E PR 360
E PR 360
E PR 360
This Standard is the property of Iranian Ministry of Petroleum. All rights are reserved to the owner.
Neither whole nor any part of this document may be disclosed to any third party, reproduced, stored in
any retrieval system or transmitted in any form or by any means without the prior written consent of the
Iranian Ministry of Petroleum.
ENGINEERING STANDARD
FOR
PROCESS DESIGN OF LIQUID & GAS
TRANSFER AND STORAGE
ORIGINAL EDITION
DEC. 1997
This standard specification is reviewed and
updated by the relevant technical committee on
July 2006. The approved modifications are
included in the present issue of IPS.
Dec. 1997
IPS-E-PR-360
1
CONTENTS : PAGE No.
0. INTRODUCTION............................................................................................................................. 4
1. SCOPE............................................................................................................................................ 5
2. REFERENCES................................................................................................................................ 5
3. DEFINITIONS AND TERMINOLOGY............................................................................................. 7
4. SYMBOLS AND ABBREVIATIONS............................................................................................... 8
5. UNITS.............................................................................................................................................. 9
SECTION A ......................................................................................................................................... 9
6. STORAGE AND HANDLING OF CRUDE OIL AND REFINERY PRODUCTS ............................. 9
6.1 General ..................................................................................................................................... 9
6.2 Design Requirements ............................................................................................................. 9
6.2.2 Wind load.......................................................................................................................... 9
6.2.3 Earthquake load............................................................................................................... 9
6.2.4 Rainfall intensity ............................................................................................................ 10
6.3 Tank Dimensions, Capacities and Layout .......................................................................... 10
6.3.1 General............................................................................................................................ 10
6.3.2 Layout consideration .................................................................................................... 10
6.3.3 Spacing of tanks for petroleum stocks ....................................................................... 11
6.3.4 Types of storage tanks.................................................................................................. 12
6.4 Shell Attachments and Tank Appurtenances .................................................................... 15
6.4.1 General............................................................................................................................ 15
6.4.2 Shell fittings ................................................................................................................... 15
6.5 Fixed Roof Fittings................................................................................................................ 16
6.5.1 Manhole .......................................................................................................................... 16
6.5.2 Vents and relief valves .................................................................................................. 16
6.5.3 Sample points on slops tankage.................................................................................. 16
6.5.4 Control instrumentation for slops tankage................................................................. 16
6.5.5 Water drains ................................................................................................................... 16
6.6 Floating Roof Fittings ............................................................................................................... 17
6.6.1 Manholes ........................................................................................................................ 17
6.6.2 Vents ............................................................................................................................... 17
6.6.3 Heaters............................................................................................................................ 17
6.6.4 Drains.............................................................................................................................. 17
6.6.5 Arrangements for sampling and dipping .................................................................... 17
6.7 Safe Entry and Cleaning of Petroleum Storage Tank........................................................ 17
6.8 Piping System ....................................................................................................................... 18
6.8.1 General............................................................................................................................ 18
6.8.2 Piping layout .................................................................................................................. 18
SECTION B ....................................................................................................................................... 19
7. STORING AND HANDLING OF LIQUEFIED PETROLEUM GASES; LPG................................ 19
7.1 General ................................................................................................................................... 19
7.2 Physical Properties and Characteristics ............................................................................ 19
Dec. 1997
IPS-E-PR-360
2
7.3 Requirements ........................................................................................................................ 19
7.3.1 Siting ............................................................................................................................... 19
7.3.2 Layout and spacing ....................................................................................................... 20
7.3.3 Type and size of storage vessels................................................................................. 20
7.3.4 Spill containment ........................................................................................................... 20
7.4 Design Considerations ......................................................................................................... 21
7.4.1 Storage vessels ............................................................................................................. 21
7.4.2 Refrigeration system..................................................................................................... 24
7.4.3 Pumps ............................................................................................................................. 25
7.4.4 Fire protection facilities ................................................................................................ 26
7.4.5 Piping .............................................................................................................................. 26
7.4.6 Vaporizers ...................................................................................................................... 26
7.4.7 Instrumentation.............................................................................................................. 27
7.5 Transfer of LPG Within the Off-Site Facilities of OGP Plants........................................... 27
7.5.1 General............................................................................................................................ 27
7.5.2 Requirements................................................................................................................. 27
SECTION C....................................................................................................................................... 28
8. LIQUEFIED NATURAL GAS (LNG); STORAGE AND TRANSFER FACILITIES....................... 28
8.1 Introduction ........................................................................................................................... 28
8.2 General Considerations........................................................................................................ 28
8.2.1 Physical properties........................................................................................................ 28
8.2.2 Spacing and diking........................................................................................................ 28
8.3 Criteria and Requirements ................................................................................................... 28
8.3.1 Cryogenic process system........................................................................................... 28
8.4 Transfer of LNG and Refrigerants ....................................................................................... 31
8.4.1 General requirements.................................................................................................... 31
8.4.2 Piping system ................................................................................................................ 32
8.5 Fire Protection....................................................................................................................... 32
SECTION D....................................................................................................................................... 33
9. STORAGE AND HANDLING OF ETHANE AND ETHYLENE..................................................... 33
9.1 General ................................................................................................................................... 33
9.1.1 Scope .............................................................................................................................. 33
9.1.2 Reference publications ................................................................................................. 33
9.3 Distance Requirements and Exposure Limitations........................................................... 33
9.3.1 General............................................................................................................................ 33
9.3.2 Minimum distance requirement and layout ................................................................ 33
9.3.3 Exposure and other limitations .................................................................................... 34
9.3.4 Dike and drainage provisions ...................................................................................... 34
9.4 Tank Accessories.................................................................................................................. 34
9.4.1 General............................................................................................................................ 34
9.4.2 Liquid level indicator ..................................................................................................... 34
9.4.3 Level alarm..................................................................................................................... 34
9.4.4 Pressure gage................................................................................................................ 34
Dec. 1997
IPS-E-PR-360
3
9.4.5 Pressure and vacuum relieving devices ..................................................................... 34
9.5 Piping Requirements ............................................................................................................ 35
9.6 Transfer, Loading and Unloading Facilities ....................................................................... 35
9.6.1 Sizing .............................................................................................................................. 35
9.6.2 Design............................................................................................................................. 35
9.6.3 Equipment ...................................................................................................................... 36
9.7 Refrigeration System............................................................................................................ 36
9.7.1 Refrigeration load .......................................................................................................... 36
9.7.2 Other requirements ....................................................................................................... 36
SECTION E....................................................................................................................................... 37
10. STORING AND HANDLING OF ETHANOL AND GASOLINE - ETHANOL BLENDS ............. 37
10.1 General ................................................................................................................................. 37
10.2 Scope ................................................................................................................................... 37
10.3 Material Selection................................................................................................................ 37
10.4 Requirements ...................................................................................................................... 38
10.4.1 Tanks and tank lining .................................................................................................. 38
10.4.2 Handling ....................................................................................................................... 38
10.4.3 Piping ............................................................................................................................ 38
10.5 Safety and Fire Protection ................................................................................................. 38
SECTION F ....................................................................................................................................... 39
11. STORING AND HANDLING OF GASOLINE - METHANOL/COSOLVENT BLENDS.............. 39
11.1 General ................................................................................................................................. 39
11.2 Material Selection................................................................................................................ 39
11.3 Requirements ...................................................................................................................... 39
TABLE 5 - COMPATIBILITY OF COMMONLY USED MATERIALS.......................................... 40
METALS................................................................................................................................... 40
ELASTOMERS......................................................................................................................... 40
POLYMERS.............................................................................................................................. 40
APPENDICES:
APPENDIX A TABLE A.1 - NOMINAL CAPACITIES OF STANDARD VERTICAL CYLINDRICAL
TANKS.................................................................................................................... 41
APPENDIX B TYPICAL LAYOUT LPG PRESSURE STORAGE WITH COLLECTION
PIT/RETAINING SYSTEM...................................................................................... 42
APPENDIX C ARRANGEMENT OF DRAIN FACILITIES.............................................................. 43
APPENDIX D AIR - DRYER INSTALLATION FOR ETHANOL STORAGE TANKS AT
TERMINALS............................................................................................................ 44
APPENDIX E REFINERIES LIQUEFIED PETROLEUM GAS SPECICATION ............................. 45
Dec. 1997
IPS-E-PR-360
4
0. INTRODUCTION
"Process Design of Offsite Facilities for OGP Industries" is broad and contains various subjects of
paramount importance. Therefore, a group of Process Engineering Standards are prepared to cover
this subject. This group includes the following Standards:
STANDARD CODE STANDARD TITLE
IPS-E-PR-360 "Process Design of Liquid and Gas Transfer and Storage"
IPS-E-PR-370 "Process Design of Loading & Unloading Facilities"
IPS-E-PR-380 "Process Design of Solids Handling System"
This Engineering Standard Specification covers:
" PROCESS DESIGN OF LIQUID AND GAS TRANSFER AND STORAGE"
Dec. 1997
IPS-E-PR-360
5
1. SCOPE
This Standard Specification is intended to cover the minimum requirements and criteria to be
considered in process design of liquid and gas transfer and storage facilities in OGP Industries.
The requirements outlined in this Standard Specification deal with individual items of equipment and
other facilities such as storage tanks and accessories, pumps/compressors and piping connection,
instrumentation, fire protection and safety instruction, layout and spacing and other aspects, but all
to the extent of process design consideration limits.
1.1 This Standard Specification covers the following sections:
Section A: Storage and Handling of Crude Oil and Refinery Products.
Section B: Storage and Handling of Liquefied Petroleum Gases; LPG.
Section C: Liquefied Natural Gas LNG or NGL Storage and Transfer
Facilities.
Section D: Storage and Handling of Ethane and Ethylene.
Section E: Storing and Handling of Ethanol and Gasoline-Ethanol Blends.
Section F: Storing and Handling of Gasoline-Methanol/Cosolvent Blends.
Note:
This standard specification is reviewed and updated by the relevant technical committee on
July 2006. The approved modifications by T.C. were sent to IPS users as amendment No. 1
by circular No. 287 on July 2006. These modifications are included in the present issue of
IPS.
2. REFERENCES
Throughout this Standard the following dated and undated standards/codes are referred to. These
referenced documents shall, to the extent specified herein, form a part of this standard. For dated
references, the edition cited applies. The applicability of changes in dated references that occur
after the cited date shall be mutually agreed upon by the Company and the Vendor. For undated
references, the latest edition of the referenced documents (including any supplements and
amendments) applies.
API (AMERICAN PETROLEUM INSTITUTE)
API Recommended
Practice 520, Parts: I &
II, 7
th
Ed., 2000
"Sizing, Selection, and Installation of Pressure-Relieving
Devices in Refineries"
API RP 521
4
th
Ed., 1997
"Guide for Pressure-Relieving and Depressuring Systems"
API Standard 610
9
th
Ed., 2003
"Centrifugal Pumps for Petroleum, Petrochemical and
Natural Gas Industries"
API Standard 620
10
th
Ed., 2002
"Design and Construction of Large, Welded, Low Pressure
Storage Tanks"
API Standard 650
10
th
Ed., 1998
"Welded Steel Tanks for Oil Storage"
API Standard 2000
5
th
Ed., 1998
"Venting Atmospheric and Low-Pressure Storage Tanks:
Nonrefrigerated and Refrigerated"
Dec. 1997
IPS-E-PR-360
6
API Standard 2015
6
th
Ed., 2001
"Requirements for Safe Entry and Cleaning of Petroleum
Storage Tanks"
API Standard 2508
2
th
Ed., 1985
"Design and Construction of Ethane and Ethylene
Installations at Marine and Pipeline Terminals, Natural Gas
Processing Plants, Refineries, Petrochemicals Plants, and
Tank Farms"
API Standard 2510
8
th
Ed., 2001
"Design and Construction of LPG Installations"
API Recommended
Practice 1626 1
st
Ed. 1985
"Storing and Handling of Ethanol and Gasoline-ethanol
Blends at Distribution Terminals and Service Stations"
API Recommended
Practice 1627 1
st
Ed. 1986
"Storage and Handling of Gasoline-methanol/Cosolvent
Blends at Distribution Terminals and Service Stations"
API Recommended
Practice 2003 6
th
Ed. 1998
"Protection Against Ignitions Arising Out of Static, Lightning
and Stray Currents"
API Publication 2510A
2
nd
Ed., 1996
"Fire-Protection Considerations for the Design and Operation
of Liquefied Petroleum Gas (LPG) Storage Facilities"
API Publication 2015B
1
st
Ed., 1981
"Cleaning Open-Top and Covered Floating Roof Tanks"
BSI (BRITISH STANDARDS INSTITUTION)
BS 470
1984
"Specification for Inspection, Access and Entry Openings for
Pressure Vessels"
BS 2654:Part 3
1989
"Manufacturer of Vertical Steel Welded Non-Refrigerated
Storage Tanks with Butt-welded Shells for Petroleum
Industry"
BS 5429
Ed., 1988
"Code of Practice for Safe Operation of Small Scale Storage
Facilities for Cryogenic Liquids"
ASME (AMERICAN SOCIETY OF MECHANICAL ENGINEERS)
ASME B31.3
Ed. 1987
"Process Piping"
ASME B31.4
Ed. 1994
"LPG, Anhydrous Ammonia, Pipeline Transportation
Systems for Liquid hydrocarbons and other Liquids and
Alcohl"
ASME Codes, "Boiler and Pressure Vessels Codes"
Section VIII
Divisions 1 and 2
Dec. 1997
IPS-E-PR-360
7
NFPA (NATIONAL FIRE PROTECTION ASSOCIATION)
NFPA 30
Ed. 2000
"Flammable and Combustible Liquid Code"
NFPA Standard 59A,
Ed. 2001
"Standard for Production, Storage and Handling of LNG"
NFPA Vol. 2, 58
Ed., 2001
"Liquefied Petroleum Gas (LPG) Code"
UBC (UNIFORM BUILIDING CODE)
IP (INSTITUTE OF PETROLEUM, LONDON)
IP 10 (A)
July 1985
"Petroleum Measurement Manual", Part 10 : "Meter Proving
"
ISO (INTERNATIONAL ORGANIZATION FOR STANDARDIZATION)
ISO 91-2, "Petroleum Measurement Table"
1st. Ed., 1991
ISO 4266 "Direct Measurement of Level and Temperature in Storage Tank by
Ed. 1994 Automatic Methods"
IPS (IRANIAN PETROLEUM STANDARDS)
IPS-E-CE-500 "Loads"
IPS-E-GN-100 "Units"
IPS-G-ME-100 "Atmospheric Above Ground Welded Steel Storage Tanks"
IPS-E-ME-110 "Large Welded Low Pressure Storage Tanks"
IPS-E-ME-120 "Aviation Turbine Fuel Storage Tanks"
IPS-M-ME-110 "Large Welded Low Pressure Storage Tanks"
IPS-M-ME-120 "Aviation Turbine Fuel Storage Tanks"
IPS-E-PI-240 "Plant Piping Systems"
IPS-E-PM-100 "General Design Requirements of Machineries"
IPS-E-PR-190 "Layout and Spacing"
IPS-E-PR-450 "Process Design of Pressure Relieving Systems Inclusive
Safety Relief Valves"
IPS-E-PR-750 "Process Design of Compressors"
IPS-E-SF-200 "Fire Fighting Sprinkler Systems"
3. DEFINITIONS AND TERMINOLOGY
3.1 Design Pressure
The pressure used in design of equipment, a vessel or tank for the purpose of determining the
Dec. 1997
IPS-E-PR-360
8
minimum permissible thickness or physical characteristics of its different parts. When applicable
static head shall be included in the design pressure to determine the thickness of any specific part.
3.2 Dike
A structure used to establish an impounding area.
3.3 Liquefied Natural Gas (LNG)
A fluid in the liquid state composed predominantly of methane and which may contain minor
quantities of ethane, propane, nitrogen, or other components normally found in natural gas.
3.4 Liquefied Petroleum Gas (LPG or LP-Gas)
Any material in liquid form that is composed predominantly of any of the following hydrocarbons or
of a mixture thereof: propane, propylene, butanes (normal butane or isobutene), and butylenes.
3.5 Natural Gas Liquid (NGL)
A mixture of liquefied hydrocarbons extracted from natural gas by various methods to obtain a liquid
product.
3.6 Standard Condition
A temperature of 15C and a pressure of one atmosphere (101.325 kPa), which also is known as
Standard Temperature and Pressure (STP).
3.7 Vaporizer
A device other than a container which receives LP-Gas in liquid form and adds sufficient heat to
convert the liquid to a gaseous state.
3.7.1 Direct Vaporizer
A vaporizer in which heat furnished by a flame is directly applied to some form of heat exchange
surface in contact with the liquid LP-Gas to be vaporized.
3.7.2 Indirect Vaporizer
A vaporizer in which heat furnished by steam, hot water, the ground, surrounding air or other
heating medium is applied to a vaporizing chamber or to tubing, pipe coils, or other heat exchange
surface containing the liquid LP-Gas to be vaporized; the heating of the medium used being at a
point remote from the vaporizer.
4. SYMBOLS AND ABBREVIATIONS
GPA Gas Processors Association
LPG Liquefied Petroleum Gas
NGL Natural Gas Liquid
NPSH Net Positive Suction Head
OCMA Oil Companies, Material Association
OGP Oil, Gas and Petrochemical
RVP Reid Vapor Pressure
STP Standard Temperature and Pressure
Dec. 1997
IPS-E-PR-360
9
5. UNITS
This Standard is based on International System of Units (SI), as per IPS-E-GN-100 except where
otherwise specified.
SECTION A
6. STORAGE AND HANDLING OF CRUDE OIL AND REFINERY PRODUCTS
6.1 General
6.1.1 The requirements of this Section apply to the storage of crude oil and refinery products in
vertical cylindrical tanks and to storage tanks constructed of carbon steel, carbon manganese steel,
tanks constructed of carbon and alloy steels or tanks constructed of non-ferrous materials.
6.1.2 Crude oil and the refinery products should normally be stored as follows:-
a) Lighter refinery products with RVP79.3 kPa (abs) is preferably to be stored in pressure
vessels (e.g. spheres). However, where RVP of the lighter refinery products is exceeding
local atmospheric pressure, the type of storage shall be pressure vessel.
b) Aviation fuels shall be stored in a covered floating roof inside a fixed roof tank.
c) Crude oil, naphtha and kerosene and other hydrocarbons with closed flash points at or
below 45C, [except the cases covered in (a) and (b) above] should be stored in tanks fitted
with floating roofs.
d) Gas oils, diesel oils, lubricating oils, fuel oils and residues (with closed flash points above
45C) should be stored in tanks fitted with non-pressure fixed roof.
e) Exceptions to the above may occur, as for example with the storage of feed stock for
catalytic Units where, to prevent oxidation and ingress of moisture, the feed stock may be
stored in a fixed roof vertical cylindrical low pressure (21 mbar and/or 2.1 kPa) tank under a
gas blanket. Alternatively, a covered floating roof may be used in a fixed roof tank and in
this case a non-pressure tank may be used.
f) Exceptions may also occur where adverse climatic conditions such as heavy snowfalls,
preclude the use of floating roof type tanks. Fixed roof low pressure tanks (21 mbar and/or
2.1 kPa approximately), should be used in such cases.
g) For further requirement on the types of storage tanks see Clause 6.3.4.
6.2 Design Requirements
6.2.1 For engineering mechanical design the requirements of IPS Standard Specifications IPS-G-
ME-100, IPS-E-ME-110, IPS-E-ME-120 and for material selection IPS-M-ME-110, and IPS-M-ME-
120 should be considered.
6.2.2 Wind load
6.2.2.1 The design wind velocity shall be according to the requirements stipulated in IPS-E-CE-500.
6.2.3 Earthquake load
6.2.3.1 Earthquake load shall be specified in the job specification according to the latest edition of
Dec. 1997
IPS-E-PR-360
10
Uniform Building Code (UBC).
6.2.3.2 The sloshing effect due to product movement in the tank as a result of earthquake
movement shall be taken into account and calculations shall be submitted for the Companys
approval to ensure soundness of design.
6.2.4 Rainfall intensity
6.2.4.1 Rainfall intensity should be specified as per site condition and the tank shall be designed
accordingly except floating roof tanks. For this type of roof with the deck at its low position at
operating level with drain valve(s) closed and, assuming no pontoon compartment is punctured, the
deck support legs shall be designed to support the greater of the following loads:
a) Rainfall of 115 mm of water uniformly distributed all over the deck.
b) A live load as per project specification.
6.2.5 The snow load as specified in site conditions and incorporated in Paragraph 6.2.4.1.
6.2.6 When calculating for vacuum conditions during lowering of tank product in fixed roof tanks,
maximum gravity transfer conditions should also be considered.
6.3 Tank Dimensions, Capacities and Layout
6.3.1 General
6.3.1.1 Tanks should conform to the standard diameters listed in Table A.1 in Appendix A. In
selecting tank dimensions the highest tank compatible with permissible ground loading and
economic aspect should normally be chosen.
6.3.1.2 Working capacity
6.3.1.2.1 An approximation of the working capacity of tanks may be achieved by assuming a
negative capacity at the top of the tank of 500 mm height for floating roofs, and an ullage space in
fixed roofs of 150 mm. For fixed roof tanks the dead space at the bottom will extend to 150 mm
above the suction branch. For floating roof tanks the lowest position of the roof may be assumed to
be 300 mm above the suction branch. If, exceptionally, landing of the roof is permitted by the
Company during normal operation, the lowest position will be 150 mm above the suction branch.
6.3.1.2.2 The working capacity of each heated tank should be based on a minimum dip of 1 m
above the steam coil.
6.3.1.2.3 The actual allowances will depend on such factors as the position and size of outlet
branches, the position and type of pump, rate of pumping and type of level instrumentation.
6.3.2 Layout consideration
This Section covers the atmospheric storage and handling in refineries of crude petroleum and its
products, with the exception of bitumen handling and storage, LPG pressure and refrigerated
storage. The recommendations on tankage layout contained herein will normally apply to storage in
tanks outside block limits of refinery process Units. Crude oil terminals associated with production
are also covered by these recommendations.
The layout of tanks, as distinct from their spacing, shall take into consideration the accessibility
needed for fire-fighting and the potential value of a storage tank farm in providing a buffer area
between process plant and public roads, houses, etc. for environmental reasons.
Dec. 1997
IPS-E-PR-360
11
The location of tankage relative to process Units must be such as to ensure maximum safety from
possible incidents.
Primary requirements for the layout of refinery tank farms are summarized as follows:
1) Inter-tank spacings and separation distances between tank and boundary line and tank
and other facilities are of fundamental importance (see Table 1).
2) Access roadways should be provided for approach to tank sites by mobile fire-fighting
equipment and personnel.
3) The fire-water system should be laid out to provide adequate fire protection to all parts of
the storage area and the transfer facilities.
4) Bunding and draining of the area surrounding the tanks should be such that a spillage
from any tank can be controlled to minimize subsequent damage to the tank and its
contents. They should also minimize the possibility of other tanks being involved.
5) Tank farms should preferably not be located of higher levels than process Units in the
same catchment area.
6) Storage tanks holding flammable liquids should be installed in such a way that any spill
will not flow towards a process area or any other source of ignition.
6.3.3 Spacing of tanks for petroleum stocks
Table 1 gives guidance on the minimum tank spacing for petroleum stocks. The following points
should be noted:
1) Tanks of diameter up to 10 m are classed as Small Tanks.
2) Small Tanks may be sited together in groups, no group having an aggregate capacity of
more than 8000 m. Such a group may be regarded as one tank.
3) Where future changes of service of a storage tank are anticipated the layout and spacing
should be designed for the most stringent case.
4) For reasons of fire-fighting access there shall not be more than two rows of tanks
between adjacent access roads.
5) Fixed roof tanks with internal floating covers (see 6.3.4.3) should be treated for spacing
purposes as fixed roof tanks.
6) Where fixed roof and floating roof tanks are adjacent, spacing should be on the basis of
the tank(s) with the most stringent conditions.
7) Where tanks are erected on compressible soils the distance between adjacent tanks
should be sufficient to avoid excessive distortion. This can be caused by additional
settlements of the ground where the stressed soil zone of one tank overlaps that of the
adjacent tank.
8) For unclassified petroleum stocks, spacing of tanks is governed only by constructional
and operational convenience.
Figs. 1 to 4 show several typical tank installations, illustrating how the spacing guides are
interpreted.
Dec. 1997
IPS-E-PR-360
12
TABLE 1 - SPACING OF TANKS FOR PETROLEUM STOCKS
FACTOR
TYPE OF TANK ROOF
RECOMMENDED
MINIMUM DISTANCE
1
2
3
4
5
6
7
8
9
Within a group of Small Tanks.
Between a group of Small Tanks
and another group of Small Tanks
or other larger tanks.
Between adjacent individual tanks
(other than Small Tanks).
Between a tank and the top of the
inside of the wall of its compound.
Between any tank in a group of
tanks and the inside top of the
adjacent compound wall.
Between a tank and a public
boundary fence.
Between the top of the inside of the
wall of a tank compound and a
public boundary fence or any fixed
ignition source.
Between a tank and the battery limit
of a process plant.
Between the top of the inside of the
wall of a tank compound and the
battery limit of a process plant.
Fixed or floating
Fixed or floating
a) Fixed
b) Floating
Fixed or floating
Fixed or floating
Fixed or floating
---
Fixed or floating
---
Determined solely by
construction/maintenance/operational convenience.
10 m minimum, otherwise determined by the size of
the larger tanks (see 3 below).
Half the diameter of the larger tank, but not less than
10 m and need not be more than 15 m.
0.3 times the diameter of the larger tank,but not less
than 10 m and need not be more than 15 m*.
Distance equal to not less than half the height of the
tank. (Access around the tank at compound grade
level must be maintained.)
Not less than 15 m.
Not less than 30 m.
Not less than 15 m.
Not less than 30 m.
Not less than 15 m.
* In the case of crude oil tankage this 15 m option does not apply.
6.3.4 Types of storage tanks
Tanks must be built to design criteria that ensure physical integrity of the tank against all reasonably
expected forces such as tank contents, ground settlement or movement, wind and snow. Suitable
codes relating to the design and construction of tanks and their associated fittings are BS 2654 and
API Standard 650.
The main types of storage are as follows:
6.3.4.1 Floating roof tanks
Such tanks are generally used for liquids to minimize product loss and for safety and environmental
reasons. There is a preference for floating roof over fixed roof tanks as the size of the tank
increases, as the vapor pressure of the stored liquid increases, and when the flash point is below
the storage temperature.
The roof consists of an arrangement of buoyancy compartments (pontoons) and floats on the liquid.
It is sealed against the walls of the tank by mechanical means or by tubular type seals. The roof is
provided with support legs which can be adjusted to hold it in either of two positions. The upper
position should be high enough to permit access for tank cleaning and maintenance. The lower
position should keep the roof just above inlet and outlet nozzles, the drainage system, and other
accessories located near the tank bottom.
Floating roof tanks are normally equipped with rolling ladders. The tank shell is earthed and the roof
and all fittings, such as the rolling ladder, are adequately bonded to the shell as a protection against
Dec. 1997
IPS-E-PR-360
13
lightning. All internals such as gage floats, cables and mixers must also be suitably earthed to
prevent accumulation of electric charge.
6.3.4.2 Fixed roof tanks
Such tanks are generally used in refineries where the product stored does not readily vaporize at
the ambient or stored temperature conditions. The size of tank and flash point of the product stored
will also influence the choice of tank as noted in 6.3.4.1. These tanks are operated with a vapor
space above the liquid.
Depending on the materials to be stored, fixed roof tanks can be designed for storage at
atmospheric pressure in which case they are equipped with open vents. For materials, they can be
designed for pressures up to a maximum of about 50 mbar (5 kPa). Weak shell-to-roof welds can
be incorporated to give protection to the tank shell in the event of excessive internal pressure. They
are also designed for slight vacuum conditions not normally exceeding 6 mbar (0.6 kPa). Fixed roof
tanks should be adequately earthed as a protection against lightning.
6.3.4.3 Fixed roof tanks with internal floating covers
Such tanks can be used, for example, where:
a) snow loading on a floating roof may be a problem;
b) contamination by rainwater of the liquid stored in a floating roof tank is unacceptable;
c) there is an environmental or vapor loss problem with fixed roof tanks; or,
d) contact of the stored liquid with air should be avoided.
Pressure/vacuum valves or ventilating slits may be used. In the latter case vent outlets are required
in the upper ring of the tank shell and in the highest point of the fixed roof. This will assist in
reducing the gas concentration in the space between the fixed roof and the internal floating cover to
below the lower flammability limit. Such vent outlets should be constructed so as to prevent the
ingress of snow and rain. When screens are provided, the mesh opening should not be less than 6
mm square.
TANK AND COMPOUND WALL DISTANCES FROM TYPICAL FEATURES
Fig. 1
Dec. 1997
IPS-E-PR-360
14
Tanks A, B, C are fixed or floating roof small tanks
(less than 10 m diameter) with a total capacity of less
than 8000 m; no inter-tank spacing requirements other
than for construction/operation/maintenance conven-
ience.
Tank D1 and D2 are tanks with diameter greater than
10 m and with diameter of D2 greater than D1.
INTER-TANK SPACINGS BETWEEN
SMALL AND LARGER TANKS
Fig. 2
Floating roof tanks of diameter D1 D2 D3 greater than
10 m within the same compound. D1 greater than D2
and D2 greater than D3.
INTER-TANK SPACINGS FOR
FLOATING ROOF TANKS
(GREATER THAN 10 m DIAMETER)
Fig. 3
Fixed and floating roof thanks within the same compound, D1 greater than D2, D2 equal to D3.
INTER-TANK SPACINGS FOR FIXED AND FLOATING ROOF TANKS
(GREATER THAN 10 m DIAMETER)
Fig. 4
Key:
Fixed Roof
Floating Roof
Dec. 1997
IPS-E-PR-360
15
There has been some history of internal floating covers sinking in service; they should therefore be
carefully designed to minimize such a possibility. The internal floating cover should also be
designed to avoid fouling or obstruction of tank connections and of the fixed roof members and
should be electrically bonded to the main tank structure. The tank should be adequately earthed as
a protection against lightning. For further design details refer to API Bulletin 2519 and BS 2654.
6.4 Shell Attachments and Tank Appurtenances
For shell and roof design, reference is made to IPS-G-ME-100 and IPS-E-ME-110.
6.4.1 General
6.4.1.1 Shell attachments shall be designed in conformance with API Standard 650 and the
followings:
a) The orientation of the roof and shell fittings should permit the installed equipment to work
accurately and effectively. For example, the flow from a mixer should not be hindered
unduly by the siting of heaters.
b) The recommendations of ISO 4266 should be considered for automatic liquid level and
temperature measuring instruments on the storage tank.
6.4.2 Shell fittings
6.4.2.1 The checklist below covers tank shell fittings which may be required, but the number, type,
and size and location of fittings should be specified in design stage for each tank to the tank
fabricator.
6.4.2.1.1 Branches for tank contents such as:
Inlet, Outlet, Gas Blanket, Pumpout, Water Draw-Off, Jetting and Mixers.
6.4.2.1.2 Branch connections for services and maintenance such as:
Steam, Condensate, Foam (for Fire Fighting), Flush Type Clean Out Doors, Non-Flush
Clean Out Doors.
Note:
The last two, items are not normally fitted, but when they are required, the limitations
imposed by BS 2654 on shell design must be observed.
6.4.2.1.3 Branch for instruments such as:
Level Alarms, (high and low positions), Mixer Cut-Out, Float Switches, Thermowells as
required.
Note:
For fuel oil and slop tanks, thermowells should be located approximately 750 mm above the
heating element. For other tanks, the position should be agreed with the Company.
6.4.2.1.4 Other shell fittings such as:
Fire Fighting Water Spray, Manholes and Earthing Luges which shall be as API Standard
650.
Dec. 1997
IPS-E-PR-360
16
6.5 Fixed Roof Fittings
6.5.1 Manhole
6.5.1.1 One roof manhole of diameter 600 mm, should be provided for tanks 20 m diameter or less
and two for tanks over 20 m diameter.
6.5.2 Vents and relief valves
6.5.2.1 The number and size of vents provided shall be based on the venting capacity obtained
from the API Standard 2000 and should be sufficient to prevent any accumulation of pressure or
vacuum (including that arising from inert gas blanketing) exceeding the design conditions specified
for and approved by the Company.
6.5.2.2 For fixed roof low pressure tanks (20 mbar and/or 2 kPa) containing low flash point material
a pressure and vacuum type breather valve should be designed and provided upon the approval of
the Company. These valves should be fitted with a screen of appropriate mesh.
6.5.2.3 Pressure and vacuum relieving devices shall be designed in accordance with provisions of
API Standard 620 and requirements of 6.5.2.2 above.
6.5.2.4 For fixed roof non-pressure tanks containing high flash point material, which is never heated
above the flash point, free vents of the Company approved design should be provided. These free
vents should be fitted with screens of appropriate mesh. If however the contents of a fixed roof tank
are liable to be heated above the flash point then pressure and vacuum valves should be fitted.
6.5.3 Sample points on slops tankage
6.5.3.1 On tanks where liquid interfaces have to be determined, sample points operable from
ground level should be considered in design at appropriate vertical intervals. The points should be
discharged to a common oily drain; and where necessary, the system shall be heat traced to
prevent plugging.
6.5.4 Control instrumentation for slops tankage
6.5.4.1 Temperature
6.5.4.1.1 For heated tanks a multipoint high temperature (remote) alarm is required, with 6 sensing
points at suitable vertical intervals, the lowest being 750 mm above the steam coil. The alarm is to
operate in a permanently manned control room.
On the opposite side of the tank, a temperature sensing element is required 750 mm above the
steam coil, linked with the steam supply control and shut off valve. A separate thermowell with local
temperature indicator is also required at this point.
6.5.4.1.2 In the case of ballast tanks, as the steam coils are used only occasionally to aid sludge
removal, and for all unheated tanks, one local temperature indicator is sufficient.
6.5.4.2 Level
6.5.4.2.1 A local level indicator should be provided, and where the type of installation demands,
remote indication should in addition be considered. A high level (remote) alarm should operate in a
permanently manned control room.
6.5.5 Water drains
Floating roof tanks should be equipped with means for draining rainwater from the upper surface of
the roof. For pontoon-type roofs with internal articulated pipe drains a non-return valve should be
provided near the roof end to prevent backflow of stored product on to the roof in case of a leakage
in the jointed pipe.
Dec. 1997
IPS-E-PR-360
17
For double-deck type roofs this non-return valve is not necessary owing to the extra height of the
double roof, but an emergency roof drain should be fitted.
As an alternative to articulated pipes for draining water from tank roofs, internal flexible hoses are
also used. It is essential to ensure that the hoses cannot be trapped between the roof support legs
and the tank bottom.
All tanks should be fitted with a water draw-off sump and drain line leading to a valved outlet on the
tank shell, for removal of water accumulation inside the tank.
6.6 Floating Roof Fittings
6.6.1 Manholes
Manholes should be provided to permit entry to tanks, and to facilitate gas-freeing and tank cleaning
operations. Such manholes should be large enough to permit entry when full protective clothing is
worn. Reference should be made to BS 470 and API Standard 650. At least one manhole should be
provided in the lowest shell strake and one in the roof of a vertical tank. For tanks with diameters
greater than 25 m consideration should be given to providing a minimum of two manholes in the
lowest shell strake and two in the roof to facilitate tank ventilation for cleaning purposes.
6.6.1.1 600 mm diameter deck manholes should be provided for pontoon roofs, and 600 mm
diameter through manholes for double deck roofs.
6.6.1.2 One manhole should be fitted to roofs up to 20 m diameter and two for larger roofs.
6.6.1.3 One 500 mm diameter manhole should be provided for each pontoon compartment, unless
otherwise specified.
6.6.2 Vents
6.6.2.1 Automatic bleeder vents shall be used on all floating roof tanks. Size will be specified on
data sheet. Automatic bleeder vents should be made of stainless steel.
6.6.2.2 Vendor shall submit descriptive literature on the pressure vacuum vent valves, swing lines
with appurtenances and floating roof rim seals with his questions. Integral vacuum breakers and
pressure relief valves may be offered as an acceptable design.
6.6.2.3 The number of rim vents to be fitted to the roof is to be specified by the Vendor.
6.6.2.4 The Vendor should be informed of the maximum flow rates into and out of the tank to allow
him to determine the size and number of bleeder vents required.
6.6.3 Heaters
6.6.3.1 Tank heaters shall be exclusively of removable tube bundle type (whether finned or not) and
shall be approved by the Company. For bitumen storages only removable bear tube bundle shall be
used.
6.6.4 Drains
Emergency open type drains may be fitted if recommended by the Vendor/fabricator to double deck
type roofs or to pontoon roofs having more than 50% pontoon area. A drain plug should be provided
for use when taken out of service.
6.6.5 Arrangements for sampling and dipping
A tube DN 150 (6 inch) should be located at the gaging platform, for the combined purposes of leg
guide and dipping. A separate sample hatch DN 200 (8 inch) is required with appropriate drawing
approved by the Company, located under the gaging platform.
6.7 Safe Entry and Cleaning of Petroleum Storage Tank
6.7.1 All of the provisions regarding to safe entry and cleaning requirements given in API publication
2015 shall be considered in design of petroleum storage tanks. Provisions for cleaning of open-top
Dec. 1997
IPS-E-PR-360
18
and covered floating roof tanks as given in API publication 2015 B shall be considered for these
specific tanks.
6.8 Piping System
6.8.1 General
Piping system shall be designed in accordance with IPS-E-PI-240, "Plant Piping Systems" and the
following requirements:
6.8.1.1 Piping carrying crude oil and petroleum products should meet the requirements of ASME
Codes for process piping B31.3. For the piping located inside refinery/plant and ASME B31.4 for the
transportation pipelines outside refinery/plant.
6.8.1.2 Facilities should be provided on all pipelines to enable the lines to be pigged before
commissioning.
6.8.1.3 Thermal relief valves should be provided on each section of liquid filled pipeline, that could
be isolated between block valves.
6.8.1.4 Vent and drain connections should be provided where necessary for satisfactory
commissioning and operation.
6.8.1.5 Pipes and fittings supplied integrally with vessels, pumps and other equipment, may be to
suppliers standards when agreed with the Company.
6.8.1.6 Pipe sizes smaller than DN 15 ( inch) should not normally be used except for instruments.
The use of steel pipe in DN 32 (1 inch), DN 65 (2 inch), DN 90 (3 inch), DN 125 (5 inch), DN
175 (7 inch), DN 225 (9 inch) sizes should be avoided.
6.8.2 Piping layout
6.8.2.1 Provision should be made where necessary in piping system to prevent freezing or to
prevent difficulties resulting from high velocities, by following typical methods:
a) Heating may be external or internal tracing, jacketing or grouping with adjacent hot oil
lines.
b) Insulation.
c) Grading or sloping to permit complete draining.
d) Burying below frost line.
6.8.2.2 Where process lines need to be drained completely, the piping should be sloped and should
be provided with drainage points e.g.:
a) In multipurpose-lines;
b) Where hazardous or valuable liquids may be split during dismantling of pipe work;
c) Where there may be polymerization or settling of solids from liquids in the piping;
d) Where there may be contamination of pure products due to liquids standing in lines
subject to intermittent use.
6.8.2.3 Isolating valves/line blinds
Piping systems should contain a sufficient number of valves to enable each system to be operated
safely and efficiently. Such valves should enable the system to be shut down quickly in an
emergency, but without damage to equipment due to pressure surge. Where valves are not of the
rising stem type, they should embody a clear indication of the valve position.
Adequate access stairways or ladders, and operating platforms, where necessary, should be
provided to facilitate the manipulation of valves.
All nozzles, including drains on a tank shell should be provided with block valves adjacent to the
tank shell or as close as practicable. Where soft seated valves are present, they should be of fire-
safe quality.
Line blinds should be of a type which will indicate whether the line is blinded or open. A line blind
design allowing swinging of the blind without the necessity to drain the pipeline contents may be
considered.
Dec. 1997
IPS-E-PR-360
19
SECTION B
7. STORING AND HANDLING OF LIQUEFIED PETROLEUM GASES; LPG
7.1 General
7.1.1 The term liquefied petroleum gases (LPG or LP-Gas) as used in this Specification is to be
taken as applying to any material which is composed predominantly of any of the following
hydrocarbons or mixtures thereof: propane, propene, normal and isobutane, butenes.
7.2 Physical Properties and Characteristics
7.2.1 The composition of a specific grade of LPG product is not normally rigidly specified and thus,
product composition can vary from one particular refinery or petrochemical process plant to another,
hence, for process design requirement of LPG storage and handling facilities, the physical,
thermodynamic and other properties of the product should be specified in project specification.
7.2.2 LPG specification based on NIORDC's different refineries product is product is presented in
Appendix E. Noting that, whenever the words butane or propane appear hereafter, the commercial
of these products are intended. Pure and commercial products will be differentiated from one
another as necessary for design and installation of relevant storage and handling systems.
7.3 Requirements
7.3.1 Siting
7.3.1.1 General
7.3.1.1.1 Site selection is concerned with minimizing the potential risk to adjacent property
presented by the storage facility and the risk presented to the storage facility by a fire or explosion
on adjacent property.
The following factors should be considered during site selection:
a) Proximity to populated area;
b) Proximity to public ways;
c) Risk from adjacent facilities;
d) Storage quantities;
e) Present and predicted development of adjacent properties;
f) Topography of the site, including elevation and slope;
g) Access for emergency response;
h) Utilities;
i) Requirements for receipt and shipment of products;
j) Local code and regulations;
k) Prevailing wind conditions.
7.3.1.2 Above ground pressurized LPG tanks and equipment
7.3.1.2.1 Pressurized LPG tanks shall not be located within the building, within spill containment
area of flammable or combustible liquid storage tanks as determined in NFPA 30, or within the spill
contaminant area for refrigerated storage tanks.
Dec. 1997
IPS-E-PR-360
20
7.3.1.2.2 Rotating equipment and pumps taking suction from the LPG tanks shall not be located
within the spill contaminant area of any storage facility. Unless provisions are made to protect the
storage vessel from potential fire exposure.
7.3.1.2.3 Horizontal vessels used to store LPG should be oriented so that their longitudinal axes do
not point toward other containers, process equipment, control rooms, loading and unloading
facilities, or flammable or combustible liquid storage facilities located in the vicinity of the horizontal
vessel.
7.3.1.2.4 Horizontal vessels used to store LPG with the capacity of 50 m
3
and more should be
grouped with no more than six vessels in one group. Where multiple groups of horizontal LPG
vessels are to be provided, each group should be separated from adjacent groups by minimum
horizontal shell-to-shell distance of 15 m.
7.3.2 Layout and spacing
7.3.2.1 General
7.3.2.1.1 Spacing and design of LPG facilities are interdependent and must be considered together.
Spacing requirement used shall be in accordance with IPS-E-PR-190. However the requirements
specified in 7.3.2.1.2 in the Clause 7.3.2 shall also be considered in addition and/or as an
amendment to IPS-E-PR-190 (see Note 1).
7.3.2.1.2 Spacing should be sufficient to minimize both the potential for small leak ignition and the
exposure risk to adjacent vessels, equipment or installations should ignition occur.
Note 1:
A typical lay-outs are illustrated in Appendices A and B. These illustrate the slope of tank
sites, the location of vessels with respect to each other, the positioning of separation wall,
when necessary, and manifolds with respect to vessels.
7.3.2.2 Minimum distance requirement for above ground LPG tanks
The minimum horizontal distance between shell of a pressurized LPG tanks and the line of
adjoining property that may be developed shall be as specifically given in API Standard 2510 under
Clause 5.1.2.
7.3.3 Type and size of storage vessels
7.3.3.1 The type, size and number of vessels to be used must be based on operational
requirements and technical/economical considerations. The following is given as guidance for the
types normally used and the size limitations generally applicable to them.
a) Horizontal vessels which can in many instances shop fabricated, and move to site in one
piece, are normally used for unit capacities up to 200 m.
b) Vertical cylindrical vessels have an advantage to horizontal vessels in that they require
less space for a specific capacity. They are normally limited in size to a maximum of 10 m
diameter and 25 m height.
c) Spherical vessels (spheres) are normally considered if the unit capacity exceeds 400 m.
7.3.4 Spill containment
7.3.4.1 Spill containment should be provided in locations in which any of the following conditions
exist:
Dec. 1997
IPS-E-PR-360
21
a) The physical properties of the stored LPG (for example, a mixture of butane and
pentane) make it likely that liquid material will collect on the ground.
b) Climatic conditions during portions of the year make it likely that liquid material collect on
the ground.
c) The quantity of material that can be spilled is large enough that any unvaporized material
will result in a significant hazard.
7.3.4.2 If spill containment is to be provided, it shall be remote impoundment of spilled material or
by diking the area surrounding the vessel.
7.3.4.3 The pronounced volatility of LPG generally allows impoundment areas to be reduced and in
some cases makes spill containment of LPG impractical. However, the ground and surrounding of a
vessel used to store LPG shall be graded to drain any spills to a safe area away from the vessel.
7.3.4.4 All provisions under Clause 3.2 of API Standard 2510 regarding to establishment of spill
containment facilities for LPG storage vessels shall be considered as an integral part of this
Standard Specification in design and installation of LPG storage vessels.
7.4 Design Considerations
7.4.1 Storage vessels
7.4.1.1 Design code
7.4.1.1.1 Vessels design shall meet the requirements of Section VIII of the ASME Boiler and
Pressure Vessel Code (commonly called the ASME Code), Division 1 or 2.
7.4.1.1.2 When complete rules and design requirement for any specific design are not given, the
manufacturer, subject to the approval of the Company, shall provide a design as safe as would be
provided in the currently applicable ASME Code given in 7.4.1.1.1 above.
7.4.1.2 Design pressure
7.4.1.2.1 It is assumed that, the maximum operating pressure at the top of a vessel is equivalent to
the vapor pressure of the product being handled at the maximum temperature that the vessels
contents may reach under prolonged exposure of the vessel to solar radiation "the assessed
temperature".
7.4.1.2.2 The design pressure to be used for the top of the vessel shall be equal to the greater of :
a) 110% of the maximum operating pressure;
b) the maximum operating pressure plus 170 kPa (1.7 kg/cm).
7.4.1.2.3 The design pressure to be used for the bottom of the vessel shall be that of 7.4.1.2.2
above for the top of the vessel plus the static head of the content.
7.4.1.3 Design vacuum
7.4.1.3.1 LPG storage vessel design shall consider vacuum effects. Where an LPG vessel is not
designed for full vacuum,some alternatives, in order of preference, are as follows:
a) Design for partial vacuum with a vacuum relief valve and a connection to a reliable
supply of inert gas. This alternative requires a means of venting inert gas that has been
admitted to the storage vessel after it is no longer required for maintaining pressure.
b) Design for partial vacuum with a vacuum relief valve and a connection to a reliable
supply of hydrocarbon gas. This alternative may compromise product quality.
c) Design for partial vacuum with a vacuum relief valve that admits air to the vessel. This
alternative presents a hazard from air in the LPG storage vessel, and this hazard shall be
considered in the design.
Dec. 1997
IPS-E-PR-360
22
7.4.1.4 Design temperature
7.4.1.4.1 Both a minimum and a maximum design temperature should be specified. In determining
a maximum design temperature, consideration should be given to factors such as ambient
temperature, solar input, and product run down temperature. In determining a minimum design
temperature, consideration should be given to the factors in the preceding sentence plus the auto
refrigeration temperature of the stored product when it flashes to atmospheric pressure.
7.4.1.5 Filling and discharge line
7.4.1.5.1 Only one product line shall be connected to the bottom of the vessel and this line shall be
used for filling, discharge and drainage. However operational considerations may dictate the use of
a separate top connected filling line.
7.4.1.5.2 To enable complete drainage of the vessel, the connection of the bottom line to the vessel
shall be made flush with the inside of the vessel. A typical arrangement of the drain connection to
the bottom line is given in Appendix C.
7.4.1.5.3 Top connected filling and vapor lines shall be provided with a remote-controlled fail-safe
type shut-off valve if the line extends below the maximum liquid level, otherwise a shut-off valve
plus either a non-return valve or an excess flow valve may be used.
7.4.1.5.4 The product line connected to the bottom of the vessel shall be provided with either:
a) A remote-controlled fail-safe type shut-off valve located at the manifold side of the
separation wall between manifold and vessel. This line is to have a minimum size of DN
100 and should be of Schedule 80 for DN 100 size and Schedule 40 for DN 150 and larger.
A hand-operated fire-safe valve should be provided between the remote controlled valve
and the manifold separation wall if it is considered necessary;
b) A remote-controlled failed-safe type valve mounted internally in the vessel. Design
consideration should be given to the possibility/practicability of emptying the vessel in the
case of malfunctioning of the remote controlled valve. If considered necessary a by-pass
line connected to the vessel shall be provided with a shut-off valve and shall be blanked.
7.4.1.5.5 Piping connections between container and manifold shall be designed to provide adequate
allowances for construction, expansion, vibration, and settlement. In this regard, NFPA
requirements under Clause 4.3 shall be considered.
7.4.1.5.6 Other considerations for piping design should be taken as per requirements specified in
API Publication 2510A paragraph 2.7.1 and API Standard 2510 section 8.
7.4.1.6 Water drawing
7.4.1.6.1 Water can accumulate under certain conditions in LPG storage vessels and must be
removed for product quality reasons. Also, in Freezing climates, ice formation in bottom connections
can rupture piping and lead to major LPG releases. Thus facilities shall be provided and procedures
shall be established to handle water draw-off safely.
7.4.1.6.2 Considering the potential risk associated with improper handling of water removal, a
detailed written procedure should be prepared and rigidly followed. The procedure outlined in API
Publication 2510A under Paragraphs 3.4.4.1 through 3.4.4.3 is recommended to be considered
during the entire process of water removal.
Dec. 1997
IPS-E-PR-360
23
7.4.1.7 Safety/relief valves
7.4.1.7.1 LPG storage vessels shall be adequately protected by safety/relief valves directly
connected to the vapor space of the vessel. Safety/relief valves shall be provided to protect against:
a) overpressurization due to abnormal operational conditions, e.g., overfilling, high run-
down temperatures or high temperature due to solar radiation;
b) overpressurization due to fire exposure.
7.4.1.7.2 Consideration should be given to the provision of a spare safety/relief valve or connection
such that to facilitate servicing/maintenance of safety/relief valves.
7.4.1.7.3 The materials used for safety/relief valves including components, e.g., springs, valve
discs, must be suitable for use with LPG and for operation at low temperatures.
7.4.1.7.4 Pressure relief valves installed on the LPG storage vessels shall be designed to protect
the vessels during fire exposure. Other causes of tank over pressure, such as overfilling and
introduction of material with a higher vapor pressure in a common piping system, shall be
considered.
7.4.1.7.5 Pressure relief valves shall be designed and sized in accordance with IPS-E-PR-450 and
API Recommended Practice 520, Part 1 and API Recommended Practice 521.
7.4.1.7.6 All safety provisions given by NFPA 58 Chapter 2 under paragraph 2.3.2 and applicable to
spring-loaded safety relief valves installation on LPG storage vessels shall be considered to the
extent of process design requirements.
7.4.1.7.7 When a closed relief system is used all applicable points of API Publication 2510 A, under
Paragraph 2.10.3 shall strictly be considered in process design of the system. Atmospheric relief
system if proposed in project specification, requirements of API Publication 2510 A, under
Paragraph 2.10.2 shall essentially be taken account in process design of such system.
7.4.1.7.8 Tanks that may be damaged by internal vacuum shall be provided with at least one
vacuum relieving device set to open at not less than the partial vacuum design pressure.
7.4.1.7.9 When a closed inner tank design is used with an outer vapor-tight shell, the outer shell
shall be equipped with a pressure and vacuum relieving device or devices.
7.4.1.8 LPG tanks other accessories
7.4.1.8.1 Sampling connections
7.4.1.8.1.1 If sampling connections are required, they shall be installed on the thank piping rather
than on the tank. Sampling provisions given in API Publication 2510A under Paragraph 3.5 shall to
the extent of process design requirements be considered.
7.4.1.8.2 Accessory equipment and shut-off valves
7.4.1.8.2.1 Accessory equipment and shutoff valves shall be designed to meet extreme operating
pressure and temperature.
7.4.1.8.3 Liquid level gaging device
7.4.1.8.3.1 Each non-refrigerated storage vessel shall be equipped with a liquid level gaging device
of approved design. If the liquid level gaging device is a float type or a pressure differential type and
the vessel is a non-refrigerated type, the vessel shall also be provided with an auxiliary gaging
device, such as a fixed dip tube, slip tube, rotary gage, or similar device.
7.4.1.8.3.2 Refrigerated LPG storage vessels shall be equipped with a liquid level gaging device of
approved design. An auxiliary gaging device is not required for refrigerated storage vessels.
However, in lieu of an auxiliary gage, refrigerated vessels, if subject to overfilling, shall be equipped
Dec. 1997
IPS-E-PR-360
24
with an automatic device to interrupt filling of the tank when the maximum filling level is reached.
7.4.1.8.3.3 All other safety requirements relating to liquid level gaging specified in NFPA 58 under
Paragraph 3.4.3.3 through 4.4.3.4 and Paragraph 2.3.4 shall be considered.
7.4.1.8.4 Venting non-condensibles
7.4.1.8.4.1 Non-condensible gases, including air, can enter to a LPG storage vessel through a
variety of means including the following:
a) Desolved or entrained gases from processing, such as sweetening.
b) Operation of vacuum breakers.
c) System leaks while under vacuum.
d) Air or inert gas in a vessel when it is put into service.
e) Vapor return lines from trucks or rail cars that contain air or inert gas prior to loading.
7.4.1.8.4.2 The gases may cause the relief valve to operate when the liquid level is subsequently
raised and the noncondensible gases are thereby compressed.
7.4.1.8.4.3 Criteria should be developed to vent the compressed non-consibles periodically when
the oxygen concentration exceeds a specified value or when the head-space pressure exceeds the
product vapor pressure by a specified amount.
7.4.1.8.4.4 The non-condensibles may be vented to air. If regulations require venting to a flare
system, then caution is necessary, since the vented gas may contain air. In these cases
precautions shall be taken to prevent sending a flammable mixture to the flare.
7.4.1.8.5 Drain facilities
7.4.1.8.5.1 A drain connection shall be provided on the filling/discharge line at the manifold side of
the first shut-off valve (manual or remote-controlled).
7.4.1.8.5.2 If in exceptional cases a drain connection on the storage vessel is unavoidable,
Companys prior approval should be obtained in order to agree on an acceptable design of drainage
system.
7.4.1.8.5.3 The outlet of the drain line, where flammable vapor can be released, should be
discharged at a safe point, i.e., away from roads, working areas, etc.
7.4.1.8.5.4 At locations where freezing conditions can occur, the drain facilities shall be adequately
traced and insulated. Insulation and possibly, tracing of the filling/discharge line may also be
necessary.
7.4.1.8.5.5 Operational rules for drainage should be given in operating manual or as an instruction
to drainage procedure.
7.4.2 Refrigeration system
7.4.2.1 Load
The refrigeration load should take into consideration the following factors:
a) Heat flow from the following sources:
1) The difference between the design ambient and storage temperatures.
2) Maximum solar radiation.
3) Receipt of product that is warmer than the design temperature, if such an
operation is expected.
4) Foundation heaters.
5) Heat absorbed through connected piping.
b) Vapor displaced during filling or returned during product transfer.
c) Changes in barometric pressure.
Dec. 1997
IPS-E-PR-360
25
7.4.2.2 Vapor handling
7.4.2.2.1 The vapor load resulting from refrigeration may be handled by one or a combination of the
following methods:
a) Recovery by a liquefaction system.
b) Use as fuel.
c) Use as process feedstock.
d) Disposal by flaring or another safe method.
Alternative handling methods shall be provided to dispose of vented vapors in case of failure of the
normal methods. If compressors are used, castings shall be designed to withstand a suction
pressure of at least 121 percent of the tank design pressure.
7.4.2.3 System accessories
7.4.2.3.1 A refrigerated LPG system shall contain the following accessories:
a) An entrainment separator in the compressor suction line.
b) An oil separator in the compressor discharges line (unless the compressor is a dry type).
c) A drain and a gaging device for each separator.
d) A non-condensible gas purge for the condenser.
e) Automatic compressor controls and emergency alarms to signal:
1) When tank pressures approach the maximum or minimum allowable tank
working pressure or the pressure at which the vacuum vent will open, or
2) When excess pressure builds up at the condenser because of failure of the
cooling medium.
7.4.2.4 Pressure relieving devices
7.4.2.4.1 Refer to IPS-E-PR-450 and API Recommended Practice 520, Parts I and II, for the proper
design of pressure relieving devices and systems for process equipment used in liquefaction and
vaporization facilities.
7.4.3 Pumps
7.4.3.1 Centrifugal or positive displacement pumps may be used for LPG service. The pumps
should be able to operate at a low NPSH.
7.4.3.2 In process design of pumps reference is made to IPS-E-PM-100.
7.4.3.3 Centrifugal and rotary positive displacement pumps shall be equipped with mechanical
seals. Consideration should be given to the use of auxiliary glands.
7.4.3.4 If centrifugal pump is used, a return line connecting the discharge with the suction side of
the pump might be installed. The flow through this return line should be 10-30% of the design flow
of the pump at its highest efficiency.
7.4.3.5 Positive displacement pumps if are used, shall be safeguarded by a differential relief valve
in a return line from discharge to suction side. The return line shall be designed for of the designed
capacity of the pump.
7.4.3.6 Return line should either run back to the suction line of the pump or to the vapor space of
the supplying storage vessel.
7.4.3.7 Centrifugal pumps shall be provided with a vent in order to remove any accumulated vapor
before the pump started. This vent shall be connected to the vapor space of the storage vessel or
vent to atmosphere at a safe place.
Dec. 1997
IPS-E-PR-360
26
7.4.4 Fire protection facilities
7.4.4.1 Provisions given in API Standard 2510 and the API Publication 2510A as an amendment to
API Standard 2510, Section 10 shall be subject to verification or modification through analysis of
local conditions and used for process design of an efficient and perfectly reliable protection facilities.
7.4.4.2 For water sprinkler systems see IPS-E-SF-200, "Fire Fighting Sprinkler Systems".
7.4.5 Piping
7.4.5.1 All applicable portions of API Standard 2510 Section 8 shall be followed in process design of
piping.
Other considerations for piping process design are those relating parts given in API Publication
2510A under Paragraph 2.7.
7.4.6 Vaporizers
7.4.6.1 General
7.4.6.1.1 Liquefied petroleum gases are used in gaseous form. A vaporizer is required when the
heat transferred to the liquid is inadequate to vaporize sufficient gas for maximum demand. A
steam, hot water, or direct fired type vaporizer may be used.
7.4.6.1.2 A vaporizer should be equipped with an automatic means of preventing liquid passing
from vaporizer to gas discharge piping. Normally this is done by a liquid level controller and positive
shutoff of liquid inlet line or by a temperature control unit for shutting off line at low temperature
conditions within vaporizer.
7.4.6.1.3 Some installations operate on "Flash Vaporization". Whereby the liquid is converted to a
gas as soon as it enters the vaporizer, while others maintain a liquid level in the vaporizer.
7.4.6.2 Indirect vaporizers
7.4.6.2.1 Indirect vaporizers shall comply with Clause 2.5.5.1(a) through (d) of NFPA 58 and the
followings:
a) A shutoff valve shall be installed on the liquid line to the LPG vaporizer Unit at least 15
meters away from the vaporizer building.
b) The heating medium lines into and leaving the vaporizer shall be provided with suitable
means for preventing the flow of gas into the heat systems in the event of tube rupture in
the vaporizer. Vaporizers shall be provided with suitable automatic means to prevent liquid
passing from the vaporizer to the gas discharge piping.
c) The device that supplies the necessary heat for producing steam, hot water, or other
heating medium shall be separated from all compartments or rooms containing liquefied
petroleum gas vaporizers, pumps, and central gas mixing devices by a wall of substantially
fire resistant material and vapor-tight construction.
7.4.6.3 Direct fired vaporizers
7.4.6.3.1 Direct fired vaporizers shall be designed in full conformity with requirements given in
NFPA 58 under Paragraph 2.5.2 (a) to (f).
Dec. 1997
IPS-E-PR-360
27
7.4.7 Instrumentation
7.4.7.1 As a minimum, the requirements in API Standard 2510, Section 7 shall be followed. In
addition, the considerations given in 2.9.1 through 2.9.5 of API Publication 2510A to the extent
applicable to process design shall be considered.
7.5 Transfer of LPG Within the Off-Site Facilities of OGP Plants
7.5.1 General
7.5.1.1 LPG as in liquid form is permitted to be transferred from storage vessels by liquid pump or
by pressure differential.
7.5.1.2 Pressure differential may be used under certain conditions. Fuel gas or inert gas which is at
a higher pressure than of LP gas shall be used under following conditions:
a) Adequate precautions shall be taken to prevent liquefied petroleum gas from flowing
back into the fuel gas or inert gas line or system by installing two back flow check valves in
series in these lines at the point where they connect into the liquefied petroleum gas
system. In addition, a manually operated positive shutoff valve shall be installed at this
point.
b) Any fuel gas or inert gas used to obtain a pressure differential to move liquid LPG shall
be non-corrosive and dried to avoid stoppage by freezing.
c) Transfer operations shall be conducted by competent trained personnel.
d) Unloading piping or hoses shall be provided with suitable bleeder valves or other means
for relieving pressure before disconnection.
e) Precaution shall be exercised to assure that only those gases for which the system is
designed, examined, and listed are employed in its operation, particularly with regard to
pressure.
7.5.2 Requirements
7.5.2.1 The transfer system shall incorporate a means for rapidly and positively stopping the flow in
an emergency. Transfer systems shall be designed to prevent dangerous surge pressures when the
flow in either direction is stopped.
7.5.2.2 Transfer pumps may be centrifugal, reciprocating, gear or another type designed for
handling LPG. The design pressure and construction material of the pumps shall be capable of
safely withstanding the maximum pressure that could be developed by the product, the transfer
equipment, or both.
7.5.2.3 All process design requirements under Clause 7.4.3 of this Standard Specification shall be
considered when centrifugal or positive displacement pumps are used.
7.5.2.4 Provisions relating to process design requirements of a LPG transfer, loading and unloading
facilities given in API Standard 2510, under Paragraph 9, is considered as integral part of this
Standard Specification in Section B.
7.5.2.5 All safety considerations deemed necessary to be specified in process design of LPG
transfer facilities shall be in conformity with NFPA 58.
Dec. 1997
IPS-E-PR-360
28
SECTION C
8. LIQUEFIED NATURAL GAS (LNG); STORAGE AND TRANSFER FACILITIES
8.1 Introduction
Liquefied Natural Gas or (LNG) occupies about 1/600 the of its gaseous volume at Standard
Conditions. LNG main constituents, methane (CH
4
) and ethane (C
2
H
6
) in which methane
predominates, can not be liquefied by pressure alone, since the critical temperature of these gases
is well below ordinary ambient temperature, and some pre-cooling is therefore necessary before
they can be liquefied by pressure.
8.2 General Considerations
8.2.1 Physical properties
8.2.1.1 The properties of natural gas and LNG are similar to those of methane, although the
presence of other constituents should be taken into account.
8.2.1.2 Above -113C, methane vapor is lighter than air. The flammable range for methane is 5% to
15% by volume in air, which is wider than for most other gaseous fuels. The lower flammable limit
(5%) and the ignition temperature (632C) are higher than for other fuels.
8.2.2 Spacing and diking
8.2.2.1 In addition to API Standard 620, Appendix Q, NFPA 59-A, IPS-E-PR-190, and the governing
Local Regulations (if any), the following factors shall also be considered for spacing, diking and
impounding of LNG storage tank(s) and other process equipment.
a) The tank(s) shall be located as far as possible from dwelling areas or locations where
large numbers of people are working.
b) The tank(s) should have good access from at least two directions, so that fires can be
handled if they should occur.
c) Necessary impounding and diking design and capacity should be in full conformity with
Paragraph 2.2.2 of NFPA 59A. However, other methods of diking including natural
topography, steel structural dikes, pre-stressed concrete dikes and a conventional earthen
dike using a LNG collection sump within the dike area should be consulted with the
Company and used upon his approval.
d) The degree to which the facilities can, within limits of practicality, be protected against
forces of nature.
e) The area around natural gas installation should be kept free from vegetation and other
combustible materials. Smoking should be strictly prohibited in the vicinity of the storage
facility and suitable warning notices displayed.
f) Adequate arrangements for dealing with fire and larger spillages should be made.
Instruction and emergency procedure for fire fighting, should be given and regularly
practiced. For fire and fire fighting reference shall also be made to BS 5429.
8.3 Criteria and Requirements
8.3.1 Cryogenic process system
8.3.1.1 General
8.3.1.1.1 Process system equipment containing LNG, flammable refrigerants or flammable gases
Dec. 1997
IPS-E-PR-360
29
shall be either:
a) Installed outdoors for ease of operation, safe disposal of accidentally released liquids
and gases, or;
b) Installed indoors in enclosing structures complying with NFPA 59A, Paragraphs 2.3.2
and 2.3.3.
8.3.1.2 Pumps and compressors
8.3.1.2.1 Pumps and compressors shall be designed for materials suitable for the temperature and
pressure conditions.
8.3.1.2.2 Isolating valves shall be installed so that each pump or compressor can be isolated for
maintenance. Pumps or centrifugal compressors discharge lines shall be equipped with check
valves.
8.3.1.2.3 Pressure relieving device on the discharge to limit the pressure to maximum safe working
pressure of the casing and downstream piping shall be provided.
8.3.1.2.4 The foundations and sumps for cryogenic pumps shall be designed to prevent frost
heaving.
8.3.1.2.5 Pumps used for transfer of LNG at temperature below -30C shall be provided with
suitable means for precooling to reduce effect of thermal shock.
8.3.1.2.6 Compression equipment handling flammable gases shall be provided with vents from all
points, including distance pieces. Vents shall be piped to a point of safe disposal.
8.3.1.2.7 Not contrary with above, applicable process design requirement in IPS-E-PR-750 shall be
considered for compressor design respectively.
8.3.1.3 Storage tanks
8.3.1.3.1 Process design of storage tanks of LNG and refrigerants shall comply with requirements
under Section B of this Standard Specification and API Standard 2510 and applicable portions of
NFPA 59A, Paragraph 3.3.
8.3.1.3.2 The following should essentially be determined for design:
a) Purpose of the storage i.e., peak shaving or base load;
b) Volumetric capacity;
c) LNG properties;
d) Operating temperature minimum and maximum;
e) Operating and design pressure;
f) Barometric data for sizing relief valve;
g) External loading;
h) Evaporation rate.
8.3.1.3.3 Storage tanks may use internal or external pumps. If internal pumps are used, all
connections are made in the roof. When external pumps are used, bottom connection shall be
made.
8.3.1.3.4 In order to avoid LNG from falling or pouring to the bottom, a tank cooled-down line
connected to a sprayrig should be inside at the top of the tank.
8.3.1.3.5 Liquid fill lines may be designed for installation at top, bottom or both.
8.3.1.3.6 In order to provide positive suction head, the tank foundation should be elevated to an
appropriate level.
Dec. 1997
IPS-E-PR-360
30
8.3.1.3.7 Insulation
8.3.1.3.7.1 Insulation of low temperature installations in general and refrigerated LNG storage tanks
in particular is one of the most critical areas of low temperature storage design.
The selection of any of the following methods:
a) High vacuum.
b) Multiple layer.
c) Power.
d) Rigid foam.
Should carefully be studied with specific concern to the capacity of the tank, the temperature,
economic and safety requirements.
8.3.1.3.7.2 Any exposed insulation shall be non-combustible, shall contain or inherently shall be a
vapor barrier, shall be water free, and shall resist dislodgment by fire hose streams. When an outer
shell is used to retain loose insulation, the shell shall be constructed of steel or concrete.
8.3.1.3.7.3 The space between the inner tank and the outer tank shall contain insulation that is
compatible with LNG and natural gas and is non-combustible. The insulation shall be such that a
fire external to the outer tank will not cause significant deterioration to the insulation thermal
conductivity by melting, setting etc.
8.3.1.3.8 Relief devices
8.3.1.3.8.1 The LNG storage tank shall be protected when overpressured by safety relief valve(s)
providing an effective rate of discharge. The minimum required rate of discharge shall be
determined so as to prevent pressures exceeding those allowed by the governing code giving
proper consideration to fire exposure, process upsets or loss of product.
8.3.1.3.8.2 Sizing, locating, installing of necessary relieving devices shall be in accordance with
provision of API Standard 620, Appendix N therein. Safety requirement under Paragraph 4.7 of
NFPA Standard 59A, shall also be considered for applicable portions in process design.
8.3.1.3.9 Instrumentation
8.3.1.3.9.1 Each LNG storage tank shall be equipped with an adequate liquid level gaging device.
Density variations shall be considered in the selection of the gaging device. Considerations shall be
given to a secondary or backup gaging. At least one of these gages shall be replaceable without
taking the tank out of operation.
8.3.1.3.9.2 The storage tank shall be provided with a high-liquid level alarm which shall be separate
from the liquid level gaging device.
8.3.1.3.9.3 Each tank shall be equipped with a pressure gage connected to the tank at a point
above the maximum intended liquid level.
8.3.1.3.9.4 Vacuum-jacketed tank shall be equipped with instruments or connections for checking
the absolute pressure in the annular space.
8.3.1.3.9.5 Temperature monitoring devices shall be provided in field erected storage tanks to assist
in controlling temperatures when placing the tanks into service or as a method of checking and
calibrating liquid level gages.
8.3.1.3.9.6 In addition to requirements of 8.3.1.3.9 above, all instrumentation requirement given in
Section B for storage tanks of LPG shall also be considered as minimum requirement for LNG
tanks.
Dec. 1997
IPS-E-PR-360
31
8.3.1.3.10 Other requirements
8.3.1.3.10.1 To control corrosion rate in the specified level for the tank if the bottom of the tank rests
directly on the ground, appropriate cathodic protection should be established, if required in the
project specification.
8.3.1.3.10.2 All tanks in which water might accumulate under the hydrocarbon contents shall be
provided with adequate drains that are suitably protected from freezing.
8.3.1.3.10.3 All openings and accessories for tanks constructed according to this Standard shall be
installed so that any period checking, inspection, cleaning etc., can readily be made.
8.3.1.4 Piping system design requirements
8.3.1.4.1 All piping systems shall be designed in accordance with ANSI/ASME B31.4. The
additional provisions as given hereunder shall be applicable to pressurized piping systems and
components for LNG, flammable refrigerants, flammable liquids and gases or low pressure piping
systems including vent lines and drain lines which handle LNG, flammable refrigerants, with service
temperatures below -30C.
8.3.1.4.2 Piping systems and components shall be designed to accommodate the effects of fatigue
resulting from the thermal cycling to which the systems will be subjected. Particular consideration
shall be given where changes in size or wall thickness occur between pipes, fittings, valves and
components.
8.3.1.4.3 Provision for expansion and contraction of piping and piping joints due to temperature
changes shall be in accordance with Clause 319 of ASME B31.3.
8.3.1.4.4 All piping materials including gaskets and thread compounds, shall be suitably used with
the liquids and gases handled throughout the range of temperatures to which they will be subjected.
The temperature limitations for pipe materials shall be as specified in ASME B31.3.
8.3.1.4.5 Safety requirements for piping process design as given in Chapter 6 of NFPA, 59A shall
be considered.
8.4 Transfer of LNG and Refrigerants
8.4.1 General requirements
8.4.1.1 Transfer facilities shall comply in process design requirements and criteria with appropriate
provisions elsewhere in this Standard, such as those applying to siting, piping and instrumentation,
safety considerations as well as the following specific provisions:
8.4.1.1.1 When making bulk transfers into stationary storage tanks, the LNG being transferred shall
be:
a) compatible in composition or temperature and density with that already in the container,
or;
b) when the composition or temperature and density are not compatible, instruction shall be
given in operating manual to prevent stratification which might result in "roll over" and an
excessive rate of vapor evolution;
c) stratification can be prevented by means such as: introducing the denser liquid above the
surface of the stored liquid, introducing mechanical agitation, or introducing the LNG into
the tank through an inlet nozzle designed to promote mixing. If agitation system or mixing
nozzle is provided it shall be designed for sufficient energy to accomplish its purpose.
Dec. 1997
IPS-E-PR-360
32
8.4.2 Piping system
8.4.2.1 Isolating valves shall be installed so that each transfer system can be isolated at its
extremities.
8.4.2.2 When power operated isolating valves are used, a design analysis should be made to
determine that the closure time will not produce a hydraulic shock capable of causing line or
equipment failure.
8.4.2.3 Check valves shall be provided as required in transfer systems to prevent backflow and
shall be located as close as practical to the point of connection to any system from which backflow
might occur.
8.4.2.4 A piping system used for periodic transfer of cold LNG, shall be provided with suitable
means for pre-cooling before use.
8.4.2.5 All applicable provisions to process design of LNG transfer system given under Chapter 8,
of NFPA, 59A shall be considered as an integral part of requirements of this Section.
8.5 Fire Protection
8.5.1 Fire protection system shall be considered for all LNG facilities. In process design of the
system, the extent of protection shall be evaluated with specific concern to a sound fire protection
engineering principles, to provisions of IPS-E-SF-200, local conditions, process hazards, and NFPA
59A requirements under Chapter 9.
Dec. 1997
IPS-E-PR-360
33
SECTION D
9. STORAGE AND HANDLING OF ETHANE AND ETHYLENE
9.1 General
9.1.1 Scope
9.1.1.1 This Section covers the requirements and criteria for process design of ethane and ethylene
storage facilities installed at refineries, natural gas processing plants, petrochemical plants, pipeline
terminals and tank farms (except above-ground concrete tanks, frozen earth pits and under-ground
storage caverns or wells).
9.1.2 Reference publications
9.1.2.1 The latest edition or revision of API Standard 2508, "Design and Construction of Ethane and
Ethylene Installation" along with latest edition and revision of publications specified thereon shall to
the extend specified, form a part of this Section requirements.
9.2 Applicable Design Codes on Temperature and Pressure
9.2.1 Applicable requirements of the following shall be considered in process design:
a) ASME Boiler and Pressure Vessel Code, Section VIII.
b) API Standard 620 and IPS-E-PR-360, Sections B & C.
c) Safety requirements at least equal to those specified in API Standard 2510 and NFPA
59A and IPS-E-PR-360 Sections B and C.
9.2.2 The refrigeration system shall maintain the ethane and ethylene at a temperature such that its
vapor pressure does not exceed the design pressure of the tank. For systems at or near
atmospheric pressure, consideration should be given to design for additional refrigeration necessary
as a result of changes in atmospheric pressure.
9.2.3 The tank above the maximum liquid level shall be designed for a pressure not less than that at
which the pressure relief valves are to be set and for the maximum partial vacuum that can be
developed.
9.2.4 All portions of the tank below the maximum liquid level shall be designed for at least the most
severe combination of gas pressure (or partial vacuum) and static liquid head affecting each
element of the tank.
9.2.5 The design temperature shall be the minimum temperature to which the tank contents will be
refrigerated. The minimum temperatures of the part of the country where the tank is to be built shall
be considered in the design. Provisions shall be made to minimize thermal stress concentration
during initial cool down of a tank.
9.3 Distance Requirements and Exposure Limitations
9.3.1 General
9.3.1.1 Site selection shall include consideration of existing facilities, planned facilities in immediate
area, and the location of facilities adjoining the installation.
9.3.2 Minimum distance requirement and layout
9.3.2.1 All applicable provisions of IPS-E-PR-190 shall be considered for layout and spacing of
above ground ethane and ethylene storage tanks together with following requirements. In case of
any contradiction between these requirements and provisions of above said IPS, the most
protective for safety requirements shall be employed:
a) The minimum distance from the lines of adjoining property that may be built upon to the
tank shell shall be a distance of one-and-one half the tank diameter or 60 meters whichever
Dec. 1997
IPS-E-PR-360
34
is less.
b) The minimum distance between the outer surfaces of the shells of adjacent ethane and
ethylene tanks shall be a distance of one-forth the sum of the diameters of the adjacent
tanks.
c) The minimum distance from the tank shell horizontally to overhead power transmission
lines, surface equipment of storage caverns, regularly occupied buildings, loading and
unloading facilities, or stationary internal combustion engines shall be 7.5 meters. These
facilities shall not be built within a diked area.
d) The minimum distance from the tank shall to navigable waterways, docks and piers shall
be 15 meters.
9.3.3 Exposure and other limitations
9.3.3.1 The following conditions are required for locating facilities:
a) Ethane and ethylene storage tanks shall be located outside of buildings.
b) Tanks containing flammable or combustible liquids (other than ethane/ethylene) shall not
be located inside the dike surrounding ethane and ethylene storage tanks.
9.3.4 Dike and drainage provisions
9.3.4.1 Drainage systems shall have a grade of one percent or greater and shall terminate in a
surface area. Drainage systems shall have a capacity not less than that of the largest tank served.
9.3.4.2 All other provisions of API Standard 2508 regarding to dike and drainage of ethane and
ethylene storage tanks and subject to process design consideration shall be used.
9.4 Tank Accessories
9.4.1 General
9.4.1.1 Tanks shall be fitted with the following devices/equipment as suitable for use with
ethane/ethylene and designed for not less than service conditions to which it may be subjected:
9.4.2 Liquid level indicator
9.4.2.1 Each tank shall be equipped with a suitable liquid level indicator. The use of a secondary or
backup indicator shall be considered. At least one of these indicators shall be replaceable without
taking the tank out of operation. Columnar glass gages shall not be used.
9.4.3 Level alarm
9.4.3.1 Each tank shall be provided with a high liquid-level alarm, which is to be a separate device
from the gaging device specified in 9.4.2.1 above. The alarm shall be set so that the operator will
have sufficient time to stop flow without exceeding the maximum permissible filling height. The
alarm shall be located so that it is audible to personnel controlling the filling. A high level flow-cutoff
device, if used, shall not be considered as a substitute for the alarm.
9.4.4 Pressure gage
9.4.4.1 A pressure gage connected to the vapor space shall be provided on each tank.
9.4.5 Pressure and vacuum relieving devices
9.4.5.1 Each tank shall be provided with one or more spring-loaded, weighted-pallet, or pilot-
operated pressure-relief devices. For tanks designed for 104 kPa (ga) or more, the pressure relief
valves shall be set to start to discharge in accordance with the applicable paragraphs of the ASME
Code Section VIII. Weighted-pallet valves shall not be used where start-to-discharge pressure
exceeds 104 kPa (ga). Weight and lever pressure-relieving devices shall not be used.
9.4.5.2 For tanks designed for pressures below 104 kPa (ga), the pressure relief device shall be set
to discharge at no more than the maximum allowable working pressure of the tank.
9.4.5.3 Pilot-operated pressure-relief devices shall be so designed that the main valve will open
Dec. 1997
IPS-E-PR-360
35
automatically and protect the tank in the event of failure of the pilot valve or other essential
functioning device.
9.4.5.4 Each tank that may be damaged by partial vacuum shall be provided with at least one
vacuum-relieving device. The vacuum setting shall be such that the partial vacuum developed in the
tank at the maximum specified rate of air (or gas) inflow will not exceed the partial vacuum for which
the tank is designed.
9.4.5.5 When double-wall construction is used in which the inner tank holding ethane and ethylene
is surrounded by insulation contained within an outer vapor-tight jacket, the jacket shall be equipped
with a pressure and vacuum relieving device or devices. These devices shall be set to open at no
more than the maximum allowable working pressure and vacuum of the outer tank.
9.4.5.6 In addition to requirements specified under 9.4.5.1 through 9.4.5.5 above, all of the provision
under 5.1.5 through 5.1.11 of API Standard 2508 shall be considered as an integral parts of this
section for ethane/ethylene storage tanks accessories.
9.4.5.7 Sampling connections
9.4.5.7.1 Sampling connections, if required, shall be installed on tank piping rather than on the tank.
9.4.5.8 Automatic and remote devices
9.4.5.8.1 Automatic shutoff valves, remotely operated shutoff valves, automatic warning devices, or
a combination of these shall be used where tanks are remotely operating, receive ethane and
ethylene at a high rate of flow, or in other circumstances in which the designer considers it
advisable.
9.5 Piping Requirements
9.5.1 Piping shall conform to the applicable provisions of API Standard 2508, Section 6, and the
following:
9.5.1.1 Insofar as possible, all header piping, loading and unloading connections to and from the
tank, and so forth should be simplified. For example, a minimum number of connections into and
out of the storage tank is desirable. Operating errors increase as the piping installation becomes
more complex.
9.5.1.2 Shutoff valves that must be used during normal operations should be accessible to an
operator for ease of maintenance and for safety of operation and should be as close to the tank,
pump, compressor, or other equipment as possible. This should not be construed as prohibiting the
installation of remote shutoff valves or other safety appurtenances.
9.5.1.3 Buried pipelines should be installed below the frost line and protected from corrosion.
9.5.1.4 Connections from tanks to loading and unloading headers, equalizing lines, and vent or
relief lines should be installed to permit flexibility in all planes. Necessary ells or bends should be
provided for possible vertical and horizontal movement between the tank and the header.
9.5.1.5 In long lines where expansion and contraction are known to exist, each line should be
equipped with an adequate expansion bend or angular offset.
9.5.1.6 It is recommended that emergency shutoff valves be installed in long runs of piping used to
carry liquids to prevent the contents from being released in the event of line or equipment failure.
9.6 Transfer, Loading and Unloading Facilities
9.6.1 Sizing
9.6.1.1 Pumps and loading devices shall be sized to provide rates of flow appropriate to the
capacity of the facility. Extreme care shall be taken to ensure that the rates of flow are such that the
operator can follow the course of loading and unloading at all times and have adequate time to shut
down the facility before the tank or tanks are emptied completely or before they are filled beyond
their maximum filling height.
9.6.2 Design
9.6.2.1 The transfer system shall incorporate a means for rapidly and positively stopping the flow in
an emergency. Transfer systems shall be designed such that dangerous surge pressures cannot be
Dec. 1997
IPS-E-PR-360
36
generated when the flow in either direction is stopped.
9.6.3 Equipment
9.6.3.1 Pumps
9.6.3.1.1 Pumps may be centrifugal, reciprocal, gear, or other types designed for handling
refrigerated liquid ethane and ethylene. They shall have a design pressure and shall be constructed
of material capable of safely withstanding the temperature and maximum pressure which could be
developed by the product, the transfer equipment, or both.
9.6.3.1.2 Positive displacement pumps shall have a suitable relief device on the discharge side
unless other provisions are made for protection of equipment.
9.6.3.1.3 Centrifugal pumps equipped with mechanical seals or ordinary stuffing boxes are
acceptable; however mechanical seals are preferred.
9.6.3.2 Process design requirements of other equipment such as valves including emergency
shutoff valves, compressors, flow indicators, etc., shall be taken in full conformity with API Standard
2508.
9.7 Refrigeration System
9.7.1 Refrigeration load
9.7.1.1 The refrigeration load should take into consideration the following factors:
a) Temperature difference between design ambient temperature and design storage
temperature.
b) Maximum solar radiation.
c) Receipt of product that is warmer than the design temperature, if such operation is
expected.
d) Foundation heaters.
e) Heat absorbed in connected pipe.
f) Vapor displaced during filling or returned during product transfer.
g) Barometric pressure changes.
9.7.2 Other requirements
9.7.2.1 For other requirements of system process design, provisions given in API Standard 2508
shall be considered.
Dec. 1997
IPS-E-PR-360
37
SECTION E
10. STORING AND HANDLING OF ETHANOL AND GASOLINE - ETHANOL BLENDS
10.1 General
10.1.1 Motor fuels resulting from blend of 10 percent denatured anhydrous ethanol and 90 percent
gasoline have properties similar to those of gasoline. There are differences, however, which must
be recognized by those who store, handle, or provide fire protection for blended products. The
facilities required for the handling of ethanol blend are also similar to those for gasoline, with some
minor exceptions.
10.2 Scope
10.2.1 This section describes process design requirements for storing, handling and fire protection
of ethanol and gasoline-ethanol blends at distribution terminals.
10.3 Material Selection
10.3.1 Most materials used in storing, blending and transfer of gasoline are also suitable for use
with ethanol and ethanol blend. However engineering judgment is required when selecting materials
for use with ethanol and ethanol blend to ensure the safeties that handle these liquids. Some
commonly used materials and their compatibility with ethanol and ethanol blend are listed in Table 4.
TABLE 4 - COMPATIBILITY OF COMMONLY USED MATERIALS
WITH ETHANOL AND ETHANOL BLEND
RECOMMENDED NOT RECOMMENDED
METALS
Aluminum Zinc-galvanized (ethanol only)
Carbon steel
Stainless steel
Bronze
ELASTOMERS
Buna-N (hoses and gaskets) (Note 1) Buna-N (seals only) (Note 1)
Fluorel (Note 1) Neoprene (seals only)
Fluorosilicone (Note 2) Urethane rubber
Neoprene (hoses and gaskets)
Polysulfide rubber
Natural rubber (ethanol only)
Viton (Note 1)
POLYMERS
Acetal Polyurethane (Note 2)
Nylon Alcohol-based pipe dope
Polyethylene (recently applied) (Note 2)
Polypropylene
Teflon (Note 1)
Fiberglass reinforced
Plastic (Note 2)
Notes:
1) Registered trademark.
2) The manufacturer of the specific material should be considered.
Dec. 1997
IPS-E-PR-360
38
10.4 Requirements
10.4.1 Tanks and tank lining
10.4.1.1 Ethanol or ethanol blend should be stored in a tank with a fixed roof and an internal floating
cover. As an alternative, ethanol may be stored in a small cone roof tank without a floating cover
provided that air quality requirements are met.
10.4.1.2 To minimize vapor losses and where tank design permits, a 450 Pa pressure, 30 Pa
vacuum pressure-vacuum vent made for ethanol service should be installed.
10.4.1.3 In some locations, it may be necessary to dry the air going into the tank to avoid
condensation of moisture that might contaminate the ethanol. Fig. D.1 in Appendix D provides an
example of such an installation. It is important that the tank pressure-vacuum valve admit air into
the tank only when the air-dryer system fails or malfunctions. This can be done by ensuring that the
vacuum pallet on the tank pressure-vacuum valve is set at a vacuum higher than that of the air-
dryer vacuum relief valve.
10.4.1.4 To prevent any spill from spreading, it is desirable to separate tanks used to store ethanol
and their air-dryer systems from other tanks that contain flammable liquids by using intermediate
curbs, dikes, or drainage channels. In all other respects, tanks used to store ethanol and their air-
dryer systems should comply with generally accepted standards for the storage of flammable
liquids, such as those given in NFPA 30, Flammable and Combustible Liquids Code.
10.4.1.5 Riveted tanks should not be used because they are more likely to leak.
10.4.2 Handling
10.4.2.1 Ethanol should be blended with gasoline using the in-line blender or the in-tank blender.
Track blending is not recommended. (See Paragraph 2.2 of API Recommended Practice 1626, for
detail.)
10.4.2.2 For safe handling of gasoline and the ethanol-gasoline blend the accepted industry
practice as described in API Recommended Practice 2003 should be followed.
10.4.3 Piping
10.4.3.1 Approved non-metallic pipe or cathodically protected Schedule 40 steel pipe can be used
subject to the cautions stated in API Recommended Practice 1626, 1st. Ed.,1985, Paragraph
1.6.1.1 through 1.6.1.3.
10.5 Safety and Fire Protection
10.5.1 All of the applicable safety and fire protection provision, given in API Recommended Practice
1626, Section 4, and applicable NFPA standards shall be considered in process design for storage,
piping, handling and operation of these facilities.
Dec. 1997
IPS-E-PR-360
39
SECTION F
11. STORING AND HANDLING OF GASOLINE - METHANOL/COSOLVENT BLENDS
11.1 General
11.1.1 Motor fuels that consist of a blend of gasoline, methanol, a cosolvent or solvents, and
corrosion inhibitors have properties similar to those of gasoline that is not blended with these
additives. With some exceptions, the facilities required for the handling of gasoline
methanol/cosolvent blends are also similar to those required for gasoline. There are, however,
differences that must be considered in storing, handling or providing fire protection of this blend
product.
11.1.2 Methanol is an alcohol with a wide variety of use as a solvent. It also serves as a basic
building block for production of other chemicals and as a high-octane blending component for
gasoline.
11.1.3 Cosolvent alcohols act as a link between methanol and other gasoline components. They
improve a gasoline methanol blends water-tolerance properties. Cosolvents also help control the
effect of methanol on the vapor pressure of the finished gasoline methanol/cosolvent blend.
11.2 Material Selection
11.2.1 Most materials used in storing, blending, and transferring of gasoline are also suitable for
use with gasoline methanol/cosolvent blends; however, sound engineering judgment is required
when materials selection is for use in gasoline methanol/cosolvent blends to ensure the safety of
facilities that handle these liquids.
11.2.2 Some commonly used materials and their compatibility with gasoline-methanol/cosolvent
blends are listed in Table 5 which should be checked along with other materials for their best
suitability for use and selection.
11.2.3 Once the facilities are designed, installed and put into operation, it should be inspected for
suitability of selected materials periodically and should promptly be corrected/replaced in case of
any malfunction or improper selection.
11.3 Requirements
11.3.1 Following the requirements in Paragraph 11.2, above all of the provisions and specific
requirements set forth in API Recommended Practice 1627, (latest edition of this Practice) as
applicable to process design of storage and handling facilities of gasoline-methanol/cosolvent,
blends shall be considered, as integral part of this section.
11.3.2 The storage tanks used, should comply with generally accepted standards for storage of
flammable liquids, such as those given in NFPA 30 and NFPA 30A.
Dec. 1997
IPS-E-PR-360
40
TABLE 5 - COMPATIBILITY OF COMMONLY USED MATERIALS
WITH GASOLINE-METHANOL/COSOLVENT BLENDS
RECOMMENDEDa) NOT RECOMMENDED
METALS
Aluminum Galvanized metals
Carbon steel
Stainless steel
Bronze
ELASTOMERS
Buna-N
b, c)
Buna-N
b, c)
Fluorel
b)
Neoprene
c)
Fluorosilicone
d)
Neoprene
c)
Polysulfide rubber
Viton
b)
POLYMERS
Acetal Polyurethane
d)
Nylon Alcohol-based pipe dope
Polyethylene (recently applied)
d)
Polypropylene
Teflon
b)
Fiberglass reinforced plastic
d)
Notes:
a) These recommendations may not apply to phase-separated blends or to the gasoline-
methanol/cosolvent blending components. The manufacturer of the specific material should
be consulted.
b) Registered trademark.
c) Buna-N and neoprene are recommended for hoses and gaskets but not seals.
d) The manufacturer of the specific material should be consulted.
Dec. 1997
IPS-E-PR-360
41
APPENDICES
APPENDIX A
TABLE A.1 - NOMINAL CAPACITIES OF STANDARD VERTICAL CYLINDRICAL TANKS
TO BS 2654
Tank diameter(m) Tank dia
3 4 6 8 10 12.5 15 17.5 20 22.5 25 27.5 30 33 36 39 42 45
Height
Nominal capacities Nominal
m
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
m
3
7
14
21
28
35
42
m
3
12
25
37
50
62
75
87
100
m
3
28
56
84
113
141
160
197
226
254
282
m
3
50
100
150
201
251
301
351
402
452
502
552
603
m
3
78
157
235
314
392
471
549
628
706
785
863
942
1021
1099
1178
1256
m
3
122
245
358
490
613
736
859
981
1104
1227
1349
14/2
1505
1718
1840
1963
2080
2208
2331
2454
m
3
176
353
530
706
883
1060
1237
1413
1500
1767
1943
2120
2297
2474
2650
2827
3004
3180
3357
3534
3711
3887
4004
4241
4417
m
3
240
481
721
962
1202
1443
1683
1924
2164
2405
2645
2886
3126
3367
3607
3848
4088
4329
4570
4810
5051
5291
5532
5772
6013
m
3
314
628
942
1256
1570
1884
2199
2513
2827
3141
3455
3769
4084
4398
4712
5026
5340
5654
5969
6283
6597
6911
7225
7539
7853
m
3
397
795
1192
1590
1988
2385
2783
3180
3578
3976
4373
4771
5168
5566
5964
6361
6759
7156
7554
7052
8349
8747
9144
9542
9940
m
3
490
981
1472
1963
2454
2945
3436
3926
4417
4908
5399
5890
6381
6872
7363
7856
8311
8835
9326
9817
10008
10799
11290
11780
12271
m
3
593
1187
1781
2375
2969
3563
4157
4751
5345
5939
6533
7127
7721
8315
8009
9503
10097
10691
11285
11879
12473
13067
13661
14254
14848
m
3
706
1413
2120
2827
3534
4241
4048
5654
6301
7068
7775
8482
9189
9096
10602
11209
12016
12723
13430
14137
14844
15550
16257
16964
17671
m
3
855
1710
2565
3421
4276
5131
5987
6842
7697
8552
9408
10293
11118
11074
12829
13684
14540
15395
16250
17105
17961
18816
19671
70527
21382
m
3
1017
2035
3053
4071
5089
6107
7125
8142
9160
10178
11169
12214
13232
14250
15268
16285
17303
18321
19339
20357
21375
22393
23411
24428
25449
m
3
1194
2389
3583
4778
5972
7167
8362
9556
10751
11945
13140
14335
15599
16724
17918
19113
20308
21502
22697
23801
25086
26280
27475
28670
29864
m
3
1385
2770
4156
5541
6927
8312
9669
11083
12468
13854
15239
16625
18010
19396
20781
22167
23562
24937
26323
27708
29094
30479
31865
33250
34636
m
3
1590
3180
4771
6361
7952
9542
11133
12723
14313
15904
17494
19085
20675
22266
23856
25446
27037
28627
30218
31808
33399
34989
36579
38170
39700
Dec 1997
IPS-E-PR-360
42
APPENDIX B
TYPICAL LAYOUT LPG PRESSURE STORAGE WITH COLLECTION PIT/RETAINING SYSTEM
Dec 1997
IPS-E-PR-360
43
APPENDIX C
ARRANGEMENT OF DRAIN FACILITIES
Note:
Drain line to be adequately supported against reaction forces.
Dec 1997
IPS-E-PR-360
44
APPENDIX D
AIR - DRYER INSTALLATION FOR ETHANOL STORAGE TANKS AT TERMINALS
Fig D.1
Dec 1997
IPS-E-PR-360
45
APPENDIX E
REFINERIES LIQUEFIED PETROLEUM GAS SPECICATION
ANALYSIS UNIT LIMIT TEST METHOD
C2 Hydrocarbon Vol% 0.2 max ASTM D 2163
C3 Hydrocarbon Vol% * ASTM D 2163
C4 Hydrocarbon Vol% * ASTM D 2163
C5 Hydrocarbon Vol% 2 max ASTM D 2163
Hydrogen sulphide - Negative ASTM D 2420
Mercaptan sulphur gram/m
3
0.23 max(1) IP. 104 (A)
Ordorizing Agent gram/m
3
12
Note: (1) The limit applies to the product before addition of odorizing agent (Ethyl mercaptan)
* varies seasonally for refineries as follows:
(ABADAN, BANDAR ABBAS)
1 st KHORDAD
TO
1 st MEHR
1 st MEHR
TO
1 st AZAR
1 st AZAR
TO
1 st ESFAND
1 st ESFAND
TO
1 st KHORDAD
C
3
's vol%
C
4
's vol%
15-35
85-65
30-50
70-50
50-70
50-30
30-50
70-50
(TEHRAN, ARAK, SHIRAZ, KERMANSHAH, ESFAHAN)
1 st KHORDAD
TO
1 st SHAHRIVAR
1 st SHAHRIVAR
TO
1 st ABAN
1 st ABAN
TO
1 st FARVARDIN
1 st FARVARDIN
TO
1 st KHORDAD
C
3
's vol%
C
4
's vol%
15-35
85-65
30-50
70-50
50-70
50-30
30-50
70-50
(TABRIZ)
1 st TIR
TO
1 st SHAHRIVAR
1 st SHAHRIVAR
TO
1 st ABAN
1 st ABAN
TO
1 st
ORDIBEHESHT
1 st FARVARDIN
TO
1 st KHORDAD
C
3
's vol%
C
4
's vol%
15-35
85-65
30-50
70-50
50-70
50-30
30-50
70-50