Ashokleyland Isan: Indian Automobile Chennai
Ashokleyland Isan: Indian Automobile Chennai
Ashokleyland Isan: Indian Automobile Chennai
CHASIS ASSEMBLY:
In stage 1 and 2 already assembled frond and
rear axles from the machine shop-4 is fixed on the main frame that
fabricated from the machine shop-3 of the vehicle. In stage-3 the fixed
frame assembly is placed on the conveyor belt, where brake chamber is
fitted to it. In stage-4 steering gear box is fitted to the main frame. In
stage-5 silencer tank is fitted tot he main frame. In stage-6 fuel tank is
fixed to the stage of the chasis assembly. In stage-7engine is mounted on
the frame of chasis vehicle. In stage-8 Radiator is fixed at the front
of engine. In stage-9 tyres for all the wheels is fitted to the drums of the
axels. In stage-10 the vehicle is toed then and taken to the another unit to
make it running condition and test is driven out
ENGINE ASSEMBLY:
In Stage-1 crank case swr/plate/EII no is brought to
the engine assembly, here cam bearings are fixed to the crank case of the
engine. In stage-2 cam shaft types EO/EI/No are fixed in the appropriate
places in the crank case. In stage-3 crank shaft make BM/GB is fixed at
the base of the crank case like passing through the hole. In stage-4 m-14
studs are fixed to the holes of the crank case. In stage-5 1stand 6 the
piston is kept at the top dead centre and timing gears are fixed to the side
of the engine of the firing order.
In stage-6crank gears are fixed to the crank case to
operate the cam shafts in order to operate the valves. In stage-7 fly
wheel housing is fitted to the house of the engine. In stage-8 the
flywheel is fitted to the housing and 90 torques is applied to it. The fly
wheel housing consistsof the seal housing, flange and fly wheel. In
stage-9 Oil pump is fixed to the top of the crankcase to circulate oil to
the various parts of the enigne. In stage-10 the readily made piston
isfitted to the bore of the crankcase and connected to the crankshaft.
Before that, Pistonrings are of three types two compression rings and oil
ring is fixed on the piston.
In stage-11the conrod bolt is fixed to connect the
piston with the crank shaft. In stage-12 Idiling gear is fixed on the
spindles which controls the rotations of the cam gear, cam gear and
compression gear
In stage-13 cylinder head is fixed at the top of the
crank case to which rocker arm with valves are fixed. In stage-14 oil
pump is fixed at the bottom of the crank case with the adhesive(RTV)
paste. In stage-15 rocker assembly is fixed at the cylinder head. In stage16air compressor is fixed on the crank case. In stage-17 fuel injection
pump is fixed. In stage-18 valve cover is fixed. In stage-19 oil cover is
fixed. In stage-20 Injector pipe and inlet manifol is fitted. In stage -21
side cover is fixed. In stage-22 oil pump is fixed.
In stage-23starter motor is fixed. In stage-24 Exhaust
manifold is fixed. In stage-25 turbo charger is fixed. In stage-26 EII
fitments are fixed. In stage-27 fully assembled is taken to the testing area
where the testings are taken for the proper function of the engine
CHASIS ASSEMBLY:
The chasis of the vehicle is starts from here at this shop-3. The frames of
the wheels are fixed together to be sent on the chasis assembly. The
skids are mounted on the conveyor belt and frame is placed on the skids.
And frame MTG on which is mounted is fixed across the two frames.
On the rear end of the frame BKTS both sides are aligned with taper pin.
Fit and tight FSR and BKTS on the both sides with dummy bolts. Tilt
both the fsms to 90 degree by turning tackle and insert damps. Tight and
apply torque to the engineMTG Flinches and M12 with bolts.
correspondingly in every stage each workers tight appropriate bolt to the
frame before taken to the chasis assembly to make it a complete frame.
FABRICATION OF VALVE:
In stage-1 Facing and the centering (length) of the
valves are done here. In stage-2Sraightening (Bend removing) is done.
In the stage-3 Rough turning and finish turning are done. In stage-4
again the straightening is done here. In stage-5 Keyway milling(Gear
Fixing, Oil pumping) are done here. In stage-6 am milling(valve inlet,
valve outlet) are done. In stage-7 Gear hobbling is done through gear
hobbling machine. In stage-8 Gun drilling is done(through hole). In
stage-9 counter boring and tapping(nuts, front and rear).In stage-10 oil
hole drilling. In stage-11 Washing and number punching is done. In