
Bureau. For many ship-type installations, there will be a need to consider in the hull
design the interface between the position mooring system and the hull structure or
the effects of structural support reactions from deck mounted (or above deck)
equipment modules or both. When it is permitted to base the design of the ship-type
offshore installation on site-specific environmental conditions, reference is to be
made to 1.2.6 and Appendix 2, Part 9 regarding how load components can be
adjusted.
Criteria applicable to the position mooring (e.g., turret) structure itself is given in
1.4, Section 4, and the above (or on) deck equipment or module structure is
TCVN 6474 -3:2007
91
referred to in 1.7,Section 5
1.2.8.1 Position Mooring/Hull Interface
(1) Mooring/Hull Interface Modeling
A FEM analysis is to be performed and submitted for review. The modeling
technique employed should conform to that described in recognized standards.
(a) If the mooring system is of the turret or SPM type, external to the vessels
hull, the following applies:
1) Fore end mooring. The minimum extent of the model is from the fore end
of the vessel, including the turret structure and its attachment to the hull, to
a transverse plane after the aft end of the foremost cargo oil tank in the
vessel. The model can be considered fixed at the aft end of the model. The
loads modeled are to correspond to the worst-case tank loads, seakeeping
loads as determined for both the transit case and the on-site case, ancillary
structure loads, and, for the on-site case, mooring loads.
2) Aft end mooring. The minimum extent of the model is from the aft end of
the vessel, including the turret structure and its attachment to the hull, to a
transverse plane forward of the fore end of the aftmost cargo oil tank in the
hull. The model can be considered fixed at the fore end of the model. The
loads modeled are to correspond to the worst-case tank loads, seakeeping
loads as determined for both the transit case and the on-site case, ancillary
structure loads, and, for the on-site case, mooring loads.
(b) If the mooring arrangement is internal to the vessel hull (turret moored), the
following applies:
1) Fore end turret. The model is to extend from the fore end of the vessel into
the cargo tank or hold aft of the one containing the turret. The model can be
considered fixed at the aft end of the model. The loads modeled are to
correspond to the worst-case tank loads, seakeeping loads as determined for
TCVN 6474 -3:2007
92
both the transit case and the on-site case, ancillary structure loads, and for
the on-site case, mooring loads.
2) Midship turret. The model can be a 3-tank model similar to that described
in Appendix IV,Part 9 where the turret is located in the center tank of the
model. Hull girder loads are to be applied to the ends of the model. The
other loads that are modeled are to correspond to the worst-case tank loads,
seakeeping loads as determined for both the transit case and the on-site
case, ancillary structure loads, and, for the on-site case, mooring loads.
(c) For spread moored vessels
1) The local foundation structure and vessel structure are to be checked for the
given mooring loads using an appropriate FEM analysis. The mooring loads to
be used in the analysis are to be based on the breaking strength of the mooring
lines
(2) Net Scantlings for Mooring Interface Structure
A net thickness or scantling corresponds to the minimum strength capability
acceptable for classification, regardless of the design service life of the vessel, prior
to the addition of the Rules-specified design corrosion margin. The mooring
interface/hull structure analysis model is to use the design corrosion margin 10
percent of each of the as-built, gross scantlings, but need not exceed 1.5 mm. These
design corrosion margins are for use with the mooring/hull interface model and are
minimum values. They are different from the corrosion margins to be used in the
analyses specified in 1.2.7 . Should the design incorporate increased corrosion
margins, their beneficial effects can be appropriately accounted for in the design
evaluation.
The required net scantlings determined using these corrosion margins only apply in
way of the mooring structure, bounded transversely and longitudinally by watertight
bulkheads or shell plate. The net scantlings can be used for obtaining stress levels
for structure that is in way of any ancillary structure, such as flare towers or
TCVN 6474 -3:2007
93
production decks. All other areas are to be in compliance with TCVN 6259-2:2003
and applied section , 1.2.6 and 1.2.7 of this Guide .
(3) Acceptance Criteria Mooring/Hull Interface
The total assessment of the structure is to be performed against the failure modes of
material yielding, buckling and ultimate strength, and fatigue. The reference
acceptance criteria of each mode is given as the following:
(a) Material Yielding. The criteria are indicated in Appendix VI, Part 9
(b) Buckling and Ultimate Strength. The correlative criteria are indicated in TCVN
6259-2:2003.
(c) Fatigue: Mooring/Hull Interface. The required target fatigue life is 20 years.
However, due to the critical nature of these connections, additional factors of
safety may be needed. (Also see 1.4.7,Part 4.) The fatigue life of the hull
structure is to be investigated in accordance with recognized fatigue calculating
guideline and submitted for review as described below:
1) For vessels with a forward end mooring, the fatigue life of the vessel should
be investigated from the watertight bulkhead aft of the mooring to the fore end
of the vessel.
2) For vessels with mid body mooring, a three-tank analysis, where the mooring
is in the middle hold, is to be investigated
3) For aft end mooring, the fatigue life should be investigated from the watertight
bulkhead forward of the mooring to the aft end of the vessel.
Structural members in way of the turret structure or other mooring structure
are to be effectively connected to the adjacent structure in such a manner as to
avoid hard spots, notches and other harmful stress concentrations.
Special attention is to be given to cutouts, bracket toes and abrupt changes of
structural sections. These areas are considered to be critical to the vessel and
TCVN 6474 -3:2007
94
are to be free of cracks. The effects of stress risers in these areas are to be
determined and minimized.
1.2.8.2 Hull Structure to Resist Equipment Reaction Forces
The forces to be resisted by the hull structural elements in way of the equipment
supports are to be established by an acceptable method that accounts for the static
and expected motion (seakeeping) induced and other applicable load effects and the
appropriate combinations of these load components and effects. The strength of the
hull structural elements is to be based on the applicable criteria of the Steel Vessel
Rules. For vessels 150 meters (492 feet) in length and greater, the required strength is
specified in Appendix VI, Part 9 , and for vessel less than 150 meters in length,
reference is to be made to recognized Standards .
1.2.9 Marine Piping Systems
Marine piping systems are those systems that are required to conduct marine
operations and are not associated with the process facilities. These systems include,
but are not limited to, bilge, ballast, tank venting, sounding and fuel oil. Marine
piping systems on ship-type installations are to be in accordance with the applicable
requirements of TCVN 6259:2003.
1.2.10 Electrical Systems
Electrical Systems on ship-type installations are to comply with the applicable
requirements of TCVN 6259-4:2003 and applicable requirements in Appendix VII .
For area classification requirements, refer to Appendix VI, Part 9 of this Guide
1.2.10.1 Degree of protection for enclosure
Degree of protection of electrical equipment is against foreign bodies and liquid,
type of enclosure required for protection of equipment is to be suitable for the
intended location. Minimum degree of protection is shown as Table 3 3.
In order to define degree of protection shown in Table 3 3 , following regulation is
given. Degree of protection relating to protecting electrical equipment from falling of
TCVN 6474 -3:2007
95
foreign bodies and liquid into inside is defined by IP numeral with two followed
number.The first IP numeral indicate degree of protection of equipment from solid
object, the second IP numeral indicate degree of protection of equipment from liquid.
Details are given in Table 3-1 and Table 3-2.
Table 3-1 Degree of Protection Indicated by the first characteristic numeral
First IP
Numeral
Short Description Definition
0 Non-protected No special protection
1 Protected against solid
objects greater than 50 mm
Solid object exceeding 50 mm in diameter.
2 Protected against solid
objects greater than 50 mm
Solid object exceeding 50 mm in diameter.
3 Protected against solid
objects greater than 2,5 mm
Tools, wires, etc., of diameter or thickness greater
than 2.5 mm.Solid objects exceeding 2.5 mm in
diameter.
4 Protected against solid
objects greater than 1 mm
Wires or strips of thickness greater than 1 mm.
Solid objects exceeding 1 mm in diameter.
5 Dust protected
Ingress of dust is not totally prevented, but dust
does not enter in sufficient quantity to interfere with
satisfactory operation of the equipment.
6 Dust-tight No ingress of dust
TCVN 6474 -3:2007
96
Table 3-2 Degree of Protection Indicated by the second characteristic numeral
Second
IP
Numeral
Short Description Definition
0 Non-protected No special protection
1 Protected against dripping
water
Dripping water (vertically falling drops) is to have
no harmful effect.
2 Protected against dripping
water when tilted up to 15
deg.
Vertically dripping water is to have no harmful
effect when the enclosure is tilted at any angle up to
15 deg. from its normal position.
3 Protected against spraying
water
Water falling as spray at an angle up to 60 deg.
from the vertical is to have no harmful effect.
4 Protected against splashing
water
Water splashed against the enclosure from any
direction is to have no harmful effect.
5 Protected against water jets Water projected by a nozzle against the enclosure
from any direction is to have no harmful effect.
6 Protected against heavy
seas
Water from heavy seas or water projected in
powerful jets is not to enter the enclosure in harmful
quantities.
7 Protected against the
effects of immersion
Ingress of water in a harmful quantity is not to be
possible when the enclosure is immersed in water
under defined conditions of pressure and time.
8 Protected against
submersion
The equipment is suitable for continuous
submersion in water under conditions which are to
be specified by the manufacturer.
Note: Normally, this will mean that the equipment
is hermetically sealed. However, with certain types
of equipment, it can mean that water can enter but
only in such a manner that it produces no harmful
effects.
TCVN 6474 -3:2007
97
TABLE 3-3 :Minimum Degree of Protection
Example Of Location Condition of Location
Switchboards, distribution boards, motor control
centers & controllers
Generators
Motors
Transformers, Converters
Lighting fixtures
Heating appliances
Accessories
(2)
Dry accommodation space Danger of touching live parts
only
IP20 - IP20 IP20 IP20 IP20 IP20
Control rooms Danger of dripping liquid
and/or moderate mechanical
damage
IP22 - IP22 IP22 IP22 IP22 IP22
Machinery spaces above floor
plates
(5)
IP22 IP22 IP22 IP22 IP22 IP22 IP44
Steering gear rooms IP22 IP22 IP22 IP22 IP22 IP22 IP44
Refrigerating machinery rooms IP22 - IP22 IP22 IP22 IP22 IP44
Emergency machinery rooms IP22 IP22 IP22 IP22 IP22 IP22 IP44
General store rooms IP22 IP22 IP22 IP22 IP22 IP22 IP22
Pantries IP22 - IP22 IP22 IP22 IP22 IP44
Provision rooms IP22 - IP22 IP22 IP22 IP22 IP22
Bathrooms & Showers Increased danger of liquid
and/or mechanical damage
- - - - IP34 IP44 IP55
Machinery spaces below floor
l t
- - IP44 - IP34 IP44 IP55
(3)
Closed fuel oil or lubricating oil
t
IP44 - IP44 - IP34 IP44 IP55
(3)
Ballast pump rooms Increased danger of liquid
and/or mechanical damage
IP44 - IP44 IP44 IP34 IP44 IP55
Refrigerated rooms - - IP44 - IP34 IP44 IP55
Galleys and Laundries IP44 - IP44 IP44 IP34 IP44 IP44
Open decks Exposure to heavy seas IP56 - IP56 - IP55 IP56 IP56
Bilge wells Exposure to submersion - - - - IPX8 - IPX8
Notes
1. Empty spaces shown with indicate installation of electrical equipment is not
recommended.
2. Accessory includes switches, detectors, junction boxes, etc.
3. Socket outlets are not to be installed in machinery spaces below the floor plates,
enclosed fuel and lubricating oil separator rooms or spaces requiring certified safe
type equipment.
1.2.11 Fire Fighting Systems and Equipment
Fire fighting systems and equipment for vessel service functions not associated with
TCVN 6474 -3:2007
98
the process facilities are to be in accordance with the applicable requirements of
TCVN 6259-5:2003 . Fire fighting systems and equipment for protection of
hydrocarbon process and associated systems are to be in accordance with Appendix
VII, Section 9 .
1.2.12 Machinery
Machinery and equipment not associated with the process facilities are to be in
accordance with the applicable requirements of TCVN 6259-3:2003 . Machinery
forming a part of the hydrocarbon processing facilities are to be in accordance with
applicable requirements of Appendix VII, Part 9 . Refer to Section 5 of this Guide
regarding process related machinery.
1.2.13 Equipment
Equipment not associated with the process facilities are to be in accordance with the
applicable requirements of TCVN 6259-7B:2003 and TCVN 6259-2:2003 .
Equipment forming a part of the hydrocarbon processing facilities are to be in
accordance with applicable requirements of Appendix VII, Part 9 . Refer to Section 5
of this Guide regarding process related equipment .
1.2.14 Safety Equipment
See requirements in TCVN 6278:2003 and Appendix VII, Part 9 .
1.3 Column-stabilized Vessels
1.3.1 General
The design and construction of the lower hull, columns, deck and deckhouses of
column-stabilized type installations are to be based on all applicable requirements of
TCVN 5309-5319:2001 . However, the design criteria, as given in TCVN 5309-
5319:2001, can be modified to reflect the different structural performance and
demands expected of a vessel in ocean service, compared to a vessel positioned at a
particular site on a long-term basis.
TCVN 6474 -3:2007
99
1.3.2 Definitions
See Section 1 for the definition of criteria that constitute a column-stabilized vessel.
For vessels that are considered column-stabilized type, the definitions of primary
vessel characteristics can be found in TCVN 5309:2001.
1.3.3 Loading Criteria
A vessels modes of operation should be investigated using anticipated loads,
including gravity loads together with relevant environmental loads due to the effects
of wind, waves, currents, and, where deemed necessary by the Owner or designer,
the effects of earthquake, temperature, fouling, ice, etc.
A loading plan is to be prepared for each design. This plan is to show the maximum
uniform and concentrated loadings to be considered for all areas for each mode of
operation. The minimum deck loadings is shown in TCVN 5310:2001.
1.3.4 Wave Clearance
Unless deck structures are satisfactorily designed for wave impact, reasonable
clearance between the deck structures and the wave crests is to be ensured for all
afloat modes of operation, taking into account the predicted motion of the vessel
relative to the surface of the sea. Calculations, model test results or prototype
experiences are to be submitted for consideration.
1.3.5 Structural Design
The design of the vessel is to be based on the applicable portions of TCVN 5309-
5319:2001. Where the conditions at the installation site are less than those for full
ocean service that are the bases of the Mobile Offshore Drilling Unit Rules, the
design criteria for various components of the vessel structure may be reduced to
reflect these differences. However, when the installation site conditions produce
more arduous demands, it is mandatory that the design criteria be increased
appropriately.
1.3.5.1 Scantlings
TCVN 6474 -3:2007
100
Vessels scantlings, including deck (upper structure), columns and lower hulls are to
be designed in accordance with TCVN 5309-5319:2001 , with special attention to the
effects and control of corrosion.
1.3.5.2 Deckhouses
The design of the deckhouse is to comply with the requirements of TCVN 6259-2:
2005.
1.3.5.3 Helicopter Deck
The design of the helicopter deck is to comply with the requirements of TVCN
5310:2001and technical Regulation for helicopter deck on offshore installation.
1.3.5.4 Protection of Deck Openings
All deck openings, hatch covers and companionway sills are to comply with TCVN
6259-2:2005 .
1.3.5.5 Guards and Rails
Guards and rails are to comply with the requirements of TCVN 6259-2:2003 and
latest modifications.
1.3.5.6 Machinery and Equipment Foundations
Foundations for equipment subjected to high cyclic loading, such as mooring
winches, chain stoppers and foundations for rotating process equipment, are to be
analyzed to ensure satisfactory strength resistance. Local structure in way of
fairleads, winches, etc., forming part of the position mooring system is to be capable
of withstanding forces equivalent to the breaking strength of the mooring line.
1.3.5.7 Materials and Welding
Column stabilized vessels are to be constructed from steel selected in accordance
with TCVN 5317:2001 , including the topsides facilities (strength deck) where the
deck contributes to the strength of the vessel.
TCVN 6474 -3:2007
101
All fabrication and welding are to comply with the requirements in TCVN
5318:2001. The weld type and sizing are to be shown on the scantling drawings or in
the form of a welding schedule and are to comply with the Rules that govern the steel
selection.
1.3.6 Engineering Analysis of the Vessels Primary Structure
1.3.6.1 General
Document necessary to verify the structural strength of the vessel is to be submitted
for review. The criteria in this Subsection relate to the analyses required to verify the
scantlings selected in the basic design in 1.3.5 . Except as provided in TCVN 5309-
5319:2001, the results of analysis that are required in this subsection cannot be used
to reduce the scantlings established from 1.3.5 . Depending on the specific features of
the offshore installations, additional analyses to verify and help design other portions
of the vessel structural components will be required. Such additional analyses
include those for the deck structural components supporting deck-mounted
equipment and the vessel structure interface with the position mooring system.
Analysis criteria for those two situations are given in 1.3.7.
1.3.6.2 Strength Analysis of the Vessels Primary Structure
The primary structure of the vessel is to be analyzed using the loading and
environmental conditions stipulated below. Conditions representative of all modes of
operation are to be considered to determine critical cases. Calculations for critical
conditions are to be submitted for review. The analysis is to be performed using
recognized calculation methods and is to be fully documented and referenced. The
environmental loads are to be developed in accordance with 1.3 and 1.4 , Part 2
In the design of the vessels in-place strength, the following design environmental
conditions should be considered:
Severe Storm Condition
Environmental condition which produces a maximum response with a return
TCVN 6474 -3:2007
102
period up to and including 100 years. The design responses of a column-
stabilized vessel are prying/squeezing forces, torsion moments, longitudinal
shear forces between lower hulls and deck accelerations.
Normal Operations Condition
Environmental conditions that are expected to occur frequently during the service
life.
1.3.6.3 Fatigue Analysis
The possibility of fatigue damage due to cyclic loading is to be considered in the
design of the primary structures of a column-stabilized vessel. Special attention is to
be given to the major connections between the bracing members, column and deck.
Attention should also be given to structural notches, cutouts, brackets, toes and
abrupt changes of structural sections. A fatigue analysis using an appropriate loading
is to be performed to predict the service life of the vessel and determine the most
effective inspection plan.
1.3.6.4 Acceptance Criteria
The total assessment of the structure and details is to be performed against the failure
modes of material yielding, buckling and ultimate strength and fatigue. The
reference acceptance criteria of each mode is given as follows.
(1) Material Yielding
The criteria indicated in TCVN 5310:2001 should be used.
(2) Buckling and Ultimate Strength
The criteria indicated in TCVN 6259-2:2003 should be used. Alternatively, the
criteria specified in other recognized standards can be used.
(3) Fatigue
The minimum allowable fatigue life is to be FS times the design service life,
TCVN 6474 -3:2007
103
where FS is the factor of safety. FS depends on the inspectability of the structure,
as well as the criticality of the structure. The FS values to be used in calculating
the minimum fatigue life are as follows:
FS =3.00 For areas that are easy to inspect and are non-critical areas.
FS =10 For areas that are non-inspectable or critical areas. The word critical
implies that failure of these structural items would result in progressive failure of
the structure and may lead to catastrophe.
For existing vessels, the remaining fatigue life of the vessels is to be assessed and
the supporting calculations submitted for review. Special consideration is to be
given to the effects of corrosion and wastage on the remaining fatigue life of
existing structures.
Any areas determined to be critical to the structure are to be free of cracks, and the
effects of stress risers is to be determined and minimized. Critical areas may
require special analysis and survey.
1.3.7 Analysis and Design of Other Major Structures
The analysis and design criteria to be applied to the other pertinent features of the
vessel structural design are to conform to recognized practices acceptable to the
Bureau. For the column-stabilized vessel, the following will need to be considered in
the vessel structure design: the interface between the position mooring system and
the vessel structure or the effects of the structural support reactions from deck-
mounted equipment modules.
1.3.7.1 Position Mooring/Vessel Interface
The local foundation structure and vessel structure is to be checked for the given
mooring loads using an appropriate FEA model. The mooring loads to be used in the
analysis are to be the breaking strength of the mooring lines. The interface structure
between the deck equipment or module structure and the vessel is to comply with the
requirements in 1.7, Part 5.
TCVN 6474 -3:2007
104
1.3.8 Stability
1.3.8.1 Transit Voyage Stability
During transit voyages to and from the operational site, the vessel is to meet the
stability requirements of TCVN 5309-5319:2001 .
1.3.8.2 On-Site Stability
All vessels are to have positive metacentric height ( GM) in calm water equilibrium
position for all afloat conditions, including temporary positions during fabrications,
installations, ballasting and deballasting.
All vessels are to have sufficient stability at intact, as well as damage, condition. The
intact and the damage stability to withstand the overturning effect of the force
produced by the defined operating intact wind, severe storm intact wind and
damaged wind are to be investigated in accordance with TCVN 5309-5319:2001
under which the vessel was classed. The wind velocities for calculating the wind
overturning moments are to be established using the site-specific environmental
report and are to be identified in the design basis. The wind velocities used in TCVN
5309-5319:2001 for unrestricted service are quoted below for reference.
Table 3.4 The wind velocities for unrestricted area
Conditions Minimum Wind Velocity
Damaged 25.8 m/s ( 50 knots)
Operating Intact 36.0 m/s ( 70 knots)
Severe Storm Intact 51.5 m/s (100 knots)
For the purpose of determining compliance with these stability requirements, it is to
be assumed that the vessel is floating free of mooring restraints. However,
detrimental effects of catenary mooring systems or of the thrusters for dynamically
positioned vessels are to be considered.
TCVN 6474 -3:2007
105
Vessels designed to ballast or deballast through designated draft ranges or zones
need only comply with the above positive metacentric height requirement when
ballasting or deballasting through these designated zones.
The Owner is responsible for ensuring that such operations are performed only with
proper loading conditions and during periods of acceptable weather.
Alternative stability criteria may be considered acceptable by the Bureau.
1.3.9 Marine Piping Systems
Marine piping systems are those systems (such as bilge, ballast, fuel oil and tank
venting) that are required to conduct marine operations and are not associated with
process facilities. Marine piping systems are to comply with TCVN 5309-
5319:2001.
1.3.10 Electrical Systems
Electrical systems are to comply with TCVN 5316:2001 and Appendix VII ,Part 9 .
For area classification requirements, refer to Appendix VII , Part 9 of this Guide.
1.3.11 Fire Fighting Systems and Equipment
Fire fighting systems and equipment for vessel service functions not associated with
the process facilities are to be in accordance with TCVN 5314:2001 . Fire fighting
systems and equipment for protection of hydrocarbon process and associated systems
are to be in accordance with Appendix VII , Section 9 .
1.3.12 Machinery and Equipment
Machinery and equipment not associated with the process facilities are to be in
accordance with the applicable requirements of TCVN 5311 and 5315:2001 .
Machinery and equipment forming a part of the hydrocarbon processing facilities are
to be in accordance with the applicable requirements of Appendix VII , Part 9 .See
Part 5 of this Guide regarding machinery and equipment associated with the process
facilities .
TCVN 6474 -3:2007
106
1.3.13 Safety Equipment
See requirements in TCVN 5319:2001 and Appendix VII, Part 9 .
1.4 Existing Tanker Hull Structures (Ordinary Conversions)
1.4.1 Introduction
Regulation 1.1 and 1.2 apply to a new-build hull structure or a major conversion of
an existing vessel. Major conversion is conversion that affects a principal dimension
of the hull. Regulation 1.4 is applied for the typically more common conversion of
an existing tanker to a ship-type FPI .
The direct application of the criteria contained in 1.1 and 1.2 as the basis of
acceptance of the hull structure of an existing tanker for FPI service is fully
permissible . However, modified acceptance criteria, given in 1.4, may be used for
some aspects of the vessels structural design as an Ordinary Conversion for FPI
service. Regulation 1.4 applies to both the Change of Class Designation and
Transfer of Class situations where the acceptance of the existing vessels hull
structure as an Ordinary Conversion is pursued. Change of Class Designation
refers to an existing tanker classed by the Bureau which is being converted to FPI
service. Another situation, the Transfer of Class, refers to a vessel transferring into
the Bureaus classification from another Society.
1.4.2 General
All applicable criteria contained in this FPI Guide are to be used in the classification
of an Ordinary Conversion, except that some criteria (primarily in1.1 and 1.2 ) can
be modified. Specific modifications are given below for the affected criteria.
The major criteria differences for the Ordinary Conversion arise in the acceptance
of the basic design of the hull structure. The basic design of the hull structure
relates to hull girder longitudinal strength and local scantling selection.
The minimum target fatigue life of the hull structure is also fundamentally different
for a converted tanker . For a new-build, the minimum target fatigue life is 20 years;
TCVN 6474 -3:2007
107
for an existing vessel to be converted to FPI service, the minimum target fatigue life
can be less than 20 years .
1.4.3 Alternative Acceptance Criteria for the Basic Design of the Hull Structure
1.4.3.1 General
For a vessel being converted from a tanker to FPI service, the design and
construction of the existing hull, superstructure and deckhouses are to meet the
applicable criteria of TCVN 6259 at the time of original build, or as applicable, the
criteria presented in 1.4.7 below. In order to be eligible to apply this approach,Two
flowing condition is to be satisfied, as described in Appendix 1,Section 9 of this
Guide (which reflect expected conditions from the long-term mooring of the vessel at
an offshore site), are 1.0 or less, and 1.2.5 on the required hull girder longitudinal
strength is satisfied. If either of these conditions is not met, then the application of
this alternative approach is not considered valid. In that case, the unmodified FPI
Guide (i.e., Regulation 1.1 and 1.2 ) criteria or an alternative determined in
consultation with the Bureau is to be applied.
In addition, it is expected that the applicable and most recent versions of the criteria
contained in the Load Line, SOLAS and MARPOL Conventions issued by the
International Maritime Organization are to be considered.
1.4.3.2 Structural Design of the Hull
Steel renewals to be performed at the time of conversion must be carefully
considered. Estimation of corrosion rates are to be made, taking into account any
future corrosion protection measures to be used, previous service experience, the
type and temperatures of stored fluids and the other variables significantly affecting
the corrosion rate. The anticipated corrosion predicted to occur over the proposed
on-site life of the FPI is to be considered in the design.
The loads arising from the static tank testing condition are also to be directly
considered in design. It should be noted that in some instances such cases might
control the design, especially when the overflow heights are greater than normally
TCVN 6474 -3:2007
108
encountered in oil transport service or the severity of environmentally-induced load
components and cargo-specific gravity are less than usual.
1.4.3.3 Engineering Analyses of the Hull Structure
(1) General
Documentation necessary to verify the structural adequacy of the vessel is to be
submitted for review.
Depending on the specific features of the offshore installation, additional analyses to
verify and to help design other portions of the hull structure will be required. Such
additional analyses include those for the deck structural components supporting
deck-mounted equipment and the hull structure interface with the position mooring
system. Analysis criteria for these two situations are given in Part 6.
Provided a scantling of the existing tanker is not below its renewal limit, or if it is to
be renewed at the time of conversion, then it can be modeled in the structural
analyses in the conventional SafeHull manner. That is, use the net scantling,
which is the as-built value minus the current Rule (SafeHull based) specified
nominal design corrosion value.
(2) Strength Analysis of the Hull Structure
Steel renewals to be performed at the time of conversion must be carefully
considered. Estimation of corrosion rates are to be made, taking into account any
future corrosion protection measures to be used, previous service experience, the
type and temperatures of stored fluids and the other variables significantly affecting
the corrosion rate. The anticipated corrosion predicted to occur over the proposed
on-site life of the FPI is to be considered in the design.
For vessels of 150 meters (492 feet) in length and above, the extent of Finite Element
Method (FEM) strength analysis requirements are indicated in Appendix III,Part 9
of the Steel Vessel Rules. For vessels less than 150 m in length of double hull
construction or of unusual design, see Steel Vessel Rules for Finite Element Method
TCVN 6474 -3:2007
109
(FEM) analysis requirements. When it is permitted that the design can be based on
site-specific environmental conditions, the load components from the Steel Vessel
Rules to be used in the strength analyses can be adjusted as explained in 1.2.6 and
Appendix 2, Part 9.
Generally, the strength analysis is carried out to determine the load distribution in the
structure. An appropriate three-dimensional FEM model is to be analyzed for this
purpose. To determine the stress distribution in major supporting structures,
particularly at intersections of two or more members, two-dimensional fine mesh
FEM models are to be analyzed using the boundary displacements and load from the
3D FEM model. To examine stress concentrations such as at intersections of
longitudinal stiffeners with transverses and at cut outs, fine mesh 3D FEM models
are to be analyzed.
In the strength analyses, the following loading conditions are to be considered:
i. General Cargo Load Patterns : as mentioned above, when the basic
design of the vessel is accepted as an Ordinary Conversion, this analysis
may not be required. Where it is intended to perform this analysis, see the
unmodified text of this paragraph appearing in 1.2.7.
ii. Tank Test Conditions : analysis for these conditions is required; see the
unmodified text of this paragraph appearing in 1.2.7.2. (4)
iii. Transit Condition : analysis to demonstrate the adequacy of the hull
structure during the transit to the installation site is required; see the
unmodified text of this paragraph appearing in 1.2.7.2.(8).
1.4.3.4 Fatigue Analysis
For all vessels of 150 m and above, the extent of fatigue analysis required is
indicated in Appendix, Part 5 of the Steel Vessel Rules. For vessels of less than 150
m, the requirements are indicated in Appendix, Part 5 of the Steel Vessel Rules.
The fatigue strength of welded joints and details at terminations, which may or may
TCVN 6474 -3:2007
110
not be located in highly stressed areas are to be assessed, especially where higher
strength steel is used. These fatigue and/or fracture mechanics analyses, based on the
combined effect of loading, material properties, and flaw characteristics are
performed to predict the service life of the structure and determine the most effective
inspection plan. Special attention is to be given to structural notches, cutouts,
bracket toes, and abrupt changes of structural sections.
Consideration is also to be given to the following analyses:
(1) The cumulated fatigue damage during the voyage from the fabrication or
previous site to the operation site is to be included in the overall fatigue
damage assessment.
(2) The stress range due to loading and unloading cycles is to be accounted for in
the overall fatigue damage assessment, if it is significant. For any structural
detail, a minimum criterion for computing the stress range is to consider the
tanks at 90 percent full load capacity and at its residual capacity, with
adjacent tanks also at their residual capacity. A maximum fluid specific
gravity of 0.9 is to be adopted for calculating the pressure range. The stress
range is also to account for pressure range variation due to sloshing of the
fluid inside the tank at the various filling levels, if it is significant.
1.4.3.5 Acceptance Criteria
The total assessment of the structure is to be carried out against the failure modes of
material yielding, buckling and ultimate strength, and fatigue. The reference
acceptance criteria of each mode are given as follows.
(1) Material Yielding
Criteria is given in Appendix VI ,Section 9 .
(2) Buckling and Ultimate Strength
Criteria given in TCVN 6259-2:2003 is applicable.Criteria in recognized standard
is applicable
TCVN 6474 -3:2007
111
(3) Fatigue
For existing vessels that are employed in FPI service, the estimated remaining
fatigue lives of the critical structural details are to be assessed and the supporting
calculations submitted for review. Consideration is to be given to the effects of
corrosion and wastage on the remaining fatigue life of existing structures.
The required design fatigue life is 20 years. This design fatigue life can be
modified for existing classed tankers converting to FPI service. The minimum
acceptable design fatigue life for the FPI is the greatest of:
The on-site design life of the FPI,
The time to the next Special Survey or five years.
In the absence of more detailed environmental data, stress ranges are to be
obtained in consideration of the unrestricted service environment.
The fatigue strength is based on a cumulative damage theory, which infers that the
structure is likely to experience a fatigue failure after a finite number of stress
cycles occur. This is especially important when looking at FPI conversions. The
vessel has already experienced cycles of stress during the ship phase of its life
and it will experience additional cycles during the FPI phase of its life. The
basic concept is to keep the total number of cycles below the number that results
in failure.
For FPIs converted from tankers, an analysis procedure accounting for both the
ship and FPI phases of the total fatigue life is acceptable. First, the historical
cumulative fatigue damage up to the time of conversion is to be calculated through
realistic temporal weighting of wave environments experienced along the service
routes during the service life of the vessel. This will provide an estimate of the
remaining fatigue life of the structural members at the time of conversion.
Second, the expected cumulative fatigue damage is to be calculated using site-
specific wave environment and operational conditions. This will establish the
TCVN 6474 -3:2007
112
basis for comparison of expected fatigue life of the hull structure and the
remaining life of the members being investigated.
When the route and site-specific wave environments are used and they produce
less severe fatigue demands than the unrestricted service environment of the Steel
Vessel Rules, credit can be given to the less severe environment by increasing the
expected fatigue life. For site-specific environmental conditions producing more
severe fatigue demand than the Steel Vessel Rule basis, the site-specific
environmental data are to be used.
Due to the structural redundancy and relative ease of inspection inherent in typical
hull structures of ship-type vessels, there is no further need to apply additional
factors of safety above what is already built into the fatigue classification curves
cited in the above reference. However, for areas of the structure which are non-
inspectable or critical, such as in way of the connections to the mooring or
production systems additional factors of safety should be considered.
Any areas determined to be critical to the structure are to be free of cracks, and the
effects of stress risers should be determined and minimized. Critical areas may
require special analysis and survey.
For an existing classed tanker being converted to FPI service, the minimum
fatigue lives of the structural components covered in 1.4.3.6 and 1.4.3.7 can be
changed from 20 years to the alternative controlling value mentioned above .
1.4.3.6 Acceptance Criteria Mooring/Hull Interface
The total assessment of the structure is to be performed against the failure modes of
material yielding, buckling and ultimate strength, and fatigue. The reference
acceptance criteria of each mode is given as the following:
(1) Material Yielding
Criteria is given in Appendix VI ,Part 9 .
(2) Buckling and Ultimate Strength
TCVN 6474 -3:2007
113
Criteria given in TCVN 6259-2:2003 is applicable .Recognized standard is
applicable .
(3) Fatigue
The required target fatigue life is 20 years. However, due to the critical nature
of these connections, additional factors of safety may be needed. (Also see
Part 7.) The fatigue life of the hull structure is to be investigated in accordance
with recognized standard and submitted for review as described below:
i. For vessels with a forward end mooring, the fatigue life of the vessel
should be investigated from the watertight bulkhead aft of the mooring to
the fore end of the vessel.
ii. For vessels with mid body mooring, a three-tank analysis, where the
mooring is in the middle hold, is to be investigated.
iii. For aft end mooring, the fatigue life should be investigated from the
watertight bulkhead forward of the mooring to the aft end of the vessel.
Structural members in way of the turret structure or other mooring structure are
to be effectively connected to the adjacent structure in such a manner as to avoid
hard spots, notches and other harmful stress concentrations.
Special attention is to be given to cutouts, bracket toes and abrupt changes of
structural sections. These areas are considered to be critical to the vessel and are
to be free of cracks. The effects of stress risers in these areas are to be determined
and minimized.
1.4.3.7 Turret Mooring
A turret mooring system is one type of station keeping system for a floating
installation and can either be installed internally or externally. Both internal and
external turret mooring systems will allow the vessel to weathervane around the
turret. The mooring lines are fixed to the sea bottom by anchors or piles.
TCVN 6474 -3:2007
114
For an internal turret system, the turret is supported in the vessel by a system of
bearings. The loads acting on the turret will pass through the bearing system into the
vessel. Typically, a roller bearing is located near the vessel deck level, and radial
sliding bearing is located near the keel of the vessel.
For an external turret mooring system, the vessel is extended to attach the turret
mooring system at the end of the vessel.
The loads acting on an internal turret system include those basic loads induced by the
mooring lines, risers, gravity, buoyancy, inertia and hydrostatic pressure. Other
loads, such as wave slam and loads resulting from misalignment and tolerance, that
may have effect on the turret should also be considered in the design. In establishing
the controlling turret design loads, various combinations of vessel loading conditions
ranging from the full to minimum storage load conditions, wave directions, and both
collinear and non-collinear environments are to be considered. The mooring loads
and loads applied to the external turret structure are transferred through its bearing
system into the vessel. The load range and combinations to be considered and
analysis methods are similar to those stated for an internal turret mooring system,
with additional consideration of environmentally-induced loads on the turret
structure
A structural analysis using finite element method is required to verify the sufficient
strength of the turret structure. The allowable von Mises stress of the turret structure
is to be 0.6 of the yield strength for the operational intact mooring design conditions,
as specified in 1.3,Part 2. A one-third increase in the allowable stress is allowed for
the design storm intact mooring design conditions and for the design storm one-line
broken mooring condition to verify the turret structure mooring attachment locations
and supporting structure.
(Note: the yield strength is to be based on the specified minimum yield point or 72
percent of the specified minimum tensile strength, whichever is the lesser.)
The buckling strength check for the turret structures is to be performed using
requirement in TCVN 6259-2:2003 or recognized standard . A fatigue evaluation of
TCVN 6474 -3:2007
115
the turret system using a spectral method or other proven approaches is needed to
determine the fatigue lives for the turret components. Fatigue life of the turret should
not be less than three times the design life for inspectable areas and 10 times for
uninspectable areas.
1.4.4 Assessing the Basic Design of the Hull Structure
1.4.4.1 General
The Ordinary Conversion approach relies on a review of the hulls basic design.
The review consists of an assessment of the hull girder strength and midship region
scantling review of local plating and plating stiffeners that directly contribute to the
hull girder strength. Two major purposes for this review are to assess the adequacy
of the hull girder and local strength, and to benchmark the values upon which local
scantling renewals are to be based
1.4.4.2 Basic Design Review Acceptance Criteria
The review of the basic design of an existing hull structure, which is applicable to a
tanker classed for unrestricted service, does not account for the increased or reduced
local structural element strength requirements that could result from the long-term,
moored operation of the vessel at an offshore site. The approach to the design review
also allows variations in the acceptance criteria that can be based on:
The Bureaus Rules from the year of build of the vessel with the Bureaus
permissible corrosion limits for renewal; or
The Bureaus Current Rules with the Bureaus permissible corrosion limits for
renewal; or
The prior IACS members approved scantlings using that societys permissible
corrosion limits.
The combination of the variety of ways to review local scantlings and the
permissibility to account for site-dependent effects on global and local hull structural
TCVN 6474 -3:2007
116
strength requirements can lead to a range of acceptable procedures.
If it is desired to account for the on-site environmental effects and how these affect
the required scantlings, it will be necessary to compute the required scantlings on this
basis.
1.4.5 Optional: Time to Steel Renewal Assessment
The reviews and assessments described above will establish: the notional
acceptability of hull girder strength and existing scantlings, structural areas and
components requiring renewal and the limits to which structural areas and
components may corrode before requiring renewal. However, these review and
analysis procedures in themselves do not predict how much time in operation it may
take before structural steel renewal limits could be reached. In a case where the
design operational life is relatively long, the assumed corrosion rate is relatively fast
or there are only small differences between the actual scantlings and the renewal
limits, it could be very important to the Operator to pursue a hull structure life
assessment. This should be done to better assure freedom from disruption in
operation that might arise over the need to perform steel renewals during the
operational life of the FPI. It should be noted that this type of analysis is suggested,
but is not required for classification.
1.4.6 Survey Requirements for an Ordinary Conversion
1.4.6.1 Conversion Survey Requirements
(1) Drydocking Survey
The vessel is to be placed on drydock and surveyed in accordance with the
requirements of 1.4, Part 8.
(2) Special Survey of Hull
A Special Periodical Survey of Hull, appropriate to the age of the vessel, is
to be carried out in accordance with 1.7, Part 8. All requirements for Close-
up Survey and thickness measurements are to be applied.
TCVN 6474 -3:2007
117
(3) Modifications
All modifications to the vessel are to be carried out in accordance with VR-
approved drawings and to the satisfaction of the attending Surveyor. In
general, the IACS Shipbuilding and Repair Quality Standard (SARQS)
requirements are to be followed unless a recognized shipyard or national
standard is already established in the shipyard.
1.4.6.2 Structural Repairs/Steel Renewal
All renewed material should be replaced by steel of the same or higher grade and to
the approved design scantling or greater.
1.4.6.3 Bottom Plate Pitting repair
The following repair recommendations apply to pitting found in both ballast and
cargo tank bottom plating.
(1) Repair Recommendations
There are four main approaches used for dealing with severe bottom pitting.
Partially Crop and Renew Affected Bottom Plating. Partial cropping and
renewal is primarily a matter of: proper welding technique, selection of an
adequately sized plate insert and the appropriate nondestructive
examination (NDE) of repaired areas.
Clean Pitted Areas and Cover with Special Coating. Cleaning out and
covering with special coating without use of filler or weld build-up need
only be limited by the maximum allowable depth of the pits (or allowable
minimum remaining thickness of the bottom plating) permitted from a
strength or pollution risk standpoint. The allowable loss of bottom cross-
sectional area must also be considered.
Clean Pitted Areas and Fill with Plastic Compound. Use of plastic
compound filler, such as epoxy, can be considered similar to above
TCVN 6474 -3:2007
118
method.
Fill by welding. Filling with welding warrants more serious
consideration. Suggested welding practices for bottom plating are noted
below.
(2) Pitting up to 15% of Bottom Plating Thickness
No immediate remedial action is necessary, however, if the surrounding tank
bottom is specially coated, corrosion progress in the pitted areas may be very
rapid due to the area ratio effect of protected versus non-protected surfaces,
therefore, as applicable, the coating is to be repaired.
(3) Scattered Pitting Up To 33% (1/3t) of Bottom Plating Thickness
Those pitting may be filled with epoxy or other suitable protective
compounds, provided the loss of area at any transverse section of the strake in
question does not exceed 10%. Any areas that have been repaired by this
method must be mapped and noted for close-up survey in the Survey and
Inspection Plan .
(4) Pitting of Any Depth may be Welded, Provided :
Pitting may be welded, provided there is at least 6 mm (0.25 in.) remaining
original plating thickness at the bottom of the cavity and there is at least 75
mm (3 in.) between adjacent pit welding areas. The maximum nominal
diameter of any pit repaired by welding may not exceed 300 mm (12 in.).
(5) Requirements for the Welding of Pits
Pit Welding. It is recommended that pit welding in bottom plating be built
up at least 3 mm (0.125 in.) above the level of the surrounding plating and
then ground flush.
Surface Preparation. Pitted areas are to be thoroughly cleaned of rust, oil
and cargo residues prior to welding.
TCVN 6474 -3:2007
119
Filler Metal. When welding, the filler metal grade appropriate to the pitted
base metal and preheating, if applicable, are to be employed.
Layer of Welding Metal. A layer of weld metal is to be deposited along a
spiral path to the bottom center of the pitted excavation. The slag is to be
completely removed and the next successive layer is to be similarly
deposited to build up the excavation at least 3 mm
Nondestructive Examination. All welds to pitted areas in bottom plating
are to be subject to nondestructive examination with particular attention to
boundaries of the welded areas and at intersections of the welded areas
and existing structural welding. Also, for welds of higher-strength steels,
the NDE method is to be suitable for detecting sub-surface defects
Doublers. Fitting of a doubler over pits is not considered a satisfactory
repair.
1.5 Tension Leg Platforms
Tension Leg Platforms is to be designed according to recognized Standards .
1.6 Spar Vessels
Spar Vessels is to be designed according to recognized Standards .
TCVN 6474 -3:2007
120
BLANK PAGE
121
NATIONAL STANDARD TCVN 6474-4:2007
Second Edition
RULES FOR CLASSIFICATION AND TECHNICAL SUPERVISION OF
FLOATING STORAGE UNITS
PART 4: POSITION MOORING SYSTEM
Reference documents and definitions: See Part 1, TCVN 6474-1:2007 and this Part
The position mooring system includes the mooring, anchoring and dynamic
positioning (if any) systems. The purpose of the position mooring system is to keep
the Floating Installation on station at a specific site. The Position Mooring System
includes mooring lines, connectors and hardware, winches, piles, anchors and
thrusters. For a single point mooring system, the turret, turntable, disconnecting
system, buoy, anchoring legs, etc., are also part of the system.
1. Mooring system
1.1. Definitions
Typically, there are two types of position mooring systems: conventional spread
mooring and single point mooring, as defined in Part 1. Thruster-assisted systems
are defined in Part 1, Item 2.5.4.
1.1.1. Spread Mooring
A spread mooring is a system with multiple catenary mooring lines anchored to
piles or drag anchors at the sea bed. The other end of each line is individually
attached to winches or stoppers on the vessel through fairleads as necessary. A
catenary mooring line may have one or more line segments, in-line buoy(s) (spring
TCVN 6474-4:2007
122
buoy) or sinker(s) (clumped weight) along the line.
1.1.2. Single Point Mooring (SPM)
A single point mooring allows the vessel to weathervane. Three typical types of
single point mooring systems that are commonly used are described below:
1.1.2.1. CALM (catenary anchor leg mooring): A catenary anchor leg mooring system
consists of a large buoy anchored by catenary mooring lines. The vessel is moored
to the buoy by soft hawser(s) or a rigid yoke structure.
1.1.2.2. SALM (single anchor leg mooring): A single anchor leg mooring system consists
of an anchoring structure with built-in buoyancy at or near the water surface and is
itself anchored to the seabed by an articulated connection.
1.1.2.3. Turret Mooring: A turret mooring system consists of a number of mooring legs
attached to a turret that is designed to act as part of the vessel, allowing only
angular relative movement of the vessel to the turret, so that the vessel may
weathervane. The turret may be mounted internally within the vessel or externally
from the vessel bow or stern. Typically, a spread mooring arrangement connects
the turret to the seabed.
1.1.2.4. Yoke Arm: A yoke arm is a structure at the end of the vessel that only allows
angular relative movement between the vessel and the mooring attachment to the
seabed.
The above mentioned types of single mooring system are illustrated in Part 1.
1.2. System Conditions
The various conditions of a Floating Installation which are important for the
designer to consider are as follows:
1.2.1. Intact Design
A condition with all components of the system intact and exposed to an
environment as described by the design environmental condition (DEC).
TCVN 6474-4:2007
123
1.2.2. Damaged Case with One Broken Mooring Line
A condition with any one mooring line broken at the design environmental
condition (DEC) that would cause maximum mooring line load for the system. The
mooring line subjected to the maximum load in intact extreme conditions when
broken might not lead to the worst broken mooring line case. The designer should
determine the worst case by analyzing several cases of broken mooring line,
including lead line broken and adjacent line broken cases. For a disconnectable
mooring system with quick release system, the mooring analysis for a broken line
case may not be required. For unusual (non-symmetric) mooring pattern, mooring
analysis for the broken line case for the disconnectable environmental condition
may be required.
For a system utilizing the SALM concept, the case with one broken mooring line is
not relevant. A case considering loss of buoyancy due to damage of a compartment
of the SALM structure should be analyzed for position mooring capability.
The loss of thruster power or mechanical failure on thruster-assisted position
mooring systems will be considered on a case-by-case basis.
1.2.3. Transient Condition with One Broken Mooring Line
A condition with one mooring line broken (usually the lead line) in which the
moored vessel exhibits transient motions (overshooting) before it settles at a new
equilibrium position. The transient condition can be an important consideration
when proper clearance is to be maintained between the moored vessel and nearby
structures. An analysis for this condition under the design environmental condition
(DEC) is required. The effect of increased line tensions due to overshoot upon
failure of one mooring line (or thruster or propeller if mooring is power-assisted)
should also be considered.
1.3. Mooring Analysis
The analysis of a mooring system of a Floating Installation includes the
TCVN 6474-4:2007
124
determination of mean environmental forces and the extreme response of the vessel
in the DEC (design environmental condition, see in Part 2, Item 1.4) and the
corresponding mooring line tension. A moored system is a dynamic system that is
subjected to steady forces of wind, current and mean wave drift force, as well as
wind and wave-induced dynamic forces. Calculations of the maximum mooring
system loading are to consider various relative directions of the wind, wave and
current forces.
Depending on the level of sophistication and analysis objectives, quasi-static,
quasi-dynamic (begins with calculating the low-frequency responses of the moored
vessel followed by superposition of the wave-frequency motions) and dynamic
analysis methods may be used. Both frequency and time domain approaches are
acceptable. The designer should determine the extreme vessel offset and line
tension in a manner consistent with the chosen method of analysis.
For the final design of a permanent mooring system, the dynamic analysis method
is to be employed to account for mooring line dynamics. For deepwater operations
with large numbers of production risers, the mooring system analysis should take
into account the riser loads, stiffness and damping due to significant interactions
between the vessel/mooring system and riser system.
1.3.1. Mean Environmental Forces and Moments
The calculation of steady forces and yawing moments due to wind and current are
outlined in Part 2. The available methods of calculating hydrodynamic
characteristics and hydrodynamic loading are also indicated. The drift forces and
yawing moments on a moored vessel consist of a mean wave drift force, along with
the slowly varying oscillatory drift force at or near the natural period of the spring-
mass system of the moored vessel. The mean and oscillatory low frequency drift
forces may be determined by model tests or using hydrodynamic computer
programs benchmarked against model test results or other data.
Designers may use API RP 2SK for estimating purposes, if applicable, that
TCVN 6474-4:2007
125
provides mean drift force charts for ship type vessels with lengths from 122 m (400
feet) to 165 m (540 ft) and less general information for column stabilized vessels.
Vessel-specific information is to be provided based on appropriate analysis or
model testing or both.
1.3.2. Maximum Offset and Yaw Angle of the Vessel
The wave-induced vessel dynamic responses can be calculated by the methods
outlined in Part 2, Item 1.4.5.2. The maximum offset consists of static offset due to
wind, current and wave (steady drift), and both wave and wind-induced dynamic
motions (high and low frequency). The maximum responses of surge, sway and
yaw are to be determined, as follows, in accordance with API RP 2SK:
(max) ( )
max
( ) (max)
max
mean lf wf sig
mean lf sig wf
S S S
S
S S S
+ +
=
+ +
trong :
S
mean
= mean vessel offset due to wind, current and mean (steady) drift
force (m)
S
lf(sig)
= significant single amplitude low frequency motion (m)
S
lf(max)
= maximum values of low frequency motion (m)
S
wf(sig)
= significant single amplitude wave frequency motion (m)
S
wf(max)
= maximum values of wave frequency motion (m)
Alternatively, the maximum excursion can be determined through model tests.
The maximum values of low frequency motion, S
lf(max)
and wave frequency motion,
S
wf(max)
are typically calculated by multiplying the corresponding significant single
amplitude values by a factor C that is to be calculated as follows:
1
2
2ln
a
C N
T
N
T
=
=
where:
TCVN 6474-4:2007
126
T = specified storm duration (seconds), minimum of 10,800 seconds
(i.e., 3 hours). For areas with longer storm duration (e.g., a
monsoon area), a higher value of T may need to be considered.
T
a
= average response zero up-crossing period (seconds).
For low frequency components, T
a
can be taken as the natural period, T
n
of the
vessel with mooring system. T
n
can be estimated from the vessel mass (or mass
moment of inertia for yaw motion), m (including added mass or mass moment of
inertia for yaw motion), and mooring system stiffness, k for lateral and yaw
motions at the vessel's mean position and equilibrium heading as follows:
The quantities m and k are to be in consistent units.
Note: The above formula may not be applicable for C for estimating either wave
frequency or low frequency motions. Refer to API RP 2SK for statistical limits on
the value of C and applicable recognized industry standards.
Other parameters affecting the low frequency motions, such as system stiffness and
damping forces, are to be calibrated and the supporting data submitted to VR for
review.
1.3.3. Maximum Line Tension
The mean tension in a mooring line corresponds to the mean offset and equilibrium
heading of the vessel. The design (maximum) mooring line tension, T
max
is to be
determined as outlined in API RP 2SK and is summarized below:
(max) ( )
max
( ) (max)
max
mean lf wf sig
mean lf sig wf
T T T
T
T T T
+ +
=
+ +
where:
T
mean
= mean mooring line tension due to wind, current and mean
2
n
m
T
k
=
TCVN 6474-4:2007
127
(steady) drift force (N)
T
lf(sig)
= mean mooring line tension due to wind, current and mean
(steady) drift force (N)
T
wf(sig)
= significant single amplitude wave frequency tension (N)
The maximum values of low frequency tension, T
lf(max)
and wave frequency tension,
T
wf(max)
are to be calculated in the same procedure as that of obtaining the motions
at wave frequency and low frequency described in Item 1.3.2.
1.3.4. Mooring Line Fatigue Analysis
The fatigue life of mooring lines is to be assessed using the T-N approach, using a
T-N curve that gives the number of cycles, N to failure for a specific tension range,
T. The fatigue damage ratio, D
i
for a particular sea state, i is estimated in
accordance with the Miner's Rule, as follows:
i
i
i
n
D
N
=
where:
n
i
= number of cycles within the tension range interval, i for a given
sea state
N
i
= number of cycles to failure at tension range, i as given by the
appropriate T-N curve
The cumulative fatigue damage, D for all of the expected number of sea states, NN
(identified in a wave scatter diagram), is to be calculated as follows:
1
NN
i
i
D D
=
=
D is not to exceed unity for the design life, which is the field service life multiplied
by a factor of safety, as specified in Table 4-4.
It is recommended that a detailed fatigue analysis following the procedure outlined
in Part 7.5 of API RP 2SK be performed for the permanent mooring system.
TCVN 6474-4:2007
128
The fatigue life of each mooring line component is to be considered. T-N curves for
various line components are to be based on fatigue test data and a regression
analysis.
1.4. Mooring Line Design
The mooring lines are to be designed with the factors of safety specified in Table 4-
4 with respect to the breaking strength and fatigue characteristics of mooring lines.
These factors of safety are dependent on the design conditions of the system, as
well as the level of analyses. Allowances for corrosion and abrasion of a mooring
line should also be taken into consideration.
Table 4-4: Factor of Safety for Anchoring Lines
Factor of Safety
All Intact
Dynamic Analysis (DEC) 1.67
Quasi-Static (DEC) 2.00
One broken Line (at New Equilibrium Position)
Dynamic Analysis (DEC) 1.25
Quasi-Static (DEC) 1.43
One broken Line (Transient)
Dynamic Analysis (DEC) 1.05
Quasi-Static (DEC) 1.18
Mooring Component Fatigue Life w.r.t. Design Service
Life
Inspectable areas 3.00
Non-inspectable and Critical Areas 10.00
1.5. Hawser Loads
Hawsers that are used to temporarily secure vessels to the component which is
permanently anchored to the seabed are to meet the requirements of TCVN
6809:2001.
TCVN 6474-4:2007
129
1.6. Dynamic Positioning Systems
Dynamic positioning systems installed for position mooring purposes will be
subject to approval in accordance with the requirements of TCVN 5311:2001 or
applicable recognized standards.
1.7. Thruster Assisted Mooring Systems
Where Floating Installations are equipped with thrusters to assist the mooring
system, the thrusters are subject to approval by VR or applicable recognized
standards. The contribution of the thrusters in the mooring system design will be
reviewed on a case-by-case basis.
1.8. Mooring Equipment
Mooring equipment for Floating Installations includes winches, windlasses, chain,
wire rope, in-line buoys and fairleads. Anchors and single point mooring
mechanical systems are addressed elsewhere in this Part.
For the review of mooring equipment, VR will apply the requirements in published
TCVN/ relevant Guide for such equipment, are listed below:
Buoyancy Tanks ASME Boiler and Pressure Vessel Code
Chain TCVN 6259-7B:2003 and TCVN 5311:2001
Winches and Windlasses TCVN 5311:2001
Wire Rope API Spec 9A and RP 9B
In general, the design load for the fairlead and its connection to the vessel is the
breaking strength of the mooring line.
Chain stoppers used in position mooring systems are to be designed for the
breaking strength of the mooring line. The fatigue life for inspectable chain
stoppers is not to be less than three times the service life. For chain stoppers that
cannot be readily inspected, the fatigue life is to be at least 10 times the service life.
TCVN 6474-4:2007
130
The chain stoppers are to be function tested at the specified proof load to the
satisfaction of the attending Surveyor.
2. Anchor Holding Power
Different types of foundation systems used for floating installations are drag
anchors, pile anchors, vertically loaded anchors (VLAs) and suction piles. Gravity
boxes, grouted piles, templates, etc., may also be used and are considered to be
within the scope of classification.
2.1. Drag Anchor
For a mooring system with drag anchors, the mooring line length should be
sufficiently long such that there is no angle between the mooring line and the
seabed at any design condition, as described in Part 2, Item 1.3.1.
Drag anchor holding power depends on the anchor type, as well as the condition of
the anchor deployed in regard to penetration of the flukes, opening of the flukes,
depth of burial, stability of the anchor during dragging, soil behavior of the flukes,
etc. The designer should submit to the Bureau the performance data for the specific
anchor type and the site-specific soil conditions for the estimation of the ultimate
holding capacity (UHC) of an anchor design. Because of uncertainties and the wide
variation of anchor characteristics, exact holding power is to be determined after
the anchor is deployed and test loaded.
The maximum load at anchor, F
a
is to be calculated, in consistent units, as follows:
a line sub f
f sl bed sub
F P W WD F
F f L W
=
=
where:
P
line
= maximum mooring line tension (N)
WD = water depth (m)
f
sl
= frictional coefficient of mooring line on sea bed at sliding
TCVN 6474-4:2007
131
L
bed
= length of mooring line on seabed at the design storm condition,
not to exceed 20 percent of the total length of a mooring line(m)
W
sub
= submerged unit weight of mooring line (N/m)
Note: The above equation for F
a
is strictly correct only for a single line of constant,
W
sub
without buoys or clump weights. Appropriate adjustments will be required for
other cases.
The coefficient of friction f
sl
depends on the soil condition and the type of mooring
line. For soft mud, sand and clay, the following values of f
sl
along with the
coefficient of friction at start f
st
for wire rope and chain may be considered
representative in Table 4-5:
Table 4-5: Coefficient of Friction
Coefficient of Friction, f
Starting (f
st
) Sliding (f
sl
)
Chain 1.00 0.70
Wire Rope 0.60 0.25
2.2. Conventional Pile
Conventional pile anchors are capable of withstanding uplift and lateral forces at
the same time. Analysis of the pile as a beam column on an elastic foundation is to
be submitted to VR for review. The analyses for different kinds of soil using
representative soil resistance and deflection (p-y) curves are described in API RP
2A and API RP 2T, as applicable. The fatigue analysis of the pile should be
submitted for review.
2.3. Vertically Loaded Drag Anchors (VLA)
VLAs can be used in a taut leg mooring system with approximately a 35 to 45
degree angle between the seabed and the mooring lines. These anchors are
designed to withstand both the vertical and horizontal loads imposed by the
mooring line. The structural and geotechnical holding capacity design of the VLA
TCVN 6474-4:2007
132
are to be submitted for review. This is to include the ultimate holding capacity and
the anchor's burial depth beneath the seabed. Additionally, the fatigue analysis of
the anchor and the connectors joining the VLA to the mooring line should be
submitted for review.
The safety factors of VLA anchors' holding capacity are specified in Table 4-6
Table 4-6: Factor of Safety for Anchor Holding Capacities
Factor of Safety
Drag Anchors
Intact Design (DEC) 1.50
Broken Line Extreme (DEC) 1.00
Vertically Loaded Anchors (VLAs)
Intact Design (DEC) 2.00
Broken Line Extreme (DEC) 1.50
One broken Line (Transient)
Dynamic Analysis (DEC) 1.05
Quasi-Static (DEC) 1.18
Pile Anchors
Refer to API RP 2A, API RP 2T as applicable
Suction Piles
Intact Design (DEC) 1.5 to 2.0*
Broken Line Extreme (DEC) 1.2 to 1.5*
* The safety factor to be used in the design should be based on the extent of the
geotechnical investigation, confidence in the prediction of soil-pile behavior,
experience in the design and behavior of suction piles in the area of interest, and
the inclination of the mooring line load.
2.4. Suction Piles
Suction pile anchors are caisson foundations that are penetrated to the target depth
by pumping out the water inside of the pile to create underpressure within the pile.
TCVN 6474-4:2007
133
They may typically consist of a stiffened cylindrical shell with a cover plate at the
top and an open bottom and generally have larger diameters and are shorter in
length than conventional piles. These piles can be designed to have a permanent top
or a retrievable top depending on the required vertical holding capacity. The
padeye for the mooring line connection can be at the top or at an intermediate level
depending on the application of the suction pile.
Suction pile anchors are capable of withstanding uplift and lateral forces. Due to
the geometry of the suction piles, the failure modes of the soils may be different
than what are applicable for long slender conventional piles. The safety factors for
the suction piles' holding capacity are specified in Table 4-6.
Geotechnical holding capacity and structural analyses for the suction piles are to be
submitted to verify the adequacy of the suction piles to withstand the in-service and
installation loads. Additionally, fatigue analysis of the suction piles are to be
submitted to verify the adequacy of the fatigue life of the critical locations.
Installation analyses are to be submitted to verify that the suction piles can be
penetrated to the design penetration and that the suction piles can be retrieved, if
necessary. It is suggested that a ratio of at least 1.5 between the force that would
cause uplift of the soil-plug inside of the pile and the effective pile installation
force be considered in the penetration analysis.
2.5. Factor of Safety
The factors of safety for anchor holding capacity in the design of drag anchors,
VLAs and suction piles are specified in Table 4-6. The required ultimate holding
capacity should be determined based on mooring line loads derived from a dynamic
analysis to account for mooring line dynamics. Conventional pile anchors should
meet the recommended factors of safety as specified in API RP 2A, and API RP
2T, as applicable.
3. Field Test
TCVN 6474-4:2007
134
After the mooring system is deployed, each mooring line will be required to be
pull-tested. During the test, each mooring line will be pulled to the maximum
design load determined by dynamic analysis for the intact design condition and
held at that load for 30 minutes. For certain high efficiency drag anchors in soft
clay, the test load may be reduced to not less than 80 percent of the maximum
intact design load. For all types of anchors, the attainment of design-required
minimum soil penetration depth is to be verified at the site.
VR will determine the necessity of a maximum intact design tension pull test
depending on the extent of the geotechnical investigation, the magnitude of
loading, analytical methods used for the geotechnical design and the experience
with the soils in the area of interest. For suction piles, VR will also review the pile
installation records to verify the agreement between the calculated suction
pressures and the suction pressure used to install the suction piles. For conventional
piles, VR will review the pile installation records to verify the agreement between
the calculated pile driving blow counts and the actual blow counts required to drive
the piles to the design penetration.
If the maximum intact design tension pull tests are waived, VR will require
preloading each anchor to a load that is necessary to develop the ultimate holding
capacity of the anchor, but not less than the mean intact design tension, and to
ensure the integrity and alignment of the mooring line.
For a disconnectable mooring system, the pull test load will be the greater of the
following two values:
(1) Maximum design load for "Disconnecting Environmental Condition
(DISEC)", i.e., the limiting extreme environmental condition at which the
vessel is to be disconnected.
(2) Maximum design load of mooring line for the "Design Environmental
Condition (DEC)" without the vessel, i.e., the disconnected mooring system
alone.
TCVN 6474-4:2007
135
4. Single Point Moorings - CALMs, SALMs, Turrets and Yokes
4.1. Design Loadings
The design of structural and mechanical components is to consider the most
adverse combination of loads, including, but not limited to, those listed below, and
is to be submitted for review:
(1) Dead Loads
(2) Dynamic Loads due to motions
(3) Mooring Loads
(4) Fatigue Loads
4.2. Structural Components
In general, structural components are to be designed to a recognized code or
standard. The structural and buoyancy elements of CALMs and SALMs are to
comply with the requirements of the Single Point Mooring Rules - TCVN
6809:2001. Minimum mooring turret and yoke arm scantlings are to comply with
TCVN 5310:2001, Item 4.5.3
4.3. Mechanical Components
Mechanical components of an SPM usually include the Product Distribution Unit
(PDU), bearings, driving mechanisms and various types of connectors. TCVN
6809:2001 are generally applicable to these components, and in cases where
specific requirements are not addressed in the TCVN 6809:2001, VR will review
those components for compliance with the following standards and codes:
Product Distribution Unit ASME Boiler and Pressure Vessel Code
AISC Steel Code
ANSI B31.3 (for Pipe Swivels)
TCVN 6474-4:2007
136
Bearings AFBMA Codes (Anti Friction Bearing
Manufacturers Association ASME 77-DE-39
Connectors: driving mechanisms ASME Boiler and Pressure Vessel Code
AISC Steel Code
API Standards as applicable
Ancillary mechanical components, such as structural connectors, uni-joints, chain
jacks, turret retrieval mechanisms, hoists, winches, quick connect and disconnect
devices, are to be designed in accordance with Vietnam (or International)
applicable industry standards, codes and published recommended practices if was
approved by VR.
4.4. Hazardous Areas and Electrical Installations
Requirements for hazardous areas and electrical installations are in TCVN
6809:2001.
4.5. Fire Fighting Equipment
Fire fighting equipment is to comply with TCVN 6809:2001. Additionally, for the
internal turret mooring arrangement, Appendix VII, Part 9 is applicable.
4.6. Product Piping Systems and Floating Hoses
Product piping systems and floating hoses are to comply with the applicable
requirements of TCVN 6809:2001 v , Appendix VII, Part 9.
4.7. Turret Mooring
A turret mooring system is one type of station keeping system for a floating
installation and can either be installed internally or externally. Both internal and
external turret mooring systems will allow the vessel to weathervane around the
turret. The mooring lines are fixed to the sea bottom by anchors or piles.
TCVN 6474-4:2007
137
For an internal turret system, the turret is supported in the vessel by a system of
bearings. The loads acting on the turret will pass through the bearing system into
the vessel. Typically, a roller bearing is located near the vessel deck level, and
radial sliding bearing is located near the keel of the vessel. For an external turret
mooring system, the vessel is extended to attach the turret mooring system at the
end of the vessel.
The loads acting on an internal turret system include those basic loads induced by
the mooring lines, risers, gravity, buoyancy, inertia and hydrostatic pressure. Other
loads, such as wave slam and loads resulting from misalignment and tolerance, that
may have effect on the turret should also be considered in the design. In
establishing the controlling turret design loads, various combinations of vessel
loading conditions ranging from the full to minimum storage load conditions, wave
directions, and both collinear and non-collinear environments are to be considered.
The mooring loads and loads applied to the external turret structure are transferred
through its bearing system into the vessel. The load range and combinations to be
considered and analysis methods are similar to those stated for an internal turret
mooring system, with additional consideration of environmentally-induced loads
on the turret structure.
A structural analysis using finite element method is required to verify the sufficient
strength of the turret structure. The allowable von Mises stress of the turret
structure is to be 0.6 of the yield strength for the operational intact mooring design
conditions, as specified in Item 4.3. A one-third increase in the allowable stress is
allowed for the design storm intact mooring design conditions and for the design
storm one-line broken mooring condition to verify the turret structure mooring
attachment locations and supporting structure.
Note: the yield strength is to be based on the specified minimum yield point or 72
percent of the specified minimum tensile strength, whichever is the lesse.)
The buckling strength check for the turret structures is to be performed using the
criteria in TCVN 6259-2:2003 or other applicable industry standards. A fatigue
TCVN 6474-4:2007
138
evaluation of the turret system using a spectral method or other proven approaches
is needed to determine the fatigue lives for the turret components. Fatigue life of
the turret should not be less than three times the design life for inspectable areas
and 10 times for uninspectable areas.
4.8. Turret/Vessel Structural Interface Loads
The vessel structure in the way of the turret mooring system interface is to be
capable of withstanding forces (obtained as the maximum of all the design
conditions considered) from the systems and is to be suitably reinforced.
Mooring forces transmitted to the vessel's supporting structure by the turret
mooring system are to be determined by an acceptable engineering analysis. The
transmission and dissipation of the resulting mooring forces into the vessel's
structure are required to be determined by an acceptable engineering method, such
as finite element analysis. The loads acting on the vessel's supporting structures due
to the turret system are mainly transmitted through the upper and lower bearings.
The loading conditions are chosen to cause the most unfavorable loads and the load
combinations that may occur. The derivation of mooring loads is to be determined
as described in the previous Subsection of the "Turret Mooring System." The
structural model used in the finite element analysis for the vessel's supporting
structure should extend to a reasonable distance of the vessel to minimize the
effects due to the boundary conditions.
5. Surveys During Construction
Items of equipment to be used in a mooring system are to be examined during the
fabrication process, and testing is to be performed to the satisfaction of the
attending Surveyor.
Components fabricated by welding are to meet the requirements of TCVN 6259-
6:2003 and are to be to the Surveyor's satisfaction. Specifications to be used for
chain, wire rope and connecting hardware are to be submitted for review. Physical
testing, including break, pull, dimensional and nondestructive testing, is required to
TCVN 6474-4:2007
139
be performed in accordance with the submitted specifications to the satisfaction of
the attending Surveyor.
TCVN 6474-4:2007
140
BLANK PAGE
141
NATIONAL STANDARD TCVN 6474-5 : 2007
Second edition
RULES FOR CLASSIFICATION AND TECHNICAL
SUPERVISION OF FLOATING STORAGE UNITS
PART 5 : HYDROCARBON PRODUCTION AND PROCESS SYSTEMS
Reference standards and definitions: see Part 1, TCVN 6474-1: 2007
1. Hydrocarbon Production and Process Systems
1.1. General requirements
Hydrocacbon production and procesing system are to comply with requirements of
Aoppendix VII, Part 9 and sections 1.2 to 1.11 below.
1.2. Application
This section is applicable to the following:
(1) Systems that process hydrocarbon liquids, gasses, or mixtures from completed
wells.
(2) Production support systems associated with the process system, such as water,
steam, hydraulics, pneumatics, and power supply to the process.
(3) Fire protection systems for the protection of the process equipment and the
process area
(4) Systems that are utilized for stimulation of a completed well, such as chemical,
gas, or water injection downhole through a Christmas tree.
TCVN 6474-5:2007
142
(5) Power generation systems for export purposes.
(6) Electrical systems and components associated with the process facilities.
(7) Systems other than those mentioned above, such as methanol production and/or
processing, and desalination, will be the subject of special consideration.
The scope of the hydrocarbon process system is defined in Regulation 2.4, Section 2 of this
Rule. The scope of the hydrocarbon process system may also include the controls for the
well head and subsurface safety valve, if these are included in the process safety shutdown
system.
1.3. Subsea Equipment.
1.3.1 Subse equipment is not a part of the classification boundaries as defined in 3.2, Part
1. However. subsea equipment may be classed if desired by the Owner, provided these
items are approved by the VR for compliance with the requirements of recognized
standards.
1.3.2 The VR is prepared to certify the subsea equipment if the manufacturers / Owner
wish to obtain VR Certification. The design, contruction, and testing of the subsea
equipment are to be accordance with Appendix VII, Part 9.
1.4. Use other standards
Use of other standards in the design and construction of the equipment and components is
subject to pror approval and acceptance by the VR. The standards being applied are to be
adhered to in its entirety.
1.5. Non-standard Equipment
Equipment not designed to a recognized standard may be accepted based on approval of
detailed design calculations and testing results that verify the integrity of the equipment.
1.6. Design and Construction
1.6.1 General
Hydrocarbon process systems and associated equipment are to be designed to minimize the
TCVN 6474-5:2007
143
risk of hazards to personnel and property. This criterion is implemented be showed in the
amendment VII, section 9. The implementation of this criterion is intended to:
(1) Prevent an abnormal condition from causing an upset condition.
(2) Prevent an upset condition from causing a release of hydrocarbons.
(3) Safely disperse or dispose of hydrocarbon gasses and vapors released.
(4) Safely collect and contain hydrocarbon liquids released.
(5) Prevent formation of explosive mixtures.
(6) Prevent ignition of flammable liquids or gasses and vapors released.
(7) Limit exposure of personnel to fire hazards.
1.6.2 Arrangements
General arrangement drawings are to be submitted for review in accordance with
Regulation 5.2, section 1. The arrangements depicted are to comply with Regulation 17.3.2
and 17.7.4 , Appendix VII, applicable Sections of TCVN 6259:2003 and 5309-5319:2001,
as applicable.
1.6.3 Structural Considerations
Structure that supports production facilities or forms an integral part of the equipment is to
be designed to a recognized standard. Plans and calculations are to be submitted for
reviewing. Process liquid weights and dynamic loads due to vessel motions and other loads,
such as wind imposed loads, are to be considered.
1.7. Process System
1.7.1 Submittals
The various data and plans that are to be submitted to the VR for review are listed
Regulation 5.2, section 1.
TCVN 6474-5:2007
144
1.7.2 Piping System and Manifolds
Piping of the process and process support systems are to comply with the requirements of
recognized standards (refer to API 14E and ASME/ANSI B31.3 and B31.1).
1.7.3 Pressure Relief and Depressurization Systems
Pressure relief and depressurization systems are to comply with the requirements of
recognized standards (refer to API RP 520 and API RP 521).
1.7.4 Process Equipment
Process equipments are to comply with the applicable requirements in Subsections
17.3.9 of Appendix VII, section 9.
1.7.5 Prime Movers
Internal combustion engines and gas or steam turbines are to comply with Subsections
17.4.2 of Appendix VII, section 9.
1.7.6 Safety Systems
Safety systems are to comply with Subsections 17.3.4 and 17.3.5 of Appendix VII, section
9. Specific items to be addressed are as follows:
(1) The process safety and shutdown system is to comply with the requirements of
recognized standards (refer to API RP 14C).
(2) Fire detection and gas detection is to comply with the requirements of recognized
standards (refer to API RP 14C and API RP 14G). The location of the fire and gas
detectors is to be to the satisfaction of the VR .
(3) The process safety shutdown system is required to shut down the flow of
hydrocarbon from all wells and process systems. The discharge of processed
hydrocarbons to the export lines is also to be controlled by the process safety
shutdown system. Redundancy is to be provided in the power source to the
TCVN 6474-5:2007
145
process safety shutdown system such that, upon failure of the main power source,
the secondary power source is brought online automatically.
1.7.7 Control System
Control systems, in general, are to comply with regulation 6 of Appendix VII, Section 9.
Additionally, computer based control systems are to comply with the following:
(1) The control system is to be totally independent of the alarm and monitoring
system.
(2) Where computers are utilized for monitoring, alarm, and control, the
arrangements are to be such that a fault in one of these functions will not impair
the capability of other functions.
(3) The computer system for monitoring alarms and control is to include redundancy
arrangements in order to maintain continued operation of the hydrocarbon process
system.
1.7.8 Quick Disconnect System
(1) Where the Floating Installation is fitted with a quick disconnect system, the
control of this system is to be .totally independent of the process safety shutdown
system required for the hydrocarbon process system. However, the source of
power for the process safety shutdown system and controls for the quick
disconnect system need not be totally independent, provided that the failure in
one system does not render the other system ineffective, e.g., failure through
leakage in the hydraulic or pneumatic control lines.
(2) Means are to be provided for the activation of quick disconnect system from the
control station and locally in the vicinity where the disconnect arrangements are
located.
(3) The disconnect arrangement is to be designed such that, upon its activation, all
process flow to the Floating Installation is automatically stopped immediately
without leakage of process fluids
TCVN 6474-5:2007
146
1.7.9 Electrical Installations
Electrical installations for the hydrocarbon process system are to comply with the
requirements regulation 5 of Appendix VII, Section 9.
1.8. Hazardous Area Classification
Hazardous areas are to be delineated and classified as required Regulation 3 of Appendix
VII, Section 9. In general, API RP 500 & API RP 501 is to be applied to process areas, and
the Steel Vessel Rules TCVN 6259:2003 or the Mobile Offshore Drilling Unit Rules TCVN
5309-5319:2001 are applied to non process areas.
1.9. Fire protection
Fire extinguishing systems and fire fighting equipment associated with the hydrocarbon
process facilities are comply with regulation 5 of appendix VII, Part 9.
1.10. Fabrication and testing
Inspection and testing of hydrocarbon process and associated equipment at the
manufacturers facility are to be in accordance with Table 17-1 of Appendix VII, Part 9.
Construction and fabrication is to be performed in accordance with approved planls and
procedures. Respresentative survey interventions are listed as follows.
1.10.1 Pressure Vessels, Accumulators, Heat Exchangers, Separators, and Manifolds.
(1) The construction, fabrication and material are accordance with design standard
shown on the approved plans.
(2) Witness weld procedure and welder performance qualification tests.
(3) Visual inspection of weld joints, witness non-destructive testing.
(4) Fit up and joining of all pipe connections and pipe supporting arrangement.
(5) Dimensional inspection during fit-up and after completion.
(6) Internal examination.
(7) Witness calibration of hydrostatic testing equipment.
TCVN 6474-5:2007
147
(8) Witness hydrostatic tests.
1.10.2 Pumps, Compressors and Diesel/Gas Engines
(1) Witness mechanical running tests.
(2) Witness testing of auxiliary equipment and protective devices (controls, filters,
coolers, oil pumps, alarms, trips, governors).
1.10.3 Motors and Generators
(1) Functional running test for machines greater than 100 kW.
(2) Witness testing of auxiliary equipment and protective devices.
1.10.4 Switchboards and Control Panels
1.10.4.1 Inspection and witness testing at the manufacturer's facility is not required for
switchboards and control panels. These components will be accepted for use, provided they
have been designed and constructed to a recognized national or international code or
standard.
1.10.4.2 Control and alarm panels for fire protection and safety systems are to be
function-tested at the manufacturer's facility. These tests are to be conducted in the presence
of the Surveyor.
1.10.5 Process and Process Support Piping
1.10.5.1 Fabrication, inspection and testing of process and utility piping is to be
performed to the satisfaction of the attending Surveyor.
TCVN 6474-5:2007
148
BLANK PAGE
149
NATIONAL STANDARD TCVN 6474-6 : 2007
Second edition
RULES FOR CLASSIFICATION TECHNICAL SUPERVISION OF
FLOATING STORAGE UNITS
PART 6: IMPORT AND EXPORT SYSTEMS
Reference standards and definitions: see Part 1, TCVN 6474-1: 2007.
1. Import and export systems
1.1. General
This section applies to import and export systems utilized in Floating Installations. These
systems include rigid and flexible risers, connecting flow lines, submerged jumpers, and
floating offloading hoses.
1.1.1 Riser Classification Boundaries
1.1.1.1 The import/export system is assumed to consist of only rigid, flexible hose/pipe or a
combination of both rigid and flexible hose/pipe, and associated riser components, such as the
tensioning system, buoyancy modules, line buoys, permanent clamps, anchoring systems, and
safety control systems
1.1.1.2 In a typical Floating Installation import (or export) system, the applicable starting and
termination points are the riser's connection point to the PLEM and the riser's connection point
to the vessel or floating structure. The connection points are typically the discharge (or input)
flange of the PLEM and the input (or discharge) flange of the vessel or floating structure
1.1.1.3 The Import System: The Import System is to include the import risers starting from the
Import PLEM but not including the Import PLEM. For a typical flexible riser system, the
import riser may start at the PLEM/wellhead flanges and terminate at the input flange of the
TCVN 6474-6:2007
150
vessel or floating structure.
1.1.1.4 The Export System : The Export System is to include the export risers that may start
from the discharge flanges of the vessel or floating structure and terminate at the Export
PLEM but not including the Export PLEM
1.1.1.5 Where Import and/or Export Risers induce mooring restraint to the Floating Installation,
design, construction will require special consideration.
1.1.2 Basic Design Considerations
1.1.2.1 The import/export,'system is to be designed to maintain its integrity under the most
unfavorable combination of external environmental loads, internal loads due to fluid contents,
pressure and temperature, and accidental loads. This is accomplished by ensuring that riser
system design is consistent and compatible with the design philosophy used for the Floating
Installation.
1.1.2.2 The dynamic response of the import/export system is to be investigated to the level of
detail necessary to ensure that interference between the floating production vessel and the
associated mooring system does not affect the integrity of the vessel or the import/export
system.
1.1.2.3 The riser is to to be designed in confomity with the maximum vessel offset.
1.2. Submission of Plans and Design
Documentation outlining the design, manufacture, installation, and operating assumptions
applicable to the project is to be submitted for review at the initiation of the project. The
following summarizes the typical information that is required to help ensure that the design
basis and criteria selection is consistent with the design philosophy. In general, the
following are to be submitted for review:
(1) Site plan indicating bathymetric features, the location of obstructions to
be removed, the location of permanent manmade structures, and other important
TCVN 6474-6:2007
151
features related to the characteristics of the sea floor.
(2) Material specifications for the import/export system, its supports, and coatings.
(3) Pipe manufacture, testing, and quality control procedures.
(4) Flow diagrams indicating temperature and pressure profiles.
(5) Specifications and plans for installation, field testing, inspection,
anticipated component replacement, and continued maintenance of the riser system.
(6) Environmental and geotechnical report.
1.3. Environmental conditions.
Environmental loads are to be calculated in accordance with the method described in Part 2
1.4. System Design and Analysis
1.4.1 General requirements
1.4.1.1 The design of the import/export system should consider all modes of operating, testing,
survival, and accidental events. The import/export system should be analyzed to determine its
response to the design events. Each individual component should be examined for its strength
and suitability for the service conditions.
1.4.2 Rigid Risers
1.4.2.1 Design Analysis
The analysis of a rigid riser is to follow the appropriate sections of API RP 2RD and API RP
2T for all relevant design load cases. The establishment of the critical design condition must be
verified by a suitable verified program that properly simulates the dynamic response of the entire
system operating under the required design condition.
The following items, as applicable, are to be appropriately accommodated in the analysis:
TCVN 6474-6:2007
152
(1) Environmental conditions.
(2) Boundary conditions.
(3) Riser configuration.
(4) Riser joint properties.
(5) Buoyancy devices.
(6) Vessel motion (RAO's).
(7) Applicable site conditions.
(8) Effects of internal contents.
(9) Pressure testing and accidental conditions.
1.4.2.2 Design Limits
Rigid risers are to be designed against the following limits based on the design load cases being
investigated.
Maximum Stress, Stability, and Buckling . Allowable stresses in plain pipe are to be limited per
API RP 2RD. Overall stability of the riser and local pipe buckling should be evaluated.
Maximum Deflection. Acceptable limits of maximum deflection are to be determined
considering the inherent limitations of riser components, equipment used in the riser, and the
need to avoid interference with the Floating Installation.
Fatigue and Fracture. The riser system is to be designed to ensure that an adequate margin of
safety is available for critical components to counteract the effects of fatigue caused by cyclic
fluctuations (due to both internal and external loads) over the anticipated life of the system.
The cumulative damage calculated by the use of Miner's Rule is to be 0.1 or less for a critical
component, which cannot be easily inspected or repaired. For non-critical components, which
can be easily inspected, the cumulative damage should be 0.3 or less.
TCVN 6474-6:2007
153
1.4.3 Flexible Risers
1.4.3.1 place Analysis
(1) On-bottom stability for flexible flow lines
(2) Static and dynamic analysis for flexible riser
(3) A system dynamic analysis to ensure:
(a) Maximum tension and minimum radius of curvature are within the
manufacturer's
recommendations.
(b) Suspended portions of the flexible pipe (e.g., sag bends) are not allowed to
bounce on the sea floor or experience compression that might cause kinks.
(c) Suspended flexible pipes are not allowed to chafe against each other, the vessel
body, or mooring lines.
(4) Flow induced motion analysis
(5) Flexible pipe layer stress analysis.
(6) The stresses in the flexible pipe layers shall comply with the requirements of recognized
standards (refer to API SPEC 17J).
(7) Mechanical gripping devices should not cause damage to the weaker exterior layer.
(8) Service life analysis
(9) Corrosion protection system design.
1.4.3.2 Design Limits
Design limits established for the riser system are to be determined in accordance with
recognized standards (refer to API RP 17B) and confirmed by performance/acceptance testing
during the manufacture of the flexible riser and the associated components. Where sufficient test
TCVN 6474-6:2007
154
data and service history exist to confirm a component's capability, VR may consider the
acceptance of this documentation in lieu of performance/ acceptance testing.
1.4.4 Export Vessel Transfer System
This system may be classed if requested. Export of fluid to an export vessel is usually limited to
stabilized crude oil and is usually accomplished by:
Side-by-side transfer,
Tandem transfer, or
Single Point Moored Buoy via a floating hose or riser.
For certification of these systems, VR requires compliance to OCIMF Standards and
MARPOL. The OCIMF Standard is applicable for operating pressures not greater than 1.5
Mpa (15 bar gauge). In complying with these standards, VR requires the Owner to observe the
guidelines as given in The OCIMF Guide to Purchasing, Manufacturing, and Testing of
Loading and Discharge Hoses for Offshore Moorings. The operation and safety considerations
for transfer of crude are to be contained in the Floating Installation's operations manual and
consistent with the requirements outlined in The OCIMF Ship to Ship Transfer Guide and
Chapter 6.
1.4.5 System Components
All system components are to be designed in accordance with the appropriate criteria of
recognized standards. The specification for the design and manufacture of the components is
to be submitted. The specification is to include at a minimum the performance criteria
established from the riser design and analysis and give explicit acceptance criteria needed to
ensure the compliance to these criteria.
1.4.6 Installation Analysis
The installation analysis is to address all aspects of installation procedure discussed in 1.1.6 Part
TCVN 6474-6:2007
155
7. Calculations to demonstrate the structural integrity of the riser and its auxiliary components
are to be submitted for review.
The riser pipe is to be checked for all installation loads, tension and bending combination
(bending from chute, sleeve, roller, or drum), and loads caused by the installation of auxiliary
components.
Loads from mechanical gripping devices, such as clamps and tensioners, are to be checked and
are not to cause damage to the weaker exterior layer of the flexible pipe.
1.5. Material
1.5.1 Material for Rigid Risers
Material and dimensional standards for steel pipe are to be in accordance with recognized
standards (refer ANSI/ASME B31.4 and B31.8, API RP 2RD), for respect to chemical
composition, material manufacture, tolerances, strength, and testing requirements.
1.5.2 Material for Flexible Risers
Recognized standards may be used to assess the adequacy of the material standards for flexible
risers. (refer API RP 17B and API SPEC 17J)
TCVN 6474-6:2007
156
BLANK PAGE
157
NATIONAL STANDARD TCVN 6474-7 : 2007
Second Edition
RULES FOR CLASSIFICATION AND TECHNICAL SUPERVISION OF
FLOATING STORAGE UNITS
PART 7: INSTALLATION, HOOK-UP AND COMMISSIONING
Reference documents and definitions: See Part 1, TCVN 6474-1:2007.
1. Installation, Hook-up, and Commissioning
1.1. General requirements
The requirements in this Part apply to the procedures to be submitted and the
surveys to be performed by VR for all VR-classed Floating Installations. Prior to
carrying out the installation, the installation procedures are to be submitted to VR.
The installation procedures to be submitted are to include the following, where
applicable.
1.1.1. General Description
General description of the entire layout of the mooring system and of the Floating
Installation with risers, subsea pipelines and, as applicable, pipeline end manifolds
(PLEMs).
1.1.2. Pre-installation Verification
Pre-installation verification procedures for the seabed condition in way of the
installation site and contingency procedures for removing any obstacles found on
site.
1.1.3. Pile or Anchor and Mooring Line Installation
Pile or anchor and mooring line installation procedures which are to include, but
TCVN 6474-7:2007
158
are not limited to, the following:
- General preparations for installation.
- Rigging arrangements for piles, chaser pile and driving hammers.
- Work barge setup during the various phases of installation, taking into
consideration the prevailing weather conditions.
- Anticipated pile driving resistance.
- Pile penetration acceptance criteria established by design and pile refusal and
overdrive contingency procedures.
- Procedure for positioning of the pile orientation toward the center of the
Position Mooring System and the criteria for allowable deviations of position
and orientation.
- Procedure for installation of the mooring line and the precautions to be taken
in order toprevent any twisting of the mooring chains during installation.
- Procedure for installation of anchors, including piggyback anchors, if
applicable, and procedure for determining the installed positions and
orientations of the anchors. Criteria for allowable deviations in positioning and
orientation are also to be included.
1.1.4. Tensioning and Proof Load Testing
Tensioning and proof load testing procedures of the anchor piles or anchors and
chain system are to include the following:
- Rigging arrangements for proof load tension testing of the mooring chains,
anchor or pile system.
- Work barge setup to perform the proof load testing of the chains and anchor or
pile system.
TCVN 6474-7:2007
159
- Detailed tensioning procedure, including type of tensioning device to be
utilized and tensioning operations.
- Chain retrieval and abandonment procedures during tensioning.
- Procedure for chain proof load tensioning by ballasting the Floating
Installation, if applicable.
1.1.5. Hook-up of the Anchor Chain System
Procedure for hook-up of the anchor chain system to the Floating Installation,
which is to include the following:
- Rigging and towing procedures for positioning of the Floating Installation for
hook-up to the mooring system.
- Preferred ballast condition of the Floating Installation prior to the hook-up.
- Procedure for sequential hook-up of the chains, repositioning of the Floating
Installation and tensioning of the chains.
- Method of determining the correct tension of the chains and the acceptable
design tolerance.
- Procedure for determining the positioning of the SPM system relative to the
PLEM or wellhead and the acceptable design tolerance for the position of the
SPM center relative to the PLEM or wellhead.
- Method of securing the chain turntable from movement and the overall safety
precautions for the entire hook-up installation.
- Procedure for chain tensioning by ballasting the Floating Installation, if
applicable.
1.1.6. Import/Export System Installation
The Import/Export System Installation Procedure is to be submitted for review in
TCVN 6474-7:2007
160
conjunction with the design review so that it can be verified that all appropriate
installation loadings have been considered. The manual is to describe procedures to
be employed during the installation of the import/export systems. In addition, the
manual is to include a list of allowable environmental limits under which system
installation may proceed. Abandonment procedures, retrieval procedures and repair
procedures are to be supplied, when deemed necessary.
1.1.6.1. Rigid and Flexible Risers
The procedure to hook-up the import/export risers to the Floating Installation is to
include the following items, where applicable:
(1) Handling and rigging of the rigid and flexible riser during installation.
(2) Positioning of the work barge for the various phases of the installation.
(3) Procedure for installation of the buoyancy tank and arch support and clump
weight, if applicable, including steps to avoid riser interference and
precautions against damaging the riser during installation.
(4) Tie-in rigging technique for hook-up of both ends of the risers.
(5) Procedure for hydrostatic testing of the risers. Hydrotest pressure and test
duration are to be in accordance with API or other recognized code of
practice.
1.1.6.2. Export Vessel Transfer System
The procedure for installing the export system is to include the following items, as
applicable.
(1) Rigging, handling and make-up of the export hose system and precautions
against damage during installation.
(2) Fitting of all the necessary accessory and navigational aids.
(3) Procedure for paying out of the hose string into the sea.
TCVN 6474-7:2007
161
(4) Procedure for filling and testing the hose string. The required design and
testing pressure and testing duration are to be provided.
1.1.7. Disconnecting Procedure
For disconnectable mooring systems, the procedures for the disconnecting and
connecting of the Floating Installation's mooring system are to be submitted. These
procedures are to include the abandonment and retrieval of the import and export
systems. (Also see Operating Manual requirements.)
1.2. Hook-Up Procedures Submittal
Any system component installation intentionally left incomplete to ease the
installation of the Floating Installation at site is to be documented and a procedure
for site hook-up and testing is to be submitted to VR.
1.3. Start-Up and Commissioning Procedures Submittal
Start-up and commissioning procedures for the production system are to be
submitted for review in Appendix VII, Part 9.
1.4. Surveys during Installation of the Mooring Systems
During installation, the requirements as contained in the following paragraphs are
to be verified or witnessed, where applicable, by the attending Surveyor.
1.4.1. All mooring components are to be examined for transit damages prior to
installation. Any damages found are to be dealt with to the satisfaction of the
attending Surveyor.
1.4.2. All applicable components required to be certified at the manufacturers' facilities
have received certification.
1.4.3. The area at and in the vicinity of the mooring site is to be surveyed by divers or
remotely operated vehicles (ROVs) to ensure that there are no obstructions or
debris prior to installation.
1.4.4. During the installation of the anchors or anchor piles, the following are to be
verified in order, where applicable:
TCVN 6474-7:2007
162
(1) Proper locking of all connecting shackles from chains to piles or anchors and
chains to chains.
(2) Sealing of all kenter shackle locking pins.
(3) All complements of anchor chains for correct sizes and lengths.
(4) All anchor pile or anchors are installed in the designed positions and
orientations and are within the allowable design tolerance.
1.4.5. The paying out of the anchor chains after the installation of the piles is to be
performed in accordance with the approved procedures.
1.4.6. Unless otherwise approved by the attending Surveyor, the first pair of anchor
chains to be cross-tensioned is the first pair to be installed.
1.4.7. The cross-tensioning is to be verified to ensure all pretensioning loads are in
accordance with the design and there is no movement or pullout of the anchor piles.
1.4.8. Upon successful completion of the pretensioning, the subsequent hooking up of all
of the chain legs to the chain stoppers in the turntable is to be verified.
1.4.9. During tensioning of the chains for the position mooring system, the relative
position of the mooring system's center to the PLEM is to be verified for
compliance with the design specifications and tolerance.
1.4.10. Upon completion, the chain tension is to be verified by measuring the catenary
angles of the chains for compliance with the design specifications and tolerance.
Any excess length of chain above the chain stoppers is to be removed, unless it is
designed to be retained in the chain well.
1.5. Surveys During Installation of the Import/Export System
During installation of the import/export system, the following items are to be
witnessed by the Surveyor, as applicable.
1.5.1. The riser is to be examined for damage as it is being paid out, and sufficient tension
is to be maintained to ensure the riser is free of deformations or buckles. The
buoyancy tank and arch support are to be verified as being installed in the correct
position relative to the water surface end of the riser.
TCVN 6474-7:2007
163
1.5.2. The installation of the riser clamps on the buoyancy tank and arch support are to be
monitored to ensure that the riser is adequately secured and not damaged due to
excessive tightening of the clamps.
1.5.3. The installation of the end flanges of the riser is to be monitored for compliance
with the approved procedures.
1.5.4. Upon completion of installation, the entire underwater complement of components
is to be generally examined and verified by divers or ROVs for compliance with
the reviewed design specifications and configurations. At a site with limited
visibility, alternative means of verifying the installation are to be submitted for
review and are to be performed to the satisfaction of the attending Surveyor.
1.5.5. Hydrotesting of the import/export system is to be performed in accordance with the
approved procedure. The test pressure and duration of the hydrotest should follow
the appropriate codes, such as ANSI/ ASME B31.8, API RP 2RD and RP 17B.
1.5.6. The make-up of the export floating hose string is to be verified for compliance with
the approved procedures. Suitable gaskets for the hose flanges, positioning of all
navigational aids, correct location of the breakaway couplings and tightening of the
flange bolts are also to be verified.
1.5.7. During the paying out of the hose string, verification is to be made that the hose
string bend radii are not smaller than the manufacturer's recommended limits.
1.5.8. Upon completion of installation, the entire export hose string is to be
hydrostatically tested in accordance with the approved procedure and codes.
1.5.9. Subsea controls, if installed, are to be satisfactorily tested.
1.5.10. All navigational aids are to be functionally tested and proven in working order.
1.6. Surveys during Hook-Up
Survey during hook-up is to be performed following reviewed procedures and is to
include the following, where applicable:
1.6.1. Piping hook-up is to be verified for compliance with the reviewed drawings and
procedures. Welds are to be visually inspected and nondestructive testing (NDT)
performed as required. Upon completion of hook-up, the affected sections are to be
hydrostatically tested to 1.5 times the design working pressure and proven tight.
TCVN 6474-7:2007
164
1.6.2. Electrical hook-up is to be verified for compliance with the approved drawings and
procedures. Proper support for cables and proper sealing of cable entries to
equipment are to be verified. Upon completion of the hook-up, the affected sections
of the equipment and cabling are to be insulation tested and proven in order. All
grounding is also to be verified as being in order.
1.6.3. Instrumentation hook-up is to be verified for compliance with the reviewed
drawings and procedures. Tubing supports are to be verified. Upon completion, all
systems are to be functionally tested and proven as being in order. The
manufacturer's limits on bend radii for any component of the instrumentation
system are to be observed.
1.6.4. Mechanical equipment hook-up is to be verified for compliance with the reviewed
drawings and procedures, including the grounding of the equipment. Upon
completion, all equipment is to be functionally tested and proven as being in order.
1.7. Demonstration of the Disconnectable Mooring System
1.7.1. For a disconnectable mooring system, the system's capability to disconnect free
from its mooring system is to be demonstrated to the satisfaction of the attending
Surveyor, in accordance with approved test procedures.
1.7.2. During the disconnect operation, the time taken to effectively free the Floating
Installation from the mooring system is to be recorded in the Operation Manual.
1.8. Surveys During Start-Up and Commissioning
The start-up and commissioning of hydrocarbon production systems are to be
verified by the attending Surveyor. The scope of the start-up and commissioning to
be verified by the Surveyor is to include the following items:
1.8.1. The start-up and commissioning operations are to be in accordance with the
reviewed procedures.
1.8.2. Verify precautions for safety of personnel during commissioning, including checks
of operational readiness of all life saving equipment, fire and gas detection systems,
fire fighting equipment, Emergency Shutdown systems and unobstructed escape
routes.
TCVN 6474-7:2007
165
1.8.3. Verify establishment of communication procedures prior to the start of
commissioning operations.
1.8.4. Verify that emergency procedures are provided to deal with contingencies, such as
spillage, fire and other hazards.
1.8.5. Verify start-up and testing of all support utility systems, including main and
auxiliary sources, for the process system prior to commissioning.
1.8.6. Verify proper hook-up and testing of the entire process system prior to
commissioning, including the testing of entire system for leaks, the process control
functions and emergency shutdown system.
1.8.7. Verify purging of the entire production system of oxygen to an acceptable level
prior to the introduction of hydrocarbons into the production system.
1.8.8. Verify the introduction of hydrocarbon into the process system and the system's
capability to control the flow of the well effluent in the system in a stabilized
manner without undue control upsets.
1.8.9. Verify the start-up of the flare system, if applicable, including the necessary
precautions taken to eliminate the risk of explosion or fire. The functional
capability of the flare system is to be verified.
1.8.10. Verify that the post-commissioned process system is functioning satisfactorily for a
duration of at least 12 hours. Equipment required to be verified but not used during
the initial start-up and commissioning is to be identified for verification at the next
Annual Survey.
TCVN 6474-7:2007
166
BLANK PAGE
TCVN 6474-8 : 2007
167
NATIONAL STANDARD TCVN 6474-8 : 2007
Second edition
RULES FOR CLASSIFICATION AND TECHNICAL SUPERVISION OF
FLOATING STORAGE UNITS
PART 8: SURVEYS AFTER INSTALLATION AND COMMISSIONING
Reference standards and definitions: see Part 1, TCVN 7474-1: 2007
1 Class maintenance surveys
1.1 Periodical surveys
1.1.1 General
1.1.1.1 All units classed with the VR are to be subjected to the following Periodical
surveys:
(1) Annual surveys ;
(2) Docking Surveys;
(3) Intermediate surveys;
(4) Special surveys;
(5) Boiler surveys and Thermal oil Heater survey;
(6) Propeller shaft and stern tube shaft survey .
(7) Automation system and remote control survey
(8) Inert gas system survey
1.1.1.2 All examinations and tests in accordance with the requirements in 1.3 to 1.17 are to
be carried out to the satisfaction of the Surveyor.
1.1.2 Modification of Requirements
At the Periodical Surveys ,the surveyor may modify the requirements for Periodical Surveys
specified in 1.3 to 1.17 having regard to the size, service engaged, age, construction, results
of last surveys and actual condition of the unit.
TCVN 6474-8 : 2007
168
1.1.3 Definitions
The definitions of terms in the following 1.1.3.1 to 1.1.3.7 are to be in accordance with Part
8:
1.1.3.1 " Ballast tank " : is a tank which is used for water ballast and includes segregated
balast tanks ,side balast tanks, balast double bottom spaces, top-side tanks, hopper
side tanks and peak tanks. A tank which is used for both cargo and ballast will be
treated as a ballast tank when substantial corrosion has been found in that tank.
1.1.3.2 "Close-up survey" : is a survey where the details of structural components are
within the close visual inspection range of the surveyor,i.e. preferably within reach
of hand .
1.1.3.3 "Longitudinal members in the transverse section": include all longitudinal members
such as plating, longitudinals and girders at the deck, side, bottom, inner bottom and
longitudinal bulkheads in the considered transverse section.
1.1.3.4 "Representative tanks" : are those which are expected to reflect the condition of
other tanks similar types and service and service and with similar corrosion
prevention systems. When selecting representative tanks account should be taken of
the service and repair history on board and identifiable critical and or suspect areas.
1.1.3.5 "Suspect areas" : are locations showing substantial corrosion and/or are considered
by the Surveyor to be prone to rapid wastage.
1.1.3.6 "Substantial corrosion" : is such an extent of corrosion that that assessment of
corosion pattern indicates a wastage in excess of 75% of allowable margins, but
within acceptable limits.
1.1.3.7 "Oil " : is petroleum including crude oil , heavy fuel oil , lubricating oil, light oil
kerosene, gas oil .
1.1.4 Survey Reports File
All survey reports and records of all abnormalities found are to be compiled into the Survey
Report File that is to be kept onboard the Floating Installation at all times for reference
during any survey. The records to be kept include, but are not limited to, the following:
1.1.4.1 Approved Survey and Inspection Plan.
1.1.4.2 The updated status records of all class surveys.
TCVN 6474-8 : 2007
169
1.1.4.3 The records of all abnormalities found that are to include all videos and
photographic records.
1.1.4.4 The records of all repairs performed on any abnormalities found and any further
repetitive abnormalities found subsequent to the repairs.
1.1.4.5 Records of all corrosion protection system maintenance, including records of all
cathodic potential readings taken, records of depletion of all sacrificial anodes,
impressed current maintenance records, such as voltage and current demands of the
system, coating breaks and the monitoring records of the steel material wastage in
way of the coating break areas.
1.1.4.6 All classification reports pertaining to the Floating Installation.
1.1.4.7 All records of any findings of abnormalities by the crew personnel onboard,
including all leakages in bulkheads and piping.
1.1.4.8 Reports of thickness measurements of the vessel or floating structure.
1.1.4.9 Reports of all NDT performed.
1.1.5 Corrosion Prevention System - Ballast Tanks
1.1.5.1 Corrosion Prevention System is normally used one of two following types:
(1) a full, hard coating that is supplemented by anode;
(2) a full, hard coating .
1.1.5.2 Coating Condition of hard coatings is defined as follows:
(1) GOOD is a condition with only minor spot rusting.
(2) FAIR is a condition with local breakdown at edges of stiffeners and weld
connections and/or light rusting over 20 percent or more of areas under
consideration, but less than as defined for POOR condition.
(3) POOR is a condition with general breakdown of coating over 20 percent or
hard scale at 10 percent or more of areas under consideration.
1.1.5.3 Salt Water Ballast Spaces
(1) In salt water ballast spaces, other than double bottom tanks, where poor
coating condition is found and Owners or their representatives elect not to
restore the coating, where a soft coating has been applied or a protective
coating has not been applied, the ballast tanks are to be internally examined at
TCVN 6474-8 : 2007
170
each subsequent Annual Survey.
1.2 Intervarls of periodical surveys
1.2.1 General
1.2.1.1 A periodical survey, annual, intermediate or special, is to be considered as
completed when the relevalt periodical surveys both for hull and for machinery
have been completed, unless the special arrangement is made with the VR.
1.2.1.2 Except as amended at the discretion of the VR, the intervals of Periodical Surveys
are specified in 1.2.2 to 1.2.8 following.
1.2.1.3 Class Periodical Surveys should, whenever practicable, be held concurrently with
statutory periodical surveys or inspections.
1.2.1.4 Where both Annual Survey and Intermediate Survey are due at a time, only
Intermediate Survey is to be carried out .
1.2.2 Annual surveys
Annual surveys for hull, machinary of floating storage unit, production system and
mooring system are to be carried out within three months either way of each
anniversary date of the date crediting a Classification Survey or the previous Special
Survey .
1.2.3 Docking surveys
1.2.3.1 Survey intervals:
A Drydocking Survey is to be conducted two times in any 5-year period with an
interval not exceeding three years between surveys .
1.2.3.2 Extension of Docking surveys:
Consideration may be given for extensions of Rule-required Drydock Survey under
special circumstances. An underwater inspection by a diver shall be required for such
extensions.
1.2.4 Underwater Inspection in Lieu of Drydocking Survey (UWILD)
1.2.4.1 An VRs approved underwater inspection by a diver may be considered equivalent
to a Drydocking Survey, up to and including Special Periodical Survey No. 4. The
UWILD after Special Periodical Survey No. 4 may be approved by special
considerations by VR.
TCVN 6474-8 : 2007
171
1.2.4.2 Should the UWILD be contemplated, underwater inspection procedures per
Appendix VIII, Part 9 are to be submitted for review and approval in advance of
the survey.
1.2.4.3 The Underwater survey is to provide the information normally obtained from the
docking survey, so far as is practicable.
1.2.4.4 Proposals for underwater surveys are to be submitted in advance of the survey being
required so that satisfactory arrangements can be acceptable.
1.2.4.5 The under water survey is to be carried out at agreed geographical location under
the surveillance of a VR surveyor, with the unit at a suitable draught in sheltered
waters; the under-water visibility is to be good and the hull bellow the waterline is
to be clean. The surveyor is to be sastisfied that the method of pictorial presentation
is satisfactory. There is to be good two way communication between the surveyor
and the diver.
1.2.4.6 Diving and under water survey operation are to be carried out by firms recognized
by VR.
1.2.4.7 If the in-water survey reveals damage or deterioration that requires early attention,
the surveyor may require that the unit be dry-docked in order that a fuller survey
can be undertaken and necessary work carried out.
1.2.4.8 Where a unit has an IWS notation, the conditions of the high resistant paint is to be
confirmed at each dry-docking in order that the IWS notation can be maintained
1.2.5 Intermediate surveys
Intermediate Surveys are to be carried out on all units instead of the second or third
Annual Survey after completion of Classification Survey and Special Survey.
1.2.6 Special surveys
1.2.6.1 Survey intervals
Special Surveys are to be carried out at 5-yearly interval. The first Special Survey is
to be completed within 5 year from the date of build or date of Special Survey for
classification and thereafter 5 years from the date of completion of the previous
Special Survey.
1.2.6.2 Commencement of special surveys
TCVN 6474-8 : 2007
172
The Special Survey may be commenced at the 4
th
annual Survey after Clasification
Survey or previous Special Survey and be progressed during the succeeding year
with view to completion by the 5th anniversary date. As part of the preparation for
the Special Survey, the thickness measurement should be dealt with, so far as
practical in connection with the 4th Annual Survey.
1.2.6.3 Premature commencement of Special survey
Special surveys which are commenced prior to the date are not to extend over a
period greater than 12 months, except with the priod approval of the VR.
1.2.6.4 Completion of special survey
When a Special survey is not completely carried out one time, the date of completion
of the Special Survey will be the date at which the principal part of the requirements
is complied with.
1.2.6.5 Unusual Cases
Special consideration may be given to Special Periodical Survey requirements in the
case of Floating Installations of unusual design, in lay-up or in unusual
circumstances. Consideration may be given for extensions of Rule-required Special
Periodical Surveys under extreme circumstances.
1.2.6.6 Continuous Surveys
(1) At the request of Owners, and after approval of the proposed arrangements by
the VR a system of Continuous Survey may be undertaken where by the
Special survey requirements are carried out in rotation to complete all the
requirements of the particular Special Survey within five years and interval of
consecutive surveys of each part or item is not to exceed five years.
(2) If any defects are found during the surveys, further parts or items are to be
opened up and examined as considered necessary by the Surveyor, and the
defects are to be repaired to his satisfaction.
(3) Where some units of machinary are opened up and examined by the chief
engineer as normal routine for maintenance at ports where the surveyor is not
available or at sea, the opened-up-inspection of the units, at the request of
Owners, under certain conditions, may be dispensed with at the discretion of
TCVN 6474-8 : 2007
173
the surveyor subject to a confirmatory survey at the next port of call where the
surveyor is available.
(4) Drydocking or UWILD may be performed at any time during the cycle 5 year,
provided that all requirements of 1.4 or 1.5 are met and thickness measurements are
taken when the vessel is surveyed.
1.2.7 Boiler surveys
1.2.7.1 Survey intervals
(1) Water tube boilers used for propulsion including double evaporation boilers
are to be surveyed internally and externally at 2.5 year intervals, except for
ships with single main boiler, where surveys are to be carried out at 2.5 year
intervals until they are 7.5 years old, and subsequently annually.
(2) Fired tube boilers: Boilers are to be surveyed when they are 4 year old and 6
years old, after that they are to be surveyed annually.
(3) All other boilers of essential service, boilers of non-essential service having
working pressure exceeding 0.35 MPa (3.5 bar or 50 psi) and heating surface
excceding 4,5 m
2
, exhaust gas boilers, economizers, thermal oil heaters and
steam generators are to be surveyed internally and externally at 2,5 yearly
intervals
(4) Notwithstanding the requirements in (1) and (2), certain types of boilers, when
the VR deems it necessary, may be required to be surveyed internally and
externally at yearly intervals.
(5) General inspection of boilers including confirmation of their safety devices is
to be carried out at yearly intervas in the course of annual survey of the unit
(see 3.7.1(6) TCVN 6259-1:2003).
(6) Notwithstanding the requirements in (1) and (2), an extension of boiler survey
may be granted for a period not exceeding 6 months from the due date, when
requested by the Owners, subject to the survey for the extension.
1.2.8 Propeller shaft and stern tube shaft surveys
1.2.8.1 Ordinary surveys are to be carried out at intervals specified below:
(1) Propeller shaft kind 1 specified in 1.2.39 Part 1-A TCVN 6259-1:2003, are to
TCVN 6474-8 : 2007
174
be surveyed at least once every four years for units fitted with water-
lubricated stern tube bearings (Which include shaft bracket bearings, the same
being referred to hereinafter in this part) and five years for units fitted with
oil-lubricated stern tube bearings .
(2) Propeller shaft kind 2 specified in 1.2.39 Part 1-A TCVN 6259-1:2003, are to
be surveyed at least once every two and a half years. Where, however, the part
of the construction of the shaft in the stern tube bearing corresponds to the
shaft kind 1 and the construction of the shaft between the stern tube and the
shaft bracket bearing corresponds to the shaft kind 2, the shaft may be
surveyed at the intervals specified in 1.2.8.1(1) , on condition that the part of
the shaft which corresponds to the shaft kind 2 is surveyed at least once every
two and half years .
(2) Notwithstanding the requirements in 1.2.8.1(1) , Ordinary surveys for
propeller shaft kind 1A and stern tube shaft kind 1A, propeller shaft kind 1B
and stern tube shaft kind 1B, and propeller shaft kind 1C may be postponned
for not more than the period given in following Table from the date of the
postponement survey prescribed in 3.11.2-2 TCVN 6259-1:2003 provided that
the survey is carried out on the due date of the Ordinary Survey .
Table 8-1: Postponement period
No Kind of postponement
Survey Kind of shafts
Postponement
Survey kind A
Postponement
Survey kind B
Postponement
Survey kind C
1 Shafts kind 1A - -
2 Shafts kind 1B 1 year 2,5 year -
3 Shafts kind 1C 5 year
1.2.8.2 Notwithstanding the requirements in 1.2.8.1 or 1.2.8.2, The Ordinary Surveys may
be postponned for not more than six months, when requested by the Owners, on the
basis of the approval by the VR. However, this postponement may be granted only
once in an interval between Ordinary Surveys.
1.3 Annual surveys
1.3.1 Requirements for Annual Surveys Hull
TCVN 6474-8 : 2007
175
1.3.1.1 At each annual survey beetween special surveys, general condition for hull,
equipment, fire extinguishing systems, etc. are to be examined as far as practicable,
annual surveys includes following items and requirements specified in 1.3.1.2 to
1.3.1.7:
(1) Shell plating and piping systems above the waterline, externally;
(2) Visual inspection is to be carried out for structures close to water level to
make sure there is no damage due to impact (due to unit or other reasons).
(3) Opening a such as side scuttles, doors, etc. together with their closing
appliances of which watertightness and weathertightness are required ;
(4) Each deck ;
(5) Areas potentially having factigue damage due to stress concentration NDT
examination may be required if deemed necessary.
(6) Examine all navigational lights, alarm and sound devices including helicopter
lights and other safety systems.
(7) Mooring systems ;
(a) General examination of mooring lines ;
(b) General examination of installations for mooring systems ;
(c) General examination of anchors for anchor mooring systems ;
(d) General examination of steel pipes for tension mooring systems ;
(e) General examination of fenders or mooring lines for dolphin mooring
systems ;
(8) Ventilators, air pipes and sounding pipes together with their closing
appliances ;
(9) Protection of the crew, guard rails, lifelines, gangways and deckhouses
accommodating crew;
(10) Construction of fire protection and means of escape including functioning test
as far as practicable;
(11) Fire extingguishing systems including operation and functioning tests as far as
practicable;
(12) Examination of fire control plan;
TCVN 6474-8 : 2007
176
(13) Examination of fire detection system as far as practicable;
(14) Examination of main fire system and verification of performance of fire
pumps including emergency pumps;
(15) Examination of fire main, nozzles, hydrauts to ensure their satisfactory
performance and placed in order ;
(16) Examination of control system of fixed fire extinguishing control system, fire
main, fire alarm signal, ensuring they are well maintained ;
(17) Fire extingguishing bottles are placed in order and well maintenance ;
(18) Remote control and shut-down system to stop fans, engines, stop tranfering
fuel to engine room;
(19) Shutdown systems for ventilation, funnels, skylight, acess and other relevant
parts ;
(20) Examination to ensure fire extinguishing tools are adequate and good order.
(21) Examination of all hazardous areas including watertight doors and boundaries;
(22) Ensure following equipments are in good operating condition :
(a) Ventilation system, fire extinguishing system, fans and relating
devices;
(b) All machanical and electrical safety devices;
(c) Other safety equipment such as alarm system and communication
system.
(23) For the units which are necessary to be provided with the stability booklet,
loading manual and the operating booklet are kept on board the unit for ready
use ;
1.3.1.2 Suspect Areas and Ballast Tanks
Suspect areas of the hull are to be examined , including an overall and Close-up
Survey of those suspect areas which were identified at the previous surveys. Areas of
substantial corrosion identified at previous surveys are to have thickness
measurements taken. Where extensive areas of corrosion are found, thickness
measurements are to be carried out and renewals and/or repairs made when wastage
exceeds allowable margins.
TCVN 6474-8 : 2007
177
Where substantial corrosion is found, additional thickness measurements in
accordance with are to be taken to confirm the extent of substantial corrosion.
For Installations over 15 years of age: All sea water balast tanks closed to cargo(oil)
tanks, in which thermal oil heater is used, are to be internal examined. If a structural
defect was not found, the scope of examination is only included reviewing the
efffectiveness of coating systems.
1.3.1.3 Helicopter Deck
Where areas of the installation are designated for helicopter operations, the helicopter
deck, deck supporting structure, deck surface, deck drainage, tie downs, markings,
lighting, wind indicator, securing arrangements where fitted safety netting or
equivalent, access arrangements including emergency escape, and access for fire
fighting and rescue personnel, are to be examined.
1.3.1.4 Cargo Tanks
Cargo tank openings including gaskets, covers and coamings.
Pressure/vacuum relief valves, flame arrestors and flame screens. Tank vent
protective devices are to be examined externally for proper assembly and
installation, damage, deterioration or traces of carryover at the outlet. Where deemed
suspect, the tank protective device is to be opened for examination.
1.3.1.5 Piping Systems
Cargo, crude oil washing, bunker, ballast, steam, and tank vent piping systems above
the weather deck and in the cargo pump room and pipe tunnels. Where suspect,
piping may be required to be pressure-tested at the working pressure, thickness
measured or both.
Cargo and stripping pumps including foundations, gland seals, operation of remote
control and shut-down devices. Confirmation that cargo discharge pressure gauges
and level indicator systems are operational
1.3.1.6 Electrical Bonding and Equipment
Electrical bonding arrangements on the weather deck and in cargo pump rooms,
including bonding straps, where fitted, of cargo piping systems carrying flammable
liquids and piping systems routed through hazardous areas.
TCVN 6474-8 : 2007
178
Confirmation that electrical equipment in hazardous locations, including the cargo
pump room, has been properly maintained, including the following items:
Intrinsically safe and explosion-proof features of electrical equipment
installed in the hazardous areas, in particular any associated sealing
arrangement.
The physical condition of cables (wiring) and fixtures and test of insulation
resistance of the circuits. In cases where a proper record of testing is
maintained, consideration may be given to accepting recent readings.
The cable supports and the means of cable protection from mechanical
damage, as originally provided.
Gas detection system in the cargo pump room, if fitted.
Temperature-sensing devices fitted on bulkhead shaft glands, pump bearings
and casings, if any
1.3.1.7 Cargo Pump Room
Examination of pump room bulkheads for signs of leakage or fractures and, in
particular, the sealing arrangement of all penetrations of bulkheads.
Confirmation that there are no potential sources of ignition in or near the cargo pump
room and cargo area and that pump room access ladders are in good condition.
Operation of pump room bilge pumping system.
Pump room ventilation system including ducting, dampers and screens.
1.3.1.8 For column stabilized units, general examinitions of the following iterms are to be
carried:
(1) Upper hull and its supporting structure above the waterline the deck, deck
houses, structures attached to the deck, accessible internal spaces;
(2) Exposed parts of columns and bracings together with their connections above
the waterline ;
(3) Hatchways, manholes, and other openings in freeboard deck (bulkhead deck)
and enclosed superstructure Decks ;
(4) Machinery casings and covers, companionways, and deck houses protecting
openings in freeboard or enclosed-superstructure decks;
TCVN 6474-8 : 2007
179
(5) Portlights, together with deadcovers, cargo ports, bow or stern entries, chutes,
and similar openings in hull sides or ends, below the freeboard deck or in way
of enclosed superstructures ;
(6) Ventilators, tank vent pipes together with flame screens ;
(7) Overboard discharges from enclosed spaces on or below the freeboard deck ;
(8) Watertight bulkheads and end bulkheads of enclosed superstructures;
(9) Closing appliances for all of the above, including hatch covers, doors, check
valves;
(10) Protection of the crew, guard rails, lifelines, gangways and deckhouses
accommodating crew ;
(11) The Surveyors are to be satisfied at each Annual Survey that no material
alterations have been made to the Floating Installation, its structural
arrangements, subdivision, superstructure, fittings and closing appliances upon
which the load line assignment is based.
1.3.2 Annual survey for Machinery installations and Electrical Installations
1.3.2.1 At each annual survey between special surveys for machinery installations and
electrical installations, general examination of machinery installations and electrical
installations corresponding to relevant machinery installations and electrical
installations of the units are be carried out in addition to the following surveys:
(1) The propelling machinery and essential auxiliaries are to be generally
examined. The surveyor may, in addition, require such further items ro be
opened up as considered to ascertain that theyare in good working condition.
(2) Machinery and boiler spaces with particular attention to the fire and explosion
hazards, and also emergency escape routes are to be examined.
(3) All main and auxiliary steering gears including their associated equipment and
control systems are to be examined and tested in operation.
(4) All means of communication between the navigation bridge, control station
and the machinery control positions, as well as the bridge and the alternative
steering positions are to be tested.
(5) Bilge pumping systems and bilge wells including operation of pumps, remote
TCVN 6474-8 : 2007
180
reachrods and level alarms where fitted, are to be examined as far as
practicable.
(6) Boilers, thermal oil heaters, pressure and vessels and their mountings
including safety devices, foundations, controls relieving gear, high pressure
and steam escape piping, insulation and gauges are to be externally examined.
Confirmation of the safety devices of the boilers and thermal oil heaters may
be required as considered necessary by the surveyor.
(7) Electrical machinery, emergency sources of the electrical power, switchgear
and other electrical equipments are to be examined and also to be tested in
operation as feasible. If automatic control system is fitted, it is to be tested on
both automatic and manual modes.
(8) Confirmation as far as practicable of the operation of all emergency sources of
power is to be made and, if they are automatic, also in the automatic mode.
(9) Parts which are opened up for maintenance at Owner's option are to be
examinated as necessary.
(10) Where automatic and/or remote controls are fitted for essential machinery,
they are to be tested to demonstrate that they are in good working condition.
(11) Dynamic positioning systems are to be generally examined and performance
tests of them are to be carried out as far as practicable.
1.3.2.2 General conditions of electrical installations in the hazardous areas are to be
examined. For the units of ten years of age and over, insulation resistance of these
installations is to be measured. The measurement, however, may be dispensed with
in case the proper measurement records are kept on board and found satisfactory by
the surveyor.
1.3.2.3 Following Fire-extinguishing apparatus/ systems are to be examined and/or tested:
(1) Fire Main System
Fire main system, including isolating valves and hydrants. Fire mains are to
undergo satisfactory pressure testing at the working pressure.
(2) Fire Pumps
Fire pumps, including verification that each fire pump including the
TCVN 6474-8 : 2007
181
emergency fire pump can deliver two jets of water simultaneously from
different hydrants.
(3) Fire Fighting Equipment
Verification that fire hoses, nozzles, applicators and spanners are in good
working condition and situated at their respective locations.
(4) Semi-Portable and Portable Fire Extinguishers
Verification that all semi-portable and portable fire extinguishers are in their
stowed positions, checking for evidence of proper maintenance and servicing,
conducting random check for evidence of discharged containers.
(5) Fire Control Plans
Confirmation that Fire Control Plans are properly posted .
(6) International Shore Connection
Confirmation that an international shore connection is provided..
(7) Fixed Fire Fighting System
Examination of fixed fire-fighting system controls, piping, instructions and
marking, checking for evidence of proper maintenance and servicing,
including date of last systems tests; foam concentrates are to be tested at
intervals recommended by the manufacturer and renewed if found
unsatisfactory for further use.
An external examination of piping and cutout valves of cargo tank and cargo
pump room fixed fire-fighting systems..
(8) Remote Controls
Verification, as far as practicable, that the remote controls for stopping fans
and machinery and closing valves for fuel oil in machinary rooms are in
working order.
(9) Fireman's Outfits
Verification that the firemans outfits are complete and in satisfactory
condition .
(10) Closing Arrangements
Examination of the closing arrangements of openings in funnels, skylights,
TCVN 6474-8 : 2007
182
ventilators, doorways and tunnels. Ventilator ducts are to be opened to verify
satisfactory condition and operation of dampers.
(11) Deck Foam System
Confirmation that the deck foam system is in operating condition.
(12) Unloading area
An examination of unloading piping, including welded joints, identification,
means of segregation from the cargo main line, closing arrangement of the
unloading connection, draining and leak detection arrangements and spill
containment. Means of communications between the cargo control room and
the loading/unloading connection to be tested .
1.3.2.4 For the production units, the following are to be carried out:
(1) A general examination of :
(a) Cargo tank openings and pressure/vacuum valves;
(b) Crude oil piping systems;
(c) Cargo pump rooms ;
(d) Escape routes ;
(e) Fire extinction systems in crude oil tank and pump room area.
(2) The following components and systems are to be surveyed and tested for
correct functioning :
(a) Gas detection systems, flammable and toxic gases;
(b) Fire detection system;
(c) System for crude oil tank level measurements;
(d) General alarm system and communication between control stations
(3) In hazardous areas the following equipment and systems are to be surveyed
and tested :
(a) Ventilation system including overpressure alarms ;
(b) Alarms/shut-down for pressurized equipment and rooms ;
(c) Electrical equipment and cables ;
(d) Self-closing gastight doors, air locks, openings and accesses;
TCVN 6474-8 : 2007
183
(e) Protection devices for combustion equipment and engines;
(4) The emergency shut-down system is to be surveyed and function tested for
following equipments and components. Special attention is to be given to both
manual and automatic activation, power supply and alarms:
(a) ventilation;
(b) wellhead valves/oil production facilities ;
(c) all non-essential electrical equipment and essential electrical equipment
(5) Where cross connections between piping system for oil production and safe
piping system exits, the means for avoiding possible contamination of the safe
system with the hazardous medium is to be surveyed
1.3.2.5 For the production plants , the following are to be carried out :
(1) For equipment installed subsea at time of an annual survey a review of the
maintenance manual/test log is an acceptable survey method, provided
satisfactory records and acceptable maintenance procedure .
(2) An overall survey is to be carried out with particular emphasis on the
structural interity of:
(a) Flare ;
(b) derrick;
(c) skids .
(3) Wire ropes (including end attachments) and sheaves of the tensioners and
associated systems are to be surveyed. If deemed necessary by the surveyor,
checking by MPI shall be carried out.
(4) Pressure vessels and heat exchangers are to be externally surveyed. The
general condition including mountings, piping and possible insulation is to be
ascertained. The surveyor may require opening/internal survey or thickness
measurements and /or crack detection test if found necessary. Safety valves,
instrumentation and systems on tanks/separators are to be surveyed and tested
in operating condition as found necessary by the surveyor .
(5) Piping system including flexible pipes is to be surveyed and pressure tested to
working pressure. Thickness measurements are to be carried out as deemed
TCVN 6474-8 : 2007
184
necessary by the surveyor
(6) High pressure/capacity pumps and compressors are to be externally surveyed
and function tested .
(7) Risers shall be visually surveyed and inspected for corrosion, cracks and wear
as far as accessible. Pressure tests to working pressure are to be carried out .
(8) The blowout preventers shall be surveyed and pressure tested to working
pressure. NDT is to be carried out to the extent deemed necessary by the
surveyor .
(9) Riser handling devices and lifting devices for production and associated
operations to be generally surveyed and functional testing of appliance and
safety devices carried out as found necessary by the sutveyor. It is to be
verified that the marking and component certificates are available and
acceptable .
(10) The process and utility safety systems are to be surveyed during operation and
tested for correct funstioning as found necessary by the surveyor with
particular emphasis on:
(a) Shut-down valves ;
(b) Shut-down instrumentation ;
(c) Shut-down sequence and logic ;
(d) Inter connection with emergency shut-down system;
(e) Regulation/control system
(f) Alarm/system;
(11) Drainage systems for produced liquids, for hazardous and non-hazardous area
to be surveyed .
(12) Water protection systems in process area are to be surveyed .
1.3.2.6 Other examinations and tests deemed necessary by the surveyor are to be carried
out .
1.4 Docking surveys
1.4.1 General
1.4.1.1 The unit is to be placed on blocks of sufficient height in a drydock or on a ship way.
TCVN 6474-8 : 2007
185
1.4.1.2 However, where the in-water survey is requested by the Owner and approved by the
VR as substitution for a survey in a drydock or on a ship way, the in-water survey
may be accepted. Where a docking survey is altered to the in-water survey,
examinations deemed appropriate by the VR are to be carried out .
1.4.1.3 In addition to the requirements in 1.4.2, examinations as comprehensive as special
surveys may be required as to the iterms which are considered necessary by the
surveyor on the occasion of docking surveys .
1.4.2 Requirements for Docking survey
1.4.2.1 For all units, surveys are to be carried out in accordance with 3.4.1, Chapter 3, Part
1-B TCVN6259- 1:2003.
1.4.2.2 In addition to the requirements in -1, the following are to be to be performed during
all of the Drydock Surveys:
(1) Cathodic potential readings are to be taken from representative positions on
the entire underwater body and evaluated to confirm that the cathodic
protection system is operating within design limits.
(2) Sacrificial anodes are to be examined for depletion and placed in satisfactory .
(3) Impressed current system anodes and cathodes are to be checked for damage,
fouling by marine growth and carbonate deposits. The current and voltage
demands of the system are to also be checked to ensure the system is
functioning .
(4) Additional examinations are to be performed on the wind and water areas of
the structures where coating breaks are evident. Thickness measurements in
these areas may be required if found necessary by the attending Surveyor.
1.4.2.3 Particular attention is to be given to corrosion control systems in representative
ballast tanks, free-flooding areas and other locations subjected to sea water from
both sides .
1.4.2.4 If the unit is provided with the dynamic positioning system, thrusters are to be
examined.
1.4.2.5 In conjunction with dry docking surveys, after special survey No. 1 and between
subsequent special surveys, the following ballast spaces are to be internally
examinrd, thickness gauged and placed in satisfactory condition. Alternatively,
TCVN 6474-8 : 2007
186
ballast tank corrosion control arrangements are to be verified effective .
(1) For ship type and barge type units : One peak tank and at least two other
representative ballast tanks between the peak bulkheads used primary for
water ballast .
(2) For column stabilized units: Representative ballast tanks in footings, lower
hulls or free-flooding compartments as accessible, and at least two ballast
tanks in columns or upper hull, if accessible.
1.5 Underwater Inspection in Lieu of Drydocking Survey
1.5.1 General
1.5.1.1 An approved underwater inspection by a diver may be considered equivalent to a
Drydocking Survey, up to and including Special Periodical Survey No. 4.
1.5.1.2 For each drydocking or equivalent underwater examination after Special Periodical
Survey No. 4, requests to conduct an UWILD, in accordance with previously
approved plans, . For requirements of UWILD (in accordance with previously
approved procedures) after special periodical survey No 4, proposal by units owner
for this UWILD is to be submitted for consideration well in advance of the
proposed survey. The UWILD after special periodical survey No 4 may be accepted
by special consideration by VR.
1.5.1.3 Should the UWILD be contemplated, underwater inspection procedures per
Appendix VIII, Part 9 are to be submitted for review and approval in advance of
the survey. This approved procedure is to be made available onboard. In addition,
the inspection procedures are to also consist of the following:
(1) Scope of inspection that is not to be less than as noted in Appendix VII, Part
9.
(2) Procedure for divers to identify the exact location at which they are
conducting their inspection.
(3) Procedure for cleaning the marine growth for inspection purposes that is to
include the extent and location of the underwater cleaning.
(4) Procedure and extent for measuring the cathodic potential readings in way of
the structures.
TCVN 6474-8 : 2007
187
(5) Procedure and extent for taking thickness gaugings of the structures and NDT
of critical joints.
(6) Qualifications of all divers conducting the inspection, NDT and thickness
gaugings.
(7) The type of underwater video and photography, including means of
communication, monitoring and recording.
(8) For Underwater Inspections in lieu of Drydocking Surveys (UWILD)
associated with Special Periodical Survey, means are to be provided to permit
the opening up of all sea valves and overboard discharges for internal
examination. In addition, all Special Periodical Survey items related to the
underwater portion of the hull or structure, including the gauging requirements
are to be dealt with during the underwater survey.
1.5.1.4 However, during conducting UWILD if the inspections results was found
unsatisfactory by Surveyor, Surveyor may reject these inspections results and may
require that the unit be dry-docked.
1.5.2 Parts to be Examined
1.5.2.1 Hull and hull equipments of Floating storage unit
For ship-type and barge-type units:
The following items are to be examined, as applicable:
(1) The keel, stem, stern frame, rudder, propeller, and outside of side and bottom plating
are to be cleaned as necessary and examined, together with bilge keels, thrusters,
exposed parts of the stern bearing and seal assembly, sea chest, rudder pintles and
gudgeons, together with their respective securing arrangements.
(2) All sea connections and overboard discharge valves and cocks, including their
attachments to the hull or sea chests, are to be externally examined. All nonmetallic
expansion pieces in the sea-water cooling and circulating systems are to be examined
both externally and internally. The stern bearing clearance or weardown and rudder
bearing clearances are to be ascertained and reported on.
For column-stabilized units, the following are to be examined:
(1) External surfaces of the upper hull or platform, footings, pontoons or lower hulls,
TCVN 6474-8 : 2007
188
underwater areas of columns, bracing and their connections, as applicable, are to be
selectively cleaned and examined. These areas include joints of critical structural
members, areas susceptible to damage from supply vessels, anchor chains, dropped
equipment, corrosion and erosion from loss of coating, or sand scouring and areas of
progressed and accumulated wear-and-tear.
(2) Nondestructive testing may be required of areas found to be suspect. Joints of
different configurations of major structural members are to be selected, cleaned and
magnetic particle inspected. The selection of these joints are to be such that all joints
underwater are to be inspected every five years.
(3) Sea chests and strainers are to be cleaned and examined.
(4) External portions of propulsion units are to be examined, if applicable.
(5) The type, location and extent of corrosion control (coatings, cathodic protection
systems, etc.), as well as effectiveness, and repairs or renewals to same should be
reported in each survey. Particular attention is to be given to corrosion control
systems in ballast tanks, free-flooding areas and other locations subjected to sea
water from both sides.
(6) All tanks and voids that are to be internally examined are to be thoroughly ventilated
and gas freed prior to being entered and are to be carefully monitored for pocketing
or emissions of hazardous gases during examination.
(7) In conjunction with Drydocking Surveys (or equivalent), the following ballast spaces
are to be internally examined, and the effectiveness of coatings or corrosion control
arrangements are to be verified either visually by indicator strips or by thickness
gauging (as considered necessary), placed in satisfactory condition, as found
necessary, and reported upon:
(a) Representative ballast tanks in footings, lower hulls or free-flooding
compartments, as accessible.
(b) At least two ballast tanks in columns or upper hull, if applicable.
1.5.2.2 Mooring System
For mooring systems, the following are to be cleaned and examined, where
applicable:
TCVN 6474-8 : 2007
189
(1) The mooring anchor chain or cable tensions are to be measured and the end
connections of these components are to be examined. All mooring chains are
to be generally examined for their entire lengths. Anchors, cables and their
respective handling means are to be examined.
(2) The buoyancy tanks are to be cleaned and examined, if applicable.
(3) Chain and stopper assemblies are to be cleaned, examined and NDT
performed, as considered necessary by the attending Surveyor.
(4) Areas of high stress or low fatigue life are to be preselected, cleaned and NDT
performed, if considered necessary.
(5) Scour in way of anchors or anchor piles is to be examined.
(6) Cathodic potential readings are to be taken from representative positions on
the entire underwater structure of the mooring system to confirm that the
cathodic protection system is operating within design limits.
(7) Highly stressed, high wear and tear areas of the mooring chain are to be
closely examined and nondestructively tested, if found necessary by the
attending Surveyor. These include areas in way of the stoppers and sea bed
touchdown areas.
1.5.2.3 Import System
For import systems, the following are to be cleaned and examined, where applicable:
(1) The entire riser system.
(2) The arch support buoyancy tanks, their structures and the clamping devices.
(3) The flexible riser, including all end flanges and bolting arrangements and
spreader bars, if applicable.
1.5.2.4 Export System
For export systems, the following are to be cleaned and examined, where applicable:
(1) The entire export flexible system is to be examined for damage due to chafing
and fatigue fractures.
(2) All navigation aids are to be examined and functionally tested
1.6 Intermediate Surveys
1.6.1 General
TCVN 6474-8 : 2007
190
1.6.1.1 At each intermediate survey, all the requirements for an annual survey are to be
complied with .
1.6.1.2 In addition to the above requirement, surveys required in following parts are to be
carried out:
1.6.2 Intermediate survey for hull
1.6.2.1 For all units, the following requirements are to be complied with :
(1) Performance tests of openings such as side scuttles, doors, etc. required
watertightness and weathertightness together with their closing appliances;
However, performance tests may be dispensed with the discretion of the
Surveyor.
(2) Performance tests of positioning systems for a long period of time together
with their installations ; and
(3) Examination of anchor racks and fair leaders for anchor cables above the
waterline together with hull connection of these .
(4) Examination of electrical equipment in hardous areas in particular :
(a) Grounding;
(b) Explosive casing of equipment;
(c) Pressure regulating device casing and relevant components ;
(d) Conditions of safety devices ;
(e) Cable condition ;
(f) Electrical shutdown of areas fitted with dampers;
(g) Performance of pressure regulating device and function of alarm signal
1.6.2.2 For column stabilized units, examinations of the following items are to be carried
out as far as practicable .
(1) Representative ballast tanks in footings, lower hull or free-flooding
compartments as accessible, and at least two ballast tanks in columns, if
accessible ;
(2) External columns, bracings, lower hulls and footings ;
(3) Connection parts between upper hull and columns, and columns and lower
TCVN 6474-8 : 2007
191
hulls or footings, and bracings. If deemed necessary by the Surveyor, the
Surveyor may request a nondestructive test of these parts
1.6.2.3 For ship type units and barge type units, general examinations of construction of the
surrounding to openings such as a moompool above the waterline are to be carried
out in addition to 1.6.2.1.
1.7 Special surveys
1.7.1 General
1.7.1.1 The first special survey of the unit after the classification survey during
construction is designted as ' 'Special survey No.1' and subsequent special surveys
as designated as 'Special survey No.2' 'Special survey No.3 ' and ...
1.7.1.2 The kind of special survey of the unit not built under survey is to be determined in
the similar sequence as specified in 1.7.1.1 basing upon what kind of special survey
was corresponding to her classification survey
1.7.2 Special surveys for hull
1.7.2.1 Special Periodical Survey of Hull is to include compliance with the foregoing
Annual Survey and Drydocking.
1.7.2.2 For all units, Special survey No. 1 for hull, equipment, fire extinguishing systems,
etc., examinations and tests specified in the following are to be carried out :
(1) Internal and external of hull, especially machinery room, cofferdams, and
water tanks such as water ballast tanks, and oil tanks such as fuel oil tanks
deemed necessary by the VR are to be examined corresponding to the kinds of
the special survey .
(2) An overall survey is to be carried out with particular emphasis on the
structural intergrity of the deck with supporting structure .
(3) Tanks are to be tested under the pressure corresponding to the maximum head
that can be experienced in service or designed. A pressure tests of the tanks
may be omitted, provided that the Surveyor is satisfied with the condition of
the tanks from the results of an external and internal examinations of the
tanks.
(4) The thickness of structural members of the following parts listed in (a) to (c)
TCVN 6474-8 : 2007
192
are to be gauged. For accurate gauging, appropriate ultrasonic equipment or
other approved means are to be used. The results of the gaugings are to be
reported to the VR .
(a) Structural members in any locations considered by the surveyor to be
prone to rapid wastage showing excessive corosion.
(b) Representative parts of splash zones or related structure near the
draught of operational condition .
(c) Suficient parts of structural members for general asessment and
recording of corosion pattern .
(5) Anchors, chain cables and ropes for temporary mooring are to be ranged,
examined and measured .
(6) For mooring systems, the following examinations are to be carried out :
(a) Thorough examination of mooring lines
(b) Thorough examination of installations for mooring systems
(c) Thorough examination of anchors for anchor mooring systems
(d) Thorough examination of steel pipes for tension mooring system and
thickness gauging of the representative part of steel pipes
(e) General examination of fenders or mooring lines for dolphin mooring
system
(7) Non-destructive tests may be required at important parts among those stated in
the foregoing (1), (2) and (3) where deemed necessary by the VR
1.7.2.3 For column stabilized units, the following examinations are to be carried out.
However, where the units is examined in floating condition, the examinations are to
be appropriate to the VR.
(1) Connections of columns and bracings to upper hull or platform and lower hull
or pontoons are to be sufficiently cleaned and examined .
(2) Joints of supporting structure including bracings together with gussets and
brackets and internal continuation or back-up structure for those are to be
examined.
TCVN 6474-8 : 2007
193
(3) Internal and external parts of columns, lower hulls or footinga and bracings
are to be examined
(4) Non-destructive examination may be required at suspect areas.
(5) A deadweight survey is to be carried out. Where the deadweight survey
indicates a change from the calculated light ship displacement in excess of 1%
of the operating displacement, an inclining test is to be conducted.
(6) All tanks, compartments and free-flooding spaces throughout the vessel are to
be examined externally and internally. Internal examinations of lower hull are
to be specially considered. Watertight integrity of tanks, bulkheads, hull,
bulkhead deck and other compartments are to be verified by visual inspection.
Suspect areas may be required to be tested for tightness, nondestructively
tested or thickness gauged. Tanks and other normally closed compartments are
to be ventilated, gas-freed and cleaned, as necessary, to expose damage and
allow for a meaningful examination for excessive wastage. Internal
examination and testing of void spaces, compartments filled with foam or
corrosion inhibitors and tanks used only for lube oil, light fuel oil, diesel oil or
other non-corrosive products may be waived, provided that, upon general
examination, the Surveyor considers their condition to be satisfactory.
External thickness gauging may be required to confirm corrosion control.
(7) Attachments of anchor racks and anchor cable fairleads are to be examined.
Foundations in way of selective anchor line fairlead support structures are to
be cleaned and nondestructive examinations performed. Internal support
structures in way of these foundations are to be closely examined.
(8) Applicable structures, such as pipe racks, process support structures, deck
houses, superstructures, helicopter landing areas and their respective
attachments to the deck or hull..
(9) Foundations and supporting headers, brackets and stiffeners for process
related apparatus, where attached to hull, deck, superstructure or deck house.
(10) At Special Periodical Survey No. 2 and subsequent Special Periodical
Surveys, representative gaugings are to be required in accordance with Table
8-2. Special attention should be paid to the splash zones on hulls, columns and
TCVN 6474-8 : 2007
194
ballast tanks, free-flooded spaces and the bottom hulls. The thickness gauging
requirements indicated in the table may be reduced or increased, as deemed
necessary or appropriate by the Surveyor .
Table 8-2 Thickness Gauging Requirements for Column-Stabilized Units
Special Periodical
Survey No 1
Special Periodical
Survey No 2
Special Periodical
Survey No 3
Subsequent Special
Periodical Survey
TCVN 6474-8 : 2007
195
1) Suspect areas
throughout the
unit.
2) Columns and
bracings where
wastage is evident
in Splash Zone.
1) Suspect areas
throughout the unit.
2) Representative
gaugings of columns
and bracings in
Splash Zone
together with
internals in way as
deemed necessary.
3) Special and
primary application
structure where
wastage is evident.
1) Suspect areas
throughout the unit.
2)Representative
gaugings,
throughout, of
special and primary
application
structures.
3) 1 girth belt of each
of 2 columns and 2
bracings in Splash
Zone together with
internals in way as
deemed necessary.
4) Chain locker
internals as deemed
necessary.
5) Lower hulls in
way of mooring lines
where wastage is
evident.
6) 1 girth belt of each
lower hull between
one set of columns.
1) Suspect areas
throughout the unit.
2)Comprehensive
gaugings, throughout,
of special and primary
application structures.
3) 1 girth belt of each
of onehalf of the
columns and bracings
in Splash Zone and
internals in way as
deemed necessary (i.e.,
gauge half of the units
columns and bracings
in
Splash Zone).
4) Chain locker
internals as deemed
necessary.
5) Lower hulls in way
of mooring lines where
wastage is evident.
6) 1 girth belt of each
lower hull between one
set of columns.
Note: Definitions for primary and special structures see TCVN 5318:2001
1.7.2.4 For ship and barge type units, All cargo tanks, ballast tanks, combined cargo/ballast
tanks, including double bottom tanks, pump rooms, pipe tunnels, cofferdams and
void spaces bounding cargo tanks, decks and outerhull are to be examined. This
examination is to be supplemented by thickness measurementand testing as
required, to ensure that the structural integrity remains effective.
TCVN 6474-8 : 2007
196
(1) Cargo piping on deck, including Crude Oil Washing (COW) piping, and all
piping systems within the above tanks and spaces are to be examined and
operationally tested under working pressure to attending Surveyors
satisfaction to ensure that tightness and condition remain satisfactory. Special
attention is to be given to ballast piping in cargo tanks and any cargo piping in
ballast tanks and void spaces. Surveyors are to be advised on all occasions
when this piping, including valves and fittings, is open during repair periods
and can be examined internally .
(2) Structural appendages and ducts for posioning system are to be examined.
(3) Hull structure around the openings such as the moon pool is to be examined.
(4) Non-destructive tests may be required at important parts or stress concentrated
parts where deemed necessary by the VR.
1.7.2.5 The requirements for Close-up Survey and thickness gauging, per TCVN 6259-1A:
2003 will be applied to ship- and barge-type units in the following cases:
(1) The ballast tanks are uncoated.
(2) Tank coatings are in Poor condition as definition
(3) Soft coatings are found to be no longer effective
(4) Substantial corrosion is present
1.7.2.6 For ship- and barge- type units, the extent of Tank Testing are as follows:
Tanks are to be hydrostatic tested with a head of liquid to the top of hatches for cargo
tanks and to the top of air pipes for ballast tanks.
Requirements for tank testing in accordance with units age are specified as follows:
(1) Units age 5
All balast tank boundaries.
Cargo tanks boundaries facing ballast tanks, void spaces, pipe tunnels, fuel oil
tanks, pump room.
(2) 5 < Units age 10
All balast tank boundaries.
Cargo tanks boundaries facing ballast tanks, void spaces, pipe tunnels, fuel oil
TCVN 6474-8 : 2007
197
tanks, pump room.
All cargo tanks bulkheads which form the boundaries of segregated cargoes.
(3) Units age > 10
All balast tank boundaries.
Cargo tanks boundaries facing ballast tanks, void spaces, pipe tunnels, fuel oil
tanks, pump room.
All remaining cargo tank bulkheads.
1.7.2.7 At special periodical surveys after special periodical survey No 1, thickness
measurement for ballast tanks is to be carried out in accordance with requerements
1.7.2.1 to 1.7.2.4 .
1.7.3 Special surveys for Machinery Installations and Electrical Installations
1.7.3.1 At each Special Periodical Survey, the following items are to be examined and
placed in satisfactory condition:
(1) All shafts except propeller and stern tube shafts thrust blocks and lineshaft
bearings are to be examined. The lower halves of bearings need not be
exposed if alignment and wear are found satisfactory
(2) Reduction gears are to be opened up as considered necessary by the surveyor
and gears, pinions, gear teeth, shafts and bearings are to be examined.
(3) Air compressors with their intercoolers, filters and/or oil separators and safety
devices, and all pums and components used for essential services are to be
opened up as considered necessary by the surveyor and examined.
Air compressors, air reservoirs and associated piping are to be examined. If air
reservoirs cannot be examined internally, they are to be hydrostatically tested.
All relief valves and safety devices are to be proven operable .
(4) All main and auxiliary steering gears including their associated equipment and
control systems are to be examined. They are to be opened up for further
examination if considered necessary by the surveyor
(5) Windlass and mooring winches are to be examined including operational tests,
check of the brake and testing of safety devices. They are to be opened up for
further examination if considered necessary by the surveyor .
TCVN 6474-8 : 2007
198
(6) Evaporators are to be opened up and examined. Their safety relief valves are
to be checked under working condition.
(7) The foundation bolts and chocks of mainand auxiliary engines, gear cases,
thrust blocks and line shaft bearings are to be examined.
(8) All air reservoirs and other pressure vessels for essential services together
with their mountings and safety devices are to be cleaned internally and
examined internally and externally. If an internal examination of them is not
practicable, they are to be tested hydraulically to 1,5 times the working
pressure .
(9) Pumping and piping arrangements
(a) The bilge system : Valves, cocks and strainers of the bilge system
including the emergency bilge suction valve are to be opened up as
considered necessary by the surveyor and examinrd, and the systems
including pumps, remote reachrods and level alarms, where firtted, are
to be tested in operation .
(b) The oil fuel, feed and lubricating oil systems and ballast connections
and blanking arrangement to deep tanks, together with all pressure
filters, heaters and coolers for essential servises are to be opened up
and examined or tested as considered necessar by the surveyor. All
safety devices for the foregoing items are to be examined .
(c) Flammable oil tanks : Fuel oil tanks which do not form part of the hull
structure are to be examined internally and externally. At the special
survey No. 1, the internal examination of the tanks may be dispensed
with, provided they are found satisfactory in the external examination.
All mountings, fittings and remote shut-off device are to be examined
as far as practicable .
(10) Spare parts are to be checked .
(11) Automatic and remote controls: Where automatic and/or remote controls are
fitted up for essential machinery, they are to be tested to demonstrate that they
in good working order .
(12) Steam engines
TCVN 6474-8 : 2007
199
(a) Steam turbine (main and auxiliary for essential service ) : Turbine
blading, rotors together with bearings, casings, condensers and
couplings between turbine and reduction gears are to be examined. At
the special survey No.1 for the unit having more than one main
propulsion ahead turbines of well experienced type and emergency
crossover arrangements, the turbine casings need not be opened up
provided vibration indicators and rotorposition indicators are fitted and
the operating records are considered satisfactory by the surveyor. The
bulkhead stop valves and manoeuvring valves are to be opened up and
examined .
(b) Main steam piping
1) Selected number of main steam pipes are to be removed and
examined internally. In case where the pipes are jointed together
by welding and impracticable to be removed, alternative means
such as inspection through inspection holes by optical means or
checking pipe wall thickness by ultrasonic test may be accepted,
and in this case welded seams are to be examined and crack
detected to an extent as considered necessary by the surveyor.
2) At the Special survey No. 3, and subsequent special surveys,
pipes submitted to internal examination are to be hydraulically
tested to 1,5 times the working pressure
3) Where temperature of the steam at the superheater outlet does
not exceed 450oC steam pipes need not be examined at the
special survey No. 1.
(13) Internal combustion engines ( main and auxiliary for essential service) :
(a) The following parts are to be opened up and examined : Cylinders,
covers, valves and valve gears, fuel pumps and fittings, scavenge
pumps, scavenge blowers and their driving devices, turbo chargers,
pistons, piston rods, crossheads, guides, connecting rods, crank shafts
and all bearings, crank case fastening and explosion relief devices, cam
shafts and their driving gears, attached pumps and coolers, vibration
TCVN 6474-8 : 2007
200
dampers, balancers, and couplings to the shafting .
(b) Crank shafts alignment is also to be checked .
(14) Electrical installations :
Electrical installations on unit the following surveys are to be carried out :
(a) The fittings on switchboards, section boards and distribution boards are
to be examined, and overcurrent protective devices are to be checked .
(b) Cables are to be examined as far as practicable without undue
disturbance of fixtures.
(c) All generators are to be run under loaded condition, either separately or
in parallel, and performances of speed governors, generator circuit
breakers and their associated relays are to be tested as far as
practicable.
(d) The insulation resistance of generators, switchboards, motors, heaters,
lighting fittings and cables are to be tested, and adjusted if it is found
not to comply with the requirements 2.18.1 TCVN 6259-4:2003 .
(e) The whole systems of the emergency source of electrical power and its
associated equipment are to be tested to demonstrate that the whole
system is in good working order, and if they are automatic, in the
automatic mode .
(f) Navigation light indicators and all the means of communication
between the navigation bridge, the control station and the machinery
control positions as well as the bridge and alternative steering position,
if fitted, are to be tested, and where considered necessary by the
surveyor, emergency stopping means of motors for fuel oil pumps,
ventilating fans and similar loads, interlocking devices for safety
operation of electrical equipment, and motors and their control gears
for essential servces are to be tested.
(15) Machinery and boiler spaces with particular attention to the fire and explosion
hazards, and emergency escape routes are to be examined .
(16) Refrigerating installations
TCVN 6474-8 : 2007
201
Where the refrigerating installations not classed with the VR are installed on
board, the following examinations are to be carried out :
(a) The condition on the safety devices attached thereto is to be examined
to ensure that they are in good order .
(b) The machinery is to be tested under working condition .
(c) Parts of condensers, evaporators, and receivers exposed to primary
refrigerant are to be tested at a pressure of 90% of the design pressure.
However, the pressure test may be replaced by means as deemed
appropriate by the VR and where the relief valves fitted on them are
adjusted to opetate at lower than the design pressure, the testing
pressure may be reduced to 90% of the setting pressure of the relief
valves. The above pressure test may be dispensed with, at the discretion
of the surveyor, except for those used for NH3 (R717) as refrigerant.
(17) For the unit having hazardous areas defined in 1.3.15 all electrical installations
and cable therein are to be examined, and insulation resistance of the electrical
circuits therein is to be measured .
(18) Dynamic positioning system
(a) Thorough examination of thruster systems is to be carried out .
(b) Non-destructive test for mayjor parts of thruster systems is to be carried
out, if deemed necessary.
(c) Examinations and performance test are to be carried out in accordance
the test procedure, if any
1.7.3.2 For oil production units the following surveys are to be carried out :
(1) Surveys for items accociated with oil production units specified in 1.3 ;
(2) For units having boilers burning crude oil or slop, survey and testing of
control equipment including monitoring systems and shut-down functions
related to the following systems are to be carried out :
(a) Ventilation and gas-tightness, fuel supply line and boiler with boiler
front lagging;
TCVN 6474-8 : 2007
202
(b) Fuel pumps and heating arrangement;
(c) Drain pipe ducts and automatic closing drain traps;
(d) Inert and purging systems;
(e) Manual and automatic quick closing valves and shut-down systems;
(f) Boiler hood ventilation system;
(g) Boiler compartment ventilation ;
(h) Boiler front extinguishing system;
(i) Pilot burner arrangement ;
(j) Gastight bulkhead penetrations;
(k) Gas detection system;
(l) Fuel heater .
(3) For units having turbines, engines or boilers burning gas, survey and testing of
the safety and control equipment and alarm and shut-down functions related to
the following systems are to be carried out:
(a) Gas heating arrangement;
(b) Ventilation arrangement;
(c) Protection and flame screens;
(d) Gas freeing and purging systems;
(e) Manual and automatic shut-down system;
(f) Gas detection system;
(g) Pilot flame burner or fuel floor arrangement;
(h) Governor stability swiching from gas fuel to oil, or vice versa.
(4) Function test of instrumentaion and safety devices for component and systems
given in 1.3.2 - 1.3.2.43 (2) is to be carried out.
(5) The fire extinguishing system are to be surveyed and tested for correct
functioning in/at :
(a) Crude oil tank area;
(b) Crude oil pump room;
(c) Engine and boiler room
TCVN 6474-8 : 2007
203
(d) Helicopter deck.
(6) It is to be verified that the required signboards are in order;
(7) The drainage system of the hazardous areas is to be surveyed;
(8) The insulation resistance of the electrical installation in the hazardous area is
to be checked ;
(9) The fireman's outfit is to be surveyed.
1.7.3.3 For production plants the following are to be carried out :
(1) The requirements stipulated in 1.3.2.4 apply with the additions given in the
following ;
(2) The derrick installation is to be examined with emphasis on the structural
condition of bracings particularly with respect to deformation and slack/loose
bolts (if of bolted design). Thickness measurements and/or NDT ( non-
destructive testing) examination of main structural components and checking
of bolts after dismantling may be required as far as deemed necessary by the
surveyor .
(3) Main loading parts of overhead production equipment are to be checked by
MPI. Thickness measurements of structural parts as far as deemed necessary
required by surveyor. Thickness measurements of structural components
and/or NDT to be carried out as far as deemed necssary .
(4) Internal surveys, or if this is not practical, thickness measurements of pressure
vessels and heat exchangers are to be carried out. Examination of related
equipment, such as valves, pipes etc. is to be carried out. Examination of
correct setting of safety valves including remote operation of same is to be
carried out. Pressure test to maximum allowable working pressure to be
carried out .
(5) High pressure/capacity pumps and compressors shall be surveyed by opening
up fully or partly as deemed necssary by the surveyor. Pressure testing to be
carried out when relevant and found necssary by the surveyor .
(6) The riser system to be close visually surveyed. Liquid penetrations or MPI
methods shall be used to investigate critical areas for cracks. Thickness
measurements may be required if found necssary by the surveyor .
204
(7) The blowout preventer system shall be subject to complete overall and
complete performance test. Pressure testing to maximum allowable working
pressure to be carried out.
(8) For lifting devices thickness measurements of structural parts to be carried out
as far as deemed necssary. NDT of main structural components may be
required as far as deemed necessary by the surveyor .
(9) The fixed water protection systems in process area are to be surveyed and
tested for correct functioning .
(10) Function test of safety devices and instrumentation given in 1.3.2.4 is to be
carried out
1.7.3.4 Other examinations and tests deemed necessary by the surveyor are to be carried
out .
1.8 Boiler and thermal oil heater surveys
1.8.1 General
Boiler and thermal oil heater surveys are to be carried out in accordance with the
requipments in 3.8 Part 1-B, TCVN 6259-1:2003 .
1.9 Propeller shafts and stern tube shaft surveys
1.9.1 General
Propeller shafts and stern tube shaft surveys are to be carried out inaccordance with
the requipments in 3.9, Part 1-B,TCVN 6259-1:2003.
1.10 Automatic and Remote Control System Surveys
For Automatic and Remote-Control System Annual and Special Periodical Surveys,
applicable requirements of TCVN 6277:2003 Rules for Automatic and Remote-
Control System - are to be complied with.
1.11 Annual Surveys for Inert Gas Systems
At each Annual Survey of Machinery the inert gas system is to be generally examined
in so far as can be seen and placed in satisfactory condition. The survey is also to
include the following, as applicable:
1.11.1 General
1.11.1.1 External Examination
TCVN 6474-8 : 2007
205
External examination of all components and piping, including scrubber, fans, valves,
stand pipe and screens.
1.11.1.2 Inert Gas Blower
Confirmation of proper operation of inert gas blowers.
1.11.1.3 Scrubber Room Ventilation System
Observation of the operation of the scrubber room ventilation system
1.11.1.4 Non-return device
Deck seals or double block and bleed assemblies, and non-return valves are to be
examined externally and proven to be in operation. Automatic filling and draining of
the deck seal, operation of non-return valves and double block and bleed assemblies,
and the water carryover are to be checked
1.11.1.5 Control Valves.
Verify the operation of all remotely operated or automatically controlled valves and,
in particular, the flue gas isolating valves .
1.11.1.6 Interlocking Feature
Verify the operation of the interlocking feature of soot blowers
1.11.1.7 Gas Pressure Regulating Valve
Verify the automatic operation of the gas pressureregulating valve
1.11.1.8 Operation and Maintenance Records
The Surveyor is to examine the permanent records to verify the operation and
maintenance of the system.
1.11.2 Alarm and Safety Device
Verify the operation of the following alarms and safety devices using simulated
conditions, where necessary:
1.11.2.1 Flue Gas Systems
Low water pressure or low water flow rate to the flue gas scrubber, including
automatic shut-down of the inert gas blowers and gas regulating valve.
High water level in the flue gas scrubber, including automatic shut-down of the inert
gas blowers and gas regulating valve.
High gas temperature at IGS blower discharge, including automatic shut-down of the
206
inert gas blowers and gas regulating valve.
Failure of the inert gas blowers, including automatic shut-down of the gas regulating
valve.
Oxygen content in excess of 8% by volume.
Failure of the power supply to the automatic control system for the gas regulating
valve and to the oxygen content and gas pressure indicating devices.
Low water level in the water seal.
Gas pressure less than 100 mm water gauge.
High gas pressure.
Accuracy of fixed and portable oxygen measuring equipment by means of a
calibration gas.
1.11.2.2 Inert Gas Generating Systems
Low water pressure or low water flow rate to the inert gas scrubber
High gas temperature
Oxygen content in excess of 8% by volume
High gas pressure
Insufficient fuel oil supply
Failure of the power supply to the generator
Failure of the power supply to automatic control system for the generator
Accuracy of fixed and portable oxygen measuring equipment by means of a
calibration gas
1.12 Special Periodical Surveys for Inert Gas Systems
In addition to the requirements specified in 1.11, following items are to be surveyed:
1.12.1 General
All valves, including valves at boiler uptakes, air seal valves at uptakes, scrubber
isolating valves, fans inlet and outlet isolating valves, main isolating valve, re-
circulating valve (if fitted), pressure/vacuum breaker and cargo tank isolating valves
are to be examined.
Scrubber is to be examined.
TCVN 6474-8 : 2007
207
Fans (blowers), including casing drain valves are to be examined.
Fan (blower) drives, either electric motor or steam turbine are to be examined.
Bellows expansions pieces are to be examined.
Sea water pumps, valves and strainers for scrubbers and water seals together with
piping connections at the scrubber, water seals, shell plating and the remainder of
the sea water piping are to be examined.
Stand pipe, where fitted, for purging in each cargo tank is to be examined.
Deck seals or double block and bleed assemblies, and non-return valves are to be
examined externally and internally.
1.12.2 Separate Inert Gas Generator System
Surveys for separate inert gas generator systems are to comply with all applicable
requirements in 1.12.1, together with the following:
Automatic combustion control system is to be examined and tested, as necessary.
Combustion chamber and mountings are to be examined internally and externally.
Forced draft fan is to be examined.
Fuel oil service pumps are to be examined.
1.12.3 Gas Stored in Bottles System
Systems using inert gas stored in bottles are to comply with all applicable
requirements in 1.12.1, together with the following:
Bottles are to be examined internally and externally. If they cannot be examined
internally, they are to be thickness measured. When considered necessary by the
Surveyor, they are to be hydrostatically tested. Relief valves are to be proven
operable.
Where an alkali (or other) scrubber is fitted in the system, the scrubber,
circulating pump, valves and piping are to be examined internally and externally.
1.13 Annual Surveys Production Facilities
For Annual Survey of Production Facilities, the applicable requirements of the
Appendix VII, Part 9 are to be complied with.
1.14 Special Periodical Surveys - Production Facilities
208
For Special Periodical Survey of Production Facilities, the applicable requirements of
the Appendix VII, Part 9 are to be complied with.
1.15 Annual Surveys - Mooring Systems
1.15.1 Annual Surveys - Spread Mooring Systems
At each Annual Survey, the spread mooring system is to be generally examined so
far as can be seen and placed in satisfactory condition as necessary. In addition, the
following above water items are to be examined, placed in satisfactory condition and
reported upon, where applicable:
(1) The anchor chain stopper structural arrangements are to be visually examined,
including the structural foundations of all of the stoppers or holders.
Tensioning equipment is to be generally examined.
(2) The anchor chain catenary angles are to be measured to ensure that the anchor
chain tensions are within the design allowable tolerances. Where anchor
cables are used, their tensions are to be verified to be within the allowable
tensions.
(3) The anchor chains or anchor cables above the water are to be visually
examined for wear and tear.
1.15.2 Annual Surveys - Single Point Mooring (SPM) Systems
At each Annual Survey, the single point mooring system is to be generally examined
insofar as can be seen above water and placed in satisfactory condition as necessary.
In addition, the following above water items are to be examined, placed in
satisfactory condition and reported upon, where applicable:
(1) The anchor chain stopper structural arrangements are to be visually examined,
including the structural foundations of all of the stoppers.
(2) The anchor chain's catenary angles are to be measured to verify that the
anchor chain tensions are within the design allowable tolerances. Where
anchor cables are used, their tensions are to be verified to be within the
allowable tensions.
(3) The anchor chains or anchor cables above the water are to be visually
examined for wear and tear.
(4) The condition of the bearings is to be verified for continued effectiveness of
TCVN 6474-8 : 2007
209
the lubrication system.
(5) The entire assembly of the single point mooring structure above water is to be
generally examined for damage, coating breaks and excessive signs of
corrosion. This survey is to include all turret wall structures, accessible turret
well structures, mooring arms, all structures supporting the disconnectable
operations of the mooring system, etc., whichever are applicable
1.16 Special Periodical Surveys - Mooring Systems
Since it is impractical to cover all types of mooring systems, the following are
provided as guidance to show the basic intent of the Requirements. Operators and
designers may submit alternative survey requirements based either on service
experience or manufacturer's recommendations. Upon review and if found acceptable,
these alternative survey procedures will form the basis for the Special Periodical
Survey of the Mooring System.
The Special Periodical Survey is to include all items listed under the Annual Survey
and, in addition, the following are to be performed, where applicable:
1.16.1 A Drydocking Survey or equivalent underwater inspection of the SPM system is to
be performed. This survey is to include examination of the entire structure of the
SPM, the protective coating, cathodic protection system, the chain stoppers and
their locking devices.
1.16.2 Any suspect areas where excessive corrosion is evident are to be thickness gauged.
Gaugings are to be taken on the structures of the SPM when it has undergone
service for 15 years or more.
1.16.3 An examination is to be made on all anchor chains for excessive corrosion and
wastage. In particular, the areas to be specially examined are the areas having the
most relative movement between the chain links. These areas are normally located
in way of the seabed touchdown sections of the catenary part of the chains. The
chains are to be inspected for looses studs and link elongations. Sufficient
representative locations are to be gauged for wear and wastage. Areas susceptible
to corrosion, such as the wind-and-water areas, are to be specially gauged, if
considered necessary by the attending Surveyor
1.16.4 A close examination is to be performed on all mooring components and accessible
210
structural members that carry the mooring loads. These structures include the chain
stoppers or cable holders, the structures in way of the chain stoppers or cable
holders, structural bearing housing and turret/structural well annulus areas. These
structures are to be thoroughly cleaned and examined and any suspect areas are to
be nondestructively tested.
1.16.5 A general inspection is also to be carried out on the degree of scour or exposure in
way of the anchor or anchor piles to ascertain that these components are not
overexposed
1.16.6 An examination is to be performed on the main bearing of the SPM system. This
examination is to include visual inspection of bearing, if accessible, for water
egress into the structural housing, corrosion, pitting and excessive wear. If the
bearing is inaccessible, at least the weardown is to be ascertained and the condition
of the bearing seals verified. If disassembled, the bearing rollers and the racer
housings are to be examined.
1.16.7 For inaccessible structures, special alternative inspection procedures for inspection
of these areas are to be submitted for approval.
1.16.8 The chain tensions are to be checked and where found not in compliance with the
specifications are to be readjusted accordingly. Excessive loss of chain or tendon
tensions are to be investigated.
1.16.9 Representative areas of the chains are to be examined and checked for excessive
wastage. In particular, areas in way of the chain stoppers and the seabed touchdown
areas are to be specially examined and measured for excessive wear
1.16.10 For disconnectable type mooring systems, the disconnect and connect system for
the mooring system is to be tested as considered necessary by the attending
Surveyor. Alternatively, records of disconnect/connect operations between the
credit date of the last Special Periodical Survey and the current due date of same
may be reviewed, and if found satisfactory, it may be considered to have been in
compliance with this requirement
1.17 Annual Surveys - Import and Export Systems
At each Annual Survey, the import and export (when requested for classification)
systems are to be examined as far as can be seen and placed in satisfactory condition
TCVN 6474-8 : 2007
211
as necessary. In addition, the following items are to be examined, placed in
satisfactory condition and reported upon where applicable:
(1) A general examination is to be performed on all electrical and fluid swivels,
flexible risers, floating hoses, cargo piping and valves associated with the
import and export systems, expansion joints, seals, etc.
(2) The fluid swivels are to be examined for signs of leaks through their "tell-tale"
apertures.
(3) Records of maintenance are to be reviewed, including records of hose
hydrostatic testing.
(4) Navigational aids for all floating hoses are to be examined and functionally
tested.
(5) Riser tensioning arrangements are to be examined for proper functioning
order.
(6) All electrical equipment, fitted in hazardous location is to be examined for
integrity and suitability for the continued service
1.18 Special Periodical Survey Import and Export Systems
Since it is impractical to cover all types of import and export systems, the following
are provided as guidance to show the basic intent of the Requirements. Operators and
designers may submit alternative survey requirements based either on service
experience or manufacturer's recommendations. Upon review and if found acceptable,
these alternative survey procedures will form the basis for the Special Periodical
Survey of the Import and Export System
The Special Periodical Survey is to include all items listed under the Annual Survey
and, in addition, the following are to be performed:
1.18.1 Fluid and electrical swivels are to be disassembled, if considered necessary, and
examined for wear and tear. The seals are to be examined. Upon completion of the
reconditioning, the fluid swivels are to be hydrostatically tested. Similarly, the
electrical swivels are to be insulation tested upon reassembly
1.18.2 During underwater inspection of the SPM system, flexible risers are to be
examined, including all arch support buoyancy tanks. Risers are to be inspected for
212
damage in high stress areas, such as areas in way of the end flanges, areas in way of
the arch support clamps and the bottom of all looped areas. Spreader bars, if fitted
to separate one riser string from another, are to be inspected for wear and tear.
Hydrostatic tests may be required to be conducted on the risers, as deemed
necessary by the attending Surveyor
1.18.3 For deep sea applications, riser suspension or support systems are to be examined
for deterioration and loss of tension. Support areas in way of the riser are to be
closely examined for fretting corrosion, wear, kinks, creases, etc.
1.18.4 Floating export hoses are to be examined for kinks, surface cracks, chaffing
damages, etc. Hydrostatic and vacuum tests may be required to be conducted on the
floating hose string, as deemed necessary by the attending Surveyor.
1.18.5 All piping systems are to be opened up for examination. Nondestructive and
hydrostatic tests may be required, where considered necessary by the attending
Surveyor.
1.18.6 Hoses designed and manufactured based on OCIMF standards are to be tested in
accordance with the OCIMF Guide for the Handling, Storage, Inspection, and
Testing of Hoses in the Field.
213
NATIONAL STANDARD TCVN 6474-9 : 2007
Second edition
RULES FOR CLASSIFICATION AND TECHNICAL SUPERVISION OF
FLOATING STORAGE UNITS
PART 9 SPECIFIC REGULATIONS
Reference standards and definitions: see Part 1, TCVN 7474-1: 2007 and this part.
This part specifies the specific regulations used in part 1 TCVN 6474-1: 2007 to part 8,
TCVN 6474-8:2007.
1. See appendix I: The Concept and Application of Environmental Severity Factors
(ESFs) for Ship-Type Site-Dependent Designed Floating Offshore Installations;
2. See appendix II: The Modification of Ship-Type Floating Production System Criteria
for Site-Specific Environment Conditions;
3. See appendix III: Extent of structures is to be analysed by Finite Element models
(FEM);
4. See appendix IV: Load Criteria
5. See appendix V: Fatigue Life ;
6. See appendix VI: Failure Criteria Yielding;
7. See appendix VII: Machinary, process system on floating storage units;
8. See appendix VIII: Underwater Inspection procedure.
TCVN 6474-9 : 2007
214
1 Appendix I: The Concept and Application of Environmental Severity Factors
(ESFs) for Ship-Type Site-Dependent Designed Floating Offshore Installations
1.1 ESFs of the Beta Type
This type of ESF compares the severity between the intended environment relative to a
base environment, which is the North Atlantic unrestricted service environment.
In the affected formulations, the Beta factors apply only to the dynamic portions of the
load components, and the load components that are considered "static" are not affected
by the introduction of the Beta factors.
The definition of the severity measure Beta is as follows:
Beta = L
s
/L
u
where:
L
s
- most probable extreme value based on the site-specific environment for
the dynamic load parameters specified in Table 9.1-1;
L
u
- most probable extreme value base on the North Atlantic environment for
the dynamic load parameters specified in Table 9.1-1.
A Beta of 1.0 corresponds to the unrestricted service condition of a seagoing tanker.
A value of Beta less than 1.0 indicates a less severe environment than the unrestricted
case
The values calculated for L
s
and L
u
are to be consistent with vessel headings. This
means that for any dynamic load parameter, if head sea is used for example on the
calculation of Ls, the same heading is to be used for the calculation of L
u
The net scantling is to be verified using a severity beta factor based on the intended
site using a 100-year return period, and the transit condition using a return period as
specified in Part 3, clause 1.2.7.2 , whichever is worst .
For each dynamic load parameter, the severity measure beta is to account for the
vessel headings as follows:
For the intended site, the worst case between head seas, following seas and equal
probability
If no rosette information regarding the environment directionality is available for
the transit condition, the worst case between head seas, equal probability and
TCVN 6474-9 : 2007
215
oblique seas (defined as equal probability between head seas and 60 degrees from
the bow). Oblique seas are coming either from the port or the starboard side
There are 13 dynamic load components for which the beta adjustment factors have
been derived. These are for the following loads or load effects:
Table 9.1-1: Dynamic Load Parameters or ESFs
No. Name
1 Vertical Bending Moment
2 Horizontal Bending Moment
3 External Pressure Starboard
4 External Pressure Port
5 Vertical Acceleration
6 Transverse Acceleration
7 Longitudinal Acceleration
8 Relative Vertical Motion at Forepeak
9 Wave Height
10 Pitch Motion
11 Roll Motion
12 Vertical Shear Force
13 Horizontal Shear Force
As mentioned, the Beta values are a direct function of the long-term environmentally-
induced loads at the installation site compared to the unrestricted service environment
that is the basis of the Rules. The Beta values also need to address other differences
and factors between the design basis of a sea going and a moored vessel. These
include:
Different design basis return periods for environmental loads (20 vs. 100 years).
Effects of mooring system on predicted vessel load effects (including
weathervaning type behavior of a turret moored system).
TCVN 6474-9 : 2007
216
Different assumed wave energy spreading characterization between the open
ocean and a site- specific situation.
Different basis of extreme design storm characterization (i.e., long-term winter
storm vs. hurricane dominated characterization).
If a direct analysis of a floating offshore installation were to be performed, the
influences of the mentioned factors would need to be assessed and used in the vessel's
design.
Notwithstanding the listed Beta factors and their intended usage, it is still necessary to
introduce a limit to keep design parameters from going "too low". This limit is that the
result of an application of a Beta factor (e.g., in the calculation of a required scantling)
is not to be less than 85 percent of the unrestricted service (Rule) value.
1.2 ESFs of the Alpha Type
This type of ESF compares the fatigue damage between the specified environment
relative to a base environment, which is the North Atlantic environment.
First, this type of ESF is used to adjust the expected fatigue damage induced from the
dynamic components due to environmental loadings at the vessel's installation site.
Second it can be used to assess the fatigue damage accumulated during the historical
service either as a trading tanker or as an FPI, including both the historical site(s) and
historical transit routes
The definition of the severity measure a is as follows:
= D
u
/D
s
where
D
u
- annual fatigue damage based on the North Atlantic environment
(unrestricted service) at the regions of the hull structure specified in Table 9.1-2.
D
s
- annual fatigue damage based on a specified environment, for historical
routes, historical sites, transit and intended site, at the regions of the hull
structure specified in Table 9.1-2.
The values calculated for D
s
and D
u
are to be consistent with the vessel headings.
This means that for any structural detail, if head sea is used for examples on the
calculation of D
s
, the same heading is to be used for the calculation of D
u
.
TCVN 6474-9 : 2007
217
If the Owner provides no rosette information regarding the environment
directionality, the severity measure a for each structural detail is to be selected
according to the following criteria:
For site spread moored vessels the worst case between equal probability, head
seas and following seas
For site turret moored vessel, the worst case between head seas, following seas,
and oblique seas (defined as equal probability between head seas and 60 degrees
heading from the bow), with oblique seas coming either from the port or the
starboard side
For transit and historical route conditions, the worst case between head seas and
oblique seas (defined as equal probability between head seas and 60 degrees from
the bow), with the oblique seas coming either from the port or the starboard side
Table 9.1-2 - The 6 Fatigue Damage Adjustment Factors
No Alpha Applies to
1
deck
Deck
2
SShl
Side Shell
3
LBhd
Longitudinal Bulkheads
4
CBhd
Centerline Bulkheads
5
InBm
Inner Bottom
6
Bttm
Bottom
TCVN 6474-9 : 2007
218
2 Appendix II: The Modification of Ship-Type Floating Production System Criteria
for Site-Specific Environment Conditions
2.1 Deck Load
For the design and evaluation of deck structures, the following loads due to on deck
production facilities are to be considered:
(1) Static weight of on deck production facilities in upright condition.
(2) Dynamic loads due to ship motions.
(3) Wind load
2.1.1 Loads for On-Site Operation
The nominal forces from each individual deck production module at the center of gravity
of the module can be obtained from the following equations:
[ ] g a c C C W F
v v v v
/ 71 . 0 ) 71 . 0 cos)( ) 71 . 0 cos(
+ =
[ ]
wind t t t t t
F k g a c C W F + + = / 71 . 0 ) 71 . 0 sin(
[ ]
wind l l L l l
F k g a c C W F + + = / 71 . 0 ) 71 . 0 sin(
Where
and are the pitch and roll amplitudes with V = 10 knots/h and
2
3
i f
d d =
in degrees, need not to be taken more than 10 degrees
in degrees, need not to be taken more than 30 degrees
a
v
, a
t
and a
l
are the vertical, transverse and longitudinal for heading in table 9.2-1
F
v
= vertical load from each production module, positive downward
F
t
= transverse load from each production module, positive starboard
F
l
= longitudinal load from each production module, positive forward
W = weight of the production module, in kN
2
wind wind s h wind
F kA C C V =
= wind forces, kN
Two combinations of wave-induced and wind forces are to be considered: F
v
, F
t
:
F
v
, F
t
with factor k
t
=1 and F
l
with factor k
l
= 0
TCVN 6474-9 : 2007
219
F
v
, F
t
with factor k
t
=0 and Fl with factor k
l
= 1
The deck load is to be obtained for the maximum weight of on deck production facilities
for head sea (Load Case A), beam sea (Load Case B) and oblique sea (Load Case C)
listed in Table 9.2-1, where the correlation factors c
v
, c
T
, c
L
, C
, C
-1 0 -0,7
C
0 1 0,7
Wave heading
angle (degree)
0 90 60
where
V
wind
= wind velocity based on 1-hour average speed
C
s
= shape coefficient, defined in Part 2
C
h
= height coefficient, defined in in Part 2 for 1-hour average wind
The forces from each deck production module can be obtained based on long-term
prediction for the realistic sea states of the specific site of operation. In no case are the
forces Fv, Ft and Fi to be less than those obtained using the values of Environmental
Severity Factors (ESFs) established from Appendix I
where
=
=
Where:
es
and
es
are given in Appendix IV.
and are the pitch and roll amplitudes defined in Appendix IV, with V = 10 knots
and d
i
= 2/3d
f
Alternatively, nominal sloshing pressures can be calculated based on sea condition
for the specific site of operation.
2.3 Green Water
When experimental data or direct calculations are not available, nominal green water
pressure imposed on deck in the region from FP to 0.30L aft, including the extension
beyond the FP, may be obtained from the following equations:
( )
1/ 2
1 gi Ri bi
P k M k F =
kN/m
2
where
P
gi
= Green water pressure, uniformly distributed across the deck at specified
TCVN 6474-9 : 2007
221
longitudinal section i within the bow region under consideration . Pressure in between
is obtained by linear interpolation. Pgi is not to be taken less than 20.6 kN/m2 .
k = 19,614
k
1
= 1
M
Ri
=
( )
1/ 2
1, 39 /
i vm b
A L C
for L in meters
A
i
= in Table 9.2-2
vm
= a vertical motion factor
C
b
= Fulness coefficient in TCVN 6259-2:2003
L = length of vessel
F
bi
= freeboard from the highest deck at side to the load waterline (LWL) at
station i
Table 9.2-2 - Values of A
i
and B
i
Section i from F.P. A
i
B
i
-0,05L 1,25 0,36
0 1,0 0,4
0,05L 0,8 0,4375
0,1L 0,62 0,4838
0,15L 0,47 0,5532
0,2L 0,33 0,6666
0,25L 0,22 0,8182
0,3L 0,22 0,8182
2.4 Bow Impact Pressure
When experimental data or direct calculations are not available, nominal bow impact
pressures due to wave celerity above the load waterline (LWL) in the region from the
forward end to the collision bulkhead may be obtained from the following equation:
2
sin
bij k ij ij ij
P kC C V =
kN/m
2
where
TCVN 6474-9 : 2007
222
k = 1,025
( )
{ }
( )
1/ 2
2
1/ 2
1 2
1 cos 90 2 /
sin
ij bi j bi
ij ij WHT
C F a F
V L
= +
= +
1
= 3,09
2
= 1
WHT
= ESF for Wave Height
( )
1
tan tan / cos
ij ij ij
=
not to be taken less than 50 degrees
ij
= local waterline angle measured from the centerline, not to be taken less
than 35 degrees
ij
= local body plan angle measured from the horizontal , not to be taken
less than 35 degrees
F
bi
= freeboard from the highest deck at side to the load waterline (LWL) at
station i
a
j
= vertical distance from LWL to WL-j
i,j = station and waterline to be taken to correspond to the locations under
consideration
C
k
= 0.7 at collision bulkhead and 0.9 at 0.0125L, linear interpolation for in
between
= 0.9 between 0.0125L and FP
= 1.0 at and forward of FP
2.5 Bottom Slamming Pressure
For a vessel with a heavy weather draft forward less than 0.04L but greater than
0.025L, bottom slamming loads are to be considered for assessing strength of the flat
bottom plating forward and the associated stiffening system in the fore body region.
The equivalent bottom slamming pressure for strength formulation and assessment
should be determined based on well-documented experimental data or analytical
studies. When these direct calculations are not available, nominal bottom slamming
pressures may be determined by the following equations:
TCVN 6474-9 : 2007
223
( )
2
0 si i Vi ni f
P v M E E = +
kN/m
2
where
P
si
= equivalent bottom slamming pressure for section i
= 1,025
i
=
*
0
2, 2 / , 40 b d +
b* = half width of flat bottom at the i-th ship station
d
0
= 1/10th of the section draft at the heavy ballast condition
= a constant as given in table 9.2-3
E
f
=
1/ 2
1 1
f L
1
= natural angular frequency of hull girder 2-node vertical vibration of the
vessel in the wet mode and the heavy weather ballast draft condition, in rad/second
1
f
= 0,004 m
where b represents the half breadth at the 1/10th draft of the section. Linear
interpolation may be used for intermediate values
1/ 2
0 0
0
0, 29
v c L
c m
=
=
M
Ri
=
( )
1/ 2
1, 39 /
i vm b
A L C
with L in metres
M
vi
= B
i
M
Ri
where B
i
given in table 9.2-2
( )
2 2
0
exp / /
ei vi i Ri
G v M d M
= +
d
i
= local section draft, in m
E
ni
= natural log of ni
( )
1/ 2
5730 /
i Vi Ri ei
n M M G =
if n<1 then P
si
= 0
TCVN 6474-9 : 2007
224
Table 9.2-3:Values of
b/d
0
b/d
0
1 0 4 20,25
1,5 9 5 22
2 11,75 6 23,75
2,5 14,25 7 24,5
3 16,5 7,5 24,75
3,5 18,5 25 24,75
2.6 Local Structure of the Hull Supporting Deck Mounted Equipment
This Section addresses deck transverses and deck girders
2.6.1 General
Section modulus and web sectional area of the deck transverses and deck girders may
be obtained in accordance with the procedure given below or other recognized design
procedures.
Section modulus and web sectional area of the deck transverse and deck girders are
not to be less than specified below for the following load patterns:
Load pattern No.1 when a tank under consideration is empty and the deck transverse
and/or deck girder is loaded with reactions (forces and moments) from the topside
structure .
Load pattern No.2 when a tank under consideration is full and the deck transverse
and/or deck girder is loaded with cargo pressure. The loads from the topside structure
are not to be considered for this loading condition ).
2.6.2 Load Pattern No. 1
2.6.2.1 Section Modulus of Deck Transverse
The net section modulus of deck transverses, in association with the effective deck
plating, is to be obtained from the following equation:
/
b
SM M f =
cm
3
(1) For deck transverses in wing tanks
TCVN 6474-9 : 2007
225
( )
5
10
p g s
M k M M M = + +
N-cm
For deck transverses in center tanks
( )
5
10
p g b
M k M M M = + +
N-cm
where
k = 1
p
M
= bending moment due to reactions from topside structure
=
( )
v m t
M M f +
( )
( )
1 2
3 4
v t n n n
n
m n n n
n
M l P k k
M M k k
= +
= +
n
P
= reaction deck force number n, in kN , applied to the deck transverse in
tank under consideration, see Figure 9.2-1
n
M
= reaction deck moment number n, in kN-m , applied to the deck
transverse in tank under consideration, see Figure 9.2-1
n = 1, 2, 3 , Nv to obtain bending moment M
v
n = 1, 2, 3 , Nm to obtain bending moment M
m
Nv = = total number of reaction forces at deck transverse under
consideration, (in tank under consideration)
N
m
= total number of reaction moments at deck transverse under
consideration, (in tank under consideration)
l
t
= span of the deck transverse under consideration, in m
TCVN 6474-9 : 2007
226
a
n
= distance, in m , from a point of application of reaction (force P
n
or moment
M
n
) to the end of the deck transverse span 1
t
, in m , as shown in Figure 9.2-1.
z = coordinate (measured from the end of the span 1
t
) of the section of the deck
transverse under consideration, in m , as shown in Figure 9.2-1.
For the toe of the deck transverse end brackets:
/
a t
z h l =
and
1 /
a t
z h l =
h
a
= distance, in m, from the end of the span to the toe of the end bracket of the
deck transverse
Note: For a wide topside bracket, the vertical load on a deck transverse can be considered
uniformly distributed with pressure q
n
= P
n
/c, and the concentrated bending moment can
be substituted by force couples.
/( )
m n
P M kc =
where
,
n n
P M
= concentrated force and moment obtained from FE analysis of
topside structure
c = width of the topside bracket
k = shape bracket factor, and may be taken as 0.8, unless otherwise
specified.
Bending moment at the toe of the end brackets due to green water pressure, M
g
:
3 2
0,1
g gi t
M c P sl =
where
TCVN 6474-9 : 2007
227
gi
P
= nominal green water pressure imposed on the deck, in kN/m2 , as
defined in Appendix II, clause 2.3
s = spacing, in m, of the deck transverses
Bending moments due to pressure on side transverse and vertical web of longitudinal
bulkhead
2 2
2 2
s s s s s
b b b b b
M k c p sl
M k c p sl
=
=
where k
s
= 0.1, and k
b
= 0.1, unless otherwise specified
l
s
, l
b
= span, in m (ft), of side transverse and vertical web on longitudinal
bulkhead, respectively
p
s
= nominal pressure, in kN/m
2
, at the mid-span of side transverse when wing tank
is empty, adjacent tanks full
p
b
= nominal internal cargo pressure, in kN/m
2
, at the mid-span of the vertical web
on longitudinal bulkhead when center tank is empty, adjacent tanks full
Nominal pressure p
s
and p
b
can be obtained in appendix IV with the following
modifications:
i) Coefficient wv can be multiplied by factor
v
, coefficient w
l
by factor
l
,
coefficient w
t
by factor
t
, coefficient c
by factor
, coefficient c
by
factor
ii) Ship motions and accelerations
where
v
,
l
,
t
,
s
f
= permissible shear stress, (N/cm
2
)
=
0, 3
m y
S f
TCVN 6474-9 : 2007
231
2.6.3 Load Pattern No. 2
Section modulus and web sectional area of deck transverses and deck girders for load
pattern No. 2 are to be obtained from TCVN 6259-2A.
Internal pressure can be obtained from Appendix IV with the modifications given in
2.6.2.
Figure 9.2-1 - Definition of Parameters
TCVN 6474-9 : 2007
232
3 Appendix III: Extent of structures is to be analysed by Finite Element models
(FEM)
3.1 Methods of Approach and Analysis Procedures
Maximum stresses in the structure are to be determined by performing structural
analyses, as outlined below. structural idealization, load application and structural
analysis may be carried out in accordance with recognized documentation/ guideline.
In general, the strength assessment is to be focused on the results obtained from
structures in the mid hold of a three hold length model. However, the deck transverse, the
side transverse, the vertical web on longitudinal bulkheads, the horizontal girder and the
vertical web on transverse bulkheads and the cross tie are to be assessed using the end
holds of a three hold length model as well.
3.2 3D Finite Element Models
A simplified three-dimensional finite element model, representing usually three bays of
tanks within 0.4L amidships, is required to determine the load distribution in the
structure.
The same 3D model may be used for hull structures beyond 0.4L amidships with
modifications to the structural properties and the applied loads, provided that the
structural configurations are considered as representative of the location under
consideration
3.3 2D Finite Element Models
Two-dimensional fine mesh finite element models are required to determine the stress
distribution in major supporting structures, particularly at intersections of two or more
structural members.
3.4 Local Structural Models
A 3D fine mesh model is to be used to examine stress concentrations, such as at
intersections of longitudinals with transverses and at cut outs.
3.5 Load Cases
When performing structural analysis, the eight combined load cases specified in appendix
IV are to be considered. In general, the structural responses for the still-water conditions
are to be calculated separately to establish reference points for assessing the wave-
induced responses. Additional load cases may be required for special loading patterns and
TCVN 6474-9 : 2007
233
unusual design functions, such as sloshing loads. Additional load cases may also be
required for hull structures beyond the region of 0.4L amidships.
TCVN 6474-9 : 2007
234
4 Appendix IV: Load Criteria
The load criteria are applicable for floating storage units with length more than 150 m.
For floating storage units with length less than 150 m, a recognized standard may be
used. The load criteria in this appendix are used in conjunction with amendments given
on appendix II.
4.1 General
4.1.1 Load Components
In the design of the hull structure of tankers, all load components with respect to the hull
girder and local structure as specified in TCVN6259-2:2003 are to be taken into account.
These include static loads in still water, wave-induced motions and loads, sloshing,
slamming, dynamic, thermal and ice loads, where applicable.
4.2 Static Loads
4.2.1 Still-water Bending Moment
For still-water bending moment calculations, see TCVN 6259-2:2003.
When a direct calculation of wave-induced loads is not submitted, envelope curves of the
still-water bending moments (hogging and sagging) and shear forces (positive and
negative) are to be provided.
Except for special loading cases, the loading patterns shown in Figure 9.4-1 are to be
considered in determining local static loads.
TCVN 6474-9 : 2007
235
Figure 9.4-1 - Loading Pattern
4.3 Wave-induced Loads
4.3.1 General
Where a direct calculation of the wave-induced loads is not available, the approximation
equations given below and specified in TCVN6259-2:2003 may be used to calculate the
design loads.
When a direct calculation of the wave-induced loads is performed, envelope curves of the
combined wave and still-water bending moments and shear forces, covering all the
anticipated loading conditions, are to be submitted for review.
4.3.2 Horizontal Wave Bending Moment and Shear Force
4.3.2.1 Horizontal wave bending moment
The horizontal wave bending moment, positive (tension port) or negative (tension
TCVN 6474-9 : 2007
236
starboard), may be obtained from the following equation:
2 ' 3
3 1
10
H h b
M m K C L DC
=
kN-m
where
m
h
= distribution factor, as given by Figure 9.4-2
K
3
= 180
D = depth of floating unit
C
1
, L and
'
b
C
are as given in Section 13, TCVN6259-2:2003.
Figure 9.4-2 Distribution Factor mh
4.3.2.2 Horizontal Wave Shear Force
The envelope of horizontal wave shearing force, F
H
, positive (toward port forward) or
negative (toward starboard aft), may be obtained from the following equation:
( )
' 2
1
0, 7 10
H h b
F f kC L D C
= +
kN
where
f
h
= distribution factor, as given in Figure 9.4-3
k = 36
C
1
, L and C
b
are as given in Section 13, TCVN6259-2:2003.
TCVN 6474-9 : 2007
237
Figure 9.4-3 - Distribution Factor f
h
4.3.3 External Pressures
4.3.3.1 Pressure Distribution
The external pressures, p
e
, (positive toward inboard), imposed on the hull in seaways can
be expressed by the following equation at a given location:
( ) 0
e s u de
P g h k h = +
N/cm
2
where
g
= specific weight of sea water
= 1,005 N/cm
2
-m
h
s
= hydrostatic pressure head in still water, in m
k
u
= load factor, and may be taken as unity unless otherwise specified.
h
de
= hydrodynamic pressure head induced by the wave, in m (ft), may be calculated
as follows:
= k
c
h
di
where
k
c
= correlation factor for a specific combined load case, as given in 4.4.1 and 4.5.2.
h
di
= hydrodynamic pressure head, in m , at location i (i = 1,2,3,4 or 5; see figure 9.4-
4)
TCVN 6474-9 : 2007
238
=
i do
k h
+
,
0
k
=
where
x = distance from A.P. to the station considered, in m
x0 = distance from A.P. to the reference station, in m
L = the floating unit length, m
= the wave heading angle, to be taken from 0 to 90
kf o = 1.0, as specified in Table 9.4-1
The simultaneous pressure distribution around the girth of the vessel is to be determined
based on the wave heading angles specified in 4.4 and 4.5
4.4 Nominal Design Loads
4.4.1 Hull Girder Loads Longitudinal Bending Moments and Shear Forces
4.4.1.1 Total Vertical Bending Moment and Shear Force
The total longitudinal vertical bending moments and shear forces may be obtained from
the following equations::
kNm
kN
t sw u c w
t sw u c w
M M k k M
F F k k F
= +
= +
where
M
sw
and M
w
are the still-water bending moment and wave-induced bending moment,
F
sw
and F
w
are the still-water and wave-induced shear forces
k
u
is a load factor and may be taken as unity unless otherwise specified
k
c
is a correlation factor and may be taken as unity unless otherwise specified.
For determining the hull girder section modulus for 0.4L amidships, the maximum still-
water bending moments, either hogging or sagging, are to be added to the hogging or
sagging wave bending moments, respectively. Elsewhere, the total bending moment may
be directly obtained based on the envelope curves, as specified in 4.2.1 and 4.3.1.
4.4.1.2 Horizontal Wave Bending Moment and Shear Force
For non-head sea conditions, the horizontal wave bending moment and the horizontal
TCVN 6474-9 : 2007
244
shear Force , are to be considered as additional hull girder loads, especially for the design
of the side shell and inner skin structures. The effective horizontal bending moment and
shear force, MHE and FHE, may be determined by the following equations:
kNm
kN
HE u c H
HE u c H
M k k M
F k k F
=
=
where k
u
and k
c
are a load factor and a correlation factor, respectively, which may be
taken as unity unless otherwise specified
4.4.2 Local Loads for Design of Supporting Structures
In determining the required scantlings of the main supporting structures, such as girders,
transverses, stringers, floors and deep webs, the nominal loads induced by the liquid
pressures distributed over both sides of the structural panel within the tank boundaries
should be considered for the worst possible load combinations. In general, considerations
should be given to the following two loading cases accounting for the worst effects of the
dynamic load components.
i. Maximum internal pressures for a fully filled tank with the adjacent tanks
empty and minimum external pressures, where applicable.
ii. Empty tank with the surrounding tanks full and maximum external pressures,
where applicable.
Taking the side shell supporting structure as an example, the nominal loads may be
determined from either:
i.
( )
( )
max
min
i s u d
e s u de
P k g k h
P g h k h
= +
= +
ii.
( )
0
max
i
e s u de
P
P g h k h
=
= +
where k
u
= 1.
4.4.3 Local Pressures for Design of Plating and Longitudinals
In calculating the required scantlings of plating, longitudinals and stiffeners, the nominal
pressures should be considered for the two load cases given in 4.4.3, using k
u
= 1.1 for pi
and pe instead of k
u
= 1.0 as shown above
TCVN 6474-9 : 2007
245
4.5 Combined Load Cases
4.5.1 Combined Load Cases for Structural Analysis
For assessing the strength of the hull girder structure and in performing a structural
analysis , the eight combined load cases specified in Table 9.4-1 are to be considered.
Additional combined load cases may be required as warranted. The loading patterns are
shown in Figure 9.4-1 for three cargo tank lengths. The necessary correlation factors and
relevant coefficients for the loaded tanks are also given in Table 9.4-1 . The total external
pressure distribution including static and hydrodynamic pressure is illustrated in Table
9.4-6.
4.5.2 Combined Load Cases for Failure Assessment
For assessing the failure modes with respect to material yielding, buckling and ultimate
strength, the following combined load cases shall be considered.
4.5.2.1 Ultimate Strength of Hull Girder
For assessing ultimate strength of the hull girder, the combined effects of the following
primary and local loads are to be considered.
(1) Primary Loads, Longitudinal Bending Moments in Head Sea Conditions (M
H
= 0,
F
H
= 0)
t s u c w
M M k k M = +
, k
u
= 1,15, k
c
= 1
t s u c w
F F k k F = +
, k
u
= 1,15, k
c
= 1
(2) Local Loads for Large Stiffened Panels
Internal and external pressure loads as given for L.C. No. 1 and L.C. No. 2 in Table
9.4-1.
4.5.2.2 Yielding, Buckling and Ultimate Strength of Local Structures
For assessing the yielding, buckling and ultimate strength of local structures, the
eight combined load cases as given in Table 9.4-1 are to be considered.
4.5.2.3 Fatigue Strength
For assessing the fatigue strength of structural joints, the eight combined load cases
given in Table 9.4-1 are to be used
TCVN 6474-9 : 2007
246
4.6 Sloshing Loads
4.6.1 General
4.6.1.1 Except for tanks that are situated wholly within the double side or double bottom,
the natural periods of liquid motions and sloshing loads are to be examined in
assessing the strength of boundary structures for all cargo or ballast tanks which
will be partially filled between 20% and 90% of tank capacity. The sloshing
pressure heads given in this subsection may be used for determining the strength
requirements for the tank structures. Alternatively, sloshing loads may be
determined by model experiments or by numerical simulation using three
dimensional flow analysis. Methodology and procedures of tests and measurements
or analysis methods are to be fully documented and referenced. They are to be
submitted for review.
4.6.1.2 The effects of impulsive sloshing pressures on the design of the main supporting
structures of tank transverse and longitudinal bulkheads will be subject to special
consideration.
4.6.2 Strength Assessment of Tank Boundary Structures
4.6.2.1 Tank Length and Pitch Induced Sloshing Loads
4.6.2.2 Roll Induced Sloshing Loads
4.6.2.3 For long or wide cargo tanks, non-tight bulkheads or ring webs or both are to be
designed and fitted to eliminate the possibility of resonance at all filling levels.
Long tanks have length, l, exceeding 0.1L. Wide tanks have width, b, exceeding
0.6B.
4.6.2.4 For each of the anticipated loading conditions, the critical filling levels of the
tank should be avoided so that the natural periods of fluid motions in the
longitudinal and transverse directions will not synchronize with the natural periods
of the vessels pitch and roll motions, respectively.
The natural period of the fluid motion, in seconds, may be approximated by the
following equations:
( )
1/ 2
/
x T e
T k =
in the longitudinal direction
( )
1/ 2
/
y L e
T b k =
in the transverse direction
TCVN 6474-9 : 2007
247
where
e
=
=
4.6.3 Sloshing Pressures
4.6.3.1 Nominal Sloshing Pressure
For cargo tanks with filling levels within the critical range , the internal pressures pis,
including static and sloshing pressures, positive toward tank boundaries, may be
expressed in terms of equivalent liquid pressure head, he, as given below:
0
is s e
P k gh =
where
is
P
= internal pressures including static and sloshing pressures, N/cm
2
k
s
= load factor
h
e
=
m m u c
c h k h +
for y below filling level d
m
=
( )( ) ( ) /
u c t c m m
k h h h y d h d +
for y above dm
h
m
= static head, taken as the vertical distance, in m, measured from the filling level,
d
m
, down to the point considered.
d
m
= filling level, in m
k
u
= load factor, and may be taken as unity unless otherwise specified
h
c
= maximum average sloshing pressure heads, in m
=
( )
1/ 2
2 2
c s s b
k C h C h
+
h
t
= sloshing pressure heads for upper bulkhead, in m
=
( )
1/ 2
2 2
c s t s tb
k C h C h
+
h = depth of tank, in m
y = distance, in m , measured from the tank bottom to the point considered
TCVN 6474-9 : 2007
248
k
c
= correlation factor for combined load cases, and may be taken as unity unless
otherwise specified
C
s
and C
s
are the weighted coefficients as given in Figure 10 9.4-10
where
T
represents for transverse bulkheads and
L
represents for the longitudinal
bulkheads
e
= effective tank length that accounts for the effect of deep ring-web frames, in m
=
*2
T
e
b
= effective tank width that accounts for the effect of deep ring-web frames, in m
=
*2
L
b
*
T
represents * for transverse bulkheads
*
L
represents * for longitudinal bulkheads
( )( )
0
0, 5
s
=
T
represents for transverse bulkheads.
L
represents for longitudinal bulkheads
0
and
'
tb
C
are
t
C
and
tb
C
for hm = 0,7h;
'
T
and
'
L
and
s
C