7s92 06011 0000 SHR 004a r3 - Sil Classification Report
7s92 06011 0000 SHR 004a r3 - Sil Classification Report
7s92 06011 0000 SHR 004a r3 - Sil Classification Report
CONTENTS
EXECUTIVE SUMMARY ....................................................................................... 4
1.
2.
3.
Basis .................................................................................................................6
Definition of SIL ................................................................................................6
Background to Risk Based Approach Adopted for SIL Selection .....................7
4.
Introduction .......................................................................................................5
Objectives of the Study .....................................................................................5
Overview ...........................................................................................................9
Identification of SIFs .........................................................................................9
Description of Function, Initiators and Final Elements ....................................10
Causes of SIF Demand and Consequences of SIF Failure ............................10
Further Elaboration on the Approach Adopted ...............................................12
Worksheets .....................................................................................................14
Assumptions ...................................................................................................15
SIL SESSIONS............................................................................................. 16
4.1
4.2
5.
FINDINGS .................................................................................................... 16
6.
RECOMMENDATIONS ................................................................................ 19
7.
CONCLUSIONS ........................................................................................... 21
8.
REFERENCES ............................................................................................. 21
PMC
PMC
EXECUTIVE SUMMARY
A Safety Integrity Level (SIL) classification study was carried out as part of the detailed
design phase for the PTT LNG Receiving Terminal at Map Ta Phut, Thailand. The objective
of the SIL classification study was to determine the required SIL of the Safety Instrumented
Functions (SIF), based on an assessment of the risk of injury to people and damage to the
environment. The SIL defines the minimum level of the safety integrity (or reliability)
required to be implemented for each specific SIF application. The SIL could range from SIL
1 to SIL 3 (highest level of safety integrity required). SIL - has also been used for SIF not
requiring a specific level of safety integrity.
The SIL Classification study was carried out following the completion of the HAZOP
(Hazard and Operability) study. The SIL study sessions were held in TF office in Seoul,
Korea over a period of three days in July 2008, and involved representatives from PTT LNG
(Owner), Fluor (PMC), SPAN, GS Engineering & Construction (GS E&C), KOGAS-Tech.
and Daewoo Engineering Company (DEC).
The SIL Study covered all the Safety Instrumented Functions (SIFs) listed in the Cause &
Effect Diagrams/Tables (CED) and was conducted in accordance with the Safety Study
Procedure [2] by ERM. The study covered SIFs provided on both new facilities and existing
facilities.
During the sessions, 27 out of 31 Safety Instrumented Functions (SIFs) were classified, of
which 4 were classified SIL 3, 5 were classified SIL 2, 14 were classified as SIL 1, 4 did not
require a specific level of safety integrity (i.e. classified as SIL -).
As part of the SIL classification sessions, a number of recommendations were made to
advice on the proposed implementation, or record comments relating to system
design/hazards that arose from the discussions during the SIL Classification Study.
While this study has determined the target SIL for the various safety instrumented functions,
the system configuration is assessed separately to confirm whether the target SIL can be
achieved or further mitigation is required. The results of this assessment are presented in
the SIL Verification Report.
PMC
Introduction
The LNG receiving terminal at Map Ta Phut, Thailand, is designed to receive and store LNG
from LNG carrier, vaporize the LNG at high pressure, and deliver the gas to pipeline. The
terminal will be developed in two phases. The terminal is designed to deliver 5 MTPA of
LNG of regasified product in Phase I and provisions will be made to allow expansion to 10
MTPA in Phase II. A 15% design margin for the LNG send out system are considered in the
design for both phases.
Two options are additionally considered as part of the LNG receiving terminal. Option 1 is for
the LNG truck loading, and Option 3 is for the design of under-structure for a small berth
designated to handle small ships.
The LNG receiving terminal is owned and operated by PTT LNG Company Limited. The
Consortium of GS Engineering & Construction, Korea Gas Corporation, Hanyang
Corporation and Daewoo Engineering Company is responsible for the detailed engineering
and construction of the Phase 1 of LNG receiving terminal.
Environmental Resources Management (ERM), an independent HSE consultancy was
commissioned to carry out a Safety Integrity Level (SIL) review for the above facilities. The
study was carried out following the completion of the HAZOP study. The study sessions
were held in TF office in Seoul, Korea over a period of three days in July of 2008. It involved
representatives from PTT LNG (Owner), Fluor (PMC), SPAN, GS Engineering &
Construction (GS E&C), KOGAS-Tech and Daewoo Engineering Company (DEC).
1.2
The objectives of the Safety Integrity Level (SIL) classification study was to assess the SIL
of the Safety Instrumented Functions (SIF), based on an assessment of the risk of injury to
people (operators or public) and the risk of damage to the environment. This involves
evaluating the following:
PMC
The SIL defines the level of the safety integrity (or reliability) required to be implemented for
each specific SIF application, such that the residual risk due to each hazardous event in the
plant is broadly acceptable. The SIL could range from SIL 1 to SIL 3 (highest level of safety
integrity required). SIL - may be used for SIF not requiring a specific level of safety integrity.
For SIL 4, a requirement to redesign the system to achieve an inherently safer design is
recommended.
Basis
The study was based on:
Cause & Effect Chart for Interlock & ESD System [1], (hereafter referred as CED);
The basis for the SIL study was primarily the P&IDs and CED.
2.2
Definition of SIL
The SIF will be operated on demand. It will act upon a process upset leading to a
hazardous situation is detected and revert the hazardous event to a safe status. The SIL
defining a minimum level of reliability in terms of Probability of Failure on Demand (PFD), as
shown in Table 2.1 is applied for this project.
Table 2.1
SIL
1
2
3
4
PMC
SIL 4 is considered extremely rare in the process industry. If a classification leads to SIL 4,
further study should be performed including a review of the design.
The safety functionality that calls for integrity level below SIL 1 may be implemented in the
Basic Process Control System(BPCS) or retained in the ESD system as provided now.
The safety functionality that calls for integrity levels SIL 1, 2 and 3 will be implemented in the
ESD system.
Definitions of terminology are referred to Safety Study Procedure [2].
2.3
PMC
This study assesses the risk posed by each hazardous event in the plant which is resulted
from SIF failure and determines the level of reliability of the SIF to meet a target risk level or
broadly acceptable risk level. A qualitative (or a semi-quantitative approach) is adopted to
determine the risk using the Risk Graphs.
Probability of failure on demand of SIF (PFD), i.e. the reliability of the SIF is thus derived as
follows:
Target risk level (ie acceptable risk after mitigation)
PFD = Likelihood of an unwanted event x Consequence
Using safety classification as illustration, and assuming that the target risk level is 10-4 per
year, the likelihood of an unwanted event is 10-1 per year and Consequence is 1 fatality,
then
PFD = 10-4/( 10-1 x 1) = 10-3
The required SIL based on safety classification is therefore 3 for this SIF.
If the likelihood of an unwanted event is 10-1 per year and the Consequence is 0.1 fatality
(i.e. injury), then
PFD = 10-4/(10-1 x 0.1) = 10-2
The required SIL is 2.
The system configuration is then determined based on the SIL level derived above.
It may be noted that where a SIF is classified as SIL 3 or SIL 2, it means that the inherent
risk is high and hence a higher level of reliability is required for the instrumented function.
Inherent risk may be high due to the system design or the hazard presented by the system.
Similarly, where a SIF is classified as SIL 1, it means that the inherent risk is low.
The above approach ensures that a consistent basis (i.e. a risk based approach) is adopted
in determining the configuration of the instrumented system, while avoiding over engineering,
where not necessary.
The assessment is however, qualitative and is based on guidelines, experience and
judgement. A more detailed quantitative approach may be adopted but is time consuming.
The above approach is therefore considered reasonable and fit for purpose.
A conservative approach to system design may still be adopted for various reasons, such as
Licensors past experience or other factors which may not be quantifiable easily. In such
cases, although the SIL derived from above may be lower (say SIL - or SIL 1), a more
PMC
conservative SIL may be assigned, say SIL 1 or SIL 2 respectively. This study seeks to set
the minimum requirements, which however, may be exceeded if required.
3. SIL METHODOLOGY
3.1
Overview
The methodology defined in the Safety Study Procedure [2] was adopted for the SIL
Classification Study. The SIF was first defined with a function description, design intent, one
or more initiator(s) (i.e. instrument(s) to detect a hazardous situation) and one or more final
element(s) (i.e. elements that act to mitigate the hazardous situation). The study team then
described the demand scenario and consequence(s) of failure on demand (CoFoD) and
numerical frequency and consequence ratings were assigned.
The consequence ratings were based on:
The assessment takes account of the possibility to avert the hazard and the probability of
personnel being in the vicinity of the defined consequence.
A flow chart presenting the steps to assign the SIL classification is shown in Annex B.
Following identification of damage level and likelihood by the team, the SIL of the function
was classified according to Risk Diagrams as shown in Annex C.
3.2
Identification of SIFs
The CEDs were first reviewed to identify the SIFs that required SIL classification. These
were also confirmed by reviewing the P&IDs and the HAZOP sheets. Only those functions
within the ESD system and initiated by the process to prevent a specific hazardous situation
were selected for classification, thus, the following types of functions listed in the CED were
not classified:
PMC
Functions related to normal process control (eg auto start/stop of pumps as a means of
normal level control);
A complete list of SIFs is presented in Annex D. Whether the SIF relates to the new facilities
or existing facilities is also identified (e.g. SIFs relating to existing unloading arms). Some
SIFs may include both new and existing facilities (e.g. high pressure trip of sendout). This is
indicated as shared SIF.
The assessment is carried out for one set of SIF. For parallel equipments/systems with
similar SIFs, cross-reference is made to the SIF that is already classified. For example, SIFs
for P-105A HP pump are classified. For all other new and existing HP pumps, reference is
made to P-105A.
Some of the SIFs are not shown in CED but shown on the P&IDs. A note has been added in
the comment column of the Function List (Annex D), to revise the CED accordingly.
3.3
3.4
PMC
PMC
layers (IPL) that mitigate the likelihood or consequence. A reduction factor of 10 will reduce
SIL by one level while a reduction factor of 100 will reduce SIL by two levels.
The term independent protection layer has been applied to a safeguard which is capable of
preventing a scenario from proceeding to its undesired consequence independent of the
initiating event or the action of any other layer of protection associated with the scenario.
There is a slight distinction however, in IEC 61511, between the terms protection layer and
independent protection layer. Although both need to meet the criteria mentioned above, a
safeguard may qualify as a Protection layer, if at least a factor of 10 risk reduction can be
achieved while to qualify as an independent protection layer, a higher degree of reliability is
required (i.e. reduces the identified risk by a minimum of 100 fold). While this study report
has used the term IPL for all protection layers, a 100-fold risk reduction is applied only to
those protection layers such as PSVs which meet the criteria of IPL as defined in IEC 61511.
3.5
PMC
mitigate but the mitigating effect is not significant as compared to stopping of BOG
compressor. This distinction is made for the purpose of the SIL implementation only but all
the final elements as identified in the CED will be retained in the interlock and implemented
in the SIS.
3.5.3 Multiple SIFs for the Same Hazard
In some cases, multiple SIFs are provided against the same hazard. For example, sea water
low flow acts to prevent vaporiser outlet LNG low temperature although an independent low
temperature trip is provided. The former may be regarded as a layer of protection (as it takes
advance action) or may be regarded as a demand reducing function (as it reduces demand
on the LNG low temperature sensor). [Note that there are other cases for LNG low
temperature in addition to loss of sea water flow; however, for the case of low LNG
temperature due to loss of sea water flow, the low low sea water flow and low LNG
temperature may be considered together in the same function.]
In such cases, the functions may be combined, but this may present some complication in
the assessment, in terms of evaluating the percentage contribution due to the various
causes and accordingly the various sensors. To simplify the analysis, each function may be
treated separately. However, this also presents some constraint in defining the design intent,
as to whether the function is deemed to protect against an intermediate consequence or the
ultimate consequence. As a further simplification, default SIL 1 may be assigned for such
demand reducing functions or functions providing the first layers of protection.
3.5.4 Sensors with Different Set Points
In the case of low level in LNG tank, two set points are provided for each sensor. The low
set point initiates a set of action (i.e. stops BOG compressor), while the low low set point
initiates a different set of action (i.e. stops in-tank pumps).
As explained earlier, stopping BOG compressor is considered as the primary final element
and hence the SIF is defined accordingly.
3.5.5 Consideration of PZV (Safety Valves)
Where a SIF is provided in addition to a PZV (assuming the safety valve is adequately sized
for the required case), PZV has been considered as an IPL with a risk reduction factor of
100, although it could be argued that no SIF is probably required or no classification is
required.
PMC
Protective Measures
Operator Intervention (independent alarm and
possibility for operator intervention in about five
minutes)
Trip/ Independent SIF
Check valve
Relief Valve (PZV)
10
10
100
Note: where more than one protective measure exists, the highest IPL value assumed, without taking
credit for all, as a conservative measure
Table 3.2
Scenario
Control Loop Failure
Pump Trip/ Compressor Trip
Table 3.3 Rule Set for Presence in Danger Area & Possibility to Avert Hazard
3.6
G1
A2
G2
Worksheets
The session proceedings were recorded using PHA-Pro 7 [4]. The records were projected
on a screen for comment and agreement by the team members during the sessions.
PMC
Preparation for the study was conducted prior to the commencement of the classification
sessions. This comprised input of the study SIF into the PHA software, based on the
information in CED. In addition, the functions were also verified and revised, as necessary,
by the facilitator.
The completed SIL worksheets are included in Annex E.
3.7
Assumptions
Several assumptions were made regarding the basis of the design during the course of the
SIL study. The main items are:
In case of multiple equipments (with duty and standby/spare equipment) inside a unit,
the study was conducted for one set of equipment. The recommendations from this
study will therefore apply for such similar systems as well. The study has however,
considered the impact of simultaneous operation of systems in parallel or series
including the control requirements and the effect of trip of one system on the other.
The CEDs were reviewed to identify the SIFs that required SIL classification. Only those
functions within the ESD system and initiated by the process to prevent a specific
hazardous situation were chosen for classification, thus, the following types of functions
listed in the CED were not classified:
The final element(s) of the SIF were chosen as those which directly meet their design
intent. Thus, only one or two final elements were usually defined for any function. The
other elements acted upon by the initiators were left unclassified (they may however, be
retained for implementation). However, these unclassified elements may act as a
primary final element for another SIF and assigned appropriate SIL classification. Those
final elements not covered under any other SIF as primary final element were checked,
where required, to ensure no separate classification was required
PMC
4. SIL SESSIONS
4.1
Study Period
The SIL Study for the PTT LNG Receiving Terminal was conducted between 14th and 16th
July 2008 at TF Office in Seoul, Korea.
4.2
Study Team
The SIL study team comprised a multidisciplinary team of personnel involved with the
Project and having adequate experience of design, instrumentation, operations,
maintenance, safety and loss prevention. Representatives from PTT LNG (Owner), Fluor
(PMC), SPAN, GS Engineering & Construction (GS E&C), KOGAS-Tech and Daewoo
Engineering Company (DEC) participated in the SIL sessions, which were chaired by an
independent consultant from ERM. Services of other specialists were called upon as
required.
The details (names, company and discipline) of the SIL team members who attended the
sessions are presented in Annex A.
5. FINDINGS
A list of the classified functions is shown in Table 5.1.
Table 5.1
Function Name
Initiators
Target
SIL
LT-085 (1oo1)
SIL 1
ZS-020A (1oo1)
SIL 2
ZS-020A/B/C
(2oo3)
default
SIL 1
PT-210A/B/C
(2oo3)
SIL 1
PMC
Function Name
Initiators
Target
SIL
PT-210A/B/C
(2oo3)
Close SDV-291(1oo1)
SIL 1
PT-210A/B/C
(2oo3)
SIL 3
(SIL 1
when
credit
taken)
LT-202/203/204
SIL 2
(2oo3)
LT-202/203/204
SIL 1
9. On low low LNG tank T-001 level LT204, shutdown in-tank LNG pumps
LT-204(1oo1)
SIL 1
LT-204(1oo1)
SIL 1
PT210A/B/C(2oo3)
SIL 3
(SIL 2
with
recomme
ndations)
(2oo3)
PT-228A (1oo1)
SIL 1
PMC
Function Name
Initiators
Target
SIL
13. On low low intank LNG pump P001A discharge pressure, stop intank LNG pump
PT-228A (1oo1)
LT-307A/B/C
SIL -
LT-307A/B/C
(synergetic case)
SIL 2
TT-337 (1oo1)
LT-0397A/B/C
(2oo3)
SIL 1
LT-0397A/B/C
(2oo3)
(synergetic case)
SIL 3
(secondary
function)
SIL -
LT-0398 (1oo1)
SIL 2
(SIL 1
with
recomme
ndation)
(2oo3)
(2oo3)
LT-0398 (1oo1)
SIL 2
PT-0375 (1oo1)
SIL 1
TT-502 (1oo1)
SIL 1
PMC
Function Name
Initiators
Target
SIL
PT-501 (1oo1)
SIL 1
PT-501 (1oo1)
SIL -
TT-003 (1oo1)
27. On high high fuel gas heater E001A temperature, isolate E-001A
TT-006 (1oo1)
SIL 1
PT-019 (1oo1)
SIL -
PT-1004 (1oo1)
SIL 3
(SIL 1
with
recomme
ndation
No. 10)
PT-813A/B/C
(2oo3)
PT-813A/B/C
(2oo3)
SIL 1
During the sessions a total of 27 SIF were classified. A summary of the results is provided in
Table 5.2.
Table 5.2
SIF Classification
Number
4
14
5
4
0
27
%
15%
52%
18%
15%
0%
100%
6. RECOMMENDATIONS
6.1
Summary of Recommendations
In total, 13 actions were recommended for resolution or further investigation during the SIL
study, to advise on the proposed implementation, or record comments generated during the
sessions. The list of recommendations is included in Table 6.1.
PMC
Table 6.1
List of Recommendations
Recommendations
Place(s) Used
1. Review the requirement to stop the in-tank pumps on low pressure since in the case of
PC-292 malfunctions, this interlock is expected to shutdown all the in-tank LNG pumps
and therefore gas injection through PV-290 cannot be relied on. Shutting down the BOG
compressors may be sufficient. Consider keeping at least one LP pump running. This will
reduce SIL by one level.
11.1.1
13.1.1
3. Review whether additional SDV could be implemented on the common drain line as SIL
1 may be difficult to be achieved during Phase 2.
6.1.1
4. Check sizing of PSVs for backflow case from the HP header. This can reduce SIL level
to SIL 1 if credit can be taken for the PSVs.
6.1.1
17.1.1
6. Review set point of PSV-033/034 to prevent unnecessary discharge to the flare, this will
reduce SIL by one level.
20.1.2
7. Check the high high level trip configuration on the recondensor (check actions on LT397/398)
21.1.1
8. Review requirement for this interlock TT-003LL (fuel gas temperature low low).
26.1.1
9. Consider not shutting down all of the HP pumps from this interlock PT-813A/B/C, or
shutting down HP pumps in stages to prevent backflow situation at the pumps.
30.1.1, 31.1.1
10. Refer to HAZOP recommendation 91. This will eliminate the hazard.
29.1.1
11. Review the high pressure protection system for the LNG truck during vendor package
review.
29.2.1
12. Shutdown logic for the unloading arms is not clear. (mismatch between P&ID, cause
and effect diagram and operating and control philosophy). This needs to be reviewed.
2.1.1
13. Review requirement for having a balance line between individual storage tanks as these
create a potential common mode of failure for all the three tanks in Phase 2 due to
overpressure scenario.
4.1.1
Note: Place(s) Used 11.1.1 means Function 11, Design Intent 1, Demand Scenario 1.
6.2
Follow - up Actions
Proper follow-up and close-out of all recommendations are monitored through the SIL
Review Action Sheet (7S92-06011-0000-SHR-004C) which has been issued as a separate
report.
PMC
7. CONCLUSIONS
A SIL classification study has been performed on all SIFs concerning new facilities, and
target SIL determined. Based on the results of this classification, the safety instrumented
system configuration will be checked to determine if the target SILs can be achieved.
Mitigation measures will be recommended where necessary to achieve the target SIL. The
results of reliability study associated with this task will be presented in the SIL Verification
report.
8.
REFERENCES
The following documents were referenced during the preparation of this report:
[1]
[2]
[3]
[4]
PMC
PMC
Team Members
Name
Sessions
Company
1. 14-07-2008
2. 15-07-2008
3. 16-07-2008
Herve Bonnel
ERM HK
Present
Present
Present
Sunny Cao
ERM HK
Present
Present
Present
Heung-Sik Yoo
DEC
Present
Present
Present
Tae-Soon Yong
DEC
Present
Present
Present
Jee-Hwan Cho
DEC
Present
Present
FLUOR
Present
Present
DEC
Present
DEC
Present
Present
Corazon Almirez
FLUOR
Present
Present
Present
Norman Tseng
FLUOR
Present
Ceyhan Aydogan
FLUOR
Present
Present
Present
Chang-Mun Bae
DEC
Present
Thanisorn Ounharoj
PTT LNG
Present
Present
Present
Tanate Areephitak
SPAN
Present
Present
Present
K.A. Baek
GS E&C
Present
Present
Jae-Sik Kim
GS E&C
Present
Present
Ki Taek Yow
GS E&C
Present
DEC
Present
J.T. Choi
KOGAS-Tech
Wi-Tawit Piyaponsate
PTT LNG
Present
Present
Present
Present
PMC
PMC
CAUSE&EFFECT DIAGRAMS
START ANALYSIS
INITIATOR and
FINAL ELEMENT
IDENTIFICATION
SCENARIO IDENTIFICATION
CONSEQUENCE of
SIF Failure
NEXT SIF
EVALUATION of:
- Personnel Safety
- Production and Equipment Loss
- Environmental Damage
STOP ANALYSIS
PMC
PMC
Personal Safety
(W) Frequency of demand
W1 = Low (demand less than 0.1 per years)
W2 = Moderate (demand between 1 and 0.1 per years)
W3 = High (demand between 10 and 1 per years)
(S) Potential extent of human injury per demand if ESD system fails on demand
S0 = No injury
S1 = Slight injury, non-permanent
S2 = Severe injury, death of 1 person
S3 = Death of several persons
S4 = Catastrophe, many casualties
(A) Presence in danger zone at time of demand
A1 = Seldom to frequently
A2 = Frequently to continuously
(G) Possibility to avert hazard
G1 = Under certain conditions
G2 = Hardly possible
IPL0
S0
S1
G1
A1
G2
S2
G1
A2
G2
A1
S3
A2
S4
W3
W2
W1
PMC
S2
G1
A2
G2
A1
S3
A2
S4
W3
W2
W1
W3
W2
W1
IPL100
S0
S1
G1
A1
G2
S2
G1
A2
G2
A1
S3
A2
S4
PMC
Environmental Damage
(W) Frequency of demand
W1 = Low (demand less than 0.1 per years)
W2 = Moderate (demand between 1 and 0.1 per years)
W3 = High (demand between 10 and 1 per years)
(E) Environmental damage per demand if ESD system fails on demand
E0 = No release or release with negligible damage to the environment
E1 = Release with minor damage to the environment that should be reported (e.g., moderate
leak from a flange or a valve, small scale liquid spill)
E2 = Release within fence with significant damage to the environment (e.g., a cloud of
obnoxious vapour travelling beyond the unit following flange gasket blow-out or compressor
seal failure)
E3 = Release outside fence with temporary major damage to the environment (e.g., a
vapour or aerosol release with or without liquid fallout that causes temporary damage to
plants or fauna)
E4 = Release outside fence with permanent major damage to the environment (e.g., liquid
spill into a river or sea, a vapour or aerosol release with or without liquid fallout that causes
lasting damage to plants or fauna, solids fallout, liquid release that could affect groundwater)
(G) Possibility to avert hazard and to intervene
G1 = Under certain conditions
G2 = Hardly possible
IPL0
W3
W2
W1
G2
G2
E0
E1
G1
E2
G1
E3
G1
G2
E4
G1
G2
PMC
IPL10
W3
W2
W1
W3
W2
W1
G2
G2
G2
G2
E0
E1
G1
E2
G1
G2
G2
E3
G1
G2
E4
G1
G2
IPL100
E0
E1
G1
E2
G1
E3
G1
E4
G1
PMC
PMC
Function Name
Initiators
LT-085
(1oo1)
ZS-020A
(1oo1)
Target SIL
SIL 1
SIL 2
PT210A/B/C
(2oo3)
Interlock
ID
P&ID
I-001
0100-PC005
L-001A
0100-PC003
The same
classification applies
to the apex angle and
other unloading arms.
Comment
default SIL
1
The same
classification applies
to the apex angle and
other unloading arms.
L-001A
0100-PC003
SIL 1
The same
classification applies
to other LNG tanks.
I-003
I-001
0100-PC007
Close SDV-080/082
(2oo2)
Close MOV-223/224
Close SDV-045/025/055
(3oo3) (these valves are
provided with a bypass
used for initial cooldown.)
Close SDV026/056/033/034/046/291
PMC
Function Name
Initiators
Overall 1oo2
Target SIL
Comment
Interlock
ID
P&ID
PT210A/B/C
(2oo3)
Close SDV-291(1oo1)
PT210A/B/C
(2oo3)
Close MOV-223/224
SIL 1
The same
classification applies
to other LNG tanks.
I-003
0100-PC007
SIL 3 (SIL
1 when
credit
taken)
The same
classification applies
to other LNG tanks.
I-003
I-001
0100-PC007
SIL 2
The same
classification applies
I-003
I-001
0100-PC007
Close SDV-225
Close MOV-223/224
Close SDV025/026/055/056/033/034/045/046
/080/082 /225/291
Shutdown cargo pumps for LNG
unloading
Close all cargo ESD valves
Activate ESD stop ships unloading
system
Activate open ship recycle valves
LT202/203/204
Close SDV-080/082
(2oo2)
Close MOV-223/224
PMC
Function Name
shutdown unloading line
(unloading mode)
Initiators
(2oo3)
Close SDV-045/025/055
(3oo3) (these valves are
provided with a bypass
used for initial cooldown.)
Close SDV026/056/033/034/046/291
Overall 1oo3
Target SIL
Comment
Interlock
ID
P&ID
LT202/203/204
(2oo3)
LT204(1oo1)
Close MOV-223/224
SIL 1
The same
classification applies
to other LNG tanks.
I-003
0100-PC007
SIL 1
The same
classification applies
to other LNG tanks.
I-003
I-014
0100-PC007
SIL 1
I-003
I-014
0100-PC007
SIL 3 (SIL
2 with
I-003
I-007
0100-PC007
Close SDV-291
Close SDV-1005/1020/1030/1040
Close SDV-1003
Shutdown truck loading station
A/B/C/D
LT204(1oo1)
(not applicable,
synergetic case)
PT210A/B/C(2o
Shutdown BOG
compressor (C-001A/B)
Shutdown XA-227A/B
Close SDV-1003
PMC
Function Name
shutdown BOD compressor
Initiators
o3)
Target SIL
recommen
dations)
Comment
than required,
shutting down the
LNG pumps may be
considered as the
redudant final
element action.
Interlock
ID
P&ID
I-009
I-014
The same
classification applies
to other LNG tanks.
PT-228A
(1oo1)
SIL 1
PT-228A
(1oo1)
LT307A/B/C(2o
o3)
UA-325/355 (shutdown
BOG compressor C001A/B) (1oo1)
SIL -
LT307A/B/C(2o
o3)
(synergetic case)
SIL 2
TT-337
(1oo1)
The same
classification applies
to other intank LNG
pumps.
I-004
0100-PC006
The same
classification applies
to other intank LNG
pumps.
I-004
0100-PC006
SDV-300 can be
considered as
redudant final
element
0100-PC010
0100-PC010
The same
classification applies
to other BOG
compressors.
I-007
0100-PC011
PMC
Function Name
Initiators
LT0397A/B/C
(2oo3)
Stop XA406/407/408/409/410
(shut down HP LNG
pump P-005A/B/C/D/E)
(1oo1)
LT0397A/B/C
(2oo3)
Target SIL
Comment
Interlock
ID
P&ID
SIL 1
I-011
I-013
0100-PC013
(synergetic case)
SIL 3
I-011
I-013
0100-PC013
(secondary
function)
SIL -
LT-0398
(1oo1)
Close SDV-379/383
(2oo2 for holding mode
and 1oo1 for unloading
mode). However, SDV383 is only required to be
closed in case of multiple
HP pump trip, which is
less likely.
Close SDV-506/526/546/566/586
Open SDV-225/275
Open HV-223/273
SIL 2 (SIL
1 with
recommen
dation)
0100-PC017
0100-PC018
0100-PC019
0100-PC020
0100-PC021
I-011
I-004
I-006
I-007
I-009
0100-PC013
PMC
Function Name
21. On high high LNG
recondenser level (backflow
to compressor case), close
SDV-379/383
Initiators
LT-0398
(1oo1)
Close SDV-379/383
(2oo2 for holding mode
and 1oo1 for unloading
mode). However, SDV383 is only required to be
closed in case of multiple
HP pump trip, which is
less likely.
Target SIL
Comment
Interlock
ID
P&ID
SIL 2
I-011
I-004
I-006
I-007
I-009
0100-PC013
SIL 1
I-011
0100-PC013
Open SDV-225/275
Open HV-223/273
PT-0375
(1oo1)
TT-502
(1oo1)
SIL 1
The same
classification applies
to other LNG
vaporizers.
I-013
0100-PC017
PT-501
(1oo1)
SIL 1
The same
classification applies
to other LNG
vaporizers.
I-013
0100-PC017
PT-501
(1oo1)
SIL -
The same
classification applies
to other LNG
vaporizers.
I-013
0100-PC017
PMC
PMC
Function: 1. On low low LNG drain pot from LNG unloading line level
Initiator: LT-085 (1oo1)
Final Element: Shutdown XA-076 (LNG drain pot pump P-006) (1oo1)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. To prevent pump
running dry under
block suction
conditions
1. none
S
/
E
S
2
SIL
A1
G2
IPL
0
W2
SIL
1
Required Actions
(SIL)
PMC
Demand Scenario
CoFoD
IPLs
1. To prevent release of
LNG if the slew angle
exceeds the step 2
limit (disconnect)
2. Same as above
1. position monitoring
sensors (PMS) and
supervised operation
W1 selected as weather
conditions continuously
monitored, before arrival
of the carrier and during
unloading
S
/
E
SIL
S
4
N/
A
N/
A
IPL
10
W1
SIL
2
E
3
N/
A
G2
IPL
10
W1
SIL
1
Required Actions
(SIL)
PMC
Function: 3. On high high unloading arm position sensor slew angle (operational interlock to protect the unloading arm)
Function: 3. On high high unloading arm position sensor slew angle (operational interlock to protect the unloading arm)
Initiator: ZS-020A/B/C (2oo3)
Final Element: Disconnect quick release coupling for L-001A (1oo1)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
This function is provided for equipment protection. Hence, a default SIL1 has been assigned to this function.
S
/
E
SIL
Required Actions
(SIL)
PMC
Function: 4. On high high LNG tank T-001 pressure PT-210A/B/C during unloading, shutdown unloading line
Function: 4. On high high LNG tank T-001 pressure PT-210A/B/C during unloading, shutdown unloading line
Initiator: PT-210A/B/C (2oo3)
Final Element: Close SDV-080/082 (2oo2); Close SDV-045/025/055 (3oo3) (these valves are provided with a bypass used for initial cooldown.); Close SDV-225 (no credit can be given since all the tanks will be
pressure balanced); Overall 1oo2
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. To prevent
overpressure of LNG
tank T-001 (unloading
mode)
1. PCV-292 (design
cases: three
compressors not
running, and two ships
unloading).
S
/
E
SIL
S
3
A1
N/
A
IPL
100
W3
SIL
1
E
2
N/
A
G2
IPL
100
W3
SIL
1
S
3
A1
N/
A
IPL
100
W3
SIL
1
2. PSV-017 (design
cases:3 percent of tank
inventory, which is the
governing case and
including the scenario)
2. Same as above
2. To prevent
overpressure of LNG
tank T-001 (holding and
unloading mode)
1. PSV-017 (design
cases:3 percent of tank
inventory, which is the
governing case and
including the scenario)
100
Required Actions
(SIL)
13. Review
requirement for
having a balance line
between individual
storage tanks as
these create a
potential common
mode of failure for all
the three tanks in
Phase 2 due to
overpressure
scenario.
PMC
Function: 4. On high high LNG tank T-001 pressure PT-210A/B/C during unloading, shutdown unloading line
Initiator: PT-210A/B/C (2oo3)
Final Element: Close SDV-080/082 (2oo2); Close SDV-045/025/055 (3oo3) (these valves are provided with a bypass used for initial cooldown.); Close SDV-225 (no credit can be given since all the tanks will be
pressure balanced); Overall 1oo2
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
2. Same as above
3. To prevent venting of
natural gas to the
atmosphere (unloading
mode)
1. PCV-292 (design
cases: three
compressors not
running, and two ships
unloading).
10
S
/
E
SIL
E
2
N/
A
G2
IPL
100
W3
SIL
1
S
2
A1
G2
IPL
10
W3
SIL
1
E
1
N/
A
G2
IPL
10
W3
SIL
1
Required Actions
(SIL)
PMC
Function: 5. On high high LNG tank T-001 pressure PT-210A/B/C during holding, shutdown makeup line
Function: 5. On high high LNG tank T-001 pressure PT-210A/B/C during holding, shutdown makeup line
Initiator: PT-210A/B/C (2oo3)
Final Element: Close SDV-291(1oo1)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. To prevent
overpressure of LNG
tank T-001 (unloading
mode)
1. PCV-292 (design
cases: three
compressors not
running, and two ships
unloading).
2. PSV-017 (design
cases:3 percent of tank
inventory, which is the
governing case and
including the scenario)
S
/
E
SIL
S
3
A1
N/
A
IPL
100
W2
SIL
1
E
2
N/
A
G2
IPL
100
W2
SIL
-
2. Same as above
Required Actions
(SIL)
PMC
Function: 6. On high high LNG tank T-001 pressure PT-210A/B/C during unloading, shutdown cooling line return to the tank
Function: 6. On high high LNG tank T-001 pressure PT-210A/B/C during unloading, shutdown cooling line return to the tank
Initiator: PT-210A/B/C (2oo3)
Final Element: Close SDV-238 (2oo2 for Phase 1 and 3oo3 for Phase 2 as all tanks will be pressure balanced)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. To prevent
overpressure of LNG
tank T-001 (HP pump
trip case)
1. PCV-292 (design
cases: three
compressors not
running, and two ships
unloading). (no credit
taken as it is not a
design for this case)
S
3
SIL
A1
N/
A
IPL
0
W2
SIL
3
2. PSV-017 (design
cases:3 percent of tank
inventory, which is the
governing case and
including the scenario)
(no credit taken as it is
not a design for this
case)
1. PCV-292 (design
cases: three
compressors not
running, and two ships
unloading).(no credit
taken as it is not a
design for this case)
Required Actions
(SIL)
3. Review whether
additional SDV could
be implemented on
the common drain
line as SIL 1 may be
difficult to be
achieved during
Phase 2.
4. Check sizing of
PSVs for backflow
case from the HP
header. This can
reduce SIL level to
SIL 1 if credit can be
taken for the PSVs.
2. Same as above
2. To prevent venting of
natural gas to the
atmosphere (HP pump
trip case)
S
/
E
E
2
N/
A
G2
IPL
0
W2
SIL
2
S
2
A1
G2
IPL
0
W2
SIL
1
PMC
Function: 6. On high high LNG tank T-001 pressure PT-210A/B/C during unloading, shutdown cooling line return to the tank
Initiator: PT-210A/B/C (2oo3)
Final Element: Close SDV-238 (2oo2 for Phase 1 and 3oo3 for Phase 2 as all tanks will be pressure balanced)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
S
/
E
SIL
E
1
N/
A
G2
IPL
0
W2
SIL
1
2. PSV-017 (design
cases:3 percent of tank
inventory, which is the
governing case and
including the scenario)
(no credit taken as it is
not a design for this
case)
2. Same as above
Required Actions
(SIL)
PMC
Function: 7. On high high LNG tank T-001 level LT-202/203/204, shutdown unloading line (unloading mode)
Function: 7. On high high LNG tank T-001 level LT-202/203/204, shutdown unloading line (unloading mode)
Initiator: LT-202/203/204(2oo3)
Final Element: Close SDV-080/082 (2oo2); Close SDV-045/025/055 (3oo3) (these valves are provided with a bypass used for initial cooldown.); Close SDV-225 (1oo1); Overall 1oo3
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. To prevent overfilling
of LNG tank T-001
(unloading mode)
2. Same as above
S
/
E
SIL
S
3
A1
N/
A
IPL
10
W2
SIL
2
E
2
N/
A
G2
IPL
10
W2
SIL
1
Required Actions
(SIL)
PMC
Function: 8. On high high LNG tank T-001 level LT-202/203/204, shutdown unloading line (transfer mode)
Function: 8. On high high LNG tank T-001 level LT-202/203/204, shutdown unloading line (transfer mode)
Initiator: LT-202/203/204(2oo3)
Final Element: Close SDV-225 (1oo1)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. To prevent overfilling
of LNG tank T-001
(transfer mode)
2. Same as above
S
/
E
SIL
S
3
A1
N/
A
IPL
10
W1
SIL
1
E
2
N/
A
G2
IPL
10
W1
SIL
-
Base frequency is W2
reduced by one level to
account for infrequent
operations.
A1 selected for seldom
presence of the operator
in this area.
S3 selected for breach in
the tank roof.
Required Actions
(SIL)
PMC
Function: 9. On low low LNG tank T-001 level LT-204, shutdown in-tank LNG pumps
Function: 9. On low low LNG tank T-001 level LT-204, shutdown in-tank LNG pumps
Initiator: LT-204(1oo1)
Final Element: Shutdown XA-227A (in-tank LNG pump P-001A) (typical) (1oo1)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. To prevent in-tank
pumps running dry
Cavitation leading to
vibration and damage to
the pump. Since pump is
mounted inside the tank,
no hazard impact outside.
Default SIL1 is assigned
to protect the pump.
S
/
E
SIL
SIL
1
Required Actions
(SIL)
PMC
Function: 10. On low low LNG tank T-001 level LT-204, shutdown all the dedicated in-tank LNG pumps (synergetic case)
Function: 10. On low low LNG tank T-001 level LT-204, shutdown all the dedicated in-tank LNG pumps (synergetic case)
Initiator: LT-204(1oo1)
Final Element: (not applicable, synergetic case)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
Since this function is provided for equipment protection, a default SIL1 is taken. Also, refer to Function 9.
S
/
E
SIL
Required Actions
(SIL)
PMC
Demand Scenario
CoFoD
IPLs
1. To prevent the
vacuum in the LNG tank
from damaging the tank
1. Tank pressure
control valve (PV-290)
(size for this scenario,
Phase 2, 54t/hr) (no
credit taken)
2. Vacuum breaker
provided (PSV-018A-F)
only one credit give
conservatively as
during Phase 2 vacuum
breakers are designed
for 2 compressors
running and assuming
all tanks are in
operation. There are
maybe some scenarios
during Phase 2 where
only one tank is in
operation.
S4 selected to the
potential collapse of the
shell side.
S
/
E
SIL
S
4
N/
A
N/
A
IPL
10
W2
SIL
3
Required Actions
(SIL)
1. Review the
requirement to stop
the in-tank pumps on
low pressure since in
the case of PC-292
malfuntions, this
interlock is expected
to shutdown all the
in-tank LNG pumps
and therefore gas
injection through PV290 cannot be relied
on. Shutting down
the BOG ompressors
may be sufficient.
Consider keeping at
least one LP pump
running. This will
reduce SIL by one
level.
PMC
Function: 12. On high high intank LNG pump P-001A discharge pressure
Function: 12. On high high intank LNG pump P-001A discharge pressure
Initiator: PT-228A (1oo1)
Final Element: Stop XA-227A (shutdown in-tank LNG pump P-001A) (1oo1)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. Minimum flow
protection
2. Overload protection
for the pump
3. CPMS
S
/
E
SIL
SIL
1
Required Actions
(SIL)
PMC
Function: 13. On low low intank LNG pump P-001A discharge pressure,
Function: 13. On low low intank LNG pump P-001A discharge pressure,
Initiator: PT-228A (1oo1)
Final Element: Stop XA-227A (shutdown in-tank LNG pump P-001A) (1oo1)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. Design intent for this function is not clear, hence, no classification was undertaken. See recommendation 2
S
/
E
SIL
Required Actions
(SIL)
2. Review the
requirement for this
interlock (PALL from
PT-228A).
PMC
Function: 14. On high high level BOG compressor suction drum LT-307A/B/C
Function: 14. On high high level BOG compressor suction drum LT-307A/B/C
Initiator: LT-307A/B/C(2oo3)
Final Element: UA-325/355 (shutdown BOG compressor C-001A/B) (1oo1)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. TCV-309 malfunction
2. Same as above
S
/
E
SIL
S
2
A1
G2
IPL
10
W2
SIL
-
E
1
N/
A
G2
IPL
10
W2
SIL
-
Required Actions
(SIL)
PMC
Function: 15. On high high level BOG compressor suction drum LT-307A/B/C (synergetic case)
Function: 15. On high high level BOG compressor suction drum LT-307A/B/C (synergetic case)
Initiator: LT-307A/B/C(2oo3)
Final Element: (synergetic case)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. TCV-309 malfunction
2. Same as above
S
/
E
SIL
S
3
A1
N/
A
IPL
10
W2
SIL
2
E
1
N/
A
G2
IPL
10
W2
SIL
-
Required Actions
(SIL)
PMC
Function: 16. On high high BOG compressor C-001A discharge temperature, shutdown BOG compressor C-001A
Function: 16. On high high BOG compressor C-001A discharge temperature, shutdown BOG compressor C-001A
Initiator: TT-337 (1oo1)
Final Element: Stop UA-325 (shutdown BOG compressor C-001A) (1oo1)
Existing Safeguards
Design Intent
1. To protect against
damage to compressor
Demand Scenario
CoFoD
High temp. at compressor
discharge leading to
potential damage to
compressor
IPLs
1. TC-309 at suction
drum / TI-328 at
compressor suction
S
/
E
1. TC-309 at suction
drum / TI-328 at
compressor suction
2. High temp. alarm at
discharge, TI-336
SIL
Required Actions
(SIL)
PMC
Function: 16. On high high BOG compressor C-001A discharge temperature, shutdown BOG compressor C-001A
Initiator: TT-337 (1oo1)
Final Element: Stop UA-325 (shutdown BOG compressor C-001A) (1oo1)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
S
/
E
1. TC-309 at suction
drum / TI-328 at
compressor suction
2. High temp. alarm at
discharge, TI-336
SIL
Required Actions
(SIL)
PMC
Function: 16. On high high BOG compressor C-001A discharge temperature, shutdown BOG compressor C-001A
Initiator: TT-337 (1oo1)
Final Element: Stop UA-325 (shutdown BOG compressor C-001A) (1oo1)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
S
/
E
SIL
Required Actions
(SIL)
PMC
Demand Scenario
CoFoD
IPLs
1. To prevent HP pumps
running dry
2. Same as above
1. none
S
/
E
SIL
S
2
A1
G2
IPL
0
W2
SIL
1
E
1
N/
A
G2
IPL
0
W2
SIL
1
Required Actions
(SIL)
5. Confirm whether
underload protection
is provided for the
HP pumps.
PMC
Function: 18. On low low LNG recondenser V-002 liquid level (synergetic case)
Function: 18. On low low LNG recondenser V-002 liquid level (synergetic case)
Initiator: LT-0397A/B/C (2oo3)
Final Element: (synergetic case)
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. To prevent HP pumps
running dry
2. Same as above
1. none
S
/
E
SIL
S
3
A1
N/
A
IPL
0
W2
SIL
3
E
1
N/
A
G2
IPL
0
W2
SIL
1
Required Actions
(SIL)
PMC
Demand Scenario
CoFoD
IPLs
1. To prevent backflow
through the HP pumps
2. Same as above
S
/
E
SIL
S
2
A1
G2
IPL
10
W2
SIL
-
E
1
N/
A
G2
IPL
10
W2
SIL
-
2. Operator
interventions can
prevent ultimate
consequences by
closing the isolation
valves
Required Actions
(SIL)
PMC
Demand Scenario
CoFoD
IPLs
1. To prevent LNG to be
sent to flare
2. To prevent overfilling
of the recondenser
Level
build-up
in
recondenser could lead to
high pressure due to
blocked condition (as
BOG compressor and Intank pump go to shut-off
condition). Recondenser
designed for 19barg but
PSV set at 14.3barg.
LNG may get released
through PSV to flare
1. none
Level build-up in
recondenser could lead to
LNG going to warm areas
of piping, potential
thermal shock and
release of gas through
flange.
10
S
/
E
SIL
S
2
A1
G2
IPL
0
W3
SIL
1
E
1
N/
A
G2
IPL
0
W3
SIL
2
S
2
A1
G2
IPL
10
W3
SIL
1
E
1
N/
A
G2
IPL
10
W3
SIL
1
Required Actions
(SIL)
PMC
Function: 21. On high high LNG recondenser level (backflow to compressor case)
Function: 21. On high high LNG recondenser level (backflow to compressor case)
Initiator: LT-0398 (1oo1)
Final Element: Close SDV-379/383 (2oo2 for holding mode and 1oo1 for unloading mode). However, SDV-383 is only required to be closed in case of multiple HP pump trip, which is less likely.; Credit can also be
given to shutting down the LP pumps (flow from one LP pump is equivalent to 3 HP pump).
Existing Safeguards
Design Intent
Demand Scenario
CoFoD
IPLs
1. To prevent overfilling
of the recondenser
2. Same as above
Level build-up in
recondenser will lead to
pressure balance
between LP pumps and
compressor discharge
with eventual LNG
carryover to recirculation
line.
Potential overpressure of
the compressor suction.
S
/
E
SIL
S
3
A1
N/
A
IPL
10
W3
SIL
2
E
2
N/
A
G2
IPL
10
W3
SIL
2
Required Actions
(SIL)
PMC
Demand Scenario
CoFoD
IPLs
1. To prevent
overpressure of
recondenser
Potential overpressure of
recondenser since sendout gas header pressure
is 86 barg while
recondenser is only
design for 19 barg
Risk
Red.
Factor
100
S
/
E
SIL
S
3
A1
N/
A
IPL
100
W2
SIL
1
E
2
N/
A
G2
IPL
100
W2
SIL
-
S
3
A1
N/
A
IPL
100
W2
SIL
1
E
2
N/
A
G2
IPL
100
W2
SIL
-
2. Same as above
4. Same as above
Required Actions
(SIL)
PMC
Demand Scenario
CoFoD
IPLs
1. To prevent backflow
1. none
S
/
E
SIL
S
2
A1
G2
IPL
0
W2
SIL
1
E
1
N/
A
G2
IPL
0
W2
SIL
1
Required Actions
(SIL)
9. Consider not
shutting down all of
the HP pumps from
this interlock PT813A/B/C, or shutting
down HP pumps in
stages to prevent
backflow situation at
the pumps.