FABTEK
FABTEK
FABTEK
CASE SUBMISSION
Case Report
Submitted to
L S MURTY
GROUP - 9
Contents
Overview ................................................................................................................................................. 2
Current issues .......................................................................................... Error! Bookmark not defined.
The 4 options ........................................................................................... Error! Bookmark not defined.
Refco .................................................................................................... Error! Bookmark not defined.
Pierce-Pike ........................................................................................... Error! Bookmark not defined.
Worldwide Paper ................................................................................. Error! Bookmark not defined.
Kathco .................................................................................................. Error! Bookmark not defined.
Criteria to be considered ......................................................................... Error! Bookmark not defined.
Alternatives ............................................................................................................................................. 2
Capacity Constraints ............................................................................................................................... 4
Observations in criteria ........................................................................................................................... 4
Selection Method ................................................................................................................................ 5
Conclusions ......................................................................................................................................... 6
Overview
Fabtek, one of the first companies to provide industrial-use titanium products has been struggling to
have positive bottom-line despite recording its record sales of 31.2 million in 1990. There have
been issues related to excessive backlogs unreliable internal forecasts and mismanagement of the
existing capacity. In June 1991, the companys booking exceeded its capacity by a significant margin.
Under this circumstance, the company at present has four prospective orders to choose from and
need to manage the acute shortage in capacity and reduce the increasing dissatisfaction related to
late deliveries. The company has different objectives set-out by the various stakeholders and also
needs to balance them while decision-making. In this report, an analysis of the various options has
been carried out and a viable sales and operations plan is recommended to overcome the current
crisis.
Price wars with competitors due to entry into commoditized bids. Fabtek is struggling to
command a price premium for its core-competency viz. welding
Mismatch in operations and sales criteria for order attractiveness. For ex: Operations wants
technically challenging jobs while sale sis looking for simple, familiar jobs
Delays in job completion leads to payment delays leading to working capital crunch
CONs
Too much reliance on Refco - risk of losing a large portion of
business at once
Late delivery
One-time order, it is unknown whether this order will lead to
further related business
Choosing this order eliminates the opportunity to take any
other order (promising long-term relationships because of the
high demand for labour
Refco unsure of Fabtek delivery schedule - labour already
running backlogs
Rumours of Refco shifting to in-house fabrication.
Pierce-Pike
PROs
Growing market
Acquiring a new long-pursued (valuable) client (New
Business Opportunity)
Fabtek's largest competitor may lose a valuable client
Good opportunity to develop a new important
capability
CONs
Uncertainty about timely delivery (reputation damage)
No experience in a similar job
Failure can risk in losing credibility and customer forever
Progress payment only on raw material
Worldwide Paper
PROs
Opportunity to develop a standard line of product
Ease for management in training the employees
Long-term business opportunity (as WP is planning to
license this job to its manufacturer)
Experience in a similar job
In line with fabteks high quality image.
Standard work, less demanding than custom work
CONs
Penalty of 0.1% of the contract price for each working day
that the complete order was late. No incentive for early
delivery
No progress payments for material/ labor
Kathco
PROs
Enhancing the exisiting good relationship with Kathco
Simple design
CONs
The order is a one-shot deal, i.e. no long-term business
opportunity as Kathco is building its own fabrication facilities
The job doesnt fit with Fabteks high quality image and
capabilities
No new capabilities being developed
Alternatives
With the existing alternatives, 15 combinations of projects are possible for Fabtek to bid. We use the
following codes to refer the projects: A- Refco, B- Pierce Pike, C- Worldwide Paper, D- Kathco , A+BRefco & Pierce Pike and so on. The various alternatives are initially checked against the various
capacity constraints in terms of availability for welding, machining and fabrication. The alternatives
which satisfy the capacity constraints are then taken through a scoring matrix based on the critical
criteria for final recommendation.
Capacity Constraints:
The capacity constraints are evaluated in 2 steps. The first step is to check if the cumulative labor
hours left after taking up the option are not significantly negative for each of welding and fabrication
(note machining can be subcontracted). Based on the first pruning the following Alternatives are
valid: A, B, C, D, A+D, B+C, B+D, C+D and B+C+D.
The second capacity constraint is that since Kathco's horizon is just one year, the feasible alternative
cannot have negative cumulative fabrication labor in the year 1991. This eliminates A+D, C+D and
B+C+D. Hence the feasible alternatives are: A, B, C, D, B+C and B+D. The table below summarizes the
results of the method.
Possible Alternatives
A, B, C, D, A+B, A+C, A+D,
B+C, B+D, C+D, A+B+C,
A+B+D, A+C+D, B+C+D and
A+B+C+D
Capcaity Constraint 1
A, B, C, D, A+D, B+C, B+D,
C+D and B+C+D
Capacity Constraint 2
A, B, C, D, B+C and B+D
Feasible Alternatives
Observations:
It can be seen that some of the criteria are contradicting for ex. The design is simple & the cost
estimates are reliable & Job should be technically challenging. So we need to eliminate one of
these.
After scrutinizing the above criteria, we see that some of them can be merged, some are redundant
and some may need to be eliminated. We have below a consolidated criteria list:
CR1:COGS less than 85%, the lower the better
CR2:Design should be simple with reliable cost estimates
CR3:Customer contribution to overall revenue should not exceed 20% and market contribution
should not exceed 30%
CR4:Choose projects with progressive time payments to support working capital requirements
CR5:Jobs chosen should allow for standardization in the future and have long repetitive runs
CR6: Profitability should be high
Based on the information gathered from the case, we have assigned the following weights to each of
the criteria. This will be used in option evaluation where each of the available 4 options will be rated
on a scale of 1-10 on each of these chosen 6 criteria.
No.
CR1
CR2
Definition
COGS less than 85%, the lower the better
The job fits with Fabteks high-quality image and builds capabilities
CR3
11%
CR4
11%
CR5
8%
The job gives opportunity for Fabtek to enter high profit new growth
segments to beat the commodity trap
8%
Maximize Profit
25%
CR6
CR7
Weight
24%
13%
Net profit & COGS have been given the highest priority as the company has experienced a steep
decline in income (negative income in last fiscal) and thus in the short-term to stay afloat it needs to
take on projects that have a high profit and lower costs of production.
Selection Method:
Out of the five feasible alternatives, we have selected our recommendation on the basis of criteria
as mentioned above. We use a total score approach to score & rank the feasible alternatives. For
alternatives with more than one project, we use weighted average score based on the sales revenue.
The table below shows the scores(out of 100):
Score
Sales
COGS %
82.75%
80.38%
87.75%
B+C
82.00%
83.19%
B+D
80.83%
CR1
40
90
60
30
80
CR2
70
80
90
40
85
70
CR3
90
75
25
40
55
CR4
70
70
50
50
60
60
CR5
65
50
85
40
70
45
CR6
60
90
80
50
85
65
CR7
80
60
20
20
85
80
The final selected alternative, which is our recommendation is to take up the Projects Pierce-Pike
and Kathco.
Conclusions:
The projects if taken up will provide a combined profit of $ 1.06 million which might help
significantly in moving from red in the profit column to green
The COGS of this project combination is 83%, which is above our target of 80% but still
below the upper limit of 85%
For Worldwide Paper project, the design is very simple and has the scope for becoming a
standardized offering in the future and thus this is a huge positive given the direction in
which Fabtek wants to move strategically
Working Capital however will still be an issue as progressive time payments are not cleary
mentioned in the deal.
Appendix:
Decision Criteria
The criteria used by various stakeholders for selecting the projects are discussed below:
A)
B)
C)
D)
Operations Division
Job is technically challenging
The job fits with Fabteks high-quality image & capabilities
The companys engineering expertise is utilized
The job is long-run and repetitive
The company has experience with similar products
Specifications and job scope are clear
For larger orders, progress payments can be negotiated
Overall contribution before SG&A is near 20% products price
Marketing Division
The job is similar to what Fabtek had built before
The design is simple and the cost estimate is reliable
The job has good payment terms
The market area has potential for further development
The job allows adequate delivery time
Price is not the primary factor in the customers decision
Finance Department
Maintain COGS should be 80%, with 85% upper limit
Insist on progress payments to maintain healthy working capital
Corporate Policy
Maximum 20% should only reside with one customer
No more than 30% business in one market area
Orders should utilize Fabteks core competence viz. welding
30,000
25,000
20,000
15,000
10,000
5,000
Jun-91
Jul-91
Aug-91
Sep-91
Oct-91
Nov-91
Dec-91
Jan-92
Feb-92
Mar-92
Apr-92
May-92
(5,000)
(10,000)
(15,000)
(20,000)
A
A+B
A+C
A+D
B+D
C+D
A+B+C
A+B+D
A+C+D
B+C+D
A+B+C+D
20000
B+C
15000
10000
5000
0
Jun-91
Jul-91
Aug-91
Sep-91
Oct-91
Nov-91
Dec-91
Jan-92
Feb-92
Mar-92
Apr-92
May-92
-5000
-10000
A
A+B
A+C
A+D
B+D
C+D
A+B+C
A+B+D
A+C+D
B+C+D
A+B+C+D
B+C
8,000
6,000
4,000
2,000
(2,000)
(4,000)
A
A+B
A+C
A+D
B+D
C+D
A+B+C
A+B+D
A+C+D
B+C+D
A+B+C+D
B+C