Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

The Colors and Markings in This Workbook Have The Following Meanings

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 22
At a glance
Powered by AI
The key takeaways are that a project cost estimate should include development costs, hardware costs, software costs, ongoing support costs, and administrative costs. The estimate should break down costs by project phase and task. A bottoms-up estimate should also be done for increased accuracy.

The main components of a project cost estimate are development effort, hardware costs, software costs, networks, ongoing support costs, and administrative costs not covered by typical overhead. The estimate should apportion costs across project phases and further break phases down into tasks with associated effort and cost estimates.

Some of the key considerations when estimating ongoing support costs include level of support, backup and maintenance, availability monitoring and correction, patching, hardware and storage requirements, disaster recovery, and depreciation costs. Items like user setup, password resets, archiving, and job scheduling should also be accounted for.

Estimating template guidelines

Start with "the Costs number" provided in the Business Case during Phase 0
Project Costs as defined in the Business Case template instructions are:
. any costs related to completing this project including: development costs,
software costs, hardware costs, etc. as well as ongoing support costs.

As a starting point, apportion the cost dollars across the Phases of the project. (Tops Down estimate)
Further breakdown the phases of the project into a task/activity list for each phase.
Estimate the effort & costs for the project against the task/activity list (see the "effort" tab)
(Consider the following areas in estimating your software development (or upgrade) project :)
Development Effort - (time*rate) by resource type, by project phase, by task/activity
Hardware Costs
Software Costs
Networks
On-going support Costs
Admin costs (above typical overhead)

For increased accuracy, re-estimate the project using a bottoms up approach and reconcile the major differences
between the Top down and the Bottoms up estimates.(Whenever possible seek an independent validation of the
estimate before providing it to your Client.)
Document the risks assessed and assumptions made that support the estimate.
The various tabs in this workbook are intended as aids in estimating I.S. projects.
Please note the various sample tables, and estimating checklists, used throughout the workbook are intended as
guidelines or examples for potential tables to be used for individual projects. In many cases, experienced
Project Managers will have far more sophisticated tables that will better serve the project. These should
definitely be substituted for the table in the workbook. Where the Project Manager does not have such an instrument,
the workbook tables might serve as a base for what is needed for the project being estimated.

The colors and markings in this workbook have the following meanings.
Green Cells = Calculated Numbers
Gray Cells = numbers or fields to be supplied by template user.
Other colors/patterns have no meaning other than formatting

See the estimating Workbook presentation for information on how to use the estimating tabs.

Pre-estimate checklist

Pre-estimate checklist:
Project Process

Requirements
Are the Project Requirements clearly documented and Understood?

Yes

No

(by both I.S. and the Client?)

Is the criteria for meeting each requirement defined?


Are the Project Requirements Baselined (Under change control)?
Is there a "Client approved" plan for Requirements changes?
Has a Requirements Traceability Matrix been developed?
Have the requirements been validated against the business objectives?
Have you considered all of the processes that must be followed during
the project life cycle?
Have you considered all of the interfaces that must be adhered to?

Scoping
Has a Statement of Work (SOW) been reviewed/approved by the Client
Has the Statement of Work been reviewed by the virtual
team partners?
Has a Work Breakdown Structure (WBS) been reviewed by the Client
Has the WBS been reviewed by the virtual team partners?

X
X
X
X
X
X
X

X
X
X
X

Risk
Has a formal Risk Assessment been done?
(including probability, impacts, avoidance & recovery)
Is there an approved Risk Management Plan?
Was a Client representative involved with the Risk Management Plan?
Were appropriate I.S. resources involved in the Risk Management Plan?

Environments
Is the process for identifying, acquiring, establishing, and verifying the
environment understood and included in the plans for the project?
Is the Development environment adequate to support the project?
Is the Operational environment adequate to support the project?

Staff
Are appropriate staff available for the project?
Are the resources committed to participate in the required activities?
Is there a training plan to cover deficiencies?

X
X
X
X

X
X
X

X
X
X

not
necessary

Project Assumptions

Replace this sheet with a "Project Assumptions" sheet.

ALWAYS include a complete description of the assumptions and dependencies that


support the estimate.

Assumptions
Estimating usually involves making assumptions. It is important to record these
assumptions. As the project progresses, the estimating assumptions should be
reviewed and revised. To whatever degree possible, the project's scope definition
should be included in the assumptions.
Assumptions can be recorded using a format similar to the following:

Assumption

A description of the assumption.

The part of the project to which this assumption applies. For


Applicability example, the assumption may apply to the whole project, or to just
a stage, such as Business Process Redesign.
Status

Indicates whether the assumption is still valid.

Resolution

Describes the resolution of any issues highlighted by the


assumption, if applicable.

The estimating assumptions can be combined with scheduling assumptions.

Project Estimate Summary

Department name

Project name/Number

Project Manager Name, PM

Date

Effort

Hardware

Software

NetWorks

On-going support

Admin costs not in overhead

Sub Total

Risk
Change

$
$

Total (includes Risk & Change)

Project Risk Factor


Project Change Factor

258262925.xlsx

01/24/2015

17:06:38

Total "Effort estimate"

Project Name/Number ______________


Project
Activity/Task
ID (#)

Project Activity/Task name/description

Resource
Resource
Quantity (by
type
type) *

rate per
hour

Effort
hours
required

Total

estimated
effort cost
(sub total)
$

Resource type

estimated

not
estimated *

IS Project Team
Project Manager
Project Leader
Analyst
Programmer
Tester
Documentation
Third Party Prime (e.g. EPIC, Origin, BaaN)
BaaN Core Program Interface Prime
Integration Partners Core
Integration Partner Non-Core

X
X
X
X
X
X
X
X
X
X

IS Support Functions
New Product Introduction (NPI) Prime
DBA
Processing Services Prime
Desktop Prime
Networking Services Prime
Vendor Management Prime
Deployment Prime
Captive Office Prime
Functional Design Expert
Detail Design Expert

X
X
X
X
X
X
X
X
X
X

IS Other
Configuration Management Prime
Client Manager
Internal Audit
Quality Assurance Prime
Product Prime
Program Office Prime
Release Manager

X
X
X
X
X
X
X

Client
Client Prime
DEM Prime
Process Prime

X
X
X

Resource type estimate checklist:

Indirect estimate checklist:

Indirect
Subject Matter Experts from Client Organizations
Subject Matter Experts from other IS depts.
Employee Advisory Committees
Client Advisory Committee
Vendor Management
Userid Administration
Data Standards Forum
Data Management
Architecture
Core Baan Program interface organization
Integration Testing

Item
Database Administration
Resource Management
Verification and Validation
Configuration Management
Quality Assurance/Facilitation
Electronic Data Interchange
New Product Introduction
Product Management
Core Baan Program Interfaces
Networking and Computing
Processing Services
Finance
Application Modifications - vendor
Third Party Suppliers(e.g. EPIC, Baan, Origin)
IS Skills Development
3rd party warranty support vs contracted support.
computer operations support
outsourced support
Level-1/Level-2 support

X
X
X
X
X
X
X
X
X
X

estimated

not
estimated *
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X

Project support estimate checklist:

Project Manager __________


Date __________
Remarks

timate checklist:

checklist:

stimate checklist:

Total "Hardware Cost estimate"

Sample table

Server Hardware

Price per
unit

Quantity

for development
for test
for training
for production
Total (Server)

Total
$
$
$
$
$

Desktop Hardware

Price per
unit

Quantity

for development
for test
for training
for production
Total (Server)

Supporting information
-

Total

Supporting information

$
$
$
$
$

Hardware estimate checklist:


Item
Cpu Hardware
Servers
Modem
Extraordinary power supply
needs
Backup Systems
Disaster Recovery Systems
Additional Memory
Processing Services
Disk Storage
Tape Backup
UPS
Switching devices
Routers
Racks

estimated

not
estimated *
X
X
X
X
X
X
X
X
X
X
X
X
X
X

Local taxes
shipping, handling(delivery)
installation

X
X
X

Total "Software Cost estimate"

Sample table
Server Software

Price per
unit

Quantity

for development
for test
for training
for production
Total (Server)

Total
$
$
$
$
$

Desktop Software

Price per
unit

Quantity

for development
for test
for training
for production
Total (Server)

Software estimate checklist:


Item

estimated

not
estimated *

Application Licenses
Security (Nortel.Access)
RDBMS Licences
Project specific Software tools
Application Mods - vendor
Any costs that this project must bear
to decommission Legacy Systems
Archiving
Communication SW (e.g. MQ Series)
Userid Administration

X
X
X
X
X
X

also include:
The number of licenses
Any installation costs

X
X
X

X
X
X

Supporting information
-

Total

Supporting information

$
$
$
$
$

S&H costs
support costs

X
X

Total "Network Cost estimate"

Server Network Price per


needs
unit

Quantity

for development
for test
for training
for production
Total (Server)

Total
$
$
$
$
$

Desktop
Price per
Network needs
unit

for development
for test
for training
for production
Total (Server)

Quantity

Supporting information
-

Total

Supporting information

$
$
$
$
$

Network estimate checklist:


Item
LAN
WAN
Routers
Dial-up Lines
Dedicated lines
Satellite
Ports
Phones
Controllers
Switches
SW licenses
Setting up Access (e.g. Secure ID)
Other security Firewall, etc.
Processing Services
(estimate 15-20% of the hardware costs per annum)

estimated

not
estimated *
X
X
X
X
X
X
X
X
X
X
X
X
X
X

Total "On-going support estimate"

On-Going support items

Supporting information

Disaster Recovery
Depreciation costs

"On-going" support estimate checklist:


Item

estimated

not estimated
*

Level-1/L-2 support (Level of service - Platinum, Gold, Silver, Bronze)


New user setup
X
Password/User ID restores
X
Archiving of data
X
Emergency Recovery
X
Data integrity issues
X
Regular Job scheduling
X
Ad-hoc production job scheduling requests
X
Report generation & Elimination
X
Procedures Clarification
X
Ticket Status Updates
X
Scheduled maintenance
X
Recovery from failed job
X
Information flow monitoring
X
Standard Backups (non-Mac or PC)
X
System Availability Monitoring & Correction
X
System Recovery
X
Disk space management (non-Mac or PC)
X
Basis Security Services and Precautions
X
Root Cause Analysis
X
Problem Resolution
X
Liason with DBA, Networks, Local I/S
X
Patch Maintenance
X
Time Zone Coverage
X
Multiple Site Support
X
Client - Support Communication
X
Site to Site Communication
X

Level - 3 Support (above items plus):


Bug fixes
Test Environment Costs
Pre-Implementation Support:
Product Support during SIT/BIT/NIT Testing
Release Strategy Support:
Bug and Enhancements
Implementation
Customization

X
X
X
X
X
X

"On-going" support estimate checklist: (cont'd)


Item

estimated

not estimated
*

GES Renderings:
Job scheduling
X
Scheduled maintenance
X
Standard Backups (non-Mac or PC)
X
System Availability Monitoring & Correction
X
OS Patch Maintenance
X
DBA:
Back-up
X
Scheduled maintenance
X
DB Availability Monitoring & Correction
X
DB Patch Maintenance
X
Network management:
Back-up
X
Scheduled maintenance
X
NW Availability Monitoring & Correction
X
NW Patch Maintenance
X
Hardware, Storage (DASD), etc. (requirements for near & long-term)
Lease Penalties
Disaster Recovery
Depreciation costs

Total estimate for


Admin costs not in overhead

Sample table
Admin items

Supporting information

Travel
Facilities(real estate)
etc.
$

"Admin costs not in Overhead" estimate checklist:


Item
Conferences
Internal or external
Face to Face meetings
Audio/Video teleconferences
Internal Audit

estimated

not
estimated *
X
X
X
X
X

Quality Assurance

extraordinary Communications
Printing (e.g. manuals, training material)
Project Website development and maintenance
Use of Learning Institute
Administration support
Marketing
Electrical work
network connections
lighting
furniture
special Air conditioning

X
X
X
X
X
X
X
X
X
X
X

Team recognition/celebration

Risk & Change

The following is provided as a basic template that may be used in the


analysis and documentation of project risks:

Probability of Occurrence
Risk
number

Activity/Requirement

low

medium

high

Impact
low

Planned Action

Risk
medium high no action type of action weight *

You might also like