DSA 152 Manual
DSA 152 Manual
DSA 152 Manual
ISSUED 5/1/2013
REVISED 6/1/2013
REVISED 10/8/2013
Authors:
Ryan Huxley, Senior Structural Engineer
Tom Burke, Fire & Life Safety Officer
James Schaible, Senior Architect
STATE OF CALIFORNIA
TABLE OF CONTENTS
PREFACE.............................................................................................. 1
1 ADMINISTRATION ............................................................................. 4
1.1 Project Inspection Card (IC) Correlation Matrix .......................................... 5
1.2 Jobsite Documents........................................................................................ 32
1.2.1 Required Prior to Construction ................................................................... 32
1.2.2 Required During Construction .................................................................... 32
1.2.2.1 Deferred Submittals ................................................................................. 35
1.2.2.2 Construction Change Documents, Type A ................................................ 35
1.2.2.3 Notice of Deviations/Resolution of Deviations........................................... 36
1.2.2.4 Interim Verified Reports ........................................................................... 36
1.2.3 Required After Construction Completion ................................................... 37
1.2.4 Codes and Referenced Standards .............................................................. 38
STATE OF CALIFORNIA
TABLE OF CONTENTS
2.1.3.2 Masonry Retaining Wall ........................................................................... 57
2.1.3.3 Concrete Retaining Wall .......................................................................... 58
2.1.4 Anchors........................................................................................................ 58
2.1.4.1 Soil Nails ................................................................................................. 59
2.1.4.2 Tie Backs................................................................................................. 59
2.1.4.3 Prestressed Rock and Soil Foundation Anchors ....................................... 59
STATE OF CALIFORNIA
TABLE OF CONTENTS
2.3.1.1 Cast In Place (CIP) Concrete ................................................................... 74
2.3.1.2 Prestressed/Post-tension Concrete .......................................................... 83
2.3.1.3 Precast Concrete ..................................................................................... 84
2.3.1.4 Concrete Walls ........................................................................................ 85
2.3.1.4.1 CIP................................................................................................................................ 85
2.3.1.4.2 Tilt-up ........................................................................................................................... 85
2.3.1.4.3 Shotcrete ..................................................................................................................... 86
STATE OF CALIFORNIA
TABLE OF CONTENTS
2.3.4.1.1 Beams........................................................................................................................122
2.3.4.1.1.1 Composite ..........................................................................................................122
2.3.4.1.1.2 Steel Joists/Joist Girders/Trusses ..................................................................123
2.3.4.1.2 Columns ....................................................................................................................125
2.3.4.1.2.1 Composite ..........................................................................................................125
STATE OF CALIFORNIA
TABLE OF CONTENTS
2.4.4.1.1.4 Special Truss Moment Frame (STMF) ..........................................................154
2.4.4.1.2 Braced Frame ...........................................................................................................154
2.4.4.1.2.1 Special Concentric Braced Frame (SCBF) ...................................................155
2.4.4.1.2.2 Ordinary Concentric Braced Frame (OCBF) ................................................156
2.4.4.1.2.3 Eccentric Braced Frame (EBF) .......................................................................156
2.4.4.1.2.4 Buckling Restrained Braced Frame (BRBF) .................................................156
2.4.4.1.3 Special Plate Shear Wall (SPSW).........................................................................156
2.4.4.1.4 Cantilever Column Systems ...................................................................................156
STATE OF CALIFORNIA
TABLE OF CONTENTS
2.5.2.3.1 Metal Suspension Systems for Lay-In Panel Ceilings .......................................164
2.5.2.3.2 Soffits .........................................................................................................................164
STATE OF CALIFORNIA
TABLE OF CONTENTS
3.3 Fire/Smoke Protection ................................................................................ 185
3.3.1 Fire/Smoke Alarms .................................................................................... 185
3.3.2 Automatic Fire Suppression Systems ...................................................... 187
3.3.3 Other Extinguishing Systems ................................................................... 194
3.3.4 Smoke Control Systems ............................................................................ 196
3.3.5 Fire-Rated Assemblies .............................................................................. 197
3.3.5.1 Walls ..................................................................................................... 197
3.3.5.2 Horizontal Projections ............................................................................ 199
3.3.5.3 Horizontal Assemblies Floor/Ceiling and Roof/Ceiling.......................... 200
3.3.5.4 Shaft Enclosures.................................................................................... 201
3.3.5.4.1 Elevators....................................................................................................................202
STATE OF CALIFORNIA
TABLE OF CONTENTS
4.2 Building ......................................................................................................... 224
4.2.1 Signage ...................................................................................................... 224
4.2.2 Hallways, Corridors, Vestibules ................................................................ 225
4.2.3 Ramps and Landings................................................................................. 225
4.2.4 Stairs and Landings................................................................................... 226
4.2.5 Elevators and Lifts..................................................................................... 226
4.2.6 Doors and Hardware .................................................................................. 227
4.2.7 Plumbing Fixtures ..................................................................................... 228
4.2.7.1 Drinking Fountains ................................................................................. 229
4.2.8 Cabinets and Counters .............................................................................. 229
4.2.9 Alarms and Fire Extinguishers.................................................................. 230
4.2.10 Public Telephones ................................................................................... 231
4.2.11 Restrooms................................................................................................ 232
4.2.11.1 Water Closet and Water Closet Compartments .................................... 232
4.2.11.2 Grab Bars ............................................................................................ 233
4.2.11.3 Accessories ......................................................................................... 233
4.2.11.4 Lavatories ............................................................................................ 234
4.2.11.5 Urinals ................................................................................................. 234
4.2.11.6 Showers and Locker Areas .................................................................. 235
STATE OF CALIFORNIA
TABLE OF CONTENTS
APPENDIX B REFERENCED DSA FORMS .................................. 313
ix
DIVISION OF THE STATE ARCHITECT
STATE OF CALIFORNIA
LIST OF FIGURES
Figure 2-1: Sand Cone ............................................................................................................................ 48
Figure 2-2: Nuclear Density Gage ......................................................................................................... 49
Figure 2-3: Improper Trench Location Due To Column Footing Proximity ..................................... 51
Figure 2-4: Commonly Specified Pipe and Trench Locations At Or Near Footings ...................... 51
Figure 2-5: Adjacent Footings Having Different Depths .................................................................... 62
Figure 2-6: Pipe Through/Below Footing.............................................................................................. 63
Figure 2-7: Damaged Reinforcement From Gradi ng Operations ..................................................... 71
Figure 2-8: Slump Test ............................................................................................................................ 75
Figure 2-9: Proper Concrete Cylinder Storage .................................................................................... 76
Figure 2-10: Improper Storage of Concrete Cylinders ....................................................................... 76
Figure 2-11: Example of a Common Pull Test Apparatus ................................................................. 76
Figure 2-12: Lack of Tight Formwork; Wood Stake in Concrete Problems .................................... 78
Figure 2-13: Common Conduit and Anchor Bolt Problems ............................................................... 80
Figure 2-14: Extreme Reinforcing Congestion .................................................................................... 81
Figure 2-15: Poor Consolidation and Honeycomb Problems ............................................................ 81
Figure 2-16: Poor Consolidation & Ensuing Repairs .......................................................................... 82
Figure 2-17: Poor Layout for Chord Steel Connection ....................................................................... 85
Figure 2-18: Verify Weld Lengths Per Requirements......................................................................... 85
Figure 2-19: Coordination Problems in Masonry for Conduits/Pipes............................................... 93
Figure 2-20: CMU Clearance at Bolt ..................................................................................................... 93
Figure 2-21: Cleanouts at Bottoms of Cells ......................................................................................... 94
Figure 2-22: Lacking Full Head Joint; Mortar Fins Excessive ........................................................... 94
Figure 2-23: Incorrect Out-Of-Plane Strap Placement ....................................................................... 95
Figure 2-24: Congested Reinforcing in Masonry ................................................................................ 95
Figure 2-25: PT Label and explanation of labeling ............................................................................. 96
Figure 2-26: Visually Graded Framing Grade Stamp Example ........................................................ 97
Figure 2-27: MSR/MEL Grade Stamp Example .................................................................................. 97
Figure 2-28: SCL Markings Example .................................................................................................... 98
Figure 2-29: Glulam Special Inspection Stamp Example .................................................................. 98
Figure 2-30: Example Wood Structural Panel Grade Stamp ..........................................................100
Figure 2-31: Moisture Meter .................................................................................................................101
Figure 2-32: Unacceptable Notching ..................................................................................................101
Figure 2-33: Improper Hanger Installation .........................................................................................106
Figure 2-34: Commonly Specified Bolt Placement Dimensions .....................................................108
Figure 2-35: Commonly Specified Pre-Drilling for Lag Screw ........................................................110
Figure 2-36: Toe Nailing Installation ...................................................................................................112
Figure 2-37: Improper Oversized A.B. Hole.......................................................................................113
Figure 2-38: Common Sill Plate Construction Problems .................................................................113
Figure 2-39: Improper HSB Storage ...................................................................................................121
x
DIVISION OF THE STATE ARCHITECT
STATE OF CALIFORNIA
LIST OF FIGURES
Figure 2-40: Skidmore / Wilhelm Machine .........................................................................................121
Figure 2-41: Twist-Off Type Tension Control Bolts ..........................................................................121
Figure 2-42: Improperly Match Marked/Torqued ..............................................................................121
Figure 2-43: Steel Joist Bridging..........................................................................................................124
Figure 2-44: Field Splice of Steel Joists .............................................................................................125
Figure 2-45: Oversized Torch Cut Hole ..............................................................................................129
Figure 2-46: Example of Corrosion Protection at Welded Studs ....................................................132
Figure 2-47: Single Jamb Supporting Header Insufficient - Multi-Stud Jamb Incorrect Location
....................................................................................................................................................................133
Figure 2-48: Incorrect Gap for Stud Bearing ......................................................................................134
Figure 2-49: Additional Top Seam Weld Due To Burn-Through ....................................................137
Figure 2-50: Good Deck Button Punch...............................................................................................137
Figure 2-51: Skewed Deck Edge Modifies Perimeter Welding Requirements .............................138
Figure 2-52: Concrete Deck Insert ......................................................................................................139
Figure 2-53: Conduit Causes Problems for Composite Action .......................................................139
Figure 2-54: Steel Reinforcing Mechanical Splices ..........................................................................140
Figure 2-55: Special A.B. Washer Plate Placement Requirements ...............................................145
Figure 2-56: Top Plate Splice Connection Problems .......................................................................145
Figure 2-57: Hold-Down Construction Problems ..............................................................................146
Figure 2-58: Wind Uplift Commonly Specified Nail Edge Distances at Wood Structural Panel
....................................................................................................................................................................147
Figure 2-59: NDT Special Inspector Markings ..................................................................................149
Figure 2-60: Erection Bolt Closing HSS Gap .....................................................................................155
Figure 2-61: Concrete Slab at Gusset Plate ......................................................................................155
Figure 2-62: Pendant Lights Missing Safety Cables ........................................................................160
Figure 2-63: Soffit Framing at Ducts and Primary Framing .............................................................165
Figure 2-64: Example of Soffit Bracing ...............................................................................................166
Figure 2-65: Thermal System...............................................................................................................168
Figure 2-66: Water Damage to Roof Framing ...................................................................................169
Figure 2-67: Attic Ventilation Holes .....................................................................................................172
Figure 2-68: Enclosed Rafter Space Ventilation Holes at Ridge ....................................................173
Figure 3-1: Rejected Sprinkler Pipe Due To Separation At Welds ................................................189
Figure 3-2: Examples of Fire/Smoke Rated Wall Identification ......................................................199
Figure 3-3: Fire Blocking At Floor Level & Curtain Wall ..................................................................201
Figure 4-1: Path Of Travel at Site Missing Items ...........................................................................218
Figure 4-2: Example Parking Signage ................................................................................................219
Figure 4-3: Incorrect Grating Type ......................................................................................................220
Figure 4-4: Curb Ramp Examples .......................................................................................................221
Figure 4-5: Gates ...................................................................................................................................223
xi
DIVISION OF THE STATE ARCHITECT
STATE OF CALIFORNIA
LIST OF FIGURES
Figure 4-6: Example of Stair and Directional Signage .....................................................................224
Figure 4-7: Example of Restroom Signage ........................................................................................224
Figure 4-8: Elevator In-Car Controls ...................................................................................................226
Figure 4-9: Door Handles......................................................................................................................228
Figure 4-10: "Convenience" Drinking Fountain Causing Accessibility Violations ........................229
Figure 4-11: Drinking Fountains ..........................................................................................................229
Figure 4-12: Example Accessible Lab Equipment ............................................................................230
Figure 4-13: Example of Visual Fire Alarm ........................................................................................231
Figure 4-14: Example Measurement of Maneuvering Clearances .................................................232
Figure 4-15: Example Measurement of Water Closet Centerline From Adjacent Wall...............233
Figure 4-16: Example Measurement of Lavatory Rim Height .........................................................234
Figure 4-17: Example Measurement of Lavatory Centerline From Adjacent Wall ......................234
Figure 4-18: Various Accessible Locker Types .................................................................................235
Figure 5-1: Improper Piping Location at AC Switch..........................................................................237
xii
DIVISION OF THE STATE ARCHITECT
STATE OF CALIFORNIA
LIST OF TABLES
Table 1-1: Project Inspection Card Correlation Matrix ....................................................................... 31
Table 2-1: AWPA Use Categories and Brief Description.................................................................102
Table 2-2: Standard Hex Bolt Dimensions .........................................................................................107
Table 2-3: Dimensions for Standard Hex Lag Screws .....................................................................110
Table 2-4: Dimensions for Standard Wood Screws..........................................................................111
Table 2-5: Minimum Nail Dimensions .................................................................................................112
Table 2-6: Standard Cut Washer Dimensions ...................................................................................144
Table 3-1: CBC Table 508.2.5 - Incidental Accessory Occupancies - Required Separations....182
Table 3-2: CBC Table 508.4 - Occupancy Separation Requirements...........................................183
Table 3-3: CBC Table 601 - Fire Rating Requirements for Building Elements ............................184
Table 3-4: CBC Table 707.3.9 - Fire Barrier Ratings .......................................................................197
Table 3-5: CBC Table 706.4 - Fire Wall Ratings Based on Occupancy........................................197
Table 3-6: CBC Table 602 - Exterior Wall Fire Rating Requirements ...........................................198
Table A0-1: DSA 103 Correlation Matrix ............................................................................................312
xiii
DIVISION OF THE STATE ARCHITECT
STATE OF CALIFORNIA
PREFACE
PAGE 1 OF 329
STATE OF CALIFORNIA
PREFACE
This manual provides detailed descriptions of documentation and inspection requirements to
properly fill in the DSA 152 Project Inspection Card (IC). Proper inspection of construction work
is a crucial component in the Division of the State Architect (DSA) certification process that
ensures compliance with the DSA approved construction documents. Project inspectors play a
significant role in construction inspection. Duties and responsibilities for inspectors and others
involved in the construction process for projects under DSA jurisdiction are outlined in California
Code of Regulations, Title 24, Part 1. Procedure PR 13-01 provides specific required duties of
the project inspector and others with respect to relevant portions of Title 24, Part 1, and the IC.
The DSA has also issued IR A-8, which provides further performance requirements of the
project inspector. (Additional information regarding construction phase duties for others involved
in the construction process is provided in IR A-24.) For projects in which an assistant inspector
is deemed necessary, refer to IR A-7 and IR A-12 for additional information and inspector
approval requirements.
Construction projects under DSA jurisdiction require constant inspection of construction. To
facilitate proper inspection and documentation for DSA construction projects, the DSA requires
the use of the IC, similar in nature to many building department building inspection cards. The
definitions provided in PR 13-01 apply to this document.
Broadly speaking, building construction inspection entails: 1) building component verification,
and 2) building component installation verification, both in accordance with the DSA approved
construction documents. Building component verification ensures that the proper specified
component is used in construction. Building component installation verification ensures that the
specified component is properly installed. These lead to two categorical elements that are
required prior to initialing the sections and blocks on the IC for a given building or site:
I. Receipt of documentation for constructed elements, including:
I.A. Material/structural tests
I.B. Special inspections or other observations
II. Inspection of items associated with constructed elements.
This document provides a detailed list of those documentation and inspection items based on
the different DSA review disciplines of Structural Safety, Fire/Life Safety, and Accessibility. An
additional category, Other Building Systems, is also provided, which captures other necessary
inspections to ensure proper building functioning. All of these are broken up further into specific
inspection areas frequently associated with construction projects under DSA jurisdiction. Based
on the particular applicable elements for a given project, all of the applicable documentation
items shall be collected and all applicable inspections listed shall be made by the project
inspector.
PAGE 2 OF 329
STATE OF CALIFORNIA
PREFACE
If construction does not comply with the approved construction documents, DSA may issue a
Stop Work Order, or similar type of action, to halt work on the construction (IR A-13).
Improper inspection or inspection related documentation can lead to rescinding of a project
inspectors certification (IR A-7).
Authors
This manual was authored and compiled by Ryan Huxley, Senior Structural Engineer, with
contributions from Tom Burke, Fire& Life Safety Officer, for the Fire/Life Safety Inspection Items
and James Schaible, Senior Architect, for the Access Compliance Inspection Items.
Direct any correspondence related to improving this manual to Ryan.Huxley@dgs.ca.gov.
PAGE 3 OF 329
STATE OF CALIFORNIA
1 ADMINISTRATION
PAGE 4 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
1.1 Project Inspection Card (IC) Correlation Matrix
The information that follows in the correlation matrix provides a link between the sign-off blocks
in the IC and the documentation and inspection items in this manual. Prior to the project
inspector initialing any of the IC blocks, the documentation and inspections associated with the
topics listed in the correlation matrix must be received and occur, respectively.
The following provides a summary of typical construction components and systems that are
associated with each section/block in the IC. While the listing is not comprehensive, it provides
a good foundation for understanding of and consistency in the use of the IC.
Block 4 Utilities:
FLS Utilities/Systems
MEP Utilities/Systems
MEP Vaults
Thrust Blocks
Block 6 Forms:
Foundation Systems
Driven Piles
Formwork
FLS Systems
MEP Systems
Waterproofing/Vapor Barrier
PAGE 5 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Section 2 - Vertical and Horizontal Framing
Block 8 Foundation Concrete:
Verify Foundation Is Compliant
(concrete 28 day strength, etc.)
Blocks 13 - 15 Concrete, Wood, Steel:
Floors
Roofs
Section 3 Appurtenances
Block 16 Ceilings:
Ceilings
Soffits
Suspended Baffles
Walls
Shafts
Floors
Roofs
Ceilings
Doors
Fire Doors
Windows
Penetrations
Dampers
Fire-Proofing
Storefront/Window Walls
Veneer
Precast Concrete Panels
Wall Finishes
(stucco/plaster/wood/aluminum/etc.)
Manufactured Systems (EFIS, GRFC,
etc.)
Block 19 Fire Alarms:
Fire/Smoke Alarm System (includes
support, anchorage, bracing, etc.)
Block 20 Automatic Fire Suppression
Systems:
Sprinklers
Chemical
Deluge
Water Curtains
Extinguishers
Support/Bracing/Anchorage of AFSS
PAGE 6 OF 329
STATE OF CALIFORNIA
Support/Bracing/Anchorage for:
MEP
Equipment
HVAC System
Ducts
Electrical
Pendant Lights
Transformers
Switch Gears
IDF/MDF/etc.
Pipes
Tanks
Block 24 Flatwork:
Finish Grades
Grading for Accessible POT System
Grading for Run-off (drainage)
Block 25 Parking:
Drop-off
Accessible parking
Stripping
Signage
Truncated Domes
Egress Components
Doors
Gates
Emergency Lighting
Building Signage
Site Signage
Elevators
Hazardous Materials
PAGE 7 OF 329
STATE OF CALIFORNIA
Building Signage
Site Signage
Drinking Fountains
Accessible POT Systems
Stairs
Ramps
Walks
Doors
Gates
Elevator
Specialty Areas (restrooms, kitchens, casework, etc)
Note that due to the nature of the items listed in the correlation matrix and extent over which
they apply during construction, some items occur in multiple locations in the matrix. For
example, in a concrete building, some of the same concrete sections in this manual apply to the
foundation as well as the vertical and horizontal framing. In each case, while the type of
documentation and inspections are similar, they are particular to the specific stage of
construction occurring.
For projects consisting of large buildings with multiple phases, some method of
acknowledgement for incremental inspection verification at certain locations within the building
may be necessary, even though construction is not yet complete. How this is accomplished is
left to the agreements made between individuals involved with the construction, observation,
and inspection of the project. One possible method to address this issue is to use a copy of the
approved construction documents for identification of specific areas that have been inspected,
thereby allowing construction to progress in desired areas. It is important to note that the IC
should not be initialed until all construction associated with a particular inspection item is
complete.
There are abbreviations used in the correlation matrix, which are described below:
Comp. Cat.: Compliance Category
A: Administration
SS: Structural Safety Inspection Items
FLS: Fire/Life Safety Inspection Items
ACS: Access Compliance Inspection Items
PAGE 8 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Mass Grading
Building Pad
Block
Section
PAGE 9 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Drainage Devices
Utilities
Block
Section
PAGE 10 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Excavations
Block
Section
PAGE 11 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Forms
Block
Section
PAGE 12 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Steel Reinforcement
Foundation Concrete
Block
Section
PAGE 13 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Concrete
Block
Section
PAGE 14 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Section
Block
PAGE 15 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Masonry
Block
10
Section
PAGE 16 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Wood
Block
11
Section
PAGE 17 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Steel
Block
12
Section
PAGE 18 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Concrete
Block
13
Section
PAGE 19 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Wood
Block
14
Section
PAGE 20 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Steel
Block
15
Section
PAGE 21 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Section
Block
SS
FLS
Ceilings
16
Section 3
Appurtenances
ACS
PAGE 22 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Section
Block
PAGE 23 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
18
Rated
Assemb
lies
Exterior Cladding
Block
17
Section
PAGE 24 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
Section
Block
PAGE 25 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
19
Fire Alarms
Fire Suppression
Block
20
Section
PAGE 26 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
M/E/P (Structural)
Block
21
Section
PAGE 27 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
22
M/E/P (FLS)
Fine Grading
Block
23
Section
PAGE 28 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
25
Parking
26
Fire
Lane
Flatwork
Block
24
Section
PAGE 29 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
27
Structural
FLS
Block
28
Section
PAGE 30 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
ACS
Block
29
Section
PAGE 31 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
1.2 Jobsite Documents
There are many documents that must be present at the jobsite during construction. The next
several subsections provide a brief list of those documents that must be on site during the
construction process.
PAGE 32 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
I.B. Test reports indicate if tests performed show compliance with requirements given in
the DSA construction documents. While there is no required format for test reports
(suggested formats can be found in the following forms based on the type of
material and structural test performed), the information noted in these shall be
provided (refer to APPENDIX B REFERENCED DSA FORMS on page 313 or
http://www.dgs.ca.gov/dsa/Forms.aspx for these forms):
I.B.1. DSA 201: Soil Compaction
I.B.2. DSA 202: Sieve Analysis
I.B.3. DSA 203: Tension/Bend
I.B.4. DSA 204: Compression
I.B.5. DSA 205: Concrete Masonry Unit
I.B.6. DSA 206: Anchor Load
I.B.7. DSA 207: Masonry Core Shear/Compression
I.B.8. DSA 208: High Strength Bolt
I.B.9. DSA 209: Fireproofing Density
I.B.10. DSA 210: Ultrasonic (NDT)
I.B.11. DSA 211: Additional Comments
I.C. For additional information on structural testing, refer to the following IRs (additional
information related to some of these IRs and others not shown will be provided
later in this document at appropriate locations):
I.C.1. IR A-15: Testing and Inspection of Remotely Fabricated Structural
Elements
I.C.2. IR 17-1: Sampling and Testing of Structural Materials
I.C.3. IR 17-2: Nondestructive Testing
I.C.4. IR 17-4: Basics of Structural Tests and Special Inspections
I.C.5. IR 17-5: Structural Testing Laboratory Responsibilities
I.C.6. IR 17-7: Soils and Foundations Testing and Inspection
I.C.7. IR 17-8: Sampling and Testing of High Strength Bolts, Nuts, and Washers
I.C.8. IR 17-10: Sampling, Testing and Tagging of Reinforcing Bars
II. Special Inspection Documentation:
II.A. Verify current certification for all special inspectors working on the jobsite prior to
commencing construction that requires special inspection.
II.A.1. Concrete:
II.A.1.1. Verify ACI certification for shotcrete. (See
https://www.apps.dgs.ca.gov/Tracker/InspByCategory.aspx?Id=1
0 for a list of DSA approved shotcrete special inspectors.)
II.A.2. Masonry:
II.A.2.1. Verify certification for masonry special inspectors. (See
https://www.apps.dgs.ca.gov/Tracker/InspByCategory.aspx?Id=0
4 for a list of DSA approved masonry special inspectors.)
II.A.3. Wood:
II.A.3.1. Verify certification for glulam special inspectors. (See
https://www.apps.dgs.ca.gov/Tracker/InspByCategory.aspx?Id=0
2 for a list of DSA approved glulam special inspectors.)
II.A.4. Steel:
PAGE 33 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
II.A.4.1. Verify Structural Steel and Bolting ICC certification (S1) (refer to
IR 17-9 for additional information).
II.A.4.2. Verify American Welding Society (AWS) certified welding
inspector (CWI) or senior certified welding inspector (SCWI) for
welding inspectors (welding certification can be verified by going
to http://www.aws.org/w/a/certification/search.html).
II.A.4.2.1. AWS-CAWI (Certified Associate Welding Inspector) is
not acceptable AWS-CWI is the minimum requirement.
II.A.5. In-Plant constructed items:
II.A.5.1. Verify certification for in-plant inspectors. (See
https://www.apps.dgs.ca.gov/Tracker/InspByCategory.aspx?Id=0
3 for a list of DSA approved in-plant inspectors.)
II.B. Verify special inspectors have a copy of the appropriate portion of the DSA
approved construction documents. (Note: While shop drawings are often used for
fabrication, if any conflicts or uncertainties occur, the DSA approved construction
documents govern, not the design professional reviewed shop drawings.)
II.C. Special inspection reports:
II.C.1. While DSA does not have a required format, certain pieces of information
are required. Refer to DSA 250: Special Inspection Report for a suggested
general format and required content (refer to APPENDIX B
REFERENCED DSA FORMS on page 313 for forms). While special
inspections are provided by the special inspectors, oversight and
verification of such inspections by the project inspector is required. The
project inspector must become familiar with the required testing and
special inspection program for the project. For additional information
regarding special inspector duties and responsibilities, refer to IR 17-6:
Structural Special Inspector Duties and Responsibilities.
III. Project Inspector Documents
III.A. In addition to the items noted above and below, the project inspector must also
keep a job file containing various documents at the jobsite. Refer to IR A-8 and PR
13-01 for additional information.
III.B. Project Inspector Notifications (see DSA 151)
III.C. Refer to 1.2.2.3 Notice of Deviations/Resolution of Deviations on page 36 (see
DSA 154.
III.D. Completed semi-monthly reports (see DSA 155).
III.E. Additional documents required when the project inspector performs any special
inspections or aspects of structural testing:
III.E.1. Special Inspection:
III.E.1.1. The DSA 103 form provides direction for which special
inspections shall be performed by the project inspector or special
inspector. It is permitted for the project inspector to provide
special inspection if they have prior written approval by DSA.
(Refer to 1.2.3 Required After Construction Completion below for
additional required documentation related to special inspections
performed by the project inspector.)
PAGE 34 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
III.E.2. Structural Testing:
III.E.2.1. For a minor scope of work, if the project inspector provides any
sampling, protection, handling, transporting, and/or storage of
test specimens for the project (note: prior written permission by
the DSA Field Engineer is required), such tasks must be
specifically identified on the DSA 6-PI form. (See IR 17-1 for
additional information.)
IV. Other Documents
IV.A. Contractor submittals (e.g. construction schedules, design professional approved
shop drawings, certificates, product labels, concrete trip tickets, etc.).
IV.A.1. Notification to Project Inspector for the completion of construction at
appropriate phases of construction consistent with DSA 152 sections and
as indicated in PR 13-01 (see DSA 156).
IV.B. Refer to the following for additional information:
IV.B.1. 1.2.2.1 Deferred Submittals on page 35
IV.B.2. 1.2.2.2 Construction Change Documents, Type A on page 35
IV.B.3. 1.2.2.4 Interim Verified Reports on page 36.
IV.C. Proprietary Product Documents
IV.C.1. Refer to 1.3 Proprietary Products on page 40 for additional information.
V. Depending on the nature of the construction work, portions of the work may be complete
and documents associated with construction completion may be required even though
overall construction is ongoing. Refer to 1.2.3 Required After Construction Completion on
page 37 for additional information.
1.2.2.1 Deferred Submittals
A deferred submittal (DS) represents a portion of the construction that cannot be fully detailed
on the originally approved drawings because of variations in product design and manufacture.
Approval of plans for such a portion may be deferred until the material suppliers are selected.
All DS documents are listed on the DSA approved drawings. Any modifications to the
approved list of DS documents must be reviewed and approved by DSA prior to commencing
construction.
1.2.2.2 Construction Change Documents, Type A
In November 2012, a significant change occurred in the requirements for submitting and
approving construction changes to DSA approved projects. (Refer to IR A-6 and bulletin BU
12-03 for additional information.)
After a contract for the work has been let, changes to the approved construction documents
shall be made by means of Construction Change Documents (CCD). It is the responsibility of
the design professional in general responsible charge to determine if changes affect the
Structural, Access or Fire & Life Safety portions of the project. The CCD process replaces the
DIVISION OF THE STATE ARCHITECT
PAGE 35 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
need to submit change orders. Thus for projects subject to the CCD process, change orders
are not required to be submitted to DSA.
Changes to or affecting the Structural, Access or Fire-Life Safety Portions of the Project:
These changes shall be classified as CCD Category A.
CCD Category A are required to be submitted to and approved by the DSA prior to
commencement of the affected work.
CCD Category A must be submitted to the DSA using the CCD Category A form, DSA
140.
Changes not affecting the Structural Safety, Access Compliance or Fire & Life Safety portions
are classified as CCD Category B. These are not required to be submitted to the DSA unless
specifically required, in writing, by DSA.
1.2.2.3 Notice of Deviations/Resolution of Deviations
When the Project Inspector or DSA district field engineer identifies deviations from the DSA
approved construction documents the inspector must verbally notify the contractor.
(Deviations include both construction deviations and material deficiencies.) If the deviation is
not immediately corrected, the inspector is required to promptly issue a written notice of
deviation to the contractor, with a copy sent to the responsible design professional(s) and the
DSA on form DSA 154. Deviations must be resolved prior to commencement of work that will
cover up the deviant work.
When the noticed deviation is corrected, the inspector is required to promptly issue a written
notice of resolution to the contractor, with a copy sent to the responsible design professional(s)
and the DSA. The notice of resolution of deviations must be made using the original form DSA
154 that reported the deviation.
1.2.2.4 Interim Verified Reports
Prior to the Project Inspector intialing some blocks and any section of the Inspection Card
(Form DSA 152), Interim Verified Reports (IVR) are required noted in PR 13-01 and as follows:
I. Interim Verified Reports (IVR)
I.A. Architect/Engineer IVR (form DSA 6-AE):
I.A.1. Architect IVR is required for all sections.
I.A.2. Structural, electrical, mechanical engineers IVR required for any sections
containing work for which, in the plans, the engineer has affixed his/her
seal (stamped).
PAGE 36 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
I.B. Geotechnical engineer IVR (form DSA 293):
I.B.1. Geotechnical engineer IVR is required for any block and/or section relative
to geotechnical work.
I.C. In-plant inspector IVR (form DSA 6-PI)
I.C.1. For relocatable buildings constructed in the plant and being delivered to the
job site, the in-plant inspector IVR (or final verified report) is require for
each separate building for any sections affected by the siting of the
relocatable buildings.
I.D. Special inspectors IVR (form DSA 292 or DSA 291).
I.D.1. Special inspectors contracting directly and individually with the school
board IVR (form DSA 292) is required for any block or section requiring
special inspection work.
I.D.2. Special inspectors provided by the laboratory of record IVR (form DSA
291) is required for any block or section requiring special inspection work.
I.E. Laboratory of record IVR (form DSA 291).
I.E.1. Laboratory of record IVR is required for any block and/or section
containing required testing.
PAGE 37 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
1.2.4 Codes and Referenced Standards
The following is a partial list of applicable codes that the inspector must have available at the
jobsite (many are also available online, such as the 2010 versions at
http://publicecodes.cyberregs.com/st/ca/st/CA-P-2010-000008.htm) refer to the approved
construction documents for the applicable codes and reference standards:
I. Codes:
I.A. 2013 Versions:
I.A.1. 2013 Building Standards Administrative Code, Part 1, Title 24 C.C.R.
I.B. 2010 Versions:
I.B.1. 2010 Building Standards Administrative Code, Part 1, Title 24 C.C.R.
I.B.2. 2010 California Building Code (CBC), Part 2, Title 24 C.C.R.
I.B.3. 2010 California Electrical Code (CEC), Part 3, Title 24 C.C.R.
I.B.4. 2010 California Mechanical Code (CMC) Part 4, Title 24 C.C.R.
I.B.5. 2010 California Plumbing Code (CPC), Part 5, Title 24 C.C.R.
I.B.6. 2010 California Energy Code (CEC), Part 6, Title 24 C.C.R.
The following is a list of codes and standards that the project inspector should have access to
if needed for the project:
I. Codes:
I.A. 2010 Versions:
I.A.1. 2010 California Fire Code, Part 9, Title 24 C.C.R.
I.A.2. 2010 California Green Building Standards Code (CALGreen), Part 11, Title
24 C.C.R.
I.A.3. 2010 California Referenced Standards, Part 12, Title 24 C.C.R.
I.A.4. Title 19 C.C.R., Public Safety, State Fire Marshal Regulations.
II. Standards
II.A. NFPA (these standards are available online for reading only, but do require a free
registration: http://www.nfpa.org/aboutthecodes/list_of_codes_and_standards.asp;
frequently the CBC amends portions of the NFPA standards referenced below for
example, refer to 2010 CBC (SFM) Chapter 35 where noted below; additional
reference standards will be referenced later in this manual at appropriate
locations):
II.A.1. 2010 Versions:
II.A.1.1. 2010 NFPA 13 Automatic Sprinkler Systems (CA Amended)
II.A.1.2. 2007 NFPA 14 Standpipe Systems (CA Amended)
II.A.1.3. 2002 NFPA 17A Wet Chemical Systems
II.A.1.4. 2007 NFPA 20 Stationary Pumps
II.A.1.5. 2010 NFPA 24 Private Fire Mains (CA Amended)
II.A.1.6. 2010 NFPA 72 National Fire Alarm Code (CA Amended)
II.A.1.7. 2007 NFPA 80 Fire Door and Other Opening Protectives
PAGE 38 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
II.A.1.8. 2008 NFPA 2001 Clean Agent Fire Extinguishing Systems (CA
Amended)
II.B. Structural Standards will be referenced in applicable sections later in this
document.
It is important to note that with the publication of the 2010 CBC, unlike kindergarten through
twelfth grade projects, Community Colleges now have an option for which chapters of the
building code will be the basis of design for a given project. These are primarily related to
structural items and, thus, will be discussed further in the Structural Safety Items portion of this
manual.
PAGE 39 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
PAGE 40 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
I.E.1. If information is not contained on the contract documents, obtain
information from the supplier or from the online FM Approval Guide
previously noted.
I.F. Products or assemblies approved by other DSA recognized agencies
I.F.1. If information is not contained in the contract documents, obtain information
from the supplier or from the referenced report.
II. Inspection of the following items:
II.A. Proprietary Products:
II.A.1. Confirm product complies with approved construction documents.
II.A.2. Proper storage and care for product.
II.A.3. Products with an ICC ES report:
II.A.3.1. Product used complies with the manufacturers and ICC ES report
installation guidelines (refer to Section 4 and 5 of the ICC ES
report). Where conflicts occur, the ICC ES report governs (refer
to Section 5 in the ICC ES report).
II.A.3.1.1. Surrounding construction complies with requirements
(i.e. ICC ES reports frequently indicate minimum
member, fastener, and/or material requirements for
products attached to the structure).
II.A.4. Products or assemblies with an UL listing:
II.A.4.1. Product used complies with UL listing requirements and be
installed as indicated in the listing.
II.A.4.1.1. Surrounding construction complies with requirements
(i.e. UL listings frequently indicate minimum member,
fastener, and/or material requirements for products
attached to the structure).
II.A.5. Products or assemblies approved by FM:
II.A.5.1. Product used complies with FM listing requirements and be
installed as indicated in the listing.
II.A.6. Products or assemblies approved by other DSA recognized agencies:
II.A.6.1. Product used complies with referenced report requirements and
be installed as indicated in the report.
PAGE 41 OF 329
STATE OF CALIFORNIA
ADMINISTRATION
PAGE 42 OF 329
STATE OF CALIFORNIA
PAGE 43 OF 329
STATE OF CALIFORNIA
PAGE 44 OF 329
STATE OF CALIFORNIA
2.1.1 Grading
There are many items that must be inspected during the grading phase of a project. Those are
listed below based on their applicability to site work and building work.
2.1.1.1 Site
I. Receipt of documentation for constructed elements:
I.A. Receipt of project soils report, when part of the approved construction documents.
PAGE 45 OF 329
STATE OF CALIFORNIA
PAGE 46 OF 329
STATE OF CALIFORNIA
PAGE 47 OF 329
STATE OF CALIFORNIA
PAGE 48 OF 329
STATE OF CALIFORNIA
PAGE 49 OF 329
STATE OF CALIFORNIA
PAGE 50 OF 329
STATE OF CALIFORNIA
PAGE 51 OF 329
STATE OF CALIFORNIA
PAGE 52 OF 329
STATE OF CALIFORNIA
PAGE 53 OF 329
STATE OF CALIFORNIA
PAGE 54 OF 329
STATE OF CALIFORNIA
PAGE 55 OF 329
STATE OF CALIFORNIA
PAGE 56 OF 329
STATE OF CALIFORNIA
PAGE 57 OF 329
STATE OF CALIFORNIA
2.1.4 Anchors
Similar to the Grading section, the majority of the documentation and inspection items
frequently defer to the geotechnical engineer. Therefore, refer to 2.1.1 Grading on page 45 for
PAGE 58 OF 329
STATE OF CALIFORNIA
PAGE 59 OF 329
STATE OF CALIFORNIA
PAGE 60 OF 329
STATE OF CALIFORNIA
PAGE 61 OF 329
STATE OF CALIFORNIA
PAGE 62 OF 329
STATE OF CALIFORNIA
I.G. When portions of the foundation types below may qualify as deep foundation
elements, refer to 2.2.2.2 Cast-In-Place Deep Foundations (Piers) subsection I.B.2
on page 69 for additional information.
2.2.1.1.1 Footings
For footings acting as a pile cap, refer to 2.2.1.1.4 Pile Caps on page 64 for information. For
other requirements, refer to the general requirements specified in 2.2.1.1 Concrete
Foundations.
PAGE 63 OF 329
STATE OF CALIFORNIA
PAGE 64 OF 329
STATE OF CALIFORNIA
PAGE 65 OF 329
STATE OF CALIFORNIA
PAGE 66 OF 329
STATE OF CALIFORNIA
PAGE 67 OF 329
STATE OF CALIFORNIA
PAGE 68 OF 329
STATE OF CALIFORNIA
PAGE 69 OF 329
STATE OF CALIFORNIA
PAGE 70 OF 329
STATE OF CALIFORNIA
2.2.2.3 Micropiles
The following provides additional information specific to micropiles:
I. Receipt of documentation for constructed elements:
I.A. Refer to section 2.3.1.1 Cast In Place (CIP) Concrete on page 74 for requirements
applicable to grouting.
I.B. Material/Structural Test Documentation:
I.B.1. Steel materials meet or exceed requirements.
I.B.1.1. Where no mill certification is provided, coupon testing must comply
with requirements.
I.B.2. Micropile load capacity testing.
II. Inspection of the following items:
II.A. Refer to section 2.3.1.1 Cast In Place (CIP) Concrete on page 74 for requirements
applicable to grouting.
II.B. Grout Installation
PAGE 71 OF 329
STATE OF CALIFORNIA
PAGE 72 OF 329
STATE OF CALIFORNIA
PAGE 73 OF 329
STATE OF CALIFORNIA
2.3.1 Concrete
In addition to the California Building Code, projects using concrete are generally governed by a
referenced standard issued by the American Concrete Institute (ACI; see
http://www.concrete.org). The primary reference for general design and construction
requirements is:
Building Code Requirements for Structural Concrete, ACI 318
ACI 318 has both gravity and seismic requirements; unlike some other material reference
standards (e.g. steel or wood), no additional reference is necessary for the seismic lateral
resisting systems (SLRS).
Frequently, testing of concrete or steel reinforcement is necessary for various portions of
concrete construction associated with the project. When such testing is necessary as dictated
by the construction documents, certain information must be included, depending on the type of
test that is being performed. While there are no format requirements, DSA 203: Tension/Bend
and DSA 204: Compression provide a suggested format. For some projects, post-installed
anchors may also be used and require testing; DSA 206: Anchor Load provides a suggested
format for such tests (refer to APPENDIX B REFERENCED DSA FORMS on page 313 for
these forms).
Refer to form DSA 151 for requirements associated with advance notification to DSA for
various concrete related construction items.
2.3.1.1 Cast In Place (CIP) Concrete
For all CIP concrete work, the following items apply (note: CBC Chapter 19A applies to K-12
and Community College projects and Chapter 19 applies to Community College projects in
DIVISION OF THE STATE ARCHITECT
PAGE 74 OF 329
STATE OF CALIFORNIA
PAGE 75 OF 329
STATE OF CALIFORNIA
PAGE 76 OF 329
STATE OF CALIFORNIA
PAGE 77 OF 329
STATE OF CALIFORNIA
PAGE 78 OF 329
STATE OF CALIFORNIA
PAGE 79 OF 329
STATE OF CALIFORNIA
II.D. Concrete mixing, placement and curing (note: ACI 309R is a helpful resource):
II.D.1. Hot and cold weather special requirements. (Refer to form DSA 151 for
requirements associated with advance notification to DSA for various
concrete related construction items.)
II.D.1.1. Based on ASTM referenced in approved construction documents
(e.g. ASTM C94 or C685), mix times and revolutions are not
exceeded during mixing operations (e.g. C94 limits mixing to 90
minutes and 300 revolutions).
II.D.2. Proper concrete placement at large or deep elements (e.g. additional
placement tools, such as a pipe, hose, snout, etc. may be necessary to
ensure concrete is placed as close to final position as possible).
PAGE 80 OF 329
STATE OF CALIFORNIA
PAGE 81 OF 329
STATE OF CALIFORNIA
PAGE 82 OF 329
STATE OF CALIFORNIA
PAGE 83 OF 329
STATE OF CALIFORNIA
PAGE 84 OF 329
STATE OF CALIFORNIA
2.3.1.4.2 Tilt-up
For documentation and inspection requirements, refer
to 2.3.1.1 Cast In Place (CIP) Concrete on page 74
applicable to all CIP concrete walls and 2.3.1.3
Precast Concrete on page 84. For walls forming part
of the lateral system, refer to 2.4.1.1 Special
Reinforced Shear Wall on page 140 and 2.4.1.2
Intermediate Precast Shear Wall on page 141, as
applicable.
In addition, the following apply to tilt-up walls:
I. Inspection of the following items:
I.A. Prior to concrete placement, block-out
locations, including, but not limited to:
I.A.1. Hold-downs
I.A.2. Chord steel connections (See
Figure 2-17 for an example of
problems associated with poort
layout of chord reinforcing steel.)
I.A.3. Supports
I.A.4. Embeds.
I.B. Welded connections including, but not
limited to:
PAGE 85 OF 329
STATE OF CALIFORNIA
PAGE 86 OF 329
STATE OF CALIFORNIA
PAGE 87 OF 329
STATE OF CALIFORNIA
PAGE 88 OF 329
STATE OF CALIFORNIA
PAGE 89 OF 329
STATE OF CALIFORNIA
PAGE 90 OF 329
STATE OF CALIFORNIA
PAGE 91 OF 329
STATE OF CALIFORNIA
PAGE 92 OF 329
STATE OF CALIFORNIA
Figure 2-20:
PAGE 93 OF 329
STATE OF CALIFORNIA
PAGE 94 OF 329
STATE OF CALIFORNIA
PAGE 95 OF 329
STATE OF CALIFORNIA
PAGE 96 OF 329
STATE OF CALIFORNIA
PAGE 97 OF 329
STATE OF CALIFORNIA
PAGE 98 OF 329
STATE OF CALIFORNIA
PAGE 99 OF 329
STATE OF CALIFORNIA
Use Category
Brief Description
UC1
Interior Dry
UC2
Interior Damp
UC3A
UC3B
UC4A
UC4B
UC4C
UC5A
UC5B
UC5C
UCFA
UCFB
Figure
II.D.2.6.2. Reduced body diameter bolts are not permitted; full body
diameter bolts are required (refer to IR 23-5 for
additional information).
II.D.2.6.3. Installation Requirements
II.D.2.6.3.1 Bolt hole tolerance.
II.D.2.6.3.1.1 All fixes to oversized holes shall be
approved by design professional and
DSA.
II.D.2.6.3.2 Specified metal plate, strap, or washer (a
commonly specified minimum is not less than a
standard cut washer see Table 2-6 on page 144
for standard cut washer dimensions) between
wood and bolt heads.
II.D.2.6.3.2.1 Plate washers at sill plate anchor bolts.
See 2.3.3.1 Walls subsection II.C.4 on
page 104 and 2.4.3.1.1 Light Wood
Framing subsection II.B.4.5.4.2 Anchor
bolt requirements on page 143 for
additional information.
II.D.2.6.3.3 Placement of bolt (see Figure 2-34 for commonly
specified dimensions, though dimensions shown
are not absolute minimums allowed based on
code allowances with engineering analysis).
II.D.2.6.3.3.1 Edge Distance
II.D.2.6.3.3.2 End Distance
requirements).
II.D.2.7.2.2 Specified lubricant is used to facilitate lag screw
installation.
II.D.2.7.2.3 Specified penetration into main member.
II.D.2.7.2.4 Placement of lag screw:
II.D.2.7.2.4.1 Edge Distance
II.D.2.7.2.4.2 End Distance
II.D.2.7.2.4.3 Fastener Spacing
II.D.2.8. Wood screws
II.D.2.8.1. Dimensional requirements. Frequently specified
requirements include reference to ANSI/ASME Standard
B18.6.1 (refer to Table 2-4 taken from Table L3 in
AF&PA 2005 NDS) for further information).
2.3.3.1 Walls
I. Receipt of documentation for constructed elements: Refer to section 2.3.3 Wood on
page 96 for documentation and inspection requirements.
II. Inspection of the following items:
II.A. Refer to relevant sections in 2.2 Foundation Systems starting on page 62 for items
to be inspected prior to wall framing inspections (e.g. concrete foundations,
embeds, anchor bolt placement, etc.).
II.B. Walls are plumb and true within specified tolerances.
II.C. Wall sill plate
I.B.2.2. Welding:
I.B.2.2.1. Weld filler material
I.B.2.2.1.1 Identification markings per AWS designation
listed on the DSA approved documents and the
Welding Procedure Specifications (WPS).
I.B.2.2.1.2 Manufacturers certificate of compliance.
I.B.2.2.2. WPS
I.B.2.2.3. Welder qualifications
I.B.2.2.4. Equipment
I.B.2.2.5. For Non-Destructive Testing (NDT) requirements (which
are usually associated with structural steel seismic
lateral force resisting systems), refer to 2.4.4.1 Structural
Steel subsection I.A.2.1 Welding: on page 149.
I.B.3. Spray Applied Fire-Proofing
I.B.3.1. Tests of bond strength
I.B.3.2. Tests of density
I.B.4. Upon completion of all testing, the DSA approved laboratory provides a
verified report (DSA 291).
I.C. Special Inspection Documentation:
I.C.1. Special inspector to provide documentation for the following in the form of
reports of tests performed and/or daily special inspection reports.
I.C.1.1. Framing Members
I.C.1.1.1. Examine seam welds of structural tubes and pipes (refer
to IR 17-3 and Bulletin BU 07-03 for additional
information).
I.C.1.1.2. Stiffener locations
I.C.1.1.3. Connection tab locations
I.C.1.1.4. All construction details fabricated in the shop.
I.C.1.2. Connections
I.C.1.2.1. High-Strength Bolts (HSB), nuts and washers.
I.C.1.2.1.1 Refer to IR 17-9 for HSB special inspection
requirements.
I.C.1.2.1.2 Identification Markings.
I.C.1.2.1.3 Manufacturer's certificates of compliance conform
to ASTM standards specified in the DSA
approved documents.
I.C.1.2.1.3.1 Reuse of ASTM A490 and galvanized
A325 is not permitted.
DIVISION OF THE STATE ARCHITECT
2.3.4.1.1 Beams
This section covers all types of steel beams.
Refer to 2.3.4.1 Structural Steel on page 116 for documentation and inspection requirements.
2.3.4.1.1.1 Composite
For composite beams, refer to 2.3.1 Concrete on page 74 and 2.3.4.1 Structural Steel on page
116 for documentation and inspection requirements. Additionally, where steel deck occurs,
refer to 2.3.4.2.2.2 Steel Deck on page 136.
II.A.5.3. Connections
II.A.5.4. Bridging termination connections to structure.
II.A.5.4.1. Where no terminus connection is possible due to
construction phasing, temporary bracing is provided.
wind uplift design loads for joists, bottom chord bridging per
requirements.
II.A.6. Field Splices (see Figure 2-44)
II.A.7. Seating Connections
II.A.7.1. Bearing Length
II.A.7.2. Anchorage Connection
2.3.4.1.2 Columns
Refer to 2.3.4.1 Structural Steel on page 116 for documentation and inspection requirements.
2.3.4.1.2.1 Composite
2.3.4.2 Cold Formed Steel
In addition to the California Building Code, projects using cold formed steel are generally
governed by referenced standards issued by various groups, based on the type of product.
The primary reference applicable to all cold formed steel is based on a standard produced by
the American Iron and Steel Institute (AISI; see http://www.steel.org/). Specifically, the
applicable reference for all cold formed steel is listed below:
2.3.4.2.1.1 Walls
For documentation requirements, refer to 2.3.4.2 Cold Formed Steel on page 125.
I. Inspection of the following items:
I.A. Bottom Track
I.A.1. Where walls occur, foundation at base track is level within specified
tolerances.
I.A.2. Anchor bolts
I.A.2.1. Size
I.A.2.2. Embedment
I.A.2.3. Spacing
I.A.2.4. Placement
I.A.3. Work of other trades (e.g. mechanical/electrical/plumbing) does not alter
(e.g. install notches, holes, etc.) bottom track unless specifically shown on
approved drawings.
I.B. Studs
I.C.1.1. Connections
I.C.1.1.1. Welding:
I.C.1.1.1.1 Field Welding
I.C.1.1.1.1.1 End-welded stud installation (including
bend test).
I.C.1.1.1.1.2 Floor and roof deck welds. See Figure
II.B.3. Placement of welded studs, which can be affected by width of flute and
location within flute, based on requirements.
II.B.4. If high flute occurs at welded studs where no detail is provided in the
approved construction documents, a custom detail by the design
2.4.1 Concrete
For all concrete elements listed below, refer to appropriate section in 2.3.1 Concrete, starting
on page 74 for documentation and inspection requirements.
2.4.1.1 Special Reinforced Shear Wall
I. Receipt of documentation for constructed elements:
I.A. Material/Structural Test Documentation:
I.A.1. Reinforcing steel per requirements.
I.A.2. Mechanical splices per requirements.
II. Inspection of the following items:
II.A. Proper installation of mechanical splices (see Figure 2-54).
2.4.2 Masonry
2.4.2.1 Special Reinforced Shear Wall
Refer to 2.3.2 Masonry on page 89 for documentation and inspection requirements.
Figure 2-57:
II.B.4.7. Hold-downs
II.B.4.7.1. Type
II.B.4.7.2. Location
II.B.4.7.3. Fastener type and size
II.B.4.7.4. Hold-off distance to sill pates
II.B.4.7.5. Installation complies with ICC ES report.
II.B.4.7.5.1 All nuts tightened (but not over-torqued based on
ICC ES report) prior to closing in.
II.B.4.7.5.2 Surrounding framing has not been negatively
impacted or altered to accommodate hold-down
device (see Figure 2-57).
II.B.4.7.6. At floor-to-floor conditions with steel straps, strap location
ensures equal distribution of nailing into top and bottom
wall framing.
II.B.4.7.7. Anchor rod
II.B.4.7.7.1 Hold-down anchor rod does not replace anchor
bolt.
II.B.4.7.7.2 Anchor rod is not bent.
II.B.4.7.7.3 Length of rod complies with maximum limits
Hold-Down Construction
shown in drawings or specified in ICC ES (or
Problems
other DSA recognized agency) report.
II.B.4.7.8. Where through-bolt hold-down devices are used:
II.B.4.7.8.1 No countersinking occurs unless specifically
detailed on DSA approved drawings.
II.B.4.7.8.2 Hole tolerance
II.B.4.7.8.3 Washer between nut and wood on opposite side
of hold-down.
II.B.4.7.9. Post/stud size and grade, which may be different than
typical framing.
II.B.4.7.10. Panel edge nailing full height on post/studs with holddown.
II.B.4.8. Special requirements at high-wind regions
II.B.4.8.1. Nailing spacing
II.B.4.8.2. Panel thickness
II.B.4.8.3. Panel strength orientation parallel to studs (rather than
perpendicular).
Figure 2-58: Wind Uplift Commonly Specified Nail Edge Distances at Wood Structural Panel
2.4.4 Steel
2.4.4.1 Structural Steel
In addition to the California Building Code, projects using structural steel as part of the seismic
load resisting system are generally governed by the following referenced standard issued by
the AISC:
Seismic Provisions for Structural Steel Buildings, ANSI/AISC 341. When published,
supplements to the Provisions become part of that recognized standard (e.g. there was
Supplment No. 1 issued for ANSI/AISC 341-05: ANSI/AISC 341s1-05).
Another referenced standard for projects using a particular kind of seismic load resisting
system, steel moment frames, is used. Refer to 2.4.4.1.1 Moment Frame on page 149 for
further information if the project has such systems.
For welding of components in seismic lateral force resisting systems, the following reference
standard issued by AWS also applies:
D1.8 Structural Welding Code Seismic Supplement
For all structural steel lateral force resisting systems, the following applies:
I. Receipt of documentation for constructed elements:
I.A. Material/Structural Test Documentation:
I.A.1. Weld filler metal for connections that are part of the SLRS comply with
requirements.
I.A.1.1. At demand critical welds, weld filler metal complies with additional
requirements.
Early steel moment frames tended to be highly redundant and nearly every beam-column joint
was constructed to behave as part of the lateral-force-resisting system. As a result, member
sizes in these early frames were small and much of the early acceptance testing of this
typical detail was conducted with specimens constructed of small framing members. As
the cost of construction labor increased, the industry found that it was more economical to
construct steel moment-frame buildings by moment-connecting a relatively small percentage of
the beams and columns and by using larger members for these few moment-connected
elements. The amount of strain demand placed on the connection elements of a steel moment
frame is related to the span-to-depth ratio of the member. Therefore, as member sizes
increased, strain demands on the welded connections also increased, making the connections
more susceptible to brittle behavior.
In the 1960s and 1970s, when much of the initial research on steel moment-frame construction
was performed, beams were commonly fabricated using A36 material. In the 1980s, many
steel mills adopted more modern production processes, including the use of scrap-based
production. Steels produced by these more modern processes tended to include micro-alloying
elements that increased the strength of the materials so that despite the common specification
of A36 material for beams, many beams actually had yield strengths that approximated or
exceeded that required for grade 50 material. As a result of this increase in base metal yield
strength, the weld metal in the beam-flange-to-column-flange joints became under-matched,
potentially contributing to its vulnerability.
equipment can sway and contact other adjacent equipment or structure, which could lead to
falling hazards. IR 16-9 has general design requirements for pendant lights. There are no
additional documentation or inspection requirements beyond the information given in other
sections in this manual.
approved construction documents. Any changes affecting the Structural, Fire/Life Safety or
Accessibility portions of the DSA approved construction documents must be approved by the
design professional in responsible charge and submitted to and approved by DSA.
I. Receipt of documentation for constructed elements:
I.A. For documentation requirements, refer to the applicable sections above and below
based on applicable construction materials.
II. Inspection of the following items:
II.A. Framing
II.A.1. Size
II.A.2. Type
II.A.3. Spacing
II.A.3.1. At showers and similar areas, verify spacing complies with
requirements, which may be different than in other areas based
on the ceiling finish specified.
2.6.1.1 Roofing
Roofs suffering from incorrect weather protection can cause damage to structural and nonstructural components. Proper roofing products and installation, along with maintenance, are
important to minimize detrimental weathering effects on these elements.
I. Receipt of documentation for constructed elements:
3.2.1 Use/Occupancy
I. Inspection of the following items:
I.A. Review the approved plans to become familiar with the various occupancies and
room uses for the building.
I.A.1. Confirm that the use and occupancy of each room is consistent with the
approved documents.
Table 3-1: CBC Table 508.2.5 - Incidental Accessory Occupancies - Required Separations
I.B.1. Note the difference between fire walls, fire barriers and fire partitions
described in CBC 706, 707, and 709.
Table 3-3: CBC Table 601 - Fire Rating Requirements for Building Elements
II.D. Devices
II.D.1. Fire Hydrants
II.D.2. Fire pumps (see CBC 913 and NFPA 20)
II.D.2.1. Verify pump. Note that design changes to the building during
construction may affect fire pump capacity and must be reviewed
and approved by DSA prior to pump installation.
II.D.3. Back Flow Preventers
II.D.4. Fire Department Connections
II.D.5. Post Indicator Valves
II.D.6. Piping (for standpipe, riser, main and distribution systems)
II.D.6.1. Type
II.D.6.2. Size
II.D.6.3. Pressure Capacity
II.D.7. Standpipes (see CBC 905 and NFPA 14)
II.D.8. Distribution system
II.D.8.1. Sprinkler Type
II.D.8.1.1. Sprinkler Heads
II.D.8.1.1.1 Heads as required for spaces are provided and
installed in accordance with NFPA and approved
plans.
II.D.8.1.1.1.1 All heads are:
II.D.8.1.1.1.1.1 New
II.D.8.1.1.1.1.2 Unpainted
II.D.8.1.1.1.1.3 Properly temperature-rated
II.D.8.1.1.1.1.4 Provided with guards where
subject to mechanical injury.
DIVISION OF THE STATE ARCHITECT
II.A.2. Refer to the documents for the required fire rating of the building exterior
walls based on fire separation distance (refer to Table 3-6, taken from CBC
Table 602, for commonly specified fire ratings for these portions of the
building).
II.A.3. Confirm that fire walls are given construction priority for installation.
II.A.4. Wall Assembly Components
Table 3-6: CBC Table 602 - Exterior Wall Fire Rating Requirements
II.A.4.1. Wall coverings comply with specified smoke and flame spread
ratings.
II.A.4.2. Insulation per requirements.
II.A.4.3. In combustible construction, check for fire blocking in concealed
wall spaces. Verify openings comply with requirements. See
3.3.6 Fire Proofing of Structural Members on page 207.
II.A.4.4. Structural steel elements within wall requiring fireproofing are
properly covered. See 3.3.6 Fire Proofing of Structural Members
on page 207.
II.A.5. Continuity of wall:
II.A.5.1. There are many options available to the designer for maintaining
the fire rating at the perimeter of the fire-rated wall. Below are
several common conditions. Verify requirements per the
approved documents.
II.A.5.1.1. Rated wall terminates at the roof deck or exterior wall; if
so the wall or roof on either side of that rated wall may
also need to be rated.
II.A.5.1.2. Rated wall continues beyond roof deck or exterior wall
and extends beyond the roof deck and exterior wall.
II.A.5.1.2.1 Where parapets occur, they have the same fire
resistance as that required for its supporting wall.
II.A.5.1.2.2 Where rated walls serve as an exterior wall
where a building has two different roof levels, the
fire-rated wall continues through the low roof/high
roof junction.
Approved material or
system to resist spread
of heat and hot gases
II.C.3.2. Though the CBC allows exceptions (see CBC 712), the approved
construction documents dictate the requirements for the project.
II.D. Openings comply with 3.3.5.6 Openings in Rated Assemblies (Opening
Protectives) on page 205.
3.3.5.4 Shaft Enclosures
Shaft enclosures are provided to protect openings and penetrations through floor/ceiling and
roof/ceiling assemblies. They include utility shafts, interior exit stairways, and elevator shafts.
Shaft enclosures are typically built as fire barriers. Their purpose is to confine a fire to its floor
of origin and to prevent fire, smoke, heat, and hot gases from migrating to other levels. Note
that shaft enclosures are not always required depending on how many stories a utility run
extends and whether the building has a fire sprinkler system, to mention just two exceptions
found in CBC 708; verify with the DSA approved documents.
I. Receipt of documentation for constructed elements:
I.A. For proprietary products, refer to 1.3 Proprietary Products on page 40 for
requirements.
I.B. Receipt of Rational Analysis Report if elevator hoist way pressurization is a part of
the design.
II. Inspection of the following items:
I.A.3.
I.A.4.
I.B. Elevator
I.B.1.
I.B.2.
I.B.3.
I.B.4.
4.1 Site
I. Inspection of the following items:
I.A. Location
I.A.1. An accessible route of travel between all buildings and accessible site
facilities, including parking serving (see Figure 4-1):
I.A.1.1. Area of new work
I.A.1.2. Public right-of-way.
I.B. Key features of an accessible path of travel (POT):
I.B.1. Dimensions
I.B.1.1. Slope/cross-slopes
I.B.1.2. Level changes leading to additional accessible features (e.g.
ramps, stairs, etc.).
I.B.1.3. Maintenance of specified clear width and height
I.B.1.3.1. Projections into path
I.B.1.3.1.1 Overhanging obstructions
I.B.1.4. Warning Curbs
I.B.2. Surfaces
I.B.2.1. Materials on and along POT.
I.B.3. Tactile Requirements
I.B.3.1. Tactile indicators along POT.
I.B.4. Visual Requirements
I.B.4.1. Visual indicators along POT.
DIVISION OF THE STATE ARCHITECT
4.1.1 Parking
I. Inspection of the following items:
I.A. Location
I.A.1. Location and layout of accessible parking on the site
I.A.2. Number of accessible spaces per lot for multiple lots.
I.A.3. POT connection for:
I.A.3.1. Ramps at accessible spaces.
I.A.3.2. Passenger or Bus Loading zones.
I.A.3.2.1. Verify drop-off/pick-up areas do not encroach into fire
lane (see 3.1 Site Issues subsection II.A.4.1 on page
179 for additional information).
I.B. Dimensions
I.B.1. Parking Spaces
I.B.2. Access Aisles
I.B.3. Paint and required markings.
I.B.4. Vertical clearance at parking spaces.
I.B.5. Parking Structures
I.B.5.1. Special dimensions and clearance requirements per approved
construction documents.
I.C. Visual Requirements
I.C.1. Paint and required markings.
I.C.2. Signage at each type of space.
I.C.3. Tow-away sign at lot entrances.
I.D. Special equipment, where occurs per requirements:
I.D.1. Parking lot ticket dispensers.
I.D.2. Electric vehicle charging station.
4.1.2 Signage
I. Inspection of the following items:
I.A. Location
I.A.1. "Tow-away" sign(s) at parking lot
entrance(s).
I.A.2. At accessible parking spaces (see
Figure 4-2).
I.A.2.1. Van Signs
I.A.2.2. International symbol of
accessibility (ISA) at
accessible spaces.
DIVISION OF THE STATE ARCHITECT
4.1.3 Walks
I. Inspection of the following items:
I.A. Location
I.A.1. See 4.1 Site on page 218 for location information.
I.A.2. Edge protection if sloping adjacent grade occurs.
I.B. Dimensions
I.B.1. Walk/POT Width
I.B.2. Distance between landings on sloping walks.
I.B.3. Passing Spaces
I.B.4. Slope/cross-slope
I.B.4.1. At door and gate landings.
I.B.5. Warning Curbs
I.C. Surfaces
I.C.1. Texture and slipresistance, including at
level changes.
I.C.2. Transition of new walk to
existing walk.
I.C.3. Drainage gratings (see
Figure 4-3)
I.C.3.1. Locations
I.C.3.2. Type
I.C.3.3. Opening
size/orientation.
I.D. Tactile Requirements
Figure 4-3: Incorrect Grating Type
I.D.1. Tactile indicators along
POT.
I.E. Visual Requirements
I.E.1. Visual indicators along POT.
I.F. Civil Engineering work related to accessibility.
4.1.7 Gates
I. Inspection of the following items:
I.A. Location
I.A.1. Configuration
I.B. Dimensions
I.B.1. Strike-side clearance.
I.B.2. Push-side clearances.
I.B.3. Level landings
I.B.3.1. Width
I.B.3.2. Depth
I.B.4. Hardware (see Figure 4-5).
I.C. Gate Construction
4.2.1 Signage
I. Inspection of the following items:
I.A. Locations
I.A.1. ISA
I.A.2. Room Identification Signs
I.A.3. Tactile Exit Signs
I.A.4. Elevator or platform lift identification,
way-finding
I.A.5. Stairway Signage
I.A.5.1. Directional Signage (see
Figure 4-6).
I.A.6. Area of refuge
I.A.7. Building directory
I.A.8. Text Telephone (if applicable).
I.A.9. Signage at special-use areas
I.A.9.1. Assistive Listening Systems
I.A.9.2. Restroom Doors (see Figure
4-7).
I.B. Dimensions
I.B.1. Mounting height
I.B.1.1. Room Identification Signs
I.B.1.2. Tactile Exit Signs
I.C. Visual Requirements
I.C.1. Type/font
I.C.1.1. Size
I.C.1.2. Style
I.C.1.3. Raised Text
I.C.1.4. Color contrast
I.C.1.5. Texture of sign
I.D. Tactile Requirements
I.D.1. Corresponding braille text for visual
signs.
I.C. Hardware
I.C.1. Hardware Group
I.C.2. Type of hardware (see Figure 4-9).
I.D. Additional door/door related features
I.D.1. Operational Effort
I.D.1.1. Maximum effort to operate door(s).
I.D.2. Closer
I.D.3. Kick Plate
I.D.4. Anchorage of doormats, grills, and carpets.
I.D.5. Automatic doors
I.D.5.1. Fire Doors
I.D.6. Locations/types of:
I.D.6.1. Door Stops
I.D.6.2. Hold-Open Devices
I.B.3.
I.B.4.
I.B.5.
I.B.6.
I.B.2.1. Width
I.B.2.2. Depth
Height of bubbler.
Clear height of:
I.B.4.1. Knee space
I.B.4.2. Toe space.
Location of bubbler on unit.
I.B.5.1. Water flow height.
Alternate dimensions for children, if applicable.
I.A.2.
I.A.3.
I.A.4.
I.A.5.
I.A.6.
4.2.11.5 Urinals
I. Inspection of the following items:
I.A. Location
I.A.1. Number and location of accessible urinals.
I.B. Dimensions
I.B.1. Clear floor space for approach and use.
I.B.2. Height of:
Type
Material
Thickness
Shape
Joints
I.H.7.1. Type
I.H.7.2. Seams
I.H.7.3. Check for breaks or cracks.
I.H.7.4. Joint provides a smooth surface on interior of duct.
I.H.7.5. Laps are in direction of air flow.
I.H.7.6. Flexible connectors are fabricated and provided where specified.
I.H.8. Splitter dampers are provided if required and operating mechanism is
accessible.
I.H.9. Access doors and/or access space is provided at all items requiring
servicing.
I.H.9.1. Size Is sufficient for access and maintenance for the following (this
is not an exhaustive list):
I.H.9.1.1. Fire Dampers
I.H.9.1.1.1 Fire dampers of type required are furnished and
installed as specified (refer to 3.3.5.5
Penetrations of Assemblies subsection II.A.2.6 on
page 204 for additional information).
I.H.9.1.2. Automatic Dampers
I.H.9.1.3. Manual Dampers
I.H.9.1.4. Coils
I.H.9.1.5. Heaters Filters
I.H.9.1.6. Thermostats
I.H.10. Duct Lining and Insulation
I.H.10.1. Ducts are tested for air tightness, if required, before installation of
insulation.
I.H.10.2. Material
I.H.10.2.1. Fire retardant or incombustible where noted.
I.H.10.3. Type
I.H.10.4. Thickness
I.H.10.5. Extent
I.H.10.6. Method of fastening and installation are as specified.
I.H.10.7. Sound deadening and vapor barrier are provided as specified.
DIVISION OF THE STATE ARCHITECT
e. Concrete piers.
5. RETAINING WALLS:
a. Placement of soil reinforcement, drainage
devices, and backfill.
b. Segmental retaining walls; inspect
placement of units, dowels, connectors, etc.
c. Concrete retaining walls.
d. Masonry retaining walls.
6. OTHER SOILS:
CONCRETE
7. CAST IN PLACE CONCRETE
OTHER
27. SKYLIGHT LOAD TEST