Breaker Failure
Breaker Failure
Breaker Failure
Backup Protection
Revised by: E. D. PRICE
2.1.2 Sensitivity
Remote backup provides poor sensitivity. Relays at
bus G may not ‘‘see’’ faults near buses R, S, or T. For
the scheme shown in Figure 13-1, the fault infeed effect
at bus H for faults near R, S, or T tends to reduce the
current magnitude and ‘‘reach’’ of distance relays at
breaker 1 at bus G. In these cases, relays at other Figure 13-3 Remote backup at bus G, breaker 1 for line
remote terminals will have to trip first, redistributing HR with distance relays.
the fault currents and increasing the effective reach of
the relays at bus G. This can result in sequential
tripping. 2.2. Local Backup and Breaker Failure
location. For simplicity and reliability, breakers that 1 Trip 2 and 4. Transfer-trip line 1 and
are already tripped will be retripped. Assume, for 2.
example, that a fault occurs on line 1 of Figure 13-14. 2 Trip 1 and 3. Transfer-trip lines 2 and
The protective relays for line 1 will attempt to trip 3.
breakers 1 and 4 and the remote end of line 1. Assume 3 Trip 2, 4, and 5. Transfer-trip line 3.
4 Trip 1, 3, and 5. Transfer-trip line 1.
a
See schematics for Figures 13-6 or 13-7.
Figure 13-19 Transformer BF considerations. Figure 13-20 Logic diagram of the SBF-1 relay.
lower than load current, if necessary (for 5.3 Type SBF-1 Relay
example, application problems as described in
Section 5.1.2). The type SBF-1 breaker-failure relay uses the
improved concept for breaker-failure detection, as
described in Section 5.2. The relay, as shown in
Figure 13-16 Figure 13-21
Figure 13-22, consists of phase- and ground-fault
Total clearing time Total clearing time detectors, 62BF timer, and a ‘‘control’’ timer. The
¼ Protective relay time ¼ Protective relay time control timer is for resetting the SBF-1 relay. In
þ breaker interrupting time þ breaker interrupting time applying the SBF-1 relay:
þ maximum 50 reset time þ margin
þ margin þ 86BF time The fault detectors can be set below the load
þ 86BF time current.
Figure 13-24 Special consideration on breaker failure scheme for single-pole trip application.