SUF PR 14 Quality Auditing
SUF PR 14 Quality Auditing
SUF PR 14 Quality Auditing
AUTHORITY
DESIGN AND CONSTRUCTION OF SUF EJEEN
AGRICULTURAL PROJECT
REVISION
REV.
00
DATE
DESCRIPTION
First Issue
PREP.
APPROVAL
CHECK.
O.Mursal H. Serin
APPR.
______________________________________________________________________
Great Man Made River Company for Reclamation and Construction
Quality Auditing Procedure
_______________________________________________________________________
Table of Contents
1. Purpose and Scope................................................................................. 2
2. Responsibilities....................................................................................... 2
2.1
Internal Audits.............................................................................................................2
2.2
Audits of Suppliers.....................................................................................................2
3. References................................................................................................ 3
4. Description............................................................................................... 3
4.1
Internal Audits.............................................................................................................3
4.2
Planning of Audits.......................................................................................................3
4.2.1
4.2.2
4.2.3
4.2.4
4.2.5
4.3
4.3.1
4.3.2
4.3.3
Audit Schedule..................................................................................................................... 3
Carrying Out Audits..............................................................................................................4
Evaluation of Audit Reports..................................................................................................4
Corrective Actions.................................................................................................................4
Conducting Re-Audits........................................................................................................... 4
Audits of Suppliers/Subcontractors..........................................................................5
Planning of Audits.................................................................................................................5
Checklists............................................................................................................................. 5
Carrying Out Audits..............................................................................................................5
________________________________________________________________________
CP 14-00
______________________________________________________________________
Great Man Made River Company for Reclamation and Construction
Quality Auditing Procedure
_______________________________________________________________________
________________________________________________________________________
CP 14-00
______________________________________________________________________
Great Man Made River Company for Reclamation and Construction
Quality Auditing Procedure
_______________________________________________________________________
The scope of this procedure is all internal auditing works
2. Responsibilities
2.1
Internal Audits
________________________________________________________________________
CP 14-00
______________________________________________________________________
Great Man Made River Company for Reclamation and Construction
Quality Auditing Procedure
_______________________________________________________________________
All auditee are responsible for:
Providing the auditors with complete and accurate information
Showing all required documents
Implementing all corrective actions decided
2.2
Audits of Suppliers
The Quality Manager and Technical Manager are responsible for ensuring the audit to
follow the audit procedure
________________________________________________________________________
CP 14-00
______________________________________________________________________
Great Man Made River Company for Reclamation and Construction
Quality Auditing Procedure
_______________________________________________________________________
3. References
Wadi Suf Ejeen Water Supply and Irrigation Project Exhibit I Quality Assurance
Requirements
4. Description
4.1
Internal Audits
Internal audits are carried out according to planned schedule that has been approved by
the Client. Resulting documentation is also made available to the Owner.
Auditors for internal audits are selected and authorised by the Quality Management. These
staff should have the knowledge of GMMRC and should have no correlation with the
selected audit area.
4.2
Planning of Audits
________________________________________________________________________
CP 14-00
______________________________________________________________________
Great Man Made River Company for Reclamation and Construction
Quality Auditing Procedure
_______________________________________________________________________
The report contains the following information:
description of the scope of audit
name of the auditor
the name of the audited department and of the contacted person
description of the audit results,
detailed description of each deviation
proposals for correcting the procedures, worked out together with the audited
organisational unit
Date, time and place of the audit, overview of the audit result including the statement
on the audited element of the QM System.
4.2.3 Evaluation of Audit Reports
All audit reports are evaluated by the Quality Management. Before circulating the report,
the deviations are analysed to establish whether description or implementation needs
correction.
Following results are possible:
compliance ( between description and practice)
deviations from QM manual and procedures
establish defects/refusal/ recommended re-audits
4.2.4 Corrective Actions
The Quality Management is responsible for the co-ordination of the required corrective
actions. The responsible department has to confirm to the Quality Management, of having
implemented the corrective actions within the specified deadline with the specified time
frame.
4.2.5 Conducting Re-Audits
________________________________________________________________________
CP 14-00
______________________________________________________________________
Great Man Made River Company for Reclamation and Construction
Quality Auditing Procedure
_______________________________________________________________________
Depending on the deviation, the Head of the Quality Management decides whether a reaudit is necessary and the end of the deadline.
4.3
Audits of Suppliers/Subcontractors
The intention of these audits is to assure that suppliers or sub contractors are working in
accordance with quality requirement of the contract. Results of the audit shall be reported
to the Owner. Documents resulting of the audits on suppliers and sub contractors are
submitted to the Owner together as audit report including any necessary attachment.
4.3.1 Planning of Audits
The Project Quality Manager finalises schedule of planned audits during the project
4.3.2 Checklists
Project engineers who are carrying out audits prepare audit checklists which serve as a
guideline during the audit.
4.3.3 Carrying Out Audits
The auditor carries out the audit according to the prepared check list. The covered areas
are noted on this list as well as remarks and details of documents checked.
After the audit he prepares an audit report which includes all relevant audit documents.
The audit report contains following information:
description of the scope of audit
name of auditor
name of audited company, and contact person
date, time and place of the audit
quality assurance arrangements/quality system
overview of the audit results
detailed descriptions of deviations and agreement by the auditee
refusals/re-audit dates
________________________________________________________________________